1 3 Steps Approach : KHNP s Implementation of Post Fukushima Actions ST(Sung-Tae) Yang General Manager Corporate Safety Department KHNP
2 Status of Nuclear Power Plants (As of Jan 2016) In Operation Under Construction Planned Seoul 2
3
4 3 Steps Approach Post Fukushima Safety Review Stress Test New Accident Management Plan Prompt Remedy to SSC * Securing Coping Capability to Extreme External Hazards * Reviewer : Regulator-University- Institute Collaboration * 6 Area * Short Period Evaluation ( ~ 4.30) Applying International Standard Review Method * Introducing as one of presidential election pledge * Develop our own guideline by Regulator (WENRA reference) * Reviewer : Vendor (KEPCO E&C) * First Application : License Renewal Plant (Kori-1, Wolsong1), to be continued to all NPP Establishing Total Accident Response System * Systematic Approach for Effective Accident Management with MACST strategy (Similar to US FLEX) * 3 phases accident coping strategy Integration of MACST Facilities, Procedures and Emergency Plan * Mandatory Requirement
5
6 Safety Review ~ Composed of 73 external experts and regulatory body Inspectors for 21 nuclear units in operation Overall plant status Check ~ Composed of 44 internal & external experts Integrity of 4 critical areas of the plant Composed of 14 member countries and 20 regulatory experts Reviewed the Korean regulatory system (July 10-22, 2011) * IRRS : Integrated Regulatory Review Service
7 Action Items 11 Additional radiation protective equipment for the sake of residents Emergency Response 10 Passive hydrogen removal equipment or ventilation facilities in the CV Reinforcement of the SAMGs Severe Accidents 15 Mobile generator vehicles Injection loop for SFP emergency cooling water Electrical Power and Cooling Ability 20 ASTS height extension of NPP sea wall Earthquakes and Tsunamis * ASTS : Automatic Seismic Trip System, SAMG : Severe Accident Management Guideline, SFP : Spent Fuel Pond
8 Major Improvement CFVS PAR REACTOR Building reactor emergency cooling Sea Wall Water proof door EDG SFP Emergency cooling Mobile generator Steam Generator SEA Diesel driven pump REACTOR 1 Height extension of the seawall at NPP 2 Installation of waterproof doors 3 Installation of waterproof drain pumps (diesel-driven) 4 Securing mobile generator vehicles 5 Installation of external injection loop for emergency cooling water of reactor 6 Installation of injection loop for SFP 7 Installation of passive hydrogen removal equipment 8 Installation of vent or depressurizing facilities in the CV
9
10 Stress Tests Conducted in Korea Areas Guideline 1Earthquake 2Tsunami 3Loss of Safety Functions(SBO+LUHS) 4Severe accident Management 5Emergency response Stress Test Specifications of NSSC ( ) Step 1 Step 2 Step 3 Operator Self-Assessment 1 Adequacy Reviews (including plant walk-down) 2 Detailed Reviews (regulator + private experts) NSSC Reviews WOLSONG-1 KORI-1 Step 1 Step 2 Step In progress Step 1 Step 2 License Renewal 11
11 Assessment Area in Stress Test (Area 1) Safety of SSCs against Earthquakes(EU) (Area 2) Safety of SSCs against Tsunami, Storm surge and other natural disasters(eu) (Area 3) Plant Response to loss of electrical power and/or loss of the ultimate heat sink(eu) (Area 4) Severe accident management(eu) (Area 5) Emergency preparedness and response (Common) Assessment of operational aspects 12
12 Wolson #1 Action Items 6 -Installation of On-site Emergency Response Facility - Strengthen of Man-Power and Organization against Extreme Hazards Emergency Response Operational Performance Increasing SAMG Effectiveness from Steam Explosion, etc. -Feasibility Study for Dual Operation of PAR and Igniter Increasing Operability of CFVS, e.g Open Pressure Assessment Severe Accidents Managements Installation of 8-hour Seismic Battery(~ 2017) -Securing Essential Function from Multi-unit Accident Securing Long-term Cooling Capability(2016) Safety Function Failure 3 - Re-ensuring the Site Stability due to Seismic Event ( ~ 2019) - Increasing the Resistivity for Seismic Induced Fire (~ 2017) - Strengthen the Secondary Control Room( ~ 2015) Natural Hazards Fire
13 Kori #1 Action Items Kori #1 is planned to permanently defueling in 2017 for decommissioning 8 - EP enhancement for SFP Accident - Supplement the habitability of ERF Emergency Response Operational Performance 1 Field - Securing On-site Communication measures between MCR and Operators Severe Accidents Managements - Installation of 8-hour Seismic Battery 3 - Securing Essential Function from Multi-unit Accident mobile DG for single Rx, etc. - Maintenance of Mobile DG Safety Function Failure 2 - Re-review Seismic Performance of SFP Cooling Sys - Increasing the Resistivity for Seismic Induced Fire Natural Hazards Fire
14 Stress Test for All Operational Nuclear Power Plants in Korea 1 st Step : Select representative-type reactors, Sequential Evaluation Divided into 4 Reactor Type for a total of 24 nuclear plants under operation Westinghouse 2-loop, PHWR, Westinghouse 3-loop, Framatom, KSNP(Korean Standard Nuclear Power Plant) 2 nd Step : Applying the evaluation result Applying the evaluation result to the other nuclear power plants, taking into account the coverage Stress tests carried out once while operational period (for domestic operating power plants 24 unit)
15
16 Nuclear law revision (Jun 2016) all operating NPPs should submit accident management plans Target Plants All operating NPPs and under construction NPPs Schedule : Jan 2017 ~ Jun 2019 Contents of Accident Management Plan - AMP Strategies - Accident Management Implementation Structure - Accident Management Capability Evaluation - Emergency Operating Procedure Guideline - Extreme Disaster Mitigation Guideline - Severe Accident Mitigation Guideline - Accident Management Education and Training Plan
17
18 Phase Phase 1 (0 ~ 8hr) Phase 2 ( ~ 72hr) Phase 3 (72hr~ ) Responding Facility Electric Power Coolant Installed Facilities Battery CST Onsite Portable Facilities * SAFE-T Offsite supplemental Resource * SAFE-T + Outside support Portable DG DG + (EDG) 1 CST 2 DWST 3 RST 4 RWF 1 CST 2 DWST 3 RST 4 RWF 19
19 SAFE-T (30) Accident Strategy Support (16) WEC Type (4) OPR1000 (4) CANDU (4) APR1400 (2) Framatone (2) Facilities O&M Support (12) Mechanical (4) Electrical (4) I&C (4)
20
21
22
23
24 Thank You!
KHNP s strategies for Multi-unit Extreme Hazards Response
KHNP s strategies for Multi-unit Extreme Hazards Response Jang Hwan Na 2018. 5. 8 Safety Technology Center Central Research Institute, KHNP Contents 1 Post Fukushima Safety Measures 2 Stress Tests 3 Integrated
More informationWolsong-1 Stress Test
PHWR Safety 2014/CANSAS-2014 Wolsong-1 Stress Test June 23, 2014 Geun-Sun Auh Korea Institute of Nuclear Safety Table of Contents 1. Stress Test Definition 2. EU Stress Test 3. Stress Test of Korea 4.
More informationPost-Fukushima Actions in Korea
Post-Fukushima Actions in Korea IAEA TWG-LWR Vienna, June 18-20, 2013 Presented by Jong-Tae Seo 1. Impacts on National Energy Policy and NPP Plan 2. Actions Taken after Fukushima Accident 3. Findings and
More informationRegulatory Actions and Follow up Measures against Fukushima Accident in Korea
Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety
More informationPost-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford
Post-Fukushima Action Plan in Korea WNU-SI 2011, August 11 Christ Church, Oxford Contents Korean nuclear overview BK Kim Government action plan BS Jeong Post-Fukushima action plan MK Jo Nuclear Power Plants
More informationRecent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C
Int. Conf. on Topical Issues in Nuclear Installation Safety, Vienna Austria, 6~9 Jun. 2017 Recent Approaches related to Safety Enhancement of Operating NPPs in Korea Tae Eun JIN KEPCO E&C Contents 1. Introduction
More informationKorean Perspective on Nuclear Energy after Fukushima Accident
Korean Perspective on Nuclear Energy after Fukushima Accident Global 2011 Tsuruga Session December 16, 2011 Dohee Hahn Outline I II III IV Status of Nuclear Energy in Korea Impact of Fukushima Accident
More informationImplementation of Lessons Learned from Fukushima Accident in CANDU Technology
e-doc 4395709 Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Greg Rzentkowski Director General, Power Reactor Regulation Canadian Nuclear Safety Commission on behalf of CANDU
More informationPHWR Group of Countries Implementation of Lessons Learned from Fukushima Accident in CANDU Technology
Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Greg Rzentkowski Director General Directorate of Power Reactor Regulation Canadian Nuclear Safety Commission on behalf of CANDU
More informationMy name is Yong Soo Kim. I have responsibility for the development of Advanced Nuclear Power
[slide 1] Good afternoon, ladies and gentlemen. My name is Yong Soo Kim. I have responsibility for the development of Advanced Nuclear Power Rectors for Europe, particularly Czech Republic. I wish that
More informationAccident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited
Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited cmbhatia@npcil.co.in Presentation Contents Indian nuclear power
More informationCompilation of recommendations and suggestions
Post- Fukushima accident Compilation of recommendations and suggestions Peer review of stress tests performed on European nuclear power plants 26/07/2012 Compilation of Recommendations and Suggestions
More informationFormat and Content of the Safety Analysis Report for Nuclear Power Plants - Application Set -
Format and Content of the Safety Analysis Report for Nuclear Power Plants - Application Set - 2013 Contents 1. Overview 2. Chapters and Content of a SAR Chapter 1 General Information Chapter 2, 3, 4, Chapter
More informationSafety enhancement of NPPs in China after Fukushima Accident
Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015
More informationPost Fukushima actions in India. Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL
Post Fukushima actions in India Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL 14 th Meeting of IAEA-TWG on advance technologies, IAEA, Vienna, June 18-20, 2013 Presentation
More informationInsights from PSA for the operating Nuclear Power Plants in Korea
Insights from PSA for the operating Nuclear Power Plants in Korea Hojun Jeon 1, Seokwon Hwang 2, Janghwan Na 3 1 Central Research Institute of Korea Hydro & Nuclear Power Co.,Ltd., 70, 1312-gil, Yuseong-daero,
More informationSource Terms Issues and Implications on the Nuclear Reactor Safety
Source Terms Issues and Implications on the Nuclear Reactor Safety Jin Ho Song Korea Atomic Energy Research Institute t Technical Meeting on Source Term Evaluation for Severe Accidents, Vienna International
More informationIndia s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited
India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited 13 th Meeting of the Technical Working Group on Advanced Technologies for HWRs
More informationOverview of Fukushima accident. Nov. 9, 2011 Orland, Florida
Overview of Fukushima accident Nov. 9, 2011 Orland, Florida Nuclear Power Plants in Japan Japan Nuclear Japan Energy Nuclear Energy Safety Safety Organization Japan Atomic Industrial Forum, Inc. -Tohoku
More informationStress tests specifications Proposal by the WENRA Task Force 21 April 2011
Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared
More informationStatus of Decommissioning Preparation for Kori #1
Status of Decommissioning Preparation for Kori #1 http://www.khnp.co.kr December 6, 2017 KHNP Overview (1/2) AA (S&P), Aa2 (Moody s) KHNP Overview (2/2) Power Plants Operational status in Korea 24 22,529
More informationRegulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs
Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs RAHUL PORWAL Atomic Energy Regulatory Board Mumbai, INDIA Outline Introduction AERB Safety Review Methodology Safety Observations
More informationSMART Standard Design Approval inspection result July. 4 th
SMART Standard Design Approval inspection result 2012. July. 4 th Content Ⅰ. Inspection outline. 1 Ⅱ. Inspection proceedings 2 Ⅲ. SMART Standard Design features. 3 Ⅳ. Standard Design inspection result
More informationImprovements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima
Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University
More informationEletronuclear ( Brazil) Fukushima Response Plan
Eletronuclear ( Brazil) Fukushima Response Plan Edmundo Selvatici Site Manager Mario de Mello Ferreira Junior Manager, Materials Engineering Technical Meeting on Operational Experience with Implementation
More informationEnhancement of Nuclear Safety
Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2
More informationChina s HWR activities and technology development
13th Meeting of the Technical Working Group on Advanced Technologies for HWRs (TWG-HWR) China s HWR activities and technology development CNNC Nuclear Operation Management Co. Ltd. (CNNO) Chen Mingjun
More informationAPR1400 Safe, Reliable Technology
APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics
More informationCNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria
CNSC Fukushima Task Force E-doc 3743877 July 2011 Executive Summary In response to the March 11, 2011 accident at the Fukushima Daiichi Nuclear Power Plant (NPP), the CNSC convened a Task Force to evaluate
More informationDevelopment and use of SAMGs in the Krško NPP
REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12
More informationAn overview of what happened at Fukushima NPPs
An overview of what happened at Fukushima NPPs Per F. Peterson Professor and Chair Department of Nuclear Engineering University of California, Berkeley 2011 PEER Annual Meeting Hotel Shattuck Berkeley
More informationCNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements
CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements Sorin Holostencu IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in Nuclear Power Plants,
More informationSafety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency
Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA
More informationNuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level
Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant
More informationNuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level
Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant
More informationTERM TASK FORCE. Presented to: Waste Management Symposia By: Dr. Charles L. Miller. Phoenix, AZ. Fukushima Daiichi NRC Near Term Task Force 1
FUKUSHIMA DAIICHI NRC NEAR TERM TASK FORCE Presented to: Waste Management Symposia By: Dr. Charles L. Miller Phoenix, AZ 1 NRC RESPONSE Monitoring Mode Japan site team Information gathering Near Term Task
More informationPOST-FUKUSHIMA STRESS TESTS OF EUROPEAN NUCLEAR POWER PLANTS CONTENTS AND FORMAT OF NATIONAL REPORTS
HLG_p(2011-16)_85 POST-FUKUSHIMA STRESS TESTS OF EUROPEAN NUCLEAR POWER PLANTS CONTENTS AND FORMAT OF NATIONAL REPORTS This document is intended to provide guidance for the European Nuclear Regulators
More informationPost-Fukushima Assessment of the AP1000 Plant
ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,
More informationLessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)
PSAM12 2013 Tokyo Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization) April 15, 2013 Akio Komori (Takafumi Anegewa) Tokyo Electric Power Company All Rights Reserved 2013The
More informationNuclear Accident in Japan: NRC Early Protective Action Recommendations
Nuclear Accident in Japan: NRC Early Protective Action Recommendations National Radiological Emergency Preparedness Conference April 18, 2011 Patricia A. Milligan, CHP Senior Technical Advisor for Preparedness
More informationThe Risk of Nuclear Power
13 th International Conference on Probabilistic Safety Assessment and Management [PSAM13] The Risk of Nuclear Power Soon Heung Chang Handong Global University Oct 4, 2016 Contents 1 2 3 4 Introduction:
More informationINPRO Criterion Robustness of Design Position of the EPR TM reactor Part 3. Franck Lignini Reactor & Services / Safety & Licensing
INPRO Criterion 1.1.1 Robustness of Design Position of the EPR TM reactor Part 3 Franck Lignini Reactor & Services / Safety & Licensing 0 E.P?.?.?.? Robustness against External Hazards 1 External Hazards
More information6-9. June 2017, Paks Gábor Volent director of safety and security. Severe accident management at Paks NPP
6-9. June 2017, Paks Gábor Volent director of safety and security Severe accident management at Paks NPP The MVM Paks Nuclear Power Plant the only nuclear power plant in Hungary belongs to the MVM Hungarian
More informationTS1-5: Revision of NS-G-2.15 and Its Implementation for Verification and Validation of Severe Accident Management Guidelines
Technical Meeting on Verification and Validation of Severe Accident Management Guidelines for Nuclear Power Plants 12-14 December 2016, Vienna, Austria TS1-5: Revision of NS-G-2.15 and Its Implementation
More informationKAERI Presentation Title
International Experts Meeting on Assessment and Prognosis in Response to Nuclear or Radiological Emergency (IEM9) Post-accident Monitoring in Pressurized Heavy Water Reactor NPPs February 20-24, 2015 KAERI
More informationSubject: ONR Interim Report -Japanese Earthquake and Tsunami: Implications to the UK Nuclear Industry- 18 May 2011
Westinghouse Electric Company 42 Eaton Avenue Buckshaw Village Chorley, Lancashire PR7 7NA United Kingdom FAO Mike Weightman HM Chief Inspector of Nuclear Installations Redgrave Court Merton Road Bootle
More informationFukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO
Fukushima Daiichi Disaster Facts and lessons learned July 13 2011 Takashi Shoji Programme Director of WANO 7/12/2011 1 Earthquake occurrence and automatic shut-down of nuclear reactors The Tohoku Pacific
More informationThe Fukushima Daiichi Nuclear Power Station Accident
The Fukushima Daiichi Nuclear Power Station Accident Tomomi Matsunaga Kansai Electric Power Company Cooperation with JEPIC (Japan an Electric Power Information Center) Nuclear Power Plants in Japan 2 1
More informationRomanian National Action Plan post - Fukushima
ROMANIA National Commission for Nuclear Activities Control Romanian National Action Plan post - Fukushima Table Of Contents Introduction..........................................................................
More informationIAEA-J4-TM TM for Evaluation of Design Safety
Canadian Nuclear Utility Principles for Beyond Design Basis Accidents IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects Ontario Power Generation Overview
More informationRecent Developments in Risk Assessment: Future Perspectives
Recent Developments in Risk Assessment: Future Perspectives Mohammad Modarres Minta Martin Professor of Engineering Director, Reliability Engineering Program Department of Mechanical Engineering University
More informationSTRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION
STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA MARCH 27-29, 2017 1 ANPP * The ANPP is located in the western part of Ararat valley, 30 km west of Yerevan, close
More informationEuropean level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.
Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that
More informationDevelopment of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station
Development of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station December 12-14, 2016 Toshinobu KITA TEPCO Holdings, Inc. Japan BWRs SAMG Development History 1 Original
More informationSTRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT
STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT Frank Nuzzo IAEA Nuclear Power Engineering f.nuzzo@iaea.org ENSREG High Level Requirements Following the extreme events
More informationDOCUMENTATION FOR REVIEW AND ASSESSMENT - Application Set -
DOCUMENTATION FOR REVIEW AND ASSESSMENT - Application Set - Contents 1. Overview 2. Licensing Practice in Korea 3. Safety Reviews for License or Approval 4. Licensing Review Documents 5. Safety Approval
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised 1pm of March 31 Yoshiaki Oka Waseda university Recovery action is in progress.
More informationImprovements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents
Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents Jean BARBAUD IAEA, August 2013 1 1 Context - Timeline 6 fields assessed : Earthquake Flooding Loss of heat sink LHS
More informationImplementation of the EU stress test in European nuclear power plants
Implementation of the EU stress test in European nuclear power plants Dr. Cord-Henrich Lefhalm Nuclear Regulation and Licensing RWE Power AG Essen, Germany RWE Power 15.10.2012 PAGE 1 The Fukushima nuclear
More informationNational Nuclear Safety Administration, P. R. China
Current NPPs in China In commercial operation: 32 Under construction: 24 (31 March 2016) 黑龙江 吉林 Hongyanhe Haiyang Shidaowan 新疆 辽宁 Tianwan 青海 甘肃 内蒙古宁夏 山西 北京天津河北山东 Qinshan&Fangjiasha n Qinshan 2 Qinshan
More informationImprovements in defense in depth on French NPPs following Fukushima Accidents
Improvements in defense in depth on French NPPs following Fukushima Accidents Xavier Pouget-Abadie Jean BARBAUD IAEA, October 2013 1 Copyright EDF 2013 1 Context -Timeline 6 fields assessed : Earthquake
More informationEuropean Nuclear Stress Test
European Nuclear Stress Test - Peer Review Process and Results - 9. St. Galler Energietagung Oskar Grözinger Symposium : The Fukushima accident and the future of nuclear energy in Europe Den Haag, 23.11.2012
More informationCNSC Staff Briefing CMD 11-M15 March 30, 2011
CNSC Staff Briefing CMD 11-M15 March 30, 2011 CNSC Response CNSC took action immediately to: Activate Emergency Operations Centre on 3 rd floor Slater (11-March) Staff Nuclear Emergency Organization in
More informationFukushima Daiichi NPP Accident
Fukushima Daiichi NPP Accident Plant Design and Preliminary Observations K. Moriya and K. Sato Hitachi GE Nuclear Energy, Ltd. May 3, 2011 [Note] 1. The view expressed herein are not the official view
More informationNPP Safety in the aftermath of the Fukushima Accident. UK Response August 2013
Health and Safety Executive NPP Safety in the aftermath of the Fukushima Accident Dr. Gary Cook UK Response 26-29 August 2013 Overview ONR response to Fukushima ENSREG stress tests Specification and process
More informationPakistan s HWR Activities
14 th Meeting of the Technical Working Group on Advanced Technologies of Heavy Water Reactors (TWG-HWR) Vienna, Austria 18-20 June 2013 Pakistan s HWR Activities by Shahid Saghir, Senior Manager (Technical)
More informationM ertinssafety. The new German Safety Criteria for Nuclear Power Plants in the view of international standards. Prof. Dr. M.
The new German Safety Criteria for Nuclear Power Plants in the view of international standards Prof. Dr. M. Mertins 1 Content Introductory remarks Major Information Sources for elaboration of the new Safety
More informationWestinghouse AP1000 Nuclear Power Plant
Westinghouse Non-Proprietary Class 3 April 2011 Westinghouse AP1000 Nuclear Power Plant Coping with Station Blackout Westinghouse Non-Proprietary Class 3 April 2011 Westinghouse AP1000 Nuclear Power Plant
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23 in Japan Yoshiaki Oka Waseda university Recovery action is in progress. The presentation
More informationDevelopment of SAMG and its implementation in China
Development of SAMG and its implementation in China Yang Zhiyi 1, Zhang Lin 2, etc. 1. Nuclear and Radiation Safety Center, China 2. National Nuclear Safety Administration, China Vienna Austria, 2014/3/20
More informationOPG s Response to Fukushima Event- Update
OPG s Response to Fukushima Event- Update Darlington and Pickering Joint Community Advisory Committee Meeting- January 21, 2014 Mark Knutson- Director- Fukushima Support Tho-Dien Le- Projects Design Manager-
More informationWorld Efforts after Fukushima and Lessons Learned from the Accident
Fukushima 1 World Efforts after Fukushima and Lessons Learned from the Accident Takehiko Saito Federal Authority for Nuclear Regulation, UAE ex- IAEA, ex-nuclear Safety Commission of Japan, and ex-toshiba
More informationDEVELOPMENT OF LOW POWER SHUTDOWN LEVEL 1 PSA MODEL FOR WESTINGHOUSE TYPE REACTORS IN KOREA : OVERVIEW, RESULTS AND INSIGHTS
DEVELOPMENT OF LOW POWER SHUTDOWN LEVEL 1 PSA MODEL FOR WESTINGHOUSE TYPE REACTORS IN KOREA : OVERVIEW, RESULTS AND INSIGHTS Yong Suk LEE 1, Eden KIM 1,Gunhyo JUNG 1, Seok-won HWANG 2, Ho-jun JEON 2 1
More informationIAEA International Conference on Topical Issues in Nuclear Installation Safety
IAEA International Conference on Topical Issues in Nuclear Installation Safety Guidance on the Implementation of Modifications to Mitigate Beyond Design Basis Accidents Fred Dermarkar Vice President Engineering
More informationSAFETY IMPROVMENTS AT KANUPP. Ahsan Ullah Khan Principal Engineer Karachi Nuclear Power Plant
SAFETY IMPROVMENTS AT KANUPP Ahsan Ullah Khan Principal Engineer Karachi Nuclear Power Plant General 137 Mwe CANDU Plant Started commercial operation in 1972 Design life of 30 years completed in 2002 An
More informationManaging the supply chain: Challenges and Overcoming in Korean nuclear industry
Managing the supply chain: Challenges and Overcoming in Korean nuclear industry TM on Topical Issues in the Development of Nuclear Power Infrastructure 4-7 February 2014, Vienna, Austria International
More informationEnhancements to Emergency Preparedness and Response in Spain
ISSN 2285 8717 ISSN L 2248 8717 http://www.insj.info vol. 5 issue 1, 2016, pages 88-99 Enhancements to Emergency Preparedness and Response in Spain Rafael J. Caro TECNATOM, Spain rcaro@tecnatom.es ================================================================================
More informationDelaware IEEE Briefing. July 30, 2012 Jamie Mallon, Nuclear Development Manager
Delaware IEEE Briefing July 30, 2012 Jamie Mallon, Nuclear Development Manager Agenda Introductions National / Regional Energy Overview PSEG Power / PSEG Nuclear Overview Fukushima Update New Nuclear Development
More informationFukushima-Daiichi, Hurricane Sandy: NRC Standards vs. NFIP Regulations June 9-14, 2013
Fukushima-Daiichi, Hurricane Sandy: NRC Standards vs. NFIP Regulations June 9-14, 2013 TOPICS A brief comparison of Fukushima-Daiichi and Sandy Flooding Events at other Nuclear Power Plants NRC Actions
More informationPreliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development
Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of
More informationFrom the Accident at the Fukushima Daiichi NPS: Efforts to Improve Safety
From the Accident at the Fukushima Daiichi NPS: Efforts to Improve Safety Luc OURSEL President and CEO, AREVA Tokyo, April 19, 2012 Agenda Safety assessments in the EU and in France AREVA Safety of our
More informationMeetings for Sharing International Knowledge and Experience on Stress Tests
Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation
More informationIntroduction of Nation-wide Inspection and Reassessment to Chinese Research Reactors after Fukushima Accident
Introduction of Nation-wide Inspection and Reassessment to Chinese Research Reactors after Fukushima Accident XIAO Zhi 1, FU Jie 1, ZHANG Ou 1, SONG Chenxiu 2 1) I Nuclear and Radiation Safety Center,
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised April 13 Yoshiaki Oka Waseda university Recovery action is in progress. The presentation
More informationEuropean stress tests
European stress tests for nuclear power plants National progress report Sweden September 15, 2011 Abstract In the light of the Fukushima accident in Japan, the European Council of March 24 th and 25 th
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationAP1000 European 16. Technical Specifications Design Control Document
16.3 Investment Protection 16.3.1 Investment Protection Short-term Availability Controls The importance of nonsafety-related systems, structures and components in the AP1000 has been evaluated. The evaluation
More informationin China Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August , Vienna
Post-Fukushima Safety Improvement Measures for NPPs in China ZHENG Lixin Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August 26-2929 2013, Vienna 1 Background
More informationSAFARI-1 Safety Reassessment and Modifications in light of Fukushima Daiichi Accident
SAFARI-1 Safety Reassessment and Modifications in light of Fukushima Daiichi Accident Sammy Malaka NESCA, SAFARI-1 Research Reactor SOUTH AFRICA 18 th IGORR Conference and IAEA Workshop on Safety Reassessment
More informationASSESSMENTS OF SWEDISH NUCLEAR POWER PLANT IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT
ASSESSMENTS OF SWEDISH NUCLEAR POWER PLANT IN THE AFTERMATH OF THE FUKUSHIMA DAIICHI ACCIDENT Lovisa Wallin-Caldwell Outline Introduction Swedish nuclear power plants Swedish nuclear power regulation Back-fitting
More informationUnderstanding Energy: Emergency Preparedness for Nuclear in the US
Understanding Energy: Emergency Preparedness for Nuclear in the US Kimberly Cook, General Manager, Plant Operations Waterford 3 Nuclear Facility Novenber 16, 2011 Tsunami Initiates Nuclear On March 11
More informationActivities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues
Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Jiří Duspiva ÚJV Řež, a. s. Division of Nuclear Safety and Reliability Dept. of Severe Accidents and Thermomechanics
More informationFukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011
Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po 1. Description of Event March 25, 2011 The earthquake caused instant loss of offsite power. The scale-9
More informationELETRONUCLEAR s Response to the Fukushima Dai-ichi Nuclear Accident
s Response to the Fukushima Dai-ichi Nuclear Accident Rio de Janeiro, July 3 rd, 2012 Paulo Vieira First Actions Taken by Eletronuclear Establishment of a Corporate Working group Follow up of the event,
More informationModernisation of existing NPPs in Switzerland
Modernisation of existing NPPs in Switzerland Wolfgang Denk, Alpiq Suisse SA OECD/NEA Workshop in Innovations in Water-cooled Reactor Technologies Paris, 11 February 2015 Daily generation profiles 2013
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationAttachment XI-1. I. Emergency Safety Measures, etc.
Specific Countermeasures in Japan Based on the Lessons Learnt from the Accident at Fukushima Dai-ichi Nuclear Power Station of Tokyo Electric Power Co. Inc. I. Emergency Safety Measures, etc. 1. Emergency
More informationFUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES
FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES JOON-EON YANG Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Daedeok-daero 989-111,
More informationEPR Safety in the post-fukushima context
EPR Safety in the post-fukushima context October 19 th 2011 Jürgen Wirkner, Peter Volkholz EPR safety approach An accident is a complex series of events: NEED THE MEANS TO REMAIN IN CONTROL OF THE SITUATION,