ESTIMATING CONTINGENCY SUM FOR BUILDING WORKS IN GHANA

Size: px
Start display at page:

Download "ESTIMATING CONTINGENCY SUM FOR BUILDING WORKS IN GHANA"

Transcription

1 Sci., Tech. and Dev., 32 (3): , 2013 ESTIMATING CONTINGENCY SUM FOR BUILDING WORKS IN GHANA RICHARD ODURO ASAMOAH 1 *, JAMES COFIE DANKU 2 AND P.D. BAIDEN AMISSAH 1 1 Research Scientist, Building and Road Research Institute, Council for Scientific and Industrial Research, Kumasi, Ghana. 2 Department of Building Technology, Kwame Nkrumah University of Science and Technology, Ghana. Abstract It is a common practice in the construction industry in Ghana to allow for contingencies to cater for any unforeseen events. This study was to identify existing methods of determining contingency sum, factors influencing contingency sum and develop a new system of determining contingency sum. The study employed a case study of some 38 completed building projects in Ashanti and Brong Ahafo regions of Ghana to compare the accuracy of both the existing and the new method. Questionnaires were distributed to the selected professionals. Relative Importance Indices Ranking and the Kendall coefficient of concordance were used to rank factors and the agreement of factors ranking among building professions. It was established that the most commonly used method is the Percentage Approach method. The study revealed that 77% of the building professionals have been using the Percentage Approach and 23% have been using the Probabilistic Estimation Methods. These methods were based on subjective approach. Economic, Environmental and Technical factors were identified as the most influential factors. The study concludes by developing a new software system of determining contingency sum and new method was found to be 45% more accurate than the Percentage Approach. Keywords: Contingency sum, Factors, Existing methods, Proposed new method. Introduction Contingency sum has been defined as an additional fund, meant to cater for unforeseeable elements of cost, within the defined project scope. The purpose of contingency sum is to generate a reserve fund that may be sufficient to manage the inherent risk within the project, so as to complete it on time (Ford, 2002). In Ghana, it is characteristics of a construction work to proceed without any risk appraisal. In order to address any future risk, high contingency sums are included in the mark-ups (Badu, 2004). There has been little empirical research into the concept of contingency sum, its intended scope and methods of estimating contingency sum in infrastructure development contracts. The difficulty in determining contingency sum depends on technical, economic and institutional factors (Tawiah, 1999). Inappropriate contingency sums have resulted in poor management of risk leading to underestimation or overestimation, delay in the completion of projects and abandonment of projects altogether. In particular, overestimated contingency sums limit the cash-flow to contractors. To address these problems, it is important for building professionals to consider other methods of determining contingency sums. Determination of an appropriate contingency sum requires an understanding of how estimators make budget contingency decisions and the impact on the level of accuracy of the included contingency sum. The contingency sum is usually expressed as a percentage mark-up on the base estimate (Picken and Mak, 2001). In the construction industry, building professionals have not been able to state the actual percentage range for Contingency Sum. Available information, however, indicates percentage ranges of 2.5% - 10%, which have been determined for some selected projects financed by the Government of Ghana and other development partners, such as, the African Development Bank and the World Bank from 1999 to 2007 (GPRP/SIF, 2004). The amount for contingency sum varies but 10% is *Author for correspondence asamoaho@yahoo.com

2 ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA 267 recommended for lump sum projects and for other types of contracts (cost plus contracts), it is advisable to set contingency above 10% (Davey, 1992). Existing Method(s) of Determining Projects Contingency Sum in Building Works Baccarini in 2005 came out with 14 methods of determining contingency sum for construction works. The methods are as follows; Deterministic Estimation (Percentage Addition) Range Estimating Analytical Hierarchy Process Monte Carlo Simulation Probabilistic Estimating Methods of Moments Factors Rating Individual Risks expected value Regression Artificial Neural Networks Fuzzy Sets Controlled Interval Memory Influence Diagrams Theory of Constraints Preliminary survey conducted in the study indicated that among the above methods, building professionals had knowledge or had used the following methods before. These methods were: (i) Deterministic Method (Traditional or Percentage addition estimate). (ii) Probabilistic Estimation (Based on experience of past projects completed) (iii) Estimating using Risk Analysis (ERA) (iv) Range Estimating (v) Monte Carlo Simulation This study therefore used these known methods to determine the most widely used method in the building construction industry in Building Professionals Table 1. Questionnaire Response from Professionals. No. of Q uestionnaires Distributed Ghana. The study showed that the Deterministic Approach (Percentage Approach) was the most widely used and known method for determining Contingency Sum by professionals in Ghana. As indicated in Table 2, 77% of the sampled professionals have been using the Deterministic Approach and only 23% have been using the Probabilistic Estimation. The sampled professionals had knowledge about the Estimating using Risk Analysis, Range Estimating and the Monte Carlo methods of determining the Contingency Sum, but have not used any of the methods before. Methodology and Data Collection In this study, initial review of documents on the subject was conducted. Data collection was carried out using the stratified random sampling technique. The target population comprised construction professionals, working in Kumasi and Accra. The target professionals were Architects, Civil Engineers and Quantity Surveyors. Furthermore, Kumasi and Greater Accra are the commercial cities in Ghana where many of the working building professionals are located and most of the construction activities in the country could be located. Using the Kish (1965) formula, the overall sample size of 224 was obtained and assuming a return rate of 45%, the sample size was increased to 250. Two hundred and fifty (250) questionnaires were administered to professionals in the building industry. A total of 133 questionnaires representing 53.2% of the total questionnaire administered were returned. The return rate was high for the Quantity Surveyors and out of the 53.2% returned questionnaire as indicated in Table % were responsive and 20.3% were not responsive. No. of Q uestionnaires Returned % Rate of Returned Quantity Surveyors Architects Civil/Structural Engineers Total Source: Field Survey, February March, 2007

3 268 RICHARD ODURO ASAMOAH ET AL. Methods Table 2. Questionnaire Response from Professionals. Quantity Surveyors Architects Civil Engineers Total % Percentage Approach (Existing Method) Probabilistic Method Range Estimating ERA Monte Carlo Total Source: Field Survey, February March, 2007 Kendall (1970) coefficient of concordance, the best estimate of true ranking (rating) of n objects is provided, where W (the coefficient of concordance) is significant by the order of various sums of ranks. If one accepts the criteria used by the judges, then the best true ranking is provided by the mean of the ranks. This implies that most factors influencing contingency sum are the highest overall ranking. Based on the above premise, the overall rankings were calculated for the Quantity Surveyors, Architects and Civil Engineers. The Kendall s concordance coefficient, which measures the degree of agreement among professionals of ranking, is expressed as W = [ k (R i Ř) 2 ] [n (n 2-1)/12] where, k = the number of set of ranking (e.g. the number of judgments) n = the number of aspects of a problem or factors being ranked. Ř= average of the ranks assigned to the n th aspect of the problem n(n 2-1)/12 = the maximum possible squared deviation, i.e., the numerator, which will occur if there were perfect agreements among k sets of ranks, and the average ranking were 1, 2, 3,, n. R i = the rank assigned by an individual judge to one aspect of the problem posed. The sixth version of the Visual Basic (VB) was used to develop a simple calculator for determining contingency sum as shown in Fig. 2. The New Method of Determining Contingency Sum The study adopted and modified risk rating factors developed by the American Association of Cost Engineers (AACE, 2008), as shown in Table 3, to develop a system for determining contingency figure as a percentage to be added to project cost. The method is a visual basic programme designed to cover identified factors influencing the determination of contingency sum. The factors have been grouped into Economic, Technical and Environmental/Cultural Factors. From the study Technical and Environmental/Cultural Factors contribute 20% respectively to the determination of contingency sum, whiles Economic factors contributes 60%. Each of the main factors has related minor factors. Each of these minor factors has risk rated values, which vary depending on conditions and the impact of risk as identified by the project team, as shown in Table 3 and Fig. 1. Fig. 2 shows the pictorial nature of the Proposed Method. Table 5 shows the list of projects that were used for the case studies. The projects were under the sponsorship of the government of Ghana and the development partners, including the World Bank, African Development Bank and the Arab Bank. Projects include the following; Basic Education Support Project (BESP) Rehabilitation and Upgrading of Second Cycle Schools (Effiduase Senior High School) Primary Education Rehabilitation Project (PERP)

4 ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA 269 Highly Indebted Poor Country / Ghana Education Trust Fund Projects (HIPC/GETFUND) Table 3. Risk Factor Rating Promoting Partnership with Traditional Authorities Project (PPTAP). Item Factors Risk Factors Minimum Medium Maximum 1. Environmental/ Institutional A Demand for Extractive Materials 20% B Force Majeure C Cultural Implication Economic 60% D Inflation E Global Economic Pressure 3. Technical 20% F Project Specification G Design Consideration H Contract Period J Project Management L Form of Contract Source: Association of America Cost Engineers International, Table 4. Agreement between building professionals regarding factors influencing the determination of contingency sum. Factors Q uantity Surveyors Architects Civil Engineers Sum of Ranking (Ri) Mean of Ranking (Ř) Ri - Ř Ri -Ř) 2 O ver All Ranking Economic st Environmental / Institutional nd Technical nd Results and Discussions Construction professionals were asked to rate factors, influencing, contingency sum in percentage terms as indicated in Table 3. The survey revealed that, professionals in the construction industry classify the factors, influencing the determination of contingency sum into technical, economic and environmental/ institutional factors. Technical factors were considered as Project Specification, Design Consideration, Contract Period, Project Management and Form of Contract. Economic Factors included inflation and global economic pressure. Environmental factors included demand for extractive materials, force majeure and institutional factors included Social and cultural Impacts on project delivery in Ghana as shown in the flow chart of Fig. 1. In order to simplify the proposed method environmental and institutional factors were combined. Also some of these factors really do occur. According to the survey, construction professionals have all the abilities to manage the impact of technical factors in order to reduce the risk on contingency sum.

5 Environmental/ Institutional Factors (20%) Demand For Material (11) Force Majeure (7) Cultural Factors (2) Total Contingency (%) Economic Factors (60%) Inflation (40) Global Economic Pressure (20) Project Specification (4) Fig. 1. Flow Chart Indicating the Determination of Contingency Sum Technical Factors (20%) Form of Contract (6) Project Duration (2) Project Management (2) Design Consideration (6) 270 RICHARD ODURO ASAMOAH ET AL.

6 ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA 271 Fig. 2. The Proposed Method of Estimating Contingency Sum (Contingency Calculator) The study confirms that with proper planning from the conception stage, the impact of technical factors could be reduced to the minimum. The professionals agreed to rate technical factor at 20%. The survey also revealed that, environmental/institutional factors also contribute to risk in construction. In Ghana, apart from occasional flooding experience, volcanic eruption, earth quake, landslide, etc rarely do occur. Recurrent cultural developments in Ghana have shown that there is the need to consider these factors. Sometimes, some traditional leaders demand huge compensation before allowing projects to commence. Building Professionals were to rate environmental/cultural factors at 20% of the contract contingency sum. The study also revealed that, professionals have no control over the economic factors. All the selected professionals agreed to rate economic factors at 60%. It is in the domain of the central government to regulate the economic factors. Table 3 shows the rating and the agreement of factors amongst professionals in the construction industry. Grand mean Ř = ( n i 1 R i ) 1/n = (R i Ř) 2 = 1,067 where R i is the mean of rankings and n is the number of factors being ranked. Table 3 consists of factors and ratings influencing the determination of contingency. The factors and ratings were first developed by the Association of American Cost Engineers International (2008). The factors and the ratings were adopted for the purposes of the study to develop a flow chart for the new method of determining contingency sum (Fig. 1).

7 272 RICHARD ODURO ASAMOAH ET AL. The proposed method was used to calculate the contingency sums for 38 selected building projects from Ashanti and Brong Ahafo regions as indicated in Table 6. The results and discussions were based on Table 6. Fifteen (15) projects had contingency figures by the proposed method to be higher than the actual contingency figures. Ten projects were ±5% close to the actual contingency figures and five of the projects were more than +5 the actual contingency figures. Seventeen of the selected projects had contingency figures by the proposed method to be less than the actual contingency figures. Nine of these projects were ± 5% close to the actual figures and eight of the projects were less than - 5% from the actual contingency figures. Six projects were considered to have marginal percentage figures of ± 2% of the actual contingency figures. An assumption of ±5 was used to analyse the level of accuracy. Table 5 shows the outcome of the use of the proposed new Method. The table indicates that, the existing method had a contingency figure of ranging 2.5% - 10% with an average figure of 6.97%. The -5 gave a range of % with an average figure of 2.11%. And + 5 also gave a range of %, with an average figure of The proposed Method gave a range of % with an average figure of 14.54%. The -5% of the proposed method gave a range of %, with an average figure of 9.54, while the +5 gave a range of %, with an average figure of 15.75%. The existing method had an average contingency figure of 6.97%, 14.54% for the proposed Method and 15.75% for the actual contingency. This indicated that, the proposed method gave an accurate figure compared to the actual than the existing method. Using the range of ±5%, the percentage Approach Method gave an average contingency figure of 2.11% and the proposed method had an average figure of 9.54%. This implied that the proposed method could be more accurate than the percentage approach method. The +5% also gave 11.79% for the Percentage Approach Method, for the proposed method and + 5% to the actual average contingency figure was 20.75%. In comparison, the proposed method could be reliable. Table 5 showed that, the projects in items 21 and 22 had contingency figures of 2.5% each and after the completion of the projects the actual contingency was 4.8% and 4.5% respectively indicating 92% and 80 % increase in contingency sum using the Percentage Approach Method. However, the proposed method gave initial contingency figures of 10.2% and 10.8%. This suggests that, there would be enough to address unforeseen events and resources which were not be used would be reserved for future expenditures. Items 23, 27 and 33 had contingency by the Percentage Approach as 5%, 5% and 4.7%, respectively, and contingency figures from the proposed method gave 21.8%, 20.6% and 20.4% respectively. However, the actual contingency figures of 41%, 35.5% and 31.8% and were high above the initial percentage and the proposed contingency figures. In percentage terms, the actual contingency figures were 88%, 72.5% and 55.9%, respectively, high, but it could be said that the contingency figures by the Proposed Method were more accurate than the figures from the Percentage Approach Method. Item Table 5. Selected projects under the building contracts with the respective contingency figure. Project Estimated (%) Proposed Method (%) Actual (%) Difference A B C D E = D B F = D C 1. HIPC/GETFUND - Construction of Day Care, Clinic Post Office for Bosomtwi Atwima Kwanwoma District. 2. BESP 5 No 6 unit Classroom Block and 10 unit 3-seater K.V.I.P-Adansi District Ashanti Region BESP-1 3. BESP 6 No 6 unit Classroom Block and 12 unit 3-seater K.V.I.P-Offinso District Ashanti Region BESP-2 4. Basic Education Support Projects 5 No 6 unit classroom Block and 10 unit 3-seater K.V.I.P-Sekyere West District 5. PERP Construction of Classroom blocks and Ancillary Facility

8 ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA PPTAP - Construction of 6-unit Teachers Quarters- Offinso District. 7. PPTAP - Construction of 4-unit Teachers Quarters- Offinso District 8. PPTAP - Construction of 3-unit Teachers Quarters- Offinso District. 9. PPTAP - Re-roofing of Yaa Asantewaah Basic School - Kumasi 10. RUSCS Construction of 2-storey boys Dormitory- Effiduase Secondary Commercial School 11. HIPC/GETFUND Construction of 6-unit classroom Block - Kumasi 12. HIPC/GETFUND Construction of Day Care center at Old Amokom 13. HIPC/GETFUND - Construction of 6- unit classroom Block- Ahamadiya Basic School Kumasi 14. HIPC/GETFUND - Construction of 2-Room Day Care, for Bosomtwi Atwima Kwawoma District. 15. HIPC/GETFUND - Construction of 2-Room Day Care in bricks, for Bosomtwi Atwima Kwanwoma District. 16. HIPC/GETFUND - Construction of 3-unit classroom Block Bosomtwi Atwima Kwanwoma District. 17. HIPC/GETFUND - Construction of 2-storey Post Office and Stores - Kuntenase 18. HIPC/GETFUND - Construction of Community Library AME ZION Amokom- Kumasi 19. HIPC/GETFUND - Construction of 7-unit classroom Block - Amankwatia Kumasi 20. HIPC/GETFUND - Construction of Clinic for Bosomtwi Atwima Kwanwoma District. 21. BESP 5 No 6 unit classroom Block and 10 unit 3-seater K.V.I.P- Asutifi District Brong Ahafo Region BESP BESP 6 No 6 unit classroom Block and 12 unit 3-seater K.V.I.P- Asunafo District Brong Ahafo Region BESP RUSCS Construction of 2 No Masters Bungalow Dormitory- Effiduase Secondary Commercial School 24. RUSCS Construction of 2-bedroom 3-storey Masters Flat - Effiduase Secondary Commercial School 25. RUSCS Construction of 2-storey Classroom block - Effiduase Secondary Commercial School 26. RUSCS Construction of 2-storey boys Dormitory- Effiduase Secondary Commercial School 27. RUSCS Construction of 2-storey Girls Dormitory- Effiduase Secondary Commercial School. 28. RUSCS Construction of Assembly Hall - Effiduase Secondary Commercial School 29. RUSCS Construction of New Dining Hall Effiduase Secondary Commercial School 30. RUSCS Construction of Science Laboratory - Effiduase Secondary Commercial School 31. RUSCS Construction of Clinic - Effiduase Secondary Commercial School 32. HIPC/GETFUND - Construction of 6-unit classroom Block - Asokore Manpong - Kumasi Metropolitan Assembly 33. HIPC/GETFUND - Construction of 2-Room Day Care, for Kumasi Metropolitan Assembly HIPC/GETFUND - Construction of 2-Room Day Care in

9 274 RICHARD ODURO ASAMOAH ET AL. bricks, for Ejisu Juaben Municipal Assembly. 35. HIPC/GETFUND - Construction of 6-unit classroom Block Ejisu Juaben Municipal Assembly 36. HIPC/GETFUND - Construction of Community Clinic at Fenesu Adansi Central District. 37. HIPC/GETFUND - Construction of Community Library Kumasi Average Standard Deviation Table 6. Comparison contingency figures using the Percentage Approach and the Proposed Method and Actual. Item Percentage Addition Existing Method Proposed New Method Actual -5% +5% -5% +5% % Average

10 ESTIMATING CO NTINGENCY SUM FOR BUILDING WORKS IN GHANA 275 Conclusions The focus of this study was to identify more scientific method of determining contingency for the building industry. The construction industry has different methods of determining contingency sum for building works which include Monte Carlo Simulation, Range Estimation and Estimating Using Risk. However, in Ghana, particularly in the Ashanti and Greater Accra regions, building professionals have been using the Percentage Approach and the Probability Estimation. The study concludes by developing a more scientific method than the previous methods of determining contingency sum. The new method is devoid of subjectivity and gives more accurate contingency figures. The introduction of the new method will help building professionals to manage the causes of variation orders and the uses of contingency sum. Recommendations Proper feasibility studies have been identified as the main source of information for the commencement of any project. Therefore, it is recommended that, every project should commence from the feasibility stage which should include all stakeholders in a project. This will help to limit changes in design during the construction stage. The study also identified that building professionals in Ghana have been using the Percentage Approach and the Probability Estimation, which have been found to be subjective. It is, therefore, recommended that building professionals should use other methods, such as, the Monte Carlo Simulation, Range Estimation and Estimating Using Risk Analysis and other methods in order to check for accuracy of contingency sums. Finally, further studies should be done in the road sector in order to determine the possibility of using scientific method determining contingency sum for the construction industry in Ghana. References Association of America Cost Engineers International Risk Analysis and Contingency Using Range Estimation. Baccarini, D Understanding Project Cost Contingency A survey Conference Proceedings, Construction Research of the Royal Institute of Chartered Surveyors- 4-8th July 2005 at Queensland University of Technology Brisbane, Australia. Badu, E Risk Sharing in Ghanaian Construction Contracts. The Ghanaian Surveyor Journal of Ghana Institution of Surveyors. Vol , pp Davey, K Conservation Contracts and Grant Aid, Practical Guide pp 941 st Edition. London: E & FN Spon. Ford, D.N Achieving multiple project objectives through contingency management. Journal of Construction Engineering and Management, 128 (1), PP Ghana Poverty Reduction project/social Investment Fund (GPRP/SIF), 2004: Final Report. Kendall, M.G Rank correlation methods. Griffin, London. (4 th Edition). Kish, L Survey Sampling. John Wiley and Sons Inc. New York. Mak, S. and D. Picken Using risk analysis to determine construction project cost contingencies. Journal of Construction Engineering and Management, Vol. 126, pp Tawiah, O Factors Affecting the Performance of Ghanaian Owned Construction Firms (Unpublished).

Evaluation of the Adequacy and Utilization of Contingency Fund in Building Projects in Nigeria

Evaluation of the Adequacy and Utilization of Contingency Fund in Building Projects in Nigeria Open Access Library Journal 2016, Volume 3, e2925 ISSN Online: 2333-9721 ISSN Print: 2333-9705 Evaluation of the Adequacy and Utilization of Contingency Fund in Building Projects in Nigeria O. F. Akinradewo

More information

Project Cost Contingency Estimation in Ghana: An Integrated Approach

Project Cost Contingency Estimation in Ghana: An Integrated Approach Science Journal of Civil Engineering and Architecture ISSN: 2276-6332 http://www.sjpub.org Author(s) 2012. CC Attribution 3.0 License. Research Article Published By Science Journal Publication International

More information

Internal Marketing Policy of Cocoa in Ghana: Farmers Incentives and Challenges

Internal Marketing Policy of Cocoa in Ghana: Farmers Incentives and Challenges International Journal of Innovation and Applied Studies ISSN 2028-9324 Vol. 4 No. 4 Dec. 2013, pp. 658-664 2013 Innovative Space of Scientific Research Journals http://www.issr-journals.org/ijias/ Internal

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

The Changing Face of Quantity Surveying Practices in Construction Industry

The Changing Face of Quantity Surveying Practices in Construction Industry The Changing Face of Quantity Surveying Practices in Construction Industry YESHWANTH BABU REDDY School of Architecture and Building Deakin University Table of Contents: 1.1 Background... 2 1.2 Introduction...

More information

Senior Research Fellow Institute of Statistical, Social and Economic Research (ISSER) University of Ghana, Legon.

Senior Research Fellow Institute of Statistical, Social and Economic Research (ISSER) University of Ghana, Legon. SMALL TOWNS AND DECENTRALIZED DEVELOPMENT IN GHANA: A STRATEGY FOR DISPERSED URBANIZATION? George Owusu (PhD) Senior Research Fellow Institute of Statistical, Social and Economic Research (ISSER) University

More information

Methodology for risk management in systems development

Methodology for risk management in systems development Methodology for risk management in systems development Vrassidas LEOPOULOS Mechanical Engineer Dpt National Technical University of Athens Iroon Polytechniou 9 GREECE Konstantinos KIRYTOPOULOS Mechanical

More information

ESTIMATING THE LABOUR DEMAND FOR HOUSING CONSTRUCTION

ESTIMATING THE LABOUR DEMAND FOR HOUSING CONSTRUCTION ESTIMATING THE LABOUR DEMAND FOR HOUSING CONSTRUCTION Doug Forbes 1, Mohamed El-Haram 2, Malcolm Horner 3, Debbie Hatton 4 and Adam Evans 5 1,2,3, Whole Life Consultants Ltd, Dundee University Incubator,

More information

A PROTOTYPE RISK MANAGEMENT DECISION SUPPORT TOOL FOR CONSTRUCTION PROJECTS

A PROTOTYPE RISK MANAGEMENT DECISION SUPPORT TOOL FOR CONSTRUCTION PROJECTS A PROTOTYPE RISK MANAGEMENT DECISION SUPPORT TOOL FOR CONSTRUCTION PROJECTS Arif Erdem Arikan Middle East Technical University, Civil Engineering Department, Ankara, Turkey aearikan@metu.edu.tr Irem Dikmen

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

Determining Nitriding Parameters with Neural Networks

Determining Nitriding Parameters with Neural Networks Journal of ASTM International, May 2005, Vol. 2, No. 5 Paper ID JAI12213 Available online at www.astm.org Tomislav Filetin, 1 Irena Žmak, 1 and Davor Novak 1 Determining Nitriding Parameters with Neural

More information

Commercial Management in the Construction Industry

Commercial Management in the Construction Industry Unit 11: Commercial Management in the Construction Industry Unit code: A/504/4355 QCF level: 6 Credit value: 15 Aim This unit gives learners an understanding of the factors which determine the cost of

More information

Relationship between Labour Performance and Variability in Blockwork Workflow and Labour Productivity

Relationship between Labour Performance and Variability in Blockwork Workflow and Labour Productivity Relationship between Labour Performance and Variability in Blockwork Workflow and Labour Productivity John Ebhohimen Idiake Department of Quantity Surveying, Federal University of Technology P.M.B 65,

More information

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY F.H.Mustapha, Department of Civil Eng. and Building, University of Glamorgan S.G.Naoum, Tarik Aygun, School of Construction

More information

Causes of Contractors Failure: Contractors View

Causes of Contractors Failure: Contractors View 2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Causes of Contractors Failure: Contractors View Ibrahim Mahamid 1+ 1 PhD, Norwegian

More information

DATA PREPROCESSING METHOD FOR COST ESTIMATION OF BUILDING PROJECTS

DATA PREPROCESSING METHOD FOR COST ESTIMATION OF BUILDING PROJECTS DATA PREPROCESSING METHOD FOR COST ESTIMATION OF BUILDING PROJECTS Sae-Hyun Ji Ph.D. Candidate, Dept. of Architecture, Seoul National Univ., Seoul, Korea oldclock@snu.ac.kr Moonseo Park Professor, Ph.D.,

More information

Effect of Changes in Layout Shape on Unit Construction Cost of Residential Buildings

Effect of Changes in Layout Shape on Unit Construction Cost of Residential Buildings Effect of Changes in Layout Shape on Unit Construction Cost of Residential Buildings By Ahmed Doko Ibrahim Department of Surveying, Faculty of Engineering, Ahmadu Bello University, Zaria. Abstract The

More information

The Impact of the Recession on Construction Professional Services. Executive Summary

The Impact of the Recession on Construction Professional Services. Executive Summary The Impact of the Recession on Construction Professional Services Executive Summary Executive summary The headlines The recession in the construction industry has hit the construction professional services

More information

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside

More information

Summary of Findings. Bridge Inspection and Monitoring. Introduction. Findings

Summary of Findings. Bridge Inspection and Monitoring. Introduction. Findings Summary of s Introduction The Province s bridges are aging and their related condition is deteriorating. This situation highlights the need for an adequate system of bridge inspection and planning for

More information

Original Article Comparative accuracy of fl oor area, storey enclosure and cubic methods in preparing preliminary estimate in Nigeria

Original Article Comparative accuracy of fl oor area, storey enclosure and cubic methods in preparing preliminary estimate in Nigeria Original Article Comparative accuracy of floor area, storey enclosure and cubic methods in preparing preliminary estimate in Nigeria Received (in revised form): 28 th February 2011 Emma nu e l Ol us eg

More information

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10

ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 ARTICLE VII - OFF-STREET PARKING AND LOADING Section 7-10 Section 7-10.1 Off Street Parking. Off-street parking spaces, with proper access from a street, alley or driveway shall be provided in all districts

More information

Analysis of Improper Material Management Affecting Cost in Construction Projects

Analysis of Improper Material Management Affecting Cost in Construction Projects Analysis of Improper Material Management Affecting Cost in Construction Projects P.Lenin *, L.Krishnaraj *, D.Narendra Prasad *, V.R Prasath Kumar *, Assistant Professor, Civil Engineering Department,

More information

LECTURE NOTES ON CONSTRUCTION PROJECT MANAGEMENT

LECTURE NOTES ON CONSTRUCTION PROJECT MANAGEMENT LECTURE NOTES ON CONSTRUCTION PROJECT MANAGEMENT Emad Elbeltagi, Ph.D., P.Eng., Structural Engineering Department, Faculty of Engineering, Mansoura University Building and Construction Engineering Program

More information

An overview of the Standard for Infrastructure Procurement and Delivery Management

An overview of the Standard for Infrastructure Procurement and Delivery Management An overview of the Standard for Infrastructure Procurement and Delivery Management National Treasury Instruction No 4 of 2015/2016, issued in terms of the Public Finance Management Act of 1999 (PFMA),

More information

The 1995 Stanford Diagnostic Reading Test (Karlsen & Gardner, 1996) is the fourth

The 1995 Stanford Diagnostic Reading Test (Karlsen & Gardner, 1996) is the fourth Stanford Diagnostic Reading Test 4 The 1995 Stanford Diagnostic Reading Test (Karlsen & Gardner, 1996) is the fourth edition of a test originally published in 1966. The SDRT4 is a group-administered diagnostic

More information

Project Controls Expo

Project Controls Expo Project Controls Expo 09/10 Nov London 2011 What is Cost Engineering and Cost Estimating Carl Dalton Director Polaris Consulting Speaker Profile Carl Dalton Carl is a Fellow of the Association of Cost

More information

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc.

Sawtooth Software. Sample Size Issues for Conjoint Analysis Studies RESEARCH PAPER SERIES. Bryan Orme, Sawtooth Software, Inc. Sawtooth Software RESEARCH PAPER SERIES Sample Size Issues for Conjoint Analysis Studies Bryan Orme, Sawtooth Software, Inc. 1998 Copyright 1998-2001, Sawtooth Software, Inc. 530 W. Fir St. Sequim, WA

More information

ASSESSING THE EFFECT OF PROJECT PLANNING PROCESS ON THE PERFORMANCE ON NON GOVERNMENTAL ORGANISATIONS (NGOs) FUNDED PROJECTS:

ASSESSING THE EFFECT OF PROJECT PLANNING PROCESS ON THE PERFORMANCE ON NON GOVERNMENTAL ORGANISATIONS (NGOs) FUNDED PROJECTS: ASSESSING THE EFFECT OF PROJECT PLANNING PROCESS ON THE PERFORMANCE ON NON GOVERNMENTAL ORGANISATIONS (NGOs) FUNDED PROJECTS: A SURVEY OF COMPASSION INTERNATIONAL RWANDA FUNDED PROJECTS IN KIGALI CITY.

More information

Building the Future in the Euro-Mediterranean Area EUROCODES: Building the Future in the Euro-Mediterranean Area EUROCODES IN MALTA

Building the Future in the Euro-Mediterranean Area EUROCODES: Building the Future in the Euro-Mediterranean Area EUROCODES IN MALTA EUROCODES: EUROCODES IN MALTA Varese, November 27-29, 2006 RESPONSIBILITY FOR DEVELOPMENT AND ADOPTION OF EUROCODES assigned to MALTA STANDARDS AUTHORITY STANDARDISATION DIRECTORATE PREPARATION OF NATIONAL

More information

TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION

TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION Job Classification Manual Page 1 of 49 TIER II STANDARD FOR TECHNICAL COOPERATION ADMINISTRATORS INTRODUCTION 1. This grade level standard illustrates the application of the ICSC Master Standard (Tier

More information

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios Peerapat Vithayasrichareon 1, Iain MacGill 1,2, and Fushuan Wen 1,2 1 School of Electrical Engineering and Telecommunications

More information

Project Success A Survey. Adam Collins. Broad Construction Services. 82 Royal Street. East Perth Western Australia.

Project Success A Survey. Adam Collins. Broad Construction Services. 82 Royal Street. East Perth Western Australia. Project Success A Survey Adam Collins Broad Construction Services 82 Royal Street East Perth 6004 Western Australia David Baccarini* School of Architecture, Construction & Planning Curtin University of

More information

Quality Control Analysis of Enterprise Training Project. Xian Ji 1. Abstract

Quality Control Analysis of Enterprise Training Project. Xian Ji 1. Abstract 2017 3rd International Conference on Social Science, Management and Economics (SSME 2017) ISBN: 978-1-60595-462-2 Quality Control Analysis of Enterprise Training Project Xian Ji 1 Abstract Enterprise training

More information

COSCCOC02 (SQA Unit Code - HA3N 04) Prepare programmes and schedules of work in construction

COSCCOC02 (SQA Unit Code - HA3N 04) Prepare programmes and schedules of work in construction Overview This Unit is about obtaining, confirming, recording, storing, using and presenting information. You will need to identify the information you require and ensure that it is accurate, reliable and

More information

SIMULATION METHOD FOR RELIABILITY ASSESSMENT OF ELECTRICAL DISTRIBUTION SYSTEMS

SIMULATION METHOD FOR RELIABILITY ASSESSMENT OF ELECTRICAL DISTRIBUTION SYSTEMS SIMULATION METHOD FOR RELIABILITY ASSESSMENT OF ELECTRICAL DISTRIBUTION SYSTEMS Johan Setréus, Lina Bertling, Shima Mousavi Gargari KTH, School of Electrical Engineering, Stockholm, Sweden johan.setreus@ee.kth.se

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

Building a Mathematical Model for Predicting the Cost of the Communication Towers Projects Using Multifactor Linear Regression Technique

Building a Mathematical Model for Predicting the Cost of the Communication Towers Projects Using Multifactor Linear Regression Technique International Journal of Construction Engineering and Management 2016, 5(1): 25-29 DOI: 10.5923/j.ijcem.20160501.03 Building a Mathematical Model for Predicting the Cost of the Communication Towers Projects

More information

Daily Report Module for Construction Management Information System

Daily Report Module for Construction Management Information System Daily Report Module for Construction Management Information System Yan-Chyuan Shiau, Wen-Chian Wang Chung-Hua University, Department of Construction Engineering 30 Tung-Shiang, Hsin-Chu, Taiwan, 300, R.O.C.

More information

NSW DEPARTMENT OF EDUCATION AND COMMUNITIES

NSW DEPARTMENT OF EDUCATION AND COMMUNITIES NSW DEPARTMENT OF EDUCATION AND COMMUNITIES Position Description POSITION DETAILS Position Title: Reports to: Manager, Asset Management Unit (Various locations) Manager, Delivery Date: April 2010 PRIMARY

More information

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT

More information

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients December 2008 Contents Page Contents...2 Introduction...3 The Process Flowchart...4 Project Registration: Step 1...5

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

SUCCESSFUL ENTREPRENEUR: A DISCRIMINANT ANALYSIS

SUCCESSFUL ENTREPRENEUR: A DISCRIMINANT ANALYSIS SUCCESSFUL ENTREPRENEUR: A DISCRIMINANT ANALYSIS M. B. M. Ismail Department of Management, Faculty of Management and Commerce, South Eastern University of Sri Lanka, Oluvil mbmismail@seu.ac.lk ABSTRACT:

More information

CONFIDENCE INTERVALS FOR THE COEFFICIENT OF VARIATION

CONFIDENCE INTERVALS FOR THE COEFFICIENT OF VARIATION Libraries Annual Conference on Applied Statistics in Agriculture 1996-8th Annual Conference Proceedings CONFIDENCE INTERVALS FOR THE COEFFICIENT OF VARIATION Mark E. Payton Follow this and additional works

More information

Structured Approach to Project Execution, Monitoring and Control at Operational Level

Structured Approach to Project Execution, Monitoring and Control at Operational Level MANAGEMENT SCIENCE AND ENGINEERING Vol. 5, No. 1,, pp. 10-18 www.cscanada.org ISSN 1913-0341 [Print] ISSN 1913-035X [Online] www.cscanada.net Structured Approach to Project Execution, Monitoring and Control

More information

CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL

CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL By the same author Civil Engineering Quantities, Third Edition Civil Engineering Specification, Second Edition Building Quantities Explained, Third

More information

End-User Computing Satisfaction (EUCS) in Computerised Accounting System (CAS): Which the Critical Factors? A Case in Malaysia

End-User Computing Satisfaction (EUCS) in Computerised Accounting System (CAS): Which the Critical Factors? A Case in Malaysia Vol. 2, No. 1 End-User Computing Satisfaction (EUCS) in Computerised Accounting System (CAS): Which the Critical Factors? A Case in Malaysia Azleen Ilias Mohd Zulkeflee Abd Razak Rahida Abdul Rahman Mohd

More information

REINSTATEMENT VALUATION

REINSTATEMENT VALUATION REINSTATEMENT VALUATION Marylebone, London W1U FOR Mr K Prepared by: INDEPENDENT CHARTERED SURVEYORS Marketing by: CONTENTS INTRODUCTION AND INSTRUCTION SYNOPSIS CONSTRUCTION SUMMARY EXECUTIVE SUMMARY

More information

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion Cashflow The significance to the contractor s cashflow of different patterns of payment from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years duration.

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

A Direct Marketing Framework to Facilitate Data Mining Usage for Marketers: A Case Study in Supermarket Promotions Strategy

A Direct Marketing Framework to Facilitate Data Mining Usage for Marketers: A Case Study in Supermarket Promotions Strategy A Direct Marketing Framework to Facilitate Data Mining Usage for Marketers: A Case Study in Supermarket Promotions Strategy Adel Flici (0630951) Business School, Brunel University, London, UK Abstract

More information

Critical parameters in deriving fire fragility functions for steel gravity frames

Critical parameters in deriving fire fragility functions for steel gravity frames Proceedings of the 9 th International Conference on Structures in Fire (SiF 16) 8-10 June 2016, Princeton University, NJ, USA Critical parameters in deriving fire fragility functions for steel gravity

More information

Resource allocation for strategic quality management: An analytic network process (ANP) model

Resource allocation for strategic quality management: An analytic network process (ANP) model Griffith Research Online https://research-repository.griffith.edu.au Resource allocation for strategic quality management: An analytic network process (ANP) model Author Alidrisi, Hisham, Mohamed, Sherif

More information

A Decision Support System for Performance Evaluation

A Decision Support System for Performance Evaluation A Decision Support System for Performance Evaluation Ramadan AbdelHamid ZeinEldin Associate Professor Operations Research Department Institute of Statistical Studies and Research Cairo University ABSTRACT

More information

Modeling the Perceptions and Challenges of the National Service Personnel in Kumasi Metropolis, Ghana

Modeling the Perceptions and Challenges of the National Service Personnel in Kumasi Metropolis, Ghana International Journal of Applied Science and Technology Vol. 5, No. 3; June 2015 Modeling the Perceptions and Challenges of the National Service Personnel in Kumasi Metropolis, Ghana Frank Osei Frimpong

More information

28.00 Project Briefing & Procurement

28.00 Project Briefing & Procurement 28.00 Project Briefing & Procurement 28.01 Generally A new building marks a significant investment in the future of the University. For many years hence it will reflect the changing role of the University

More information

CONSTRUCTING A STANDARDIZED TEST

CONSTRUCTING A STANDARDIZED TEST Proceedings of the 2 nd SULE IC 2016, FKIP, Unsri, Palembang October 7 th 9 th, 2016 CONSTRUCTING A STANDARDIZED TEST SOFENDI English Education Study Program Sriwijaya University Palembang, e-mail: sofendi@yahoo.com

More information

Colorado Springs PMI Risk Management in Five Easy Pieces Colorado Springs, Colorado May 8 th, 2008

Colorado Springs PMI Risk Management in Five Easy Pieces Colorado Springs, Colorado May 8 th, 2008 Risk management is essential for any significant project. and is useful for any project where an unfavorable outcome is undesirable. Certain information about key project cost, performance, and schedule

More information

SIMULATION OF BORED PILE CONSTRUCTION

SIMULATION OF BORED PILE CONSTRUCTION Proceedings of the 2001 Winter Simulation Conference B. A. Peters, J. S. Smith, D. J. Medeiros, and M. W. Rohrer, eds. SIMULATION OF BORED PILE CONSTRUCTION Tarek M. Zayed Assistant Professor Construction

More information

MANAGERIAL ECONOMICS WILEY A JOHN WILEY & SONS, INC., PUBLICATION. A Mathematical Approach

MANAGERIAL ECONOMICS WILEY A JOHN WILEY & SONS, INC., PUBLICATION. A Mathematical Approach MANAGERIAL ECONOMICS A Mathematical Approach M. J. ALHABEEB L. JOE MOFFITT Isenberg School of Management University of Massachusetts Amherst, MA, USA WILEY A JOHN WILEY & SONS, INC., PUBLICATION PREFACE

More information

A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size on the AHRI-540 Method of Compressor Performance Representation

A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size on the AHRI-540 Method of Compressor Performance Representation Purdue University Purdue e-pubs International Compressor Engineering Conference School of Mechanical Engineering 2016 A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size

More information

SUPPLY CHAIN MANAGEMENT OF DIESEL MUFFLER COMPANY: A CASE STUDY

SUPPLY CHAIN MANAGEMENT OF DIESEL MUFFLER COMPANY: A CASE STUDY SUPPLY CHAIN MANAGEMENT OF DIESEL MUFFLER COMPANY: A CASE STUDY Rizky Kusuma Rakhma Oktavina Industrial Engineering Department, Gunadarma University Jl. Margonda Raya No. 100 Depok, Indonesia ekky_rizkykusuma@yahoo.com

More information

Optimal Rotation of Eucalyptus camaldulensis Plantations In Thailand Based on Financial Return and Risk 1 by Chaiwat Kongsom and Ian A.

Optimal Rotation of Eucalyptus camaldulensis Plantations In Thailand Based on Financial Return and Risk 1 by Chaiwat Kongsom and Ian A. Optimal Rotation of Eucalyptus camaldulensis Plantations In Thailand Based on Financial Return and Risk 1 by Chaiwat Kongsom and Ian A. Munn 2 Abstract Simulation models were developed to estimate optimal,

More information

Using Biomass in Minnesota

Using Biomass in Minnesota 1 2 Using Biomass in Minnesota Case Study Highlights Facility Case Study 6282 Cranberry Road, Finland, MN 55603 84,000 square feet Wolf Ridge Environmental Learning Center Authored by Adam Zoet of Dovetail

More information

Chapter 8 Designing Pay Levels, Mix, and Pay Structures

Chapter 8 Designing Pay Levels, Mix, and Pay Structures Chapter 8 Designing Pay Levels, Mix, and Pay Structures Major Decisions -Some major decisions in pay level determination: -determine pay level policy (specify employers external pay policy) -define purpose

More information

CONSIDERATION OF FACTORS IN TURNAROUND REFINERY (TAR) PROJECT MANAGEMENT

CONSIDERATION OF FACTORS IN TURNAROUND REFINERY (TAR) PROJECT MANAGEMENT CONSIDERATION OF FACTORS IN TURNAROUND REFINERY (TAR) PROJECT MANAGEMENT Fabić M. 1, Pavletić 2, D., Soković M. 3 1 Clinical Hospital Center Rijeka, Krešimirova 42, 51000 Rijeka, marko.fabic@gmail.com

More information

City of Oxnard. Public Works Integrated Master Plan

City of Oxnard. Public Works Integrated Master Plan City of Oxnard This document is released for the purpose of information exchange review and planning only under the authority of Hugh Steve McDonald, December 2015, State of California, PE No. 44074 and

More information

Cost Engineering Dr. Nabil I El Sawalhi Assistant Professor Construction Management

Cost Engineering Dr. Nabil I El Sawalhi Assistant Professor Construction Management Cost Engineering Dr. Nabil I El Sawalhi Assistant Professor Construction Management 1 Cost Engineering Definitions 2 Course Goals The course is intended to give the student the knowledge and understanding

More information

IT portfolio management template User guide

IT portfolio management template User guide IBM Rational Focal Point IT portfolio management template User guide IBM Software Group IBM Rational Focal Point IT Portfolio Management Template User Guide 2011 IBM Corporation Copyright IBM Corporation

More information

POLI 343 Introduction to Political Research

POLI 343 Introduction to Political Research POLI 343 Introduction to Political Research Session 12: Non-Probability Sampling Lecturer: Prof. A. Essuman-Johnson, Dept. of Political Science Contact Information: aessuman-johnson@ug.edu.gh College of

More information

What Is Conjoint Analysis? DSC 410/510 Multivariate Statistical Methods. How Is Conjoint Analysis Done? Empirical Example

What Is Conjoint Analysis? DSC 410/510 Multivariate Statistical Methods. How Is Conjoint Analysis Done? Empirical Example What Is Conjoint Analysis? DSC 410/510 Multivariate Statistical Methods Conjoint Analysis 1 A technique for understanding how respondents develop preferences for products or services Also known as trade-off

More information

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES TIMEBOXING PLANNING: BUFFERED MOSCOW RULES EDUARDO MIRANDA, INSTITUTE FOR SOFTWARE RESEARCH, CARNEGIE MELLON UNIVERSITY, SEPTEMBER 2011 ABSTRACT Time boxing is a management technique which prioritizes

More information

Life Cycle Assessment A product-oriented method for sustainability analysis. UNEP LCA Training Kit Module f Interpretation 1

Life Cycle Assessment A product-oriented method for sustainability analysis. UNEP LCA Training Kit Module f Interpretation 1 Life Cycle Assessment A product-oriented method for sustainability analysis UNEP LCA Training Kit Module f Interpretation 1 ISO 14040 framework Life cycle assessment framework Goal and scope definition

More information

Vulnerability modelling of metal-clad industrial buildings to extreme wind loading

Vulnerability modelling of metal-clad industrial buildings to extreme wind loading Vulnerability modelling of metal-clad industrial buildings to extreme wind loading *K.M. Chaminda Konthesingha 1),Mark G. Stewart 2), John Ginger 3), David Henderson 4) 1), 2) Centre for Infrastructure

More information

Use of AHP Method in Efficiency Analysis of Existing Water Treatment Plants

Use of AHP Method in Efficiency Analysis of Existing Water Treatment Plants International Journal of Engineering Research and Development ISSN: 78-067X, Volume 1, Issue 7 (June 01), PP.4-51 Use of AHP Method in Efficiency Analysis of Existing Treatment Plants Madhu M. Tomar 1,

More information

Comparison of tasks and responsibilities in the building control systems of European Union countries

Comparison of tasks and responsibilities in the building control systems of European Union countries Comparison of tasks and responsibilities in the building control systems of European Union countries João Branco Pedro 1&2, Frits Meijer 1 and Henk Visscher 1 1 OTB Research Institute for Housing, Urban

More information

A study on agriculture information generation and dissemination at the Department of Agriculture (DOA) in Sri Lanka

A study on agriculture information generation and dissemination at the Department of Agriculture (DOA) in Sri Lanka A study on agriculture information generation and dissemination at the Department of Agriculture (DOA) in Sri Lanka Dilrukshi, W.P.T 1 and Muddannayake, I 2 Abstract The paper discusses findings of a survey

More information

SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA

SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA SELECTING A PROFOUND TECHNICAL SERVICE PROVIDER TO PERFORM A TECHNICAL FIELD DEVELOPMENT STUDY FROM GIVEN MULTIPLE CRITERIA Slamet Riyadi, Lokman Effendi and Rafikul Islam Department of Business Administration,

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

RISK MANAGEMENT AND RESOLUTION STRATEGIES FOR ESTABLISHED AND NOVEL TECHNOLOGIES IN THE LOW HEAD, SMALL HYDROPOWER MARKET

RISK MANAGEMENT AND RESOLUTION STRATEGIES FOR ESTABLISHED AND NOVEL TECHNOLOGIES IN THE LOW HEAD, SMALL HYDROPOWER MARKET RISK MANAGEMENT AND RESOLUTION STRATEGIES FOR ESTABLISHED AND NOVEL TECHNOLOGIES IN THE LOW HEAD, SMALL HYDROPOWER MARKET ABSTRACT Patrick WIEMANN (1) Gerald MÜLLER James SENIOR University of Southampton,

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Pre-Contract Estimates And Cost Plans Preface Preface A Working Committee with representatives from The Hong Kong Institute of Surveyors, Association of Consultant

More information

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report Page 1 of 54 16 November 27 US climate change impacts from the PAGE22 integrated assessment model used in the Stern report Chris Hope & Stephan Alberth Judge Business School, University of Cambridge, UK

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

INTERIOR DESIGN AND CONSTRUCTION PROJECT MANAGEMENT: PERFORMANCE AND PRODUCTIVITY IN MALAYSIAN BUILDING INDUSTRY

INTERIOR DESIGN AND CONSTRUCTION PROJECT MANAGEMENT: PERFORMANCE AND PRODUCTIVITY IN MALAYSIAN BUILDING INDUSTRY JOURNAL OF ARCHITCTURE, PLANNING & CONSTRUCTION MANAGEMENT Volume 6 Issue 1, 2016 INTERIOR DESIGN AND CONSTRUCTION PROJECT MANAGEMENT: PERFORMANCE AND PRODUCTIVITY IN MALAYSIAN BUILDING INDUSTRY International

More information

EST Accuracy of FEL 2 Estimates in Process Plants

EST Accuracy of FEL 2 Estimates in Process Plants EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only

More information

SUPPLIER SEGMENTATION IN IRANIAN AUTOMOTIVE INDUSTRY

SUPPLIER SEGMENTATION IN IRANIAN AUTOMOTIVE INDUSTRY SUPPLIER SEGMENTATION IN IRANIAN AUTOMOTIVE INDUSTRY Mehdi Rahimi 1, Nargess Imanipoor 2, Nasrin Akhondi 3, Shohreh Ghadami 4 Abstract New concepts of Supply Chain Management have appeared more than 20

More information

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M.

Introduction. Project Scheduling. Morgan State University ARCH 738: REAL ESTATE PROJECT MANAGEMENT. Jason E. Charalambides, PhD, M. Project Scheduling ARCH 738: REAL ESTATE PROJECT MANAGEMENT Morgan State University Jason E. Charalambides, PhD, M.ASCE, AIA, ENV_SP (This material has been prepared for educational purposes) Introduction

More information

Good Practice Urban Agriculture and Better Built Environment in India

Good Practice Urban Agriculture and Better Built Environment in India Good Practice Urban Agriculture and Better Built Environment in India Abstract There must be a long term regional perspective to make cities sustainable through urban agriculture. The rivers, canals, agricultural

More information

Construction Project Scheduling of MK Apartment Using MS Project 2013

Construction Project Scheduling of MK Apartment Using MS Project 2013 Construction Project Scheduling of MK Apartment Using MS Project 2013 Monish Kumar K 1, Maheshwar S Maregoudru 2, Sparsha B.P 3 1,2 PG Student, Dept. of Civil Engineering, KVGCE, Sullia, Karnataka, India

More information

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering Design and construct Superseding (in part) NZS 3910:2003 NZS 3916:2013 COMMITTEE REPRESENTATION This Standard was prepared

More information

Risk Analysis Overview

Risk Analysis Overview Risk Analysis Overview What Is Risk? Uncertainty about a situation can often indicate risk, which is the possibility of loss, damage, or any other undesirable event. Most people desire low risk, which

More information

Bridging the gap between predicted and actual energy performance in schools

Bridging the gap between predicted and actual energy performance in schools Bridging the gap between predicted and actual energy performance in schools Christine Demanuele 1*, Tamsin Tweddell 2 and Michael Davies 1 1 Bartlett School of Graduate Studies, University College London,

More information

REGULATING CONCRETE QUALITY

REGULATING CONCRETE QUALITY REGULATING CONCRETE QUALITY Ken W. Oay*, Consultant, Melbourne, Australia 29th Conference on OUR WORLD IN CONCRETE & STRUCTURES: 25-26 August 2004, Singapore Article Online Id: 100029005 The online version

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Test your Understanding-The Answers

Test your Understanding-The Answers Table of Contents Module 1 Project management methodology... 2 A. Introduction to Project Management... 2 B. The Phases of Project Management... 2 C. Project Management Methodology questions... 2 Module

More information

DEVELOPMENT OF RISK-BASED STANDARDIZED WBS (WORK BREAKDOWN STRUCTURE) FOR COST ESTIMATION OF APARTMENT S PROJECT

DEVELOPMENT OF RISK-BASED STANDARDIZED WBS (WORK BREAKDOWN STRUCTURE) FOR COST ESTIMATION OF APARTMENT S PROJECT International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 10, October 2017, pp. 822 833, Article ID: IJCIET_08_10_087 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=10

More information

Job Content and Training Needs of Agricultural Extension Agents in South-Central Botswana 1

Job Content and Training Needs of Agricultural Extension Agents in South-Central Botswana 1 Job Content and Training Needs of Agricultural Extension Agents in South-Central Botswana 1 Flora M. Tladi, PhD Botswana College of Agriculture The University of Botswana Private Bag 0027, Gaborone, Botswana

More information

Commercial Construction 1

Commercial Construction 1 Commercial Construction 1 Your topic: Your written report should be 2,500 words in length and should be referenced where necessary using an appropriate referencing style. Your report should analyze at

More information