Kibali Mine Development

Size: px
Start display at page:

Download "Kibali Mine Development"

Transcription

1 Kibali Mine Development The Kibali mine development in the Democratic Republic of Congo is the largest project undertaken to date by Randgold. With a reserve base at plus 10 million ounces and still growing, it will rank as one of the largest gold mines in Africa. KIBALI MINE DESIGN KIBALI MINE KEY INDICATORS for the 12 months ended 31 December KIBALI FORECAST PRODUCTION (000oz) Forecast Reserves Resources KIBALI TOTAL RESOURCES AND RESERVES (Moz) RANDGOLD RESOURCES Annual Report 2011

2 Achieved in 2011 KIBALI PLANT DESIGN Substantially bigger project defined All predevelopment objectives achieved; preconstruction underway Public participation process completed; community resettlement (RAP) advanced with first two villages successfully moved to new model town of Kokiza Detailed design of first hydropower facility completed Project infrastructure enhanced through major road construction programme Grade control of main KCD pit started Key long lead time orders placed Camp infrastructure enhanced to facilitate construction start-up Local partnerships developed in RAP construction Targeted for 2012 Source: DRA Mineral Projects KIBALI HEADGEAR AND SHAFT DESIGN Start construction of plant and infrastructure Complete detailed design for vertical shaft; begin decline and shaft development Start open pit mining Commence assembly of operational team Complete construction of first hydropower facility Start construction of employee housing Progress community resettlement to final stage Annual Report 2011 RANDGOLD RESOURCES 47

3 Kibali Mine Development (continued) The Kibali project is a gold development property which covers an area of 1 836km 2 on the Moto Goldfields in the north east of the DRC. It is located some 560 kilometres north east of the city of Kisangani and 150 kilometres west of the Ugandan border town of Arua. Kibali is a joint venture between Randgold (45%), AngloGold Ashanti (45%) and a Congolese parastatal, Sokimo (10%). The project development is being managed by Randgold which will also operate the mine. It is envisaged that the Kibali mine will comprise an integrated open pit and underground operation with the core capital programme scheduled to run over the next four years. It is anticipated that the project will ultimately be supplied by four hydropower stations supported by a thermal power station for low rainfall periods and back-up. The Moto Goldfields are located within the Moto greenstone belt, which is comprised of the Archean Kibalian (Upper and Lower) volcano-sedimentary rocks and ironstone-chert horizons that have been metamorphosed to greenschist facies. The stratigraphy consists of a volcano-sedimentary sequence comprising finegrained sedimentary rocks, several varieties of pyroclastic rocks, basaltic flow rocks, mafic-intermediate intrusions (dykes and sills) and intermediate-felsic intrusive rocks (stocks, dykes and sills). The majority of gold mineralisation identified to date is disseminated style, hosted within a sequence of coarse volcaniclastic and sedimentary rocks. The mineralisation is generally stratigraphic and associated with quartz-carbonate alteration and pyrite. Feasibility study and mine development PROgress The project successfully completed a critical year with the optimised feasibility study having been finalised by year end, as scheduled. The optimised feasibility presents a larger project compared to the previously published feasibility study, with a plant throughput of 6 million tonnes per annum, due to be commissioned in the fourth quarter of During the year, the Resettlement Action Plan (RAP) progressed on schedule, with the first two of the 14 villages successfully relocated to the new model village of Kokiza. This programme remains on the critical path to ensure the timely start-up of mining and construction. For more information on this project, please refer to the Sustainability Report on pages 76 to 104. At the same time, grade control drilling on the main KCD pit started, in advance of the mining activities which are scheduled to begin in the second quarter of KIBALI RESOURCES AND RESERVES Attributable gold*** Tonnes (Mt) Grade (g/t) Gold (Moz) 45% (Moz) at 31 December Category MineRAl resources* Open pit Indicated Inferred Underground Indicated Inferred Total mineral resources Indicated Inferred MineRAl reserves** Open pit Probable Underground Probable Total mineral reserves Probable * Open pit mineral resources are the insitu mineral resources falling within the US$1 500/oz pit shell reported at a cut-off of 0.5g/t. Underground mineral resources are those insitu mineral resources at the KCD deposit that fall below the metre RL elevation, reported at a cut-off of 1.5g/t. Mineral resources were generated by Mr Ernest Doh, an officer of the company and competent person. ** Open pit mineral reserves were reported at a gold price of US$1 000/oz and an average cut-off of 0.9g/t and include dilution and ore loss factors. Open pit mineral reserves were calculated by Mr Onno ten Brinke and Mr Nicholas Coomson, both officers of the company and competent persons. Underground mineral reserves were reported at a gold price of US$1 000/oz and a cut-off of 2.2g/t and include dilution and ore loss factors. Underground mineral reserves were calculated by Mr Andrew Fox and Mr Tim Peters, both independent consultants and competent persons. *** Attributable gold (Moz) refers to the quantity attributable to Randgold based on Randgold s 45% interest in the Kibali gold project. See comments and US disclaimer on page 74 of this Annual Report. 48 RANDGOLD RESOURCES Annual Report 2011

4 DEVELOPMENT TIMELINE Throughout the year, significant improvements were made to the surrounding infrastructure, especially roads, with approximately 200 kilometres of existing roads upgraded and 300 kilometres of new roads completed. Significant improvements to the existing camp and preparation for the new 400 man construction camp were completed, as well as the design of the first hydropower station. In total, US$157.4 million was spent on the project (100%). An updated costing and feasibility study was completed based on a revised underground mining plan which incorporated the combination of a twin decline and vertical ore hoisting shaft targeting the deeper 5000 lode as a priority. This was then integrated into a final mining plan including multi open pit and underground schedules. The study has been through internal and external review. Optimisation of the mining and processing rates, capital estimate scheduling, and the final design was approved by the Randgold board in January 2012 and is awaiting approval by the AngloGold Ashanti board. The revised open pit and underground mining designs and schedules support a 6Mtpa operation, planned for commissioning in the last quarter of 2013 and extending to The prospectivity of the area suggests this mine life could be extended with further exploration and conversion of these new discoveries and extension of mineral reserves. KIBALI PREDEVELOPMENT Annual Report 2011 RANDGOLD RESOURCES 49

5 Kibali Mine Development (continued) KIBALI: MINERALISED WIREFRAME OF KCD OREBODY WITH CONDUCTIVITY MODEL Updated processing and general administration (G&A) costs have been determined based on the larger plant throughput and higher power load demand of the underground mine. A standard crushing, milling and Carbon in Leach (CIL) processing plant is expected to be commissioned on plant start-up, planned for late Full flotation and flash flotation circuits will be incorporated to recover the sulphide for an overall increase in gold recovery. The underground mine design consists of a twin decline that accesses the ore beneath the KCD pit and then connects with a vertical shaft ore hoisting system to exploit the high tonnage stopes planned for the 5000 lode and deeper 9000 lode. The aim is to target the large 5000 lode from a mid-level off the shaft and the declines, thus bringing the large longhole open stopes of this lode into production quicker. RSV Perth completed the feasibility study for the shaft and electrical reticulation of the underground mine. The updated Life of Mine (LOM) study, which is based only on existing reserves, currently anticipates: Total open pit ore mined of 37.2Mt of ore containing 3.4Moz of gold at a strip ratio of 4.7:1. Total underground ore mined of 36.2Mt containing 6.8Moz of gold, giving combined total tonnes mined of 249Mt. Open pit mining costs average US$3.98/tonne mined over the LOM. Underground mining costs including ore development of US$51.45/ore tonne. Mill throughput of 6Mt per year. Plant costs average US$14.33/tonne milled. G&A cost of US$6.37/tonne milled over the LOM, including outside engineering costs and Aru road maintenance. Source: DRA Mineral Projects DETAILED KIBALI PLANT DESIGN 50 RANDGOLD RESOURCES Annual Report 2011

6 LIFE OF MINE FINANCIAL MODEL Results* The construction capital (excluding contingencies or escalation) is split into two phases: Phase 1 capital programme, to bring the mine into production at the end of 2013 (first gold), is estimated at US$920 million (in 2011 money) and will cover the metallurgical facility, one hydropower station and back-up thermal power facility, construction of the tailings storage facility, relocation of villages, open pit mining and all shared infrastructure. This will run over a two year period. Phase 2 capital programme, which will run concurrently with Phase 1 but will extend over four years, is focused primarily on the underground development and includes a twin decline and vertical shaft system as well as three hydropower stations. This is expected to bring the underground into first production by the end of 2014, with steady state production targeted for the end of Phase 2 capital cost is estimated at US$650 million (in 2011 money). Internal rate of return (IRR) 22% Total cash cost per ounce US$515/oz * Using a US$1 400/oz gold price. The LOM financial model carried out using a US$1 400/oz gold price gave the returns and cash costs of production shown in the table above. Assuming a gold price of US$1 500/oz, peak funding of US$1.2 billion is expected during Design and planning is now in the process of being implemented with earthworks and open pit mining having started early in 2012 and decline and shaft sinking scheduled for the second half. The advanced grade control drilling on the KCD pit is well advanced and will be completed together with predewatering of the open pit, decline and shaft sites prior to development. GEOTECHNICAL DRILLING FOR kibali shaft Annual Report 2011 RANDGOLD RESOURCES 51

7 Kibali Mine Development (continued) THE NEW KOKIZA VILLAGE NEAR KIBALI Health, safety and environment The introduction during the year of an additional construction employees, mostly novices from the surrounding villages, to the workforce resulted in Lost Time Injuries (LTIs) increasing from 11 in 2010 to 31 in The increase mainly concerned finger injuries sustained in the building of resettlement houses. Despite the increase in the number of LTIs, the LTIFR decreased year on year from to 6.14 reflecting the significant increase in construction activity. As the year progressed the number of safety incidents and LTIs injuries dropped as concerted steps were taken such as continuing risk assessments, daily toolbox meetings, elimination of hazards and enhanced supervision to improve safety practices. Environmental monitoring continues as defined in the ESIA document prepared by Digby Wells and Associates. Community The community development function at Kibali worked in close liaison with the RAP, especially in the areas of food security, life skill training and liaison with the cultural committee when relocating graves. Beyond the relocation, Kibali witnessed a wider acceptance of the project in the area as we approached the start of physical movement of the people to the resettlement host site as a result of more engagement with various stakeholders. Human resources The Kibali project currently employs 16 expatriates and 123 local employees. There are a further 20 expatriates and local employees employed by contractors engaged in various aspects of the construction project. KIBALI MANPOWER Nat- Natat 31 Dec Expats ionals Total Expats ionals Total Employees Contractors Total For more details on health, safety, the environment, manpower and industrial and community relations at Kibali, refer to the Sustainability Report on pages 76 to 104 of this Annual Report. Exploration A brownfields exploration team is progressing the feasibility work and testing extensions on known deposits while a greenfields team is evaluating the greater lease area. More details can be found in the Exploration Review on pages 56 to 70 of this Annual Report. KIBALI EXPLORATION 52 RANDGOLD RESOURCES Annual Report 2011

oz 2 % 8.7Moz LTIFR 0.47 KIBALI GOLD MINE. $287.7 million 1% $773/oz 5% $1.95 million. MALARIA IncIDence RATE

oz 2 % 8.7Moz LTIFR 0.47 KIBALI GOLD MINE. $287.7 million 1% $773/oz 5% $1.95 million. MALARIA IncIDence RATE KIBALI GOLD MINE PRODuceD 596 225 oz 2 % DIRecT CONTRIBUTIon TO COMMunITY DeveLopMENT $1.95 million PROFIT FROM MINING ACTIVITY 1 $287.7 million 1% ToTAL cash cost 1 $773/oz 5% TOTAL RESERveS 8.7Moz MALARIA

More information

70 019oz 30 % 0.19Moz LTIFR 0.0. $19.1 million 32% $988/oz 11 % $1.14 million. MALARIA IncIDence RATE. 48 Randgold Resources ANNUAL REPORT 2017

70 019oz 30 % 0.19Moz LTIFR 0.0. $19.1 million 32% $988/oz 11 % $1.14 million. MALARIA IncIDence RATE. 48 Randgold Resources ANNUAL REPORT 2017 MORILA gold mine PRODuceD 70 09oz 30 % ToTAL cash cost $988/oz % LTIFR 0.0 PROFIT FROM MINING ACTIVITY $9. million 3% TOTAL RESERveS 0.9Moz MALARIA IncIDence RATE TO % DIRecT CONTRIBUTION TO COMMunITY

More information

Kibali First Gold September 2013

Kibali First Gold September 2013 Kibali First Gold September 2013 Kibali gold mine where we ve come from Security: Previous instability in the northeast corner of the DRC had to be suitably addressed to allow the uninterrupted building

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information

For personal use only

For personal use only Positive Scoping Study: Aphrodite Gold Project 9 February 2012 Company Announcements Office Australian Securities Exchange Limited Positive Scoping Study for Aphrodite Gold Project Potential to Become

More information

For personal use only

For personal use only ASX Release 20 March 2012 PANTON REVIEW STUDY RESULTS (ASX:PLA) is pleased to advise that the results from the recently completed Panton Review Study ( PRS ) showed that the Project could achieve and Internal

More information

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME ASX ANNOUNCEMENT 23 February 2012 (8 pages by email) TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME Sumatra Copper & Gold plc ( Sumatra or the Company ) is pleased to announce that the Prefeasibility

More information

Ravenswood Expansion Project Update

Ravenswood Expansion Project Update 11 July 2018 Ravenswood Expansion Project Update Highlights AISC down, mine life extended, all required approvals received Significant enhancements have been made to Ravenswood Expansion Project All required

More information

For personal use only

For personal use only 28 November 2017 Corporate Details Ordinary Shares: 780,917,069 Market Capitalisation: ~$156 million Cash and bullion at 30 September 2017: ~$20.1 million Debt: NIL ASX Code: MOY Board of Directors Greg

More information

For personal use only

For personal use only 7 August 2012 ASX: PAN Gidgee Gold Project Scoping Study Key Highlights Gold Production estimated at 606,000oz of gold over an initial seven years, average annual production of 87,000oz Operating Cash

More information

For personal use only

For personal use only ACN 097 088 689 01 DEFINITIVE FEASIBILITY STUDY SUPPORTS A MAJOR EXPANSION OF THE SYAMA GOLD MINE Definitive Feasibility Study completed for multifaceted expansion of Syama operation confirms its technical

More information

For personal use only

For personal use only Highlights March 2014 Quarterly Report 30 April 2014 Record tonnes milled of 131,950 tonnes for the quarter. Gold production of 7,786 oz for the quarter. Average gold price received of A$1,447/oz (US$1,300

More information

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Chalice Gold Mines Limited ABN 47 116 648 956 30 October 2009 Highlights Scoping Study finds Koka deposit at the Zara Project in Eritrea

More information

Highlights. Wa Project. Akoko Project. Scoping studies on the Julie West gold vein were completed with the following outcomes;

Highlights. Wa Project. Akoko Project. Scoping studies on the Julie West gold vein were completed with the following outcomes; 24 th July 2009 June December 2009 Quarterly Report Report 2008 Highlights Wa Project Scoping studies on the Julie West gold vein were completed with the following outcomes; 250,000 tonnes @ 4.9g/t gold

More information

Gum Creek Gold Project Free Milling Scoping Study

Gum Creek Gold Project Free Milling Scoping Study 18 March 2016 ASX: PAN Highlights Gum Creek Gold Project Free Milling Scoping Study Mining Inventory of 4.9Mt at 1.94g/t Au for 309koz gold based on material from Swan, Swift and Howards Resources Average

More information

QUARTERLY ACTIVITIES REPORT

QUARTERLY ACTIVITIES REPORT QUARTERLY ACTIVITIES REPORT For the quarter ended 31 March 2011 ABN: 38 108 779 782 Silver Lake Resources Ltd ( Silver Lake or the Company ) is pleased to present this Quarterly Activities Report. Les

More information

ALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE

ALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE ALACER GOLD ANNOUNCES FOURTH QUARTER MINE PRODUCTION AND 2012 GUIDANCE Quarterly Gold Production Increases to 113,861 ounces and 421,204 Ounces Achieved for January 24, 2012 Alacer Gold Corp ( Alacer or

More information

Malachite Resources AGM. November For personal use only. Malachite Resources Limited

Malachite Resources AGM. November For personal use only. Malachite Resources Limited Malachite Resources AGM November 2013 1 Malachite Resources Limited Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk

More information

For personal use only

For personal use only ASX Announcement 19 December 2014 BOARD OF DIRECTORS Paul Murphy (Non-Executive Chairman) Bryan Dixon (Managing Director) Alan Thom (Executive Director) Greg Miles (Non-Executive Director) ASX CODE BLK

More information

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces ABN 28 009 174 761 31 March 2011 Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 www.regisresources.com Level 1 1 Alvan

More information

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES July 25 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES The Process

More information

For personal use only

For personal use only FAST FACTS Capital Structure Shares on issue 300 million Market Cap ~A$480 million Cash in bank ~A$50.4 million (June 11 quarterly) CORPORATE DIRECTORY Mel Ashton Non-Executive Chairman Stephen Parsons

More information

MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES

MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES 15 June 2011 MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES (MELBOURNE) OceanaGold Corporation (ASX: OGC, TSX: OGC, NZX: OGC) ( the Company )

More information

DALGARANGA PRE-FEASIBILITY UPDATE

DALGARANGA PRE-FEASIBILITY UPDATE January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

For personal use only

For personal use only January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

ASX : BLK. Australian gold producer with exceptional growth opportunity

ASX : BLK. Australian gold producer with exceptional growth opportunity ASX : BLK Australian gold producer with exceptional growth opportunity AMEC Conference Perth June 2017 The information contained in the report that relates to ore reserves at the Matilda Gold Project is

More information

For personal use only

For personal use only Mutiny makes substantial metallurgical performance gains Forecast copper recoveries increased from 58.5% to 64% in the oxide zone and copper concentrate grade increased from 21.5% Cu to 35% Cu Forecast

More information

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD December 8 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD Construction at Gascoyne s

More information

Study on Gonka Deposit and Taurus Extension

Study on Gonka Deposit and Taurus Extension Study on Gonka Deposit and Taurus Extension RNS Number : 7037N Hummingbird Resources PLC 02 February 2016 Hummingbird Resources plc ('Hummingbird' or 'the Company') Study on Gonka Deposit and Taurus Extension

More information

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

For personal use only

For personal use only December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

Great Western Scoping Study Update & Onsite Gold Processing

Great Western Scoping Study Update & Onsite Gold Processing ASX RELEASE 10 August 2017 ABN: 45 116 153 514 ASX: TMX Great Western Scoping Study Update & Onsite Gold Processing Terrain Minerals Limited (ASX: TMX) is pleased to provide the following update on its

More information

OZ MINERALS SECOND QUARTER REPORT Andrew Michelmore Managing Director & CEO. 22 July 2008

OZ MINERALS SECOND QUARTER REPORT Andrew Michelmore Managing Director & CEO. 22 July 2008 OZ MINERALS SECOND QUARTER REPORT Andrew Michelmore Managing Director & CEO 22 July 2008 CONTENT 1. HIGHLIGHTS 2. MARKETS 3. SEPON GOLD AND COPPER 4. SEPON COPPER EXPLORATION 5. GOLDEN GROVE 6. PROMINENT

More information

For personal use only

For personal use only 4 AUGUST 2017 TROPICANA GOLD MINE UPDATE Independence Group NL ( IGO or the Company ) (ASX: IGO) is pleased to provide a progress report on initiatives to further maximise and optimise the Tropicana Gold

More information

TEMBANG PROJECT OPTIMISATION

TEMBANG PROJECT OPTIMISATION ASX ANNOUNCEMENT 16 April 2012 (13 pages by email) TEMBANG PROJECT OPTIMISATION Sumatra Copper & Gold plc ('Sumatra' or 'the Company') is pleased to confirm Optimisation Studies for its wholly-owned Tembang

More information

EXCO S PROJECT PIPELINE

EXCO S PROJECT PIPELINE EXCO S PROJECT PIPELINE INVESTOR UPDATE EXCO RESOURCES N.L. MAY 2010 Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking statements that are subject to

More information

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET May 30 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET First Gold poured from Dalgaranga

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 30th September, 2014 ABM s Development Plan & Production Guidance for Old Pirate High-Grade Gold Deposit Highlights: 50,000 to 60,000 ounces of gold production

More information

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE August 7 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE Credit approved commitment letters received from a number of tier

More information

Confidence in Carrapateena project grows

Confidence in Carrapateena project grows 7 NOVEMBER 2016 Confidence in Carrapateena project grows Carrapateena Pre-Feasibility Study released - project competitive with, or better than comparable long-life copper assets globally Project metrics

More information

For personal use only

For personal use only 25 May 2012 AMENDED PERKOA JOINT VENTURE PROJECT MINERAL RESOURCE UPGRADE Please find attached an amended version of the Perkoa Joint Venture Project Mineral Resource Upgrade announcement released yesterday.

More information

Australian gold producer 90, ,000 CY19

Australian gold producer 90, ,000 CY19 Australian gold producer 90,000-100,000 CY19 Rising grades, rising production +100,000ozpa targeted production New discoveries driving growth ------------------------------------------- February 2019 Corporate

More information

For personal use only

For personal use only 11 June 2015 ASX Limited Marked Announcements Platform Exchange Centre 20 Bridge Street Sydney NSW 2000 Preliminary Economic Assessment Delivers Excellent Results at the Fair Bride Deposit Study confirms

More information

LOULO-GOUNKOTO PRODUCTION AND FIVE YEAR FORECAST LOULO TOTAL MINERAL GOUNKOTO TOTAL MINERAL RESOURCES AND ORE RESERVES 1 32 ANNUAL REPORT 2016

LOULO-GOUNKOTO PRODUCTION AND FIVE YEAR FORECAST LOULO TOTAL MINERAL GOUNKOTO TOTAL MINERAL RESOURCES AND ORE RESERVES 1 32 ANNUAL REPORT 2016 The Loulo-Gounkoto mining complex straddles two distinct mining permits, the Loulo mining permit and the Gounkoto mining permit. It is situated in western Mali, approximately 500 kilometres from the capital

More information

For personal use only

For personal use only September 2013 Quarterly Report 24 October 2013 Highlights Record gold production of 7,733 oz (34% increase on the previous quarter) Average gold price received of A$1,465/oz (US$1,335/oz) Cash costs reduced

More information

ASX Release ASX Code: YTC

ASX Release ASX Code: YTC HERA DEFINITIVE FEASIBILITY STUDY TO BE EXPANDED Hera DFS scope to be expanded to include the assessment of mining and treatment of high grade copper ores from the Nymagee Copper Mine together with additional

More information

For personal use only

For personal use only ACN 092 471 513 QUARTERLY REPORT FOR THE PERIOD ENDING 31 DECEMBER 2017 HIGHLIGHTS PENNY S FIND GOLD MINE KALGOORLIE (WA) 84,367 tonnes of ore processed at an average head grade of 3.09g/t Au 7,837 ounces

More information

Azure Minerals Ltd ASX Code:

Azure Minerals Ltd ASX Code: Azure Minerals Ltd ASX Code: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director Azure Minerals Ltd Objective To be a low cost, high margin copper producer Strategy Developing our

More information

Southern Cross Goldfields Ltd

Southern Cross Goldfields Ltd Southern Cross Goldfields Ltd ASX Announcement - 20 December 2013 Marda Gold Project: Feasibility Study Review Additional Information On 10 December 2013, Southern Cross Goldfields (ASX: SXG SXG or the

More information

For personal use only

For personal use only June 2013 Quarterly Report 30 July 2013 Highlights Total gold production was 5,767 ounces for the quarter. Cash operating profit was A$628,000 for the quarter. Gold production at Lily was 4,641 ounces

More information

Australia's Newest Gold Producer

Australia's Newest Gold Producer ASX : BLK Australia's Newest Gold Producer AGM 25 November 2016 Australia s Newest Gold Producer Gold production commenced in Oct 2016 at 5.1Moz Matilda/Wiluna Gold Operation 5.1Moz resource, 4 large gold

More information

For personal use only

For personal use only Date: 14 March 2013 Mount Magnet South NL Is an emerging gold producer targeting commencement of production in 2013 at an initial rate of 68,000 ounces per year. Fast Facts Share Price (13/03/2013) $0.053

More information

Q Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update

Q Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update For immediate release 10 January 2018 Centamin plc ("Centamin" or "the Company") (LSE:CEY, TSX:CEE) Q4 2017 Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 5th September, 2012 Old Pirate Metallurgical Test-Work delivers Exceptional Gold Recovery (up to 97.3%) from Two Different Gravity Methods ABM Resources NL ( ABM

More information

Kingsgate 2012 Mineral Resources & Ore Reserves

Kingsgate 2012 Mineral Resources & Ore Reserves 16 October 2012 Via ASX Online Manager Company Announcements Office Australian Securities Exchange Kingsgate 2012 Mineral Resources & Ore Reserves Kingsgate Consolidated Limited (ASX: KCN) increased its

More information

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD November 3 rd 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD Construction work at Gascoyne s 100%

More information

For personal use only

For personal use only Pre-Feasibility Study Highlights World Class Potential of Mt Lindsay Tin/Tungsten Project ASX Announcement Tuesday, 1 March 2011 Ref: /VMS/606/VMS/0249 Highlights: Project generates substantial revenue

More information

For personal use only

For personal use only ACN 092 471 513 QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2018 HIGHLIGHTS PENNY S FIND GOLD MINE KALGOORLIE (WA) 25,771 dry tonnes of ore processed at an average head grade of 6.55g/t Au 5,061 ounces

More information

For personal use only

For personal use only Corporate Details Ordinary Shares: 795,237,123 Market Capitalisation: ~$180 million Cash, bullion and available financing facilities at 31 December 2018: $18.2 million Debt at 31 December 2018: $5 million

More information

ABM Hits 3000 Ounce Target from Trial Mining

ABM Hits 3000 Ounce Target from Trial Mining ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 12 th December 2013 ABM Hits 3000 Ounce Target from Trial Mining ABM Resources NL ( ABM or The Company ) presents an update on the Trial Mining and Processing at

More information

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD March 19 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD Process plant construction

More information

TONGON GOLD MINE TONGON TOTAL MINERAL RESOURCES AND ORE RESERVES1 TONGON PRODUCTION AND FIVE YEAR FORECAST. Moz. Resources.

TONGON GOLD MINE TONGON TOTAL MINERAL RESOURCES AND ORE RESERVES1 TONGON PRODUCTION AND FIVE YEAR FORECAST. Moz. Resources. TONGON GOLD MINE TONGON PRODUCTION AND FIVE YEAR FORECAST Cash cost $/oz 900 Production 000oz Capex $ million TONGON TOTAL MINERAL RESOURCES AND ORE RESERVES1 Moz Grade g/t 4 5 800 4 700 3 600 3 500 400

More information

Millennium delivers outstanding operational performance, beating production and cost guidance and achieving 100kozpa run rate

Millennium delivers outstanding operational performance, beating production and cost guidance and achieving 100kozpa run rate Corporate Details Ordinary Shares: 792,144,996 Market Capitalisation: ~$190 million Cash and bullion at 30 September 2018: $17.8 million Debt: $10 million ASX Code: MOY Board of Directors Greg Bittar Non-Executive

More information

For personal use only

For personal use only Corporate Details Ordinary Shares: 792,144,996 Market Capitalisation: ~$190 million Cash and bullion at 30 September 2018: $17.8 million Debt: $10 million ASX Code: MOY Board of Directors Greg Bittar Non-Executive

More information

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX Code: WRM Issued Securities Shares: 441.3 million Options: 100.5 million

More information

Olympias: Highlights Q Phase 1 Retreatment. Acquired from European Goldfields in February. EIA approved. Phase 1 Retreatment began

Olympias: Highlights Q Phase 1 Retreatment. Acquired from European Goldfields in February. EIA approved. Phase 1 Retreatment began Olympias Olympias: Highlights 2011 2012 2013 2016 Q3 2017 EIA approved Acquired from European Goldfields in February Phase 1 Retreatment began Phase 1 Retreatment complete Planned Phase 2 Commercial Production

More information

For personal use only

For personal use only ABN 79 106 879 690 30 August 2016 The Manager Companies ASX Limited 20 Bridge Street Sydney NSW 2000 (11 pages by email) Updated Internal Scoping Study Delivers Positive Results (ASX: AUK) The Directors

More information

ASX ANNOUNCEMENT 12 MAY 2016

ASX ANNOUNCEMENT 12 MAY 2016 ASX ANNOUNCEMENT 12 MAY 2016 FÄBOLIDEN METALLURGICAL TEST WORK IMPROVES RECOVERY LEVELS Dragon Mining Limited (ASX:DRA) ( Dragon Mining or the Company ) is pleased to announce that the second phase of

More information

Prominent Hill 2011 Annual Mineral Resource and Ore Reserve Statement

Prominent Hill 2011 Annual Mineral Resource and Ore Reserve Statement 16 DECEMBER 2011 ASX Release Prominent Hill 2011 Annual Mineral Resource and Ore Reserve Statement OZ Minerals has today released its annual Prominent Hill Mineral Resource and Ore Reserve Statement for

More information

ARM COPPER. Thando Mkatshana Chief Executive: ARM Copper and ARM Coal. Vale/ARM joint venture 50% 50% Refining. Flash/ Isa smelt smelting

ARM COPPER. Thando Mkatshana Chief Executive: ARM Copper and ARM Coal. Vale/ARM joint venture 50% 50% Refining. Flash/ Isa smelt smelting 110 INTEGRATED ANNUAL REPORT 2016 ARM COPPER Thando Mkatshana Chief Executive: ARM Copper and ARM Coal ZCCM-IH 80% 50% 100% 20% Lubambe Copper Mine and Extension Area Vale/ARM joint venture 50% Vale S.A.

More information

Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion. ASX Code : DEG May 2017 Andy Beckwith

Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion. ASX Code : DEG May 2017 Andy Beckwith Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion ASX Code : DEG May 2017 Andy Beckwith De Grey Corporate Snapshot ASX: DEG De Grey Ordinary Shares

More information

Maiden Ore Reserve for Camel Creek JV

Maiden Ore Reserve for Camel Creek JV 10 September 2013 Manager Company Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 ABN 85 003 257 556 Maiden Ore Reserve for Camel

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

EXCO S PROJECT PIPELINE. Unlocking the Value

EXCO S PROJECT PIPELINE. Unlocking the Value EXCO S PROJECT PIPELINE Unlocking the Value EXCO RESOURCES N.L. 20 AUGUST 2010 Wholesale Investors Forum Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking

More information

FIRST QUARTILE CASH COSTS

FIRST QUARTILE CASH COSTS Quarterly Report Period Ending 30 June 2009 FIRST QUARTILE CASH COSTS HIGHLIGHTS: Zinc C1 cash costs US$0.24/lb (after credits) Improved copper concentrate grades Zinc metal production up 22% Silver production

More information

African focussed company developing a new gold project in the world class Ashanti Gold Belt of Ghana

African focussed company developing a new gold project in the world class Ashanti Gold Belt of Ghana A NEW GOLD PROJECT IN THE ASHANTI GOLD BELT OF GHANA DIGGERS AND DEALERS August 2009 COMPANY PROFILE African focussed company developing a new gold project in the world class Ashanti Gold Belt of Ghana

More information

Health and Safety. Update: No LTI at Prestea Open Pits. 5.65M man hours worked with no LTI

Health and Safety. Update: No LTI at Prestea Open Pits. 5.65M man hours worked with no LTI SIMPLE Expanding Production & LEAN and Reducing PRODUCER Costs Health and Safety Update: No LTI at Prestea Open Pits 5.65M man hours worked with no LTI 510 Days as at 31 st Oct without LTI. Last LTI on

More information

Overview. Gold Production and NCE Margin ( E) koz % Durban E. Mineral Reserves & Resources 31 Dec 2010 (Moz)

Overview. Gold Production and NCE Margin ( E) koz % Durban E. Mineral Reserves & Resources 31 Dec 2010 (Moz) South Africa Region Overview Cape Town KDC South Deep Beatrix Bloemfontein Gold Production and NCE Margin (2008 2011E) koz % 2 500 16 2 000 14 12 1 500 10 8 Durban 1000 2,066 2,095 1,866 6 500 4 2 0 0

More information

Massawa gold project January 2016

Massawa gold project January 2016 Massawa gold project January 2016 Senegal permits onto geology SENEGAL N Sadiola Yatela Teranga MALI Kanoumba Massawa Gara Yalea Permits Surface(Km 2 ) Miko Segala Kanoumba 506 Miko 61 Dalema 228.3 Tomboronkoto

More information

Cowal Drilling revolution. CWEDG 18 August 2016 Joe Booth Geology Superintendent- Cowal

Cowal Drilling revolution. CWEDG 18 August 2016 Joe Booth Geology Superintendent- Cowal Cowal Drilling revolution CWEDG 18 August 2016 Joe Booth Geology Superintendent- Cowal Site summary Residential workforce Workforce: 264 employees and 91 contractors Shift roster: 7:7 Mining commenced

More information

VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE

VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE VALUE THROUGH GOLD BRUCEJACK PROJECT PREMIER S NATURAL RESOURCE CONFERENCE January 2016 CAUTIONARY STATEMENT Forward Looking Information This Presentation contains forward-looking information and forward

More information

NEWS RELEASE ROXGOLD ANNOUNCES POSITIVE FEASIBILITY STUDY FOR ITS BAGASSI SOUTH PROJECT

NEWS RELEASE ROXGOLD ANNOUNCES POSITIVE FEASIBILITY STUDY FOR ITS BAGASSI SOUTH PROJECT NEWS RELEASE ROXGOLD ANNOUNCES POSITIVE FEASIBILITY STUDY FOR ITS BAGASSI SOUTH PROJECT Yaramoko annual gold production expected to increase approximately 40% to over 150,000 ounces Toronto, Ontario November

More information

Quarterly Report for Shareholders Period Ending 30 September 2010

Quarterly Report for Shareholders Period Ending 30 September 2010 Quarterly Report for Shareholders Period Ending 30 September 2010 ASX Code: BDR Directors: Craig Readhead Mike Donaldson Jim Jewell Peter Bowler Robert Watkins Greg Barrett Corporate Details: Non-Exec.

More information

QUARTERLY ACTIVITIES REPORT

QUARTERLY ACTIVITIES REPORT Suite 4, Level 3 South Shore Centre 85 South Perth Esplanade South Perth WA 6151 TEL +61 8 6313 3800 FAX +61 8 6313 3888 ABN 38 108 779 782 Silver Lake Resources Ltd ( Silver Lake or the Company ) is pleased

More information

DRDGOLD Annual Report

DRDGOLD Annual Report DRDGOLD Annual Report 21 17 Review of operations DRDGOLD reported two fatalities in FY21 compared with five in the previous year, translating into a 58% improvement in the Fatal Injury Frequency Rate (FIFR)

More information

North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company )

North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company ) North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company ) Namib Project - Mine Development Plan North River is pleased

More information

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES 7 November 2008 UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES Highlights Broken Hill Ore Reserves increase life of mine to 9 years at conservative price assumptions Substantial Resource base

More information

Tri-K feasibility study update

Tri-K feasibility study update Tri-K feasibility study update Feasibility study work to date confirms technical viability of low cash cost operation Mining licence application process commenced, based on technical information submitted

More information

ASX ANNOUNCEMENT 26 February 2013 ASX Code: BDR. MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 584, g/t for 71,000 oz gold

ASX ANNOUNCEMENT 26 February 2013 ASX Code: BDR. MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 584, g/t for 71,000 oz gold ASX ANNOUNCEMENT 2 February 2013 ASX Code: BDR MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 58,000 tonnes @ 3.8 g/t for 71,000 oz gold MAIDEN DUCKHEAD HANGINGWALL STARTER PIT RESERVE 272,000 tonnes @ 3.2

More information

Dalgaranga A Near Term +100,000 ozpa Low Cost and High Margin Gold Project in Western Australia Moving Towards Production

Dalgaranga A Near Term +100,000 ozpa Low Cost and High Margin Gold Project in Western Australia Moving Towards Production Dalgaranga A Near Term +100,000 ozpa Low Cost and High Margin Gold Project in Western Australia Moving Towards Production Sydney Mining Club Presentation September 2017 Disclaimer & Competent Persons Statement

More information

For personal use only

For personal use only Poised to become a +100kozpa Australian gold producer in the Pilbara Region, WA Reaping the rewards of our aggressive exploration commitment and expansion strategy at Nullagine -------------------------------------------

More information

Corporate Overview. Capital Structure Monthly Volume (shares)

Corporate Overview. Capital Structure Monthly Volume (shares) Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve subjective judgement and analysis and are subject to significant

More information

ASX Release Prominent Hill 2012 Annual Mineral Resources and Ore Reserves Statement

ASX Release Prominent Hill 2012 Annual Mineral Resources and Ore Reserves Statement 21 JANUARY 2013 ASX Release Prominent Hill 2012 Annual Mineral Resources and Ore Reserves Statement OZ Minerals has today released its annual Prominent Hill Mineral Resources and Ore Reserves Statement

More information

For personal use only

For personal use only Saracen Mineral Holdings Limited Australian Gold Producer ASX:SAR SARACEN MINERAL HOLDINGS LTD Guido Staltari, Executive Chairman Raleigh Finlayson, Chief Operating Officer Denver Gold Forum Denver, CO

More information

SARACEN MINERAL HOLDINGS LTD

SARACEN MINERAL HOLDINGS LTD Saracen Mineral Holdings Limited Australian Gold Producer ASX:SAR SARACEN MINERAL HOLDINGS LTD Guido Staltari, Executive Chairman Raleigh Finlayson, Chief Operating Officer Denver Gold Forum Denver, CO

More information

AGM - Lorena Gold Project

AGM - Lorena Gold Project AGM - Lorena Gold Project For personal use onlynovember 2015 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors

More information

Forward Looking Statement

Forward Looking Statement Olympias Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation

More information

Base Metals Capability Profile

Base Metals Capability Profile Base Metals Capability Profile About DRA Over more than 30 years, the DRA Group (DRA) has established itself globally as a first tier supplier of engineering and project management services. We work with

More information

Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise)

Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise) NEWS RELEASE ASX: NCM POMSOX: NCM TSX: NM Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise) Melbourne, Australia, August

More information

A Step-Change at Nullagine

A Step-Change at Nullagine A Step-Change at Nullagine Building a +100kozpa Australian gold producer ------------------------------------------- Peter Cash, CEO Corporate Presentation May 2018 1 Disclaimer & Competent Person s Statement

More information