SeaGen Project. Strangford Lough SeaGen Tidal Turbine monitoring programme and mitigation, some initial results

Size: px
Start display at page:

Download "SeaGen Project. Strangford Lough SeaGen Tidal Turbine monitoring programme and mitigation, some initial results"

Transcription

1 SeaGen Project Strangford Lough SeaGen Tidal Turbine monitoring programme and mitigation, some initial results

2 About SeaGen Free stream tidal energy device that converts energy from tidal flow into electricity. Twin 16m diameter rotors connected to a generator through a gearbox, with a rotor system supported on the end of a cross beam. The cross beam is, in turn, supported by a 3m diameter pile. The cross beam can slide vertically up and down the pile to allow access to the rotors, generator and gearbox for servicing and inspection, thus minimising the requirement for diver intervention. The top of the pile is approximately 9m above the average sea level; The twin rotors begin to generate electricity at a current speed greater than 1m/s. At a predetermined maximum tidal speed the rotors start to adjust their pitch to limit the maximum rotational speed to 14 RPM, resulting in a peak rotor tip speed of around 12m/s.

3 Location: Strangford Lough Narrows

4 Strangford Lough Narrows Significant tidal resource; Easy access; Grid connection; QUB marine station; and Local skills base for assembly and O&M. The site is within a European Marine Site and hosts European Protected species.

5 SeaGen: The journey Scoping Report Environmental Statement (ES) Environmental Impact Assessment (EIA) Environmental Action and Safety Management Plan (EASMP) Environmental Monitoring Programme (EMP) Scoping ES EMP EASMP Installation: March 2008 Postinstallation EMP coordination and reporting EIA FEPA licence granted/ re-issued ES addendum Design change: Quadropod base

6 Installation Installation of the moorings for anchoring the SeaGen was completed in March The SeaGen structure was positioned on the seabed on April 2nd 2008 by the crane barge Rambiz. Drilling for the pin piles, grouting and completion of assembly was achieved by late May Commissioning and Operation Commissioning commenced in July 2008, culminating in full 1.2MW power generation to the grid in December Operation is within the constraints of FEPA license conditions with the environmental monitoring and mitigation results contributing to an adaptive management strategy, advised by an independently chaired Science Group, where findings are periodically reviewed and improvements to the application of the FEPA restrictions are made.

7 Environmental Impact Assessment The EIA process identified various levels of uncertainty surrounding potential impacts on key marine species and features within the Strangford Lough Special Area of Conservation (SAC) Common seals Phoca vitulina 1) Are the patterns of usage of the Narrows by seals altered by the turbine installation and operation? 2) Are seals (or other large marine animals) being struck by the turbine rotors? Reef (rocky and biogenic) 1) Does the installation and operation of the turbine significantly effect the extent, quality or composition of seabed communities?

8 FEPA License Conditions Put required a number of tiers of mitigation, to summarise key elements : MMO presence on pile with ability to shutdown; Daylight operation only, initially; Active sonar development as further tier of mitigation. An adaptive management approach has been taken to operation of the device and the operation of the mitigation measures via advice of the SeaGen Science Group. More on this later!

9 Monitoring Mammal Northern Irish Coast study site - Aerial surveys (SMRU) - Harbour seal telemetry (SMRU) - Shoreline surveys Strangford Narrows study site - Shore-based visual surveys (QUB/SMRU) - TPOD monitoring (SMRU) Benthic Ecology Monitoring (RH and QUB) ADCP surveys (QUB) Mitigation - Active Sonar (SMRU) - Pile-based Marine Mammal Observation (RH)

10 Biannual Report (July 2009) Key environmental questions Set of operational objectives which are reported against Monitoring results Next report January

11 So, what have we found so far?

12 Marine mammals and sharks Effort limited visual surveys (QUB) Analysis of monitoring during the installation and initial commissioning period indicate that: Time of day, tidal state and spatial location all significant influences on data. No evidence for human disturbance effects during installation and no evidence for a change in seal abundance in the area during times of lower activity; and The natural variability in the system under study is large, which makes disentangling the effects of the turbine challenging. The level of survey effort has currently been increased to maximise the power of the current monitoring programme to detect genuine changes in marine mammal abundance Tidal Cycle Combined POD data Visual Observations

13 Marine mammals Passive acoustic monitoring (SMRU) Using T-PODs - to provide continuous data on harbour porpoise activity in proximity to SeaGen. Preliminary examination of the effect of limited turbine activity between July 2008 and May 2009 does not suggest any dramatic impact on porpoise activity; In the Narrows significantly more days without porpoise detections during the operational period compared to the baseline, however this may be an underlying seasonal effect; Detection Positive Minutes (DPM) per day lower within the Narrows and inner Lough during the operational period (July 2008 May 2009) compared to the pre-installation baseline period; No significant difference in the number of porpoise positive days recorded by PODs north and south of the turbine for either the pre-installation or operational period, indicating that SeaGen does not present a barrier effect; Tidal Cycle Combined POD data Visual Observations

14 Monitoring - Harbour seals Aerial survey outputs Distribution of seal haul out sites within and around Strangford Lough Abundance of seals surveyed during moult (August/Sept) and breeding season (November) SMRU Ltd Moult surveys in 2006 and 2007 show similar counts of harbour seals over the whole survey area; The number of hauled-out harbour seals was variable both within and between years; 2008 the breeding season adult counts for the Lough and Narrows were higher than in The pup counts also increased, as they did in other regions; SMRU Ltd

15 Monitoring - Harbour seals cont. Aerial survey outputs Overall more pups were counted in relation to adults in 2008 than in 2006 The consistent increase in numbers of pups in relation to adults across the whole survey area indicates that the Strangford Lough and Narrows counts showed changes consistent with the wider survey area; Grey seals are much less abundant in the survey area than harbour seals and numbers counted within each sub-region are variable within and between years, although there has been a general increase in numbers of grey seals since SMRU Ltd SMRU Ltd The increase in the number of adults and pups in the Narrows and Strangford Lough potentially indicates that the installation phase of the turbine did not cause any displacement of the seals prior to the 2008 breeding season.

16 Monitoring - Harbour seals GSM satellite tracking outputs 12 animals tagged in March 2006, 2008 and planned 2010 In 2008, as in 2006 there was considerable between-seal variability in movement data, but consistency within individuals; Some individuals travelled to distant haul out sites in the Irish Sea and clearly forage outside Strangford Lough. This indicates that seals in Strangford Lough/Narrows are not ecologically isolated from the remaining North Ireland population; SMRU Ltd SMRU Ltd No evidence for a change in daily transit rates past the turbine between years;

17 Monitoring - Harbour seals cont. GSM satellite tracking outputs There was no significant difference in the probability of hauling out within the Narrows between years; SMRU Ltd There was no evidence for a change in overall usage patterns between years, with usage concentrated in the Narrows and south of the Lough With just two years of data the effect of the installation and operation of the turbine cannot be separated from natural inter-annual variability. SMRU Ltd

18 Monitoring - Shoreline surveillance Incidental strandings: managed by NIEA None reported November 2008 to spring 2009 Standardised beach surveys: managed by QUB No surveys between September 2008 May 2009 due to SeaGen down time Weekly surveys re-commenced at the start of June All common seal, grey seal and harbour porpoise carcasses found within the study site have been post-mortemed by a Vet Pathologist at Stormont. No post mortem evidence for any carcasses is suggestive of interaction with the SeaGen turbine.

19 Robust Environmental Action Plan (Designed and coordinated by Royal Haskoning) Scenario tree

20 Monitoring - Benthic Ecology Broad scale mapping and diver surveys have significantly increased our knowledge of the seabed in the Narrows in proximity to the turbine Enabled the RH team to quantify the potential footprint of the installation, operational and decommissioning phases Benthic Monitoring The monitoring programme objective is to detect broad change in the benthic community structure (e.g. abundance shifts in dominant or characterising species) that may arise from increased sedimentation, changes in scour or flow pattern, or through direct physical damage.

21 Monitoring - Benthic ecology cont. The status of the seabed close to the turbine has been assessed on the basis of three sample time points; the first a pre-installation survey in March/April 2008, followed by a post-installation survey in July 2008 and the third in March 2009, just after the start of turbine operation. Communities at each sampling time and at all stations were different from the communities recorded at the previous sampling times, but changes largely due to subtle abundance adjustment; Dominant taxa (hydroids and sponges) in the pre-installation samples have maintained dominance throughout the following monitoring visits; Community changes across all stations broadly similar over time and are largely mirrored in the reference station. Data support a conclusion that the observed changes over the three sample times are relatively minor and result of a combination of normal seasonal variation and natural species competition and succession.

22 Mitigation - Pile-based MMO observations The MMO programme was primarily established as a mitigation measure, guarding against potentially harmful marine mammal interactions with the SeaGen turbine. An established systematic quantitative sightings protocol using a spatial grid system has, however, provided useful qualitative data on mammal activity close to SeaGen and has proved an important calibration element for the active sonar system. Confirm presence of marine mammal, shut down as appropriate, make detailed record of sightings (with focal follows of sightings within 200m) Provide detailed information relating to the behaviour and movements of marine mammals and sharks in proximity to the SeaGen turbine Date Species SeaGen operational activity (twin/ single rotor) Distance from turbine (m) Behaviour State of tide E-stop initiated by? 1 08/07/2008 Common seal Single 130 Drifting Flood MMO 2 06/10/2008 Common seal Single 50 Drifting Flood MMO 3 07/10/2008 Unidentified target Single 60 Travelling Flood ASO 4 15/10/2008 Common seal Single 80 Drifting HW Slack + 1 hr MMO 1 1 hr: 16 mins before HW Slack, 2 1 hr: 9 mins before HW slack, 3 1 hr: 10 mins before HW slack, 4 1 hr: 30 mins before HW slack 5 15/12/2008 Common seal Twin 50 Travelling HW Slack + 1 hr MMO 6 13/05/2009 Common seal Single 40 Drifting Flood 1 MMO 7 27/05/2009 Common seal Twin 40 Travelling Flood 2 MMO 8 27/05/2009 Common seal Twin 80 Milling Flood 3 MMO 9 27/05/2009 Common seal Twin 70 Travelling Flood 4 ASO 10 08/06/2009 Common seal Twin 40 Travelling Ebb ASO 11 10/06/2009 Common seal Twin 80 Drifting HW Slack + 1 hr MMO 12 22/06/2009 Common seal Twin 38 Travelling LW Slack + 1 hr ASO 13 02/07/2009 Common seal Twin 20 Travelling Ebb MMO 14 02/07/2009 Unidentified target Twin 44 Travelling Ebb ASO 15 06/07/2009 Common seal Twin 40 Travelling Flood MMO

23 Mitigation - Pile-based MMO observations cont. Confirm presence of marine mammal, shut down as appropriate, make detailed record of sightings (with focal follows of sightings within 200m). Provides detailed information relating to the behaviour and movements of marine mammals and sharks in proximity to the SeaGen turbine MMO surveys from SeaGen throughout operation until September 2009 Over 381 hours of survey, equates to approximately 55 days of survey effort (based on an average of 7 hours survey per day), between 8th July th June 2009 Shut down limit gradually reduced by Science Group from 200 to 50m based on data collected Date Species SeaGen Since July 2008 to July shutdowns MMO mitigation suspended in September and replaces with active sonar based on Science Group advice with NIEA agreement operational activity (twin/ single rotor) Distance from turbine (m) Behaviour State of tide E-stop initiated by? 1 08/07/2008 Common seal Single 130 Drifting Flood MMO 2 06/10/2008 Common seal Single 50 Drifting Flood MMO 3 07/10/2008 Unidentified target Single 60 Travelling Flood ASO 4 15/10/2008 Common seal Single 80 Drifting HW Slack + 1 hr MMO 5 15/12/2008 Common seal Twin 50 Travelling HW Slack + 1 hr MMO 6 13/05/2009 Common seal Single 40 Drifting Flood 1 MMO 7 27/05/2009 Common seal Twin 40 Travelling Flood 2 MMO 8 27/05/2009 Common seal Twin 80 Milling Flood 3 MMO 9 27/05/2009 Common seal Twin 70 Travelling Flood 4 ASO 10 08/06/2009 Common seal Twin 40 Travelling Ebb ASO 11 10/06/2009 Common seal Twin 80 Drifting HW Slack + 1 hr MMO 12 22/06/2009 Common seal Twin 38 Travelling LW Slack + 1 hr ASO 13 02/07/2009 Common seal Twin 20 Travelling Ebb MMO 14 02/07/2009 Unidentified target Twin 44 Travelling Ebb ASO 15 06/07/2009 Common seal Twin 40 Travelling Flood MMO

24 SMRU Ltd SMRU Ltd Mitigation - Active sonar (SMRU) Coordinated alongside MMO observations, allowing calibration. Trail of real time sub-surface sonar imagery of seals, cetaceans and basking sharks close to the SeaGen. Manned operation, initially on pile alongside MMO, now remotely. Detection from 80m, well within shut down action distance of 50m Now demonstrated effectiveness, removed MMOs and 24 hour operation. Next investigate mammal behaviour at night eventually remove shutdown protocol

25 Active sonar (SMRU) cont. Relationship between MMO and ASO records of marine mammal activity throughout the tidal cycle. Majority of marine mammal activity occurs around slack water. No noticeable difference between activity during turbine operation & nonoperation. Apparent over recording using active sonar. Possible under recording using MMO. SMRU Ltd SMRU Ltd

26 Summary of key findings: Shore based surveys during installation show no evidence for increased human disturbance or a change in relative seal abundance in the area; MMO and shore based observation data show low incidence of seal and porpoise sightings in the central portion of Strangford Narrows; Active sonar can detect marine mammals birds in real time. No seal carcasses to date have exhibited signs of any possible interaction with SeaGen; Aerial surveys during the 2008 breeding and moult seasons found an increase in the number of harbour seal adults and pups in the Narrows and Strangford Lough, suggesting installation did not cause displacement prior to the 2008 breeding season;

27 The key findings cont: TPOD data indicated lower detection positive minutes for harbour porpoises in the Narrows and inner Lough during the operational phase (July 2008 May 2009) compared to the pre-installation baseline. There has, however, been limited turbine activity during the operational phase and the reduced detection may be the result of an underlying seasonal variation. There was no difference in porpoise positive days to the north and south of the turbine indicating that SeaGen does not present a barrier effect to harbour porpoises. Harbour seal telemetry data shows no evidence of change in haul out behaviour within the Narrows or transit rates past the turbine; and Benthic community monitoring has detected no change in seabed communities attributable to the SeaGen installation or operation.

28 Finally - some interesting SeaGen facts SeaGen has already delivered over 350MWh of power into the Northern Irish electricity grid. The twin generators typically produce an average of 5MWh of electricity during the 6¼ hours of each ebb and each flood tide. This is enough energy to meet the average electricity needs for 1500 UK homes. The SeaGen turbine is officially accredited by OFGEM as a UK power station, the first tidal power system to secure this. SeaGen is earning revenue from the sale of the power that is being generated and it also earns ROCs, the Renewable Obligation Certificates that are awarded for clean renewable generation.

29

30 Seagen Marine Mammal Mitigation Marine Mammal Observation and Active Sonar Data

31 Background Data collected between 08 July 2008 and 16 July Data collection continues during ongoing mitigation. MMO data filtered to within estimated 80m of Seagen (range of the active sonar). Provides relatively low no. of records (75 MMO sightings and 216 Active Sonar Operator records).

32 MMO sightings & potential for interaction with SeaGen Sightings categorised by potential likelihood of interacting with rotors : High less than 50m from the turbine resulting in the turbine being shutdown. Moderate between 50-80m from the turbine & no shutdown instigated. Turbine not turning.

33 MMO sightings & potential for interaction with SeaGen cont. 35 Number of sightings at less than 100m distance compared with state of tide for high* or moderate** potential interaction with turbine rotors Low water High water High Moderate Not Turning TOTAL No. of sightings LW - 2-3hrs LW - 1-2hrs LW - 0-1hrs LW + 0-1hrs LW + 1-2hrs LW + 2-3hrs HW - 2-3hrs HW - 1-2hrs HW - 0-1hrs HW + 0-1hrs HW + 1-2hrs HW + 2-3hrs

34 MMO sightings during Seagen operation and non-operation 35 MMO sightings during operation and non-operation Low water High water Turning Not turning TOTAL No. sightings LW - 2-3hrs LW - 1-2hrs LW - 0-1hrs LW + 0-1hrs LW + 1-2hrs LW + 2-3hrs HW - 2-3hrs HW - 1-2hrs HW - 0-1hrs HW + 0-1hrs HW + 1-2hrs HW + 2-3hrs

35 Active Sonar records Sonar records confirmed and unconfirmed by MMO Low water High water Confirmed sightings Unconfirmed records TOTAL 25 No. sightings LW - 2-3hrs LW - 1-2hrs LW - 0-1hrs LW + 0-1hrs LW + 1-2hrs LW + 2-3hrs HW - 2-3hrs HW - 1-2hrs HW - 0-1hrs HW + 0-1hrs HW + 1-2hrs HW + 2-3hrs

36 Active sonar and MMO records 35 Low water Total sonar compared with total MMO records High water 30 MMO sightings ASO records 25 No. sightings LW - 2-3hrs LW - 1-2hrs LW - 0-1hrs LW + 0-1hrs LW + 1-2hrs LW + 2-3hrs HW - 2-3hrs HW - 1-2hrs HW - 0-1hrs HW + 0-1hrs HW + 1-2hrs HW + 2-3hrs

37 Summary Relationship between MMO and ASO records of marine mammal activity throughout the tidal cycle. Majority of marine mammal activity occurs around slack water. No noticeable difference between activity during turbine operation & non-operation. Apparent over recording using active sonar. Possible under recording using MMO.

38 Conclusions Active sonar expected to provide conservative mitigation. No apparent need for an MMO to be present. ASO could provide mitigation through night.

ADCP monitoring seagen tidal turbine

ADCP monitoring seagen tidal turbine Nortek European Users Symposium Oslo, 2010 ADCP monitoring seagen tidal turbine Cuan Boake Senior Research Fellow Marine Energy Research Group (QUB) Agenda Seagen Project ADCP Monitoring for Seagen Resource

More information

The use of ADCP data from the Inner Bristol Channel, UK and CFD to study power attenuation effects on HATT performance

The use of ADCP data from the Inner Bristol Channel, UK and CFD to study power attenuation effects on HATT performance The use of ADCP data from the Inner Bristol Channel, UK and CFD to study power attenuation effects on HATT performance 1 Mason-Jones, A., 1 O Doherty, D. M., 1 O Doherty, T., 2 Evans, P. S., 2 Wooldridge

More information

Experience from the UK: Monitoring, Modelling and Uncertainty

Experience from the UK: Monitoring, Modelling and Uncertainty Experience from the UK: Monitoring, Modelling and Uncertainty Lucy Greenhill Offshore Industries Advisor Joint Nature Conservation Committee (JNCC) Symposium: Towards an Environmentally Sound Offshore

More information

Welcome to Fair Head Tidal Information Day

Welcome to Fair Head Tidal Information Day Welcome to Fair Head Tidal Information Day Fair Head Tidal (FHT) was awarded an Agreement for Lease from The Crown Estate in 2012 which grants it exclusive rights to carry out surveys on the site and,

More information

Walney Extension Offshore Wind Farm

Walney Extension Offshore Wind Farm WALNEY EXTENSION OFFSHORE WIND FARM Walney Extension Offshore Wind Farm Statement of Common Ground Between: 1. DONG Energy Walney Extension (UK) Limited 2. Whale and Dolphin Conservation In relation to

More information

Wave & Tidal Consenting Position Paper Series. Marine Mammal Impacts

Wave & Tidal Consenting Position Paper Series. Marine Mammal Impacts Wave & Tidal Consenting Position Paper Series Marine Mammal Impacts Contents Background 4 Key Issues 5 Key Impacts 7 Impact Mitigation 13 Key Research 14 Recommendations 17 References 19 authors Paper

More information

Marine Renewable Energy and the Environment: Progress and Challenges

Marine Renewable Energy and the Environment: Progress and Challenges Marine Renewable Energy and the Environment: Progress and Challenges Brian Polagye Assistant Professor Department of Mechanical Engineering University of Washington Northwest National Marine Renewable

More information

Technologies for Marine Energy Extraction

Technologies for Marine Energy Extraction Technologies for Marine Energy Extraction Stephanie Merry Renewable Energy Association Today s presentation Government and EU targets for electricity generation mix The marine energy resource Technologies

More information

Pilot Project Licensing Justification Statement

Pilot Project Licensing Justification Statement Pilot Project Licensing Justification Statement The following demonstrates that the Snohomish County Public Utility District No. 1 (Snohomish) Admiralty Inlet Pilot Tidal Project (the Project ) meets the

More information

A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland. December 2013 Version 1.3

A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland. December 2013 Version 1.3 A Risk Assessment Framework for Fisheries in Natura 2000 sites in Ireland December 2013 Version 1.3 1 Contents Introduction... 3 DPSIR Framework (Drivers, Pressures, States, Impacts, Responses)... 3 Components

More information

Framework Ecology and Cumulation

Framework Ecology and Cumulation Framework Ecology and Cumulation, Ministry of Infrastructure and Environment, Commissioned by: Ministry of Economic Affairs Why assessing cumulative effects of offshore wind farm development? Plans for

More information

Tidal Energy Exploration in Puget Sound

Tidal Energy Exploration in Puget Sound Tidal Energy Exploration in Puget Sound Project Objectives Objective is to generate relevant data to better evaluate the technical, economic, and environmental feasibility of tidal energy generation. Project

More information

Floating Tidal Instream Energy Jason Hayman, Dr. Ralf Starzmann Sustainable Marine Energy & SCHOTTEL HYDRO Manila, June 2018

Floating Tidal Instream Energy Jason Hayman, Dr. Ralf Starzmann Sustainable Marine Energy & SCHOTTEL HYDRO Manila, June 2018 Floating Tidal Instream Energy Jason Hayman, Dr. Ralf Starzmann Sustainable Marine Energy & SCHOTTEL HYDRO Manila, June 2018 Hydrokinetic Energy Global Market Opportunity The Philippines KEY MARKET FACTS

More information

Kentish Flats Offshore Wind Farm

Kentish Flats Offshore Wind Farm Kentish Flats Offshore Wind Farm A pure spot on the Map of the World Kentish Flats Offshore Wind Farm features 30 wind-powered turbines each with a nominal rated capacity of 3 MW making a net capacity

More information

Advancing Tidal Research Initiatives for Nova Scotia

Advancing Tidal Research Initiatives for Nova Scotia Issue 3 Spring 2011 Advancing Tidal Research Initiatives for Nova Scotia Cape Split on Flood Tide Photo Credit: Colin Buhariwalla, Acadia University In this issue of Currents OEER Association (OEER) is

More information

A POSITIVE FUTURE FOR PORPOISES AND RENEWABLES. Assessing the benefits of noise reduction to harbour porpoises during offshore wind farm construction.

A POSITIVE FUTURE FOR PORPOISES AND RENEWABLES. Assessing the benefits of noise reduction to harbour porpoises during offshore wind farm construction. PHOTO FLORIAN GRANER / NATUREPL / WWF A POSITIVE FUTURE FOR PORPOISES AND RENEWABLES Assessing the benefits of noise reduction to harbour porpoises during offshore wind farm construction. September 2016

More information

Bioacoustics Research. Dr Paul Lepper - Loughborough University

Bioacoustics Research. Dr Paul Lepper - Loughborough University Bioacoustics Research Dr Paul Lepper - Loughborough University Underwater noise and impact research In relation to the underwater energy, Good Environmental Status certainly occurs when there is no adverse

More information

Environmental monitoring at Havsul-1

Environmental monitoring at Havsul-1 Environmental monitoring at Havsul-1, Marie-Lise Schläppy, Aleksej Shashkov, Mathias Andersson, Yuri Rzhanov, Ilker Fer and Erling Heggøy Presented by Dominique Durand Uni Research Why wind farms at exposed

More information

Marine Renewable Energy

Marine Renewable Energy Policy Marine Renewable Energy Scope of this policy 1. This policy should be read in conjunction with SWT s policy Energy and Nature Conservation (2007). It updates that policy in certain areas in response

More information

Guidance on Survey and Monitoring in Relation to Marine Renewables Deployments in Scotland Volume 3: Seals

Guidance on Survey and Monitoring in Relation to Marine Renewables Deployments in Scotland Volume 3: Seals Guidance on Survey and Monitoring in Relation to Marine Renewables Deployments in Scotland Volume 3: Seals This report was produced by SMRU Ltd and Royal Haskoning on behalf of Scottish Natural Heritage

More information

WP2: ENVIRONMENTAL ASPECTS RESULTS AND OUTCOMES

WP2: ENVIRONMENTAL ASPECTS RESULTS AND OUTCOMES WP2: ENVIRONMENTAL ASPECTS RESULTS AND OUTCOMES WP Objectives Investigate the best locations for different tidal energy systems with regards to: Energy extraction potential Environmental effects WP Rationale

More information

OSPAR Guidance on Environmental Considerations for Offshore Wind Farm Development

OSPAR Guidance on Environmental Considerations for Offshore Wind Farm Development OSPAR CONVENTION FOR THE PROTECTION OF THE MARINE ENVIRONMENT OF THE NORTH-EAST ATLANTIC OSPAR Guidance on Environmental Considerations for Offshore Wind Farm Development (Reference number: 2008-3) 1 Table

More information

Offshore Wind: Ecological risks and opportunities

Offshore Wind: Ecological risks and opportunities Offshore Wind: Ecological risks and opportunities Guido Schild Nathalie Strookman Offshore wind: Ecological risks and opportunities 1. Status of offshore wind in the Netherlands 2. Ecological risks 3.

More information

Techniques for Marine Biological Baseline Data Collection at Offshore Renewable Energy Developments and How Best to Apply These to Guernsey Waters

Techniques for Marine Biological Baseline Data Collection at Offshore Renewable Energy Developments and How Best to Apply These to Guernsey Waters Techniques for Marine Biological Baseline Data Collection at Offshore Renewable Energy Developments and How Best to Apply These to Guernsey Waters By Seumas MacKenzie Thesis submitted to Plymouth University

More information

Firth of Tay & Eden Estuary Special Area of Conservation

Firth of Tay & Eden Estuary Special Area of Conservation Firth of Tay & Eden Estuary Special Area of Conservation Advice under Regulation 33(2) of The Conservation (Natural Habitats, &c.) Regulations 1994 (as amended) 30 March 2006 About this Package: Section

More information

Feasibility Study and Cost-Benefit Analysis of Tidal Energy: A Case Study for Ireland

Feasibility Study and Cost-Benefit Analysis of Tidal Energy: A Case Study for Ireland Feasibility Study and Cost-Benefit Analysis of Tidal Energy: A Case Study for Ireland D. Jackson 1 and T. Persoons 2 1 Dept. of Mechanical and Manufacturing Engineering, University of Dublin, Trinity College,

More information

LSI Toolbox. Heidi Roberts.

LSI Toolbox. Heidi Roberts. LSI Toolbox Heidi Roberts hroberts@abpmer.co.uk Name of presentation Integration of LSI into MSP and associated SEA Practical Toolbox for Practitioners on LSI Easily applied within any admin. or governance

More information

Offshore Renewables. Harnessing the energy at sea. Metocean conditions. Model testing. Habitat impact. Environmental impact. Survey and monitoring

Offshore Renewables. Harnessing the energy at sea. Metocean conditions. Model testing. Habitat impact. Environmental impact. Survey and monitoring Offshore Renewables Harnessing the energy at sea Metocean conditions Habitat impact Model testing Environmental impact Survey and monitoring Forecasting Energy resources Offshore renewable energy DHI is

More information

Falmouth Marina Dredging - Environmental Impact Assessment

Falmouth Marina Dredging - Environmental Impact Assessment Falmouth Marina Dredging - Environmental Impact Assessment Environmental Statement Non-Technical Summary Hyder Consulting (UK) Limited 2212959 Firecrest Court Centre Park Warrington WA1 1RG United Kingdom

More information

Consenting, EIA and HRA Guidance for Marine Renewable Energy Developments in Scotland

Consenting, EIA and HRA Guidance for Marine Renewable Energy Developments in Scotland Consenting, EIA and HRA Guidance for Marine Renewable Energy Developments in Scotland Scottish Environment LINK is the forum for Scotland's voluntary environment organisations, with over 30 member bodies

More information

Draft Resolution: Ocean Energy

Draft Resolution: Ocean Energy Agenda Item 6.2.2 Further Implementation of the Agreement Conservation Issues Document 6.2.2 Draft Resolution: Action Requested Review the draft Resolution Introduce any changes as desired Adopt the Resolution

More information

Gwynt y Môr Offshore Wind Farm

Gwynt y Môr Offshore Wind Farm Gwynt y Môr Offshore Wind Farm Environmental Statement Non Technical Summary November 2005 Contents 3 Introduction 3 Purpose of this document 3 Background to the proposal 5 The need for Gwynt y Môr 6 Outline

More information

Northwest National Marine Renewable Energy Center

Northwest National Marine Renewable Energy Center Northwest National Marine Renewable Energy Center Riding the Tide: Tidal Power Development in Puget Sound March 9, 2010 Brian Polagye Research Assistant Professor University of Washington Overview Devices

More information

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE

Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE 1. Introduction Poole Harbour Channel Deepening and Beneficial Use Review of Physical monitoring in Poole Bay Technical Note 1 WITHOUT PREJUDICE This technical note reviews the physical data that was collected

More information

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht MARINE NATURA IMPACT STATEMENTS IN IRISH SPECIAL AREAS OF CONSERVATION A WORKING DOCUMENT APRIL 2012 Prepared by the National Parks & Wildlife Service of the Department of Arts, Heritage & the Gaeltacht

More information

London Array: the world s largest operational offshore wind farm

London Array: the world s largest operational offshore wind farm Case Study 1st published in January 2015 ISSN 2056-4007 www.ietdl.org : the world s largest operational offshore wind farm Operations & Maintenance Base Abstract The is the world s largest offshore wind

More information

Study of the environmental impacts of noise, vibrations and electromagnetic emissions from marine renewables - RTD-K MRE

Study of the environmental impacts of noise, vibrations and electromagnetic emissions from marine renewables - RTD-K MRE Study of the environmental impacts of noise, vibrations and electromagnetic emissions from marine renewables - RTD-K3-2012-MRE Thomsen, F., Gill, A., Kosecka, M., Andersson, M.H., Andre M., Degraer, S.,

More information

Tidal Hydrokinetic Energy

Tidal Hydrokinetic Energy Tidal Hydrokinetic Energy Brian Polagye Research Assistant Professor University of Washington September 23, 2010 Tidal Energy Challenges Northwest National Marine Renewable Energy Center Tidal Energy Barrage

More information

Offshore wind & the environment: the UK planning system. January 2012 Emma Cole

Offshore wind & the environment: the UK planning system. January 2012 Emma Cole Offshore wind & the environment: the UK planning system January 2012 Emma Cole Summary Drivers and ambitions Market and deployment The regulatory framework (More) planning reform Challenges Drivers and

More information

Maintenance Dredging 2015 Environmental Monitoring Report

Maintenance Dredging 2015 Environmental Monitoring Report Maintenance Dredging 2015 Environmental Monitoring Report 1208_001/1_Rev0 July 2015 P:\SouthernPorts\1208_PortAlbanyMaintDredging\001_OriginalScope\Reports\ReportFolder_EnvironmentalMonitoring\AlbanyPorts20

More information

Berth 9 Quay Extension Environmental Statement Non-Technical Summary

Berth 9 Quay Extension Environmental Statement Non-Technical Summary Berth 9 Quay Extension Hutchison Ports UK Ltd July 2013 Final Report 9Y0150 CONTENTS Page 1 PROJECT BACKGROUND 1 2 NEED FOR THE PROPOSED SCHEME 4 3 DESCRIPTION OF THE CONSTRUCTION PHASE 4 4 DESCRIPTION

More information

Engineering Research Needs & Links to Science

Engineering Research Needs & Links to Science Engineering Research Needs & Links to Science OEER/FORCE Tidal Energy Workshop October 14, 2010 Scientific Research to Date FORCE To achieve environmental approval Bathymetry/current data from BIO: External

More information

Risk-Based Assessments of Fisheries in MPAs

Risk-Based Assessments of Fisheries in MPAs Risk-Based Assessments of Fisheries in MPAs Suzannah Walmsley, ABPmer Common Language Group, 22 March 2016 Overview Background to project Overview of methodology Summary conclusions for case study sites

More information

Emission-Free Electricity from the World s Rivers and Seas

Emission-Free Electricity from the World s Rivers and Seas Emission-Free Electricity from the World s Rivers and Seas Presentation for the: Second Annual Cobscook Bay Conference Renewable Energy in Maine Communities The Boat School on Deep Cove Road, Eastport

More information

Consultation. The Approach to Environmental Impact Assessment. Neart na Gaoithe Offshore Wind Farm Environmental Statement. 6.

Consultation. The Approach to Environmental Impact Assessment. Neart na Gaoithe Offshore Wind Farm Environmental Statement. 6. Chapter 6 The Approach to Environmental Impact Assessment 6.1 Introduction 1 Under European legislation, transposed into UK and Scottish law (see Chapter 3: Regulatory and Policy Context for further information),

More information

Appendix 4.2. Outline Operation Environmental Management Plan

Appendix 4.2. Outline Operation Environmental Management Plan Appendix 4.2 Outline Operation Environmental Management Plan Tidal Lagoon Swansea Bay Appendix 4.2 The Outline Operational Environmental Management Plan (Outline OEMP) idal Lagoon Swansea Bay Operation

More information

LID6 Environmental Statement On behalf of Lincs Wind Farm Limited. Non-Technical Summary May Produced in association with

LID6 Environmental Statement On behalf of Lincs Wind Farm Limited. Non-Technical Summary May Produced in association with On behalf of Lincs Wind Farm Limited Non-Technical Summary May 2010 Produced in association with Non-Technical Summary Introduction This document provides a Non-Technical Summary (NTS) of the Environmental

More information

Chapter 8.0 Coastal Processes, Sediment Transport and Contamination

Chapter 8.0 Coastal Processes, Sediment Transport and Contamination Chapter 8.0 Coastal Processes, Sediment Transport and Contamination www.tidallagoonswanseabay.com www.tidallagooncardiff.com 8.0 Coastal Processes, Sediment Transport and Contamination 8.1 Overview of

More information

12. Environmental management

12. Environmental management 12. Environmental management 12.1 Overview This section summarises the framework for managing environmental risks associated with construction, commissioning and operation of the Project. It also includes

More information

Beatrice Offshore Wind Farm Environmental Statement Addendum

Beatrice Offshore Wind Farm Environmental Statement Addendum Beatrice Offshore Wind Farm Environmental Statement Addendum Non Technical Summary May 2013 Beatrice Offshore Wind Farm Non Technical Summary CONTENTS 1 INTRODUCTION... 1 2 ENVIRONMENTAL IMPACT ASSESSMENT

More information

Contents 1. Introduction HSE Studies Design of Environmental Parameters Monitoring System Environmental Parameters and

Contents 1. Introduction HSE Studies Design of Environmental Parameters Monitoring System Environmental Parameters and WEST PATRAIKOS LEASE AREA ENVIRONMENTAL REPORT 2018 Contents 1. Introduction... 3 2. HSE Studies... 4 2.1. Design of Environmental Parameters Monitoring System... 4 2.2. Environmental Parameters and Monitoring

More information

GUIDELINES FOR MINIMISING ACOUSTIC DISTURBANCE TO MARINE MAMMALS FROM SEISMIC SURVEYS. April 2004

GUIDELINES FOR MINIMISING ACOUSTIC DISTURBANCE TO MARINE MAMMALS FROM SEISMIC SURVEYS. April 2004 JOINT NATURE CONSERVATION COMMITTEE Marine Advice Dunnet House 7 Thistle Place ABERDEEN AB10 1UZ Tel: 01224 655716 E-mail: seismic@jncc.gov.uk Website: www.jncc.gov.uk/marine GUIDELINES FOR MINIMISING

More information

xxxxxx xxxxxx VOLUME 5: FOLDER 1 Consultation Report Chapter 4. PHASE 1B: EIA scoping

xxxxxx xxxxxx VOLUME 5: FOLDER 1 Consultation Report Chapter 4. PHASE 1B: EIA scoping xxxxxx xxxxxx VOLUME 5: FOLDER 1 Consultation Report Chapter 4. PHASE 1B: EIA scoping www.tidallagoonswanseabay.com www.tidallagoonswanseabay.com Consultation Report Chapter 4 Tidal Lagoon Swansea Bay

More information

Seismic Surveys & Marine Mammals

Seismic Surveys & Marine Mammals REPORT 576 JANUARY 2017 Seismic Surveys & Marine Mammals Joint IOGP/IAGC position paper The oil and gas and geophysical industries are committed to operating in an environmentally responsible manner. This

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Chapter. Biological Environment MARINE MAMMALS. Contents

Chapter. Biological Environment MARINE MAMMALS. Contents Contents Contents... i List of Tables... iii List of Figures... v Abbreviations and Acronyms... vi.1 Introduction... 1.2 Consultation... 1.3 Legislation and Policy... 7.3.1 Legislation... 7.3.2 Policy...

More information

8. Risk Assessment Process

8. Risk Assessment Process 134 Browse FLNG Development Draft Environmental Impact Statement 8. Risk Assessment Process This section provides an overview of the EIA process undertaken for the Browse FLNG Development, from identification

More information

Environmental Monitoring & Management Plans

Environmental Monitoring & Management Plans Environmental Monitoring & Management Plans Trans-Tasman Resources Ltd Iron Sand Extraction Project South Taranaki Bight Summary of Evidence: Daniel Govier 1 Environmental Monitoring Overview Evidence

More information

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and

More information

A positive experience from Great Britain and Northern Europe: Best Practice in Offshore Wind Farm environmental impact assessment

A positive experience from Great Britain and Northern Europe: Best Practice in Offshore Wind Farm environmental impact assessment A positive experience from Great Britain and Northern Europe: Best Practice in Offshore Wind Farm environmental impact assessment Adrian Judd Cefas POWERED IPA Adriatic Project Seminar 11 th October 2013,

More information

Deepwater Wind was awarded a 20 year contract (PPA) to supply power to LIPA in East Hampton. 90 MW wind farm located 30 miles east of Montauk

Deepwater Wind was awarded a 20 year contract (PPA) to supply power to LIPA in East Hampton. 90 MW wind farm located 30 miles east of Montauk Deepwater Wind was awarded a 20 year contract (PPA) to supply power to LIPA in East Hampton 90 MW wind farm located 30 miles east of Montauk Will power 50,000 typical homes Allows LIPA to defer construction

More information

SENSE - Self Erecting Nacelle and Service System Estimated Cost Savings

SENSE - Self Erecting Nacelle and Service System Estimated Cost Savings - Self Erecting Nacelle and Service System Estimated Cost Savings 1. Modelling Work This document sets out the preliminary final results from the combined cost and marine operations modelling undertaken

More information

Summary of Suggested Mitigation and Monitoring

Summary of Suggested Mitigation and Monitoring Chapter 25 Summary of Suggested Mitigation and Monitoring 25.1 Introduction 1 Mainstream Renewable Power (Mainstream) is committed to being a good neighbour and creating and maintaining a harmonious relationship

More information

Environmental Impact of Marine Renewable Energy

Environmental Impact of Marine Renewable Energy Environmental Impact of Marine Renewable Energy Prof. Martin J Attrill Director Plymouth University Marine Institute, UK mattrill@plymouth.ac.uk @mjattrill Plan of Presentation Environmental Impact of

More information

Outreach Report Water Wall Turbine Inc.

Outreach Report Water Wall Turbine Inc. Outreach Report Water Wall Turbine Inc. Project: 443 MH - WWT Dent Island Tidal Power Generation Project March 2017 I. Executive Summary The Water Wall Turbine (WWT) project has produced the world s first

More information

Ocean Energy: A European Perspective

Ocean Energy: A European Perspective Ocean Energy: A European Perspective PICES : October, 2010 Henry F Jeffrey UK Energy Research Centre University of Edinburgh UK Energy Research Centre Background North Sea, Oil and Gas Energy Marine Renewables:

More information

Environmental effects of marine renewable energy

Environmental effects of marine renewable energy Environmental effects of marine renewable energy What do we know? Marie-Lise Schläppy University of the Highlands and Islands The MERIKA Project has received funding from the European Union Seventh Framework

More information

Monitoring, modelling and management of Irish Sea mussel stocks

Monitoring, modelling and management of Irish Sea mussel stocks Monitoring, modelling and management of Irish Sea mussel stocks Gavin Burnell Aquaculture and Fisheries Development Centre University College Cork Ireland The Shellfish Association of Great Britain, Annual

More information

Assessing technical risks in the geological storage of CO 2

Assessing technical risks in the geological storage of CO 2 Assessing technical risks in the geological storage of CO 2 Jonathan Pearce British Geological Survey With many thanks to: Richard Metcalfe (Quintessa), Jerry Blackford (Plymouth Marine Laboratory) and

More information

Project history. The developers. Our core purpose is to provide the energy people need in a reliable and sustainable way.

Project history. The developers. Our core purpose is to provide the energy people need in a reliable and sustainable way. Project history In November 2008, The Crown Estate opened up the Pentland Firth and Orkney Waters Leasing Round (PFOW) to marine energy developers by inviting bids for exclusive site development rights.

More information

Environmental Impact of Marine Renewable Energy

Environmental Impact of Marine Renewable Energy Environmental Impact of Marine Renewable Energy Prof. Martin J Attrill Director Plymouth University Marine Institute, UK Peninsula Research Institute for Marine Renewable Energy Plan of Presentation Environmental

More information

7 MONITORING PLAN 7.1 INTRODUCTION

7 MONITORING PLAN 7.1 INTRODUCTION 7 MONITORING PLAN 7.1 INTRODUCTION The purpose of this chapter is to outline the key monitoring requirements identified through the EIA process to monitor the environmental and social performance of the

More information

A Seminar report On

A Seminar report On A Seminar report On Tidal Energy Submitted in partial fulfillment of the requirement for the award of degree Of Computer Science SUBMITTED TO: SUBMITTED BY: www.studymafia.org www.studymafia.org Preface

More information

Case Study. Defence climate change risk assessment. Overview. Background

Case Study. Defence climate change risk assessment. Overview. Background Case Study Defence climate change risk assessment Overview This case study describes the process used by the Australian Department of Defence to undertake climate risk assessments and adaptation planning

More information

Integrated SET Plan Actions No.1&2. ISSUES PAPER on OCEAN ENERGY

Integrated SET Plan Actions No.1&2. ISSUES PAPER on OCEAN ENERGY EUROPEAN COMMISSION RTD - Energy ENER - Renewables, R&I, Energy Efficiency JRC Institute for Energy and Transport SET Plan Secretariat Integrated SET Plan Actions No.1&2 ISSUES PAPER on OCEAN ENERGY Purpose

More information

Proposed Tidal Lagoon Development, Cardiff, South Wales

Proposed Tidal Lagoon Development, Cardiff, South Wales Proposed Tidal Lagoon Development, Cardiff, South Wales Evidence Plan Framework August 2015 www.tidallagooncardiff.com Document title Evidence Plan Framework Document reference Revision number 0.4 Date

More information

EXHIBIT A DESCRIPTION OF PROJECT

EXHIBIT A DESCRIPTION OF PROJECT EXHIBIT A DESCRIPTION OF PROJECT Exhibit A 1 SUMMARY DESCRIPTION OF PROJECT Public Utility District No. 1 of Snohomish County, Washington (Snohomish), is applying to the Federal Energy Regulatory Commission

More information

2012 Code of Conduct for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations

2012 Code of Conduct for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations 2012 Code of Conduct for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations The Guidelines for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations

More information

Dealing with cumulative effects of offshore windfarms on marine ecology

Dealing with cumulative effects of offshore windfarms on marine ecology Dealing with cumulative effects of offshore windfarms on marine ecology Applying first results in consenting process for offshore wind in Dutch North Sea Maarten Platteeuw, Ministry of Infrastructure and

More information

Environmental Impact Assessment

Environmental Impact Assessment The Project Hoben International Ltd proposes to develop a single 500kW wind turbine at their Manystones Lane site near Brassington. The turbine will be located approximately 350m to the south east of the

More information

Cape Sharp Tidal Venture: Environmental Effects Monitoring Program

Cape Sharp Tidal Venture: Environmental Effects Monitoring Program Cape Sharp Tidal Venture: Environmental Effects Monitoring Program February 2016 1.0 Introduction Cape Sharp Tidal Venture (CSTV), a partnership between Emera Inc. and OpenHydro, is proposing to deploy

More information

Calculating the Level of the Renewables Obligation

Calculating the Level of the Renewables Obligation Calculating the Level of the Renewables Obligation The Renewables Obligation Order (ROO) 2009 introduced changes that require the Secretary of State to announce the level of the Obligation six months preceding

More information

Non-Technical Summary (NTS)

Non-Technical Summary (NTS) OFFSHORE WIND AND MARINE RENEWABLE ENERGY IN NORTHERN IRELAND STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) Non-Technical Summary (NTS) AECOM and Metoc December 2009 CONTENTS 1. Introduction 2. Overview of

More information

Strategy ENERGY March 2012

Strategy ENERGY March 2012 Strategy ENERGY March 2012 Department of Enterprise, Trade and Investment Offshore Renewable Energy Strategic Action Plan 2012-2020 March 2012 Contents Ministerial Foreword Page 7 1 Introduction Page

More information

Known and potential impacts of deep sea mining and oil and gas exploration

Known and potential impacts of deep sea mining and oil and gas exploration Known and potential impacts of deep sea mining and oil and gas exploration Dave Paton 1 & Simon Childerhouse 2 Blue Planet Marine 1 Canberra, Australia; 2 Nelson, New Zealand www.blueplanetmarine.com Whales

More information

Scientific Advice on Matters Related to the Management of Seal Populations: 2016

Scientific Advice on Matters Related to the Management of Seal Populations: 2016 Main Advice Scientific Advice on Matters Related to the Management of Seal Populations: 2016 Contents Executive Summary Scientific Advice ANNEX I Terms of reference and membership of SCOS ANNEX II Questions

More information

DeepGreenHolyheadDeep

DeepGreenHolyheadDeep DeepGreenHolyheadDeep Non-technicalSummary March2016 Non-Technical Summary L100194-S00 Client: Minesto AB Document Type: Environmental Impact Assessment Document Number: L-100194-S00-EIAS-001-022 A01 08/03/2016

More information

4.17 Report on environmental monitoring protocols

4.17 Report on environmental monitoring protocols http://recruitment.jrc.ec.europa.eu/?type=tr&inst=3415&site=ptt Marine Renewables Infrastructure Network Work Package 4: Research 4.17 Report on environmental monitoring protocols Author(s): Davide Magagna

More information

Testing Tidal Turbines - Part 1: Steady Towing Tests vs Tidal Moored Tests

Testing Tidal Turbines - Part 1: Steady Towing Tests vs Tidal Moored Tests Testing Tidal Turbines - Part 1: Steady Towing Tests vs Tidal Moored Tests Jeffcoate, P., Elsaesser, B., Whittaker, T., & Boake, C. (2014). Testing Tidal Turbines - Part 1: Steady Towing Tests vs Tidal

More information

Environmental Effects of Tidal Energy Outcomes of a Scientific Workshop

Environmental Effects of Tidal Energy Outcomes of a Scientific Workshop Environmental Effects of Tidal Energy Outcomes of a Scientific Workshop Brian Polagye University of Washington Northwest National Marine Renewable Energy Center Boundaries: Benthic and Coastal Environments

More information

Sustainable Shellfish aquaculture the Ecosystem approach

Sustainable Shellfish aquaculture the Ecosystem approach Sustainable Shellfish aquaculture the Ecosystem approach Shellfish Growing in Ireland Fish Farmers 1,716 Processing 2,860 Ancillary 1,140 Shellfish 172 million - 4.53 from 4920 tonnes In total in N Ireland

More information

HORNS REV 1 OFFSHORE WIND FARM

HORNS REV 1 OFFSHORE WIND FARM HORNS REV 1 OFFSHORE WIND FARM Mankind has been making use of wind power for thousands of years. The current trend is moving away from small groups of land-based wind turbines to larger offshore wind farms.

More information

1. Thames Estuary Wind Farm Site Gunfleet

1. Thames Estuary Wind Farm Site Gunfleet 1. Thames Estuary Wind Farm Site Gunfleet 1.1. Overview Area of sea in relation to coastline, 12nm and continental shelf, estuaries etc Gunfleet Sands Offshore Wind Farm (OWF) lies approximately 7 km off

More information

Monitoring the impact of onshore wind farms on birds - January 2009

Monitoring the impact of onshore wind farms on birds - January 2009 Guidance te Monitoring the impact of onshore wind farms on birds - January 2009 Introduction 1. As the number of wind farms constructed in Scotland increases the need to understand the impact that these

More information

Review of international environmental best practice for floating wind turbine systems

Review of international environmental best practice for floating wind turbine systems Review of international environmental best practice for floating wind turbine systems Deliverable nº: 7.2 EC-GA nº Project full title: 295977 Demonstration of two floating wind turbine systems for power

More information

Scotrenewables Tidal Turbine (SRTT): A case study

Scotrenewables Tidal Turbine (SRTT): A case study Scotrenewables Tidal Turbine (SRTT): A case study Developer/Institutional collaboration within the Scottish marine energy policy framework Rhydar Harris Prestedge Retief Dresner Wijnberg (Pty) Ltd 18 September

More information

Emerging long term effects:

Emerging long term effects: Emerging long term effects: 14 years of Exxon Valdez oil spill studies documents delayed, chronic and indirect effects of marine oil pollution (Peterson et. al. 2003. SCIENCE 302, p. 2084) Seabirds Thick-billed

More information

Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014

Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014 Seaham North Pier Environmental Impact Assessment Volume 1: Non-Technical Summary January 2014 CONTENTS INTRODUCTION SEAHAM NORTH PIER THE ENVIRONMENTAL IMPACT ASSESSMENT ENVIRONMENTAL EFFECTS INTRODUCTION

More information

DeepGreenHolyheadDeepProject PhaseI(0.5MW) Non-technicalSummary. June2016

DeepGreenHolyheadDeepProject PhaseI(0.5MW) Non-technicalSummary. June2016 DeepGreenHolyheadDeepProject PhaseI(0.5MW) Non-technicalSummary June2016 Non-Technical Summary L100194-S14 Client: Minesto AB Document Type: Environmental Impact Assessment Document Number: L-100194-S14-EIAS-002

More information

The Importance of Interim Storage in the Management of Higher Activity Radioactive Waste

The Importance of Interim Storage in the Management of Higher Activity Radioactive Waste in the Management of Higher Activity Radioactive Waste February 2017 Contents 1. Purpose of the document 1 2. The lifecycle of HAW 1 3. Storage of HAW implementing Government policies 1 4. Storage of HAW

More information