Small Generator Interconnection Procedures (SGIP) Customer Guide
|
|
- Eric Warner
- 6 years ago
- Views:
Transcription
1 Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission and distribution system. The SGIP and all required documents can be found on SCE&G s Open Access Same-time Information System (OASIS). This document is intended as a guide to help the Interconnecting Customer understand the SGIP. Should there be any discrepancies in this document and the SGIP, the SGIP will apply. FACILITY SIZE 1 APPLICABLE TARIFF PROCEDURE > 20 MW LARGE GENERATOR INTERCONNECTION PROCEDURE, PLEASE REFER TO THE SCE&G OASIS FOR MORE INFORMATION. QUALIFYING FACILITIES NOT PARTICIPATING IN THE STATE NET METERING PROGRAM STATE NET METERING PROGRAM >5 MW - 20MW, or <5 MW and ineligible for Fast Track or 10kW inverter process 10kW - up to 5 MW See table below for eligibility SGIP STUDY PROCESS SGIP FAST TRACK PROCESS (IF SCREENS ARE MET, OTHERWISE STUDY PROCESS) 0-10kW SGIP INVERTER PROCESS (IF SCREENS ARE MET, OTHERWISE STUDY PROCESS) 0-100kW PLEASE CONTACT SCE&G RENEWABLES PRODUCTS & SERVICES AT The SGIP contains four processes. The applicable process for each specific interconnection request depends on a number of factors. 1. Pre- Application Process An Interconnection Customer (IC) may submit a formal written request form along with a non-refundable fee of $300 for a pre-application report on a proposed project at a specific site. Transmission Provider (TP) shall provide pre-application report within 20 Business Days (BD) of receipt of the completed request form and payment of the $300 fee. The report need only include existing data. The report is non-binding, does not confer any rights, and the IC must still successfully apply to be interconnected to the TP s system. 1 Interconnection Requests shall be evaluated based on the Small Generating Facility s maximum rated capacity. 1 of 5
2 Customer Guide 2. Fast Track Process For Certified Small Generating Facilities as identified on Fast Track Eligibility table, Technical screens are used to quickly identify reliability and safety issues instead of the interconnection studies. Line Voltage Fast Track Eligibility for Inverter-Based Systems Fast Track Eligibility Regardless of Location Fast Track Eligibility on a Mainline 2 and 2.5 Electrical Circuit Miles from Substation 3 5kV 500kW 500kW 5kV and < 15kV 2MW 3MW 15kV and < 30kV 3MW 4MW 30kV and 69kV 4MW 5MW 3. Study Process Default method consisting of a scoping meeting, a feasibility study, a system impact study and a facilities study. Feasibility Study - This is a preliminary technical assessment of the proposed interconnection. 4 System Impact Study - This is a more detailed assessment of the effect the interconnection would have on the TP s electric system and Affected Systems. Facilities Study This determines what modification to the TP s electric system are needed, includes detailed costs and scheduled completion dates for these modifications. Once IC agrees to fund any needed upgrades, the Parties execute a Small Generator Interconnection Agreement (SGIA ) that, among other things, formalizes responsibility for construction and payment for Interconnection Facilities and Upgrades kw Inverter Process For Certified inverter-based Small Generating Facility no larger than 10kW Small Generator Interconnection Agreement (SGIA) does not apply to requests to interconnect submitted under the 10kW Inverter Process. The TP s evaluation of a project with multiple Points of Interconnection should be performed, using Good Utility Practice (TP has the option to either treat such projects separately for queuing and interconnection study purposes, or as a single Point of Interconnection), based on the project s unique engineering and geographic needs. 2 A main line is a three-phase backbone of a circuit; will typically constitute lines with wire sizes of 4/0 American wire gauge, kcmil, kcmil, 477 kcmil and 795 kcmil. 3 An Interconnection Customer can determine this information about it s proposed interconnection location in advance by requesting a pre-application report pursuant to section In the case an overlap between the feasibility study and the system impact study occurs, it may be reasonable to skip the feasibility study entirely where the distinction may not be enough to require that both studies be performed. 2 of 5
3 Section 1. Pre-Application/Request Note: 1. $300 non-refundable fee for a pre-application report on a proposed project at a specific site. 2. A complete IR includes a completed application form, $1,000 deposit, and demonstration of site control. IC deposit goes towards the cost of the feasibility study. A $500 processing fee is required under the Fast Track Process. A $100 non-refundable application fee is due under the 10kW Inverter Process. 3 of 5
4 Section 2. Fast Track Process (Only available for certified SGF s based on Fast Track eligibility ) 1 Notes: 1. A Certified Small Generating Facility is one that has been certified by a nationally recognized laboratory before the Interconnection Request is submitted to the TP. 2. The Fast Track Process is available to the IC if the SGF meets the requirements of Attachments 3 & 4 of the SGIP, or if the TP has reviewed the design or tested the SGF and is satisfied that it is safe to operate [2.1]. 3. If the IC does not sign the IA, or request that it be filed unexecuted within 30 BD, the IR is deemed withdrawn. 4 of 5
5 Section 3. Study Process Notes: 1. The Scoping Meeting may be omitted by mutual agreement. 2. The TP has 20 additional BD to complete a system impact study requiring review by Affected Systems. 3. In cases where upgrades are required, the facilities study must be completed within 45 BD. In cases where no upgrades are necessary, and the required facilities are limited to Interconnection Facilities, the facilities study must be completed within 30 BD. 4. If the IC does not sign the IA, or request that it be filed unexecuted within 30 BD, the IR is deemed withdrawn. 5. Facilities Study Agreement, Section 9. 5 of 5
Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW)
Appendix C RM13-2-000 (Revised) Small Generator Interconnection Procedures (SGIP) (For Generating Facilities No Larger Than 20 MW) Where to Send Comments on Public Reporting Burden The public reporting
More informationATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)
Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14
More informationAn Introduction to Interconnection Policy in the United States
An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator
More informationLong Island Power Authority Seventh Revised Leaf No. 16
Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that
More informationCluster Study Process
Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO
More informationLong Island Power Authority Seventh Revised Leaf No. 16
Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that
More informationPJM Queue Position Establishment Background and Support for Problem Statement
PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing
More informationWholesale DER Interconnections
Wholesale DER Interconnections David Egan / Susan McGill Manager, Interconnection Projects / Analysis July 30, 2018 Distributed Energy Resources Subcommittee Agenda Jurisdiction Pre-Applications: Formal
More informationGenerator Interconnection Procedures Overview
Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution
More informationSMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)
The revisions to this document take effect August 28, 2006, per FERC Order No. 2006-B issued July 20, 2006, FERC Stats. & Regs. 31,221, which was published in the Federal Register July 27, 2006 (71 FR
More informationGenerator Interconnection Process. Wholesale Distribution Overview
1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation
More informationFirm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.
Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider
More informationInterconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions
After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners
More informationPG&E s WDT Interconnection Reform Principles Document
PG&E s WDT Interconnection Reform Principles Document The purpose of this document is to lay out PG&E s high-level objectives and to discuss the underlying principles behind the interconnection process
More informationATTACHMENT P SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW)
ATTACHMENT P SMALL GENERATOR INTERCONNECTION PROCEDURES (SGIP) (For Generating Facilities No Larger Than 20 MW) Section 1 Application 1.1 Applicability 1.1.1 A request to interconnect a certified Small
More informationNYISO Governance Summary of Sector Definitions and Related Terms
NYISO Governance Summary of Sector Definitions and Related Terms There are five voting sectors that participate in the NYISO s shared governance. They are: Generation Owners Other Suppliers Transmission
More informationRule 21 Tariff / Process Overview 6/17/2015
Rule 21 Tariff / Process Overview 6/17/2015 Rule 21/WDAT Overview Rule 21 Jurisdiction CPUC FERC WDAT Applicability Generator/storage retail interconnections (transmission or distribution); retail solicitations
More informationWhat You Need to Know Before Requesting Interconnection
Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection
More informationDG Interconnection Procedures Collaborative. January 20, 2017
DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process
More informationSmall Generator Interconnection Procedures
Small Generator Interconnection Procedures Thinh Nguyen Senior Manager, Interconnection Projects ICAP WG/MIWG/PRLWG September 28, 2018 Topics Determining the Applicable Interconnection Process for ERIS
More informationeffective date 1/8/01
25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical
More informationNEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems
NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I
More informationTARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201
TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service
More informationQueue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012
Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new
More informationBusiness Practice Manual for Distributed Generation Deliverability. Version
Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:
More informationQ: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager:
FAQs from 2017-08-30 Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: PSCo2017AllSource@xcelenergy.com Q:
More informationIs FERC s Generator Interconnection Policy really conducive to efficient generation development?
By Steven S. Garwood PowerGrid Strategies, LLC March 24, 2010 Is FERC s Generator Interconnection Policy really conducive to efficient generation development? Critical environment for efficient generation
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility
More informationUnion Power Cooperative
Union Power Cooperative INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities of the local
More informationStakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting
Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Submitted by Company Date Submitted Kevin T. Fox Keyes & Fox, LLP 436 14 th
More informationNV Energy s Open Access Transmission Tariff (OATT) Proposed Changes. November 2011
NV Energy s Open Access Transmission Tariff (OATT) Proposed Changes November 2011 Proposed Tariff Changes More detailed Intra-hour scheduling language to be added Revisions to Attachment N (Large Generator
More informationRenewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)
Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Program Overview August 8, 2013 1 ReMAT Schedule Date (2013) July 23 July 24 August 8 August 16 TBD TBD October 1 November 1 Event E-PWF &
More informationTransmission Expansion and Interconnection Manual. June 2017
MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection
More informationFirst Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE
First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 1. ELIGIBILITY FOR SERVICE RETAIL WHEELING SERVICE All Special Contract Customers, and all Schedule 48 Customers as of March 9, 2001,
More informationSMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS)
SMALL GENERATION SYSTEM APPLICATION (10 kw OR LESS) This application, terms, and conditions, and Interconnection Agreement is for Xcel Energy customers requesting the installation of a small generation
More informationPJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018
PJM Manual 14E: Additional Information for Upgrade and Transmission Revision: 05 Effective Date: April 1, 2018 Prepared by System Planning Division Department PJM 2018 Table of Contents Table of Contents
More informationENTERGY FACILITY CONNECTION REQUIREMENTS March 2007
ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007 Rev. No. Revision Description Date Reviewed By Approved By 0 Initial Issue 3/1/2007 - TL 1 Cover Page Updated 10/24/2008 - BKW 2 Revised Format, Updated
More informationSCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013
SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:
More informationInterconnection of New Generation Facilities
Interconnection of New Generation Facilities Jennifer Heintz Chief Counsel Public Service Commission of Missouri February 7, 2013 Abu Dhabi, U.A.E. Generation and Transmission in the United States In the
More informationGeneration Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016
Generation Process SWANA Spring Conference Atlantic City, NJ April 18, 2016 www.pjm.com PJM process is FERC Pro Forma Customer enters queue to sell output into PJM wholesale market (regardless of size)
More informationSeptember 30, Louisville Gas & Electric Company, et al., Docket No. ER The ITO s Semi-Annual Report
September 30, 2011 The Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Louisville Gas & Electric Company, et al., Docket No.
More informationNew York Independent System Operator System Reliability Impact Study Criteria and Procedures
New York Independent System Operator System Reliability Impact Study Criteria and Procedures Note: Project Developers are advised that these documents do not address cost allocation Approved by the Operating
More informationDated: April 16, 2002
Central Hudson Gas & Electric Corporation (CHG&E) Application Process for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System Dated: April 16,
More informationTransmission Planning Process Phase 3 Competitive Solicitation
2018 2019 Transmission Planning Process Phase 3 Competitive Solicitation Scott Vaughan Lead Grid Assets Engineer Chris Hillman Lead Grid Assets Engineer April 11, 2019 Transmission Planning Process Phase
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction
More informationRelevant changes will be made to corresponding sections of OA and RAA.
PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 59933-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 59625-E Rule 21 Sheet 7 A. TABLE OF CONTENTS Hh. Smart Inverter Generating
More informationSERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE
Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION NO. 14-RA The
More informationRequest for Proposal
Request for Proposal RFP # SPP-RFP-000001 RFP ISSUED DATE: May 5, 2015 RFP ORIGINATION STUDY: 2015 Integrated Transmission Planning 10-Year Study ( 2015 ITP10 ) Table of Contents Table of Contents... 2
More informationProcedure: Station Power Portfolio Application
Overview Introduction FERC has established a policy that allows a single corporate entity that owns one or more Generating Units to self-supply Station Power over a monthly netting period using Energy
More informationDefining Outage States to Include a Mothball Outage
Defining Outage States to Include a Mothball Outage Emilie Nelson Director, Operations Josh Boles Manager ICAP Market Market Issues Working Group November 7, 2013 2013 New York Independent System Operator,
More informationSmart Grid Small Generator Interconnection Procedure (SGIP) Updates. December 06, 2016
Smart Grid Small Generator Interconnection Procedure (SGIP) Updates December 06, 2016 1 Agenda Background on Interconnection Procedure Modification on SGIP process Interconnection Online Application Portal
More informationCOMBINED HEAT AND POWER CALL FOR CHP PROJECTS PROJECT SUBMISSION FORM
COMBINED HEAT AND POWER CALL FOR CHP PROJECTS PROJECT SUBMISSION FORM THE PURPOSE OF THIS FORM IS TO OBTAIN BASIC INFORMATION TO DETERMINE ELIGIBILITY OF PROJECTS TO RECEIVE INCENTIVES UNDER THE PECO CHP
More informationRequirements For Generation and Transmission Interconnections
Requirements For Generation and Transmission Interconnections Table of Contents 1.0 INTRODUCTION... 1 2.0 INTERCONNECTION POLICY... 2 3.0 STANDARD INTERCONNECTION PROCESS... 3 3.1 ASSUMPTIONS... 3 3.2
More informationSERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And DECADE ENERGY, LLC
Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 952 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE
More informationQueue Management Process
SPP and MISO Queue Management Process By: Noumvi G. Ghomsi Utility Engineering Specialist II Missouri Public Service Commission 200 Madison Street Jefferson City, MO 65102 (573) 526-9681 Noumvi.Ghomsi@psc.mo.gov
More informationCHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X
Fifth Revised Page No. 59 908 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X A. AVAILABILITY Available to members of the Cooperative for purchases of electricity by the Cooperative from qualified
More informationRevised Transmission Planning Process. Complete Final Proposal
Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission
More informationNBP (ATG) IR 01 March 5, Reference: NBP 18.01
NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence
More informationSERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And
Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 970 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE
More information83D Q & A Set #8. Answer: Please see response to question 117.
83D Q & A Set #8 (15) Section 2.2.1.8 Please confirm that bidding projects are only required to demonstrate the ability to meet the requirements for Forward Capacity Auction Qualification in their proposal.
More informationStakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012
Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business
More informationSPP at a Glance. Located in Little Rock. Approximately 600 employees
SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment
More informationISA FORM TEMPLATE (From Attachment O of the PJM Tariff)
ISA FORM TEMPLATE (From Attachment O of the PJM Tariff) Original Service Agreement No. [ ] Effective Date: [ ] (PJM Queue # ) INTERCONNECTION SERVICE AGREEMENT Among PJM INTERCONNECTION, L.L.C. And And
More informationKANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF)
KANSAS CITY POWER & LIGHT COMPANY FERC ELECTRIC TARIFF, THIRD REVISED VOLUME NO. 3 (OPEN ACCESS TRANSMISSION TARIFF) TABLE OF CONTENTS I. COMMON SERVICE PROVISIONS 1 Definitions 1.1 Ancillary Services
More informationPJM Strawman Proposal
PJM Strawman Proposal Special MIC DER November 17, 2017 DER Proposal: General Overview 1. Not Demand Response, not Generation: proposal is for 3rd ruleset for DER. DER can choose to participate as either
More informationRATE DS-4 LARGE GENERAL DELIVERY SERVICE
d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential
More informationUNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY
UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2004/22 30 June 2004 REGULATION NO.
More informationBusiness Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015
Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating
More informationDISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET
DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS FACT SHEET FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION Purpose This fact sheet outlines the steps required for you to undertake an interconnection
More informationENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.
ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application
More informationSERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION
Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE
More informationMothball Outages in Capacity Markets
Mothball Outages in Capacity Markets (preliminary review and summary for working group discussion purposes consult relevant ISO directly for latest and detailed legal requirements) September 13, 2017 NYISO
More informationRenewable Generation - REFIT and Grid Connection
Renewable Generation - REFIT and Grid Connection Ivan Codd Renewable Planning Manager, Asset Management, ESB Networks IrBEA National Bioenergy Conference 4 th February 2015 AGENDA Introduction ESB Networks
More informationFERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION
FERC Electric Tariff 8th Rev. Volume No. 7 Original Sheet No. 1 FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION OPEN ACCESS
More informationGeneration Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction
More informationThe State of Wind Energy in New England
JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New
More informationWater & Energy Consulting Lon W. House, Ph.D.
Water & Energy Consulting Lon W. House, Ph.D. 530.409.9702 (cell) lonwhouse@waterandenergyconsulting.com www.waterandenergyconsulting.com 2795 East Bidwell Street 10645 N. Oracle Rd. Suite 100-176 Suite
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
SECTION II ATTACHMENT H UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Entergy Services, Inc., ) ) on behalf of the Entergy Operating ) Docket No. RT01-75 Companies: Entergy
More informationBC Hydro Open Access Transmission Tariff Effective: April 18, 2013 OATT Terms and Conditions First Revision of Page i
First Revision of Page i BRITISH COLUMBIA HYDRO AND POWER AUTHORITY (OATT) ACCEPTED: ORDERNO.. G_-_59_-_13 First Revision of Page ii Table of Contents Part I. COMMON SERVICE PROVISIONS... 1 1. Definitions...
More informationOPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE
Operating Companies of the Sixth Revised Sheet No. 1 Supersedes Fifth Revised Sheet No. 1 OPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM AEP Texas Central Company AEP Texas
More informationPresentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects
Presentation Title ( Arial, Font size 28 ) Urban Rooftop PV Projects Date, Venue, etc..( Arial, Font size 18 ) 3 rd April 2012 1 Renewable Energy Portfolio of Tata Power Mithapur 25 MW Samana 50 MW Mulshi
More informationGRENLEC s Renewable Standard Offer
GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase
More informationSCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.
SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become
More informationSERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And RADIANT BMT, LLC
Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 1002 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE
More informationOPEN ACCESS TRANSMISSION SERVICE TARIFF OF THE AMERICAN ELECTRIC POWER SYSTEM
Appalachian Power Company as of 4/9/2018 Electric TCS and MBR Open Access Transmission Tariff Effective Date: 06/20/2017 Status: Effective FERC Docket: ER17-01500-000 696 FERC Order: Delegated Letter Order
More informationSCHEDULE 12 Transmission Enhancement Charges
SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. One or more of the Transmission Owners may be designated to construct and own and/or finance Required
More informationInterconnection Application
Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to
More informationMISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE MODULES Effective On: November 19, 2013
MISO MODULE B TRANSMISSION SERVICE MISO I INTRODUCTION The Transmission Provider shall provide Point-To-Point and Network Integration Transmission Service pursuant to the applicable terms and conditions
More informationTransmission Interconnection Requirements. Table of Contents
Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection Agreement III. Facility Requirements IV. Interconnection Initiation I. Introduction A. Purpose and Scope
More informationPACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF
PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY FERC Electric Tariff First Revised Volume 4 Original Sheet No. 1 TABLE OF CONTENTS 1. Preamble and Applicability...4
More informationBusiness Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)
(Modifications Issued on August 11, 2016) 1 List of Contents Introduction Purpose of Document Overview of Transmission Services in New England Definitions Applicable Schedules Services Applicable to these
More informationINTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION
PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection
More informationPJM Business Practices for Hudson Transmission Service
PJM Business Practices for Hudson Transmission Service Table of Contents Page About These Practices... 1 1. Valid Paths for the HUDSON Reservations on the PJM OASIS... 1 2. Acquiring Hudson Service...
More informationBGE Smart Energy Savers Program Combined Heat and Power Program Manual
BGE Smart Energy Savers Program Combined Heat and Power 2015-2017 Program Manual Page 1 of 20 Table of Contents Introduction... 3 Purpose... 3 Goal... 3 ICF s Role... 3 Overview of BGE... 3 BGE Service
More informationATTACHMENT DD. Reliability Pricing Model
OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.
More informationDistributed Generation. Technical Requirements and Interconnection Agreements
Distributed Generation Technical Requirements and Interconnection Agreements February 2005 Table of Contents Section 1: Interconnection Process for Distributed Generation Systems (17 pages) Section 2:
More informationFinancial Transmission Rights
PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM
More informationCapacity Market. Overview RPM Capacity Market. Market Design
Section 4 Capacity Capacity Market Each organization serving PJM load must meet its capacity obligations through the PJM Capacity Market, where load serving entities (LSEs) must pay the locational capacity
More information