Underground System Design TADP 547

Size: px
Start display at page:

Download "Underground System Design TADP 547"

Transcription

1 Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas

2 Transmission Design and Installation When planning an underground power cables system the challenge is to design a system that can withstand both the electrical and physical parameters. To avoid installation problems and achieve a reliable long-term cable system, installation conditions and methods must be an integral part of the design phase. This session will cover important design requirements and options that should be considered when installing an underground transmission circuit.

3 Cable Installation Considerations Cable Selection Route Selection Construction methods Maintenance requirements

4 Cable Selection Typically based on voltage level, route, and length of circuit. Most common installations in North America have been HPFF pipe type. More recently, XLPE cables are now becoming the more popular choice. HPFF cables have been installed since early 1930 s and have a very reliable track record. XLPE cable installations do not have the long track record that fluid filled cables have. However, they have proved reliable over the short term.

5 Cable Selection (cont.) Each utility has different systems so most choose a cable they are comfortable with and only introduce new types slowly in short lengths to gain experience. Current LPFF cable use is limited and tends to be confined to extra high voltage (EHV) circuits and underwater (submarine) installations. For short lengths, XLPE cables are generally preferred since no hydraulic equipment is required - compared to fluid filled systems.

6 Route Selection When selecting a route you must look at the following: Environmental concerns Land permits Soil conditions Existing utilities Construction requirements

7 Environmental Concerns/Permits When choosing a route, the entire area needs to be surveyed to avoid (if possible) wetlands, waterways, archeological sites, and sensitive areas such as schools, playgrounds, and parks. These areas require special permits and the permitting process may take several years before being granted - which can impact cost and schedule. Most underground utilities are installed in public roadways and permits may be an issue if the street was recently paved, traffic flow to businesses or residence in the area is obstructed, and noise restrictions exist.

8 Soil Conditions Depending on type of soil being excavated, soil conditions can effect installation cost and schedule. Amount of pavement or rock to be removed or, if in soft soil, extensive shoring required. Soil resistivity can effect cable rating so a geotechnical study should be performed and soil conditions corrected with thermal backfill, when necessary. Whenever possible, engineers/designers should avoid difficult routes or excavating areas.

9 Existing Utilities Locating other underground utilities can help with route design by selecting depth required to avoid conflict, or by selecting different route if street is too congested. External heat sources (such as distribution circuits or steam pipes found in urban areas) should be avoided or a 10 minimum clearance maintained to prevent possible thermal de-rating of the installed line. Although thermal barriers or mitigation is possible, it is generally a very costly alternative.

10 Construction Requirements Manhole installations: Manholes are installed at locations where cables need to be spliced. Manhole spacing determined by maximum cable length on a reel, along with weight and size of reels that can be transported to job site. Maximum pulling tension and sidewall pressure allowed.

11 Manhole Installations Manholes are either precast or casted-in-place and precast are more economical. However, precast manholes require heavy equipment to transport and install and contractors must ensure adequate clearance exists to move equipment into position to unload and install manholes. In urban congested areas, cast-in-place might be only viable option. For pipe-type systems, manholes from feet long can be spaced between 2,500 to 3,500 feet apart.

12 Manhole Installations (cont.) Manholes for LPFF are ft. long and spaced about 800 to 1,600 feet apart. For XLPE cable systems, manholes typically longer to allow for joint construction approximately ft. and spaced 2,000 to 3,000 feet apart. Manholes usually installed first so that they can be moved if other utilities are in the way. As moving manholes may change cable cut lengths, engineers and designers typically add 5% to cable lengths to account for such changes.

13 Precast Manhole Installation

14 Cast-in-Place Manhole Installation

15 Conduit Installation Engineers/designers should ensure contractor s realize transmission cable conduit installation is critical and that strict quality control is required during installation. Transmission cables are typically large, heavy, and require a large radii. Duct systems also need to be robust to withstand high installation loads required for longer pulls. Very important that duct alignment, especially at joints, is kept straight to avoid cable damage (which can lead to failures) during installation.

16 Conduit Installation (cont.) Spacing and size determined by ampacity and cable design requirements - spare conduits usually installed. Duct banks typically have minimum 30 cover and are encased with high strength 3,000-3,500 psi thermal backfill for mechanical protection. Ducts typically made of PVC are Schedule 40 thickness. (When encased in concrete, thinner ducts tend to become oval to a point where cable cannot be pulled through.) Other types of ducts used are polyethylene (PE) and fiberglass conduits - in 10 and 20 ft. sections.

17 Conduit Installation (cont.)

18 Pipe-Type Installation When installing pipe for pipe-type cables, trench excavation is similar to installing a duct system. However, the actual installation practice is different. Before pipe is installed, engineer/designer must provide a weld procedure and ensure welders are qualified by performing test welds and having qualified testing agency approve them - welds must meet American Petroleum Institute (API) Standard Pipe installations typically require an open trench of at least 200 feet to allow for adjusting alignment of pipe, if needed.

19 Pipe-Type Installation (cont.) Pipe is either welded in trench or on top and lower into trench or, in some cases, pulled with a winch line so pipe can be fed underneath existing utilities. Pipe sections typically 20 and 40 ft. long with flared ends to provide smooth transition between pipes when welded. Joint inside surface must be smooth to avoid damage to cable during pulling. To prevent weld beads from entering pipe during welding, a backer or chill ring is used. A portable bending machine can be used to bend pipes to the desire radius in the field

20 Pipe-Type Installation (cont.) Typical bending radius for 8 pipe is 50 ft. and for vertical grade changes it should be limited to 500 ft. A larger radius requires a lower pulling tension. All welds tested using magnetic particle, dye penetrant, ultrasound, or radio graphical (X-rays) test methods. Most common methods used today have been X-Ray and dye penetrant tests. After welds tested and approved a corrosion protected coating is installed over welded area.

21 Pipe-Type Installation (cont.) Current corrosion coatings are polymeric heat shrink sleeves to cover weld area. Pipe coating are tested for damage and imperfections that may occur during production or installation prior to backfilling the trench. After backfilling, a manhole-to-manhole coating resistance test is performed to make sure no damage occurred during the backfill process. The pipe must be kept dry during installation so 5 psi dry nitrogen pressure is applied to each completed section.

22 Typical Pipe Trench

23 Pipe-Type Installation (cont.) When pipe termination point is reached a trifurcating joint is used to go from single pipe to three individual pipes (typically made of stainless steel or other nonferrous/non-magnetic metal) for termination ends. After pipe installed and tested, inside is cleaned with swabs, mandrelled, and pressure and vacuum tested. Mandrel checks roundness of pipe to assure proper diameter is maintained. AEIC specifies size and shape of mandrels for various pipe sizes. Typically, the mandrel is about ¼ smaller then pipe diameter.

24 Pipe-Type Installation (cont.) Vacuum process performed to dry pipe prior to pulling cable. Each pipe section vacuumed until desired reading obtained - typically 150 microns with 100 micron rise in one hour. If unable to achieve desired reading, continued vacuum process for another 4 to 8 hours and repeat test. Once required vacuum reading achieved apply 10 psi dry nitrogen pressure and maintained until cable pulling operation begins.

25 Cable Pulling - HPFF When pipe is ready the cable pulling process can begin. Weather a key factor for pulling HPFF cable since pipetype cables have no protective sheath. If rain or snow forecast, the pulling operation must be rescheduled. Cable and pipe must be kept dry at all times. In a pipe-type installation, all three cables are pulled in at the same time. You must, therefore, verify there is sufficient space to set up reel trailer(s) and/or reels. All pulling tensions must be within cable s design parameters.

26 Cable Pulling HPFF (cont.) Once cable has been pulled into a section both pipe ends (including cable) are sealed to protect against moisture until the splicing process has been completed. Install end (or night) caps at each end to seal cable and pipe section. Evacuate section to keep cable and pipe dry. When desired vacuum achieved (typically 250 microns or less) a positive dry Nitrogen pressure of 5 psi is applied. Always follow safety procedures when bleeding or using Nitrogen in manholes or confined spaces.

27 Cable Pulling Cable Reel Trailer

28 HPFF Splicing Prior to initiating the splicing operation, protective covers or temporary housing is applied to the manholes to prevent moisture/ water from entering manholes. Splicing area must be clean and dry to avoid possible contamination during splicing. Manhole or splicing area must be climate controlled during entire splicing process - maintain F and relative humidity of 35% or below. Once splicing completed and joint casing installed a final system vacuum is performed. Terminations are spliced in a similar process - protective shelter built around termination area to keep it dry/clean.

29 HPFF Splice

30 HPFF Splicing (cont.) Based on line length, multiple vacuum pumps can be used to achieve required vacuum reading (250 microns) sooner. Line ready for filling with dielectric fluid when final vacuum level achieved. Filling from lowest line elevation, with vacuum pump at highest point, is generally preferred. Multiple tanker trucks used to fill line at gallons per minute. When line is filled the pressurizing process begins. Line pressure raised in 25 psi steps every 8-12 hours until a normal operating pressure of 200 psi achieved.

31 HPFF Splicing (cont.) After line reaches normal operating pressure it should be maintained for 24 hours prior to applying any test or operating voltages. For HPFF cables, AEIC Standards specify DC Hi-Pot voltage test level and time duration - typically 3.5 times rated voltage for 15 minutes on each cable phase. In some cases the DC Hi-Pot test is followed by a 24 hour system voltage, no load, electrical soak test. (Some utilities may require a longer soak time.)

32 Solid Dielectric Cable Installation To verify conduit integrity a mandrel is pulled through duct. The cable is ready for pulling after duct has been deemed acceptable. Temperatures must be above 20 F to avoid cable damage. Unlike HPFF cables, solid dielectric cables are pulled one phase at a time. A pulling lubricant is used to reduce friction. Positioning of cable reels and rigging manhole with rollers required to maintain minimum bending radius and allowable pulling tensions. Once cable is installed each end is typically sealed with a heat shrink cap to prevent moisture from entering cable.

33 Solid Dielectric Cable Pulling Cable Reel Trailer

34 Solid Dielectric Cable Pulling (cont.) 345 kv XLPE Cable Installation

35 Solid Dielectric Cable Pulling (cont.) 345 kv XLPE Cable Installation

36 Solid Dielectric Cable Splicing: When splicing solid dielectric cables, splice shelters or manholes must be clean and protected from weather conditions and humidity. To prevent future cable failure, splicing should be performed in a clean, dry, and controlled space to avoid contaminants. Termination splicing is handled in the same manner - a protective shelter is built over the termination structure to keep the area clean and protected from weather conditions.

37 Solid Dielectric Cable Splicing Cable splicing in a manhole

38 Solid Dielectric Termination Splice (cont.)

39 LPFF or SCOF Installations LPFF cable installations are similar to solid dielectric cables. However, the fluid/hydraulic system must be addressed for LPFF cables systems. Reel or portable pressure reservoirs used to maintain fluid pressure on the cable during pulling and splicing. After completion, joints and terminations are evacuated and filled with a degassed dielectric fluid.

40 General To provide for maintenance to the system, it will be important to secure an easement or access for all cable types. Typical underground line easement widths of ft. allow equipment to access the site for conduit/pipe or cable repairs. Clearance between other utilities is also important since there must be enough room between utilities for future maintenance and repairs to the pipe or conduit system.

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES

3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1 Underground transmission lines 69 kv and

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

7/20/2017 MEETING--- POST MEETING MARKUP

7/20/2017 MEETING--- POST MEETING MARKUP 7/20/2017 MEETING--- POST MEETING MARKUP 3.0) TRANSMISSION LINES MINIMUM REQUIRED STANDARDS LINES 3.2 Underground Lines [below sections will be renumbered at a later date] 5.0 GENERAL REQUIREMENTS 5.1

More information

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal.

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal. PART 1: GENERAL 1.01 Scope of Standard A. This standard provides general guidance concerning the specific preferences of Texas State University for for Electrical System. B. Texas State University recognizes

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

This Overview contains information about electric transmission lines which are installed

This Overview contains information about electric transmission lines which are installed Underground Electric Transmission Lines This Overview contains information about electric transmission lines which are installed underground, rather than overhead on poles or towers.1 Underground lines

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

Multi-Gard PVC Assembly/ Field Cuts

Multi-Gard PVC Assembly/ Field Cuts Multi-Gard PVC Assembly/ Field Cuts Assembly 1. Distribute Multi-gard sections along the sides of the trench with male ends pointing towards starting vault entrance.. Remove protective cap and install

More information

For the 6/15/2017 meeting review

For the 6/15/2017 meeting review For the 6/15/2017 meeting review PJM DESIGNATED ENTITY DESIGN STANDARDS UNDERGROUND LINES 1.0 PURPOSE These standards represent the minimum criteria by which a competitively solicited facility must be

More information

New designed XLPE-insulated cables substituting paper-insulated pipe type cables

New designed XLPE-insulated cables substituting paper-insulated pipe type cables MODERN CABLE SYSTEMS IN STEEL PIPES New designed XLPE-insulated cables substituting paper-insulated pipe type cables Volker AUE, Nexans Deutschland Industries, Germany, Volker.Aue@nexans.com Wilfried ROSEBROCK,

More information

345 kv Underground Report

345 kv Underground Report POWER ENGINEERS, INC. February 24, 2010 345 kv Underground Report PROJECT NUMBER: 117910 PROJECT CONTACT: Mike Mueller Richard C. Mues, PE EMAIL: mike.mueller@powereng.com rmues@powereng.com PHONE: 314-851-4050

More information

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL Multicell Vikimatic MultiCell Conduit Systems These guidelines should help you install MultiCell Conduit in the simplest way possible and should be read in their entirety before attempting to install the

More information

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 PART 1 - GENERAL... 2 1.1 Work Included... 2 1.2 Related Sections... 2 1.3 Reference Standards... 2 1.4 Shop Drawings... 3 1.5 Certificates...

More information

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems. Date Description of Change Pages / Sections Modified ID 6/15/16 Entire document - mgl44 PART 1 - INTRODUCTION 1.1 PURPOSE A. This section is intended to provide design guidelines for Utility Direct Buried

More information

SRPE AASHTO Specifications.

SRPE AASHTO Specifications. SRPE AASHTO Specifications July 19, 2013 Steel Ribbed HDPE = SRHDPE = SRPE Now has AASHTO Design and Construction Specifications for SRPE. 2 But wait there is more AASHTO Bridge Design Specs - Section

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

Underground Conduit Systems

Underground Conduit Systems Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications. 16402 ELECTRICAL SITE UTILITIES ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 33 50 00. *************************************************************************************************************

More information

Customer Requirements Conduit Installations, High Voltage

Customer Requirements Conduit Installations, High Voltage Application Requirements for high voltage underground conduit systems, installed by customer or contractor, which will be owned and maintained by Tacoma Power. High voltage underground conduit installations

More information

SECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL

SECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL SECTION 260513 - MEDIUM-VOLTAGE CABLES PART 1 GENERAL 1.1 SECTION INCLUDES A. Medium voltage cable. B. Cable terminations. C. This specification describes single conductor EPR (Ethylene-propylene-rubber)

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

SECTION ELECTRICAL SITE UTILITIES

SECTION ELECTRICAL SITE UTILITIES SECTION 16402 ELECTRICAL SITE UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

More information

GENERAL UTILITIES REQUIREMENTS

GENERAL UTILITIES REQUIREMENTS 33 00 00 GENERAL UTILITIES REQUIREMENTS i. 01 41 26.02 Local Utility Information & Locate ii. 23 05 19 Meters and Gages iii. 33 10 00 Water Utilities Public Water Distribution System iv. 33 12 13.13 Water

More information

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street

Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street 1600 SW Western Blvd, Suite 100 Corvallis, OR 97333 (541) 766-4601(desk) GOrmsby@TriAxisEng.com August 30, 2013 Robert White Power Services Manager Tillamook People s Utility District 1115 Pacific Avenue

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

DUO-THERM 505 Specification Guide

DUO-THERM 505 Specification Guide STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish

More information

SECTION ELECTRICAL UTILITY SERVICES

SECTION ELECTRICAL UTILITY SERVICES SECTION 33 71 73 ELECTRICAL UTILITY SERVICES PART 1 GENERAL 1.1 REFERENCES A. American Association of State Highway Officials (AASHO): 1. Standard Specifications B. California Administrative Code (CAC):

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV Network(s): Summary: ENGINEERING INSTRUCTION EI 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV EPN, LPN, SPN This engineering instruction details the minimum requirements acceptable for the installation

More information

SECTION VI SANITARY SEWERS

SECTION VI SANITARY SEWERS SECTION VI SANITARY SEWERS VI-1. DESIGN GUIDELINES Sewer collection lines and appurtenant structures within the jurisdiction of City of Paso Robles shall be constructed in accordance with plans prepared

More information

Specifications for Electrical Underground Residential Distribution Systems

Specifications for Electrical Underground Residential Distribution Systems Specifications for Electrical Underground Residential Distribution Systems Specification DDS-2 Revision 13, February 2010 ONCOR ELECTRIC DELIVERY COMPANY SPECIFICATIONS FOR ELECTRICAL UNDERGROUND RESIDENTIAL

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION A. This section specifies the furnishing, installation, and connection of precast manholes and pullboxes with ducts

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES B-1 General Notes: SACWSD Standard Construction Drawing Notes 1. No work shall begin on any water or wastewater construction project until the construction

More information

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE

TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GUJARAT ENERGY TRANSMISSION CORPORATION LTD. Sardar Patel Vidyut Bhavan, Race Course, Vadodara: 390 007 TECHNICAL SPECIFICATIONS OF LAYING OF UNDER GROUND POWER CABLE FOR TRANSMISSION LINE GETCO/E/TS LUC058/R1

More information

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details Changes for the 2017 TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details The following changes are made to the existing standards and details to clarify or improve existing information.

More information

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PUBLIC WORKS DEPARTMENT GENERAL NOTES PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

SECTION 503 TEMPORARY PAVEMENT RESTORATION

SECTION 503 TEMPORARY PAVEMENT RESTORATION SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with

More information

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS SECTION 02530 - SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

Specifications for Electrical Underground Distribution Systems from Overhead Transformation, Apartments & Condominiums

Specifications for Electrical Underground Distribution Systems from Overhead Transformation, Apartments & Condominiums Specifications for Electrical Underground Distribution Systems from Overhead Transformation, Apartments & Condominiums Specification DDS-3 OH Revision 10, March 2010 ONCOR ELECTRIC DELIVERY COMPANY SPECIFICATIONS

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

Vikimatic MultiCell Conduit Systems

Vikimatic MultiCell Conduit Systems Conduit Systems These guidelines should help you install MultiCell Conduit in the simplest way possible and should be read in their entirety before attempting to install the system to have as smooth an

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Section 4 Service Lines

Section 4 Service Lines Section 4 Service Lines A. General 1. A service line is that portion of a sanitary sewer line that extends from the outer building wall or foundation wall to its connection with the sewer lateral at the

More information

AEP 69-kV Oil-Insulated Transmission Line Removal Project

AEP 69-kV Oil-Insulated Transmission Line Removal Project AEP 69-kV Oil-Insulated Transmission Line Removal Project Michael Glueck, PE, American Electric Power Michelle Beckman, Burns & McDonnell Bill Halliburton, PG, Burns & McDonnell Woody McOmber, PE, Burns

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Change History Date Description of Change Pages / Sections Modified Change Approver Initials 8/1/17 Update sections Materials and Special Requirements 3 F. 2. 4 H. 2.; 10. & 11(added) 6/15/16 Updated division

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light

More information

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS PART 1 - GENERAL 01.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this Section.

More information

Section 7: Specifications

Section 7: Specifications Section 7: Specifications 29 31 Building Boundary of Clear Area See Note # 1 8' Shrubs 8' Concrete Pad Equipment 8' TRAVELED WAY M Meter Pedestal 8' Curb Protective Vehicle Posts (Bollards) If Required

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation)

SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) PART 1 GENERAL SUGGESTED MANHOLE FRAME SEALING SPECIFICATION (Rehabilitation) 1.01 SCOPE This specification includes the materials and procedures required for the internal sealing of the frame-chimney

More information

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS SECTION 401 PIPE AND FITTINGS PART 2 MATERIALS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS A. PVC Pressure Pipe sizes 4 inch through 12 inch: ANSI/AWWA C 900 1. DR18 B. PVC Pressure Pipe sizes 14 inch

More information

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1993 Specifications CSJ 0144-01-060 SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1. General. (1) Scope. This Section includes the furnishing, installation, and subsequent

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area

More information

PIPE BURSTING SUCCESS

PIPE BURSTING SUCCESS GRUNDOCRACK PNEUMATIC PIPE BURSTING SYSTEM PIPE BURSTING SUCCESS STARTS HERE TT Technologies is the world leader in pipe bursting equipment and experience. For over 20 years contractors have relied upon

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 604 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

CITY OF FARGO SPECIFICATION SANITARY SEWER

CITY OF FARGO SPECIFICATION SANITARY SEWER SECTION 1200 SECTION 1200 CITY OF FARGO SPECIFICATION SANITARY SEWER PART 1 DESCRIPTION OF WORK (revised March, 2007) The work to be done under these Specifications and the accompanying drawings consist

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

UNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06

UNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06 Communications Underground Ducts, Structures and Raceways PART 1: GENERAL The Contractor is held responsible to be familiar with the provisions contained herein and with other Sections of this Specification

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

PILC Replacement: Getting the Lead Out

PILC Replacement: Getting the Lead Out PILC Replacement: Getting the Lead Out Spring Cincinnati, OH April 30, 2003 Page 1 PILC IS GREAT! Low Profile High Fault Current Capability on Shield High Degree of Water Blocking So why shouldn t you

More information

SECTION GRAVITY WASTEWATER LINES

SECTION GRAVITY WASTEWATER LINES SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS

More information

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated

More information

TECHNICAL PROCEDURE TABLE OF CONTENTS

TECHNICAL PROCEDURE TABLE OF CONTENTS TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 SPEC WRITER NOTE: 1. Use this section only for NCA projects. Delete // // if not applicable to project. Also, delete any other item or paragraph not applicable

More information

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565)

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) PLASTIC CONDUIT AND FITTINGS PLACING INSTRUCTION NOTE: This "Guide" summarizes the opinions, recommendations, and practices of the Western Underground

More information

D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d

D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d D e s i g n a n d c o n f i g u r a t i o n s t a n d a r d 132 kv 400 kv Installation of underground AC cables in urban areas EDS-0074 Document title EDS-0074 Rev 0 Installation of underground AC cables

More information

ONE PIPE LENGTH MAX (REFER TO 1/4"/FT SLOPE (MIN) 5'-0" (MIN) OR 4" LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4"x6" REFER TO TYPICAL EXCAVATION,

ONE PIPE LENGTH MAX (REFER TO 1/4/FT SLOPE (MIN) 5'-0 (MIN) OR 4 LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4x6 REFER TO TYPICAL EXCAVATION, VENT CAP (MUSHROOM TYPE) SOLID CAP EXIST GRADE MIN BUILDING REFER TO NOTE #4 MIN CONCRETE SIDEWALK CURB OR EDGE OF SIDEWALK STREET CLEANOUT (REFER TO NOTE #3) VENT PIPE 4" PVC 6" PVC CLEANOUT CONCRETE

More information

Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING. We Build Tough Products for Tough Environments

Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING. We Build Tough Products for Tough Environments Installation Guide BLUE904 PEX MUNICIPAL WATER SERVICE TUBING W A T E R S E R V I C E T U B I N G We Build Tough Products for Tough Environments Blue904 Installation Guide 1 TABLE OF CONTENTS Introduction...................................2

More information

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL

REVISION OF SECTION 623 IRRIGATION SYSTEM GENERAL 623.01 SUMMARY: GENERAL Section Includes: Landscape irrigation system as shown on the drawings for complete coverage to landscape areas. Furnish design for layout, pipe sizing, valving and head types and

More information

INDUSTRIAL PIPE FITTINGS, LLC

INDUSTRIAL PIPE FITTINGS, LLC Page 1 of 9 SPIROLITE MUNICIPAL AND INDUSTRIAL ODOR CONTROL PIPING Municipal wastewater treatment plants, industrial processes and composting facilities can be assured of trouble free transport of foul

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information