ERRATA TO THE FINAL EIR
|
|
- Daisy Palmer
- 5 years ago
- Views:
Transcription
1 DRAFT EIR ERRATA TO THE FINAL EIR The following paragraphs in Section 6.0, Alternatives, are edited as follows: The following discussion evaluates alternatives to the Proposed Project and examines the potential of each alternative to avoid or substantially lessen its potential environmental impacts. CEQA requires the comparison of environmentally superior alternatives in an EIR. As the only significant and unavoidable impact for this Proposed Project is air quality during construction, it is the one impact comparison discussed for each Alternative. While the Proposed Project is not anticipated to result in significant traffic impacts, a traffic impact analysis is provided for each alternative for informational and decision-making purposes only. Through comparison of these alternatives to the Proposed Project, the relative environmental advantages and disadvantages of each are weighed and analyzed. Based on the CEQA Guidelines, several factors need to be considered in determining the range of alternatives to be analyzed in the EIR and the level of analytical detail that should be provided for each alternative. These factors include: (1) the nature of the significant impacts of the Proposed Project, (2) the ability of alternatives to avoid or lessen the significant impacts associated with the Proposed Project, (3) the ability of the alternatives to meet the objectives of the Proposed Project, and (4) the feasibility of the alternatives. The analysis in this EIR shows that all impacts of the Proposed Project can either be mitigated to a level of less than significant or are less than significant. The alternatives examined herein represent alternatives that are intended to reduce or avoid certain the significant but mitigable impacts associated with implementation of the Proposed Project. As required by Section of the CEQA Guidelines, this section of the EIR examines a range of reasonable alternatives to the Proposed Project. A Reduced Project alternative to lessen the significant and unavoidable impact on air quality during construction was considered, as discussed below, but rejected as infeasible. In addition, the following paragraphs and subsequent tables in Section 6.0, Alternatives, subsection, 6.2, Alternative 2: Commercial Development in Accordance with Current General Plan Designation, are edited as follows: As shown in Table 6-2, the maximum daily emissions of ROGs during construction for Alternative 2 would be substantially higher than those of the Proposed Project, primarily owing to the application of architectural coatings. According to SCAQMD Rule 1113, architectural coatings used on commercial buildings may emit higher ROGs than those used on residential buildings, which would result in higher ROG emissions for Alternative 2 than the Proposed Project, even though the Proposed Project has a larger building footprint; but, similar to the Proposed Project, maximum daily ROG emissions would exceed the SCAQMD threshold of 75 lbs/day. No other SCAQMD thresholds or Localized Significance Thresholds (LSTs) would be exceeded. Mitigation Measure AQ-1 would apply to reduce ROG emissions by applying lowemission architectural coatings and extending the duration of painting. Overall impacts on air quality during construction would be less than significant with mitigation incorporated. 1-1 September 2016
2 Table 6-2 Alternative 2 Construction Emissions Alternative 2 Maximum Daily Construction Emissions 2017 Maximum Estimated Maximum Emissions (lbs/day) 1 ROG NOX CO PM10 PM Alternative 2 Maximum Daily On-Site Construction Emissions 2017 Maximum On-Site On-Site n/a 193 1, Proposed Project Maximum Daily Construction Emissions for Comparison 2017 Maximum n/a 193 1, Notes: All calculations were made using CalEEMod. See Appendix E (Appendix C) for calculations. Grading, Paving, Building Construction, and Architectural Coating totals include worker trips, soil export hauling trips, construction vehicle emissions, and fugitive dust. Numbers may not add up due to rounding error 1. Grading phases incorporate anticipated emissions reductions from the conditions listed above, which are required by SCAQMD Rule 403 to reduce fugitive dust. The architectural coating phases incorporate anticipated emissions reductions from the conditions listed above, which are required by Rule LSTs are for a acre Project in SRA-6 within a distance of 82 feet from the site boundary. 1-2 September 2016
3 Table 6-3 Alternative 2 Operational Emissions Estimated Maximum Emissions (lbs/day) Emissions Source ROG NOX CO SOx PM10 PM2.5 Vehicles Electricity and Natural Gas Consumption, 16.8 Landscaping, Consumer Products < Subtotal Existing Emissions to be Removed 1 (13.1) (19.4) (89.5) (0.1) (8.4) (2.4) Net Emissions Increase - Alternative SCAQMD Thresholds Threshold Exceeded? No No No No No No Proposed Project Net Operational Emissions for Comparison SCAQMD Thresholds Threshold Exceeded? No No No No No No See Appendix E (Appendix C)for CalEEMod computer model output. Note: Numbers may not add up due to rounding. ( ) indicates subtraction, Numbers may not add due to rounding 1. See Table in Section 4.1, Air Quality Likewise, the following paragraphs and subsequent tables in Section 6.0, Alternatives, subsection, 6.3, Alternative 3: Mixed-Use, are edited as follows: As shown in Table 6-9, maximum daily emissions of ROGs for Alternative 3 would be higher than those of the Proposed Project, primarily owing to emissions from architectural coatings. The discussion above regarding Alternative 2 states that according to SCAQMD Rule 1113, architectural coatings used on commercial buildings may emit higher ROGs than those used on residential buildings. This use would result in higher ROG emissions for Alternative 3 than the Proposed Project, even though the Proposed Project has a larger building footprint. Similar to the Proposed Project, maximum daily ROG emissions for Alternative 3 would exceed the SCAQMD threshold of 75 lbs/day, but no other SCAQMD thresholds or LSTs would be exceeded. Mitigation Measure AQ-1 would apply to reduce ROG emissions by applying lowemission architectural coatings and extending the duration of painting. 1-3 September 2016
4 Table 6-9 Alternative 3 Construction Emissions Estimated Maximum Emissions (lbs/day) 1 Alternative 3 Maximum Daily Construction Emissions 2017 Maximum ROG NOX CO PM10 PM Alternative 3 Maximum Daily On-Site Construction Emissions 2017 Maximum On-Site On-Site n/a 193 1, Proposed Project Maximum Daily Construction Emissions for Comparison 2017 Maximum n/a 193 1, Notes: All calculations were made using CalEEMod. See Appendix E (Appendix C) for calculations. Grading, Paving, Building Construction, and Architectural Coating totals include worker trips, soil export hauling trips, construction vehicle emissions, and fugitive dust. Numbers may not add up due to rounding error 1. Grading phases incorporate anticipated emissions reductions from the conditions listed above, which are required by SCAQMD Rule 403 to reduce fugitive dust. The architectural coating phases incorporate anticipated emissions reductions from the conditions listed above, which are required by Rule LSTs are for a acre Project in SRA-6 within a distance of 82 feet from the site boundary. 1-4 September 2016
5 Emissions Source Vehicles Electricity and Natural Gas Consumption, Landscaping, Consumer Products Subtotal Table 6-10 Alternative 3 Operational Emissions Estimated Maximum Emissions (lbs/day) ROG NOX CO SOx PM10 PM < Existing Emissions to be Removed 1 (13.1) (19.4) (89.5) (0.1) (8.4) (2.4) Net Emissions Increase - Alternative SCAQMD Thresholds Threshold Exceeded? No No No No No No See Appendix E (Appendix C) for CalEEMod computer model output. Note: Numbers may not add up due to rounding. ( ) indicates subtraction, Numbers may not add due to rounding 1. See Table in Section 4.1, Air Quality h. Alternative 3 Summary. Most mitigation measures for the Proposed Project would apply to Alternative 3, allowing impacts to be mitigated to less than significant levels except for impacts on air quality from construction activities. Construction air quality and Operational impacts for Alternative 3 would be greater than for the Proposed Project. Alternative 3 would increase trip generation relative to the existing conditions by an estimated 3,865 average daily trips, 120 additional trips during the A.M. peak hours and 273 additional trips during the P.M. peak hours. Traffic impacts would occur at one of the studied intersections during the P.M. peak hours (Topanga Canyon Boulevard/Ventura Boulevard). Further analysis would be required to determine whether additional impacts would occur outside of the current study area. Due to the increase in traffic, this alternative would result in higher CO levels at local intersections. Operational emissions for Alternative 3 in all categories would also increase relative to the Proposed Project. However, neither Alternative 3 nor the Proposed Project would generate emissions exceeding SCAQMD thresholds. 1-5 September 2016
6 This page left intentionally blank 1-6 September 2016
3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS
3 CONSTRUCTION-GENERATED CRITERIA AIR POLLUTANT AND PRECURSOR EMISSIONS 3.1 INTRODUCTION Construction activities have the potential to generate a substantial amount of air pollution. In some cases, the
More information3.0 ERRATA TO THE DRAFT EIR
Errata to the Draft EIR 3.0 ERRATA TO THE DRAFT EIR 3.1 Introduction This section includes the minor changes to the Draft EIR because of typographical errors, clarification of wording, correction of references,
More informationAPPENDIX II.2. Land Use Equivalency Program Technical Report Prepared by Christopher A. Joseph & Associates, May 2010
APPENDIX II.2 Land Use Equivalency Program Technical Report Prepared by Christopher A. Joseph & Associates, May 2010 LAND USE EQUIVALENCY PROGRAM TECHNICAL REPORT Prepared for: Wilshire Grand Redevelopment
More informationTuscan Village Addendum
Tuscan Village Addendum To: Date: Subject: Bruce Ambo, Principal Planner, City of Chico Planning Services March 19, 2018 Tuscan Village Addendum (Amber Lynn Estates) Response to Butte County AQMD Comments
More informationSchwan Self-Storage. Addendum to Schwan Self-Storage Project Mitigated Negative Declaration Case No DP RV
Schwan Self-Storage Addendum to Schwan Self-Storage Project Mitigated Negative Declaration Case No. 17-055-DP RV Prepared by: City of Goleta 130 Cremona Drive, Suite B Goleta, CA 93117 September 2017 Addendum
More informationHollister Village Apartments. Addendum to Westar Village Final Environmental Impact Report Case No
Addendum to Westar Village Final Environmental Impact Report Case No. 16-029 Prepared by: City of Goleta 130 Cremona Drive, Suite B Goleta, CA 93117 Prepared July 2016 Revised February 2017 and July 2017
More information5.0 ALTERNATIVE VARIATIONS
5.0 ALTERNATIVE VARIATIONS 5.1 INTRODUCTION The Draft EIR for the Beverly Hilton Revitalization Plan evaluated five alternatives to the project, pursuant to Section 15126.6 of the California Environmental
More informationAPPENDIX G. Alternatives Background: Air Quality, GHG and Transportation and Circulation
APPENDIX G Alternatives Background: Air Quality, GHG and Transportation and Circulation Marin General Hospital Replacement Building Project G-1 ESA / 210606 Draft EIR August 2012 This page intentionally
More informationLOS ANGELES INTERNATIONAL AIRPORT (LAX) UNITED AIRLINES EAST AIRCRAFT MAINTENANCE AND GROUND SUPPORT EQUIPMENT PROJECT
Draft Environmental Impact Report () LOS ANGELES INTERNATIONAL AIRPORT (LAX) UNITED AIRLINES EAST AIRCRAFT MAINTENANCE AND GROUND SUPPORT EQUIPMENT PROJECT Map data 2018 Google [State Clearinghouse No.
More informationPARKMERCED PROJECT EIR ERRATA
PARKMERCED PROJECT EIR ERRATA This section presents additional staff initiated text changes for the Parkmerced Project Draft Environmental Impact Report. These EIR text changes reflect revisions that have
More informationIntroduction. Chapter 3 Modifications to the Draft EIS/EIR
1 2 Chapter 3 Modifications to the Draft EIS/EIR 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Introduction This chapter of the document addresses modifications to
More informationKevin Johnson Design & Historic Preservation Section City of Pasadena Planning & Community Development Department
Memorandum To: Kevin Johnson Design & Historic Preservation Section City of Pasadena Planning & Community Development Department From: Rusty Whisman and Terrance Wong, ICF CC: Charles Smith and Tamseel
More informationSECTION 6.0 Alternatives to the Proposed Project
SECTION 6.0 Alternatives to the Proposed Project 6.0 ALTERNATIVES TO THE PROPOSED PROJECT CEQA requires that an EIR include an analysis of a range of project alternatives that could feasibly attain most
More information5.0 ALTERNATIVES 5.1 INTRODUCTION
5.1 INTRODUCTION The California Environmental Quality Act (CEQA) Guidelines state that an EIR shall describe a range of reasonable alternatives to the Project, or to the location of the Project, which
More informationALTERNATIVES TECHNICAL DETAIL
ALTERNATIVES TECHNICAL DETAIL June 2016 TRIP GENERATION TABLE 1 SUMMARY OF PROJECT ALTERNATIVE LAND USE PLANS Project Alternative A Alternative B Alternative C Residential Units (Dwelling Units) Single-Family
More informationAir Quality/Greenhouse Gas Analysis for the Duke Warehouse at Perris Boulevard and Markham Street Project (DPR ), City of Perris
WO: 2017-8 Technical Memorandum To: From: Adam Schmid, Duke Realty Eliza Laws, Senior Environmental Analyst Noemi Avila, Assistant Environmental Analyst Date: December 13, 2017 Re: Air Quality/Greenhouse
More informationAPPENDIX 4.5 Greenhouse Gas Emissions
APPENDIX 4.5 Greenhouse Gas Emissions Road Construction Emissions Model, Version 6.3.2 Emission Estimates for -> Via Princessa East Extension Total Exhaust Fugitive Dust Total Exhaust Fugitive Dust Project
More informationAppendix A. Notice of Preparation and Comment Letters
Appendix A Notice of Preparation and Comment Letters South Coast Air Quality Management District 21865 Copley Drive, Diamond Bar, CA 91765-4182 (909) 396-2000 www.aqmd.gov March 3, 2010 Mr. Louie
More informationCourtyard and Towneplace Suites Hotel Project Air Quality Study
Courtyard and Towneplace Suites Hotel Project TABLE OF CONTENTS Page Project Description... 1 Air Quality Background... 1 Local Climate and Meteorology... 1 Air Quality Regulation... 2 Current Air Quality...
More informationCity of Long Beach Shoreline Gateway East Tower Project. Addendum to the Final Environmental Impact Report
Shoreline Gateway East Tower Project Addendum to the Final Environmental Impact Report October 2016 ADDENDUM TO THE FINAL ENVIRONMNETAL IMPACT REPORT SHORELINE GATEWAY EAST TOWER PROJECT Prepared for:
More informationFinal Initial Study/Mitigated Negative Declaration Indianola Subdivision Project City of Sanger, Fresno County, California
Final Initial Study/Mitigated Negative Declaration Indianola Subdivision Project City of Sanger, Fresno County, California Prepared for: City of Sanger 1700 7 th Street Sanger, CA 93657 559.876.6300 Contact:
More information6.1 SIGNIFICANT IMPACTS OF THE PROJECT
SECTION 6.0 ALTERNATIVES CEQA requires that an EIR identify alternatives to a project as it is proposed. The CEQA Guidelines specify that the EIR should identify alternatives which would feasibly attain
More informationAlternative 3: San Vicente 50,000 AF + Moosa 50,000 AF Air Quality
5.5 This section evaluates the potential impacts of the SV 50K/Moosa 50K Alternative on air quality. This evaluation includes an assessment of the direct, indirect, construction-related, longterm, and
More informationAPPENDIX A. CalEEMod Model Output
APPENDIX A CalEEMod Model Output This page intentionally left blank. Remarks for the San Joaquin Valley Christian School Project Greenhouse Gas Emissions Methodology and Modeling Calculations November
More informationExhibit G. Construction Mitigation Plan
Exhibit G Construction Mitigation Plan Construction Period Mitigation 1. A construction period mitigation plan shall be prepared by the applicant for approval by the Public Works Department prior to issuance
More informationDRAFT ENVIRONMENTAL IMPACT REPORT
DRAFT ENVIRONMENTAL IMPACT REPORT Beverly Hills High School, Hawthorne K-8 School, and El Rodeo K-8 School Improvement Project Prepared for: BEVERLY HILLS UNIFIED SCHOOL DISTRICT 255 South Lasky Drive
More informationStaybridge Suites Hotel
Staybridge Suites Hotel Initial Study Mitigated Negative Declaration prepared by City of Long Beach 333 W. Ocean Boulevard, 5 th Floor Long Beach, California 90802 prepared with the assistance of Rincon
More informationMonterey Bay Unified Air Pollution Control District (
3.3.8 Air Quality Introduction The Air Quality section addresses the impacts of the project on ambient air quality and the exposure of people, especially sensitive individuals, to hazardous pollutant concentrations.
More information5.0 ALTERNATIVES ANALYSIS
5.0 ALTERNATIVES ANALYSIS In accordance with the California Environmental Quality Act (CEQA), an Environmental Impact Report (EIR) must include the evaluation of comparative effects of a range of reasonable
More informationOakland Planning Commission August 3, 2016 Case File Number: PLN Item #5: Additional Construction Emissions Analysis
Oakland Planning Commission August 3, 216 Case File Number: PLN16133 Item #5: Additional Construction Emissions Analysis July 5, 216 Memo to: Justin Osler, The Martin Group From: Allan Daly Subject: Evaluation
More informationCity of Anaheim Hines OC Link Apartments Project Air Quality Technical Memorandum.
VISTA ENVIRONMENTAL February, 0 Josh Haskins Sagecrest Planning & Environmental 00 E. Katella Avenue, Suite 00 Anaheim, CA 0 Subject: City of Anaheim Hines OC Link Apartments Project Air Quality Technical
More information4.8 GREENHOUSE GAS INTRODUCTION ENVIRONMENTAL SETTING. Section 4.8 Greenhouse Gas
4.8 GREENHOUSE GAS 4.8.1 INTRODUCTION This section provides an overview of the existing greenhouse gas conditions within the project area and surrounding region, regulatory framework, and environmental
More informationUS Army Corps of Engineers Los Angeles District. Los Angeles River Ecosystem Restoration Feasibility Study. DRAFT APPENDIX F Air Quality
US Army Corps of Engineers Los Angeles District Los Angeles River Ecosystem Restoration Feasibility Study DRAFT APPENDIX F Air Quality This page left blank intentionally LOS ANGELES RIVER ECOSYSTEM RESTORATION
More informationCEQA AIR QUALITY HANDBOOK. Guidelines for the Implementation of the. California Environmental Quality Act of 1970, as amended
CEQA AIR QUALITY HANDBOOK Guidelines for the Implementation of the California Environmental Quality Act of 1970, as amended As Amended by Imperial County Air Pollution Control District 150 South Ninth
More information7.1 Introduction. 7.2 Criteria for Alternatives Analysis
SECTION 7.0 Alternatives Analysis 7.1 Introduction The identification and analysis of alternatives is a fundamental concept under California Environmental Quality Act (CEQA). The role of alternatives in
More informationCHAPTER 3 ENVIRONMENTAL SETTING AND PROJECT IMPACTS
CHAPTER 3 ENVIRONMENTAL SETTING AND PROJECT IMPACTS 3.0 INTRODUCTION This chapter describes the area of influence, setting (environmental and regulatory), methodology, potential impacts, and mitigation
More informationFinal Environmental Impact Statement/Final Environment Impact Report Appendix K Responses to Comments Received
Final Environmental Impact Statement/Final Environment Impact Report August 2011 K-153 Final Environmental Impact Statement/Final Environmental Impact Report K-154 August 2011 Final Environmental Impact
More informationRENAISSANCE EAST ADDENDUM TO THE RENAISSANCE SPECIFIC PLAN FINAL ENVIRONMENTAL IMPACT REPORT VOLUME 1 OF 2 STATE CLEARINGHOUSE #
RENAISSANCE EAST ADDENDUM TO THE RENAISSANCE SPECIFIC PLAN FINAL ENVIRONMENTAL IMPACT REPORT VOLUME 1 OF 2 STATE CLEARINGHOUSE #2006071021 Prepared For: City of Rialto 150 South Palm Avenue Rialto, CA
More informationAnalysis of Alternatives
Chapter Analysis of Alternatives 0. Introduction This chapter presents a comparison of alternatives to the proposed Project. Various Project alternatives were considered during preparation of this Draft
More informationVista Canyon Transit Center - Air Quality Technical Memorandum
803 Camarillo Springs Road, Suite C Camarillo, California 93012 (805) 437-1900 FAX (805) 437 1901 www.impactsciences.com MEMORANDUM To: Kris Markarian, City of Santa Clarita Job No. 1046.003 From: Susan
More information4.12 AIR QUALITY INTRODUCTION
4.12 AIR QUALITY INTRODUCTION Air quality is an environmental factor that helps to define the quality of life throughout the San Joaquin Valley. In Fresno County, ambient air quality conditions presently
More informationPrado Planned Deviation Project Air Quality/Greenhouse Gas Emissions
August 17, 2015 Daniel Bott Principal Planner Orange County Water District 18700 Ward Street Fountain Valley, California 92708 VIA EMAIL DBott@OCWD.com Subject: Prado Planned Deviation Project Air Quality/Greenhouse
More informationSECTION 6: ALTERNATIVES TO THE PROPOSED PROJECT
Recirculated Draft EIR No. 534 Alternatives to the Proposed Project SECTION 6: ALTERNATIVES TO THE PROPOSED PROJECT 6.1 - Introduction In accordance with State CEQA Guidelines Section 15126.6, this Recirculated
More informationFacebook Campus Project. City Council Study Session January 31, 2012
Facebook Campus Project City Council Study Session January 31, 2012 Meeting Purpose Opportunity for the City Council to become familiar with project and reports released to date Opportunity for the City
More information7.0 ALTERNATIVES PURPOSE SELECTION OF ALTERNATIVES FOR ANALYSIS
7.0 ALTERNATIVES PURPOSE This section of the EIR provides a comparative analysis of the merits of alternatives to the proposed project pursuant to Section 15126.6 of the California Environmental Quality
More informationAppendix FEIR-D. Air Quality and Greenhouse Gas Memorandum
Appendix FEIR-D Air Quality and Greenhouse Gas Memorandum Appendix FEIR-D Air Quality and Greenhouse Gas Memorandum This Air Quality and Greenhouse Gas Memorandum (AQ/GHG Memo) has been prepared by Eyestone
More informationSECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT
City of American Canyon Broadway District Specific Plan Alternatives to the Proposed Project SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT 5.1 Introduction In accordance with CEQA Guidelines Section
More informationDraft Environmental Impact Report
Pacific Pointe East Development Project Draft Environmental Impact Report SCH # 2014011059 April 2014 Draft Environmental Impact Report Pacific Pointe East Development Project Prepared by: Development
More informationIII. Corrections and Additions
A. Introduction The following corrections and additions are set forth to update the 100 W. Walnut Planned Development Draft Environmental Impact Report (Draft EIR) in response to the comments received
More informationPROJECT ALTERNATIVES 1.0 INTRODUCTION
VI. PROJECT ALTERNATIVES 1.0 INTRODUCTION The California Environmental Quality Act (CEQA) Guidelines (Section 15126.6(a)) require an EIR to (1) describe a range of reasonable alternatives to the proposed
More informationSection 4.7 Air Quality
Section 4.7 Air Quality This section summarizes the potential for air quality impacts resulting from construction and operation of the proposed Eastside Transit Corridor Phase 2 Project alternatives. Information
More information24.12 CHAPTER 12 - AIR QUALITY
. CHAPTER - AIR QUALITY Section.., DEIR/EIS page -, FEIR/EIS page -: Revisions based on public comment.. Climate and Topography The primary factors that determine air quality are the locations of air pollutant
More information3.1 LAND USE Existing Environmental Setting Certified 2008 EIR
3.1 LAND USE 3.1.1 Existing Environmental Setting Please see Section 4.1 of the certified 2008 EIR for a summary of the existing environmental setting for Land Use. The subject property from the certified
More informationVI. ALTERNATIVES ALTERNATIVES TO THE PROPOSED PROJECT
VI. ALTERNATIVES The CEQA Guidelines require that EIRs include the identification and evaluation of a reasonable range of alternatives that are designed to reduce the significant environmental impacts
More informationSECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT
SECTION 5: ALTERNATIVES TO THE PROPOSED PROJECT 5.1 - Introduction In accordance with CEQA Guidelines Section 15126.6, this Draft Subsequent Environmental Impact Report (DSEIR) contains a comparative impact
More informationEnvironmental Analysis, Chapter 4 Consequences, and Mitigation
Environmental Analysis, Chapter 4 4.5 Air Quality This section describes the air quality conditions for the project area and analyzes both shortterm impacts of emissions during construction and long-term
More information4.3 AIR QUALITY Setting
4.3 AIR QUALITY This section assesses the impacts of the proposed Specific Plan on local and regional air quality. Both temporary impacts relating to onsite construction activity and long-term impacts
More informationf. Implement a high-quality architectural design that improves the overall aesthetics of the project site and surrounding area.
September 20, 2018 Craig Spencer, Supervising Planner Monterey County Resource Management Agency Planning Department 1441 Schilling Place Salinas, California 93901 Subject: Rio Ranch Market Place Draft
More informationLOWE S HOME IMPROVEMENT WAREHOUSE
LOWE S HOME IMPROVEMENT WAREHOUSE DRAFT ENVIRONMENTAL IMPACT REPORT V. PROJECT ALTERNATIVES A. Introduction Section III of this document provides a detailed analysis of potential impacts associated with
More informationAir Quality and Greenhouse Gas Analysis
Air Quality and Greenhouse Gas Analysis Prepared for: BRENTWOOD DEVELOPMENTS JANUARY 2018 Prepared by: 1501 Sports Drive, Suite A Sacramento CA 95834 Office 916.372.6100 Fax 916.419.6108 INFO@raneymanagement.com
More informationAppendix AQ-2. Mather South Community Master Plan Air Quality Master Plan
Appendix AQ-2 Mather South Community Master Plan Air Quality Master Plan 1. Introduction The Mather South Community Master Plan (MSCMP or project) is a proposed development area (referred to as project
More information47. RESPONSES TO COMMENTS FROM ALICIA HERNANDEZ, DATED MAY 9, 2011.
Waste Management Material Recovery Facility Transfer Station and Household Hazardous Waste Facility Environmental Impact Report 47. RESPONSES TO COMMENTS FROM ALICIA HERNANDEZ, DATED MAY 9, 2011. 47-1
More informationZAB Hearing May 14, 2015
ZAB Hearing May 14, 2015 Comments from April 23rd TOPICS Streamlined Environmental Review Protections for Berkeley High School Air Quality, Noise, and Traffic Project Alternatives Water Supply/Wastewater
More informationTo Peterson Z. Vollmann, Planner III Page 1
\ AECOM One Montgomery Street Suite 900 San Francisco, CA 94104 www.aecom.com Memorandum 415.896.5858 tel 415.882.9261 fax To Peterson Z. Vollmann, Planner III Page 1 Subject Greenhouse Gases and Climate
More information4 Project Alternatives
CHAPTER 4 PROJECT ALTERNATIVES 4.1 Introduction This section summarizes The Villages Escondido Country Club Project (Project) to allow for an evaluation of its comparative merit with a range of reasonable
More informationDirection regarding the definition of project alternatives is provided in the CEQA Guidelines as follows:
7.0 Alternatives 7.0 ALTERNATIVES Under CEQA, the identification and analysis of alternatives to a project is a fundamental part of the environmental review process. CEQA Public Resources Code Section
More informationROUTE 66 CORRIDOR SPECIFIC PLAN
Administrative Draft EIR Completed: August 11, 2003 Draft Check Copy EIR Completed: September 30, 2003 Public Review Draft EIR Completed: October 7, 2003 PUBLIC REVIEW DRAFT ROUTE 66 CORRIDOR SPECIFIC
More informationDavid Balducci, Align Real Estate Doug Flaming, Doug Flaming Construction Management, Inc. Shari Libicki, Sarah Manzano, Kevin Warner
MEMO Date: 1/13/17 To From CC David Balducci, Align Real Estate Doug Flaming, Doug Flaming Construction Management, Inc. Shari Libicki, Sarah Manzano, Kevin Warner Amara Morrison, Wendel Rosen Black &
More informationTherefore, each of the alternatives to the Specific Plan addressed in this EIR were selected based on the following factors:
CHAPTER 5 Alternatives 5.1 Criteria for Selecting Alternatives CEQA requires that the EIR compare the effects of a reasonable range of alternatives to the effects of the project. The alternatives selected
More information3.2 AIR QUALITY Introduction Environmental Setting
3.2 Air Quality 3.2 AIR QUALITY 3.2.1 Introduction Section 3.2 of the FEIR (Section 3.2-1 thru Section 3.2-5), incorporated by reference herein as though fully set forth, describes the existing air quality
More informationSMUD Franklin Electric Transmission Project. Initial Study and Mitigated Negative Declaration Addendum July 2017
SMUD Franklin Electric Transmission Project Initial Study and Mitigated Negative Declaration Addendum July 2017 Sacramento Municipal Utility District Franklin Electric Transmission Project Initial Study
More informationDraft Environmental Impact Report Serramonte Views Condominiums and Hotel Project
Draft Environmental Impact Report Serramonte Views Condominiums and Hotel Project File Nos. GPA-9-14-9640, PD-9-14-9637, SUB-9-14-9643, Design Review-9-14-9644, UPR-1-18-013248 SCH# 2016062063 Prepared
More informationII. Corrections and Additions
II. Corrections and Additions This section of the Final EIR provides changes to the Draft EIR that have been made to clarify, correct, or add to the environmental impact analysis for the Project (Project).
More informationprepared for: prepared by: THE PLATINUM TRIANGLE SUBSEQUENT ENVIRONMENTAL IMPACT REPORT SCH # VOLUME III RESPONSE TO COMMENTS
FINAL THE PLATINUM TRIANGLE SUBSEQUENT ENVIRONMENTAL IMPACT REPORT SCH # 2004121045 VOLUME III RESPONSE TO COMMENTS prepared for: CITY OF ANAHEIM Contact: Linda Johnson, Principal Planner prepared by:
More informationAppendix D1 Screening Analysis
Appendix D Screening Analysis of Additional Resource Areas for Consideration in the CS SEIR due to Assumed Incremental Increase in Terminal Throughput under the Revised Project Appendix D1 Screening Analysis
More informationAPPENDIX I RECORD OF NON APPLICABILITY
APPENDIX I RECORD OF NON APPLICABILITY RECORD OF NON-APPLICABILITY FOR CLEAN AIR ACT CONFORMITY (RONA) AND AIR QUALITY DATA SIO/UCSD MARFAC BERTHING WHARF AND PIER REPLACEMENT UCSD Project Number: 963990/4425
More informationNo change in the hours of operation is proposed. In accordance with the existing CUP, the facility will operate from 7 a.m. to 8 p.m. daily.
Executive Summary Overview The purpose of the Executive Summary and impact summary tables is to provide the reader with a brief overview of the proposed Athens Sun Valley Material Recovery Facility (Project),
More informationTable Ambient Criteria Air Pollutant Monitoring Data ( )
Section 5.4 Air Quality and Climate Change This section describes the potential air quality and climate change impacts associated with the proposed changes to the approved project. This section supplements
More informationRevisions to the Kern County Zoning Ordinance, 2015 C
Revisions to the Kern County Zoning Ordinance, 2015 C Oil and Gas Activities Joint Briefing Workshop Lorelei H. Oviatt, AICP Director Kern County Planning And Community Development Department July 27,2015
More informationCounty of El Dorado. El Dorado Hills Apartments Project Draft Environmental Impact Report. SCH No Prepared For: Prepared by:
County of El Dorado El Dorado Hills Apartments Project Draft Environmental Impact Report SCH No. 2017042017 Prepared by: 505 14th Street, Suite 1230 Oakland, California 94612 Prepared For: County of El
More information3.3 AIR QUALITY Existing Conditions
3.3 AIR QUALITY This section describes existing air quality conditions and relevant air quality regulations, assesses potential impacts of the proposed project on air quality, and recommends mitigation
More informationDECEMBER2014. CityofSantaAna. RBFConsulting PREPAREDFOR: PREPAREDBY:
DECEMBER2014 PREPAREDFOR: CityofSantaAna PREPAREDBY: RBFConsulting FINAL ENVIRONMENTAL IMPACT REPORT MATER DEI HIGH SCHOOL PARKING STRUCTURE AND SCHOOL EXPANSION PROJECT SCH NO. 2012111043 Lead Agency:
More informationAPPENDIX I GENERAL CONFORMITY ANALYSIS For WESTMINSTER, EAST GARDEN GROVE FLOOD RISK MANAGEMENT STUDY
APPENDIX I GENERAL CONFORMITY ANALYSIS For WESTMINSTER, EAST GARDEN GROVE FLOOD RISK MANAGEMENT STUDY October 2018 Page intentionally left blank Appendix I - General Conformity Analysis Contents 1.0 Introduction...
More informationCHAPTER 10.0 ALTERNATIVES TO THE PROPOSED PROJECT
HAPTER 10.0 ALTERNATIVES TO THE PROPOSED PROJET 10.1 Introduction 10.1.1 Purpose and Scope EQA requires that an EIR describe a reasonable range of alternatives to the project, or to the location of the
More information5.0 ALTERNATIVES 5.0 ALTERNATIVES
5.0 ALTERNATIVES The California Environmental Quality Act (CEQA), Section 15126.6, requires an Environmental Impact Report (EIR) to describe a reasonable range of alternatives to a project or to the location
More informationAppendix G Analysis of Project Impacts Compared to Existing Conditions
Appendix G Analysis of Project Impacts Compared to Existing Conditions This page intentionally left blank. Analysis of Project Impacts Compared to Existing Conditions Introduction The analysis scenarios
More informationChapter 4 ALTERNATIVES COMPARISON
Chapter 4 ALTERNATES COMPARSON 4.1 NTRODUCTON This chapter presents a comparison of the alternatives that were considered during preparation of this Draft ES/ER. Section 1.6 of this Draft ES/ER presents
More informationCEQA Addendum. The Caves at Soda Canyon P Planning Commission Hearing April 19, 2017
E CEQA Addendum The Caves at Soda Canyon P16-00106 Planning Commission Hearing April 19, 2017 Planning, Building & Environmental Services 1195 Third Street, Suite 210 Napa, CA 94559 www.countyofnapa.org
More informationEnvironmental Setting, Impacts, and Mitigation Measures
First page header CHAPTER 4 Environmental Setting, Impacts, and Mitigation Measures 4.0 INTRODUCTION TO THE ENVIRONMENTAL ANALYSIS Sections 4.1 through 4.13 of Chapter 4 of this EIR contain a discussion
More informationCity of Los Angeles 2010 Bicycle Plan First Year of the First Five-Year Implementation Strategy & Figueroa Streetscape Project Draft EIR
5.0 ALTERNATIVES California Environmental Quality Act (CEQA) requires that an EIR describe a range of reasonable alternatives to the project or to the location of the project that could feasibly avoid
More information3.1 Existing Setting Regulatory Framework Changes in Population, Employment, and Housing
EXECUTIVE SUMMARY ES.1 Purpose and Scope of the EIR... ES-1 ES.2 Project Characteristics... ES-1 ES.3 Project Alternatives Summary... ES-2 ES.4 Areas of Controversy... ES-2 ES.5 Summary of Environmental
More informationRINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Addendum to the Final Environmental Impact Report
RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Addendum to the Final Environmental Impact Report June 2016 State Clearinghouse Number 2014012012 Project Number 93294057 Prepared by: Michael
More information4.2 AIR QUALITY. This section analyzes the temporary and long-term impacts to local and regional air quality resulting from onsite development.
4.2 AIR QUALITY This section analyzes the temporary and long-term impacts to local and regional air quality resulting from onsite development. 4.2.1 Setting a. Climate and Meteorology. The is within the
More informationThis comparison is designed to satisfy the requirements of State CEQA Guidelines, Section (d), Evaluation of Alternatives, which state that:
6.0 Comparison of Proposed Project and Alternatives This chapter summarizes the environmental advantages and disadvantages associated with the Proposed Project and the alternatives. Based upon this discussion,
More informationINTRODUCTION AND EXECUTIVE SUMMARY
I INTRODUCTION AND EXECUTIVE SUMMARY A. INTRODUCTION This Draft EIR has been prepared in accordance with the California Environmental Quality Act (CEQA), the CEQA Guidelines, and the City of Los Angeles
More informationFIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015
FIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015 CITY OF SANTA MONICA PLANNING AND COMMUNITY DEVELOPMENT 1685 MAIN STREET SANTA MONICA, CA 90401 INTRODUCTION This document is the Fifth Addendum
More information4.4 AIR QUALITY INTRODUCTION ENVIRONMENTAL SETTING. Section 4.4 Air Quality
4.4 AIR QUALITY 4.4.1 INTRODUCTION This section provides an overview of the existing air quality conditions within the project area and surrounding region, regulatory framework, and environmental analysis
More informationAIR QUALITY IMPACT ANALYSIS HERITAGE SQUARE
AIR QUALITY IMPACT ANALYSIS HERITAGE SQUARE Prepared For: Heritage Square LLC 41391 Kalmia Street, Suite 200 Murrieta, CA 92562 February 5, 2007 TABLE OF CONTENTS SECTION 1 INTRODUCTION AND SUMMARY...
More informationRUNWAY 7L/25R RUNWAY SAFETY AREA (RSA) AND ASSOCIATED IMPROVEMENTS PROJECT MITIGATION MONITORING AND REPORTING PROGRAM 2017 PROGRESS REPORT
RUNWAY 7L/25R RUNWAY SAFETY AREA (RSA) AND ASSOCIATED IMPROVEMENTS PROJECT MITIGATION MONITORING AND REPORTING PROGRAM 2017 PROGRESS REPORT PUBLISHED JUNE 2018 TM Los Angeles World Airports LOS ANGELES
More informationAppendix G Air Quality Modeling Data Sheets
Appendices Appendix G Air Quality Modeling Data Sheets IBC Vision Plan and Mixed Use Overlay Zoning Code Recirculated DEIR City of Irvine Appendices This page intentionally left blank. The Planning Center
More information