1 DIVISION 1 GENERAL REQUIREMENTS SECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal Form, Contract Form, General Conditions, Supplementary Conditions, Information Available to Bidders (Geotechnical Report), Division I General Requirements, and all other documents as delineated by the Bid Package Table of Contents, apply to Work of this Section as though bound herein. B. The following Specification Sections are specifically referenced in this Section: 1.2 SUMMARY 1. Section Milestone Completion Dates. 2. Section Bid Categories and Scopes of Work A. This Section specifies the contract requirements relating to schedules and scheduling necessary to accomplish the completion of the work within the prescribed time frame. B. The requirements of this Section are specifically intended to expand upon the requirements of Specification Section Milestone Dates. C. Any reference to "Project Schedule", "Schedule" or any form of such throughout the Contract Documents shall refer to any appropriate form of the Project Schedule as defined herein. D. The following forms of schedules and data shall be utilized during the course of the project and shall all be considered part of the Project Schedule. 1. Initial Schedule Data Submission 2. Initial Progress Schedule 3. Updated Progress Schedules 4. Summary Schedule 5. Weekly Look Ahead Schedule 6. Recovery Schedule 7. Submittal Schedule 8. Schedule Progress Report 9. Critical Items Report E. All schedules shall use the Critical Path Method (CPM), unless a bar chart is specifically authorized in the Bid Categories and Scope of Work for the Bid Package. F. The Progress Schedule will be the main tool used to construct this Project. It will be in the form of a cost loaded CPM schedule with all activities of all entities involved in the project included in the database. The output format will be in the form of a bar chart sorted by responsibility. The responsibility level will include the Owner, Architect, Construction Manager and Contractors. 13-HC

2 G. Coordination of the Project Schedule shall be maintained by updating at monthly intervals. Shorter interval updates may be necessary and shall be determined by the Construction Manager. All Contractors shall participate in all Project Schedule updates as required. H. The approval of a Contractor's Monthly Progress Payment Request will be directly dependent upon the Contractor's keeping current with the completion of work as scheduled and the transmission of information to keep the Progress Schedule accurate. No Payment Requests will be approved for processing without the latest updated version of the Progress Schedule being formally accepted by all Contractors. I. The duties, obligation and warranties of the Owner to the Contractor shall be applicable only to the completion of the Work on the Milestone and Completion Dates required in the Owner-Contractor Agreement, unless Owner, Construction Manager, State Commission, and Contractor otherwise agree in writing. 1.3 RESPONSIBILITIES A. The Construction Manager is responsible for the following: 1. Development of the Summary Schedule. 2. Determination of milestone dates as provided in Section Milestone Completion Dates. 3. Overall phasing required to accommodate the Milestone Completion Dates. 4. Determine the work priority sequencing between Contractors. B. By submitting a bid, each Contractor has accepted the sequencing and milestones of the Summary Schedule included at the end of this Section. Each Contractor also acknowledges he has included enough manpower and resources to accomplish all work within the prescribed time frames. C. The Construction Manager, in association with and based upon input from the Contractors, will develop the Progress Schedule by expanding upon the Summary Schedule. All other reports and schedules will be prepared using the Progress Schedule database. D. Each Contractor shall be responsive to the overall schedule coordination responsibilities assigned to the Construction Manager. Each Contractor shall provide administrative and procedural coordination of scheduling and reporting with those of the other Contractors. E. Each Contractor shall coordinate his Work with that of other Contractors and shall cooperate fully with the Construction Manager in maintaining orderly progress toward completion of the Work as scheduled. The Construction Manager s decisions regarding priority between the contractor s Work and the Work of other Contractors shall be final and shall not be cause for extra compensation or an extension of time. F. Failure of Owner furnished equipment and materials to arrive as scheduled, or failure of other Contractors to meet their schedule, shall not be justification for an extension of time, except where such failure causes, in the opinion of the Construction Manager, an unreasonable delay in the Contractor s Work, in which case the provisions of the General Conditions regarding extensions of time and extra Work shall apply. G. The Contractor shall keep himself, and his subcontractors, advised at all times during the course of the Work regarding delivery status of Owner furnished equipment and materials and of the progress of construction Work being performed under separate Contracts. H. The Construction Manager shall distribute all forms of the Project Schedule and all updates to the Owner, Architect, Commission, Contractors and other entities associated with the HC1-033

3 1.4 FLOAT project. The Contractors shall be responsible to duplicate and distribute each schedule to their subcontractors and/or suppliers. The Construction Manager shall post the latest version of the Progress Schedule in the Construction Manager s Field Office. I. A Contractor may not unreasonably withhold his acceptance of an updated Progress Schedule. A. Total Float is defined as the time between the earliest start date and the latest start date or between the earliest finish date and the latest finish date of a chain of activities. Total Float is not for the exclusive use or benefit of either the Contractor or the Owner. The Contractor s Work shall proceed according to early start dates, and the Construction Manager shall have the right to reserve and/or apportion Total Float according to the needs of the project. The Contractor acknowledges and agrees that actual delays, affecting paths of activities containing float time, will not have any affect upon contract completion time, providing that the actual delay does not exceed the Total Float associated with those activities. B. Free Float is defined as the time between the early finish of an activity and the early start of a succeeding activity. Changes in logic that do not affect Total Float may have a profound impact on the early start date of activities while not affecting total duration. These conditions may have an impact on material delivery /storage and manpower scheduling of Contractors. The Construction Manager shall have the right to reserve and/or apportion Free Float according to the needs of the project. The Contractor acknowledges and agrees that logic changes that do not affect Total Float may have an impact on the Work of other Contractors. C. Extensions of time for performance as described in the Contract Documents will be granted only to the extent that time adjustments for the activity or activities affected by any condition or event which entitles the Contractor to a time extension exceeds the total float along the path of activities affected by a Change Order or the commencement of any delay or condition for which an adjustment is warranted under the Contract. 1.5 WORK SEQUENCE A. The Work Sequence is intended to represent the natural progression of Work throughout the construction period. The Work Sequence for a particular item includes but is not necessarily limited to the following: 1. Shop Drawing, Product Data and or Sample submittal preparation. 2. Shop Drawing, Product Data and or Sample submittal approval. 3. Fabrication and/or delivery of material/equipment. 4. Mock-up preparation and/or testing. 5. Coordination of work of previous and subsequent trades as it applies to installation of material/equipment. 6. Installation of material/equipment. 7. Coordination of impact of material/equipment on following trades. 8. Start-up and/or Testing material/equipment. 9. Clean-up, both as work progresses and a final effort. 10. Completion of close-out information. B. Although all attempts will be made to accommodate the Contractor's preferred sequencing, the final Work Sequence of a particular Contractor may not be ideal as far as maximizing efficiency and/or minimizing cost for that particular Contractor. A Contractor will not be 13-HC

4 entitled to extra compensation of an extension of time because of any such conditions. The Construction Manager shall be the sole judge as to the sequencing of Work between Contractors. C. Changes in the Work Sequence will not be made without the approval of the Construction Manager. 1.6 SCHEDULE REVISIONS A. Schedule revisions may be Contractor generated or Owner generated. No changes shall be valid and/or effective unless accepted by the Owner, Architect, State Commission, Construction Manager and all Contractors. B. All Contractor generated changes shall conform to the following format. 1. If a Contractor would like to change the Progress Schedule Work Sequence, he shall submit a formal request with the following information: a. Outline the proposed changes. b. Show all logic implications. c. Describe the purpose for the proposed changes. d. Define the impact the proposed changes would have on other Contractors. e. State any cost impact of proposed changes. 2. The Construction Manager will review the proposed changes. If the changes are rejected, the Contractor shall be notified immediately. If the changes are feasible, the changes will be presented to all other Contractor s for their review and approval. All Contractors will have to agree with any proposed change. 3. No Contractor generated changes will be processed that increase the overall net cost for the project to the Owner. Changes that increase the effort of one Contractor while reducing the scope of another Contractor will be considered but the net change must be no greater than $0. C. Owner generated changes shall conform to the following format. 1. The Owner, through the Construction Manager, shall submit the proposed changes to all Contractors for their review. Any proposed changes in Milestone Dates and/or Completion Dates shall be noted. 2. Within five (5) working days, the Contractors shall respond to the proposed changes in writing to the Construction Manager. If a Contractor believes the proposed changes have a cost impact on his work, he shall note that in his response and give a detailed accounting for said costs. 3. If the Contractor s responses are acceptable, the changes will be incorporated into the Progress Schedule. D. For a revised Progress Schedule, the Construction Manager will issue a sign-off form to all Contractors indicating their acceptance with the revised Progress Schedule. Each Contractor shall be required to sign and return this form to the Construction Manager. Unless specifically excepted by the Construction Manager, all subsequent project payments will be not be approved for processing until the revised Progress Schedule is accepted by all Contractors HC1-033

5 E. Should any proposed and subsequently accepted changes in the Progress Schedule result in earlier or later Milestone or Completion Dates, the revised dates shall become the new dates and all penalties shall apply thereto. The Owner, Architect, State Commission, and Construction Manager shall not be liable to the Contractor for any costs or other damages, should the Contractor be unable to complete the Work before said Milestone and/or Completion Dates. F. The Owner, Architect and Construction Manager must approve in writing any revised Progress Schedule that affects Milestone and/or Completion Dates. Said approval shall be in the form of a Contract Change Order. G. No revision to the Progress Schedule shall have the effect of amending of modifying, in any way, the Contract Duration, any Milestone Dates, any Contract Completion Dates or any of the Contractor s obligations under this Contract unless such revision is included as a Contract Change Order. 1.7 INITIAL SCHEDULE DATA SUBMISSION A. Ten (10) working days after award of the Contract, or unless otherwise specified, each Contractor shall prepare, submit, and review with the Construction Manager the following data which shall be considered the Initial Schedule Data Submission. B. The Initial Schedule Data Submission shall contain a detailed listing of the required work activities for incorporation into the Progress Schedule. The Construction Manager will issue a Schedule Input Form as described in paragraph 3.1 for use in preparation of this data. The level of detail required for each Contractor will be dependent on the complexity of the work. Each Contractor will show the interrelation with all other Contractors. C. The Construction Manager will be available, during normal working hours, to consult with the Contractors if questions arise while the Contractors are assembling the information required herein. D. A list of schedule activities shall be furnished. The activities shall be created to conform to the general categories listed under Work Sequence elsewhere in this Section. Each activity shall contain the following data: 1. An Activity Description which shall be clear and concise. 2. An Activity Duration which shall represent the time frame in working days that will be required to complete the task. The activity must be no more than fifteen working days in duration, unless approved by the Construction Manager. 3. An Activity Responsibility Code which shall identify the entity responsible for the completion of the task represented by the activity. 4. Activity Resource Loading which shall assign, manpower (by craft), commodity and equipment resources to the activity. Activities for entities other than the Contractor need not be resource loaded. 5. Activity Cost Loading which shall be broken down into both labor and material components. The sum of all of the costs for all of a Contractor s activities shall equal the Contractor s Contract Sum. This cost data shall be correlated to the Contractor's Schedule of Values, although several schedule activities may relate to one item on the Schedule of Values. The Contractor shall provide a detailed listing of this 13-HC

6 corresponding data to the Construction Manager. Activities for entities other than the Contractor need not be cost loaded. E. As part of this Initial Schedule Data Submission, each contractor shall submit a Project Submittal Log which is a complete listing of work related submittals. The Log shall be in the form of activities entered on the schedule input form. The Log shall be derived from the Submittals requirements of the detailed specifications and shall conform to the following parameters: 1. Identify by Specification Section. 2. Correlate with the applicable contractor s subcontractor and/or material supplier. 3. Stagger submittal dates to address the most critical items first and delay less critical items until later. 4. Create activities for each type of submittal (product data, shop drawings, samples or other type item). 5. Create activities for the fabrication and/or delivery of each item. Normally a separate activity for delivery is not necessary but ample time for delivery must be included in the duration given for the fabrication to accommodate delivery time. It is extremely important to tie these activities to the actual installation type activity to properly monitor the material delivery status of materials for the Project. 6. Subdivide a particular subject into submittal groups if all data will not be submitted at the same time. For example, structural steel may be received by areas of the building so there may be several submittals staggered for each area. F. The identification of any potential problems or constraints related to the implementation of the overall construction schedule shall be identified. G. The interrelation with the activities of the other Contractors and with the work of outside entities such as utility companies, furnishings vendors, and/or communications suppliers shall be clearly identified. H. The submitted data shall be grouped and/or organized with the following considerations: 1. Arrange data with notations to show how the sequence of work is affected by requirements for phased completion, work by separate non-prime contractors, work by the Owner, pre-purchased materials, coordination with existing work, limitations of continued occupancies, non-interruptible services, partial occupancy prior to substantial completion, site restrictions, provisions for future work, seasonal variations, environmental control and similar provisions of the total project. 2. Arrange data for each major area of construction and each major category or unit of work. Show where each major category or unit of work must be sequenced or integrated with other work as needed for structural completion, permanent space enclosure, completion of mechanical/electrical work and for overall work in the area. Except as otherwise indicated, or subsequently agreed with the Construction Manager, a major area is defined to mean a story of construction or similar major separation or component of the building. 1.8 INITIAL PROGRESS SCHEDULE A. The Initial Progress Schedule will be compiled by the Construction Manager with the input of all Contractors involved in the Project HC1-033

7 B. The Construction Manager will incorporate the Initial Schedule Data Submission information from all the Contractors into a database and subsequently publish and distribute the Initial Progress Schedule. Any impact on the Summary Schedule will be noted on the distribution transmittal. C. The Construction Manager will schedule a meeting approximately ten (10) days after distribution of the Initial Progress Schedule. Each Contractor will be required to send a knowledgeable and contributing company representative who has a working knowledge of the project, is familiar with CPM schedules and will have authority to sign-off on the Initial Progress Schedule including any changes which may be discussed at the meeting. If more than one representative is required to accommodate the requirements then the Contractor shall send additional personnel. The initial Progress Schedule will be reviewed in detail. Any proposed changes will be discussed and the impact on all Contractors will be reviewed. Each Contractor shall be required to allocate all the time necessary to complete the schedule review even if it requires more than one day s commitment. Any impact upon the Summary Schedule will be reviewed and resolved. D. After all items are discussed and resolved, the Construction Manager will change the database and then publish the Progress Schedule. This document will become the schedule to which all Contractors shall adhere. E. The Construction Manager will issue a sign-off form to all Contractors indicating their acceptance with the Initial Progress Schedule. Each Contractor shall be required to sign and return this form to the Construction Manager. Unless specifically exempted by the Construction Manager, all initial project payments will be held for processing until the Initial Progress Schedule is accepted by all Contractors. 1.9 PROGRESS SCHEDULE A. After the Initial Progress Schedule is prepared and approved by all Contractors it shall then become known as the Progress Schedule and will be maintained and updated throughout the course of the Project. B. Each Contractor shall submit a Schedule Progress Report to the Construction Manager to allow the Progress Schedule to be updated on a monthly basis. This report shall be in the format described elsewhere in this Section. The Construction Manager will generate a Cost Report from this data to monitor and verify progress and use to validate the Contractor s Pay Application. This report shall be submitted on the last day of the third week of a pay period and will anticipate progress to the end of the period. C. The Construction Manager will input the monthly data and recalculate the Progress Schedule based upon the actual progress. 1. If the updated Progress Schedule does not adversely affect any critical path dates, a preliminary version of the Progress Schedule will be reviewed by all Contractors at a Master Schedule Update Meeting on the first Monday of each month per Section a. Each Contractor shall notify the Construction Manager of any changes in the progress that could affect contract completion dates. b. Each Contractor shall give a conditional approval to the updated Progress Schedule at this meeting. 13-HC

8 c. The Construction Manager will then make any agreed changes to the Progress Schedule and reissue a formal updated Progress Schedule within five (5) working days of the meeting. d. Each Contractor shall then issue a formal acceptance of the updated Progress Schedule on a form approved by the Construction Manager. e. Unless a specific exception is made by the Construction Manager, all project payments will be withheld until the Progress Schedule update is accepted by all Contractors. 2. If the updated Progress Schedule adversely affects any critical path dates, the Construction Manager shall issue a notice for the need for a Recovery Schedule. All Contractors will then follow the procedures outlined in the paragraphs describing the Recovery Schedule. D. The Construction Manager will issue a sign-off form to all Contractors indicating their acceptance with the updated Progress Schedule. Each Contractor shall be required to sign and return this form to the Construction Manager. Unless specifically excepted by the Construction Manager, all project payments will be not be approved for processing until the updated Progress Schedule is accepted by all Contractors WEEKLY LOOK AHEAD SCHEDULE A. A Weekly Look Ahead Schedule will be prepared by the Construction Manager. It will be reviewed at the Weekly Progress Meetings as specified in Section and will be used as a tool to monitor schedule compliance on a weekly basis. The look-ahead period will be determined by the Construction Manager to best fit the job conditions. B. The Weekly Look Ahead Schedule will be prepared using an estimated percent complete for activities occurring during the period under consideration. The percentage values will be determined by the Construction Manager. The Progress Schedule database will be used to prepare this schedule. C. If a Weekly Look Ahead Schedule indicates progress slippage, the Construction Manager may use the information to require the preparation of a Recovery Schedule RECOVERY SCHEDULE A. If the Progress Schedule update results in a slippage of critical dates or should any conditions exist or occur such that activities fall behind schedule to the extent that any of the critical path dates or completion dates are in jeopardy, the offending Contractor (herein referred to as Offender) shall be required at no extra cost to the Owner, prepare and submit to the Construction Manager, a Recovery Schedule. This Recovery Schedule shall be in a form and detail appropriate to the need, to explain and display how the Offender intends to reschedule those activities to regain compliance with the Progress Schedule during the immediate pay periods. All Contractors shall be notified by the Construction Manager of such conditions in writing with the Offender identified. B. Within three (3) working days, the Offender shall submit to the Construction Manager his proposed Recovery Schedule. The Recovery Schedule shall represent the Offender s best judgment as to how he shall reorganize his Work so that he may regain the time lost and the critical path is no longer in jeopardy. The Recovery Schedule shall be prepared to a level equal to the Progress Schedule and shall provide for recovery within one month which be called the Recovery Period. The Construction Manager will assist in the preparation of the Recovery Schedule if requested by the Offender. If the initial submittal of the Recovery HC1-033

9 Schedule is not accepted by the Construction Manager, the Offender shall make necessary revisions and resubmit the Recovery Schedule within one (1) day of notification of rejection. C. One working day after the Construction Manager accepts the basic concept of the Recovery Schedule, he will issue it to all other Contractors for their review. D. Within two (2) working days after the Construction Manager issues the Recovery Schedule, all Contractors shall participate in a Recovery Schedule Conference with the Architect and Construction Manager to review, evaluate and approve the Recovery Schedule. Any revisions necessary as a result of this Conference shall be addressed and their impact identified. If the revisions are of such a magnitude that changes cannot be evaluated immediately, the Offender, within two (2) working days, will make the necessary changes and the Conference will be reconvened. Any cost impact a Contractor believes he will have as a result of the Recovery Schedule must be addressed at this Conference or the Contractor forfeits all rights to a claim for extra compensation. All Contractors must approve the Recovery Schedule at the conclusion of the Recovery Schedule Conference. E. Within two (2) working days after the Recovery Schedule meeting, the Construction Manager shall issue an updated Progress Schedule. This updated Progress Schedule shall incorporate all of the changes that result from the Recovery Schedule including any modifications generated at the Recovery Schedule meeting. This updated Progress Schedule shall be assumed to have been accepted by all Contractors because of their participation and actions at the Recovery Schedule Conference. F. Five (5) working days prior to the end of the Recovery Period, the Offender and Construction Manager shall meet at the job site to determine the effectiveness of the Recovery Schedule and to determine whether the Offender is in compliance with the latest update of the Progress Schedule. At the direction of the Construction Manager, one of the following will happen: 1. If, in the opinion of the Construction Manager, the Offender is still behind schedule, the Offender will prepare another Recovery Schedule, at the Offender s expense, to take effect during the immediate subsequent pay period. The Offender, and/or his suppliers/subcontractors, shall furnish such manpower, materials, facilities and equipment and shall work such hours, including night shifts, overtime, Sundays and holidays, as may be necessary to complete the work so that the date of Milestone and/or Completion Dates are met. The Offender shall be responsible for all costs incurred by him and/or other Contractors for support and/or acceleration. 2. If, in the opinion of the Construction Manager, the Offender is still behind schedule and an emergency exists, the Construction Manager may direct the Contractor to take any and all actions necessary to correct the unacceptable progress. The Offender shall be responsible for all costs incurred by him and/or other Contractors for support and/or acceleration. 3. If, in the opinion of the Construction Manager, the Offender is in compliance with the Progress Schedule, the Recovery Period shall be deemed complete SUBMITTAL SCHEDULE A. A Submittal Schedule will be a three part report and will be formatted from the Progress Schedule database by the Construction Manager that will isolate in tabular form all of the material or equipment submittals required for the Project. The three parts are Submittal Preparation Log, Submittal Review/Approval Log and Material Fabrication/Delivery Log. B. All three parts of the Submittal Schedule shall be sorted by Responsibility, Specification Section and Early Start in that order. 13-HC

10 C. The Submittal Preparation Log will isolate all of the submittal preparation activities and is generally for the use of the Contractors in easily identifying their requirements. The headings for the columns of this part will be Submittal Number, Specification Section, Description, Start Preparation Date and Submit for Review Date. D. The Submittal Review/Approval Log isolates all of the Architect s Approval activities and is intended to document review periods for all of the submittals. The headings for the columns of this part will be Submittal Number, Specification Section, Description, Start Review Date and Complete Review Date. E. The Material Fabrication/Delivery Log isolates all of the material fabrication activities and is intended to provide a quick reference for the material fabrication status. The headings for the columns of this part will be Submittal Number, Specification Section, Description, Start Fabrication Date, Fabrication Duration, Received from Manufacturer and Possible Float. The Start Fabrication Dates are important to allow confirmation from a manufacturer that fabrication has started when required. F. The Submittal Schedule will be issued by the Construction Manager with each issue of the Progress Schedule SCHEDULE PROGRESS REPORTS A. Each Contractor shall submit with each Payment Request a narrative report with the up dated progress analysis at the last weekly progress meeting of each month. B. The Schedule Progress Report shall be in the following format and shall include: 1. A listing of activities started during the period with the date of start. 2. A listing of activities completed during the period with the date of completion. 3. A listing of activities in progress during the period with duration's to completion. 4. A narrative indicating any deviations that would affect any Milestone and/or Completion Dates. 5. A narrative with an updated progress analysis which shall include, but not necessarily be limited to: a. A description of problem areas b. Current and anticipated delaying factors and their impact c. An explanation of any corrective action taken during the period. d. Any newly planned activities. 6. A narrative outlining any Recovery Schedules necessitated by the submitting Contractor with an analysis of the progress of the recovery. 7. A narrative describing the actual work accomplished during the pay period. 8. A list of major construction equipment used or idle on the during the pay period. 9. A total number of employees by craft actually engaged on the work during the pay period, with separate subtotals as to office, supervisory and trade personnel. 10. A manpower and equipment forecast for the succeeding pay period, stating the total number of employees with separate subtotals as to office, supervisory and trade personnel. 11. A list of Contractor supplied permanent plant materials and equipment indicating current availability and anticipated job site delivery date. 12. Changes or additions to the Contractor s supervisory personnel since the last Schedule Progress Report HC1-033

11 C. The Construction Manager will not be obligated to review or to start to process any application for Progress Payment until the Contractor has submitted this Schedule Progress Report CRITICAL ITEMS REPORT A. Upon request from the Construction Manager, a Contractor shall submit a Critical Items Report. Such report will not be required more than once in a five (5) working day period. B. The Critical Items Report shall identify items by cause and impact that are, or will seriously affect the Contractor s progress or ability to perform Work in accordance with the current Progress Schedule. The report shall be in sufficient detail to define the cause and potential impact of any actual or anticipated changes in material or equipment deliveries (Contractor or Owner-furnished), manpower availability, weather conditions or other items critical to maintaining the Progress Schedule DEFAULT A. Failure of a Contractor to substantially comply with the requirements of this Section shall constitute reason that the Contractor is failing to prosecute the Work with such diligence as will insure its completion within the Contract times and shall be considered grounds for termination by the Owner. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION 3.1 SCHEDULE INPUT FORM A. The following is a sample of a Schedule Input Form that shall be issued by the Construction Manager. DETAILED LISTING OF MASTER SCHEDULE ACTIVITIES Contractor: Name: Trade ID: Date: Project: Activity Number Activity Description Duration Responsibility. Labor Cost Material Equip. Cost Successors Relation Type/Lag 13-HC

12 B. The Contractor shall promptly return the completed form. The data entered shall conform to Primavera Project Planner requirements and shall be as follows: 1. The Activity Number shall be ten characters long. The first character shall represent a project breakdown as defined by the Construction Manager. The second character shall represent a project area as defined by the Construction Manager. The next five characters shall represent the Specification Section that most represents the activity being defined. The last three characters shall be a sequence number. 2. The Activity Description shall be a maximum of thirty characters long. Descriptions should be consistent in format and concise. 3. The Duration shall given in working days. 4. The Responsibility shall be three characters long and will be defined by the Construction Manager. 5. The Labor Cost shall represent the labor cost required for this activity and should relate to the Contract Cost Breakdown as described in Section The Material/Equipment Cost shall represent the material and or equipment cost required for this activity and should relate to the Contract Cost Breakdown. 7. The Successor(s) shall be all Activities that are constrained by the Activity being defined. 8. The Relationship Type / Lag shall define the constraint type (FS, FF, SF, or SS) and the lag, if any, associated with that constraint. END OF SECTION HC1-033

EXHIBIT 2-2-C SCHEDULES

EXHIBIT 2-2-C SCHEDULES EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS]

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS] SECTION 01 32 00.1 CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS] Note: This section is intended to include general procedural requirements for the preparation, submittal and updating

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS SECTION 01 32 00.3 CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS Note: This section is intended to include general procedural requirements for the preparation, submittal and updating

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 GENERAL 1.01 SECTION INCLUDES A. Preliminary schedule. SECTION 01 32 00 SECTION 01 32 00 B. Construction progress schedule, with network analysis diagrams and reports. C. Daily construction reports.

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 June 28, 2017 ADDENDUM NUMBER: TWO (2) TITLE: Riverview Water Main Extension Phase

More information

East Central College

East Central College SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Exposition Metro Line Construction Authority CRITICAL PATH METHOD SCHEDULE AND COST/SCHEDULE INTEGRATION SYSTEM

Exposition Metro Line Construction Authority CRITICAL PATH METHOD SCHEDULE AND COST/SCHEDULE INTEGRATION SYSTEM SECTION 01310 CRITICAL PATH METHOD SCHEDULE AND COST/SCHEDULE INTEGRATION SYSTEM 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining a Critical Path Method

More information

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects under $1,000,000 use other section if more than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR:

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR: MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE CFS:BD 1 of 14 APPR:MB:JJG 09-29-18 FHWA:APPR:10-01-18 a. Description. Prepare and submit a critical path method

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

CONSTRUCTION STANDARD DOCUMENT

CONSTRUCTION STANDARD DOCUMENT CONSTRUCTION STANDARD DOCUMENT OVERALL CONSTRUCTION SCHEDULE REQUIREMENTS The Overall Schedule shall be prepared by the Contractor based on information from all subcontractors engaged on this project.

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

SECTION NETWORK ANALYSIS SCHEDULES (NCA) PART 1- GENERAL 1.1 DESCRIPTION: SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULES (NCA) SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Coordinate this section with the paragraphs of FAR

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

EL RANCHO UNIFIED SCHOOL DISTRICT

EL RANCHO UNIFIED SCHOOL DISTRICT November 2, 2016 To: Re: All Prospective Vendors Innovation Labs Phase 1 Schools RFB #647 BID ADDENDUM NO. 3 Request for Bid #647 for Innovation Labs Phase 1 Schools is herein amended to include the following

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: PROCEDURE NO.: 015 DATE: 08I'4I09 TITLE: CONSTRUCTION

More information

GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT

GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT JUNE 13, 2018 PROJECT MANUAL SAVANNAH-CHATHAM COUNTY PUBLIC SCHOOL SYSTEM DULOHERY WEEKS GADSDEN ELEMENTARY SCHOOL PHOTOVOLTAIC SYSTEM PROJECT TABLE

More information

THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR CLARIFICATIONS:

THIS ADDENDUM IS FOR THE PURPOSE OF MAKING THE FOLLOWING CHANGES OR CLARIFICATIONS: ADDENDUM NUMBER: TWO (2) Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 July 6, 2017 TITLE: Water/Wastewater General Construction

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year Two Thousand and BETWEEN the Architect s client identified as the Owner: Capitol

More information

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202 Procurement Department Bid Office Customer Center 1 st Floor, Room 002 21 W. Church Street Jacksonville, Florida 32202 ADDENDUM NUMBER: ONE (1) December 15, 2017 TITLE: Construction Services for St. Johns

More information

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109 RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS

More information

EXHIBIT 6 Preconstruction Work

EXHIBIT 6 Preconstruction Work EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01 40 00 PART 1 - GENERAL 1.1 SUMMARY A. This section covers the establishment and operation of the Contractor s Quality Control (CQC) system as specified by the General Conditions of the Contract.

More information

INVITATION FOR BID (IFB):

INVITATION FOR BID (IFB): DATE: May 8, 2018 ADDENDUM NO. 1 INVITATION FOR BID (IFB): B180022132 RPD Furnish & Install Ballistic Glass Lobby Counters IFB #B180022132 WAS ISSUED: Wednesday April 25, 2018 RECEIPT DATE: May 23, 2018

More information

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101 Request for Qualifications Construction Manager at Risk (CMAR) INSTRUCTIONS

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

GENERAL REQUIREMENTS

GENERAL REQUIREMENTS CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction

More information

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers DIVISION 01 GENERAL REQUIREMENTS 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013150 Requests for Information 013200 Construction Progress

More information

Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it

Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it Header1 Project control can be reduced to two basic components: Monitoring and control Construction

More information

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove Improved Project Control Through Scheduling January 24, 2014 The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit

More information

SECTION SUPPLEMENTARY GENERAL CONDITIONS

SECTION SUPPLEMENTARY GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY GENERAL CONDITIONS PART 1 - GENERAL 1.1 SCOPE OF WORK In general, the Work consists of application of a fluid applied membrane, installation of new tapered insulation, installation

More information

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1. Massport Capital Programs Enterprise Schedule Management Document 11 A Primavera Schedule Toolkit Vertical Projects July 2017 Version 1.5 Contents 1.0 INTRODUCTION 2 1.1 DISCLAIMER 2 2.0 TOOLKIT SCHEDULE

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL 1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit. Contract Time Determination (CTD) January 2018 Version 1.

Massport Capital Programs Enterprise Schedule Management. Primavera Schedule Toolkit. Contract Time Determination (CTD) January 2018 Version 1. Massport Capital Programs Enterprise Schedule Management Primavera Schedule Toolkit Contract Time Determination (CTD) January 2018 Version 1.0 CONTENT 1 CTD GUIDELINE SUMMARY... 3 1.1 INTRODUCTION... 3

More information

ADMINISTRATIVE DIRECTIVE #CS-04

ADMINISTRATIVE DIRECTIVE #CS-04 HILLSBOROUGH COUNTY Office of the County Administrator ADMINISTRATIVE DIRECTIVE #CS-04 SUBJECT: EFFECTIVE DATE: UTILITY COORDINATION PROCEDURES FOR HILLSBOROUGH COUNTY CONSTRUCTION PROJECTS WITHIN COUNTY

More information

CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION

CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION PHASE 1: PRE-CONSTRUCTION Schematics Phase Based upon program requirements and design parameters, D&J will establish conceptual budget and preliminary schedule for the project, which will highlight specific

More information

Jacksonville District Master

Jacksonville District Master USACE / NAVFAC / AFCEC / NASA UFGS-01 32 01 (August 2008) Change 1-08/13 --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE

More information

Downloaded from

Downloaded from USACE / NAVFAC / AFCESA UFGS-01321N (February 2002) ------------------------------- Preparing Activity: NAVFAC Superseding UFGS 01321N (September 2000) UNIFIED FACILITIES GUIDE SPECIFICATIONS Revised throughout

More information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction

More information

Appendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services

Appendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services Appendix D University of Maine System Supplementary Requirements to AIA Document B201-2007 Standard Form of Architect s Services This document provides the Architect s scope of services only and must be

More information

G , Request for Proposal Land Survey

G , Request for Proposal Land Survey G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994

More information

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES

More information

CONSTRUCTION PROCEDURES MANUAL PROJECT

CONSTRUCTION PROCEDURES MANUAL PROJECT CONSTRUCTION PROCEDURES MANUAL ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS (DATE) Page 1 ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS TABLE OF CONTENTS CONTENTS PAGE: 1.0

More information

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts) Volume (5) Number (8) August 2015 J. Appl. Environ. Biol. Sci., 5(8)55-69, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Commencement

More information

Specifications and Drawings

Specifications and Drawings Specifications and Drawings for Lowertown Community Centre 40 Cobourg Street Ottawa, ON K1N 8Z6 prepared for City of Ottawa prepared by Architect. Second Floor, 43 Eccles Street Ottawa, Ontario K1R 6S3

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Step 1 Preliminary Design and Engineering

Step 1 Preliminary Design and Engineering The Austin Company offers a variety of approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.

The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built. L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally

More information

San Antonio Water System Standard Specifications for Construction

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 Construction Qc/Qa Program Formatted: Font: 11.5 pt Formatted: Font: 11.5 pt 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality

More information

A62 UT PRE-CONSTRUCTION MEETING AGENDA

A62 UT PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

UFGS Project Schedule Requirements [Section ] WED by David Long

UFGS Project Schedule Requirements [Section ] WED by David Long [Section 01 32 01.00 10] WED 200 315 by David Long [Section 01 32 01.00 10] Disclaimer The information contained in this presentation and discussion is not a formal or official Government interpretation

More information

REPLACE SUBSTATION SWITCHGEAR SECTION ADMINISTRATIVE REQUIREMENTS 02/10

REPLACE SUBSTATION SWITCHGEAR SECTION ADMINISTRATIVE REQUIREMENTS 02/10 REPLACE SUBSTATION GEAR SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS 02/10 PART 1 GENERAL 1.1 SUBMITTALS Government approval is required for submittals with a "G" designation; submittals not having a "G"

More information

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual.

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no. 1801.01 07 12 2018 Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

SECTION SUBSTITUTION PROCEDURES

SECTION SUBSTITUTION PROCEDURES SECTION 01 25 00 SECTION 01 25 00 PART ONE: GENERAL 1.1 Related Documents 1.1.2 Construction Documents and general provisions of the Agreement Between Owner and Construction Manager and consultant and

More information

Professional Practice 544

Professional Practice 544 February 22, 2016 February 29, 2016 Professional Practice 544 AIA-B101 Owner - Architect Agreement Michael J. Hanahan Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information

Multi-Institutional Academic Health Science & Research Center Evansville, IN

Multi-Institutional Academic Health Science & Research Center Evansville, IN SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

ATTACHMENT W.2 GENERAL SPECIFICATIONS

ATTACHMENT W.2 GENERAL SPECIFICATIONS ATTACHMENT W.2 GENERAL SPECIFICATIONS IFB No. 016-002 Virginia Railway Express Page 1 of 39 General Specifications Table of Contents SECTION TITLE PAGE Title Page 1 00 01 10 Table of Contents 2 Division

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

CONSTRUCTION MANAGEMENT AGREEMENT

CONSTRUCTION MANAGEMENT AGREEMENT CONSTRUCTION MANAGEMENT AGREEMENT This Construction Management Agreement ( Agreement ) is made and entered into effective November 1, 2012, by and between the Newark Unified School District ( District

More information

A62 PRE-CONSTRUCTION MEETING AGENDA

A62 PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

Chapter 6, Construction

Chapter 6, Construction Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference

More information

CHARLES COUNTY, MARYLAND CLIFFTON PUMP STATION NO. 4 IMPROVEMENTS PROJECT NO. UN 1219 TABLE OF CONTENTS. Table of Contents

CHARLES COUNTY, MARYLAND CLIFFTON PUMP STATION NO. 4 IMPROVEMENTS PROJECT NO. UN 1219 TABLE OF CONTENTS. Table of Contents CHARLES COUNTY, MARYLAND CLIFFTON PUMP STATION NO. 4 IMPROVEMENTS PROJECT NO. UN 1219 TABLE OF CONTENTS Table of Contents TC-1 DIVISION 1 GENERAL REQUIREMENTS Section 01106 - Construction, Coordination

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes administrative and procedural requirements for quality assurance and quality control. B. Testing and inspecting services

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

Dealing with Substitutions to Your Design

Dealing with Substitutions to Your Design December 31, 2016 Dealing with Substitutions to Your Design Recent research into claims arising against architects has confirmed that many involve substitutions to the systems and designs provided by the

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

100% FINAL DESIGN DRAFT SPECIFICATIONS MAY 17, 2018

100% FINAL DESIGN DRAFT SPECIFICATIONS MAY 17, 2018 100% FINAL DESIGN DRAFT SPECIFICATIONS MAY 17, 2018 TABLE OF CONTENTS DIVISION 1 - GENERAL REQUIREMENTS 10000 GENERAL CONDITIONS (Provided by Owner) 01110 SUMMARY OF WORK 01150 APPLICABLE STANDARDS 01305

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

SECTION 50 CONTROL OF WORK

SECTION 50 CONTROL OF WORK SECTION 50 CONTROL OF WORK 50-01 AUTHORITY OF THE ENGINEER. The Engineer shall decide any and all questions which may arise as to the quality and acceptability of materials furnished, work performed, and

More information

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents VAE VIEW ELEMENTARY WINDOW REPLACEMENT 1750 West 1600 North Layton, UT 84041 Specifications 19 March 2018 TABLE OF CONTENTS DIVISION 00 PREREQUIREMENT AND CONTRACTING REQUIREMENTS A101 A201 A310 A312 G701

More information

CONTRACT FOR PROFESSIONAL SERVICES CHAPTER TWO PROFESSIONAL S REQUIRED SERVICES

CONTRACT FOR PROFESSIONAL SERVICES CHAPTER TWO PROFESSIONAL S REQUIRED SERVICES Contract For Professional Services Chapter Two Professional s Required Services Rev. 05/16/12 Client Contract Number TABLE OF CONTENTS ARTICLE 1 GENERAL PROJECT SERVICES... 4 1.1 Essential Services...

More information

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67

PROJECT MANUAL for Phantom Canyon Tunnel Repair Project. Location On Fremont County Road miles North of Intersection US Highway 50 with FCR 67 August 28, 2018 PROJECT MANUAL for Phantom Canyon Tunnel Repair Project Location On Fremont County Road 67 7.5 miles North of Intersection US Highway 50 with FCR 67 Fremont County, Colorado OWNER: Fremont

More information

PENNSYLVANIA TURNPIKE COMMISSION Harrisburg, PA

PENNSYLVANIA TURNPIKE COMMISSION Harrisburg, PA PENNSYLVANIA TURNPIKE COMMISSION Harrisburg, PA CONTRACT NO. T-020.47S002-3-02 FOR SUPERSTRUCTURE REPLACEMENT OF BRIDGE NO. WB-224B AT MILEPOST 20.47 IN BEAVER COUNTY, PENNSYLVANIA SPECIAL PROVISIONS INDEX

More information

Estimating and Scheduling

Estimating and Scheduling Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques

More information

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information