Risk Assessment & Safe Working Practice

Size: px
Start display at page:

Download "Risk Assessment & Safe Working Practice"

Transcription

1 RA Ref Number: 08 Revision: 3 Project/Job Number Reference Insert Job Number Approval Date: 30/03/2018 RA Description: Working above false ceilings (in false ceiling s) Next Review Date: 01/04/2019 Notes: Please refer to Safe Working Practices 08 for definitions of items in this assessment. Created by: Lee Davies Risk Assessment Method & Scoring The summary risk assessment is calculated as Likelihood x Consequence and categorised as follows; 1 to 6 = 7 to 16 = 17 to 25 = High Risk Issued by: Issue Date: Insert Name Insert Date Asbestos related disease. Injuries from dropping tiles during removal. Injury from the collapse of the ceiling grid. All Present. Total 15 Engineer Engineer / below Total 15 Engineers are trained in asbestos recognition. Engineers are trained to not touch any tiles they suspect may contain asbestos. Engineers are trained to report to the client any tiles they suspect may contain asbestos. Engineers ask to see the asbestos register for the building prior to any works taking place, should this not be available, and the presence of asbestos is suspected the work does not start until a qualified person has carried out a suitable survey. Engineers are trained in tile removal. Tiles are removed one at a time. If only a single tile is removed from an area of six tiles, it is not removed from the ceiling. If other persons are present, two men are used to carry out this task, the tiles are handed down to a person on the ground for stacking. Engineers are trained to inspect the ceiling fixings for any sign of weakening. Any potential failure points are noted, reported to the client, and work does not continue. Tiles are never removed from a grid to a greater ratio than 1 out to 1 in. Tiles are never stacked in a to a greater ratio of 6 in to 1 out. CDI works never involve the any ceiling supports. Total 5 Total 5 RA Number: 08 - Issue Revision: 3 Page 1 of 5

2 storage of removed ceiling tiles use of tools, or pulling of cabling in a ceiling. The fitting of a containment drop through a tile. The fitting of a containment drop through a side support grid. The steel type ceiling tiles in none lay in grid systems. Injury from trips / falls over stored tiles. Injury from tiles being damaged from above and from items dropped through the open grid. Failure of the tile due to cutting. Failure of the ceiling due to the cutting of a support grid. Injury from tiles dropping out of the grid after re-fitting, due to expansion of the slots. All present. All present. Likelihood 4 Total 16 Engineers are trained to stack removed tiles neatly in a dedicated storage area. Warning signs and barriers are placed around the stacked tiles to keep unauthorised persons away. Engineers are trained never to overreach in ceiling s. Engineers are trained never to lean on, or place items within the ceiling. Engineers are trained never to take any items into the ceiling apart from those immediately required. The ceiling is not used as a storage space. Cutting / setting of containment is not carried out in the ceiling. Engineers are trained to install a plywood section of minimum 4mm depth, and the same size as the tile, into the ceiling grid to support the containment, and remove the strain from the cut tile. Engineers are trained to chop a slice of plaster out from behind the grid to run cabling, thus the grid is not cut at all. On finding a tile where the grid is in danger of expanding engineers are trained to fit a drilled fixing into the slab above the tile, and to then pass a thin wire through the fixing and the tile, to allow for only a short drop of the tile before it is caught by the support wire. RA Number: 08 - Issue Revision: 3 Page 2 of 5

3 fibreglass insulation. fibreglass insulation. Contamination of the area from loose dust. Skin irritation by fibreglass particles. All present. Likelihood 4 Total 16 Engineer Likelihood 4 Engineers are trained to assess the condition of fibreglass insulation. On a single tile, if insulation is found to be breaking down into dust, the works are stopped, and the client contacted. The client appoints a specialist contractor to assess the insulation. Engineers are trained to wear the correct PPE for fibreglass where the task specific RA requires it. EG; 1. Latex / cotton gloves. AC PN 5935 (AC Electrical part no). 2. A dust mask and filter AC PN FFP3 Fine dust spec. 3. Overalls with sleeves disposable paper type. AC PN 7780 / Goggles AC PN fibre glass insulation fibre glass insulation Contamination of the area from loose dust during works. Contamination from fibreglass dust during cleaning up. All present. Likelihood 4 All present Likelihood 4 Engineers are trained to place dustsheets over the areas likely to be contaminated prior to ceiling tile removal. Engineers are supplied with vacuums and suitable filters / bags to remove dust after works. Engineers are trained in the disposal of all overalls, dustsheets, vacuum bags etc so as to not compromise the environment. Engineers remove overalls in a controlled environment, and the areas are vacuumed clean afterwards. RA Number: 08 - Issue Revision: 3 Page 3 of 5

4 Safe Working Practice: 08 Working above false ceilings (in false ceiling s) 1 PURPOSE: The purpose of this guide is to highlight safe working practices for: Working above false ceilings (in false ceiling s) THIS INSTRUCTION MUST NOT BE TREATED AS A SUBSTITUTE FOR TRAINING. All persons working above false ceilings must receive appropriate training 2 PROTECTIVE CLOTHING AND EQUIPMENT Operators must wear Safety Boots/Shoes incorporating steel toe-caps CDI issued work wear Eye Protection where appropriate Hard Hat where appropriate 3 BEFORE WORK Be aware that there are many types of ceiling tile. The older types can contain asbestos, or be painted with lead/asbestos type paints. Never attempt to remove a tile you are unsure of, ask to see the building asbestos register, but even if the tiles are not listed, assume that they are asbestos, and contact the main contractor/client, or a specialist contractor. Lock in grid type ceilings can only be removed by cutting the tiles and sliding them along the grid. This is a specialist job, and should not be attempted by an untrained person. Steel type tiles push fit into the grid, and once removed can become loose and fall. When the tile is replaced, drill a cable base fixing into the slab above it, and pass a length of wire through the base fixing, passing through the small holes in the tile. This should be long enough to support the tile should it drop out of the grid, but be short enough to keep the dropped tile above head height of passers by. Be aware that above tiles fibreglass insulation can often be found. Always wear a dust mask and overalls when removing tiles. If loose insulation is found in large quantities it should be removed by a specialist contractor prior to works continuing. LAY IN GRID TYPE. First survey the building to establish which tiles are to be removed. Lay out a dust sheet, or arrange to have a vacuum on hand. Ensure your hands are clean, or you have clean gloves. Set up a set of steps, or a tower, being aware of the practices listed in working at height. RA Number: 08 - Issue Revision: 3 Page 4 of 5

5 4 DURING WORK LAY IN GRID TYPE. Tiles should not be removed whilst persons are directly beneath the area of works. Push gently up on the centre of the tile, and tapping the corners gently it should lift easily out of the grid, turn the tile through 90 degrees, and lower it through the grid square. Should there be resistance to lifting, do not force it. Try another tile nearby instead. When the first tile is out, store it to one side where it cannot be trodden on, knocked over, or damaged in other ways. With the first tile out, look carefully over the ceiling from within the grid to establish any difficulties with other tiles to be removed. Typically these will be trunking, conduits, ducts, insulation, etc. Some tiles may have to be left in due to equipment being fitted close to the grid on the inside. Carry on along the run to remove other tiles. Never remove all the tiles from an area as this will weaken the grid. Stack all the removed tiles in one place. Never remove grid bars from the ceiling. Do not remove or cut ceiling suspension wires. When tiles are removed from an area, take them away, and store them flat, in a clean secure place, until the job is finished. If possible, do not replace tiles that will have to be removed later in the job, as this will increase the risk of damage to the tile. Some clients may insist that tiles are replaced at the end of every shift, typically during night works where the building is returned to as was at the end of every shift. If this is the case ask the customer to provide a box of spare tiles to replace damaged units. Never lean on the grid, place weight on other tiles or the grid, or allow cables to drag against the grid when they are being pulled in. Always have a man in the tile space to feed cabling over the grid, never over-reach, and always remove another tile to access areas beyond your arm s length. 5 AFTER WORK All debris shall be removed from the ceiling upon completion of work prior to reinstalling tiles. Ensure that all tiles that you have removed are replaced. Vacuum carefully to clean up all dust after tiles have been replaced. Remove all waste to the designated containers, or return to CDI for correct disposal CDI GROUP LTD PLACES GREAT IMPORTANCE ON EVERYONE'S SAFETY: FAILURE TO COMPLY WITH ANY OF THE ABOVE MAY RESULT IN DISCIPLINARY ACTION RA Number: 08 - Issue Revision: 3 Page 5 of 5

Risk Assessment & Safe Working Practice

Risk Assessment & Safe Working Practice RA Ref Number: 38 Revision: 3 Project/Job Number Reference Insert Job Number Approval Date: 30/03/2018 RA Description: Installing cable tray and basket Next Review Date: 01/04/2019 Notes: Please refer

More information

Risk Assessment & Safe Working Practice

Risk Assessment & Safe Working Practice RA Ref Number: 01f Revision: 2 Project/Job Number Reference Insert Job Number Approval Date: 30/03/2018 RA Description: Working at Heights Fixed Tubular Scaffolds Next Review Date: 01/04/2019 Notes: Please

More information

K.Construction Scotland LTD

K.Construction Scotland LTD K.Construction Scotland LTD Leith, Edinburgh, EH6 5NA, Scotland, U.K Tel: 0131-554-0514 Email: contact@kconstructionltd.com Company Number: SC288209 VAT number: GB870618611, Method Statement For the Refurbishment

More information

Risk Assessment Site name:

Risk Assessment Site name: Risk Assessment Site name: Task: Installation of signage externally fixed at height Ref: INS/Site/RA194 Persons Affected: Insign installation operatives, Visitors to the site, Clients employees, Members

More information

SOUNDSCAPES BAFFLES. Assembly and Installation Instructions

SOUNDSCAPES BAFFLES. Assembly and Installation Instructions SOUNDSCAPES BAFFLES Assembly and Installation Instructions DO NOT REMOVE BAFFLES FROM THE CARTON UNTIL YOU HAVE READ THESE INSTRUCTIONS IN THEIR ENTIRETY. 1. GENERAL 1.1 Product Description SOUNDSCAPES

More information

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4

LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 LOS ANGELES COMMUNITY COLLEGES OFFICE OF THE CHANCELLOR ADMINISTRATIVE REGULATIONS INDEX NUMBER B-4 REFERENCE: ISSUE DATE: January, 1983 CHANGES: TOPIC: Asbestos INITIATED BY: Business Services DATE OF

More information

24 Portable Saw Mill OWNER S MANUAL

24 Portable Saw Mill OWNER S MANUAL 24 Portable Saw Mill OWNER S MANUAL WARNING: Carefully read and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions

More information

20 Portable Saw Mill OWNER S MANUAL

20 Portable Saw Mill OWNER S MANUAL 20 Portable Saw Mill OWNER S MANUAL WARNING: Carefully read and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions

More information

Glasboard Liners. installation details. Installation Guide for Glasbord Fibreglass Reinforced Plastic (FRP) panels

Glasboard Liners. installation details. Installation Guide for Glasbord Fibreglass Reinforced Plastic (FRP) panels Glasboard Liners installation details Installation Guide for Glasbord Fibreglass Reinforced Plastic (FRP) panels PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNING INSTALLATION These guidelines are provided

More information

PAINT REMOVAL SPECIFICATION CONTRACTOR GUIDE FOR LEAD PAINT REMOVAL

PAINT REMOVAL SPECIFICATION CONTRACTOR GUIDE FOR LEAD PAINT REMOVAL CONTENTS: PAINT REMOVAL SPECIFICATION CONTRACTOR GUIDE FOR LEAD PAINT REMOVAL 1.0 AWARENESS AND PRECAUTION 2.0 TEST SAMPLING & REMOVAL EVALUATION 3.0 SITE EVALUATION 4.0 SITE PREPARATION 5.0 SAFETY EQUIPMENT

More information

RISK ASSESSMENT. HAZARD POTENTIAL 3 x MAJOR 2 SERIOUS 1 SLIGHT. RISK POTENTIAL 3 x HIGH 2 MEDIUM 1 LOW

RISK ASSESSMENT. HAZARD POTENTIAL 3 x MAJOR 2 SERIOUS 1 SLIGHT. RISK POTENTIAL 3 x HIGH 2 MEDIUM 1 LOW MANUAL HANDLING 1 Operative Sustaining Back Injury 2 Operative Sustaining Injury to Limbs 1 Where there is a risk of injury from the manual handling of materials, equipment etc., an assessment will be

More information

INSTALLATION INSTRUCTIONS LAMINATE

INSTALLATION INSTRUCTIONS LAMINATE INSTALLATION INSTRUCTIONS LAMINATE DROP LOCK GENERAL INSTRUCTIONS FOR LAMINATE HARDWOOD FLOORING ACCLIMATION Acclimation is a recommended procedure prior to installation of laminate flooring either on

More information

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR ANGLE-TO-ANGLE FLOORING

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR ANGLE-TO-ANGLE FLOORING LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR ANGLE-TO-ANGLE FLOORING WARNING Prior to installation, please ensure that the product received is the correct style and color as well as to the customer s

More information

METHOD STATEMENT SCREEDING OF FLOOR

METHOD STATEMENT SCREEDING OF FLOOR 17-18 Gaerwen Industrial Estate Gaerwen Isle of Anglesey LL60-6HR Tel: 01248-422555 Fax: 01248-422556 Mobile: 07891-557581 Project/Contract Preparation of sub floors & screeding principal Contractor Apollo

More information

INTRODUCTION TO THE PROGRAM

INTRODUCTION TO THE PROGRAM INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented in a definite order, so that employees will see the relationships between the various groups of information

More information

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM Revised January 2017 Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Introduction 1 Scope 1 Policy Statement

More information

2200-Lb. Semi-Electric Stacker OWNER S MANUAL

2200-Lb. Semi-Electric Stacker OWNER S MANUAL 2200-Lb. Semi-Electric Stacker OWNER S MANUAL WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR DROP LOCK FLOORING

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR DROP LOCK FLOORING LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR DROP LOCK FLOORING WARNING Prior to installation, please ensure that the product received is the correct style and color as well as to the customer s satisfaction.

More information

Modular Coldroom Installation Manual

Modular Coldroom Installation Manual Modular Coldroom Installation Manual May 2005 Disclaimer: The information contained in this installation guide is provided "as is". Bromic Pty Ltd does not warrant the accuracy, adequacy or completeness

More information

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES

University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES University of Toronto Asbestos Management Program PROCEDURAL CHECKLIST FOR TYPE 1 ASBESTOS ACTIVITIES Project Description: Date Work Conducted: Completed by: (Name and Dept) NOTIFICATION/AWARENESS: 1.

More information

1850 x 40/50mm Raised Shower Tray Kit

1850 x 40/50mm Raised Shower Tray Kit Installation Instructions 850 x 40/50mm Raised Shower Tray Kit Parts Supplied Description Qty Shower Tray Shower Tray Extension Parts Required (Fitting Kit) Materials Required Description Qty Description

More information

METALWorkS. RH200 Custom Hook-on Panels. General Installation Instructions. Ceiling 1.0 GENERAL Site Conditions Product Description

METALWorkS. RH200 Custom Hook-on Panels. General Installation Instructions. Ceiling 1.0 GENERAL Site Conditions Product Description Ceiling Systems Between us, ideas become reality METALWorkS General Installation Instructions RH200 Custom Hook-on Panels 1.0 GENERAL 1.1. Product Description RH200 system is a downward accessible, metal

More information

CDM Action Plan. This is a Construction Phase Plan for the following project:

CDM Action Plan. This is a Construction Phase Plan for the following project: CDM Action Plan This is a Construction Phase Plan for the following project: Plan Job name JB exterior Your name/company Ramsay Clay Your email address colour@ramsayclay.com Client Name Joe Bloggs Client

More information

Sprayed or Blown Fibre & Ceramic Fibre (Blanket)

Sprayed or Blown Fibre & Ceramic Fibre (Blanket) TRADE OF Industrial Insulation PHASE 2 Module 4 Insulation Materials, Science and Application UNIT: 8 Sprayed or Blown Fibre & Ceramic Fibre (Blanket) Produced by In cooperation with subject matter expert:

More information

Impression Graphic panels

Impression Graphic panels Impression Graphic panels Installation Guidelines 6003.I Rev. 02 8/15 Please Read Disclaimers: PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNING INSTALLATION!! These guidelines are provided in good faith to

More information

North West Facilities Ltd

North West Facilities Ltd Project/Contract North West Facilities Ltd 17-18 Gaerwen Industrial Estate Gaerwen Isle of Anglesey LL60-6HR Tel: 01248-422555 Fax: 01248-422556 Mobile: 07891 557 581 Full bathroom refit Principle Contractor

More information

HANDING-OVER CERTIFICATE - SCAFFOLDING

HANDING-OVER CERTIFICATE - SCAFFOLDING HANDING-OVER CERTIFICATE - SCAFFOLDING Contractor : Site : Contractor. customername Site. Site name Date : Time : Erected by : Signature : Description of section handed over Job specification. description

More information

SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE

SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE HARD SURFACE INSTALLATION You will need: Tape measure Rope or spray paint Weed spray Sharp utility knife and spare blades Synthetic grass adhesive

More information

COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS

COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS Refer to Technical Advisory for Scaffolds 1 No. Hazards Possible

More information

"ASBESTOS AWARENESS IN THE WORKPLACE"

ASBESTOS AWARENESS IN THE WORKPLACE MAJOR PROGRAM POINTS "ASBESTOS AWARENESS IN THE WORKPLACE" Training For THE OSHA ASBESTOS STANDARD Quality Safety and Health Products, for Today...and Tomorrow Outline of Major Points Covered in the "Asbestos

More information

Asbestos Management Plan

Asbestos Management Plan Asbestos Management Plan Purpose: In accordance with the Work Place Health and Safety regulations this Asbestos Management Plan must remain available on site at all times Building address 775 Kingsford

More information

RISK ASSESSMENT SHEET

RISK ASSESSMENT SHEET Task Generic install telecoms equipment Assessment date 3rd October 2017 Location Various Review date 2nd October 2018 Number of staff at work Various Signature 1 Selected locations Works carried out during

More information

ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET

ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET EP IDE KE GU IS TH ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET Asbestos could be in the house or building you are working on right now. Left alone, it isn t dangerous. However, once disturbed, tiny

More information

STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING

STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING STATE BANK OF INDIA-NUAGAON ADB SCHEDULE OF RATES FOR THE FACE LIFTING OF THE BRANCH BUILDING Sl. No. Description of the Works Unit Quantity Rate Amount 1 DISMANTLING WORKS Surface cleaning of roof by

More information

OPTIMA Vector Plank Installation Instructions

OPTIMA Vector Plank Installation Instructions CEILING SYSTEMS Between us, ideas become reality OPTIMA Vector Plank Installation Instructions 1. GENERAL 1.1. Product Description The Vector products referenced in these instructions are made from fiberglass.

More information

Optima Vector Plank. Installation Instructions. Ceiling

Optima Vector Plank. Installation Instructions. Ceiling Ceiling Systems Between us, ideas become reality Optima Vector Plank Installation Instructions 1. GENERAL 1.1. Product Description The Vector products referenced in these instructions are made from fiberglass.

More information

CPT 60 Powerfloat. User & Safety Instructions

CPT 60 Powerfloat. User & Safety Instructions CPT 60 Powerfloat User & Safety Instructions This handbook contains operating and maintenance instructions for the Refina CPT60 Power float Please keep it in a safe place. You may need to refer to it at

More information

MMM MASONRY, INC. Employee Safety Guidelines

MMM MASONRY, INC. Employee Safety Guidelines MMM MASONRY, INC. Employee Safety Guidelines This manual represents common hazards associated with masonry construction and is no way intended to replace the OSHA 29CFR 1926 Safety Standards. It is the

More information

Asbestos in Your Home

Asbestos in Your Home Asbestos in Your Home Your guide on where it may be used and what to do if it s in your home the facts Sandbourne Housing Association Registered Office: Beech House, 28-30 Wimborne Road, Poole, BH15 2BU

More information

SAFE WORK METHOD STATEMENTS (Draft version)

SAFE WORK METHOD STATEMENTS (Draft version) SAFE WORK METHOD STATEMENTS (Draft version) ZENTIH GLASS 3 Squill Place Arndell Park NSW Assisted by RICHMOND RIVER AGENCIES Bringing knowledge to work April 3rd 2007. www.richmondriveragencies.com.au

More information

Jointofeu Series Fire Barriers I Installation Instructions

Jointofeu Series Fire Barriers I Installation Instructions Product Description Jointofeu is manufactured from a woven mineral wool and installed into expansion joints with a heat resistant adhesive. It is suitable for both vertical and horizontal expansion joints

More information

In general, the management plan development process consisted of:

In general, the management plan development process consisted of: NWASCO SCHOOL DISTRICT #21 ASBESTOS MANAGEMENT PLAN PART I: GENERAL PROVISIONS OF THE MANAGEMENT PLAN 1.0 INTRODUCTION This Asbestos Management Plan was developed in accordance with the United States Department

More information

Level 2 NVQ Diploma in Removal of Hazardous Waste (Construction) Licensed Asbestos

Level 2 NVQ Diploma in Removal of Hazardous Waste (Construction) Licensed Asbestos Level 2 NVQ Diploma in Removal of Hazardous Waste (Construction) Licensed Asbestos November 2016 This qualification has a Total Qualification time (TQT) of 420 Hours Guided Learning Hours: 191 Ofqual Qualification

More information

IDENTIFICATION AND MANAGEMENT OF HAZARDS

IDENTIFICATION AND MANAGEMENT OF HAZARDS ) ERECTION OF INSULATED HOARDING SCREENS HOARDING MATERIAL The insulated hoarding consists of a 10mm thick layer of Foamex PVC bolted with M12 nylon bolts to a fibreglass scaffold frame. The panels will

More information

Asbestos Awareness Program

Asbestos Awareness Program Safety Manual 1 of 9 Safety Manual Sect: 1.0 Purpose 2.0 Scope Rel. Date: Last Review: This program covers Ardent policy related to asbestos, either discovered or suspected in the workplace. Ardent recognizes

More information

OSH INFORMATION MEMORANDUM 95 X 96. Inspection Guidelines for the Revised Personal Protective Equipment Standards for General Industry

OSH INFORMATION MEMORANDUM 95 X 96. Inspection Guidelines for the Revised Personal Protective Equipment Standards for General Industry OSH INFORMATION MEMORANDUM 95 X 96 TO: FROM: All OSH Compliance Personnel W. M. Lybrand DATE: August 8, 1995 SUBJECT: Inspection Guidelines for the Revised Personal Protective Equipment Standards for General

More information

PREMIER V Bucko Cast In Place

PREMIER V Bucko Cast In Place PREMIER V Bucko Cast In Place 28972 R. Ave Adel, Iowa 50003 800-343-9370 1850 West Adriatic Place Englewood, Colorado 80110 303-935-4679 Visit Monarch Materials Group, Inc. at www.monmatgrp.com Premier

More information

BRICK TANDOOR OVEN. Overview. What you will need JAMIE & JIMMY S FRIDAY NIGHT FEAST SERIES 6

BRICK TANDOOR OVEN. Overview. What you will need JAMIE & JIMMY S FRIDAY NIGHT FEAST SERIES 6 BRICK TANDOOR OVEN JAMIE & JIMMY S FRIDAY NIGHT FEAST SERIES 6 Overview This is a great way to build a tandoor at home, using easy to buy materials. A tandoor is a traditional oven found across Asia, which

More information

SUCCESS ON THE JOB SITE

SUCCESS ON THE JOB SITE Guide to SUCCESS ON THE JOB SITE Storage, handling and preparation Complete guide to pre-finished materials always there, naturally Woodtone Success on the Job Site Section 1: Before you Begin Please ensure

More information

Mounting Screw. Channel Filler. Light Angle Adjustable Screw. LED Board Vertical stud and blocking Locking Nose. Driver.

Mounting Screw. Channel Filler. Light Angle Adjustable Screw. LED Board Vertical stud and blocking Locking Nose. Driver. The Knife Edge Cove is a modular lighting system consisting of two parts: 1- An aluminum fixture housing extrusion 2- Drop-in lighting modules The fixture will provide a continuous knife edge architectural

More information

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the City of Vancouver Invitation to Tender including all available documents,

More information

1000-LB. CAPACITY STEEL LOADING RAMPS (PAIR)

1000-LB. CAPACITY STEEL LOADING RAMPS (PAIR) 1000-LB. CAPACITY STEEL LOADING RAMPS (PAIR) OWNER S MANUAL WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other

More information

These procedures are to be followed by all persons required to perform the following work:

These procedures are to be followed by all persons required to perform the following work: These procedures are to be followed by all persons required to perform the following work: Entry into any ceiling space above which an asbestos-containing fireproofing or thermal insulation is present.

More information

Health & Safety Plan DEMOLITION WORKS: No 2 Substation

Health & Safety Plan DEMOLITION WORKS: No 2 Substation DEMOLITION WORKS: No 2 Substation Revision History Revision Date Section Detail of Amendment By r3a 09/10/14 First Issue JH 17 October 2014 Page 2 Revision 4 Contents 1. Description of Project 1.1. Introduction

More information

Prepared By: Progressive Safety Services LLC

Prepared By: Progressive Safety Services LLC Prepared By: Progressive Safety Services LLC Definition Goals/Benefits Involvement Job Safety Analysis (JSA) Review The assessment of risks present in a particular environment Classification of exposure

More information

ASBESTOS MATERIALS REVIEW

ASBESTOS MATERIALS REVIEW ASBESTOS MATERIALS REVIEW MOTEL PRINCES HIGHWAY VICTORIA Prepared by PREMIER SAFETY and ENVIRONMENTAL Health Safety & Environmental Consultants Mobile: 048 51594 Office: (0) 5156 0272 ruary 2017 PREMIER

More information

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August

DOUBLE SLIDE RAIL INSTALLATION METHOD. Double Slide Rail August Double Slide Rail August 2015 1 DOUBLE SLIDE RAIL INSTALLATION METHOD Introduction Slide rail shoring systems can be used for trenches up to 12m wide and 6m deep. Module length is determined by panels

More information

JASPER. PAGE 2: 2x2 T-GRID INSTALLATION. PAGE 3: 2x2 SRI SHEETROCK INSTALLATION. PAGE 4: 2x2 IEM INSTALLATION

JASPER. PAGE 2: 2x2 T-GRID INSTALLATION. PAGE 3: 2x2 SRI SHEETROCK INSTALLATION. PAGE 4: 2x2 IEM INSTALLATION 2016 JASPER CM2082 (2x2) PAGE 2: 2x2 T-GRID INSTALLATION PAGE 3: 2x2 SRI SHEETROCK INSTALLATION PAGE 4: 2x2 IEM INSTALLATION PAGE 5: INSTALLATION OF THE EARTHQUAKE CLIPS Drawing: 762300XX_2x2 Rev: A Sheet:

More information

2013 HSC Electrotechnology Marking Guidelines

2013 HSC Electrotechnology Marking Guidelines 2013 HSC Electrotechnology Marking Guidelines Section I Multiple-choice Answer Key Question Answer 1 B 2 D 3 A 4 B 5 D 6 A 7 D 8 C 9 A 10 D 11 A 12 B 13 C 14 B 15 C 1 Section II Question 16 (a) Identifies

More information

MODULAR ACOUSTIC FENCING INSTALLATION GUIDE

MODULAR ACOUSTIC FENCING  INSTALLATION GUIDE MODULAR ACOUSTIC FENCING WWW.QUICKBUILTSYSTEMS.COM.AU INSTALLATION GUIDE INTRODUCTION THE QUICKBUILT FENCE SYSTEM IS A SMARTLY DESIGNED MODULAR SYSTEM EASY AND FAST TO INSTALL AND COST EFFECTIVE. // THE

More information

Safe Work Method Statement

Safe Work Method Statement Safe Work Method Statement Disclaimer: Use of Master Builders Generic Safe Work Method Statements The Master Builders Association of Victoria expressly disclaim all and any liability to any person in respect

More information

NC Sturgeon Safety Management System

NC Sturgeon Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose To provide guidelines for identifying, assessing and controlling workplace hazards; To ensure the potential hazards

More information

COMPOSITES LAB MANUAL

COMPOSITES LAB MANUAL COMPOSITES LAB MANUAL Version 1 Lab 2: Health concerns and safety procedures The original version of this manual was a one student senior design project written by Katherine White, the Composite lab assistant,

More information

PORTABLE GARAGE CAR CANOPY

PORTABLE GARAGE CAR CANOPY PORTABLE GARAGE CAR CANOPY 40544 ASSEMBLY INSTRUCTIONS 3491 Mission Oaks Blvd., Camarillo, CA 93011 Copyright 1999 by Harbor Freight Tools. All rights reserved. No portion of this manual or any artwork

More information

ARTEX AND PLASTER. 2 - Choosing the right product

ARTEX AND PLASTER. 2 - Choosing the right product ARTEX AND PLASTER Proper plastering is not easy. But DIY plasters are designed with ease of use in mind, and Artex TM is no more difficult to apply than thick paint. It is best to wear gloves when mixing

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

2010 HSC Construction Sample Answers

2010 HSC Construction Sample Answers 2010 HSC Construction Sample Answers Section II This document contains sample answers, or, in the case of some questions, answers could include. These are developed by the examination committee for two

More information

Asbestos in the home. Do s and don ts. for you - for your community - not for profit.

Asbestos in the home. Do s and don ts. for you - for your community - not for profit. Asbestos in the home Do s and don ts www.tworivershousing.org.uk for you - for your community - not for profit Facts about asbestos, where it may be used and what to do if you find it Introduction This

More information

HAZARD IDENTIFICATION AND ASSESSMENT

HAZARD IDENTIFICATION AND ASSESSMENT Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose To provide guidelines for identifying, assessing and controlling workplace hazards; To ensure the potential hazards

More information

SECTION ALTERATION PROJECT PROCEDURES

SECTION ALTERATION PROJECT PROCEDURES SECTION 013516 ALTERATION PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for protection of existing facilities during construction operations. 2. Demolition and removals

More information

Industrial flue gas probes. Instruction manual

Industrial flue gas probes. Instruction manual Industrial flue gas probes Instruction manual 2 1 Contents 1 Contents 1 Contents... 3 2 Safety and the environment... 4 2.1. About this document... 4 2.2. Ensure safety... 4 2.3. Protecting the environment...

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors)

XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors) XXVI. Contractor Safety & Environmental Guidelines (For General Contractors and Sub-Contractors) 1. PURPOSE 1.1 This procedure highlights minimum safe working practices required for all contractors working

More information

Aluminum Headache Rack

Aluminum Headache Rack Instruction Manual Aluminum Headache Rack ITEM NO.: AHAR Read and understand this entire manual before assembling, installing, operating, or servicing this product. SAVE THIS MANUAL IMPORTANT SAFETY INFORMATION

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

7 2 i n. x 9 i n. Tr i - Fo l d R a m p s OWNER S MANUAL

7 2 i n. x 9 i n. Tr i - Fo l d R a m p s OWNER S MANUAL 7 2 i n. x 9 i n. Tr i - Fo l d R a m p s OWNER S MANUAL WARNING: Read carefully and understand all ASSEMBLY AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other basic

More information

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080 PART 1 GENERAL 1.0 Instructions To Bidders Hazardous Materials Contractors are responsible for the information as provided in the Invitation to Tender including all available documents, meeting minutes,

More information

VESDURA VINYL PLANKS 7.5MM WPC CLICK LOCK - AMERICANA COLLECTION

VESDURA VINYL PLANKS 7.5MM WPC CLICK LOCK - AMERICANA COLLECTION VESDURA VINYL PLANKS 7.5MM WPC CLICK LOCK - AMERICANA COLLECTION Before You Start Click lock vinyl plank flooring is normally laid without adhesive. Before installation, planks must be allowed to acclimatize

More information

VESDURA VINYL PLANKS 5.5MM WPC CLICK LOCK - AMERICANA COLLECTION

VESDURA VINYL PLANKS 5.5MM WPC CLICK LOCK - AMERICANA COLLECTION VESDURA VINYL PLANKS 5.5MM WPC CLICK LOCK - AMERICANA COLLECTION Before You Start Click lock vinyl plank flooring is normally laid without adhesive. Before installation, planks must be allowed to acclimatize

More information

One Meter Internal Dome Oven AVERAGE GUIDE

One Meter Internal Dome Oven AVERAGE GUIDE FIELD FURNACE REFRACTORIES Pty Ltd. 8 Arnott Place Wetherill Park NSW 2164 Phone: 02-9729-1799 Fax: 02-9729-1899 One Meter Internal Dome Oven AVERAGE GUIDE Quantity Description Unit price Total 192 Tapered

More information

Manual handling and lifting guide. Telephone: Fax: Training enquiries:

Manual handling and lifting guide. Telephone: Fax: Training enquiries: Gyproc, Thistle, Gypframe, Glasroc and Arteco are all registered trade names of BPB United Kingdom Limited. Isover is a registered trade name of Saint-Gobain. British Gypsum reserves the right to revise

More information

CORNER SLIDE RAIL OPEN PIT INSTALLATION INSTRUCTIONS

CORNER SLIDE RAIL OPEN PIT INSTALLATION INSTRUCTIONS CORNER SLIDE RAIL OPEN PIT INSTALLATION INSTRUCTIONS Introduction The double corner slide rail shoring system can be used for open pit excavations up to a 5m deep pit in various square or rectangular configurations

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Company Name: THE GROUP PTY LTD This SWMS has been developed and: (T/A ARTHUR S CONCRETE CUTTING) Approved by: ATHANASIOS Address: 18 PANANIA AVE PANANIA NSW 2213 Position: TEL:

More information

ESTATES DEPARTMENT. Management of Asbestos Policy and Procedures Document. Rev 9

ESTATES DEPARTMENT. Management of Asbestos Policy and Procedures Document. Rev 9 ESTATES DEPARTMENT Management of Asbestos Policy and Procedures Document Rev 9 Contents SECTION 1: Estates Management of Asbestos Policy 1.1 Introduction 1.2 Policy Statement 1.3 Legal Requirements 1.4

More information

Commercial & Industrial

Commercial & Industrial BLANKET PINK BATTS BUILDING INSULATION BLANKET (BIB) Installation Instructions Correct installation with no compression, gaps or folds is critical to ensure Pink Batts Building Insulation Blanket performance

More information

Mill, Burr STANDARD OPERATING PROCEDURE

Mill, Burr STANDARD OPERATING PROCEDURE STANDARD OPERATING PROCEDURE Mill, Burr Model: DK-15LS Manufacturer: Mahlkonig Gmbh & Company KG/Mahlkonig USA Location: Dry Processing Pilot Plant, 1851 Food Sciences Building Publication Date: 04/30/2015

More information

Premium wall cladding. Complete system. Installation guide. Preparation Profiles Sheet preparation and installation After care

Premium wall cladding. Complete system. Installation guide. Preparation Profiles Sheet preparation and installation After care Premium wall cladding Complete system Installation guide 1969 Preparation Profiles Sheet preparation and installation After care Cladright wall cladding installation guide This installation guide complies

More information

RAPID-EPS PATENT PENDING

RAPID-EPS PATENT PENDING SAFETY INSTRUCTIONS AND INSTALLATION GUIDE Rapid-Edge Protection Systems Document ref: MK 3 1108 Issue Date: Issued by:. Approved by: CONTENTS Safety instructions 3 Important 4 General 5 Product information..

More information

A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet

A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet 01 This mandatory safety sign means. A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet 02 If your employer asks you to work for another

More information

A. only after an accident. B. upon job completion C. only when told by supervisor. D. whenever one feels like it

A. only after an accident. B. upon job completion C. only when told by supervisor. D. whenever one feels like it 01 Workers are expected to and comply with Workplace Safety and Health regulations. A. carry out work quickly B. know the hazards asscoiated with work C. disregard workplace safety rules D. work overtime

More information

Scissor Lift Safety for Clients and Employees or ARS

Scissor Lift Safety for Clients and Employees or ARS ADVANCED RESOURCE SOLUTIONS INNOVATIVE SOLUTIONS FOR PROJECT SUCCESS Scissor Lift Safety for Clients and Employees or ARS Added 1/20/2017 Employees: Guidelines addressed in OSHA 1926.451; 1926.452(w);

More information

The management of asbestos-containing materials in the retail sector

The management of asbestos-containing materials in the retail sector The management of asbestos-containing materials in the retail sector Interpreting the Control of Asbestos Regulations (CAR) 2012 Section 6: Management of asbestos during maintenance works Summary of the

More information

DIVISION 02 SELECTIVE DEMOLITION

DIVISION 02 SELECTIVE DEMOLITION DIVISION 02 SELECTIVE DEMOLITION SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building.

More information

IBC Container. Introduction. Important Notes. Key Benefits. User Guide

IBC Container. Introduction. Important Notes. Key Benefits. User Guide User Guide IBC Container Introduction The Conquip IBC Liquid Container is an Intermediate Bulk Container for transporting and storing bulk liquids and other substances. It is a pallet tank that is reusable

More information

Developing Your PPE Program

Developing Your PPE Program Developing Your PPE Program A variety of hazards can exist in every workplace which may be exposing your employees to a potential injury or illness. As an employer you have a responsibility to implement

More information

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised:

JOB SAFETY ANALYSIS PROGRAM. Owner: Risk Management Revision No: 01. Document number: Q-001 Date last revised: Table of Contents 1.0 Applicability...2 2.0 Scope...2 3.0 Definitions...2 4.0 Core Information and Requirements...2 5.0 Roles and Responsibilities...6 6.0 Goals, Objectives and Performance Measures...7

More information

SYSTEM 600 BILL CHANGER INSTALLATION INSTRUCTIONS Congratulations...

SYSTEM 600 BILL CHANGER INSTALLATION INSTRUCTIONS Congratulations... www.standardchange.com 1-800-968-6955 Technical Phone Support is from 8:00AM to 7:30PM E.S.T., Monday-Friday Walk-in Service is from 8:00AM to 4:30PM E.S.T., Monday-Friday Parts Department is from 8:00AM

More information