Appendix B.2. Addendum to Visibility Analysis Technical Report

Size: px
Start display at page:

Download "Appendix B.2. Addendum to Visibility Analysis Technical Report"

Transcription

1 Appendix B.2 Addendum to Visibility Analysis Technical Report

2 PACIFIC WIND ENERGY PROJECT ADDENDUM TO THE VISIBILITY ANALYSIS TECHNICAL REPORT Prepared for: enxco Development Corporation 4000 Executive Parkway, Suite 100 San Ramon, California Prepared by: 430 North Halstead St. Pasadena, California 91107

3 INTRODUCTION This addresses the May 6, 2010, refined conceptual site plan developed by the enxco Development Corporation (enxco) to minimize potential impacts, maximize wind generation capacity, and optimize use of available property. On May 6, 2010, the refined conceptual site plan for the proposed project was modified to include the relocation of 120 wind turbine generators (WTG), relocation of three substations, realignment of two transmission corridors, and the additional option to connect to the Tehachapi Renewable Transmission Project (TRTP) transmission corridor. The new layout includes 69 REpower MM megawatt (MW) WTGs and 66 GE 1.5xle 1.5-MW WTGs, for a total of 135 WTGs (Figure R1.3-1, Conceptual Location of and 1.5-MW WTGs). In addition to switching the generator type, the total number of turbines was increased to 135 WTGs. The project applicant is seeking approval for the May 6, 2010, refined conceptual site plan; however, two other conceptual site plans were evaluated in the March 8, 2010, Visibility Analysis Technical Report 1 to understand the comparative level of impact resulting from using different wind turbine generators and the associated changes in density and distribution: (1) 120 Vestas V MW WTGs or (2) 125 REpower MM MW WTGs. Consequently, this Addendum revises the March 8, 2010, Visibility Analysis Technical Report with new analysis based on the May 6, 2010, refined conceptual site plan. This was prepared to analyze the refined location of each turbine, create a photomontage of the new turbine locations, and update a Key Observation Point (KOP) that characterized the changes to the viewshed in a previously undeveloped area of the southwestern portion of the project area, resulting from the May 6, 2010, refined conceptual site plan. Since KOP-7 was analyzed as part of the March 8, 2010, Visibility Analysis Technical Report, the visual simulation for KOP-7 was rerun with the specifications for the May 6, 2010, refined conceptual site plan to account for the refined location, number, type of turbines. REVISIONS TO THE VISIBILITY ANALYSIS TECHNICAL REPORT 1.3 Project Description The May 6, 2010, refined conceptual site plan proposed project facilities would include WTGs, service roads, a power collection system, communication cables, overhead and underground transmission lines, electrical switchyards, up to three project substations, up to seven meteorological towers, and one Operations and Maintenance (O&M) facility. The refined project s temporary facilities would include construction access roads, laydown areas, and concrete batch plants. Refined project elements are shown on Figure R1.3-1 and include: Up to a maximum of MW WTGs not to exceed 500 feet in height with associated generators, towers, foundations, and pad-mounted transformers (each WTG could range from 1 MW to 3 MW), for a total generation capacity not to exceed 250 MW of electricity; Up to 7 meteorological towers; 1 8 March Visibility Analysis Technical Report. Prepared for: enxco Development Corporation. Pasadena, CA. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 2

4 LEGEND Residences o KWF\Q:\1378\ \ArcProjects\WindPRO\AEIR\CncptSitePlan.mxd GE 1.5-MW REpower 2.05-MW Pacific Crest Trail Existing SCE Transmission Lines and TRTP Approved Route Franchise Route Overhead KV Route 1 1:72,000 Miles Overhead KV Route 2 Overhead KV Route 3 PdV and Pacific Wind Secondary Route - Route 4 Substations Project Boundary SOURCE: SEI, enxco FIGURE R Conceptual Location of and 1.5-MW WTGs

5 On-site and off-site project access roads, control cables, power collection cables, and transmission lines necessary to serve the proposed project and connect to the California Independent System Operator (CAISO) grid; Up to three project substations to step up the voltage generated by the WTGs to meet the electrical transmission system s 230-kilovolt (kv) voltage; One O&M buildings of approximately 4,800 square feet; Up to 10 yards as temporary laydown construction yards that include up to six temporary portable batch plant alternative locations for the construction phase of the proposed project (the number of actual batch plants is schedule-dependent, and no batch plants will remain after the completion of construction); and One yard would remain as the O&M facility, and up to three yards would remain for the project substation for ongoing use during the life of the proposed project. The refined project site plan (Figure R1.3-1) is not intended to reflect the precise location of proposed WTGs and structures. Overhead Transmission Lines Transmission Lines to Serve the Proposed Project The project proponent is continuing to evaluate the final alignment of the transmission line and substation locations for the proposed project based on land acquisition and the availability of Los Angeles Department of Water and Power (LADWP) easement crossing rights. The project proponent is therefore proposing four different 230-kV double-circuited overhead transmission line options for interconnection into the proposed Southern California Edison (SCE) Whirlwind Substation location (Figure R1.3-2, Pacific Wind Transmission Alternatives). Transmission line routes, referred to as Route 1, Route 2, Route 3, and Route 4, are depicted on Figure R These transmission lines would consist of a three-phase electrical line design and would be carried on electric poles ranging from 28 feet (for lower voltage and communication lines) up to 150 feet in height. The electrical power poles support three insulators, cross arms, and conductors (wires) per circuit and may support two circuits. Transmission along at least one of these lines will run through the proposed project site to the Whirlwind Substation to serve the proposed project. In the event that construction of the proposed project is phased for purposes of sale or financing, it is possible, although unlikely, that some portions of up to three of these transmission lines would need to be constructed. The more likely scenario is that one or two, but not all three, of the potential transmission lines would be constructed to serve the project. Route 1 and Route 2 Routes 1 and 2 begin at a northerly boundary of the proposed project site and/or a proposed project substation location and then continue in a southerly direction on private easements to the SCE interconnection point. Route 2 would generally be located to the east of Route 1 until it would connect with the SCE interconnection. Route 1, Route 2, or both Routes 1 and 2 would potentially be built regardless of whether construction of the project is phased for purposes of sale or financing. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 3

6 LEGEND 230 KV Transmission Alternatives Overhead KV Route 1 Overhead KV Route 2 Overhead KV Route 3 Existing SCE Transmission Lines and TRTP Approved Route Franchise Route Manzana (formerly PdV) and Pacific Wind Secondary Route - Route 4 Substations Project Boundary o0 1 2 Miles KWF\Q:\1378\ \ArcProjects\WindPRO\AEIR\RevisedELEC.mxd FIGURE R Pacific Wind Transmission Alternatives

7 Route 3 A third potential transmission alignment, Route 3, could be constructed in the event that project construction is phased due to sale or financing. Route 3 would initiate at a proposed project substation location in the central portion of the proposed project site and travel in a southwest direction parallel but outside of the southern margin of the LADWP aqueduct right-of-way (ROW) where it would turn southeast along the existing SCE 500-kV lines and then to the SCE interconnection point at Whirlwind. The solid line of this alignment was approved by the California Public Utilities Commission (CPUC) and subjected to the California Environmental Quality Act (CEQA) review process as part of the CPUC s approval of the TRTP. The dashed portion of the line corresponding to Route 3 is the portion of the line analyzed for the Pacific Wind Energy Project. One or both of the dashed portions of the line could be built to support the interconnection of the project. Each of these potential overhead transmission alignments is anticipated to cross LADWP aqueducts No. 1 and/or No. 2, either at the approved crossing defined in the Manzana (formerly PdV) Wind Energy Project Environmental Impact Report (EIR) or the pending approval of preliminary design and authorization from LADWP. LADWP Aqueduct No. 1 is considered to be eligible for inclusion in the National Register of Historic Places (NRHP) as a contributing element to the proposed First Los Angeles Aqueduct Historical Archaeological District. These electrical crossings would span the entire LADWP easement, meeting the required electrical design criteria for spans and line sag and the lines would not touch the surface of the site at any time, and heavy equipment would not cross the aqueducts during construction except at the LADWP-approved crossing locations as defined in the approved Manzana Wind Energy Project. The proposed project would in addition require SCE 12-kV lines and communication lines for the project substations and O&M facility. These lines would be along 170th Street West, as approved for the Manzana Wind Energy Project and tiered off for the proposed project to the required locations as defined by SCE. The proposed project would also have some lines as required at the power collection system voltage of 34.5 kv, and up to three proposed project substation collection areas. Other Transmission Lines Crossing the Proposed Project Site In addition to the transmission line or lines that would serve the proposed project, one or more additional lines serving the already approved adjacent Manzana Wind Energy Project will run through the proposed project site to the Whirlwind Substation. One alignment route for the Manzana Wind Energy Project, referred to as the Eastern Alignment, begins at the collector substation on the Manzana Wind Energy Project site (not shown on Figure R1.3-2) and trends to the southeast across properties under the control of the project developer and is shown as the Manzana Pacific Wind Secondary Route (Route 4) on Figure R The Eastern Alignment follows a route previously analyzed in the PdV Infill Wind Energy Project Addendum to the EIR for both an electric distribution line and fiber optic line to a point on the southeastern boundary of the Manzana Wind Energy Project site where the alignment joins 170th Street. Near the point where the Eastern Alignment would intersect 170th Street, the transmission line would trend north-south and cross the California Aqueduct. The Eastern Alignment remains on the west side of 170th Street and continues south for 3.25 miles, directly to the Whirlwind Substation. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 4

8 Alternatively, the Manzana Wind Energy Project could be served by a transmission line proposed to be located in or next to the Kern County ROW, referred to as the Franchise Route. The Franchise Route would begin from a proposed project substation and travel east to the north side of Los Angeles Department of LADWP Aqueduct No. 1 (Figure R1.3-2). The line would then turn south following the access route approved for the Manzana Wind Energy Project by Kern County in July 2008 and then along 170th Street West to the SCE Whirlwind Substation interconnection point. The portion of the line extending from the LADWP Aqueduct No. 1 to Rosamond Boulevard would be within or next to the alignment of an access road ROW that has been dedicated to the Manzana Wind Energy Project, but not yet accepted by Kern County. South of Rosamond Boulevard, the line would follow 170th Street West, an existing public road, to the SCE Whirlwind Substation. A final alternative transmission route being considered for the Manzana Wind Energy Project, referred to as the Western Alternative, could potentially pass through the proposed project site from the northwest to the southeast (Figure R1.3-2). The Western Alternative would originate near the center of the Manzana Wind Energy Project site and travel to the southwest for approximately two miles where it intersects the existing SCE transmission line corridor located on the western boundary of the proposed project site. The Western Alternative would then proceed in parallel on the east side of the SCE transmission corridor southeasterly to its intersection with the proposed SCE Whirlwind Substation. This alternative has been subject to environmental review by the CPUC under the TRTP. The use of overhead electrical lines in the proposed project site is limited to the interconnection from up to three substations and switchyard to the interconnection point of the utility. The 34.5-kV electrical collection systems would be double-circuited transmission structures. The structure type and design is not specified for the 230-kV overhead transmission lines; therefore, they could be wooden monopoles, wooden H-frames, or tubular steel poles (TSPs). TSPs would be visually compatible with the WTG monopoles of the proposed project. 3.2 Assessment Methods and Models At the request of Kern County, each KOP was described according to the four California Public Utilities Commission visual condition factors: visual quality, viewer types and volumes, viewer exposure, and visual sensitivity. KOP-7 was updated to characterize new project areas developed as a result of the May 6, 2010, refined conceptual site plan. KOP-7 is located southwest of the proposed project property at the intersection of 220th Street West and Avenue A (Figure R , Visibility Analysis Observation Point Index for and 1.5-MW WTGs). These two roads have a low traffic volume. This observation point was chosen to give a representative view of the proposed project property from the southwest at a distance where the proposed project is in the background. Figure R , Key Observation Point 7 with 2.05-MW Turbines, is a photomontage that includes a photograph showing the existing conditions from KOP-7 and a visual simulation representing how the proposed project would appear after construction. The WTGs are minimally visible from this distance and appear to be two-inch vertical structures on the foothills of the Tehachapi Mountains. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 5

9 AA AA KWF\Q:\1378\ \ArcProjects\WindPRO\AEIR\Viz_Index.mxd o Miles 1:84,000 Observation Point 4 A A A Observation Point 5 Observation Point 3 A A Observation Point 1 Observation Point 6 Rosamond 110th LEGEND Residences GE (1.5-MW) REpower (2.05-MW) Observation Points Roads Pacific Crest Trail Los Angeles Aqueduct Proposed Project Property Observation Point 2 Observation Point 7 A Avenue A 170th 220th A Avenue C FIGURE R Visibility Analysis Observation Point Index for and 1.5-MW WTGs

10 KWF\Q:\1378\ \ArcProjects\WindPRO\AEIR\Vis_Obs7_ mxd Existing Condition Visual Simulation FIGURE R Key Observation Point 7 with 2.05-MW Turbines

11 3.4 Results Although the refined location, number, and type of WTGs affect the locations from where these WTGs would be visible within the proposed project area, the analysis of the refined site plan indicates that the results remain the same as the original March 8, 2010, Visibility Analysis Technical Report. Due to the construction of the proposed project, impacts would be significant and unavoidable. Seven (7) KOPs were selected for detailed analysis in the Draft EIR, based on their ability to exemplify visual resource impacts at particular locations. KOPs that were analyzed are representative of project-induced visual resource impacts to this particular landscape. Visual Impacts at Specific KOPs There are two primary and paved public use roads from which the public could view the proposed project: Rosamond Boulevard and 170th Street West. In addition, there are some one-lane dirt roads inside and/or near the proposed project site from which the public could view the proposed project. The PCT runs through the middle of the proposed project site in a south-north direction and provides pedestrian and equestrian viewers with a close-up view of the project. The project would result in changes to the visual environment that may result in potentially adverse effects on visual quality throughout the project area. KOP-1 Northbound 170th Street West KOP-1 is located on 170 th Street West, just south of Rosamond Boulevard, heading northbound. KOP-1 provides expansive views north toward the proposed project site. The visual simulation photomontage indicates that 2.05-MW WTGs would be visible in the foreground, middleground, and background to viewers from this observation point. In addition, the proposed project would partially obstruct and degrade the view of the mountains in the more distant background from this vantage point. Viewers who would be affected by the aesthetic impacts at or nearby this observation point include drivers on 170 th Street West and West Rosamond Boulevard, and residents of nearby homes along 170th Street to the south of this KOP. Overall Visual Change Construction of the proposed project would result in approximately 20 to 30 WTGs being visible in the foreground, middleground, and background range of views from KOP-1. However, the WTGs are set back from 170 th Street and Rosamond Boulevard, and therefore would not be expected to impact the immediate foreground view. The WTGs closest to the mountains would be farthest from the viewer, or would be in the background range and therefore only slightly obstruct the view. Visual Sensitivity/Visual Change With the exception of a few residents located along 170 th Street and Rosamond Boulevard, the majority of viewers would be traveling past this KOP only expecting to see low vegetation such as creosote bush scrub and native grassland. The addition of WTGs expanding beyond this intersection into the vegetation would be obvious, causing a change to the existing visual characteristics of the location. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 6

12 Due to the number of WTGs visible from this KOP and considering viewers would be in motion, the overall visual sensitivity would be considered low to moderate while the overall visual change would be moderate, adverse but not significant. KOP-2 Northbound PCT KOP-2 is located on northbound PCT, the usual direction that through-hikers would take on this stretch of the PCT. At this point, hikers and equestrians have been walking or riding through the flat desert landscape of the northern Antelope Valley for approximately 20 miles. This observation point is located on a dirt road south of the proposed project site, looking northeast along the PCT. KOP-2 provides expansive views north and east toward the proposed project site from the PCT. The visual simulation photomontage indicates that the 2.05-MW WTGs would be visible in the middleground and background to viewers from this vantage point. Viewers who would be affected by the aesthetic impacts at this observation point include hikers and equestrians along the PCT. Overall Visual Change From KOP-2, only a few WTGs would be visible in the middleground after construction of the proposed project. In the background range, approximately 10 to 15 WTGs would be visible. However, these WTGs would appear to be very small. As a result, there would be very little visual change for the viewer from this KOP. Visual Sensitivity/Visual Change If a viewer were standing at the location of KOP-2, they would see vegetation on both sides. Off in the distance, the viewer would see small rolling hills covered predominantly with creosote bush. The majority of viewers traveling on the PCT include hikers and equestrians. These users are considered to be very sensitive to aesthetic changes to their environment. Construction of WTGs along-side the PCT would be of moderate-to-high concern to these visitors. However, given the low number of WTGs in the middleground and the distance from the WTGs in the background, the overall visual sensitivity would be considered moderate while the overall visual change would be low-to-moderate. KOP-3 Northbound PCT KOP-3 is located on northbound PCT, the usual direction that through-hikers would take on this stretch of the PCT. At this point, hikers and equestrians are located near the middle of the proposed project site on a dirt road. KOP-3 provides expansive views from within the proposed project site along the PCT in the four cardinal directions. An approximately 5-mile portion of the PCT bisects the proposed project site from north to south. Users of the PCT are recreational hikers that would be expected to be highly sensitive to changes in visual quality. The visual simulation photomontage indicates that 2.05-MW WTGs would be visible in the foreground, middleground, and background to viewers from this observation point. In addition, the proposed project would partially obstruct and degrade the view of the mountains in the more distant background from this vantage point. Viewers who would be affected by the aesthetic impacts at this observation point and along the PCT as it crosses the proposed project site include hikers and equestrians. In addition, the WTG layout include WTGs that would be within 300 feet of the PCT and thus, within the immediate foreground distance zone for trail users; at this proximity, the aesthetic impacts of the proposed project would be more severe. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 7

13 Overall Visual Change Several WTGs visible from KOP-3 are located within the foreground range and a few WTGs fall into the background range, partially blocking the mountains. The overall number of WTGs visible from KOP-3 would be less than five, but the impact of adding WTGs in this remote section of the PCT would be potentially significant to the visiting recreational users. Visual Sensitivity/Visual Change The majority of viewers utilizing the PCT include hikers and equestrians who are considered to be highly sensitive to changes to their aesthetic environment. At this section of the PCT, viewers are generally surrounded by small rolling hills and native vegetation. The Tehachapi Mountains are visible to the north. Due to the KOP being centralized in the project and surrounded on all four cardinal sides by the natural beauty of the terrain, the overall visual sensitivity would be considered moderate-to-high while the overall visual change would be moderate, adverse and potentially significant. KOP-4 PCT Looking South KOP-4 is located on the PCT at the northern extent of the proposed project site. At this location, the PCT is a single-track hiking and equestrian trail, rather than a dirt road, as was the case for KOP-2 and KOP-3. KOP-4 provides expansive views south toward the proposed project site from the PCT. The visual simulation photomontage indicates that the 2.05-MW WTGs would be visible in the foreground, middleground, and background to viewers from this vantage point. Viewers who would be affected by the aesthetic impacts at this observation point include hikers and equestrians along the PCT. Overall Visual Change From KOP-4, only a few WTGs would be visible in the middleground, as well as the background range, after construction of the proposed project. In the background range, those three to four WTGs visible would appear to be very small as a result of the distance. Although the WTGs would not be in the immediate foreground or foreground, the viewer would be on the PCT at the northern most section of the project, which borders the approved Manzana Wind Energy Project. Visual Sensitivity/Visual Change The PCT is popular with viewers such as hikers and equestrians, who are considered to be sensitive to changes to their aesthetic environment and who would most likely be adversely affected by the addition of WTGs within the middleground range. With low vegetation and no landforms or structures obstructing the view of the WTGs from the PCT, viewers attention would be drawn to the 500-foot-tall structures. As a result of the KOP being south of the approved Manzana Wind Energy Project, the visual change resulting from the would not be substantial. The overall visual sensitivity and overall visual change from this KOP would be considered moderate-to-high. resulting in an adverse and potentially significant impact for visitors. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 8

14 KOP-5 Northwest Corner of Project KOP-5 is located in the northwest corner of the proposed project site. This observation point was chosen to give a representative view of the proposed project from the northwest. It is representative of the view from a residence that is located near this observation point. KOP-5 provides views toward the proposed project site in a southeasterly direction from the proposed project s northwestern corner. The visual simulation photomontage indicates that the 2.05-MW WTGs would be visible in the foreground and middleground to viewers from this vantage point. Viewers who would be affected by the aesthetic impacts at or nearby this observation point include the nearby resident. Overall Visual Change The location of KOP-5 is remote and somewhat difficult to access without a four-wheel-drive vehicle but this vantage point is important because of its isolation from major roads or the popular PCT and the fact there are several residences nearby. WTGs will be visible in the foreground, middleground, and background range of KOP-5. Visual Sensitivity/Visual Change There are no landforms or structures in the vicinity and only low vegetation with the San Gabriel Mountains in the background. As a result, there would be unobstructed views of the WTGs from the residences. Although WTGs are not blocked from any vantage point near KOP-5, the location is remote, and the number of viewers is expected to be low. Visual impacts from this KOP would generally affect residents. As a result, visual sensitivity would be low-to-moderate. KOP-6 Northeast Corner of Project KOP-6 is located east of the northeastern portion of the proposed project site. This observation point was chosen to provide a representative view of the proposed project from the east at a distance where the proposed project is in the middleground. This location is representative of the view from a residence that is located near this observation point. KOP-6 provides expansive views west toward the proposed project site. The visual simulation photomontage indicates that the 2.05-MW WTGs would be visible in the middleground and background to viewers from this observation point. In addition, the proposed project would partially obstruct and degrade the view of the mountains in the more distant background from this observation point. Viewers who would be affected by the aesthetic impacts at or nearby this observation point include the nearby residents. Overall Visual Change All WTGs visible from KOP-6 are either in the middleground or background range. The immediate foreground and foreground would not be altered after construction of the proposed project. The 8 to 10 WTGs visible in the middle and background range will partially obstruct the view of some vegetation and a portion of the view of the mountains in the distance. Visual change from KOP-6 would be considered low-to-moderate. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 9

15 Visual Sensitivity/Visual Change KOP-6 was chosen due to its proximity to a small residential community that is outside the proposed project area but close enough to be considered visually sensitive to the project. Although the number of WTGs being constructed for the proposed site within the view of this community is approximately 10, the approved Manzana Wind Energy Project would also be visible in the distance, behind the WTGs proposed for the. As a result, the proposed project will not substantially alter the existing visual character of the site. Although nearby residents may be accustomed to seeing WTGs in the project vicinity, adding additional WTGs as a result of the proposed project would result in a visual sensitivity level of moderate-to-high, or adverse but not significant. KOP TH Street West and Avenue A KOP-7 is located at the corner of 220 th Street West and Avenue A approximately two miles southwest of the project. This observation point was chosen to provide a representative view of the proposed project from the southwest at a distance where the proposed project is in the background. This location provides an example of the view from local unimproved roads with low traffic volume. KOP-7 provides expansive views northeast toward the proposed project site. The visual simulation photomontage indicates that the and 1.5-MW WTGs would be visible in the background to viewers from this observation point. In addition, the proposed project would partially obstruct and degrade the view of the mountains in the more distant background from this observation point (Figure R ). Overall Visual Change Construction of the proposed project would result in up to 250 WTGs being constructed along the foothills of the Tehachapi Mountains. These WTGs would be visible in the background range from KOP-7. All WTGs would not be visible from this KOP as a result of the distance and topography. The Tehachapi Mountains would be partially obstructed, and the visual change would be considered low-to-moderate. Visual Sensitivity/Visual Change Potential viewers who would be sensitive to visual impacts from this observation point include drivers on the two local roads (Figure R ). Although nearby residents may be accustomed to seeing WTGs in the project vicinity, adding additional WTGs as a result of the proposed project would result in a visual sensitivity level of moderate-to-high, or adverse but not significant. W:\PROJECTS\1378\ \Documents\Tech Report Addenda_ \Addendum Vis Tech Report.Doc Page 10

Pacific Wind Energy Project Draft Environmental Impact Report

Pacific Wind Energy Project Draft Environmental Impact Report Pacific Wind Energy Project Table of Contents VOLUME 1 1 Executive Summary... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-1 1.3 Purpose and Use of the Draft EIR... 1-4 1.4 Project Overview...

More information

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas.

Oil Lines and Wells Utilities and Service Systems. Solid Waste Affected Environment Electricity. Natural Gas. Affected Environment, Environmental 2.1.4 Utilities and Service Systems This section addresses the potential impacts to public utilities and service systems within the project area as a result of project

More information

Project Description. Chapter Project Overview. 3.2 Proposed Project

Project Description. Chapter Project Overview. 3.2 Proposed Project 3.1 Project Overview Chapter 3 Project Description This Environmental Impact Report (EIR) has been prepared to identify and evaluate potential environmental impacts associated with implementation of enxco

More information

Chapter 6 Alternatives

Chapter 6 Alternatives 6 invisible_toc_marker 6.1 Introduction Chapter 6 Alternatives As described in Chapter 2 of this Supplemental EIR (SEIR), an EIR was previously certified for the Alta Oak Creek Mojave (AOCM) Project. Two

More information

Photomontages SECTION 10

Photomontages SECTION 10 Photomontages SECTION 10 10.1 Photomontages Photomontages have been prepared by Truescape Visual Communication to illustrate the likely location of the Collector Wind Farm turbines following construction.

More information

ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project

ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project ADDENDUM to the Environmental Impact Report for the Rosamond Solar Project Original Final EIR (SCH# 2010031024) (by SGS Antelope Valley Development, LLC) ROSAMOND SOLAR MODIFICATION PROJECT (Sites 5 &

More information

Appendix B. Aesthetics Technical Report

Appendix B. Aesthetics Technical Report Appendix B Aesthetics Technical Report Draft Aesthetics Technical Report North Sky River Wind Energy Project Prepared For: North Sky River Energy, LLC NextEra Energy Resources, LLC 700 Universe Boulevard

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,

More information

4.1 AESTHETICS EXISTING SETTING

4.1 AESTHETICS EXISTING SETTING 4.1 AESTHETICS This section describes the existing visual resources in the area and summarizes applicable plans, policies, and regulations. This section also includes an overview of the methodology used

More information

APPENDIX J. Dry Utilities Master Plan

APPENDIX J. Dry Utilities Master Plan APPENDIX J Dry Utilities Master Plan Sutter Pointe Specific Plan Dry Utilities Master Plan Prepared by MacKay & Somps Civil Engineers, Inc. 1771 Tribute Road, Suite E Sacramento, California 95818 (916)

More information

NOTICE OF PREPARATION AND SCOPING MEETING

NOTICE OF PREPARATION AND SCOPING MEETING April 9, 2013 NOTICE OF PREPARATION AND SCOPING MEETING SUBJECT: Notice of preparation of a Draft Environmental Impact Report (DEIR) for the California Flats Solar Project. The County of Monterey will

More information

3 PROJECT DESCRIPTION

3 PROJECT DESCRIPTION 3.1 PROJECT OVERVIEW 3 PROJECT DESCRIPTION The Rocklin 60 project (proposed project) includes the subdivision of 56.9 acres of land, construction of 179 single-family, detached dwelling units, and installation

More information

EIGHT POINT WIND ENERGY CENTER

EIGHT POINT WIND ENERGY CENTER EIGHT POINT WIND ENERGY CENTER Case No. 16 F 0062 1001.11 Exhibit 11 Preliminary Design Drawings Contents Exhibit 11: Preliminary Design Drawings... 1 11(a) Site Plan... 1 11(b) Construction Operations

More information

SOUTHWEST CONNECTICUT RELIABILITY PROJECT

SOUTHWEST CONNECTICUT RELIABILITY PROJECT SOUTHWEST CONNECTICUT RELIABILITY PROJECT BY THE CONNECTICUT LIGHT AND POWER COMPANY DOING BUSINESS AS EVERSOURCE ENERGY VOLUME 1: DESCRIPTION OF THE PROPOSED PROJECT AND ALTERNATIVES ANALYSIS APRIL 2016

More information

ALAMEDA COUNTY COMMUNITY DEVELOPMENT AGENCY. September 15, 2014

ALAMEDA COUNTY COMMUNITY DEVELOPMENT AGENCY. September 15, 2014 h ALAMEDA COUNTY COMMUNITY DEVELOPMENT AGENCY P L A N N I N G D E P A R T M E N T Chris Bazar Agency Director Albert Lopez Planning Director 224 West Winton Ave Room 111 Hayward California 94544 phone

More information

SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW

SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW SECTION 10 TRANSMISSION LINE DESIGN AND RIGHT-OF-WAY CONFIGURATION OPTIONS IN MANSFIELD HOLLOW Supplemental Municipal Consultation Filing The Interstate Reliability Project 10. TRANSMISSION LINE DESIGN

More information

Re: Revised Draft Environmental Impact Report for the Rosamond Solar Array Project by First Solar, Inc. (PP10231)

Re: Revised Draft Environmental Impact Report for the Rosamond Solar Array Project by First Solar, Inc. (PP10231) PLANNING AND COMMUNITY DEVELOPMENT DEPARTMENT Lorelei H. Oviatt, AICP, Director 2700 "M" STREET, SUITE 00 BAKERSFIELD, CA 9330-2323 Phone: (66) 862-8600 FAX: (66) 862-860 TTY Relay -800-735-2929 E-Mail:

More information

The Tehachapi Renewable Transmission Project

The Tehachapi Renewable Transmission Project The Tehachapi Renewable Transmission Project GREENING THE GRID Celebrating California s Progress in Renewable Energy March 2010 Tehachapi Renewable Transmission Project: Leading the Way to a Greener Future

More information

3.12 LAND USE AND PLANNING

3.12 LAND USE AND PLANNING 3.12 LAND USE AND PLANNING 3.12.1 INTRODUCTION This section describes the existing land uses in the project vicinity that could be affected by implementation of the Proposed Action and the alternatives.

More information

Derby North Gateway Tax Increment Financing District Redevelopment Project Plan. July 25, 2013

Derby North Gateway Tax Increment Financing District Redevelopment Project Plan. July 25, 2013 Derby North Gateway Tax Increment Financing District Redevelopment Project Plan July 25, 2013 1 Table of Contents I. Summary of Feasibility Study... 3 (Includes District Map and Legal Description) II.

More information

Section 3.9 Land Use and Planning ENVIRONMENTAL SETTING

Section 3.9 Land Use and Planning ENVIRONMENTAL SETTING Section 3.9 Land Use and Planning This section evaluates the existing land use setting and potential land use and planning impacts that may result from construction and/or operation of the proposed project.

More information

4.7 Livestock Grazing

4.7 Livestock Grazing This section of the Draft Plan Amendment, Draft Environmental Impact Statement/Environmental Impact Report (Draft EIS/EIR) addresses potential impacts of the Alta East Wind Project (AEWP) on livestock

More information

Karen, Best regards, *National Environmental Policy Act

Karen, Best regards, *National Environmental Policy Act From: Pell, Jerry To: 'karen_goebel@fws.gov' Cc: 'Tim Murphy' ; 'Richard Williams' ; Como, Anthony ;

More information

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview... TABLE OF CONTENTS 4 DESCRIPTION AND EVALUATION OF ALTERNATIVES... 4-1 4.1 INTRODUCTION... 4-1 4.2 METHODOLOGY... 4-1 4.3 DESCRIPTION OF ALTERNATIVES... 4-2 4.3.1 No Project Alternative... 4-2 4.3.2 Alternative

More information

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No. d/b/a National Grid and Clear River Energy LLC (Burrillville Interconnection Project) RIPUC Dkt. No. Testimony of David J. Beron, P.E., P.M.P. November, 0 0-v R.I.P.U.C. Dkt. No. 0 0 INTRODUCTION Q. Please

More information

Jean E. Vissering Landscape Architecture 3700 NORTH STREET MONTPELIER VERMONT Phone:

Jean E. Vissering Landscape Architecture 3700 NORTH STREET MONTPELIER VERMONT Phone: Jean E. Vissering Landscape Architecture 3700 NORTH STREET MONTPELIER VERMONT 05602 Phone: 802-223-3262 1 SITING WIND TURBINES Introduction First, I want to discuss utility scale wind farms and then smaller

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information

SECTION 6.0 Alternatives to the Proposed Project

SECTION 6.0 Alternatives to the Proposed Project SECTION 6.0 Alternatives to the Proposed Project 6.0 ALTERNATIVES TO THE PROPOSED PROJECT CEQA requires that an EIR include an analysis of a range of project alternatives that could feasibly attain most

More information

5.0 ALTERNATIVE VARIATIONS

5.0 ALTERNATIVE VARIATIONS 5.0 ALTERNATIVE VARIATIONS 5.1 INTRODUCTION The Draft EIR for the Beverly Hilton Revitalization Plan evaluated five alternatives to the project, pursuant to Section 15126.6 of the California Environmental

More information

Clinton Keith Road Extension Project

Clinton Keith Road Extension Project Clinton Keith Road Extension Project Addendum to Supplemental Environmental Impact Report (SCH#1995062022) Clinton Keith Road Extension Project Riverside County, California Prepared for County of Riverside

More information

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm EXECUTIVE SUMMARY This (SEIS) has been prepared for the proposed Jericho Rise Wind Farm (the Project). LLC (the Applicant), a wholly owned subsidiary of EDP Renewables (EDPR), is proposing to construct

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

NIGHTTIME ILLUMINATION

NIGHTTIME ILLUMINATION IV.A.3 NIGHTTIME ILLUMINATION 1. INTRODUCTION This section analyzes and discusses the extent to which the proposed project s artificial lighting would affect the visual environment of the project site

More information

OPTIONAL STATIONAVIATION/MANCHESTER

OPTIONAL STATIONAVIATION/MANCHESTER CRENSHAW/LAX TRANSIT CORRIDOR PROJECT FEIS/FEIR OPTIONAL STATIONAVIATION/MANCHESTER Aviation and Manchester, Looking East Aviation/Manchester Station (Optional) The Optional Aviation/Manchester Station

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1. Introduction 1.1 Purpose of the Supplemental Environmental Impact Report (EIR) The California Environmental Quality Act (CEQA) requires preparation of an Environmental Impact Report (EIR) when

More information

5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1

5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1 SECTION 5 STREET LIGHTING CONTENTS Page 5-1 Street Lights Required...5-1 5-2 Street Lights on Private Roadways...5-1 5-3 Developer s Responsibility...5-1 5-4 Utility Company Authorization...5-1 5-5 General

More information

(1) The proposed commercial solar energy generation facility is either

(1) The proposed commercial solar energy generation facility is either (2) The design and siting of these facilities shall avoid the placement of turbines on or immediately adjacent to the upwind side of ridge crests; (3) The design may include other design features to minimize

More information

6.1 Introduction. Chapter 6 Alternatives

6.1 Introduction. Chapter 6 Alternatives Chapter 6 Alternatives 6.1 Introduction CEQA requires that an EIR describe a range of reasonable alternatives to the proposed project or to the location of the proposed project that could feasibly avoid

More information

ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES

ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES 4.12.5 ELECTRICITY, NATURAL GAS, AND TELECOMMUNICATION SERVICES 4.12.5.1 INTRODUCTION The electricity, natural gas and telecommunications analysis is based on information within the following documents:

More information

CHAPTER 2 DESIGN REFINEMENTS

CHAPTER 2 DESIGN REFINEMENTS CHAPTER 2 DESIGN REFINEMENTS 2.1 INTRODUCTION Since publication of the Draft 2 nd Supplemental Environmental Impact Report (SEIR-2), additional design refinements have been identified. Some of these refinements

More information

CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO

CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO CITY OF TONKA BAY COUNTY OF HENNEPIN STATE OF MINNESOTA ORDINANCE NO. 2017- AN ORDINANCE AMENDING CHAPTER X, ZONING, SECTION 1011, GENERAL DEVELOPMENT AND PERFORMANCE STANDARDS WIND ENERGY CONVERSION SYSTEMS

More information

) ) ) ) ) ) ) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

) ) ) ) ) ) ) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BUCZKOWSKI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: Exhibit No.: Witness: A.1-1-01 David Buczkowski Application of Southern California Gas Company (U 0 G and San Diego Gas & Electric Company (U 0 G For Authority To Recover North-South Project

More information

Application for a Certificate of Environmental Compatibility

Application for a Certificate of Environmental Compatibility Application for a Certificate of Environmental Compatibility Irvington to Kino 138 kilovolt Transmission Line Project Prepared for: Arizona Power Plant and Transmission Line Siting Committee Submitted

More information

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT

DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CONTENTS CENTINELA SOLAR ENERGY PROJECT CONTENTS DRAFT ENVIRONMENTAL IMPACT REPORT/ ENVIRONMENTAL ASSESSMENT CENTINELA SOLAR ENERGY PROJECT CHAPTER 1.0 INTRODUCTION 1.1 PURPOSE OF THE DOCUMENT... 1.0 1 1.2 PROJECT BACKGROUND... 1.0 1 1.3 Project

More information

Bureau of Land Management. Public Scoping Meeting

Bureau of Land Management. Public Scoping Meeting Bureau of Land Management Public Scoping Meeting April 2010 NOTICE OF INTENT Federal Register / Vol. 74, No. 102 / Friday, May 29, 2009 / Notices DEPARTMENT OF THE INTERIOR Bureau of Land Management [NM-114438;

More information

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED

APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED APPENDIX A: NOTICE OF PREPARATION AND COMMENTS RECEIVED Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal

More information

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT Date: September 19, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS B203 Sacramento,

More information

ATTACHMENT B THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA RESOLUTION NO._6022_

ATTACHMENT B THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA RESOLUTION NO._6022_ ATTACHMENT B THE COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA RESOLUTION NO._6022_ RESOLUTION ADOPTING A DESIGN FOR DEVELOPMENT FOR BILLBOARD STRUCTURES IN THE ADELANTE EASTSIDE REDEVELOPMENT

More information

Appendix N-3. Electricity

Appendix N-3. Electricity Appendix N-3 Electricity Appendix N-3-1 Electricity Technical Report Table of Contents ELECTRICAL SYSTEM TECHNICAL REPORT 1.0 Introduction 1.1 Scope of Work 1.2 Project Site Description 2.0 Environmental

More information

Lloydminster to Spruce Lake 138kV Transmission Line Projects

Lloydminster to Spruce Lake 138kV Transmission Line Projects Lloydminster to Spruce Lake 138kV Transmission Line Projects Preferred Corridor Presentation June 2017 SaskPower continues to invest in the province s electricity system to ensure we have the infrastructure

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane.

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane. 17. SERVICES 17.1 Introduction 17.1.1 WSP Development Limited has been appointed by CALA Homes to investigate and appraise the availability of services to serve a proposed mix-use development of approximately

More information

Environmental and Development Services Department Planning Division San Pablo Avenue, El Cerrito, CA (510) FAX: (510)

Environmental and Development Services Department Planning Division San Pablo Avenue, El Cerrito, CA (510) FAX: (510) Environmental and Development Services Department Planning Division 10890 San Pablo Avenue, El Cerrito, CA 94530 (510) 215-4330 - FAX: (510) 233-5401 N O T I C E O F P R E P A R A T I O N DATE: April 4,

More information

Technical Data

Technical Data 4906-17-05 Technical Data (A) PROJECT AREA SITE have occurred in this section. (1) Geography and Topography have occurred in this section. (2) Aerial Photography have occurred in this section. (3) Site

More information

APPENDICES. Table 46: Quantified Objectives (October 2013 to October 2021) New Construction Rehabilitation Conservation/Preservation

APPENDICES. Table 46: Quantified Objectives (October 2013 to October 2021) New Construction Rehabilitation Conservation/Preservation VI. APPENDICES APPENDIX A. QUANTIFIED OBJECTIVES The City of Placerville has established quantified (numerical) objectives for several program categories to provide measurable standards for monitoring

More information

Southwest Renewable Energy Conference

Southwest Renewable Energy Conference Southwest Renewable Energy Conference James Sahagian Vice President Commercial Development 9/11/09 2009 Sempra Global. All copyright and trademark rights reserved. Sempra Energy Sempra Energy Develops,

More information

NOTICE OF PREPARATION DRAFT ENVIRONMENTAL IMPACT REPORT

NOTICE OF PREPARATION DRAFT ENVIRONMENTAL IMPACT REPORT NOTICE OF PREPARATION DRAFT ENVIRONMENTAL IMPACT REPORT To: From: (Potential Responsible, City of Perris Trustee, Federal and Local Development Services Department Agencies and nearby property 135 North

More information

65 East Project (P18-045) Addendum to an Environmental Impact Report

65 East Project (P18-045) Addendum to an Environmental Impact Report 65 East Project (P18-045) Addendum to an Environmental Impact Report File Number/Project Name: 65 East Project (P18-045) Project Location and Surrounding Land Uses: The proposed project site consists of

More information

SEATON MUNICIPAL TRANSFORMER STATION. Welcome to our Public Information Centre

SEATON MUNICIPAL TRANSFORMER STATION. Welcome to our Public Information Centre Welcome to our Public Information Centre Delivering Power to Your Community Hydro One Networks Inc. s (Hydro One) transmission system carries high-voltage electricity across the province to local distribution

More information

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Project Description Canadian Niagara Power Inc. ( CNP ) proposes to replace two existing lattice steel towers (Queen Street

More information

6. Cumulative Impacts

6. Cumulative Impacts 6.1 OVERVIEW Section 15355 of the California Environmental Quality Act (CEQA) Guidelines defines cumulative impacts as: "...two or more individual effects which when considered together, are considerable

More information

DESIGN REVIEW COMMITTEE AGENDA ITEM

DESIGN REVIEW COMMITTEE AGENDA ITEM DESIGN REVIEW COMMITTEE AGENDA ITEM AGENDA DATE: MARCH 15, 2017 TO: THRU: FROM: SUBJECT: Chair Fox and Members of the Design Review Committee Anna Pehoushek, Assistant Community Development Director Monique

More information

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address. Application 06-12-005 et al. Exhibit Date: August, 2008 PREPARED TESTIMONY OF LEE LISECKI Q. Please state your name, professional position, and business address. A. My name is Lee Lisecki. I am a principal

More information

LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT

LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT PUCO Case No. 14-1397-EL-BLN Submitted pursuant to OAC 4906-11-01 AEP Ohio Transmission Company (AEP Ohio

More information

Northwest State Route 138 Corridor Improvement Project

Northwest State Route 138 Corridor Improvement Project Northwest State Route 138 Corridor Improvement Project Los Angeles County, CA DISTRICT 7- LA- 138 (PM 0.0/36.8); DISTRICT 7- LA- 05 (PM 79.5/83.1); DISTRICT 7- LA- 14 (PM 73.4/74.4) 265100/ 0700001816

More information

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report APPENDIX B Excerpts from the October 2002 Interstate 83 and PA Route 921 The objective for the SR 921 interchange site was to study alternatives for construction of a new interchange. There are no short-term

More information

Energize Eastside Transmission Capacity Project April 13, 2016

Energize Eastside Transmission Capacity Project April 13, 2016 Energize Eastside Transmission Capacity Project April 13, 2016 Background Electricity is currently delivered to the Eastside area 1 through two 230 kv/115 kv bulk electric substations Sammamish substation

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest What s Inside? Answers to On: NextBridge Infrastructure and the East-West Tie Project Electricity in Northern Ontario Land issues Routing Project approval process Health

More information

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION PETITION OF PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE FOR A LICENSE TO CONSTRUCT AND MAINTAIN ELECTRIC LINES, STATIC WIRES AND FIBER OPTIC

More information

5. Environmental Analysis

5. Environmental Analysis 5.6 This section evaluates the potential impacts of the proposed project on human health and the environment due to exposure to hazardous materials or conditions associated with the project site, project

More information

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary:

CHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary: 7 Errata CHAPTER 7. ERRATA This chapter addresses errors and corrections to the text of the Phase 1 Draft EIS and is organized by Draft EIS chapter, section, and page number. 1) Chapter 1 Introduction

More information

AGRICULTURAL LAND AND PRODUCTION

AGRICULTURAL LAND AND PRODUCTION IV.12 AGRICULTURAL LAND AND PRODUCTION The analysis in this chapter addresses potential impacts to agricultural resources from adoption and implementation of the Desert Renewable Energy Conservation Plan

More information

July 26, Revised Electric and Magnetic Fields (EMF) Design Guidelines of Southern California Edison Company

July 26, Revised Electric and Magnetic Fields (EMF) Design Guidelines of Southern California Edison Company Akbar Jazayeri Vice President, Revenue and Tariffs July 26, 2006 ADVICE 2018-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Revised Electric and Magnetic Fields

More information

STATE OF NEW HAMPSHIRE Inter-Department Communication. Tf~ Tom Frantz - Director, Electric Division

STATE OF NEW HAMPSHIRE Inter-Department Communication. Tf~ Tom Frantz - Director, Electric Division STATE OF NEW HAMPSHIRE Inter-Department Communication FROM: \"""' Tf~ Tom Frantz - Director, Electric Division DATE: 15 October 2010 AT (OFFICE): NHPUC SUBJECT: DE 10-224: Petition by PSNH for a License

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

Impacts and Mitigation Measures

Impacts and Mitigation Measures means of reducing the effects of wind-generated noise at the microphone. Ambient noise level measurements may be performed when wind velocities at the proposed project site are sufficient to allow wind

More information

Policy Statement. Objective. Context. References and Supporting Documentation. Policy Statement

Policy Statement. Objective. Context. References and Supporting Documentation. Policy Statement Policy Statement Subject Guidelines for Placement of Power Poles Within Road Reserves in Built-Up Areas Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

Section 3.11 Land Use

Section 3.11 Land Use Chapter 3 Affected Environment, Environmental Consequences, and Mitigation Measures Section 3.11 Land Use Introduction This section discusses the effect of the proposed alternatives on existing land use,

More information

4.16 Utilities and Service Systems

4.16 Utilities and Service Systems 4.16 Utilities and Service Systems This section describes utilities and services in the area of the Proposed Project and assesses the potential environmental impacts. The Proposed Project would not result

More information

3.12 UTILITIES Introduction Environmental Setting

3.12 UTILITIES Introduction Environmental Setting 3.12 UTILITIES 3. Affected Environment and Environmental Analysis 3.12 UTILITIES 3.12.1 Introduction This section addresses the potential for impacting public utilities within the Port, the Main Channel,

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

STAFF REPORT. Permit Number: Tallman. Kitsap County Board of Commissioners; Kitsap County Planning Commission

STAFF REPORT. Permit Number: Tallman. Kitsap County Board of Commissioners; Kitsap County Planning Commission STAFF REPORT Permit Number: 15 00742 Tallman DATE: November 9, 2015 TO: FROM: RE: Kitsap County Board of Commissioners; Kitsap County Planning Commission Katrina Knutson, AICP, Senior Planner, DCD and

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES

SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES GOAL: Appropriately sited energy facilities that efficiently

More information

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS). This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit

More information

Mendocino Forest Products Grading For Industrial Land Improvements

Mendocino Forest Products Grading For Industrial Land Improvements Mendocino Forest Products Grading For Industrial Land Improvements Technical Memorandum #10 CEQA Evaluation of Environmental Impacts Prepared for: Mendocino Forest Products Company, LLC Consulting Engineers

More information

II. Corrections and Additions to the Draft EIR

II. Corrections and Additions to the Draft EIR II. Corrections and Additions to the Draft EIR II. Corrections and Additions to the Draft EIR This section of the Final EIR provides changes to the Draft EIR that have been made to clarify, correct, or

More information

6: OTHER CEQA CONSIDERATIONS

6: OTHER CEQA CONSIDERATIONS 6.1 Mandatory Findings of Significance 6: OTHER CEQA CONSIDERATIONS This chapter discusses the broader questions posed by CEQA. These include significant effects that cannot be mitigated to less than significant

More information

Planning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015

Planning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015 Planning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015 ITEM 4 Provo City s Energy Department requests Final Project Plan approval to rebuild and expand the Energy Department

More information

COVER FEATURE. Micropile. Design Minimizes. California Edison Project

COVER FEATURE. Micropile. Design Minimizes. California Edison Project COVER FEATURE Micropile Foundation Design Minimizes Environmental Impact for Southern California Edison Project by Chih-Hung Chen, P.E., Burns & McDonnell, and Nick Salisbury, Crux Subsurface, Inc. Micropiles

More information

CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report

CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report City of Tehachapi CITY OF TEHACHAPI GENERAL PLAN Draft Environmental Impact Report SCH No. 2009101084 Prepared for: City of Tehachapi Community Development Department 115 South Robinson Street Tehachapi,

More information

Addendum to Mitigated Negative Declaration

Addendum to Mitigated Negative Declaration REMARKS Background Addendum to Mitigated Negative Declaration Date of Publication of Addendum: Date of Final MND: March 29, 2012 Case No.: 2004.1004E Project Title: 1150 16 th Street Residential Retail

More information

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports.

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. June 29, 2017 Introduction This document addresses the siting work outstanding as of the November 10 th, 2016 siting

More information

1.0 INTRODUCTION 1.1 THE ENVIRONMENTAL REVIEW PROCESS Purpose and Authority

1.0 INTRODUCTION 1.1 THE ENVIRONMENTAL REVIEW PROCESS Purpose and Authority Lancaster Energy Center Introduction 1.0 INTRODUCTION 1.1 THE ENVIRONMENTAL REVIEW PROCESS The California Environmental Quality Act (CEQA) requires public agencies to identify, disclose, and consider the

More information

SILVER LEVEL AWARD WINNER. City of Carson Sustainability Best Practices Activities

SILVER LEVEL AWARD WINNER. City of Carson Sustainability Best Practices Activities SILVER LEVEL AWARD WINNER City of Carson Sustainability Best Practices Activities SPOTLIGHT AWARD Areas of Accomplishment SILVER LEVEL GOLD LEVEL PLATINUM LEVEL Agency GHG Reductions 26% Community GHG

More information

CONNECTING. Big Chino Valley Pumped Storage Project. Energy Infrastructure

CONNECTING. Big Chino Valley Pumped Storage Project. Energy Infrastructure CONNECTING Energy Infrastructure Big Chino Valley Pumped Storage Project Brian Studenka, Director, ITC Grid Development Andrew Jamieson, Regulatory Counsel, ITC Kim Goodnight, Regional Manager, Community

More information

Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement

Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement DATE: July 15, 2011 ADDENDUM NUMBER: 2 MODIFYING: Specifications No. 1698 PROJECT: Colorado River Aqueduct Pumping Plants 230 kv Disconnect Switches Replacement BID TIME AND DATE: 2:00 p.m., July 19, 2011

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA

DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,

More information