SMUD Franklin Electric Transmission Project. Initial Study and Mitigated Negative Declaration Addendum July 2017

Size: px
Start display at page:

Download "SMUD Franklin Electric Transmission Project. Initial Study and Mitigated Negative Declaration Addendum July 2017"

Transcription

1 SMUD Franklin Electric Transmission Project Initial Study and Mitigated Negative Declaration Addendum July 2017

2

3 Sacramento Municipal Utility District Franklin Electric Transmission Project Initial Study Mitigated Negative Declaration Addendum July 2017 Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento, CA or P.O. Box MS H201 Sacramento, CA Attn: Kim Crawford (916) or kim.crawford@smud.org

4

5 Franklin Electric Transmission Project Addendum July 2017 Executive Summary The Sacramento Municipal Utility District (SMUD) adopted an Initial Study/Mitigated Negative Declaration (IS/MND) (State Clearinghouse [SCH] No ) for the Franklin Electric Transmission Project in October The project includes constructing and operating a new bulk transmission substation (Franklin Bulk substation), constructing and operating a new distribution substation (Franklin Distribution substation), modifying existing and constructing new overhead 69 kilovolt (kv) and 230kV power lines to link the substations to the electrical grid, and dismantling a nearby distribution substation. Since adoption of the 2016 IS/MND and approval of the project, SMUD has refined the substation design to address flood risks, thus requiring further environmental analysis. Flood protection is an important site design criterion to maintain SMUD s electric system reliability. During final design of the Franklin Bulk and Franklin Distribution Substation, SMUD determined that the planned Franklin Substation site should be raised above the previously proposed base elevation to provide adequate flood protection. SMUD will raise the grade of the substation to provide adequate head room based upon historical water level data for the Franklin area from the Sacramento County Department of Water Resources. The minimum surface elevation of the substation site will be increased from elevation 19.0 to 23.0 feet. The purpose of this Addendum is to evaluate the environmental effects of this design modification and determine whether the project, as modified, will result in any new or substantially greater significant effects or require any new mitigation measures not identified in the previously circulated 2016 IS/MND. Based on the information provided in this Addendum, the modification will not result in new significant environmental impacts compared to those previously analyzed in the 2016 IS/MND. No changes have occurred with respect to project circumstances that will cause significant environmental impacts, and no new information has become available that shows that the project will cause new significant environmental impacts. No new significant impacts have been identified, nor is the severity of previously identified impacts substantially greater than those presented in the 2016 IS/MND. Therefore, the analyses conducted and the conclusions reached in the IS/MND adopted in October 2016 remain valid and no supplemental environmental review is required beyond this Addendum.

6 Page intentionally blank Franklin Electric Transmission Project Addendum July 2017

7 Table of Contents Executive Summary Franklin Electric Transmission Project Addendum July Introduction Background Purpose of the Addendum to the IS/MND Project Description Project Location Project Modifications Since IS/MND Adoption Environmental Impact Analysis Aesthetics Air Quality Biological Resources Cultural Resources Geology and Soils Greenhouse Gas Emissions Hazards and Hazardous Materials Hydrology and Water Quality Noise Transportation and Circulation Other Environmental Topics Conclusions References Report Preparers List of Appendices Appendix A Air Emissions Modeling CalEEMod Output

8 Acronyms and Abbreviations Franklin Electric Transmission Project Addendum July 2017 BMPs CEQA dba EIR EMF GHG IS IS/MND kv LOS MND MTCO 2 e ND NO x Project SMAQMD SMUD SWPPP UPRR best management practices California Environmental Quality Act A-weighted decibels Environmental Impact Report Electric and Magnetic Fields Greenhouse gas Initial Study Initial Study/Mitigated Negative Declaration kilovolt level of service Mitigated Negative Declaration metric tons of carbon dioxide equivalents Negative Declaration oxides of nitrogen Franklin Electric Transmission Project Sacramento Metropolitan Air Quality Management District Sacramento Municipal Utility District Storm Water Pollution Prevention Plan Union Pacific Railroad

9 Franklin Electric Transmission Project Addendum July Introduction The Sacramento Municipal Utility District (SMUD) adopted an Initial Study/Mitigated Negative Declaration (IS/MND) (State Clearinghouse [SCH] No ) for the Franklin Electric Transmission Project in October The project includes constructing and operating a new bulk transmission substation (Franklin Bulk substation), constructing and operating a new distribution substation (Franklin Distribution substation), modifying existing and constructing new overhead 69 kilovolt (kv) and 230kV power lines to link the substations to the electrical grid, and dismantling a nearby distribution substation. Since adoption of the 2016 IS/MND, SMUD has refined the substation design to address flood risks, thus requiring further environmental analysis. The potential environmental impacts resulting from project changes are addressed in this Addendum. As demonstrated in this Addendum, the IS/MND continues to serve as the appropriate document addressing the environmental impacts of the project pursuant to the California Environmental Quality Act (CEQA). The 2016 Draft and Final IS/MND (SCH No ) are hereby incorporated by reference; the 2016 Draft and Final IS/MND are available for review on SMUD s CEQA Reports web page: Background SMUD published a Draft IS/MND on April 19, 2016, followed by a 30-day public review period and a public meeting. A Notice of Intent to adopt the MND was distributed to property owners and occupants of record within at least 500 feet of the project boundary. The Draft IS/MND was distributed to the Governor s Office of Planning and Research, the State Clearinghouse (SCH); local libraries; the County of Sacramento; the City of Elk Grove; and relevant resource agencies. SMUD then published a Final IS/MND containing responses to comments and a Mitigation Monitoring and Reporting Program (MMRP) with mitigation measures to address the project s potential environmental impacts. SMUD s Board of Directors certified the Final IS/MND and approved the project on October 20, A Notice of Determination was filed with the SCH on October 25, The 2016 IS/MND assessed the environmental impacts that may result from the construction and operation of the project. It identified potentially significant impacts associated with air quality, biological resources, cultural resources, geology/soils, greenhouse gas, hazards/hazardous materials, and hydrology/water quality. SMUD determined that those impacts will be less than significant with implementation of mitigation measures, which were adopted in the MMRP. Page 1 of 23

10 Franklin Electric Transmission Project Addendum July 2017 During final design of the Franklin Bulk and Franklin Distribution Substation, SMUD determined that the elevation of the approximately 17-acre substation site 1 should be raised to approximately 3 feet higher than originally planned to alleviate risk of flooding. 1.2 Purpose of the Addendum to the IS/MND This addendum describes the project modification and documents SMUD s determination that the modification does not require preparation of a subsequent or supplemental IS/MND. This determination is necessary because after an IS/MND has been approved, CEQA requires an agency, as part of any further discretionary approvals, to evaluate any project modifications that necessitate changes or additions to the IS/MND. If the project modifications are substantial and require major changes to the previous IS/MND because of new significant environmental effects or a substantial increase in the severity of previously identified effects, then the agency must prepare a subsequent or supplemental IS/MND. For project modifications that do not rise to this level but necessitate some revisions to the IS/MND, the agency may prepare an addendum to describe the project modifications and explain why a subsequent or supplemental MND is not required. Accordingly, a technical analysis of the incremental environmental effects posed by the modification was completed, using the project as described in the IS/MND as the baseline. This addendum describes that analysis, which concludes that the modifications will not cause new significant environmental effects or a substantial increase in the severity of previously identified effects (CEQA Guidelines Section 15164). There are also no changes in circumstances or new information that should have been known with reasonable diligence materialize that will substantially affect the project. 1 The proposed Franklin Bulk and Franklin Distribution substations would be co-located within the Project s substation footprint. This area is referred to as the substation site in the IS/MND. Page 2 of 23

11 Franklin Electric Transmission Project Addendum July Project Description The objective of the project is to maintain SMUD s electric system reliability and to increase the electric system capacity to meet expected customer demand as a result of planned land development in the southwest area of Sacramento County. In response, SMUD is planning to construct and operate a new bulk transmission substation (Franklin Bulk substation), construct and operate a new distribution substation (Franklin Distribution substation), modify existing and construct new overhead 69kV and 230kV power lines that will link the substations to the electrical grid, and dismantle a nearby distribution substation. The project elements and construction methods are described in detail in the 2016 Draft and Final IS/MND, which are incorporated by reference. This section describes the project changes analyzed in this IS/MND Addendum. 2.1 Project Location The project is located in southwestern Sacramento County, California (Figures 1 and 2). The planned substation is located in unincorporated Sacramento County and the subtransmission pole modifications extend into the City of Elk Grove, California. As described in the 2016 IS/MND, the Franklin Distribution substation will be co-located within the footprint of the Franklin Bulk substation. This area is referred to as the Franklin Substation site or substation site in the 2016 IS/MND and will occupy an approximately 17-acre site located southeast of the intersection of Franklin Boulevard and Hood Franklin Road and adjacent to an existing 230kV SMUD electrical transmission corridor and UPRR tracks to the east (Figure 2). 2.2 Project Modifications Since IS/MND Adoption SMUD has determined that the planned Franklin Substation site elevation should be increased for flood protection. Flood protection is an important site design criterion to maintain SMUD s electric system reliability. The site is located just north of and outside of the existing Federal Emergency Management Agency (FEMA) 100-year flood plain boundary (Figure 3). After the recent winter and associated flooding in the southern portion of the County, SMUD requested historical hydrologic information from the County Department of Water Resources. From those data, SMUD has determined that the highest previously recorded water elevation in the substation area was 21.0 feet above mean sea level, which is higher than the previously planned minimum elevation of 19.0 feet. Therefore, to adequately protect the substation and electric system reliability, SMUD will raise the substation site elevation to provide adequate flood protection. Page 3 of 23

12 Franklin Electric Transmission Project Addendum July 2017 Figure 1. Regional Location Page 4 of 23

13 Franklin Electric Transmission Project Addendum July 2017 Figure 2. Project Overview Page 5 of 23

14 Franklin Electric Transmission Project Addendum July 2017 Figure 3. FEMA 100-Year Floodplain Page 6 of 23

15 Franklin Electric Transmission Project Addendum July 2017 The minimum elevation within the substation site will be increased from 19.0 to 23.0 feet. The substation perimeter along Franklin Boulevard, which was originally planned to have an approximately 2 foot elevation difference between Franklin Boulevard and the substation, will instead have an elevation difference of approximately 5 feet, as shown in Figure 4 below. Thus the project change results in an incremental elevation change that raises the substation by 3 additional feet. The transition between Franklin Boulevard and the substation will be accomplished with a 3 to 1 slope (i.e., for every 3 feet of horizontal distance, the ground elevation increases by 1 foot). The area between Franklin Boulevard and the perimeter block wall will be landscaped. The drainage and grading plan, including design of the onsite detention basin and storm water collection facilities, has been refined (Figure 5). Figure 4. Elevations at Substation Site Raising the substation elevation does not change the project footprint or substantially alter the construction methods or the schedule described in the 2016 IS/MND. The 2016 IS/MND states that the substation site will be graded to accommodate substation equipment, drainage, and access roads, and that approximately 82,000 cubic yards of engineered fill will be imported. It states that grading, installing drainage facilities, and improving the access road will require approximately 16 weeks. With the elevation change, the estimated volume of imported material will increase to approximately 110,850 cubic yards and the duration of grading work will extend by three days. The 2016 IS/MND reported that construction of the Franklin Bulk substation was planned to begin in early 2017 and be completed in However, the project start date has been adjusted to September 2017; therefore, construction of the Franklin Bulk substation will be completed by the end of 2019 and other project components will extend until Page 7 of 23

16 Franklin Electric Transmission Project Addendum July 2017 Page intentionally blank Page 8 of 23

17 Franklin Electric Transmission Project Addendum July 2017 Figure 5. Preliminary Substation Drainage and Grading Plan Page 9 of 23

18 Franklin Electric Transmission Project Addendum July 2017 Page intentionally blank Page 10 of 23

19 Franklin Electric Transmission Project Addendum July Environmental Impact Analysis This comparative analysis has been undertaken pursuant to the provisions of CEQA Guidelines Section and to provide SMUD with the factual basis for determining whether changes in the project, changes in circumstances, or new information since the 2016 IS/MND was certified may require additional environmental review. The 2016 IS/MND found that the project will result in impacts that were either less than significant or less than significant with mitigation. The project has been modified to raise the elevation of the substation site to reduce flood risk. The environmental evaluation focuses on resource areas for which the project change warrants additional consideration. This section does not re-evaluate resources that are unaffected by the project modification. 3.1 Aesthetics As described in the 2016 Draft and Final IS/MND, the substations will be visible to nearby residents and will alter the view along Franklin Boulevard and Hood Franklin Road. SMUD has sited the substation in a location that will minimize the visual effect on residents. The 2016 IS/MND concluded that the project will not change the visual character of the area or result in a significant impact on aesthetics. The project has been modified to raise the elevation of the substation site by approximately 5 feet. The substation perimeter along Franklin Boulevard was originally planned to have an approximately 2 foot elevation difference between Franklin Boulevard and the substation. This elevation difference will now be raised by an additional 3 feet for a total of 5 feet elevation difference between Franklin Boulevard and the substation. This additional raise of the substation will make tall electrical equipment within the substation visible at greater distances than previously analyzed. The tall equipment includes two transformers (approximately 35 feet tall), up to thirteen 230kV power circuit breakers (approximately 25 feet tall), a network of steel structures to support the equipment (varying in height from approximately 16 to 80 feet tall), overhead conductors entering the substation from the interconnecting subtransmission and transmission overhead lines, and a two-story control building. Raising the substation site elevation and consequently the height of the electrical facilities will make these features visible at a greater distance. More of the substation s tall vertical elements will be visible from the Rancho Verde neighborhood east of the substation site. However, the original plan was to raise the site elevation by 2 feet, thus the incremental elevation change above the original plan is only 3 feet. In addition, most of the substation site still will be obscured by an existing sound barrier wall and vegetation. As noted in the 2016 IS/MND, the substation will be visible to residents and visitors to the Franklin community north of the Hood-Franklin/Franklin Boulevard intersection. Raising the substation site by approximately 5 feet will make these elements visible at a slightly greater distance; however, this change will not appreciably increase the project s effects on the overall visual character. The impact of the project on views and the visual character of the area remain the same as described in the 2016 IS/MND. Therefore, no changes to the conclusions of Page 11 of 23

20 Franklin Electric Transmission Project Addendum July 2017 the aesthetics analysis presented in the 2016 IS/MND are required. No new or substantially more severe significant effects will occur. 3.2 Air Quality The 2016 IS/MND identified potential impacts and mitigation measures for short-term construction impacts on air quality. It concluded that construction-generated emissions attributable to the project will exceed the Sacramento Metropolitan Air Quality Management District (SMAQMD) recommended significance threshold for oxides of nitrogen (NO x ). It also determined that emissions of particulate matter (PM), both PM 10 and PM 2.5, which are primarily associated with ground-disturbing activities (e.g., site preparation, grading, trenching), will not exceed the SMAQMD s daily or annual emissions thresholds. The SMAQMD updated their thresholds of significance in May 2017 (SMAQMD 2017); however, the update did not affect the construction thresholds used in the 2016 IS/MND analysis and therefore does not affect the impact conclusions. The project change will require additional earthwork and truck trips during the grading phase of construction. The 2016 IS/MND reported that approximately 82,000 cubic yards of engineered fill will be imported and that grading, drainage facilities, and access road improvements will require approximately 16 weeks of construction. With the additional fill, the volume of imported material will increase to approximately 110,850 cubic yards and the duration of grading work will extend by 3 days (totaling 16.5 weeks). To evaluate the potential impacts of the change on air quality, this addendum contains updated emissions calculations. Updated emissions estimates were calculated using the California Emissions Estimator Model (CalEEMod) Version The revised calculations accounted for the import of 110,843 cubic yards of fill and export of 14,991 cubic yards, resulting in a total of 13,287 haul trips. This represents a 4.5% increase in haul trips compared to the 2016 IS/MND, which evaluated 12,712 haul trips. The revised emissions estimates do not change the impact conclusions presented in the 2016 IS/MND. As shown in Table 1, PM emissions are well below the emission limits; however, NO x exceeds the adopted emission threshold during the first 2 years of construction (see Appendix A for additional details). Page 12 of 23

21 Franklin Electric Transmission Project Addendum July 2017 Table 1. Unmitigated Daily Construction Emissions (lbs/day) Year ROG NO x PM 10 1 PM Maximum Daily Emissions (lbs/day) SMAQMD Threshold Exceeds Threshold -- Yes No No Maximum Daily Emissions (lbs/day) reported in 2016 IS/MND Notes: Exceeds Threshold -- Yes No No 1 PM 10 emissions shown include the sum of particulate matter with aerodynamic diameter 0 to 2.5 microns and particulate matter with aerodynamic diameter 2.5 to 10 microns. ROG = reactive organic gases; NO x = oxides of nitrogen; PM 10 = suspended particulate matter; PM 2.5 = fine particulate matter; lbs/day = pounds per day Source: AECOM 2017, AMBIENT Air Quality and Noise Consulting 2015 The mitigation measures identified in the 2016 IS/MND include implementation of a Fugitive Dust Control Plan (AIR-1) and SMAQMD-recommended NO x reduction measures (AIR-2). Mitigation Measure AIR-2 includes a combination of construction equipment emission reductions and enhanced measures to reduce NO x emissions. To maintain NO x emissions below the SMAQMD emission threshold, SMUD will revise the technical specifications contained in Mitigation Measure AIR-2 to require use of Tier 4 Final equipment instead of Tier 3 equipment. With Tier 4 equipment, which is more effective in reducing NOx emissions, maximum mitigated daily emissions will be below SMAQMD thresholds (see Appendix A). Changes to Mitigation Measure AIR-2 are shown below; deletions are shown as strikeout text and additions are shown as double underline text. These changes are incorporated into the MMRP. Mitigation Measure AIR-2: NOx Reduction Measures The following SMAQMD-recommended basic and enhanced measures shall be implemented during substation construction and during the decommissioning of the Franklin-Bilby substation to reduce mobile source emissions of NO x : Page 13 of 23

22 Franklin Electric Transmission Project Addendum July 2017 Basic Measures: a. Minimize idling time of diesel-powered equipment either by shutting equipment off when not in use or reducing the time of idling to 5 minutes [required by California Code of Regulations, Title 13, sections 2449(d)(3) and 2485]. Provide clear signage that posts this requirement for workers at the entrances to the site. b. Maintain all construction equipment in proper working condition according to manufacturer s specifications. The equipment must be checked by a certified mechanic and determine to be running in proper condition before initial use in the Project Area. Documentation verifying compliance with this measure shall be retained on site and provided to SMAQMD upon request. c. When leasing equipment, the contractor shall use alternatively fueled equipment (e.g., electric, propane, etc.), in lieu of diesel- or gasoline-fueled equipment, whenever possible and to the extent available. Enhanced Measures: d. A comprehensive inventory of all off-road construction equipment, equal to or greater than 50 horsepower, that would be used in aggregate of 40 or more hours during substation construction and during the decommissioning of the Franklin-Bilby substation shall be submitted to the SMAQMD. The inventory shall include the horsepower rating, engine model year, and projected hours of use for each piece of equipment. The contractor shall provide the anticipated construction timeline including start date, and name and phone number of the project manager and on-site foreman. This information shall be submitted at least four business days prior to the use of subject heavy-duty off-road equipment. The inventory shall be updated and submitted monthly throughout the duration of the Project, except that an inventory shall not be required for any 30-day period in which no construction activity occurs. e. A plan shall be submitted to the SMAQMD demonstrating that combined emissions from heavy-duty off-road equipment (50 horsepower or more), construction vehicles, and haul truck to be used during substation construction and during the decommissioning of the Franklin-Bilby substation, including owned, leased, and subcontractor vehicles, will achieve NO X reductions sufficient to demonstrate compliance with the SMAQMD s maximum allowable mass emissions threshold of 85 pounds per day (lbs/day) of NOx. The use of newer heavy-duty off-road equipment will be sufficient to reduce construction-generated emissions to below SMAQMD s maximum allowable mass emissions threshold of 85 lbs/day of NO x. The construction contractor shall use offroad construction diesel engines that meet, at a minimum, the Tier 4 Final California Emissions Standards, unless such an engine is not available for a particular item of equipment. Lesser tier engines will be allowed on a case-by-case basis when the contractor has documented that no Tier 4 Final equipment or emissions equivalent retrofit equipment is available for a particular equipment type Page 14 of 23

23 Franklin Electric Transmission Project Addendum July 2017 that must be used to complete construction. SMAQMD s Construction Mitigation Tool spreadsheet (last updated January 1, 2017) shall be employed to confirm consistency with the plan. The plan shall include an inventory of all off-road equipment and haul trucks to be used during construction. Acceptable options for reducing emissions may include use of late model engines, low-emission diesel products, alternative fuels, engine retrofit technology, aftertreatment products, limitations on the use of off-road equipment and/or haul trucks, changes in construction schedules, the payment of mitigation fees to the SMAQMD, and/or other options as they become available. The SMAQMD s Construction Mitigation Calculator can be used to identify an equipment fleet that achieves this reduction. f. SMUD shall ensure that emissions from all off-road diesel powered equipment used in substation construction and during the decommissioning of the Franklin-Bilby substation do not exceed 40% opacity for more than three minutes in any one hour. Any equipment found to exceed 40 percent opacity (or Ringelmann 2.0) shall be repaired immediately. Non-compliant equipment shall be documented and a summary provided to SMAQMD monthly. A visual survey of all in-operation equipment shall be made at least weekly. A monthly summary of the visual survey results shall be submitted throughout the duration of the Project, except that the monthly summary shall not be required for any 30-day period in which no construction activity occurs. The monthly summary shall include the quantity and type of vehicles surveyed as well as the dates of each survey. g. In lieu of implementing all or a portion of the above Enhanced Measures, a refined emissions modeling analysis can be performed, once more detailed construction information becomes available. The refined analysis shall be conducted in accordance with applicable SMAQMD-recommended methodologies and guidance. Emissionsreduction measures shall be included sufficient to demonstrate compliance with SMAQMD s maximum allowable mass emissions threshold of 85 lbs/day of NO x. The refined analysis shall be reviewed and endorsed by the SMAQMD prior to initiating construction. Based on a preliminary analysis of the proposed Project, the The use of newer heavy-duty off-road equipment (i.e., Tier 3 4 or newer [EPA 2015]) would will be sufficient to reduce construction-generated emissions to below SMAQMD s maximum allowable mass emissions threshold of 85 lbs/day of NO x. Page 15 of 23

24 Franklin Electric Transmission Project Addendum July Biological Resources The project modification will not change the impact conclusions for biological resources. The substation remains within the previously evaluated 17-acre site. Raising the elevation of the substation will not result in new or substantially more severe significant effects on biological resources. Impacts on biological resources will be less-than-significant with mitigation incorporated. No changes have been made to the conclusions of the biological resources analysis presented in the 2016 IS/MND. 3.4 Cultural Resources As described in the 2016 IS/MND, impacts on cultural resources will be less-than-significant with mitigation incorporated. The project modification will not change the impact conclusions for cultural resources. The substation remains within the previously evaluated 17-acre site and raising the elevation of the substation will not result in new or substantially more severe significant effects on cultural resources. No changes have been made to the conclusions of the cultural resources analysis presented in the 2016 IS/MND. 3.5 Geology and Soils The 2016 IS/MND describes impacts to soil erosion as less-than-significant with mitigation incorporated. The 2016 IS/MND states that the grading and ground-disturbing activities will expose soils and could result in accelerated erosion. Preparation and implementation of a Storm Water Pollution Prevention Plan (SWPPP) is included as a mitigation measure to reduce this potential impact to a less-than-significant level. Through the SWPPP, SMUD will implement erosion control measures and best management practices (BMPs) to stabilize soils during and following construction. Raising the elevation of the substation site elevation does not change the project footprint or substantially alter the construction methods described in the 2016 Draft IS/MND. However, with the elevation change, the estimated volume of imported material will increase and the duration of grading work will extend by less than one week. These changes will not result in new or substantially more severe significant effects on soil erosion than those described in the 2016 IS/MND, and no changes are needed to the adopted mitigation measure. 3.6 Greenhouse Gas Emissions As described in the 2016 IS/MND, construction will result in the temporary generation of greenhouse gas (GHG) emissions. The 2016 IS/MND reported that annual GHG emissions during the initial year of construction could potentially exceed SMAQMD s significance threshold of 1,100 metric tons of carbon dioxide equivalents (MTCO 2 e) per year. The 2016 IS/MND included Mitigation Measure GHG-1. With this mitigation, the impact was determined to be less than significant. To evaluate the effect of adding fill and truck trips, updated GHG emissions calculations were completed (see Appendix A). The revised analysis shows that the estimated GHG emissions will be higher than originally planned but will not exceed the SMAQMD s annual threshold. Although Page 16 of 23

25 Franklin Electric Transmission Project Addendum July 2017 the number of haul truck trips has increased, the revised construction start date and schedule spreads these emissions over more years, with the initial construction stages (including import of fill and grading) spread more evenly between the first 2 years. In the 2016 IS/MND, GHG emissions in the first 2 years of construction were estimated at 1,230 and 476 MTCO2e/year. With the project change, the estimates for the first two years of construction are 969 and 720 MTCO2e/year (Appendix A). Therefore, the modified project s GHG emissions impacts will be less than significant. Mitigation Measure GHG-1, adopted by SMUD, includes the following provision: In lieu of implementing the above measure, a refined emissions modeling analysis can be performed, once more detailed construction information becomes available. The refined analysis shall be conducted in accordance with applicable SMAQMDrecommended methodologies and guidance. Emissions-reduction measures shall be included sufficient to demonstrate compliance with SMAQMD s mass emissions threshold of 1,100 MTCO2e/year. The refined analysis shall be reviewed and endorsed by the SMAQMD prior to initiating construction. The revised GHG analysis presented in Appendix A constitutes a refined emissions modeling analysis, which SMUD will transmit to SMAQMD as proof of completion of mitigation measure GHG Hazards and Hazardous Materials As described in the 2016 Draft and Final IS/MND, impacts on hazards and hazardous materials are considered less-than-significant with mitigation incorporated. The 2016 IS/MND includes mitigation measures to minimize the potential for accidental releases of hazardous materials into the environment during construction and operation. These measures include preparation and implementation of a worker training program; a SWPPP; a Spill Prevention, Control, and Countermeasures Plan; and a Hazardous Materials Business Plan. Raising the elevation of the substation site elevation does not change the project footprint or alter the construction methods and materials to be used at the site. Therefore, no changes are needed to the impact conclusions for hazards and hazardous materials. The 2016 Final IS/MND presented results of pre- and post-project electric and magnetic fields (EMF) modeling and determined that 1) the project will not result in an appreciable increase in EMF exposure to nearby residents over existing conditions, and 2) exposure levels will be far below published EMF guidelines (see 2016 Final IS/MND pages 65 to 77). As noted in the analysis, EMF strength is affected by distance, conductor spacing, load, and phase configuration. Raising the substation site elevation by approximately 5 feet will not change these factors. The project footprint and electrical equipment design has not been modified substantially, thus no changes in the factors that influence EMF strength, including distance from electric facilities to surrounding residents, will occur. The modeling and conclusions presented in the 2016 Final IS/MND for EMF are valid. The project will not have a significant effect on public health related to EMF emissions and no mitigation is required. Page 17 of 23

26 Franklin Electric Transmission Project Addendum July Hydrology and Water Quality The 2016 IS/MND describes impacts on hydrology as less than significant and impacts on water quality as less than significant with mitigation incorporated. As shown in Figure 3, the substation site is located immediately north of the FEMA 100-year floodplain boundary. The 2016 IS/MND determined that: the onsite drainage management system and detention basin will not alter downstream flows, the project would not impede or redirect flood flows, and the substation minimum site elevation will be at least 1.5 feet above the 100-year floodplain per County of Sacramento requirements. After the recent winter and associated flooding in the southern portion of the County, SMUD decided to change the final design by adjusting the substation elevation to adequately protect the substation and electric system reliability during high flood events. The design of the onsite detention basin and storm water collection facilities has been refined to match the new higher elevation (Figure 5). Therefore, the project modifications do not change the hydrology conclusions presented in the 2016 IS/MND. No new or substantially more severe significant effects on water quality or hydrology would occur, and no changes are needed to the adopted mitigation measures to address potential water quality impacts. 3.9 Noise The 2016 IS/MND evaluated short-term (construction) and operational noise impacts of the substation on nearby sensitive noise receptors, including residences and schools. The 2016 IS/MND noted that the highest noise levels would be associated with earth-moving equipment used during site preparation, grading and trenching activities. Noise resulting from constructiongenerated vehicle traffic on primarily affected roadway segments was also calculated. The results of the 2016 IS/MND analysis found that the increase in ambient noise levels during construction and operation would result in less-than-significant impacts on nearby sensitive receptors. The project has been modified to raise the elevation of the substation site, which will require additional earthwork and truck trips to import engineered fill during the grading phase of construction. The construction vehicle-generated noise analysis in the 2016 IS/MND was based on an estimate of 12,712 truck trips during this phase. With the project modification, an estimated 13,287 truck trips would be required; this results in approximately 575 additional truck trips during the grading phase of construction. In addition, as described above, the duration of construction will increase by 3 days for the additional grading and related work. However, the increase in haul truck traffic will not increase construction noise because the additional (approximately 575) haul trips would be distributed over the duration of the longer (83 days) filling and grading phase, resulting in an additional approximately 7 trips per day (less than more 1 trip per hour). Because Page 18 of 23

27 Franklin Electric Transmission Project Addendum July 2017 the construction phase would be longer, the number of trucks per day would not increase substantially. Therefore, the impact conclusions in the 2016 ISMND would remain the same. With respect to operational noise, the analysis in 2016 IS/MND shows that the operational noise levels at the property lines of the nearest residential land uses (not accounting for noise reduction from the substation perimeter wall along Franklin Boulevard) would be approximately 43 dba L eq /L 50 2 or less, under normal daytime operational conditions including the simultaneous operation of all onsite transformers and cooling fans from both the bulk and distribution substations. Elevating the substation would slightly increase the noise levels at the property lines. However, because this change would not move the noise source closer to the residences and the planned substation perimeter wall along Franklin Boulevard will provide noise protection to the nearest residents, the increase in noise levels would not exceed applicable thresholds at nearby noisesensitive uses. Therefore, the noise impact conclusions related to operation noise levels would remain the same Transportation and Circulation As described in the 2016 IS/MND, the project would have less-than-significant impacts on traffic and circulation. The potential impacts of the project on intersections and roadways were assessed by evaluating the estimated construction trips under worst case assumptions and assessing associated potential impacts on intersection and roadway level of service (LOS), and potential safety impacts at the substation site access points. Construction material loads will be highest during the initial site preparation and grading phase. Trip generation estimates for the worse-case scenario are presented in Table TRA-1 of the 2016 Draft IS/MND. The worst case analysis shows 370 truck trips required for materials import and export occurring on a typical construction grading workday. This activity represents an average of 46 truck trips on an hourly basis over an 8-hour haul day. As material receiving hours will be 7:00 a.m. to 3:00 p.m., the project will add truck traffic during the a.m. peak hour, but the contribution during the p.m. peak hour would be limited. Using a worse-case assumption, project construction could generate approximately 430 daily truck trips under the 2016 IS/MND analysis, with most of that activity concentrated at the beginning and end of the work day when worker commutes occur. The 2016 IS/MND analysis found that the increase in traffic during construction would result in less-thansignificant impacts on nearby interchange and roadway LOS. The project change will require additional earthwork and add approximately 575 additional truck trips during the grading phase. Using a worse-case assumption analysis for the updated construction scenario (all additional truck trips occur over the three additional grading days) would result in approximately 192 trips per day. Therefore, the additional truck trips will not result in an increase in the daily trip generation estimate because the additional trips would be distributed over the extended construction period rather than compressed into the three 2 A-weighted decibels (dba) = the decibel level which has been weighted to approximate the frequency response of the average human ear. Energy-Equivalent Noise Level (L eq ) = an average of the sound energy occurring over a specified period. In effect, L eq is the steady-state sound level containing the same acoustical energy as the time-varying sound that actually occurs during the same period. Page 19 of 23

28 Franklin Electric Transmission Project Addendum July 2017 additional days of grading work. No change to the impact conclusions in the 2016 IS/MND is needed Other Environmental Topics The environmental analysis provided in the 2016 IS/MND remains current and applicable to the project in areas unaffected by the design refinement. Substation construction would be completed within the previously evaluated 17-acre site and the project modifications would not change the impact conclusions related to the following resources: Agricultural resources; Land use and planning, Mineral resources, Population and housing, Public services, Recreation, and Utilities and service systems. The project would neither increase the severity of these impacts nor result in new or substantially different environmental effects than those described in the 2016 IS/MND. These topics do not warrant further discussion in this Addendum. Page 20 of 23

29 Franklin Electric Transmission Project Addendum July Conclusions Based on the information provided above, SMUD has determined that the project modifications would not have a significant effect on the environment and that changing the specifications in Mitigation Measure AIR-2 to require Tier 4 equipment will address increases in NOx emissions. No new significant impacts have been identified, nor is the severity of previously identified impacts substantially greater than those presented in the 2016 IS/MND. No new mitigation measures would be necessary to reduce significant impacts. Furthermore, no changes have occurred with respect to circumstances surrounding the project that would cause significant environmental impacts and no new information has become available that shows that the project would cause new significant environmental impacts. Therefore, this addendum, which considers increasing the substation elevation, is consistent with the MND adopted by the SMUD Board of Directors in Kim Crawford Date Environmental Management Specialist Page 21 of 23

30 Franklin Electric Transmission Project Addendum July References AECOM Air Quality and Greenhouse Gas Technical Memorandum for the Revised Franklin Electric Transmission Project. June 2017 Ambient Air Quality and Noise Consulting Air Quality and Greenhouse Gas Impact Assessment Report for the Franklin Electric Transmission Project. September Sacramento Metropolitan Air Quality Management District (SMAQMD). May Guide to Air Quality Assessment in Sacramento County. Available at: Guidance-Tools. Accessed June Page 22 of 23

31 Franklin Electric Transmission Project Addendum July Report Preparers SMUD Kim Crawford, Environmental Specialist Area West Environmental, Inc. Aimee Dour-Smith, Senior Planner Becky Rozumowicz, Principal AECOM, Inc. Susan Sanders, Project Manager Peter Boucher, CEQA/NEPA Specialist Petra Unger, CEQA/NEPA Specialist Caitlin Miller, Air Quality Specialist Mohammad Issa Mahmodi, Traffic and Noise Analyst Page 23 of 23

32 Appendix A. Air Emissions Modeling CalEEMod Output

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99

100

101

102

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120

121

122

123

124

125

126

127

128

129

130

131

132

133

134

135

136

137

138

139

140

141

142

143

144

145

146

147

148

149

150

151

152

153

154

155

156

157

158

159

160

161

162

163

164

165

166

167

168

169

170

171

172

173

174

175

176

177

178

179

180

181

182

183

184

185

186

187

3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS

3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS 3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS 3.1 INTRODUCTION Construction activities have the potential to generate a substantial amount of air pollution. In some cases, the

More information

Schwan Self-Storage. Addendum to Schwan Self-Storage Project Mitigated Negative Declaration Case No DP RV

Schwan Self-Storage. Addendum to Schwan Self-Storage Project Mitigated Negative Declaration Case No DP RV Schwan Self-Storage Addendum to Schwan Self-Storage Project Mitigated Negative Declaration Case No. 17-055-DP RV Prepared by: City of Goleta 130 Cremona Drive, Suite B Goleta, CA 93117 September 2017 Addendum

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,

More information

Nishi Residential Development Project

Nishi Residential Development Project Nishi Residential Development Project Environmental Checklist Addendum to the Nishi Gateway EIR (State Clearinghouse #2015012066) PREPARED FOR: Community Development 23 Russell Boulevard Suite 2 Davis,

More information

The following findings are hereby adopted by The Regents in conjunction with the approval of the Project which is set forth in Section III, below.

The following findings are hereby adopted by The Regents in conjunction with the approval of the Project which is set forth in Section III, below. CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE EAST CAMPUS STUDENT HOUSING PHASE III DEVELOPMENT PROJECT UNIVERSITY OF CALIFORNIA, IRVINE I. ADOPTION OF THE MITIGATED

More information

3.1 Existing Setting Regulatory Framework Changes in Population, Employment, and Housing

3.1 Existing Setting Regulatory Framework Changes in Population, Employment, and Housing EXECUTIVE SUMMARY ES.1 Purpose and Scope of the EIR... ES-1 ES.2 Project Characteristics... ES-1 ES.3 Project Alternatives Summary... ES-2 ES.4 Areas of Controversy... ES-2 ES.5 Summary of Environmental

More information

RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Addendum to the Final Environmental Impact Report

RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Addendum to the Final Environmental Impact Report RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Addendum to the Final Environmental Impact Report June 2016 State Clearinghouse Number 2014012012 Project Number 93294057 Prepared by: Michael

More information

NAPA SANITATION DISTRICT SOLAR PROJECT

NAPA SANITATION DISTRICT SOLAR PROJECT NAPA SANITATION DISTRICT SOLAR PROJECT Addendum to Initial Study / Mitigated Negative Declaration Prepared for March 2016 Napa Sanitation District NAPA SANITATION DISTRICT SOLAR PROJECT Addendum to Initial

More information

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance Project: East Hampton Temporary Generation Facility Expansion Date: May 17, 2018 This notice is issued

More information

ERRATA TO THE FINAL EIR

ERRATA TO THE FINAL EIR DRAFT EIR ERRATA TO THE FINAL EIR The following paragraphs in Section 6.0, Alternatives, are edited as follows: The following discussion evaluates alternatives to the Proposed Project and examines the

More information

Sacramento Area Flood Control Agency. May State Clearinghouse No Prepared for: Prepared by: Consulting Engineers and Scientists

Sacramento Area Flood Control Agency. May State Clearinghouse No Prepared for: Prepared by: Consulting Engineers and Scientists Addendum No. 3 (North Sacramento Streams) to the Environmental Impact Report on the North Sacramento Streams, Sacramento River East Levee, Lower American River, and Related Flood Improvements Project Prepared

More information

Table Ambient Criteria Air Pollutant Monitoring Data ( )

Table Ambient Criteria Air Pollutant Monitoring Data ( ) Section 5.4 Air Quality and Climate Change This section describes the potential air quality and climate change impacts associated with the proposed changes to the approved project. This section supplements

More information

Sacramento Municipal Utility District Station E Substation Project. Initial Study and Mitigated Negative Declaration Addendum March 2017

Sacramento Municipal Utility District Station E Substation Project. Initial Study and Mitigated Negative Declaration Addendum March 2017 Sacramento Municipal Utility District Station E Substation Project Initial Study and Mitigated Negative Declaration Addendum March 2017 Sacramento Municipal Utility District Station E Substation Project

More information

5.0 ALTERNATIVE VARIATIONS

5.0 ALTERNATIVE VARIATIONS 5.0 ALTERNATIVE VARIATIONS 5.1 INTRODUCTION The Draft EIR for the Beverly Hilton Revitalization Plan evaluated five alternatives to the project, pursuant to Section 15126.6 of the California Environmental

More information

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS B203 Sacramento,

More information

Addendum to Mitigated Negative Declaration

Addendum to Mitigated Negative Declaration Background Addendum to Mitigated Negative Declaration Addendum Date: Case No.: 2011.0408E Project Title: Internet Services Exchange 2011.0408E, adopted July 24, 2014 Project Sponsor: John Wilson, The Cambay

More information

ZAB Hearing May 14, 2015

ZAB Hearing May 14, 2015 ZAB Hearing May 14, 2015 Comments from April 23rd TOPICS Streamlined Environmental Review Protections for Berkeley High School Air Quality, Noise, and Traffic Project Alternatives Water Supply/Wastewater

More information

FINAL ENVIRONMENTAL IMPACT REPORT SCH NO

FINAL ENVIRONMENTAL IMPACT REPORT SCH NO STERLING MEADOWS FINAL ENVIRONMENTAL IMPACT REPORT SCH NO. 1999122067 Prepared by CITY OF ELK GROVE DEVELOPMENT SERVICES 8401 LAGUNA PALMS WAY ELK GROVE, CA 95758 APRIL 2008 FINAL ENVIRONMENTAL IMPACT

More information

SECTION 6.0 Alternatives to the Proposed Project

SECTION 6.0 Alternatives to the Proposed Project SECTION 6.0 Alternatives to the Proposed Project 6.0 ALTERNATIVES TO THE PROPOSED PROJECT CEQA requires that an EIR include an analysis of a range of project alternatives that could feasibly attain most

More information

Tuscan Village Addendum

Tuscan Village Addendum Tuscan Village Addendum To: Date: Subject: Bruce Ambo, Principal Planner, City of Chico Planning Services March 19, 2018 Tuscan Village Addendum (Amber Lynn Estates) Response to Butte County AQMD Comments

More information

TABLE OF CONTENTS ES EXECUTIVE SUMMARY 1.0 INTRODUCTION 2.0 PROJECT DESCRIPTION 3.0 ENVIRONMENTAL ANALYSIS

TABLE OF CONTENTS ES EXECUTIVE SUMMARY 1.0 INTRODUCTION 2.0 PROJECT DESCRIPTION 3.0 ENVIRONMENTAL ANALYSIS ES EXECUTIVE SUMMARY ES1 ES2 ES3 ES4 ES5 Purpose and Scope of the Environmental Impact Report... ES-1 Project Summary... ES-1 Project Alternatives Summary... ES-1 Areas of Controversy/Issues to be Resolved...

More information

Station E Substation Project. Final Initial Study and Mitigated Negative Declaration March 2014

Station E Substation Project. Final Initial Study and Mitigated Negative Declaration March 2014 Station E Substation Project Initial Study and Mitigated Negative Declaration March 2014 Station E Substation Project Initial Study and Mitigated Negative Declaration Lead Agency: Sacramento Municipal

More information

2 ENVIRONMENTAL REVIEW AND THRESHOLDS OF SIGNIFICANCE

2 ENVIRONMENTAL REVIEW AND THRESHOLDS OF SIGNIFICANCE 2 ENVIRONMENTAL REVIEW AND THRESHOLDS OF SIGNIFICANCE 2.1 ENVIRONMENTAL REVIEW PROCESS The California Environmental Quality Act (CEQA) requires that public agencies (e.g., local, county, regional, and

More information

LOWE S HOME IMPROVEMENT WAREHOUSE

LOWE S HOME IMPROVEMENT WAREHOUSE LOWE S HOME IMPROVEMENT WAREHOUSE DRAFT ENVIRONMENTAL IMPACT REPORT V. PROJECT ALTERNATIVES A. Introduction Section III of this document provides a detailed analysis of potential impacts associated with

More information

City of Palo Alto (ID # 7047) City Council Staff Report

City of Palo Alto (ID # 7047) City Council Staff Report City of Palo Alto (ID # 7047) City Council Staff Report Report Type: Consent Calendar Meeting Date: 6/13/2016 Summary Title: East Palo Alto Comment Letter Title: Approval and Authorization for the City

More information

Air Quality and Greenhouse Gas Analysis

Air Quality and Greenhouse Gas Analysis Air Quality and Greenhouse Gas Analysis Prepared for: BRENTWOOD DEVELOPMENTS JANUARY 2018 Prepared by: 1501 Sports Drive, Suite A Sacramento CA 95834 Office 916.372.6100 Fax 916.419.6108 INFO@raneymanagement.com

More information

DRAFT ENVIRONMENTAL IMPACT REPORT

DRAFT ENVIRONMENTAL IMPACT REPORT DRAFT ENVIRONMENTAL IMPACT REPORT Beverly Hills High School, Hawthorne K-8 School, and El Rodeo K-8 School Improvement Project Prepared for: BEVERLY HILLS UNIFIED SCHOOL DISTRICT 255 South Lasky Drive

More information

Final Environmental Impact Report BARTON PLACE

Final Environmental Impact Report BARTON PLACE Final Environmental Impact Report VOLUME IV - Response to Comments and Errata BARTON PLACE City of Cypress, California SCH No. 2015031004 Prepared by l s a a s s o c i a t e s, i n c. October 2015 This

More information

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project Sacramento Municipal Utility District Headquarters Building Final Initial Study and Mitigated Negative Declaration March 2015 Sacramento Municipal Utility District Headquarters Building Final Initial Study

More information

4.3 AIR QUALITY EXISTING CONDITIONS CLIMATE AND METEOROLOGY

4.3 AIR QUALITY EXISTING CONDITIONS CLIMATE AND METEOROLOGY 4.3 AIR QUALITY The information presented in this section is based on documents prepared by the Sacramento Metropolitan Air Pollution Control District (APCD), U.S. Environmental Protection Agency (EPA),

More information

CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report

CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report City of Tehachapi CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report SCH No. 2009101084 Prepared for: City of Tehachapi Community Development Department 115 South Robinson Street Tehachapi,

More information

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE MUSIC BUILDING PROJECT

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE MUSIC BUILDING PROJECT CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE MUSIC BUILDING PROJECT I. APPROVAL OF THE MITIGATED NEGATIVE DECLARATION Pursuant to Title 14, California

More information

City of Malibu. Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I. Prepared For: Prepared by:

City of Malibu. Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I. Prepared For: Prepared by: City of Malibu Whole Foods and the Park Shopping Center Draft Environmental Impact Report Volume I Prepared For: Prepared by: I M PA C T S C I E N C E S, I N C. 638 East Colorado Blvd, Suite 301 Pasadena,

More information

(1) The proposed commercial solar energy generation facility is either

(1) The proposed commercial solar energy generation facility is either (2) The design and siting of these facilities shall avoid the placement of turbines on or immediately adjacent to the upwind side of ridge crests; (3) The design may include other design features to minimize

More information

Hollister Village Apartments. Addendum to Westar Village Final Environmental Impact Report Case No

Hollister Village Apartments. Addendum to Westar Village Final Environmental Impact Report Case No Addendum to Westar Village Final Environmental Impact Report Case No. 16-029 Prepared by: City of Goleta 130 Cremona Drive, Suite B Goleta, CA 93117 Prepared July 2016 Revised February 2017 and July 2017

More information

Table of Contents. City of Redlands - Redlands Crossing Center

Table of Contents. City of Redlands - Redlands Crossing Center City of Redlands - Redlands Crossing Center Executive Summary... ES-1 Section 1: Introduction...1-1 1.1 - Overview of the CEQA Process...1-1 1.2 - Scope of the EIR...1-5 1.3 - Organization of the EIR...1-8

More information

Hazel Avenue Electrical Facilities Relocation and Expansion Project

Hazel Avenue Electrical Facilities Relocation and Expansion Project Hazel Avenue Electrical Facilities Relocation and Expansion Project Recirculated Draft Initial Study and Mitigated Negative Declaration December, 2013 Hazel Avenue Electrical Facilities Relocation and

More information

Introduction. Chapter 3 Modifications to the Draft EIS/EIR

Introduction. Chapter 3 Modifications to the Draft EIS/EIR 1 2 Chapter 3 Modifications to the Draft EIS/EIR 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Introduction This chapter of the document addresses modifications to

More information

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE SEGUNDO INFILL HOUSING PROJECT, DAVIS CAMPUS

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE SEGUNDO INFILL HOUSING PROJECT, DAVIS CAMPUS CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE DESIGN OF THE SEGUNDO INFILL HOUSING PROJECT, DAVIS CAMPUS I. ADOPTION OF THE MITIGATED NEGATIVE DECLARATION In accordance

More information

Notice of Preparation of Draft EIR Notice of Public Scoping Meeting ARB Southern California Consolidation Project

Notice of Preparation of Draft EIR Notice of Public Scoping Meeting ARB Southern California Consolidation Project Date: August 1, 2016 To: Subject: Contact: State Clearinghouse, Responsible Agencies, Trustee Agencies, Federal Agencies, Interested Parties, and Organizations of a Draft Environmental Impact Report and

More information

APPENDIX B REVISED AIR QUALITY

APPENDIX B REVISED AIR QUALITY APPENDIX B REVISED AIR QUALITY TABLE OF CONTENTS Page 1.0 CONSTRUCTION EMISSIONS... 1 1.1 CONSTRUCTION EQUIPMENT... 1 1.2 CONSTRUCTION EMISSION SUMMARY... 6 1.2.1 On-Road Emissions... 6 1.2.2 Off-Road

More information

FINAL ENVIRONMENTAL IMPACT REPORT Volume 1. NBC Universal Evolution Plan ENV EIR STATE CLEARINGHOUSE NO Council District 4

FINAL ENVIRONMENTAL IMPACT REPORT Volume 1. NBC Universal Evolution Plan ENV EIR STATE CLEARINGHOUSE NO Council District 4 Division of Land / Environmental Review City Hall 200 N. Spring Street, Room 750 Los Angeles, CA 90012 FINAL ENVIRONMENTAL IMPACT REPORT Volume 1 ENV-2007-0254-EIR STATE CLEARINGHOUSE NO. 2007071036 Council

More information

First and foremost, alternatives in an EIR must be potentially feasible. In the context of CEQA, feasible is defined as:

First and foremost, alternatives in an EIR must be potentially feasible. In the context of CEQA, feasible is defined as: ALTERNATIVES TO THE PROPOSED PROJECT 5.0 5.1 CEQA REQUIREMENTS CEQA requires that an EIR analyze a reasonable range of feasible alternatives that meet most or all project objectives while reducing or avoiding

More information

Final Initial Study/Mitigated Negative Declaration Indianola Subdivision Project City of Sanger, Fresno County, California

Final Initial Study/Mitigated Negative Declaration Indianola Subdivision Project City of Sanger, Fresno County, California Final Initial Study/Mitigated Negative Declaration Indianola Subdivision Project City of Sanger, Fresno County, California Prepared for: City of Sanger 1700 7 th Street Sanger, CA 93657 559.876.6300 Contact:

More information

65 East Project (P18-045) Addendum to an Environmental Impact Report

65 East Project (P18-045) Addendum to an Environmental Impact Report 65 East Project (P18-045) Addendum to an Environmental Impact Report File Number/Project Name: 65 East Project (P18-045) Project Location and Surrounding Land Uses: The proposed project site consists of

More information

3.0 ERRATA TO THE DRAFT EIR

3.0 ERRATA TO THE DRAFT EIR Errata to the Draft EIR 3.0 ERRATA TO THE DRAFT EIR 3.1 Introduction This section includes the minor changes to the Draft EIR because of typographical errors, clarification of wording, correction of references,

More information

Exhibit G. Construction Mitigation Plan

Exhibit G. Construction Mitigation Plan Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance

More information

This comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that:

This comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that: 6.0 Comparison of Proposed Project and Alternatives This chapter summarizes the environmental advantages and disadvantages associated with the Proposed Project and the alternatives. Based upon this discussion,

More information

Inglewood Oil Field Specific Plan Project Draft Environmental Impact Report

Inglewood Oil Field Specific Plan Project Draft Environmental Impact Report Draft Environmental Impact Report SCH No. 2015101030 Prepared for: City of Culver City Planning Division 9770 Culver Boulevard Culver City, California 90232 Prepared by: Psomas 225 South Lake Avenue Suite

More information

MITIGATION MONITORING AND REPORTING PROGRAM Valero Benicia Crude By Rail Project

MITIGATION MONITORING AND REPORTING PROGRAM Valero Benicia Crude By Rail Project MITIGATION MONITORING AND REPORTING PROGRAM Valero Benicia Crude By Rail Project Introduction This document describes the mitigation monitoring and reporting program (MMRP) for ensuring the effective implementation

More information

I. CONSIDERATION OF 2020 LRDP FEIR (1/05) AND ADDENDUM #8 1

I. CONSIDERATION OF 2020 LRDP FEIR (1/05) AND ADDENDUM #8 1 ATTACHMENT 5 CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF AMENDMENT #2 TO THE 2020 LONG RANGE DEVELOPMENT PLAN -- CAMPUS SPACE AND INFRASTRUCTURE CHAPTER, AND APPROVAL

More information

APPLICATION FOR REVIEW OF IMPORT EXPORT (EFFECTIVE 5/17/2010) REV: 7/18 GGI-08

APPLICATION FOR REVIEW OF IMPORT EXPORT (EFFECTIVE 5/17/2010) REV: 7/18 GGI-08 APPLICATION FOR REVIEW OF IMPORT EXPORT (EFFECTIVE 5/17/2010) REV: 7/18 GGI-08 SECTION 91.7006.7.5, REQUIRES A PUBLIC HEARING BEFORE THE BOARD OF BUILDING AND SAFETY COMMISSIONERS (BBSC) FOR ANY IMPORT

More information

Folsom South of U.S. Highway 50 Specific Plan Project

Folsom South of U.S. Highway 50 Specific Plan Project Mitigation Monitoring and Reporting Program Folsom South of U.S. Highway 50 Specific Plan Project SCH #2008092051 Prepared by: May 2011 Mitigation Monitoring and Reporting Program Folsom South of U.S.

More information

METRO BLUE LINE TRACK IMPROVEMENT PROJECT. July2016 TRANSMITTAL NO. 3

METRO BLUE LINE TRACK IMPROVEMENT PROJECT. July2016 TRANSMITTAL NO. 3 ADDENDUM NO. 2 TO MITIGATED NEGATIVE DECLARATION METRO BLUE LINE TRACK IMPROVEMENT PROJECT LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (JUNE 2015) SCH # 2015051044 METRO BLUE LINE TRACK IMPROVEMENT

More information

Washoe County PLAN SUBMITTAL

Washoe County PLAN SUBMITTAL Washoe County PLAN SUBMITTAL Grading Residential and Commercial Washoe County Permits Plus Zone 1001 East Ninth Street PO Box 11130 Reno, NV 89520-0027 GRADING PERMIT SUBMITTAL GUIDELINES The following

More information

Pacific Wind Energy Project Draft Environmental Impact Report

Pacific Wind Energy Project Draft Environmental Impact Report Pacific Wind Energy Project Table of Contents VOLUME 1 1 Executive Summary... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-1 1.3 Purpose and Use of the Draft EIR... 1-4 1.4 Project Overview...

More information

County of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by:

County of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by: County of El Dorado El Dorado Hills Apartments Project Draft Environmental Impact Report SCH No. 2017042017 Prepared by: 505 14th Street, Suite 1230 Oakland, California 94612 Prepared For: County of El

More information

5.0 ALTERNATIVES 5.1 INTRODUCTION

5.0 ALTERNATIVES 5.1 INTRODUCTION 5.1 INTRODUCTION The California Environmental Quality Act (CEQA) Guidelines state that an EIR shall describe a range of reasonable alternatives to the Project, or to the location of the Project, which

More information

MITIGATION MONITORING & REPORTING PLAN

MITIGATION MONITORING & REPORTING PLAN MITIGATION MONITORING & REPORTING PLAN The following environmental mitigation measures shall be incorporated into the project development as Conditions of Approval (MND 2318). The Project Applicant shall

More information

Addendum to Mitigated Negative Declaration

Addendum to Mitigated Negative Declaration REMARKS Background Addendum to Mitigated Negative Declaration Date of Publication of Addendum: Date of Final MND: March 29, 2012 Case No.: 2004.1004E Project Title: 1150 16 th Street Residential Retail

More information

RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Second Addendum to the Final Environmental Impact Report

RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Second Addendum to the Final Environmental Impact Report RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Second Addendum to the Final Environmental Impact Report January 2017 State Clearinghouse Number 2014012012 Project Number 93294057 Prepared

More information

PROJECT DESCRIPTION...

PROJECT DESCRIPTION... TABLE OF CONTENTS Volume I Chapter Page 1. INTRODUCTION... 1-1 1.1 Introduction... 1-1 1.2 Project Description... 1-1 1.3 Purpose of the EIR... 1-2 1.4 EIR Process... 1-3 1.5 Scope of the Draft EIR...

More information

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,

More information

NORTH BOWL PARKING LOT PHASE 1

NORTH BOWL PARKING LOT PHASE 1 NORTH BOWL PARKING LOT PHASE 1 Addendum No. 2 to the 2009 UC Merced Long Range Development Plan Environmental Impact Statement / Environmental Impact Report The following Addendum has been prepared in

More information

Waste Management of North County Compressed Natural Gas Vehicle Fueling Facility

Waste Management of North County Compressed Natural Gas Vehicle Fueling Facility Final Mitigated Negative Declaration for the Waste Management of North County Compressed Natural Gas Vehicle Fueling Facility O C T O B E R 2 0 1 2 L E A D A G E N C Y: City of Oceanside 300 North Coast

More information

Peninsula Corridor Electrification Project. Draft Environmental Impact Report

Peninsula Corridor Electrification Project. Draft Environmental Impact Report Peninsula Corridor Electrification Project Draft Environmental Impact Report Public Meeting Purpose of Tonight s Meeting Provide an overview of Draft Environmental Impact Report (Draft EIR) Receive comments,

More information

2. Introduction. California Environmental Quality Act (CEQA) of 1970, as amended (Public Resources Code Section et seq.)

2. Introduction. California Environmental Quality Act (CEQA) of 1970, as amended (Public Resources Code Section et seq.) 2.1 PURPOSE OF THE ENVIRONMENTAL IMPACT REPORT The California Environmental Quality Act requires that all State and local governmental agencies consider the environmental consequences of projects over

More information

JACK LONDON SQUARE REDEVELOPMENT PROJECT

JACK LONDON SQUARE REDEVELOPMENT PROJECT JACK LONDON SQUARE REDEVELOPMENT PROJECT Addendum to the 2004 EIR SCH No. 2003022086 Prepared for May 9, 2014 The City of Oakland JACK LONDON SQUARE REDEVELOPMENT PROJECT Addendum to the 2004 EIR SCH

More information

David Balducci, Align Real Estate Doug Flaming, Doug Flaming Construction Management, Inc. Shari Libicki, Sarah Manzano, Kevin Warner

David Balducci, Align Real Estate Doug Flaming, Doug Flaming Construction Management, Inc. Shari Libicki, Sarah Manzano, Kevin Warner MEMO Date: 1/13/17 To From CC David Balducci, Align Real Estate Doug Flaming, Doug Flaming Construction Management, Inc. Shari Libicki, Sarah Manzano, Kevin Warner Amara Morrison, Wendel Rosen Black &

More information

APPENDIX G. Alternatives Background: Air Quality, GHG and Transportation and Circulation

APPENDIX G. Alternatives Background: Air Quality, GHG and Transportation and Circulation APPENDIX G Alternatives Background: Air Quality, GHG and Transportation and Circulation Marin General Hospital Replacement Building Project G-1 ESA / 210606 Draft EIR August 2012 This page intentionally

More information

From: City of Santa Cruz, Planning Dept., 809 Center Street, Room 206, Santa Cruz, CA 95060

From: City of Santa Cruz, Planning Dept., 809 Center Street, Room 206, Santa Cruz, CA 95060 CITY OF SANTA CRUZ Notice of Exemption To: Clerk of the Board Office of Planning and Research County of Santa Cruz 1400 Tenth Street, Room 121 Governmental Center Sacramento, CA 95814 701 Ocean Street

More information

Draft Environmental Impact Report Serramonte Views Condominiums and Hotel Project

Draft Environmental Impact Report Serramonte Views Condominiums and Hotel Project Draft Environmental Impact Report Serramonte Views Condominiums and Hotel Project File Nos. GPA-9-14-9640, PD-9-14-9637, SUB-9-14-9643, Design Review-9-14-9644, UPR-1-18-013248 SCH# 2016062063 Prepared

More information

CORRECTIONS AND ADDITIONS

CORRECTIONS AND ADDITIONS II CORRECTIONS AND ADDITIONS Hudson Ranch Power II and Simbol Calipatria II Final EIR This page intentionally left blank. Hudson Ranch Power II and Simbol Calipatria II Final EIR II CORRECTIONS AND ADDITIONS

More information

Noise Abatement Decision Report. Addendum. Supplemented by the August 2015 Noise Study Report Addendum

Noise Abatement Decision Report. Addendum. Supplemented by the August 2015 Noise Study Report Addendum Interstate 10 Corridor Project Draft NADR Addendum Noise Abatement Decision Report Addendum Supplemented by the August 2015 Noise Study Report Addendum San Bernardino and Los Angeles Counties 07-LA-10

More information

RESOLUTION NO:

RESOLUTION NO: RESOLUTION NO: 11-031 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PASO ROBLES CERTIFYING THE FINAL ENVIRONMENTAL IMPACT REPORT FOR THE 2011 CIRCULATION ELEMENT OF THE GENERAL PLAN AND ADOPTING FINDINGS,

More information

Alternative 3: San Vicente 50,000 AF + Moosa 50,000 AF Air Quality

Alternative 3: San Vicente 50,000 AF + Moosa 50,000 AF Air Quality 5.5 This section evaluates the potential impacts of the SV 50K/Moosa 50K Alternative on air quality. This evaluation includes an assessment of the direct, indirect, construction-related, longterm, and

More information

6. Cumulative Impacts

6. Cumulative Impacts 6.1 OVERVIEW Section 15355 of the California Environmental Quality Act (CEQA) Guidelines defines cumulative impacts as: "...two or more individual effects which when considered together, are considerable

More information

Section 2.0 Introduction and Purpose

Section 2.0 Introduction and Purpose Section 2.0 SECTION 2.0 INTRODUCTION AND PURPOSE The California Environmental Quality Act (CEQA) requires that all State and local agencies consider the environmental consequences of projects over which

More information

3.12 NOISE Regulatory Setting Environmental Setting EXISTING NOISE SOURCES AND SENSITIVE LAND USES

3.12 NOISE Regulatory Setting Environmental Setting EXISTING NOISE SOURCES AND SENSITIVE LAND USES 3.12 NOISE This section assesses the potential for implementation of the West Village Expansion component to result in impacts related to short-term construction, long-term operational noise sources, and

More information

Council Agenda Report

Council Agenda Report Agenda Item # 7 Council Agenda Report SUBJECT: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RIO VISTA APPROVING THE PRELIMINARY ENGINEERING REPORT, CONCEPT PLANS DESIGNS AND FINAL INITIAL STUDY/MITIGATED

More information

Facebook Campus Project. City Council Study Session January 31, 2012

Facebook Campus Project. City Council Study Session January 31, 2012 Facebook Campus Project City Council Study Session January 31, 2012 Meeting Purpose Opportunity for the City Council to become familiar with project and reports released to date Opportunity for the City

More information

Subject: Notice of Preparation of a Draft Environmental Impact Report

Subject: Notice of Preparation of a Draft Environmental Impact Report NOTICE OF PREPARATION From: Santa Clara Valley Water District 5750 Almaden Expressway San Jose, CA 95118 Subject: Notice of Preparation of a Draft Environmental Impact Report Project Title: Guadalupe Dam

More information

4.8 GREENHOUSE GAS INTRODUCTION ENVIRONMENTAL SETTING. Section 4.8 Greenhouse Gas

4.8 GREENHOUSE GAS INTRODUCTION ENVIRONMENTAL SETTING. Section 4.8 Greenhouse Gas 4.8 GREENHOUSE GAS 4.8.1 INTRODUCTION This section provides an overview of the existing greenhouse gas conditions within the project area and surrounding region, regulatory framework, and environmental

More information

San Ramon City Center Draft Subsequent EIR

San Ramon City Center Draft Subsequent EIR San Ramon City Center State Clearinghouse Number 2007042022 Prepared for: City of San Ramon Planning/Community Development Department Planning Services Division 2222 Camino Ramon San Ramon, CA 94583 Prepared

More information

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE Chapter 17: Construction A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter discusses the various activities that would be involved in constructing Hamilton Green. The potential for significant adverse

More information

ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project

ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project Original Final EIR (SCH# 2010031024) (by SGS Antelope Valley Development, LLC) ROSAMOND SOLAR MODIFICATION PROJECT (Sites 5 &

More information

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT CONTENTS DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CENTINELA SOLAR ENERGY PROJECT CHAPTER 1.0 INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT... 1.0 1 1.2 PROJECT BACKGROUND... 1.0 1 1.3 Project

More information

Final Elk Grove Sphere of Influence Amendment and Multi-Sport Park Complex Environmental Impact Report (SCH# )

Final Elk Grove Sphere of Influence Amendment and Multi-Sport Park Complex Environmental Impact Report (SCH# ) Final Elk Grove Sphere of Influence Amendment and Multi-Sport Park Complex Environmental Impact Report (SCH# 2015102067) Prepared for: Sacramento Local Agency Formation Commission City of Elk Grove March

More information

III. Corrections and Additions

III. Corrections and Additions A. Introduction The following corrections and additions are set forth to update the 100 W. Walnut Planned Development Draft Environmental Impact Report (Draft EIR) in response to the comments received

More information

FIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015

FIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015 FIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015 CITY OF SANTA MONICA PLANNING AND COMMUNITY DEVELOPMENT 1685 MAIN STREET SANTA MONICA, CA 90401 INTRODUCTION This document is the Fifth Addendum

More information

CEQA FINDINGS IN CONNECTION WITH THE APPROVAL OF THE INTEGRATIVE GENOMICS BUILDING PROJECT, LAWRENCE BERKELEY NATIONAL LABORATORY

CEQA FINDINGS IN CONNECTION WITH THE APPROVAL OF THE INTEGRATIVE GENOMICS BUILDING PROJECT, LAWRENCE BERKELEY NATIONAL LABORATORY ATTACHMENT 4 CEQA FINDINGS IN CONNECTION WITH THE APPROVAL OF THE INTEGRATIVE GENOMICS BUILDING PROJECT, LAWRENCE BERKELEY NATIONAL LABORATORY I. CONSIDERATION OF THE 2006 LRDP EIR AND INTEGRATIVE GENOMICS

More information

LOS ANGELES INTERNATIONAL AIRPORT (LAX) UNITED AIRLINES EAST AIRCRAFT MAINTENANCE AND GROUND SUPPORT EQUIPMENT PROJECT

LOS ANGELES INTERNATIONAL AIRPORT (LAX) UNITED AIRLINES EAST AIRCRAFT MAINTENANCE AND GROUND SUPPORT EQUIPMENT PROJECT Draft Environmental Impact Report () LOS ANGELES INTERNATIONAL AIRPORT (LAX) UNITED AIRLINES EAST AIRCRAFT MAINTENANCE AND GROUND SUPPORT EQUIPMENT PROJECT Map data 2018 Google [State Clearinghouse No.

More information

HELENA CHEMICAL COMPANY NELSON TERMINAL PROJECT USE PERMIT UP Butte County Board of Supervisors January 29, 2013

HELENA CHEMICAL COMPANY NELSON TERMINAL PROJECT USE PERMIT UP Butte County Board of Supervisors January 29, 2013 HELENA CHEMICAL COMPANY NELSON TERMINAL PROJECT USE PERMIT UP10-0003 Butte County Board of Supervisors January 29, 2013 Helena Chemical Nelson Terminal Project Develop the Nelson site for use as a regional

More information

Appendix D1 Screening Analysis

Appendix D1 Screening Analysis Appendix D Screening Analysis of Additional Resource Areas for Consideration in the CS SEIR due to Assumed Incremental Increase in Terminal Throughput under the Revised Project Appendix D1 Screening Analysis

More information

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview... TABLE OF CONTENTS 4 DESCRIPTION AND EVALUATION OF ALTERNATIVES... 4-1 4.1 INTRODUCTION... 4-1 4.2 METHODOLOGY... 4-1 4.3 DESCRIPTION OF ALTERNATIVES... 4-2 4.3.1 No Project Alternative... 4-2 4.3.2 Alternative

More information

Prado Planned Deviation Project Air Quality/Greenhouse Gas Emissions

Prado Planned Deviation Project Air Quality/Greenhouse Gas Emissions August 17, 2015 Daniel Bott Principal Planner Orange County Water District 18700 Ward Street Fountain Valley, California 92708 VIA EMAIL DBott@OCWD.com Subject: Prado Planned Deviation Project Air Quality/Greenhouse

More information

COMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts

COMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts COMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts March 2004 Prepared for: New York City Department of Sanitation

More information

CHAPTER 2 DESIGN REFINEMENTS

CHAPTER 2 DESIGN REFINEMENTS CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements

More information

Section 4.8 Climate Change

Section 4.8 Climate Change Section 4.8 Climate Change This section summarizes the potential for climate change impacts resulting from construction and operation of the proposed Eastside Transit Corridor Phase 2 Project alternatives.

More information