Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street

Size: px
Start display at page:

Download "Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street"

Transcription

1 1600 SW Western Blvd, Suite 100 Corvallis, OR (541) (desk) August 30, 2013 Robert White Power Services Manager Tillamook People s Utility District 1115 Pacific Avenue Tillamook, Oregon BWhite@TPUD.org Mr. White, Subject: Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street Per our authorization and further discussion this report provides a brief independent feasibility assessment of a proposed 115-kV underground transmission concept along Front Street in Tillamook. The objective of this feasibility assessment is to describe and estimate the impacts of the most probable underground facility concept that may be permitted by various agencies, accepted by the PUD, and properly designed for construction on the planned alignment. Thanks again for asking us to help you with this effort. Please call if you have any questions. Sincerely, TriAxis Engineering, Inc. Gordon Ormsby, P.E. Project Engineer Tillamook 115kV UG Feasibility Assessment Cover Letter Cover Letter

2 The City of Tillamook requested Tillamook PUD to investigate placing a 0.5-mile-long segment of the proposed Oceanside overhead transmission line underground along Front Street in Tillamook. The underground portion would parallel the south side of Hoquarten Slough, cross under Oregon Highway 101 and would need to accommodate the future planned ODOT rearrangement of Highway 101 at the Hoquarten Bridge. In response to the City s request, TriAxis Engineering, Inc. completed the attached Feasibility Assessment for 115-kV Underground Transmission Line Segment on Front Street, dated August 30, Executive Summary Reliaibility A four-cable underground system would be required as the proposed Oceanside 115-kV Transmission Line would be the only 115-kV circuit serving the Netarts-Oceanside Area. Three of the cables would be normally energized. The fourth emergency cable would be terminated on a riser pole. If the underground segment along Front Street were constructed with only three cables, a failure of any component of the underground segment would cause an area-wide outage. Failure of an underground cable, splice, or riser component would require a minimum of several weeks or months to repair, compared to the repair time of overhead line, primarily due to the fact that high-voltage underground systems and individual components are specialized devices and require specialized technicians. Spare components would be warehoused at the PUD, but specialists to perform the work would need to be brought in to the area to make the repairs. Field installations would require building a climate-controlled room around termination sites or inside the splice vaults. Because repairs typically require weeks, transmission systems must mitigate the risk of a failure. The District plans to improve its existing 25-kV distribution line to the Oceanside area to serve as an emergency power supply in the case of a transmission outage. This planned emergency distribution tie line would be designed to serve the area for a few hours or days at a time, but would not be practical to design with enough efficiency and reliability for long-term (weeks or months) transmission line outages. 115-kV Cables Underground cables will be designed to match the thermal capacity of the overhead conductors of the transmission line. The size of the underground cable is calculated to keep the cable temperature under the manufacturer s maximum specified operating temperature. Depending on the required size of the copper conductor, the finished diameter is expected to be approximately 3.5 inches in diameter and weigh about 9.5 pounds per foot. Duct Bank A typical transmission line duct bank design has four large conduits placed in a square arrangement. Each of the transmission line cables must be placed in its own conduit to facilitate the pulling-in or replacement of the cables and to provide for heat dissipation. Two smaller conduits would also be

3 installed above the transmission conduits. The entire duct bank is anchored to the floor of the trench with an initial placement of 3-4 of concrete, which is allowed to set. Then the entire duct bank assembly is encased with a high-strength, thermally-conductive concrete mix. Concrete encasement under city streets and highways include steel reinforcing bars on the corners of the duct bank to improve the strength of the encasement and control cracking. Construction of duct banks under roads is complex and the trench width must be increased. For protection against dig-ins, the top of the transmission line conduit is typically placed from grade; the trench will be about 6 feet deep. Under pavement, the roadway occupancy permit may allow the duct bank to be placed in a shallow trench. Shallow placement under roadways may be allowed due to the intrinsic protection against dig-ins. If a narrow trench is required, the top of the encasement could be just under the pavement material and the trench will be approximately 3 feet deep. If a 5-foot-wide trench is allowed, the conduits may be laid flat and a trench depth of 2 feet may be practical. A shallower trench along Front Street would interfere with fewer of the existing underground utilities. However, the wide-trench option to lay the conduits flat, would increase surfacing demolition and repair work. Riser Termination Poles At both ends of the underground run, all four cables must rise up a self-supporting tubular-steel pole. These steel poles are approximately 80 to 90 feet above grade. Foundations may consist of vibrahammer-installed steel caissons. Alternatively, if soils are corrosive, construction may require drilled-pier-type concrete foundations. Splice Vaults Splice Vaults for 115-kV underground circuits are made of prefabricated concrete sections with inside dimensions of approximately 20 feet long, 10 feet wide, and 7-6 floor to ceiling. The maximum distance between splice vaults is determined by the weight of the cable, the friction in the conduit, and the number and degree of bends. Due to bends in the typical trench route, the distance between vaults will normally be less than 2000 feet. Construction Method Underground construction becomes unconventional when special conditions are encountered for the excavation and placement of splice vaults and duct banks. The Front Street trench route presents a list of unconventional situations that will cause design and construction impacts: a. Wider trench and shoring required by saturated soils and possible lack of soil stability b. Trench de-watering and proper disposal of the seepage water c. Special Mitigation of subsurface discoveries during trenching, such as environmental hazards, or archeological finds d. Asphalt pavement cuts and repairs e. Concrete pavement cuts and repairs f. Salty ground water requires that all reinforcing steel in duct bank encasement and splice vaults be coated for corrosion protection. g. Special Civil/Structural design to mitigate construction problems due to the proximity to building foundations, or the crossing of water, sewer, storm sewer, communication lines, and other power lines on the line route

4 h. Directional Boring: This method requires the directional bore of a pilot hole followed by a series of passes to ream the hole as necessary for the pulling-in of a 24 diameter steel pipe for the length of the bore. The PVC Duct bank with special spacers is pulled into the 24 pipe. Slurry thermal concrete is then pumped into the spaces between conduits to fill the pipe. Operation and Maintenance Requirements. Two manhole access covers would be required. Manhole access holes must be large enough to apply active ventilation pipes for people entering and working in the vaults. Splice vaults under Front Street would generate special design features. Vaults along Hoquarten Slough would be subject to relatively frequent flooding and the continual ingress of brackish ground water. Salty water will inevitably enter the vaults due to the water table level, and floods will fill the vaults and cover them by several feet. The PUD must have plans and equipment in place for dewatering and cleaning. In addition, PUD operation and maintenance staff may require primary and backup sump pumps constructed into the vault. Reliable electric service to these pumps would need to be provided and maintained. Flood or seepage water removed from the vault, as well as vault cleaning water must be disposed of in compliance with City requirements. Proper connections to the City storm or sanitary sewer may be required for these purposes. Vaults must be designed with coated reinforcing steel and a specific concrete mix. Interior vault fittings, fasteners, racks, and ladders must be designed to resist salt water corrosion in a humid atmosphere. Vault design will require special specification and sourcing of stainless steel, plastics, and fiberglass fasteners and equipment. FRONT STREET 115-KV UNDERGROUND CONSTRUCTION COST ESTIMATES Estimated costs are ballpark amounts and are the professional opinion of the engineer. l project costs might be if based on numerous best guess assumptions. If the PUD proceeded with an underground option a stepwise approach to confirm the technical feasibility: starting with the geotechnical engineering exploration, and then preliminary design development for the purpose of ODOT permitting. 1. Probable Front Street Design and Construction The estimate is based on a 0.5-mile-long underground 115-kV transmission line project consisting of four 115-kV cables in the alignment described in the foregoing discussion. The construction assumes: 2 Terminal/Riser Poles 3 Splice Vaults with special water handling provisions (sump pumps and/or City plumbing connections 2640 feet of reinforced concrete-encased duct bank at typical depth, with special design accommodations for crossing utilities and adjacent building foundations It is assumed that the Oregon Department of Transportation will Permit the Tillamook PUD transmission line duct bank crossing, and will construct the PUD duct bank as part of its proposed re-construction of the Hoquarten Slough Bridge and Highway 101 work. This configuration of construction is judged by us to be the most probable configuration

5 that may be eventually permitted and constructed along Front Street. The following is a listing of major cost items and the expected Order-of-Magnitude cost for each line item. Pre-Design Plan and Profile Survey and Mapping: $20,000 Pre-Design Sub-Surface City Record Investigation and Ground-Penetrating RadSurveys: $40,000 Tillamook 115kV UG Feasibility Assessment Page 13 of 14 Design Development and Permit Engineering Underground 115-kV System $80,000 Structural/Civil Design $20,000 Final Design Engineering Underground 115-kV System $200,000 Structural/Civil Design $30,000 Engineering Services during Construction Underground 115-kV System $50,000 Structural/Civil Design $50,000 Total Engineering Cost: $430,000 Subtotal Surveys and Engineering: $490,000 Labor and Material Construction Contractor Compensation: $2,360,000 Subtotal: $2,850,000 Design and Construction Contingency (25% rounded up): $750,000 Tillamook PUD Administrative and Financing (4%-5% of Subtotal): $150,000 Tillamook PUD Cost to Obtain New Conditional Use Permit: $150,000 (PUD Estimate based on Original CUP Cost) Grand Total: $3,900,000 CONSTRUCTION OPTIONS 1. Shallow Trench Construction In Paved Areas: If the City and the PUD can permit and accept a shallow trench under paved areas, the structural mitigations due to the adjacent building foundations and waterline crossings may be totally avoided. In this case, the expected cost may be reduced. Expected Cost Reduction: $370, Design Without Vaults: During the design development process, it may be found possible and preferable to design the system without vaults. Because the trench is very straight and the length of the project is about 2500 feet, it seems technically possible to install the four cables in a continuous duct bank without a splice vault between the two terminal riser poles. To provide for this no-vault design, the first 100 feet from the termination/riser poles would have the cables placed in a sand bed in a wide trench without conduits. In these two areas, the cables would be laid flat in sand bedding, separated by 3 feet or so, and snaked to allow some slack. The cables would be protected with removable concrete slabs that would be covered with sufficient topsoil to allow some native grasses or vines. If this design was acceptable to the City and the PUD, the construction cost could be reduced. Expected Cost Reduction: $350,000Concrete Roadway Cuts and Repairs for Highway 101 New Bridge Approach: If ODOT does not construct the duct bank as part of the Bridge project, cost to install the duct bank later will involve concrete cuts, special repair designs, special construction schedules, and traffic flagging costs. Expected Cost Increase: $250,000

6 4. Directional Boring: Directional boring for may not be technically possible. Vertical geotechnical test borings along the line route would be necessary to determine feasibility and provide the basis of a better cost estimate. Directional bores can cost 3 to 5 times (or more) the cost of conventional construction. Subtract trenching and related costs:$1,000,000 Add Boring and Pipe installation: $4,000,000 Expected Cost Addition: $3,000,000 EXPECTED PROJECT SCHEDULE FOR THE DESCRIBED PROJECT Pre-Design Surveys: 2 months Design, PUD Reviews, Rural Utility Service Financing Reviews, and Permitting:12 months Construction Bidding: 2 months Contract Selection, Negotiation, and Execution: 1 month Material Procurement and Delivery: 12 months (Cable and steel riser poles are the longlead items) Construction: 3 months (street use may be disrupted for 5 weeks) Total Schedule Requirement: 32 months

7

8 115-kV UNDERGROUND CONSTRUCTION ALONG FRONT STREET LOCATION AND ALIGNMENT Tillamook PUD plans to construct a 115-kV overhead transmission line between the Bonneville Power Administration Tillamook Substation east of the City of Tillamook and a proposed PUD substation between the towns of Netarts and Oceanside. The City has asked Tillamook PUD to investigate the concept of placing a 0.5-mile-long segment of the alignment underground along Front Street in Tillamook. The underground portion would parallel the south side of Hoquarten Slough. The underground facility would cross under Oregon Highway 101 and would need to accommodate the future planned rearrangement of Highway 101 at the Hoquarten Bridge. The following map indicates the location of the alignment and the end points of the underground segment. Project location SYSTEM CONFIGURATION The system configuration is determined by the following criteria: 1. Reliability Requires a 4-Cable System. The Oceanside 115-kV Transmission Line will be the only 115-kV circuit serving the Netarts-Oceanside Area. This circuit is composed of three energized wires. If the underground segment along Front Street were constructed with three cables, a failure of any component of the underground segment would cause an area-wide outage in the area served by the new Netarts/Oceanside substation. Repair of an overhead transmission line is usually accomplished in a matter of hours with the PUD s linemen, equipment, spare conductor, and hardware. However, failure of an underground cable, splice, or riser terminator will require a minimum of several weeks or months to repair the failed components. This Tillamook 115kV UG Feasibility Assessment Page 1 of 14

9 is because high-voltage underground systems and the individual components are specialized devices, carefully matched with each other, and requiring technicians of carefully maintained training and certification. The PUD would store spare components, but with no underground transmission technicians on staff, the PUD would need to schedule a specialist to mobilize to Tillamook with the proper equipment to make the repairs. Although cable rated 35 kv and below is common, cable for transmission voltages is rarely justified, and is therefore rarely installed. Because transmission line outages can affect thousands of consumers, transmission cables are manufactured to higher dimensional and purity standards than the common underground distribution cable. To reduce deterioration due to the high voltage stress, 115-kV transmission cable incorporates a welded copper or lead moisture barrier to preclude any water molecules from the insulation. As a result, the terminations and splices must be installed in clean room laboratory conditions. Consequently, field installations require building a climate-controlled room around termination sites or inside the splice vaults. The cable ends must be prepared to exacting tolerances and cleanliness. It is typical to expect that the installation of each high-voltage terminal or splice will require one 8-hour shift by a skilled technician. Even with the best of transmission cable installations, there remains a probability of an equipment failure due to manufacturer or installation defect. An underground transmission system has an expected life of about 50 years, and the failure probability tends to increase with age. In addition, there is always the risk of damage due to severe storm, vehicle accident, fire, or vandalism. Because repairs typically require weeks, owners of transmission systems must mitigate the risk of a failure. Usually, the risk is covered by constructing a redundant circuit on a separate alignment. These looped systems are typical in metropolitan transmission networks. The PUD s plan for the proposed Oceanside 115-kV overhead transmission line does not include a second 115-kV transmission source to the proposed Oceanside Substation. Instead, the PUD plans to improve its existing 25-kV distribution line to the Netarts-Oceanside area so that it can serve as an emergency power supply in the case of a brief transmission outage. However, a failure in the 115-kV underground segment would take weeks or months to correct. The planned emergency distribution tie line to the Netarts/Oceanside area will be designed to serve the area for a few hours or days at a time, but it will not be practical to design this tie line with enough efficiency and reliability for long-term (weeks or months) transmission line outages. Therefore, in my opinion, because a single-component 115-kV underground failure is the is most likely mode of failure, the PUD should install four, terminated, and tested cables; this way, the failure of any one of the three normally-energized cables can be by-passed with the fourth (spare) cable to restore service. With the spare 115-kV cable operating, The PUD can order parts and arrange for qualified repair personnel and equipment. When finally ready for the permanent repairs to the failed component, the 115-kV transmission would be de-energized and the emergency distribution tie line would be used to carry the load. With the fourth cable in place, the emergency tie will only operate during the several days that the 115-kV line is actually shut down for repairs. Tillamook 115kV UG Feasibility Assessment Page 2 of 14

10 115-kV CABLES Three of the 115-kV cables would be normally energized. The fourth (emergency) cable will be terminated on the side of the riser pole where the overhead conductors are deadended. The spare cable termination would be positioned between the overhead conductors so that it can be jumpered to take the place of the failed cable or terminator. This process can be done with a man-lift truck and with the system de-energized and grounded. The design and planning of the permanent repair must begin as soon as possible. The nature and cost of the repair will depend on the extent of damage. Replacement cable, terminators, and additional underground splice vaults may be required. The cables specified for this system will have a stranded copper conductor at its core and insulated with cross-linked polyethylene. The cable construction will include a conductor shield material, an insulation shield material, an impervious copper or lead inner jacket and a tough plastic outer jacket. The underground cables will be designed to match the thermal capacity of the overhead conductors of this transmission line. Given the thermal properties of the duct bank and concrete encasement, the size of the stranded copper conductor of the underground cable is calculated to keep the cable temperature under the manufacturer s maximum specified operating temperature. Depending on the required size of the copper conductor, the finished diameter is expected to be approximately 3.5 inches in diameter and weigh about 9.5 pounds per foot. Tillamook 115kV UG Feasibility Assessment Page 3 of 14

11 Tillamook 115kV UG Feasibility Assessment Page 4 of 14

12 DUCT BANK A typical transmission line duct bank design has four large PVC pipes (conduits or ducts) placed in a square arrangement using plastic spacer devices. Each of the transmission line cables must be placed in its own conduit to facilitate the pulling-in, or replacement, of the cables, and to provide for heat dissipation. Two smaller conduits would also be installed above the transmission conduits: usually one for a transmission line protective relay communication cable, and another conduit used as a spare or for substation data acquisition and control. The entire duct bank is anchored to the floor of the trench with an initial placement of 3-4 of concrete, which is allowed to set. Then the entire duct bank assembly is encased with a high-strength, thermally-conductive concrete mix, which is designed and tested for this purpose. Concrete encasement under city streets and highways include steel reinforcing bars on the corners of the duct bank to improve the strength of the encasement and control cracking. Because steel reinforcement rods must have at least 3 of concrete around them, construction of duct banks under roads is more complex, and the trench width must be increased. For protection against dig-ins, the top of the transmission line conduit is typically placed from grade; the trench will be about 6 feet deep. However, power cables generate heat and soil acts as insulation that causes the cable temperature to rise. Engineers test the soil thermal characteristic and use this value in the design of the optimum duct bank depth and encasement. The design objective is to economically limit the maximum cable temperature to the manufacturer s specification. Under pavement, the roadway occupancy permit may allow the duct bank to be placed in a shallow trench. Shallow placement under roadways may be allowed due to the intrinsic protection against dig-ins. If a narrow trench is required, the top of the encasement could be just under the pavement material and the trench will be approximately 3 feet deep. If a 5-foot-wide trench is allowed, the conduits may be laid flat and a trench depth of 2 feet may be practical. A shallower trench along Front Street would interfere with fewer of the existing underground utilities. However, the wide-trench option to lay the conduits flat, would increase surfacing demolition and repair work. Tillamook 115kV UG Feasibility Assessment Page 5 of 14

13 Typical Duct Bank under soil (under roadway, excavation will be shallower) Note: This illustration does not include the fiber optic conduit. Typical construction in an asphalt roadway: Pavement cuts, trenching in road base, and duct bank construction Tillamook 115kV UG Feasibility Assessment Page 6 of 14

14 Placing concrete encasement around and over a duct bank Note: The Front Street duct bank will require pavement cuts, shoring, and coated-steel reinforcing bars. RISER TERMINATION POLES At both ends of the underground run, all four cables must rise up a self-supporting tubular-steel pole. The pole-top assembly includes four cable termination devices that provide an electrical transition from insulated cable to the bare overhead conductor (wire). These steel poles are approximately 80 to 90 feet above grade and capable of holding the full tension of the adjacent overhead transmission line span. Foundations may consist of vibrahammer-installed steel caissons. Alternatively, if soils are corrosive, construction may require drilled-pier-type concrete foundations. The Front Street project would require all four cables to rise up the outside of the poles with cable clamps, and be protected by steel shrouds up to 18 feet from the ground. Tillamook 115kV UG Feasibility Assessment Page 7 of 14

15 Spare cable Three normally energized cables (spare cable on back) Rural Example 115-kV Riser Pole with Four Underground Cables (TriAxis Design, Bend, Oregon) Tillamook 115kV UG Feasibility Assessment Page 8 of 14

16 Urban Street Example 115-kV Riser Pole with Four Underground Cables (TriAxis Design, Portland, Oregon) SPLICE VAULTS Splice Vaults for 115-kV underground circuits are made of prefabricated concrete sections with inside dimensions of approximately 20 feet long, 10 feet wide, and 7-6 floor to ceiling. The maximum distance between splice vaults is determined by the weight of the cable, the friction in the conduit, and the number and degree of bends. Experience indicates that the calculated maximum pulling length of a 115-kV cable in a straight duct bank is approximately 2500 feet. This distance correlates well with practical cable reel sizes for shipment, and handling at the job site. Due to bends in the typical trench route, the distance between vaults will normally be less than 2000 feet. Tillamook 115kV UG Feasibility Assessment Page 9 of 14

17 115-kV Splice Vault Interior Prior to Cable Pulling. (splice racks partially assembled) (Eugene Water and Electric Board) 2. Construction Methods. Conventional Underground Construction: Typical cross country construction involves a wide trench approximately 6 feet deep. A duct bank consisting of four 6 PVC conduits and two 2 PVC conduits would be placed at the bottom of the trench and then encased in concrete as described earlier. The duct bank would run between splice vaults located at the termination riser poles and otherwise spaced every 2000 to Unconventional Underground Construction Underground construction becomes unconventional when special conditions are encountered for the excavation and placement of splice vaults and duct banks. The Front Street trench route presents a list of unconventional situations that will cause design and construction impacts: a. Wider trench and shoring required by saturated soils and possible lack of soil stability at trench depth b. Trench de-watering and proper disposal of the seepage water c. Special Mitigation of subsurface discoveries during trenching, such as environmental hazards, or archeological finds d. Asphalt pavement cuts and repairs e. Concrete pavement cuts and repairs Tillamook 115kV UG Feasibility Assessment Page 10 of 14

18 f. Salty ground water requires that all reinforcing steel in duct bank encasement and splice vaults be coated for corrosion protection. g. Special Civil/Structural design to mitigate construction problems due to the proximity to building foundations, or the crossing of water, sewer, storm sewer, communication lines, and other power lines on the line route h. Directional Boring: This method requires the directional bore of a pilot hole followed by a series of passes to ream the hole as necessary for the pulling-in of a 24 diameter steel pipe for the length of the bore. The PVC Duct bank with special spacers is pulled into the 24 pipe. Slurry thermal concrete is then pumped into the spaces between conduits to fill the pipe. 3. Operation and Maintenance Requirements. Due to the size of the splice vaults, two manhole access covers are required along with ladders. Where vaults are subject to ground or surface water intrusion, effective drains, or sump pumps are required. Manhole access holes must be large enough to apply active ventilation pipes for people entering and working in the vaults. Splice vaults under Front Street would generate special design features: Vaults along Hoquarten Slough would be subject to relatively frequent flooding and the continual ingress of brackish ground water. The floor of the vaults in this area would be below the average water table, which is influenced by the tides. Salty water will inevitably enter the vaults to the water table level, and floods will fill the vaults and cover them by several feet. The PUD must have plans and equipment in place for dewatering and cleaning. In addition, PUD operation and maintenance staff may require primary and backup sump pumps constructed into the vault. Reliable electric service to these pumps would need to be provided and maintained. Flood or seepage water removed from the vault, as well as vault cleaning water must be disposed of in compliance with City requirements. Proper connections to the City storm or sanitary sewer may be required for these purposes. Vaults must be designed with coated reinforcing steel and a specific concrete mix. Interior vault fittings, fasteners, racks, and ladders must be designed to resist salt water corrosion in a humid atmosphere. Vault design will require special specification and sourcing of stainless steel, plastics, and fiberglass fasteners and equipment. Tillamook 115kV UG Feasibility Assessment Page 11 of 14

19 FRONT STREET 115-KV UNDERGROUND CONSTRUCTION COST ESTIMATES The cost of any project is determined by the design. In this case a final design concept is not available. The design criteria can only be listed after requirements of the State, County, City, and the PUD are completely determined, soils are tested, and all surveys complete. The design process requires initial investigations, the development of design proposals, and then revisions to address review comments. Meetings with all stakeholders may be needed to resolve conflicting requirements. Therefore, cost estimating at this time can be no more than order-of magnitude (ballpark) accuracy. Due to the lack of geotechnical information and other archeological or hazardous trenching finds that may be present, I judged that a minimum of 25% design and construction contingency must be added to these estimates. The estimates that follow are my professional opinion of what competitive final project costs might be if based on numerous best guess assumptions, and caveats. If the PUD proceeded with an underground option, I would advise that the approach be stepwise to confirm the technical feasibility: starting with the geotechnical engineering exploration, and then preliminary design development for the purpose of ODOT permitting. The construction estimating developed here is based on recent bidding experience for 115-kV construction, and then adapted with my professional judgment to the project envisioned along Front Street. 1. Probable Front Street Design and Construction The estimate is based on a 0.5-mile-long underground 115-kV transmission line project consisting of four 115-kV cables in the alignment described in the foregoing discussion. The construction assumes: 2 Terminal/Riser Poles 3 Splice Vaults with special water handling provisions (sump pumps and/or City plumbing connections 2640 feet of reinforced concrete-encased duct bank at typical depth, with special design accommodations for crossing utilities and adjacent building foundations It is assumed that the Oregon Department of Transportation will Permit the Tillamook PUD transmission line duct bank crossing, and will construct the PUD duct bank as part of its proposed re-construction of the Hoquarten Slough Bridge and Highway 101 work. This configuration of construction is judged by us to be the most probable configuration that may be eventually permitted and constructed along Front Street. The following is a listing of major cost items and the expected Order-of-Magnitude cost for each line item. Pre-Design Plan and Profile Survey and Mapping: $20,000 Pre-Design Sub-Surface City Record Investigation and Ground-Penetrating Radar Surveys: $40,000 Tillamook 115kV UG Feasibility Assessment Page 12 of 14

20 Design Development and Permit Engineering Underground 115-kV System $80,000 Structural/Civil Design $20,000 Final Design Engineering Underground 115-kV System $200,000 Structural/Civil Design $30,000 Engineering Services during Construction Underground 115-kV System $50,000 Structural/Civil Design $50,000 Total Engineering Cost: $430,000 Subtotal Surveys and Engineering: $490,000 Labor and Material Construction Contractor Compensation: $2,360,000 Subtotal: $2,850,000 Design and Construction Contingency (25% rounded up): $750,000 Tillamook PUD Administrative and Financing (4%-5% of Subtotal): $150,000 Tillamook PUD Cost to Obtain New Conditional Use Permit: $150,000 (PUD Estimate based on Original CUP Cost) Grand Total: $3,900,000 CONSTRUCTION OPTIONS 1. Shallow Trench Construction In Paved Areas: If the City and the PUD can permit and accept a shallow trench under paved areas, the structural mitigations due to the adjacent building foundations and waterline crossings may be totally avoided. In this case, the expected cost may be reduced. Expected Cost Reduction: $370, Design Without Vaults: During the design development process, it may be found possible and preferable to design the system without vaults. Because the trench is very straight and the length of the project is about 2500 feet, it seems technically possible to install the four cables in a continuous duct bank without a splice vault between the two terminal riser poles. To provide for this no-vault design, the first 100 feet from the termination/riser poles would have the cables placed in a sand bed in a wide trench without conduits. In these two areas, the cables would be laid flat in sand bedding, separated by 3 feet or so, and snaked to allow some slack. The cables would be protected with removable concrete slabs that would be covered with sufficient topsoil to allow some native grasses or vines. If this design was acceptable to the City and the PUD, the construction cost could be reduced. Expected Cost Reduction: $350,000 Tillamook 115kV UG Feasibility Assessment Page 13 of 14

21 3. Concrete Roadway Cuts and Repairs for Highway 101 New Bridge Approach: If ODOT does not construct the duct bank as part of the Bridge project, cost to install the duct bank later will involve concrete cuts, special repair designs, special construction schedules, and traffic flagging costs. Expected Cost Increase: $250, Directional Boring: Directional boring for may not be technically possible. Vertical geotechnical test borings along the line route would be necessary to determine feasibility and provide the basis of a better cost estimate. Directional bores can cost 3 to 5 times (or more) the cost of conventional construction. Subtract trenching and related costs:$1,000,000 Add Boring and Pipe installation: $4,000,000 Expected Cost Addition: $3,000,000 EXPECTED PROJECT SCHEDULE FOR THE DESCRIBED PROJECT Pre-Design Surveys: 2 months Design, PUD Reviews, Rural Utility Service Financing Reviews, and Permitting:12 months Construction Bidding: 2 months Contract Selection, Negotiation, and Execution: 1 month Material Procurement and Delivery: 12 months (Cable and steel riser poles are the longlead items) Construction: 3 months (street use may be disrupted for 5 weeks) Total Schedule Requirement: 32 months Tillamook 115kV UG Feasibility Assessment Page 14 of 14

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

Underground System Design TADP 547

Underground System Design TADP 547 Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS

SECTION UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS SECTION 02670 UTILITY POLYETHYLENE CONTAINMENT PIPE SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of containment

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Change History Date Description of Change Pages / Sections Modified Change Approver Initials 8/1/17 Update sections Materials and Special Requirements 3 F. 2. 4 H. 2.; 10. & 11(added) 6/15/16 Updated division

More information

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION

ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ANCHORAGE MUNICIPAL LIGHT & POWER ENGINEERING DIVISION ML&P ELECTRICAL FACILITY CLEARANCE REQUIREMENTS FOR CONSTRUCTION OR MAINTENANCE NEAR ELECTRICAL FACILITIES July 31, 2014 MUNICIPAL LIGHT & POWER ELECTRICAL

More information

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal.

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal. PART 1: GENERAL 1.01 Scope of Standard A. This standard provides general guidance concerning the specific preferences of Texas State University for for Electrical System. B. Texas State University recognizes

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 092216 - NON-STRUCTURAL METAL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS CS-2-01. GENERAL: Trench excavation shall conform with the City Standard Specifications. In general a trench is defined as an excavation in which

More information

SECTION ELECTRICAL SITE UTILITIES

SECTION ELECTRICAL SITE UTILITIES SECTION 16402 ELECTRICAL SITE UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

Underground Conduit Systems

Underground Conduit Systems Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different

More information

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The following changes are made to the Proposal, Specifications, and Plans. PROPOSAL Proposal Sheets

More information

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS 1 33 63 00 - Underground Steam and Condensate Distribution System 1. Introduction A. Steam is distributed to University and Medical Center buildings through an underground piping system year-round at a

More information

SECTION HORIZONTAL DIRECTIONAL DRILLING

SECTION HORIZONTAL DIRECTIONAL DRILLING SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 GROUNDING AND BONDING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION BORING AND/OR JACKING PIPE

SECTION BORING AND/OR JACKING PIPE 02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe

More information

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION

SECTION UNDERGROUND ELECTRICAL CONSTRUCTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 41 UNDERGROUND ELECTRICAL CONSTRUCTION A. This section specifies the furnishing, installation, and connection of precast manholes and pullboxes with ducts

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

TS 804 CABLES TABLE OF CONTENTS TRAFFIC SIGNAL EQUIPMENT POLE WIRING DIAGRAM LOCATIONS WITH CENTRE MEDIANS

TS 804 CABLES TABLE OF CONTENTS TRAFFIC SIGNAL EQUIPMENT POLE WIRING DIAGRAM LOCATIONS WITH CENTRE MEDIANS TORONTO TRANSPORTATION January 2012 TS 804 CABLES TABLE OF CONTENTS 1. DRAWINGS TTD 804.001 TTD 804.002 TTD 804.003 TTD 804.005 TTD 804.006 TTD 804.007 TTD 804.010 TTD 804.015 TTD 804.020 TTD 804.025 TTD

More information

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System 2004 Specifications Houston District SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System 1. Description. Furnish and place a Multi-Duct Conduit (MDC) system that is suitable for installation in an outdoor

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT

CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 623 JANUARY 1990 CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT 623.01 SCOPE 623.02 REFERENCES 623.05 MATERIALS TABLE OF CONTENTS 623.05.01

More information

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 05 26 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph

More information

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications. 16402 ELECTRICAL SITE UTILITIES ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 33 50 00. *************************************************************************************************************

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 02222 - EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES PART 1 - GENERAL 1.01 SECTION INCLUDES A. Excavating trenches for the installation of utilities and stormwater detention facilities. B.

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL Multicell Vikimatic MultiCell Conduit Systems These guidelines should help you install MultiCell Conduit in the simplest way possible and should be read in their entirety before attempting to install the

More information

GENERAL UTILITIES REQUIREMENTS

GENERAL UTILITIES REQUIREMENTS 33 00 00 GENERAL UTILITIES REQUIREMENTS i. 01 41 26.02 Local Utility Information & Locate ii. 23 05 19 Meters and Gages iii. 33 10 00 Water Utilities Public Water Distribution System iv. 33 12 13.13 Water

More information

DETAILED SCOPE OF WORK IN-STREAM TIDAL GENERATING PLANT TISEC COLLECTOR CIRCUITS DEVELOPMENT

DETAILED SCOPE OF WORK IN-STREAM TIDAL GENERATING PLANT TISEC COLLECTOR CIRCUITS DEVELOPMENT PAGE I TABLE OF CONTENTS SECTION DESCRIPTION PAGE 1 GENERAL 1 1.1 OVERVIEW 1 1.2 PREPARATORY WORK CARRIED OUT BY OTHERS 2 1.3 MATERIALS TO BE SUPPLIED BY THE OWNER 2 1.4 PROJECT SCHEDULE 3 1.5 PROJECT

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED

More information

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number: SECTION 260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract apply to this Section. 1.2 SUMMARY A. This Section

More information

16300 HIGH VOLTAGE DISTRIBUTION

16300 HIGH VOLTAGE DISTRIBUTION 16300 HIGH VOLTAGE DISTRIBUTION PART 1: GENERAL 1.01 WORK INCLUDED A. Most new loads will be served from the underground electric distribution system. This system is a primary open loop configuration served

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

SECTION GRAVITY WASTEWATER LINES

SECTION GRAVITY WASTEWATER LINES SECTION GRAVITY WASTEWATER LINES 1. DESCRIPTION This specification shall govern all work required for furnishing, handling and installing gravity wastewater lines required to complete the project. 2. MATERIALS

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL I. GENERAL I.1. I.2. I.3. Driven or bored casing pipe provides an effective housing for duct. Its use is required in situations where open cutting is not permitted such as crossings under railroads and

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

City of Logan Sanitary Sewer Design Standards

City of Logan Sanitary Sewer Design Standards City of Logan Sanitary Sewer Design Standards 2011 http://www.loganutah.org/public_works/engineering/stdsspecsdesign.cfm Table of Contents PART 1. CITY OF LOGAN SANITARY SEWER SYSTEM DESIGN STANDARDS FOR

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

SECTION FACILITY LIGHTNING PROTECTION

SECTION FACILITY LIGHTNING PROTECTION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 41 00 FACILITY LIGHTNING PROTECTION SPEC WRITER NOTE: Delete between //----//if not applicable to project. Also delete any other item or paragraph not applicable

More information

New Construction Units. a. Includes the furnishing of all labor and equipment for the installation of new construction units.

New Construction Units. a. Includes the furnishing of all labor and equipment for the installation of new construction units. 1 All construction is to follow design and construction documents approved by the Engineer and marked approved for construction. All construction shall also follow the National Electrical Safety Code,

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES

SECTION PROTECTION AND RESTORATION OF EXISTING FACILITIES PART 1 - GENERAL 1.1 GENERAL A. The CONTRACTOR shall protect all existing utilities and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements

More information

WOOD POLE SPAN WIRE SIGNAL SYSTEMS

WOOD POLE SPAN WIRE SIGNAL SYSTEMS 7 A wood pole span wire traffic control signal system differs from a mast arm steel pole traffic control signal system in that it uses wood poles and span wires to place the signal indications in the driver

More information

Multi-Gard PVC Assembly/ Field Cuts

Multi-Gard PVC Assembly/ Field Cuts Multi-Gard PVC Assembly/ Field Cuts Assembly 1. Distribute Multi-gard sections along the sides of the trench with male ends pointing towards starting vault entrance.. Remove protective cap and install

More information

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR GROUNDING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

406 - PIPE SEWERS - MTC FORM 406

406 - PIPE SEWERS - MTC FORM 406 406 - - MTC FORM 406 INDEX 406.1 GENERAL Types of Pipe Pipe Strength, Rigid Pipes Polyethylene Pipe Strength - Rigid or Flexible Pipe Strength and Treatment, Flexible Pipes Selection of Type, Strength

More information

Grant PUD. Joint Use Standards. For Pole Attachments including: Cable Television Fiber Optics Telecommunications

Grant PUD. Joint Use Standards. For Pole Attachments including: Cable Television Fiber Optics Telecommunications Grant PUD Joint Use Standards For Pole Attachments including: Cable Television Fiber Optics Telecommunications REVISED: July 25, 2018 INTRODUCTION AND OVERVIEW The information contained in these Joint

More information

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PUBLIC WORKS DEPARTMENT GENERAL NOTES PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard

More information

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION

ITEM L-119 AIRPORT OBSTRUCTION LIGHTS DESCRIPTION SECTION 74 AIRPORT OBSTRUCTION LIGHTS (FAA L-119) 74-1 GENERAL The Contractor shall perform all work required by the plans and specifications for construction of obstruction lights in accordance with the

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4. 6.2 OVERHEAD SERVICES Wiring of any premises for connection

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

The Medical Center Company Electrical System Installation Requirements

The Medical Center Company Electrical System Installation Requirements The Medical Center Company Electrical System Installation Requirements Introduction System Description Approvals Scheduling of Power Shutdowns and Power Transfers 5. Service Entrance 6. Feeder Systems

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

WIRING METHODS CHAPTER 38

WIRING METHODS CHAPTER 38 CHAPTER 38 WIRING METHODS SECTION E3801 GENERAL REQUIREMENTS E3801.1 Scope. This chapter covers the wiring methods for services, feeders and branch circuits for electrical power and distribution. E3801.2

More information

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS AFTER FEBRUARY 1, 2011 ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS 481.1 Description. This specification shall govern for the construction of monolithic, reinforced concrete box sewers of the size,

More information

XXXXXXXXXXX Solar (XXX) Generation Interconnection

XXXXXXXXXXX Solar (XXX) Generation Interconnection Facility Study For XXXXXXXXXXX Solar (XXX) Generation Interconnection Prepared For: Randy Harlas, Substation Manager El Paso Electric Company El Paso, TX September 2010 Table of Contents 1. GENERAL...

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

Merrimac Municipal Light Department. Commercial Developments Policy

Merrimac Municipal Light Department. Commercial Developments Policy Merrimac Municipal Light Department Commercial Developments Policy General: This document provides specific instructions for the provision of underground electrical facilities associated with the construction

More information

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated

More information

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations. Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet

More information

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS SECTION 26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule 1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238

More information

City of Rohnert Park Building Department Inspection Descriptions

City of Rohnert Park Building Department Inspection Descriptions 200 SITE REVIEW: Prior to a permit being issued the Fire / Building Department is authorized to examine existing buildings, structures, and site for which an application has been filed. 201 PRECONSTRUCTION

More information

FOR HISTORICAL REFERENCE ONLY

FOR HISTORICAL REFERENCE ONLY To: From: Subject: Electronic Distribution Recipients MINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No. 12-01-B-01 February 7, 2012 Jon M. Chiglo, P.E. Division

More information

APPENDIX A MEASUREMENT AND PAYMENT

APPENDIX A MEASUREMENT AND PAYMENT P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged

More information

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL

UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL UNDERGROUND SERVICES - GENERAL SERVICE AND MULTI-UNIT RESIDENTIAL 8.01 GENERAL This material is not intended to cover service from OPPD s network in the downtown Omaha area. See Chapter 12 for details

More information

INSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT

INSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT UNDERGROUND ELECTRICAL PART 1 GENERAL 1.1 SECTION INCLUDES: A. The work specified in this section consists of furnishing and installing underground utilities using the method of installation commonly referred

More information

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual [Type text] Heber Light & Power Developers & Excavators Electrical Service Requirements Manual May 2017 E.1.1 - GENERAL REQUIREMENTS PURPOSE This section was prepared to aid developers, contractors, engineers

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR: MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER OPR:CT 1 of 5 APPR:JAR:DBP:09-07-11 FHWA:APPR:09-07-11 a. Description. This work consists of furnishing and installing

More information

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565)

WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) WESTERN UNDERGROUND COMMITTEE GUIDE 3.4 (3.4/00/0565) PLASTIC CONDUIT AND FITTINGS PLACING INSTRUCTION NOTE: This "Guide" summarizes the opinions, recommendations, and practices of the Western Underground

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

Cutouts and Fuse Links Equipment to protect against faults and over-current conditions on power distribution systems. Open-Type Cutouts Linkbreak Cutouts Loadbreak Cutouts Cutout-Arrester Combinations

More information

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 604 NOVEMBER 2004 CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION TABLE OF CONTENTS 604.01 SCOPE 604.02 REFERENCES 604.03 DEFINITIONS - Not Used

More information

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1 1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include

More information