Cluster Study Process

Size: px
Start display at page:

Download "Cluster Study Process"

Transcription

1 Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO s Tariff. It is not intended to replace the tariff. PG&E advises customers to become familiar with the applicable tariff and use this tool as a supplement. Generation Services October 27,

2 Overview of Wholesale Generation Process Transmission s Governed by California Independent System Operator Corporation (CAISO) Tariff PG&E s transmission interconnections are for 60 kv and higher All applications must be submitted to the CAISO These slides are pursuant to CAISO Tariff Appendix Y which is subject to the CAISO Distribution s Governed by PG&E s Wholesale Distribution Tariff (WDT) PG&E s distribution voltage level is defined as facilities operating below 60 kv All applications must be submitted to PG&E These slides are pursuant to WDT Attachment I 1

3 Cluster Study Process Distribution Transmission* Tariff Section 4 Section 6 & 7 Applicability Default Default Cluster Window Oct 15 Nov 15 March 1-31 Fee $50k plus $1k/MW (max $250k) Oct 15 Nov 15 March 1-31 $50k plus $1k/MW (max $250k) Study Distribution Timing Distribution Fee Transmission* Timing Transmission* Fee Study Start Phase I 134 CD Included 134 CD Included Jun 1 Phase II 196 CD Included 196 CD Included Jan 15 2 Windows for single annual cluster * Subject to CAISO BD Business Day CD Calendar Day 2

4 Complete Transmission* s Completed Site Plan Diagram Single Line Diagram $50k plus $1k/MW ($250k max) Fee Site Control or In-Lieu Security Distribution s Completed Site Plan Diagram Single Line Diagram $50k plus $1k/MW ($250k max)** Fee Site Control *Subject to CAISO ** Fee can be paid after an Invoice Letter is issued by PG&E 3

5 Transmission* s The Request form can be found on the CAISO website under the heading Cluster Study Process Current process for New Generation s, Effective December 19, 2010 Distribution s to be on Web soon Send Request form along with Site Plan, Site Control, and Single Line Diagram to gen@pge.com or mail to: Generator Services Pacific Gas and Electric Company P.O. Box , Mail Code N7L San Francisco, CA Overnight address: 245 Market Street Mail Code N7L San Francisco, CA GIS will send an Invoice Letter when an Request is received with instructions on a wire payment *Subject to CAISO 4

6 Timeline (Cluster Process) Process Milestone Duration Responsible Party Submit Clock Start Customer Deem Complete or Provide Notice of Outstanding Items 10 BD PG&E or CAISO* Provide outstanding items Notify Customer of whether is Complete Deem Complete 10 BD from Deemed Complete Notification or 20 BD of Close of Window 5 BD after additional info is provided Customer PG&E or CAISO* PG&E or CAISO* * Subject to CAISO BD Business Day CD Calendar Day 5

7 Purpose is designed to provide the Customer: Ensure common understanding of Customer s project Ensure understanding of Generator Procedure Come to agreement on Point of and generator size PG&E will provide technical system details, limitations, and queued ahead projects PG&E will advise regarding which process Customer qualifies for and study to be conducted Next Steps 5 Business Days (3BD CAISO) after, the Developer must: Provide confirmation on the Point of Provide confirmation on Generator Size 6

8 Process Milestone Duration Responsible Party Deem Complete Clock Start PG&E or CAISO* Schedule 10 BD PG&E or CAISO* Designate and Confirm Point of Tender Generator Study Process (GISPA) Scheduled or 60 CD from Window Close 5 BD WDT 3 BD CAISO 10 BD or 60 CD from Window Close All Parties Customer PG&E or CAISO* * Subject to CAISO BD Business Day CD Calendar Day 7

9 Scope of are intended to provide: Impact of generation on PG&E s electric system Scope of Capital Improvements to PG&E s electric system to ensure the safety, reliability, and integrity of the grid: - Facilities Generator Specific facilities required for interconnection -Distribution Upgrades Upgrades to the Distribution System triggered by Generator or Cluster -Network Upgrades Upgrades to the Network (CAISO Controlled Grid) triggered by Generator or Cluster Cost Estimate for Scope of Capital Improvements Required and Schedule 8

10 Phase I Study Process Milestone Duration Responsible Party Tender Generator Study Process (GISPA) Clock Start PG&E or CAISO* Execute GISPA 30 CD Customer Execute GISPA A.S.A.P. PG&E or CAISO* Begin Phase I Study Jun 1 PG&E or CAISO* Provide Phase I Study Results 134 CD PG&E or CAISO* Post Initial Posting 90 CD Customer Phase I Study Results 30 CD from Phase I Study Results All Parties * Subject to CAISO BD Business Day CD Calendar Day 9

11 Phase II Study Process Milestone Duration Responsible Party Phase I Study Results Clock Start All Parties Provide Attachment 3 (Data Form To Be Provided by the Customer Prior to Commencement of the Phase II Study) 5 BD Customer Begin Phase II Study Jan 15 PG&E or CAISO* Provide Phase II Study Results 196 CD PG&E or CAISO* Post Second Posting 180 CD Customer Phase II Study Results 30 CD from Phase II Study Results All Parties * Subject to CAISO BD Business Day CD Calendar Day 10

12 (IA) Small Generator (SGIA) 20MW or less Large Generator (LGIA) greater than 20 MW CAISO GIA is a three-party between CAISO, PG&E, and Customer Process Milestone Duration Responsible Party Provide Final Study Results Clock Start PG&E or CAISO* Tender IA 30 CD PG&E or CAISO* Respond to Draft 30 CD All Parties IA negotiated and agreed 90 CD from Clock Start All Parties PG&E or CAISO to issue executable IA 15 BD PG&E or CAISO* All parties execute IA A.S.A.P. All Parties Post Final Posting On or before the start of construction Customer * Subject to CAISO BD Business Day CD Calendar Day 11

13 Post, PG&E and Customer should be engineering and designing, procuring, and constructing the electrical interconnection PG&E will be engineering the Capital Improvements as agreed upon in the Customer will be engineering the electrical system on the Customer s side of the meter and any upgrades that will be applicant built and deeded Post EPC, PG&E, CAISO (if applicable), Customer will coordinate a pre-parallel inspection and commissioning to achieve Commercial Operation. 12

14 Financial Security Postings Posting Number Initial Second Third Posting Type Posting Amount Timing Phase Facilities and Distribution Upgrades Network Upgrades Facilities and Distribution Upgrades Network Upgrades Facilities and Distribution Upgrades Network Upgrades 100% Lesser of 20% or $20k/MW 15% or $20k/MW or $7.5M (>20MW) 30 CD WDT 60 CD CAISO* 90 CD 30% 120 CD 30% or $1M (<20MW) or $15M (>20MW) 180 CD 100% On or before the start of construction After System Impact Study (SIS) After Phase I After Facilities Study After Phase II After IA (acquisition of permits) * Subject to CAISO BD Business Day CD Calendar Day 13

15 Financial Security Posting Instructions Transmission* s Links to Letter of Credit Documents and Surety Bond can be found in the CAISO website under the heading Participating Transmission Owner Financial Security Instruments Distribution s Letter of Credit Documents and Surety Bond will be on GIS website shortly *Subject to CAISO 14

16 Appendix: Clustering Methodology Please refer to section Grouping of Requests in the WDT. 20 MW New BK M New 12 MW Two or more interconnection requests at a single substation that do not pass the Independent Study Electrical Independence Test (EIT) will be clustered together. 15

17 Appendix: Distribution Schedule Summary Fast Track Process These diagrams are for estimating purposes. It assumes immediate response from Customer. Independent Study Process Cluster Process 16

18 Appendix: Transmission Schedule Summary Fast Track Process These diagrams are for estimating purposes. It assumes immediate response from Customer. Independent Study Process Cluster Process 17

19 Appendix: Capital Improvement Terms Facilities The Distribution Provider's Facilities and the Customer's Facilities. Collectively, Facilities include all facilities and equipment between the GF and the Point of, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the GF to the Distribution Provider's Distribution System. Facilities are sole use facilities and shall not include Distribution Upgrades or Network Upgrades. Distribution Upgrades The additions, modifications, and upgrades to the Distribution Provider's Distribution System at or beyond the Point of to facilitate interconnection of the GF and render the service necessary to effect the Customer's wholesale sale of electricity in interstate commerce. Distribution Upgrades do not include Facilities. Network Upgrades Additions, modifications, and upgrades to the Distribution Provider's Transmission System required at or beyond the point at which the Distribution System connects to the Distribution Provider s Transmission System to accommodate the interconnection of the GF to the Distribution Provider s Transmission System. Network Upgrades do not include Distribution Upgrades. 18

20 Appendix: Key Terms Point of The point where the Facilities connect with the Distribution Provider's Distribution System. Facilities The Distribution Provider's Facilities and the Customer's Facilities. Collectively, Facilities include all facilities and equipment between the GF and the Point of, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the GF to the Distribution Provider's Distribution System. Facilities are sole use facilities and shall not include Distribution Upgrades or Network Upgrades. Distribution System Those non-iso transmission and distribution facilities owned, controlled and operated by the Distribution Provider that are used to provide distribution service under the Tariff, which facilities and equipment are used to transmit electricity to ultimate usage points such as homes and industries directly from nearby generators or from interchanges with higher voltage transmission networks which transport bulk power over longer distances. The voltage levels at which Distribution Systems operate differ among areas. Upgrades The required additions and modifications to the Distribution Provider's Transmission System and Distribution System at or beyond the Point of. Upgrades may be Network Upgrades or Distribution Upgrades. Upgrades do not include Facilities. 19

21 Point of Illustration Simplified Single Line for Tap Simplified Single Line for Gen-Tie PG&E Substation 115/21 kv PG&E Substation 115/21 kv Network System 115kV Network System 115kV BK Distribution System BK Distribution System 21kV Point of 21kV PG&E 21kV Gen-Tie Point of PG&E 21kV Distribution Distribution Provider s Facilities Distribution System Distribution Provider s Facilities M 21 kv Tap (PG&E-owned) M Customer s Facilities Point of ownership change Transformer Customer s Facilities Point of ownership change Transformer Generator Generator 20

Generator Interconnection Procedures Overview

Generator Interconnection Procedures Overview Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution

More information

Generator Interconnection Process. Wholesale Distribution Overview

Generator Interconnection Process. Wholesale Distribution Overview 1 Generator Process Wholesale Distribution Overview 2 This presentation summarizes the FERCapproved Generator Procedures (GIP) in Attachment I of PG&E s Wholesale Distribution Tariff (WDT). The presentation

More information

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT) Program Overview August 8, 2013 1 ReMAT Schedule Date (2013) July 23 July 24 August 8 August 16 TBD TBD October 1 November 1 Event E-PWF &

More information

What You Need to Know Before Requesting Interconnection

What You Need to Know Before Requesting Interconnection Connecting to the Utility Grid What You Need to Know Before Requesting Interconnection Peter Giannotti Southern California Edison August 16, 2017 Tampa Convention Center Tampa, Florida Why is Grid Interconnection

More information

PG&E s WDT Interconnection Reform Principles Document

PG&E s WDT Interconnection Reform Principles Document PG&E s WDT Interconnection Reform Principles Document The purpose of this document is to lay out PG&E s high-level objectives and to discuss the underlying principles behind the interconnection process

More information

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14 FERC Electric Tariff Page 1 of 2 ATTACHMENT N Small Generator Interconnection Procedures and Agreement (For Generating Facilities No Larger Than 20 MW) Idaho Power Company 3.14

More information

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions

Interconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners

More information

Small Generator Interconnection Procedures (SGIP) Customer Guide

Small Generator Interconnection Procedures (SGIP) Customer Guide Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission

More information

Business Practice Manual for Distributed Generation Deliverability. Version

Business Practice Manual for Distributed Generation Deliverability. Version Business Practice Manual for Distributed Generation Deliverability Version 0.12.0 Revision Date: June 6, 20141, 2015 Approval History Approval Date: June 6, 2014 Effective Date: June 6, 2014 BPM Owner:

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012

Stakeholder Comments Template. Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Stakeholder Comments Template Generator Interconnection Procedures Phase 3 ( GIP 3 ) Issue Paper, posted March 1, 2012 Please submit comments (in MS Word) to GIP3@caiso.com no later than the close of business

More information

DG Interconnection Procedures Collaborative. January 20, 2017

DG Interconnection Procedures Collaborative. January 20, 2017 DG Interconnection Procedures Collaborative January 20, 2017 1 Interconnection Procedures Collaborative State Ombudsman kick-off October 2016 Goal: develop improvements to Con Edison s internal process

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And DECADE ENERGY, LLC

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And DECADE ENERGY, LLC Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 952 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And RADIANT BMT, LLC

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And RADIANT BMT, LLC Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 1002 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES

PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES PSCO QUEUE REFORM STAKEHOLDER MEETING #2 JUNE 19, 2018 LIAM NOAILLES 303-571-2794 1 1 FIRE SAFETY Proceed out of the building to the designated meeting location. Do not use the elevators. Stairs are located

More information

California Independent System Operator Corporation. California ISO. Invoicing WECC NERC/ERO Costs. March 29, Prepared by: Michael Epstein

California Independent System Operator Corporation. California ISO. Invoicing WECC NERC/ERO Costs. March 29, Prepared by: Michael Epstein California Independent System Operator Corporation California ISO Invoicing WECC NERC/ERO Costs March 29, 2007 Prepared by: Michael Epstein Table of Contents 1. Executive Summary 2. Background 3. Overview

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 970 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

Rule 21 Tariff / Process Overview 6/17/2015

Rule 21 Tariff / Process Overview 6/17/2015 Rule 21 Tariff / Process Overview 6/17/2015 Rule 21/WDAT Overview Rule 21 Jurisdiction CPUC FERC WDAT Applicability Generator/storage retail interconnections (transmission or distribution); retail solicitations

More information

Procedure: Station Power Portfolio Application

Procedure: Station Power Portfolio Application Overview Introduction FERC has established a policy that allows a single corporate entity that owns one or more Generating Units to self-supply Station Power over a monthly netting period using Energy

More information

October 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto; and the Service Agreement.

October 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto; and the Service Agreement. James A. Cuillier Director FERC Rates & Regulation October 9, 2015 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant

More information

Queue Management Process

Queue Management Process SPP and MISO Queue Management Process By: Noumvi G. Ghomsi Utility Engineering Specialist II Missouri Public Service Commission 200 Madison Street Jefferson City, MO 65102 (573) 526-9681 Noumvi.Ghomsi@psc.mo.gov

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

Water & Energy Consulting Lon W. House, Ph.D.

Water & Energy Consulting Lon W. House, Ph.D. Water & Energy Consulting Lon W. House, Ph.D. 530.409.9702 (cell) lonwhouse@waterandenergyconsulting.com www.waterandenergyconsulting.com 2795 East Bidwell Street 10645 N. Oracle Rd. Suite 100-176 Suite

More information

September 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Agreement.

September 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Agreement. Regulation James A. Cuillier Director FERC Rates & Regulation September 9, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012

Queue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012 Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new

More information

PacifiCorp Contract Review. Discussion Paper

PacifiCorp Contract Review. Discussion Paper PacifiCorp Contract Review Discussion Paper June 24, 2016 M&ID/D. Le Vine Page 1 Table of Contents 1 Executive Summary... 4 2 Introduction... 5 3 Stakeholder Process Next Steps... 7 4 Agreements PacifiCorp

More information

New York Independent System Operator System Reliability Impact Study Criteria and Procedures

New York Independent System Operator System Reliability Impact Study Criteria and Procedures New York Independent System Operator System Reliability Impact Study Criteria and Procedures Note: Project Developers are advised that these documents do not address cost allocation Approved by the Operating

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Submitted by Company Date Submitted Kevin T. Fox Keyes & Fox, LLP 436 14 th

More information

Subject: Corrective Filing -- Electric Interruptible Load Program (E-OBMC)

Subject: Corrective Filing -- Electric Interruptible Load Program (E-OBMC) April 24, 2001 ADVICE 2106-E (Pacific Gas and Electric Company ID U 39 E) Public Utilities Commission of the State of California Subject: Corrective Filing -- Electric Interruptible Load Program (E-OBMC)

More information

Defining Outage States to Include a Mothball Outage

Defining Outage States to Include a Mothball Outage Defining Outage States to Include a Mothball Outage Emilie Nelson Director, Operations Josh Boles Manager ICAP Market Market Issues Working Group November 7, 2013 2013 New York Independent System Operator,

More information

COUNTY OF SANTA BARBARA

COUNTY OF SANTA BARBARA Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 1057 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD

ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD ATTACHMENT B TECHNICAL AND OPERATIONAL IMPLEMENTATION OF THE TARIFF FOR WHOLESALE DISTRIBUTION LOAD 1. Metering And Communications Equipment: Data retrieval requirements, procedures, and schedules shall

More information

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X Fifth Revised Page No. 59 908 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X A. AVAILABILITY Available to members of the Cooperative for purchases of electricity by the Cooperative from qualified

More information

Operations Highlights

Operations Highlights Operations Highlights Description Highlights of Operations System Performance. A high-level summary of notable events and update of important operation information not otherwise covered in other Board

More information

Third Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates.

Third Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates. Definitions T U - V Tangible Net Worth: Tangible Net Worth shall mean all assets (not including any intangible assets such as goodwill) less all liabilities. Any such calculation may be reduced by PJMSettlement

More information

FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION

FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION FERC Electric Tariff 8th Rev. Volume No. 7 Original Sheet No. 1 FERC ELECTRIC TARIFF EIGHTH REVISED VOLUME NO. 7 OF PUGET SOUND ENERGY, INC. filed with the FEDERAL ENERGY REGULATORY COMMISSION OPEN ACCESS

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling storage assets providing regulated cost-ofservice-based transmission service to access market revenues Straw Proposal Karl Meeusen, Ph.D. Stakeholder Meeting May

More information

Generator Interconnection Driven Network Upgrade Cost Recovery. Draft Final Proposal

Generator Interconnection Driven Network Upgrade Cost Recovery. Draft Final Proposal Generator Interconnection Driven Network Upgrade Cost Recovery Draft Final Proposal February 6, 2017 California ISO Draft Final Proposal Table of Contents 1. Summary... 3 2. Background... 3 3. Stakeholder

More information

California ISO Revised Draft Final Proposal IPE 2015

California ISO Revised Draft Final Proposal IPE 2015 Stakeholder Comments Template Submitted by Company Date Submitted Rachel Gold, Policy Director (Rachel@largescalesolar.org) Susan Schneider, Consultant (Schneider@phoenix-co.com) Large-scale Solar Association

More information

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018 Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process Planning Advisory Committee September 26, 2018 Discussion Today Discuss Stakeholder response to MISO proposed process

More information

Market Procedure: Network Control Services

Market Procedure: Network Control Services ELECTRICITY INDUSTRY ACT 2004 ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES Market Procedure: Network Control Services Version 2 Commencement:

More information

NSTAR ELECTRIC COMPANY M.D.P.U. No. 6 WESTERN MASSACHUSETTS TERMS AND CONDITIONS GREEN OPTIONS SUPPLIERS

NSTAR ELECTRIC COMPANY M.D.P.U. No. 6 WESTERN MASSACHUSETTS TERMS AND CONDITIONS GREEN OPTIONS SUPPLIERS Page 1 of 14 1. Applicability 1A. The following Terms and Conditions for Western Massachusetts Green Options Suppliers ( WGO Terms and Conditions ) shall apply to every licensed Western Massachusetts Green

More information

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS Program Guide TABLE OF CONTENTS Introduction... 2 Purpose... 2 About CHP... 2 Program Description... 2 Call for CHP Projects... 3 Participant Webinar...

More information

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION

INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection

More information

PJM Queue Position Establishment Background and Support for Problem Statement

PJM Queue Position Establishment Background and Support for Problem Statement PJM Queue Position Establishment Background and Support for Problem Statement Presented by David Egan Manager, Interconnection Projects To the PJM Planning Committee June 11, 2015 Overview Establishing

More information

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider

More information

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets March 8, 2010 Revised Draft Final Proposal for Participation of Non- Generator Resources

More information

Combined Heat and Power ( CHP ) Request for Offers. Participants Conference January 12, 2012

Combined Heat and Power ( CHP ) Request for Offers. Participants Conference January 12, 2012 Combined Heat and Power ( CHP ) Request for Offers Participants Conference January 12, 2012 Agenda Topics: Introduction CHP Settlement Overview Solicitation Overview Offer Submittal Process Offer Form

More information

Issue Paper. Direct Participation of Demand Response Resources in CAISO Electricity Markets. December 22, CAISO JEP / BDC/ JDG 12/22/08, page 1

Issue Paper. Direct Participation of Demand Response Resources in CAISO Electricity Markets. December 22, CAISO JEP / BDC/ JDG 12/22/08, page 1 Issue Paper Direct Participation of Demand Response Resources in CAISO Electricity Markets December 22, 2008 CAISO JEP / BDC/ JDG 12/22/08, page 1 Direct Participation of DR Resources Table of Contents

More information

Part 1 Introduction and Overview

Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Application for Customer Generation Cost Responsibility Surcharge (CRS) Tariff Exemptions (Application) is for the purpose of requesting an exemption

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling storage assets providing regulated cost-ofservice-based transmission service to access market revenues Working Group Meeting Karl Meeusen, Ph.D. Stakeholder Meeting

More information

effective date 1/8/01

effective date 1/8/01 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context clearly indicates otherwise, in this section and 25.212 of this title (relating to Technical

More information

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF

PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY WHOLESALE DISTRIBUTION TARIFF PACIFIC GAS AND ELECTRIC COMPANY FERC Electric Tariff First Revised Volume 4 Original Sheet No. 1 TABLE OF CONTENTS 1. Preamble and Applicability...4

More information

Business Practice Manual for the Transmission Planning Process

Business Practice Manual for the Transmission Planning Process Business Practice Manual for the Transmission Planning Process Order 890 Compliance Version 76.0 September 15,February 11, 2010 TABLE OF CONTENTS Order 890 Compliance... i 1. Introduction... 6 1.1 Purpose

More information

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Stakeholder Comments Template Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting Leslie Padilla Submitted by Company Date Submitted lpadilla@semprageneration.com

More information

Transmission Expansion and Interconnection Manual. June 2017

Transmission Expansion and Interconnection Manual. June 2017 MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection

More information

Revised Transmission Planning Process. Complete Final Proposal

Revised Transmission Planning Process. Complete Final Proposal Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 4120 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1 Background... 3 2.2 Scope/ Applicability... 4 3. PROCEDURE DETAIL... 4 3.1 General Information... 4 3.2

More information

CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)

CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) Ethan D. Avallone Senior Market Design Specialist, Energy Market Design Management Committee March 28, 2018

More information

Invitation for Expression of Interest to provide Flexible Services 3 April 2018

Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Flexible Services Expression of Interest/3 April 2018 Page 1 of 21 VERSION HISTORY Version Date Author Status Comments 1.0

More information

Rule 21 Working Group 3

Rule 21 Working Group 3 Rule 21 Working Group 3 CONFERENCE CALL JANUARY 16, 2019 HTTPS://WWW.UBERCONFERENCE.COM/GRIDWORKS https://gridworks.org/initiatives/rule-21-working-group-3/ Agenda 2:00-2:10 Regulatory updates 2:10-2:15

More information

An Introduction to Interconnection Policy in the United States

An Introduction to Interconnection Policy in the United States An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator

More information

THE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 19

THE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 19 TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 19 1. Applicability 1A. The following Terms and Conditions shall apply to every registered Electric Supplier authorized to do business within Connecticut

More information

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the FERC ELECTRIC TARIFF First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 3.1 Nature of Relationship. Each Participating

More information

2018 Open Season Request for Offers Procedural Overview & Instructions

2018 Open Season Request for Offers Procedural Overview & Instructions 2018 Open Season Request for Offers Procedural Overview & Instructions 1. Introduction As part of its ongoing effort to deliver environmentally responsible, competitively priced retail electricity service

More information

January 9, Tariff Amendment to Implement 2018 Expedited Interconnection Process Enhancements

January 9, Tariff Amendment to Implement 2018 Expedited Interconnection Process Enhancements California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 9, 2018 Re: California

More information

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 4120C Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Detail... 4 3.2. Notice of

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Subject: Generation Interconnection Procedures Phase 2 ( GIP 2 ) Submitted by Company Date Submitted Rob Longnecker rob@clean-coalition.org 415-787-3080 Clean Coalition June

More information

Transmission Interconnection Requirements. Table of Contents

Transmission Interconnection Requirements. Table of Contents Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection Agreement III. Facility Requirements IV. Interconnection Initiation I. Introduction A. Purpose and Scope

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling transmission connected storage assets providing regulated cost-of-service-based transmission service to also access other market revenue streams March 30, 2018

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

QF Settlement Agreement Overview QF Meeting Rosemead, CA. July 22, 2011

QF Settlement Agreement Overview QF Meeting Rosemead, CA. July 22, 2011 QF Settlement Agreement Overview QF Meeting Rosemead, CA July 22, 2011 Welcome and introduction Mike Marelli 1 Agenda for the morning Continental breakfast and guest registration Welcome and introductions

More information

Appendix D Minimum Requirements For Developmental Resources For

Appendix D Minimum Requirements For Developmental Resources For Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc. Entergy Services, Inc. July 13, 2016 MINIMUM REQUIREMENTS FOR

More information

Feed-in-Tariff (FIT) Connection Application Guidelines

Feed-in-Tariff (FIT) Connection Application Guidelines Generation Planning & Transmission Capacity Feed-in-Tariff (FIT) Connection Application Guidelines These guidelines help to ensure efficient processing and implementation of the FIT project. It is important

More information

New York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules

New York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules New York Independent System Operator, Inc. NYISO Tariffs OATT Schedules Document Generated On: 6/30/2010 Page 1 Contents 6 Schedules... 7 6.1 Schedule 1 Scheduling, System Control and Dispatch Service...

More information

GRENLEC s Renewable Standard Offer

GRENLEC s Renewable Standard Offer GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 65402-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 64974-E Schedule TOU-GS-3-SOP Sheet 1 APPLICABILITY Applicable to single-

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling transmission-connected storage assets providing regulated cost-of-service-based transmission service to also access other market revenue streams Issue Paper Karl

More information

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201

TARIFF FOR WHOLESALE TRANSMISSION SERVICE SHARYLAND UTILITIES, L.P. SHARYLAND UTILITIES, L.P North Akard Dallas, Texas 75201 TARIFF FOR WHOLESALE TRANSMISSION SERVICE 1900 North Akard Dallas, Texas 75201 Applicability: Entire System Sheet No. 1 Effective Date: May 25, 2018 Revision: 17 Availability Wholesale Transmission Service

More information

Portland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1

Portland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1 First Revision of Sheet No. 26-1 P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1 PURPOSE SCHEDULE 26 NONRESIDENTIAL DEMAND RESPONSE PILOT PROGRAM This schedule is an optional supplemental service

More information

PG&E s Bidders Webinar

PG&E s Bidders Webinar PG&E s Bidders Webinar Distribution Resources Plan (DRP) Demonstration Project D RFO May 24, 2017 Agenda Topics Introduction Goals of DRP Demo D Overview Distribution Services Needed Solicitation Overview

More information

Advancing Renewable Alternatives

Advancing Renewable Alternatives Advancing Renewable Alternatives FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 Abigail Krich President, Boreas Renewables About Boreas Renewables

More information

Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection.

Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection. Comments of the California Wind Energy Association on CAISO s August 23, 2007 Draft Proposal for Remote Resource Interconnection September 5, 2007 The California Wind Energy Association ( CalWEA ) appreciates

More information

FAC Facility Interconnection Requirements

FAC Facility Interconnection Requirements FAC-001-3 Interconnection Requirements A. Introduction 1. Title: Interconnection Requirements 2. Number: FAC-001-3 3. Purpose: To avoid adverse impacts on the reliability of the Bulk Electric System, Transmission

More information

Summary of Submitted Comments

Summary of Submitted Comments Stakeholder Process: Generator Interconnection Procedures Phase 2 Summary of Submitted Comments Stakeholders have submitted four rounds of written comments to the ISO on the following dates: Round One:

More information

Appendix D. Minimum Requirements For Developmental Resources For

Appendix D. Minimum Requirements For Developmental Resources For Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc. DRAFT Entergy Services, Inc. May 6July 13, 2016 MINIMUM REQUIREMENTS

More information

PJM Business Practices for Neptune Transmission Service

PJM Business Practices for Neptune Transmission Service PJM Business Practices for Neptune Transmission Service Last Updated: September 3, 2009August 21, 2015 Table of Contents About These Practices... 3 1. Valid Paths for the NEPTUNE Reservations on the PJM

More information

Definitions O - P. Open Access Same-Time Information System (OASIS) or PJM Open Access Same-time Information System:

Definitions O - P. Open Access Same-Time Information System (OASIS) or PJM Open Access Same-time Information System: Definitions O - P Offer Data: Offer Data shall mean the scheduling, operations planning, dispatch, new resource, and other data and information necessary to schedule and dispatch generation resources and

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

Table of Contents. Purpose. Pre-Schedule & Check-Out Validation. Procedure No. S-312 Version No Operating Procedure

Table of Contents. Purpose. Pre-Schedule & Check-Out Validation. Procedure No. S-312 Version No Operating Procedure No. S-312 Table of Contents Purpose... 1 Actions... 2 Pre-Schedule... 2 Validation and Processing... 2 Daily Pre-Schedule Check Out... 3 Supporting Information... 4 Responsibilities... 4 References...

More information

Interconnection of New Generation Facilities

Interconnection of New Generation Facilities Interconnection of New Generation Facilities Jennifer Heintz Chief Counsel Public Service Commission of Missouri February 7, 2013 Abu Dhabi, U.A.E. Generation and Transmission in the United States In the

More information

RATE DS-4 LARGE GENERAL DELIVERY SERVICE

RATE DS-4 LARGE GENERAL DELIVERY SERVICE d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential

More information

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW

More information

Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS

Rule 21 Sheet 1 GENERATING FACILITY INTERCONNECTIONS Southern California Edison Revised Cal. PUC Sheet No. 31574-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 30685-E Rule 21 Sheet 1 A. Applicability 1. This Rule describes the Interconnection,

More information