Is FERC s Generator Interconnection Policy really conducive to efficient generation development?

Size: px
Start display at page:

Download "Is FERC s Generator Interconnection Policy really conducive to efficient generation development?"

Transcription

1 By Steven S. Garwood PowerGrid Strategies, LLC March 24, 2010

2 Is FERC s Generator Interconnection Policy really conducive to efficient generation development? Critical environment for efficient generation development: Process should provide reasonable level of schedule certainty Process should provide reasonable level of cost certainty Process should be integrated with, but not be a substitute for, overall system reliability planning In many respects, FERC s implementation of its Interconnection Policy, including allowed variations in regions of the country, significantly fail to produce an environment of business certainty. energy market 2

3 FERC Orders Od 2003, 2006 and 661 In Order 2003 (LGIP >20MW) and 2006 (SGIP <20MW), FERC required jurisdictional utilities to implement so-called Standardized Generator Interconnection ti Procedures (GIP) and Interconnection ti Agreements (GIA). Order 661 came later to address technical limitations of wind turbine technology. FERC s stated goal was to prevent undue discrimination, preserve reliability, increase energy supply, and lower wholesale prices for customers by increasing the number and variety of new generation that will compete in the wholesale electricity market. Variations in the standard d were permitted in rare circumstances by non- RTO/ISO Transmission Providers based on demonstration that variations were superior to the pro forma standard. An enormous degree of deference was granted RTOs and ISOs with regard to implementing variations to the pro forma standards. The results implementation of not-so standard GIP throughout much of the country which pose risks to generator developers in the form of uncertainty as to schedule and cost thatt threatenst achieving i the very results FERC s socalled Standard GIP were suppose to promote. energy market 3

4 Pro Forma Standard GIP Highlights Application & Queue Processing First-Come, First-Served (FC-FS) $10, Deposit + Site Control or additional $10, In-Service Date within 7-10 yrs. of Application Date Tied to Planning Horizon of Transmission Provider (TP) TP Posts Request details on OASIS Generator Interconnection ti Queue masking identity of Interconnection Customer (IC) until GIA is executed or filed at FERC Queue position dictates t order of performing studies and responsibility for new or upgraded facilities costs Scoping Meeting held within 30-days to discuss alternate POI and details for Interconnection Studies energy market 4

5 Pro Forma Standard GIP Highlights Application & Queue Processing - continued Queue Position Maintained Provided: Deposits for Interconnection Studies are made timely Study Agreements are executed timely No Material Modifications are made to Project Suspension periods not to exceed 36 months cumulatively GIA is negotiated, executed or requested to be filed with FERC unexecuted on a timely basis energy market 5

6 Pro Forma Standard GIP Highlights Application & Queue Processing - continued Interconnection Service Types Energy Resource (ER) allows IC to deliver full output of generating facility using existing firm or non-firm transmission capacity on an asavailable basis. Network Capacity Resource (NR) allows IC to be interconnected and integrated comparable to TP s own generating facilities used to serve native load, or if in an RTO/ISO with market-based congestion management, on the same basis as all other Network Resources. energy market 6

7 Pro Forma Standard GIP Highlights Material Modifications Changes to proposed generating facility that result in new request and loss of existing queue position TP has discretion to determine if proposed changes are Material Modifications during interconnection studies Explicitly allowed changes deemed not Material Modifications Prior to executing System Impact Study (SIS) Agreement - Up to 60% decrease in capacity, changes to configuration, technical parameters and transformer impedance Prior to executing Facilities Study (FS) Agreement Up to an additional 15% decrease in capacity, changes to configuration, technical parameters and transformer impedance energy market 7

8 Pro Forma Standard GIP Highlights Interconnection Studies (Individually or Clustered) Feasibility Study (FEAS) IC pays $10,000 deposit / commits to pay actual study costs TP expected to complete study in 45-days rarely accomplished Study Scope includes power flow analysis looking at thermal, voltage and short-circuit impacts, taking into account existing and prior-queued generators System Impact Study (SIS) IC pays $50,000 deposit / commits to pay actual study costs TP expected to complete study in 90-days rarely accomplished Study Scope adds stability analysis to the FEAS Study; recognizes ER vs. NR Facilities Study (FS) IC pays $100,000 deposit / commits to pay actual study costs TP expected to perform 90-day or 180-day version at IC s request rarely accomplished Study Scope to include detailed design of Network Upgrades and TP Interconnection Facilities energy market 8

9 Pro Forma Standard GIP Highlights Responsibility for Cost of new/upgraded facilities Interconnection Facilities Developer elope pays 100% Network Upgrades Developer pays 100% of facilities that would not be built but-for the need to interconnect the developer s generating facility Developer receives a refund of amounts paid for network upgrades: Via transmission service payment credits for initial 5-yrs Balance refunded regardless of transmission service payments over a period not to exceed 20-yrs for COD Refunds to include interest on un-refunded balance energy market 9

10 It Interconnection ti Queue Backlog Spawns Reforms FERC Seeks Queue Reforms December 11, 2007 FERC held a technical ca conference e ce to hear interested parties take on problems with queuing practices; TP s not processing queue within tariff time lines; Complications / delays caused by re-studies when projects withdraw Volume of requests taxing queuing process in some locales; Large number of renewable projects with expedited development schedules not able to be accommodated Implementation of new Capacity Market Rules not accommodated well energy market 10

11 Interconnection Queue Backlog Spawns Reforms FERC Seeks Queue Reforms - continued March 20, 2008 FERC issued an Order in Docket No. AD stating: These backlogs not only deprive generation developers of needed business certainty, they also undermine other important public goals. over the long term, the improved transmission planning required under Order No. 890 result in a more robust transmission system and make it easier to interconnect with the transmission system. Required all RTO/ISO to file reports on the status of their queue management practices and reforms to mitigate the queue backlog. energy market 11

12 Interconnection Queue Backlog Spawns Reforms FERC Seeks Queue Reforms continued FERC encouraged consideration to the following when developing new GIP: Use of cluster studies and allocating cost of common upgrades Cluster groups based on other attributes other than timing of request Increasing staff to perform studies, including use of consultants Eliminating the Feasibility Study Alternative basis for prioritizing queue requests such as first-ready / first served instead of first-come / first served approach Increasing requirements to obtain and maintain a queue position Impact on small projects Impact on existing requests, especially late-stage existing requests vs. future new requests energy market 12

13 ISO NE Standard GIP Highlights Pre-Queue Reforms Queue Processing based on First-Come, First-Served (FC-FS) Studies performed individually/serially, not Clustered FEAS and FS - optional Study Deposits / Timing: FEAS = $10k of est. monthly study costs / 45-days SIS = $50k or est. monthly study costs / 90-days FS = $100k or est. monthly study costs / days N0 distinction between ER & NR all are NR Interconnection Studies based on Minimum Interconnection Standard (MIS ) per FERC Order energy market 13

14 ISO NE Standard GIP Highlights Pre-Queue Reforms Continued Generator pays 100% of all Transmission Upgrades + on-going O&M with no opportunity for any refund No transmission charges for wheeling output Same Material Modification and Suspension language as Pro Forma April 2008 Queue contained 104 interconnect t requests 13,400MW energy market 14

15 ISO NE Standard GIP Highlights Queue Reforms Filed Oct / Effective Feb. 1, 2009 Most reforms related to integration of Forward Capacity Market (FCM) Rules with GIP: Distinguishes ER vs. NR (referred to as NR vs. CNR in New England) First-Cleared / First-Served Queue Processing for CNR projects Additional group studies for CNR demonstrating interconnection possible by start of FCM Capability Commitment Period and intra-zonal deliverability Additional Non-refundable Deposits and new Milestone Requirements to obtain/maintain queue position as CNR Long-Lead Facility Treatment availability energy market 15

16 ISO NE Standard d GIP Highlights ht Queue Reforms continued Other Non-FCM Reforms -increased deposits / more stringent milestones: Deposits: Application = $50k + proof of site control or add l non-refundable $10k FEAS = 100% of estimated study costs paid at execution of study agreement SIS = >100% est. study cost or $250k; or < 100% est. study cost or $50k + proof of having all Major Permits and at least $250k of At-Risk expenditures FS = >25% est. study cost or $250k; or > 100% est. 1 st mo. study cost or $100k + proof of having all Major Permits and at least $250k of At-Risk expenditures or 25% of total study costs Milestone reforms more stringent site control; insurance; payment schedules March 2010 queue 93 generator interconnect requests 18,700MW Meaningful / Effective Improvements? Distinct process for recognizing CNR vs. NR energy market 16

17 PJM Standard GIP Highlights Pre-Queue Reforms Queue Processing based First-Come, First-Served (FC-FS) within biannual Queue Submittal Windows Studies may be performed in Clusters Study Deposits / Time (Study costs allocated among clustered projects) FEAS = $10k / days beginning as close of window,.i.e. 8-9 months SIS = $50k / days FS = >$100k or est. 3-months study costs / no specified time to complete Distinction between ER & NR by requiring demonstration of deliverability for NR energy market 17

18 PJM Standard GIP Highlights Pre-Queue Reforms Continued Generator pays 100% of all Transmission Upgrades + Interconnection Facilities (IF) and on-going IF-related O&M with no opportunity for any refund Upgrade Costs allocated on stand-alone basis based on Queue Position No transmission charges for wheeling output Material Modification similar to Pro Forma but allows up to > 20% or 50MW capacity decrease up to execution of interconnect agreement Suspension language same as Pro Forma Use of Interim Interconnection and Construction Services Agreements used to expedite process April 2008 queue 360 generator interconnect requests - 84,164MW energy market 18

19 PJM Standard GIP Highlights Queue Reforms Developed in response to the Dominion Settlement Agreement in Docket No. EL08-36 involving capacity rights of an existing Generating Facility Increased Queue Submittal Windows from 2 per year to 4 per year Increased Deposit Requirements: At Request / FEAS = Initial $100-$200/MW up to $100k + Base $10k-$30k non- refundable. Study to be completed 90-days after close of submittal window SIS = $50k non-refundable + >$100-$300/MW; less for <20MW; study to commence 6-months after close of submittal window and completed in 120-days. (Non-Refundable amounts become refundable if SIS 60-days late) FS = $100k refundable; less for <20MW. Est. time to complete = 180-days Mandatory Scoping Meetings explicitly waive, hold or be terminated Projects not ready to proceed may opt out and be studied in next Queue Window energy market 19

20 PJM Standard GIP Highlights Queue Reforms Continued Network Upgrade Cost Allocation: excluding stability-related upgrades, and upgrades <$5 million, allocated among all Clustered Projects based on distribution factors (DFAX) >$5 million based first on queue position, then on DFAX for stability determined in Facilities Study on individual project basis cost reallocation of prior queue-related upgrades limited it to upgrades > $5 million and not more than 5-yrs from date of ISA for project first identified Current queue 408 generator interconnect requests 94,315MW Meaningful improvements? Additional queue submittal windows Partial refund of study funds for late SIS completion Limit on new projects being allocated cost of prior upgrades energy market 20

21 SPP Standard GIP Highlights Pre-Queue Reforms Queue Processing based First-Come, First-Served (FC-FS) Studies performed individually/serially, not Clustered Application & Study Deposits / Time Application = $10k + proof of site control or add l $10k FEAS (Optional) = $10k / 45-days per tariff; actual experience is 5-7 months SIS = $50k / 90 days per tariff; actual experience 6 months or more FS = >$100k or est. monthly study costs / days Distinction between ER & NR by requiring demonstration of deliverability for NR energy market 21

22 SPP Standard GIP Highlights Pre-Queue Reforms Continued Generator pays 100% of all Transmission Upgrades + and Interconnection Facilities (IF) and on-going IF-related O&M Upgrade Costs allocated on stand-alone basis based on Queue Position Transmission Service (TS) required for delivery of output Network Upgrade costs reimbursed via TS Credits for initial 5-yrs with balance refunded regardless of TS Credits within 20-yrs. Material Modification and Suspension same as Pro Forma April 2008 queue 106 generator interconnect requests 26,811MW. 94 were wind projects totaling 24,473MW June 2009 queue 255 generator requests-57,000mw, 50,000MW of which were wind. energy market 22

23 SPP Standard GIP Highlights Queue Reforms Sept. 09 SPP implemented transitional MW Segment Cluster Studies to clear back log prior to implementation of other/permanent reforms Two 15,000MW Clusters Upgrade costs allocated pro rata within each cluster without regard to queue position Permanent Reforms filed June 1, 2009 include: Fast-track option for qualifying projects Stringent suspension provisions Increased Deposit Fees New 4-Tier Study Queue including a preliminary queue and non-binding technical analysis option for speculative projects Project Readiness Milestones required to enter final queue energy market 23

24 SPP Standard GIP Highlights Queue Reforms Continued Fast-Track Option First-Ready, First Served (FR-FS) FS) Suspensions limited to 18-months, significant financial security for construction of shared network upgrades without delaying construction Permanent Adoption of Cluster Studies as the norm 4-Tier Study Queue: Interconnection Feas Study Queue (IFS Queue) - Optional / 90-day submittal window /lowest priority queue / Queue Priority within IFS Queue based on FC/FS. No re-studies for withdrawal al Preliminary Interconnection SIS Queue (PISIS Queue) Optional / 180-day window submittal / Queue priority within PSIS Queue based on FR-FS; Priority > IFS < DISIS. No re-study for withdrawals Definitive Interconnection SIS Queue (DISI Queue) - mandatory milestones / superior queue priority to IFS or PISIS / FR-FS priority within DISIS Queue Definitive Interconnection FS (DIFS) same mandatory milestones and queue priority as DISIS energy market 24

25 SPP Standard d GIP Highlights ht Queue Reforms Continued Application & Study Deposits / Time: Application Request = $10k + proof of site control or move to IFS Queue IFS Queue = $10k / 90-days for requests submitted in same 90-day window PISIS = Proof of Site Control + $40k (<100MW); $60k (>100<800MW); $90k (>800MW). study to commence 6-months after close of submittal window and completed in 120-days. (Non-Refundable amounts become refundable if SIS 60-days late) DISIS = Proof of Site Control & Adequacy + $75k (<75MW) $150k (>75MW); Deposit set at 2X cost and non-refundable if withdrawn day submittal window and 120-day study period Facilities Study (FS) = Additional security covering cost of Network Upgrades; Est. time to complete: draft reports 90-days; final reports: 8- months Study cost allocation: 50% per project / 50% pro rata MWs energy market 25

26 SPP Standard d GIP Highlights ht Queue Reforms Continued Current Queue updated March 12, 2010 shows the Active Queue containing 232 requests totally more than 41.5 GW of which 189 are wind projects totaling 33.2 GW. Eliminating those that state they are in commercial operation, total t requests decline to about 182 requests and 30.1 GW energy market 26

27 And How About MISO MISO filed its proposed GIP Queue Reforms June 26, 2008 in Docket No. ER which FERC approved effective August 25, MISO s new GIP adopted many of FERC s suggested changes. Results to-date continuing uncertainty in terms of scheduling, network upgrades required, and cost responsibility. Case in point Group 5 transitional group 37 projects totaling over 2,765MW (originally a few have withdrawn) So-called FINAL SIS published Oct. 2007; many additional studies followed with last Facilities Study just recently completed No projects yet connected / none, if any, likely to for years to come Group 5 studies used for purpose of larger regional system planning Cost allocation changed mid-stream poses significant cost increases $700 million 220 mile 345kV line allocated to 19 generators at last minute No workable solution in sight. FERC yet to provide any useful, meaningful guidance. energy market 27

28 MISO Standard d GIP Highlights ht Queue Reforms MISO Queue reforms included: d First-ready / first served prioritization Increased requirements to obtain and maintain queue position, i.e. higher deposits (including significant non-refundable portions) and additional milestones which must be strictly adhered to Cluster Study groups no longer based solely on queue position timing/order. Qualitative Feasibility Studies for determining queue processing Possible Fast-Track based on Feasibility Study Results Introduction of Temporary Interconnection Agreement Refinements to Material Modification provisions Limited opportunity for Suspensions Eliminated distinction of Generators < / > 20MW energy market 28

29 MISO Standard d GIP Highlights ht Queue Reforms Continued MISO s GIP revised to include 4 new distinct t phases: 1. Pre-Queue Phase voluntary pre-application session with MISO to understand GIP, understand obligations, how to complete application. 2. Application Review Phase MISO determines whether application is complete; once complete initial queue position is established and initial screening-level Feasibility Study including up to 3 POIs, is scheduled. 3. System Planning & Analysis Phase (SPA) Initial System Impact Study is performed during this phase likely to be a Cluster Study. Depending on Feasibility Study results, projects could skip SPA Phase. 4. Definitive Planning Phase (DPP) Re-studies of System Impact Studies and Facilities Studies are performed during this phase. Optional Study available to developers prior to submitting a formal application. energy market 29

30 MISO Standard d GIP Highlights ht Queue Reforms Continued Queue Position Prioritization: iti Initial queue position based on time of completed application Determines order in which Feasibility Studies are performed After Feasibility Study, queue processing / prioritization is based on Feasibility Study Results and achievement of Milestones Cluster System Impact Studies (SIS): Initial i SIS performed during SPA Re-study of SIS performed during DPP Generators included based on relative electrical proximity and initial queue position Withdrawn generators may be replaced with other similar generators pending in the queue but not yet included in an SIS, with unspent deposit of withdrawn generator being used to off-set study costs energy market 30

31 MISO Standard d GIP Highlights ht Queue Reforms Continued New Deposit Requirements Two Deposits are now required; one at time of Application and another at the time of entering the DPP (prior procedures required 4-deposits) Deposits include significant non-refundable amounts and are based on maximum capacity of proposed generating project Application Deposit 0-5MW $15k 6-20MW $25k 21-50MW $35k MW $65k MW $95k > 1000MW $125k Incl. Non-Refundable $5k Application Fee Additional $100k required w/o site control DPP Deposit based on 2X Study Cost w/ excess forfeited upon withdrawal from queue, or used to support construction. DPP Deposit 0-5MW $55k 6-20MW $125k 21-50MW $185k MW $275k MW $325k MW $425k MW $535k > 1000MW $645k energy market 31

32 MISO Standard d GIP Highlights ht Queue Reforms Continued New Milestone Requirements new GIP includes new mandatory Milestones which must be achieved in order to advance through the various phases of the GIP. M1 Milestones during Application Phase M2 Milestones at fist stage of DPP M3 Milestones at second stage of DPP New Milestones include Technical, Non-Technical and Financial. Financial Milestones are in addition to Deposits. energy market 32

33 MISO Standard d GIP Highlights ht Queue Reforms Continued MI Milestones for Application to be complete, all of the following Technical Milestones must be achieved / satisfied: M1 Technical Milestones Generic Study Model Point of Interconnection (POI) Impedance from collector substation to POI Technical data to run studies One-line diagram Generator output (MW) Step-up transmission data Simplified stability model. Location of the POI in study model. Impedance of radial line from GSU to POI. Data to run studies, i.e. sequence impedance, generator reactance, saturation curve, etc. (as applicable). Diagram of Generating Facility showing Interconnection Facilities and POI. Seasonal Gross and Net MW output Specs. of the GSU energy market 33

34 MISO Standard GIP Highlights Queue Reforms Continued M2 Milestones Definitive Planning Entry Milestones. Customer must meet all of the technical milestones, plus any two of the non-technical milestones. M2 Technical Milestones Detailed Stability Model Definitive Point of Interconnection (POI) Definitive one-line diagram Actual stability model. Final opportunity to select final POI. Any subsequent material changes will resulting in withdrawal. Definitive Generator output (MW) Any subsequent material changes will resulting in withdrawal. energy market 34

35 MISO Standard GIP Highlights Queue Reforms Continued M2 Milestones Milestones needed for SPA and Definitive Planning Phase Entry. Customer must meet all of the technical milestones, plus any two of the non technical milestones. (Continued) M2 Non-Technical Milestones (meet any two or their substitutes at Definitive Planning Entry) Primary M2 Milestones Proof that Turbines are on order Proof of submission of all required permits Approval of State Regulatory Commission Board Approval or approval of highest level of approval authority per its governance M2 Deposit (D2) Substitute M2 Milestones Deposit or LOC = 1-month transmission charge due at SPA (Refundable upon M3 Milestones or Withdrawal Deposit or LOC = 1-month transmission charge due at SPA (Refundable upon M3 Milestones or Withdrawal Deposit or LOC = 1-month transmission charge due at SPA (Refundable upon M3 Milestones or Withdrawal Deposit or LOC = 1-month transmission charge due at SPA (Refundable upon M3 Milestones or Withdrawal NA energy market 35

36 MISO Standard d GIP Highlights ht Queue Reforms Continued M3 Milestones Milestones needed for continuing Definitive Planning Phase. Customer must initially meet one of the three non-technical milestones. There are no Technical Milestones in M3. M3 Non-Technical Milestones (meet any one at initial M3 submission). Financial Security Deposit or LOC = est. cost of Network Upgrades (Refundable upon execution of GIA) Executed PPA or Office Attestation Execution of PPA or statement of officer attesting that Generating Facility is included in state resource adequacy plan Turbine Order Demonstration that turbines have been ordered energy market 36

37 MISO Standard GIP Highlights Queue Reforms Continued Suspensions New GIP include limited opportunity for Suspensions Suspensions permitted for Force Majeure only Non-refundable deposit equal to greater of cost of Network Upgrades or $5M Network Upgrade engineering / construction will continue on schedule unless a regulatory order states otherwise energy market 37

38 MISO Standard GIP Highlights Queue Reforms Continued To deal with Common Use Upgrades (CUU) MISO introduces new Multi- Party Facility Construction Services Agreement (MPFCA) Contract for construction and payment of CUU Parties include MISO, TO responsible for construction of CUU and all generators deemed responsible for need and cost of CUU Generators must execute MPFCA or are terminated t Generators must provide financial security covering their respective total cost responsibility for CUU at least 30-days prior to TO s need for funds If Generators withdraw/terminate, costs shift to remaining generators Withdrawing/terminated generators lose deposit/financial security unless cause for withdrawal is due to cost increase > 25% energy market 38

39 MISO Standard d GIP Highlights ht And the Uncertainty / Unworkable continues July 2009 MISO filed interim i revised generator interconnection- ti related network upgrade cost allocation which FERC approved Oct Prior methodology allocated 50% of network upgrades to generators serving load in MISO, except for ATC/ITC network upgrades which were fully refunded; New methodology allocates generator interconnection-related network upgrades as follows: 90% for network upgrades > 345kV 100% for network upgrades < 345kV Interim method in effect until July 2010 when MISO is required to file new proposal for permanent methodology Premise of need for new method is threat of OTP and MDU withdrawing from MISO due to prior cost allocation method energy market 39

40 MISO Standard d GIP Highlights ht And the uncertainty / unworkable continues FERC approved interim solution without evidence to support that OTP s and MDU s costs would be reduced as stand-alone utilities MISO and several committees working to develop new methodology that goes beyond interconnection costs, and includes transmission service rate design Main themes/debates should generators pay on-going transmission charges and how to ensure the right load pays for costs allocated to load What facilities costs should be in a Regional / Sub-regional/Local rate MISO seems intent on proposing an Injection-Withdrawal methodology despite independent market report noting negative impacts to market efficiencies from proposal Generators favor Highway/Byway method under consideration in SPP energy market 40

41 SO Much for Standardization Conclusions: FERC s implementation of GIP in RTO/ISOs has resulted in not-so standard GIP Queue Reforms have not been very effective at meeting objectives Reforms appear to focus more on creating / increasing barriers to entry Some RTO/ISO GIP seem to work better than others There are some real challenges ahead for generation development in MISO due to business uncertainty and signs of potentially higher cost for transmission access FERC, State Commissions and ISO s need to understand that business certainty is critical to a vibrant and efficient market for generation development to occur energy market 41

42 For further information contact: Steven S. Garwood PowerGrid Strategies, LLC (207) or energy market 42

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012 Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new

More information

Queue Management Process

Queue Management Process SPP and MISO Queue Management Process By: Noumvi G. Ghomsi Utility Engineering Specialist II Missouri Public Service Commission 200 Madison Street Jefferson City, MO 65102 (573) 526-9681 Noumvi.Ghomsi@psc.mo.gov

More information

Interconnection of New Generation Facilities

Interconnection of New Generation Facilities Interconnection of New Generation Facilities Jennifer Heintz Chief Counsel Public Service Commission of Missouri February 7, 2013 Abu Dhabi, U.A.E. Generation and Transmission in the United States In the

More information

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES 303-571-2794 1 1 FIRE SAFETY Proceed out of the building to the designated meeting location. Do not use the elevators. Stairs are located

More information

Small Generator Interconnection Procedures (SGIP) Customer Guide

Small Generator Interconnection Procedures (SGIP) Customer Guide Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission

More information

An Introduction to Interconnection Policy in the United States

An Introduction to Interconnection Policy in the United States An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator

More information

Advancing Renewable Alternatives

Advancing Renewable Alternatives Advancing Renewable Alternatives FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 Abigail Krich President, Boreas Renewables About Boreas Renewables

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016 Generation Process SWANA Spring Conference Atlantic City, NJ April 18, 2016 www.pjm.com PJM process is FERC Pro Forma Customer enters queue to sell output into PJM wholesale market (regardless of size)

More information

PG&E s WDT Interconnection Reform Principles Document

PG&E s WDT Interconnection Reform Principles Document PG&E s WDT Interconnection Reform Principles Document The purpose of this document is to lay out PG&E s high-level objectives and to discuss the underlying principles behind the interconnection process

More information

Transmission Expansion and Interconnection Manual. June 2017

Transmission Expansion and Interconnection Manual. June 2017 MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection

More information

Small Generator Interconnection Procedures

Small Generator Interconnection Procedures Small Generator Interconnection Procedures Thinh Nguyen Senior Manager, Interconnection Projects ICAP WG/MIWG/PRLWG September 28, 2018 Topics Determining the Applicable Interconnection Process for ERIS

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Leslie Padilla Submitted by Company Date Submitted lpadilla@semprageneration.com

More information

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business

More information

Rule 21 Tariff / Process Overview 6/17/2015

Rule 21 Tariff / Process Overview 6/17/2015 Rule 21 Tariff / Process Overview 6/17/2015 Rule 21/WDAT Overview Rule 21 Jurisdiction CPUC FERC WDAT Applicability Generator/storage retail interconnections (transmission or distribution); retail solicitations

More information

Public Service Company of Colorado Generation Interconnection Queue Reform Post-Meeting Stakeholder Comment Form

Public Service Company of Colorado Generation Interconnection Queue Reform Post-Meeting Stakeholder Comment Form Public Service Company of Colorado Generation Interconnection Queue Reform Post-Meeting Stakeholder Comment Form Thank you for participating in the May 18, 2018 stakeholder meeting. Please use this form

More information

What You Need to Know Before Requesting Interconnection

What You Need to Know Before Requesting Interconnection Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection

More information

Integration of Transmission Planning and Generation Interconnection Procedures

Integration of Transmission Planning and Generation Interconnection Procedures Integration of Transmission Planning and Generation Interconnection Procedures (TPP-GIP Integration) Revised Straw Proposal September 12, 2011 Market and Infrastructure Development Integration of Transmission

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Subject: Generation Interconnection Procedures Phase 2 ( GIP 2 ) Submitted by Company Date Submitted Rob Longnecker rob@clean-coalition.org 415-787-3080 Clean Coalition June

More information

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners

More information

Cluster Study Process

Cluster Study Process Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system

More information

SCHEDULE 12 Transmission Enhancement Charges

SCHEDULE 12 Transmission Enhancement Charges SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. One or more of the Transmission Owners may be designated to construct and own and/or finance Required

More information

Bonneville Power Administration Current Transmission Perspectives

Bonneville Power Administration Current Transmission Perspectives Bonneville Power Administration Current Transmission Perspectives WSCC Operating Committee September 26, 2011 Lauren Nichols-Kinas lnichols@bpa.gov 1 BPA: A Brief Description Bonneville Power Administration

More information

regulations of the Federal Energy Regulatory Commission ( Commission or FERC ), 2 PJM

regulations of the Federal Energy Regulatory Commission ( Commission or FERC ), 2 PJM PJM Interconnection Valley Forge Corporate Center 955 Jefferson Avenue Norristown, PA 19403-2497 Jennifer H. Tribulski Senior Counsel 610.666.4363 fax 610.666.8211 tribuj@pjm.com Filing Via etariff Honorable

More information

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Program Overview August 8, 2013 1 ReMAT Schedule Date (2013) July 23 July 24 August 8 August 16 TBD TBD October 1 November 1 Event E-PWF &

More information

The State of Wind Energy in New England

The State of Wind Energy in New England JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New

More information

Nancy Rader, Executive Director Dariush Shirmohammadi, Transmission Advisor California Wind Energy Association. August 9, 2011

Nancy Rader, Executive Director Dariush Shirmohammadi, Transmission Advisor California Wind Energy Association. August 9, 2011 Comments of the California Wind Energy Association on Integration of Transmission Planning and Generation Interconnection Procedures (TPP-GIP Integration) Straw Proposal (7/21/2011) Nancy Rader, Executive

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Submitted by Company Date Submitted Kevin T. Fox Keyes & Fox, LLP 436 14 th

More information

Wholesale DER Interconnections

Wholesale DER Interconnections Wholesale DER Interconnections David Egan / Susan McGill Manager, Interconnection Projects / Analysis July 30, 2018 Distributed Energy Resources Subcommittee Agenda Jurisdiction Pre-Applications: Formal

More information

Generator Interconnection Procedures Overview

Generator Interconnection Procedures Overview Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution

More information

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016 PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session June 3, 2016 By Vilna Gaston Associate General Regulatory Counsel PSEG Services Corporation

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges. SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become

More information

PJM Queue Position Establishment Background and Support for Problem Statement

PJM Queue Position Establishment Background and Support for Problem Statement PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction

More information

PJM s Implementation of Order 845

PJM s Implementation of Order 845 PJM s Implementation of Order 845 Susan McGill Manager, Interconnection Analysis Michelle Harhai PJM Legal Compliance Filing Update On September 24, 2018, the Edison Electric Institute on behalf of its

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

Revised Transmission Planning Process. Complete Final Proposal

Revised Transmission Planning Process. Complete Final Proposal Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission

More information

Generator Interconnection Process. Wholesale Distribution Overview

Generator Interconnection Process. Wholesale Distribution Overview 1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

PJM Strawman Proposal

PJM Strawman Proposal PJM Strawman Proposal Special MIC DER November 17, 2017 DER Proposal: General Overview 1. Not Demand Response, not Generation: proposal is for 3rd ruleset for DER. DER can choose to participate as either

More information

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

163 FERC 61,146 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

163 FERC 61,146 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 163 FERC 61,146 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Kevin J. McIntyre, Chairman; Cheryl A. LaFleur, Neil Chatterjee, Robert F. Powelson, and Richard Glick.

More information

Summary of Submitted Comments

Summary of Submitted Comments Stakeholder Process: Generator Interconnection Procedures Phase 2 Summary of Submitted Comments Stakeholders have submitted four rounds of written comments to the ISO on the following dates: Round One:

More information

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013

MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013 MISO MODULE B TRANSMISSION SERVICE MISO I INTRODUCTION The Transmission Provider shall provide Point-To-Point and Network Integration Transmission Service pursuant to the applicable terms and conditions

More information

Re: Large Generator Interconnection Procedures (LGIP) - Generator Queuing Practices Docket No. AD

Re: Large Generator Interconnection Procedures (LGIP) - Generator Queuing Practices Docket No. AD California Independent System Operator Corporation December 13, 2007 Via Electronic Filing The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

CAISO Resource Adequacy Deliverability for Distributed Generation

CAISO Resource Adequacy Deliverability for Distributed Generation CAISO Resource Adequacy Deliverability for Distributed Generation Clean Coalition comments on Compliance with FERC Order issued 11/16/12 Kenneth Sahm White April 10, 2013 I. Introduction The Clean Coalition

More information

Financial Transmission Rights

Financial Transmission Rights PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM

More information

Six Cities Comments Generator Interconnection Driven Network Upgrade Cost Recovery Initiative. Revised Straw Proposal

Six Cities Comments Generator Interconnection Driven Network Upgrade Cost Recovery Initiative. Revised Straw Proposal Six Cities Comments Generator Interconnection Driven Network Upgrade Cost Recovery Initiative Submitted by Company Date Submitted Meg McNaul mmcnaul@thompsoncoburn.com 202-585-6940 Bonnie Blair bblair@thompsoncoburn.com

More information

TPP-GIP Integration Proposal November 30, 2011

TPP-GIP Integration Proposal November 30, 2011 TPP-GIP Integration Proposal November 30, 2011 Major Elements of Proposal Demand-Based Planning of Network Upgrades in the TPP Synchronize GIP, TPP and the LSE Procurement Processes Allocation of Deliverability

More information

Broader Regional Markets Report

Broader Regional Markets Report Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting June 20, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement

More information

January 9, Tariff Amendment to Implement 2018 Expedited Interconnection Process Enhancements

January 9, Tariff Amendment to Implement 2018 Expedited Interconnection Process Enhancements California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 9, 2018 Re: California

More information

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS Program Guide TABLE OF CONTENTS Introduction... 2 Purpose... 2 About CHP... 2 Program Description... 2 Call for CHP Projects... 3 Participant Webinar...

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager:

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: FAQs from 2017-08-30 Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: PSCo2017AllSource@xcelenergy.com Q:

More information

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14

More information

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report

September 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report September 30, 2011 The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Louisville Gas & Electric Company, et al., Docket No.

More information

Virtual Workshop on PJM ARR and FTR Market 2017/2018

Virtual Workshop on PJM ARR and FTR Market 2017/2018 Virtual Workshop on PJM ARR and FTR Market 2017/2018 PJM State & Member Training Dept. Webex February 10, 2017 PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information

More information

California ISO Revised Draft Final Proposal IPE 2015

California ISO Revised Draft Final Proposal IPE 2015 Stakeholder Comments Template Submitted by Company Date Submitted Rachel Gold, Policy Director (Rachel@largescalesolar.org) Susan Schneider, Consultant (Schneider@phoenix-co.com) Large-scale Solar Association

More information

First Solar Proposal Integration of Transmission Planning Process and Generation Interconnection Procedures (TPP-GIP Integration)

First Solar Proposal Integration of Transmission Planning Process and Generation Interconnection Procedures (TPP-GIP Integration) First Solar Proposal Integration of Transmission Planning Process and Generation Interconnection Procedures (TPP-GIP Integration) Introduction The CAISO s Revised Straw Proposal of September 12, 2011 is

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

83D Q & A Set #8. Answer: Please see response to question 117.

83D Q & A Set #8. Answer: Please see response to question 117. 83D Q & A Set #8 (15) Section 2.2.1.8 Please confirm that bidding projects are only required to demonstrate the ability to meet the requirements for Forward Capacity Auction Qualification in their proposal.

More information

Transmission & Ancillary Services Formula Rates. Public Information Forums November 19, Omaha, NE November 20, Fargo, ND

Transmission & Ancillary Services Formula Rates. Public Information Forums November 19, Omaha, NE November 20, Fargo, ND Transmission & Ancillary Services Formula Rates Public Information Forums November 19, 2014 - Omaha, NE November 20, 2014 - Fargo, ND Introductions Lloyd Linke Operations Manager Gary Hoffman Attorney-Advisor

More information

ATTACHMENT DD. Reliability Pricing Model

ATTACHMENT DD. Reliability Pricing Model OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.

More information

Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection.

Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection. Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection September 5, 2007 The California Wind Energy Association ( CalWEA ) appreciates

More information

SECTION 6 - ANCILLARY SERVICE MARKETS

SECTION 6 - ANCILLARY SERVICE MARKETS 2010 Quarterly State of the Market Report for PJM: January through March ANCILLARY SERVICES 6 SECTION SECTION 6 - ANCILLARY SERVICE MARKETS The United States Federal Energy Regulatory Commission (FERC)

More information

Generation Interconnection System Impact Study Report

Generation Interconnection System Impact Study Report MARYLAND PUBLIC SERVICE COMMISSION OFFSHORE WIND ANALYSIS 3.2.1 Generation Interconnection System Impact Study Report Prepared for The Maryland Public Service Commission January 30, 2015 Axum Energy Ventures,

More information

PJM Manual 14A Updates

PJM Manual 14A Updates PJM Manual 14A Updates Presented by Joseph Hay Project Manager, Interconnection Projects Presented to PJM Planning Committee June 8, 2017 Manual 14A Updates: Interconnection Projects Reasons for Updates:

More information

NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011

NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011 NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes November 2011 Proposed Tariff Changes More detailed Intra-hour scheduling language to be added Revisions to Attachment N (Large Generator

More information

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:

More information

Deliverability for Distributed Generation. Proposal for Complying with 11/16/12 FERC Order

Deliverability for Distributed Generation. Proposal for Complying with 11/16/12 FERC Order Deliverability for Distributed Generation Proposal for Complying with 11/16/12 FERC Order Lorenzo Kristov, Market & Infrastructure Policy Stakeholder Call, April 3, 2013 Schedule for remaining activities

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets

More information

CURRENT FEDERAL AND REGIONAL ELECTRIC POLICY ISSUES FOR THE ILLINOIS COMMERCE COMMISSION

CURRENT FEDERAL AND REGIONAL ELECTRIC POLICY ISSUES FOR THE ILLINOIS COMMERCE COMMISSION CURRENT FEDERAL AND REGIONAL ELECTRIC POLICY ISSUES FOR THE ILLINOIS COMMERCE COMMISSION Randy Rismiller Manager, Federal Energy Program Illinois Commerce Commission 1 THE FEDERAL ENERGY REGULATORY COMMISSION

More information

Reliability Pricing Model (RPM) DRAFT Business Rules

Reliability Pricing Model (RPM) DRAFT Business Rules Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional

More information

December 11, 2013 VIA ELECTRONIC FILING

December 11, 2013 VIA ELECTRONIC FILING VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No. ER14- -000 Compliance

More information

Status Update Assessment of ICT/RTO Options and Issues

Status Update Assessment of ICT/RTO Options and Issues JULY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT WORK IN PROGRESS Session 5 Status Update Assessment of ICT/RTO Options and Issues Kurt Castleberry July 15, 2010 1 JULY 2010 PRELIMINARY TECHNICAL CONFERENCE

More information

All Source Request for Proposals Interim Summary

All Source Request for Proposals Interim Summary All Source Request for Proposals Interim Summary Introduction and Request for Proposal Overview Northern Indiana Public Service Company ( NIPSCO ) does business in the State of Indiana as a regulated public

More information

Generator Interconnection Developer Perspective. February 28, 2019

Generator Interconnection Developer Perspective. February 28, 2019 Generator Interconnection Developer Perspective February 28, 2019 DENNIS DESMARAIS, PE Energy industry entire career PGE 17 years PacifiCorp 7 years Generator Interconnection Queue Management Transmission

More information

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011

Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration. March 7-8, 2011 Midwest ISO EIM Start-up and Exiting Issues Todd Ramey, Executive Director Market Administration March 7-8, 2011 Agenda Greetings and Introductions Introduction of the Midwest ISO Overview of the Midwest

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

Comparison Matrix of Existing Capacity Market Attributes: RPM & FCM

Comparison Matrix of Existing Capacity Market Attributes: RPM & FCM Comparison Matrix of Existing Capacity Market Attributes: RPM & FCM RPM / PJM FCM / ISO-NE Qualification for Existing Resources Qualification for New Resources Procurement cycle Commitment Term Base Auction

More information

Illinois State Institute for Regulatory Policy Studies Conference

Illinois State Institute for Regulatory Policy Studies Conference Illinois State Institute for Regulatory Policy Studies Conference Rob Berntsen 10/20/2011 Overview MISO RTOs What We Do FERC Order 1000 MISO s View of FERC Order 1000 MISO s Planning Process MVPs Benefits

More information

Developing a Comprehensive Methodology for Valuating Transmission Impacts for New Generation Developments

Developing a Comprehensive Methodology for Valuating Transmission Impacts for New Generation Developments Developing a Comprehensive Methodology for Valuating Transmission Impacts for New Generation Developments Bhaskar Ray, Southern California Edison Presentation at Transmission Planning Technical Panel Session

More information

Requirements For Generation and Transmission Interconnections

Requirements For Generation and Transmission Interconnections Requirements For Generation and Transmission Interconnections Table of Contents 1.0 INTRODUCTION... 1 2.0 INTERCONNECTION POLICY... 2 3.0 STANDARD INTERCONNECTION PROCESS... 3 3.1 ASSUMPTIONS... 3 3.2

More information

Broader Regional Markets Report

Broader Regional Markets Report Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting February 14, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement

More information

Public Policy and Multi-Driver Projects. RPPTF August 10, 2012

Public Policy and Multi-Driver Projects. RPPTF August 10, 2012 Public Policy and Multi-Driver Projects RPPTF August 10, 2012 Order 1000 Requirements: Planning authority required to consider public policy requirements (defined as legislative and regulatory requirements)

More information

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018 Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process Planning Advisory Committee September 26, 2018 Discussion Today Discuss Stakeholder response to MISO proposed process

More information

MISO-PJM JOA Biennial Review

MISO-PJM JOA Biennial Review MISO-PJM JOA Biennial Review Midcontinent ISO PJM Interconnection 1/20/2016 1. Background On January 4, 2011, Midwest 1 Independent Transmission System Operator, Inc. (MISO) and PJM Interconnection, LLC

More information

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Agenda 1. Overview 2. MISO Update 3. PJM Update 4. JOA Changes Joint Filing 5. Congestion Overlap 6. Next Steps Appendix 2 Overview Purpose Provide

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM pseudo ties

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

OPPORTUNITIES AND BARRIERS. EESI Briefing. June 13, 2008

OPPORTUNITIES AND BARRIERS. EESI Briefing. June 13, 2008 CHARLOTTE CHICAGO GENEVA LONDON LOS ANGELES MOSCOW NEW YORK NEWARK PARIS SAN FRANCISCO WASHINGTON, D.C. RENEWABLE ENERGY AND TRANSMISSION: OPPORTUNITIES AND BARRIERS Raymond Wuslich EESI Briefing June

More information

Mid-Continent Independent System Operator (MISO) Overview. INCMA February 15, 2017

Mid-Continent Independent System Operator (MISO) Overview. INCMA February 15, 2017 Mid-Continent Independent System Operator (MISO) Overview INCMA February 15, 2017 1 2 ISO s/rto s manage flows on the transmission system by directing generator usage 3 North American Electric Grid Operators

More information

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018 PJM Manual 14E: Additional Information for Upgrade and Transmission Revision: 05 Effective Date: April 1, 2018 Prepared by System Planning Division Department PJM 2018 Table of Contents Table of Contents

More information

Capacity Performance Proposal. Summary of Key Design Elements

Capacity Performance Proposal. Summary of Key Design Elements December 3, 2014 This page is intentionally left blank. PJM 2014 1 P a g e Capacity Product Synopsis PJM Interconnection is proposing a single capacity product called Capacity Performance, similar to the

More information