PLANNING. Planning for Renewable Energy A Companion Guide to PPS22

Size: px
Start display at page:

Download "PLANNING. Planning for Renewable Energy A Companion Guide to PPS22"

Transcription

1 Planning shapes the places where people live and work and the country we live in. It plays a key role in supporting the Government s wider economic, social and environmental objectives and for sustainable communities. PLANNING Planning for Renewable Energy A Companion Guide to PPS22

2 Planning for Renewable Energy A Companion Guide to PPS22

3 Acknowledgements This guide has been produced by Ove Arup and Partners. The project was supervised by officials from ODPM and DTI and supported by an advisory group, comprising representatives of: British Wind Energy Association Renewable Power Association British Biogen Royal Town Planning Institute Scottish Natural Heritage/The Landscape Institute Royal Society for the Protection of Birds Government Office for the South West Government Office for the North West London Borough of Merton DTI Defra The project team comprised representatives of Arup, TNEI Services Ltd and Dulas Ltd. The Department and its consultants wish to thank all those who assisted with the guide, including those who kindly gave their permission for the use of case studies and other material. Queen s Printer and Controller of Her Majesty s Stationery Office 2004 Copyright in the typographical arrangement and design and rests with the Crown Published for the Office of the Deputy Prime Minister, under licence from the Controller of Her Majesty s Stationery Office. This publication excluding logos, may be reproduced free of charge in any format or medium for research, private study or for internal circulation within an organisation. This is subject to it being reproduced accurately and not in a misleading context. The material must be acknowledged as Crown copyright and the title of the publication specified. For any other use of this material please write to The HMSO Licensing Division, HMSO, St Clements House, 2-16 Colegate, Norwich NR3 1BQ. Fax or licencing@cabinet-office.x.gsi.gov.uk ISBN Product code 04PD02691

4 176 PLANNING FOR RENEWABLE ENERGY Technical Annex : Wind operators in the UK and acts as a central point of contact for identifying specific consultees relevant to a site. OFCOM will identify any radio installations relevant to a wind farm site. Although OFCOM passes any enquiry on to other interested parties, who should respond to an application, this process is only partial and an applicant seeking planning permission would be well advised to make direct contact with any authorities/bodies which are likely to be interested a list of potentially interested parties is given at the end of this Section. 72. In addition, it may be necessary to consult the local water company, gas company and electricity company, and also emergency services such as the police, ambulance service and the coastguard. Shadow Flicker and Reflected Light 73. Under certain combinations of geographical position and time of day, the sun may pass behind the rotors of a wind turbine and cast a shadow over neighbouring properties. When the blades rotate, the shadow flicks on and off; the effect is known as shadow flicker. It only occurs inside buildings where the flicker appears through a narrow window opening. The seasonal duration of this effect can be calculated from the geometry of the machine and the latitude of the site. Although problems caused by shadow flicker are rare, for sites where existing development may be subject to this problem, applicants for planning permission for wind turbine installations should provide an analysis to quantify the effect. A single window in a single building is likely to be affected for a few minutes at certain times of the day during short periods of the year. The likelihood of this occurring and the duration of such an effect depends upon: the direction of the residence relative to the turbine(s); the distance from the turbine(s); the turbine hub-height and rotor diameter; the time of year; the proportion of day-light hours in which the turbines operate; the frequency of bright sunshine and cloudless skies (particularly at low elevations above the horizon); and, the prevailing wind direction.

5 PLANNING FOR RENEWABLE ENERGY Technical Annex : Wind 177 Only properties within 130 degrees either side of north, relative to the turbines can be affected at these latitudes in the UK turbines do not cast long shadows on their southern side. 74. The further the observer is from the turbine the less pronounced the effect will be. There are several reasons for this: there are fewer times when the sun is low enough to cast a long shadow; when the sun is low it is more likely to be obscured by either cloud on the horizon or intervening buildings and vegetation; and, the centre of the rotor s shadow passes more quickly over the land reducing the duration of the effect. 75. At distance, the blades do not cover the sun but only partly mask it, substantially weakening the shadow. This effect occurs first with the shadow from the blade tip, the tips being thinner in section than the rest of the blade. The shadows from the tips extend the furthest and so only a very weak effect is observed at distance from the turbines. 76. Shadow flicker can be mitigated by siting wind turbines at sufficient distance from residences likely to be affected. Flicker effects have been proven to occur only within ten rotor diameters of a turbine. Therefore if the turbine has 80m diameter blades, the potential shadow flicker effect could be felt up to 800m from a turbine. 77. Around 0.5 % of the population is epileptic and of these around 5 % are photo-sensitive. Of photo-sensitive epileptics less than 5 % are sensitive to lowest frequencies of Hz, the remainder are sensitive only to higher frequencies. The flicker caused by wind turbines is equal to the blade passing frequency. A fast-moving three-bladed machine will give rise to the highest levels of flicker frequency. These levels are well below 2 Hz. The new generation of wind turbines is known to operate at levels below 1 Hz. 78. Turbines can also cause flashes of reflected light, which can be visible for some distance. It is possible to ameliorate the flashing but it is not possible to eliminate it. Careful choice of blade colour and surface finish can help reduce the effect. Light grey semi-matt finishes are often used for this. Other colours and patterns can also be used to reduce the effect further. (See The Influence of Colour on the Aesthetics of Wind Turbine Generators ETSU W/14/00533/00/00).

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and

More information

Rumster Wind Energy Project

Rumster Wind Energy Project Rumster Wind Energy Project Report OSE3525 Appendix D Noise and Shadow Flicker Assessment Orkney Sustainable Energy Limited 6 North End Road Stromness Orkney KW16 3AG Telephone 01856850054 Facsimile 01856851199

More information

Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS.

Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS. 8. SHADOW FLICKER Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS. 8.1 RECEIVING ENVIRONMENT Wind turbines, as with trees or any other tall structure,

More information

REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT

REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT MORTLAKE SOUTH WIND FARM SITE VICTORIA (AUSTRALIA) March 2016 Contents 1 Executive Summary... 3 2 Mortlake Site... 5 2.1 Site Location...

More information

Environmental Impact Assessment

Environmental Impact Assessment The Project Hoben International Ltd proposes to develop a single 500kW wind turbine at their Manystones Lane site near Brassington. The turbine will be located approximately 350m to the south east of the

More information

Amending the Definition of a Caravan. Consultation Paper

Amending the Definition of a Caravan. Consultation Paper Amending the Definition of a Caravan Consultation Paper August 2005 Amending the Definition of a Caravan A Consultation Paper August 2005 Office of the Deputy Prime Minister: London Office of the Deputy

More information

Appendix K Shadow Flicker Study

Appendix K Shadow Flicker Study Appendix K Shadow Flicker Study Shadow Flicker Assessment- Honeywood Final Report Submitted to: Geilectric 1850, Panama Street, Suite 501 Brossard (Québec) Canada J4W 3C6 Classification: Reference: Honeywood_ShadowFlickering

More information

Separation between Wind Turbines and Overhead Lines Principles of Good Practice

Separation between Wind Turbines and Overhead Lines Principles of Good Practice PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation L44 Separation between Wind Turbines and Overhead Lines Principles of Good Practice www.energynetworks.org

More information

Shadow Flicker Impact Analysis for the Alabama Ledge Wind Farm in Genesee County, New York

Shadow Flicker Impact Analysis for the Alabama Ledge Wind Farm in Genesee County, New York Shadow Flicker Impact Analysis for the Alabama Ledge Wind Farm in Genesee County, New York Prepared for Alabama Ledge Wind Farm, LLC 2 Borden Avenue, Suite 203 Perry, New York 14530 Prepared by 160 Federal

More information

Appendix T BIWF Shadow Flicker Analysis

Appendix T BIWF Shadow Flicker Analysis Appendix T BIWF Shadow Flicker Analysis Shadow Flicker Impact Analysis for the Block Island Wind Farm Prepared for Deepwater Wind Block Island, LLC Prepared by 160 Federal Street Boston, MA 02110 May 2012

More information

MARRIAGE (SCOTLAND) BILL

MARRIAGE (SCOTLAND) BILL MARRIAGE (SCOTLAND) BILL POLICY MEMORANDUM INTRODUCTION 1. This document relates to the Marriage (Scotland) Bill introduced in the Scottish Parliament on 13 November 2001. It has been prepared by the Scottish

More information

Burnt Hill Wind Development

Burnt Hill Wind Development Report OSE3581 Appendix D Noise and Shadow Flicker Assessment Environmental Health Studies: Noise and Shadow Flicker Assessment 1 Summary results 1.1 Wind turbines can create two types of environmental

More information

Skeabrae Wind Energy Project

Skeabrae Wind Energy Project Skeabrae Document OSE/3526 March 2013 Skeabrae Wind Energy Project Noise and Shadow Impact Revision 3: V29 225kW wind turbine Richard Gauld IEng MInstMC BSc(Hons) Dip. DesInn Dip. GeoSci 1 Skeabrae Wind

More information

Environmental Statement Volume 1. Non-Technical Summary. Land south of Pendown Farm Cornwall

Environmental Statement Volume 1. Non-Technical Summary. Land south of Pendown Farm Cornwall Environmental Statement Volume 1 Land south of Pendown Farm Cornwall August 2012 1. INTRODUCTION 1.1. Windberry Energy Operations Limited has submitted a planning application to Cornwall Council (CC) for

More information

PLANNING. Planning Policy Statement 23: Planning and Pollution Control

PLANNING. Planning Policy Statement 23: Planning and Pollution Control Planning shapes the places where people live and work and the country we live in. It plays a key role in supporting the Government s wider social, environmental and economic objectives and for sustainable

More information

Glazing safety in relation to impact, opening and cleaning

Glazing safety in relation to impact, opening and cleaning The Building Regulations 2000 Glazing safety in relation to impact, opening and cleaning N APPROVED DOCUMENT N1 N2 N3 N4 Protection against impact Manifestation of glazing Safe opening and closing of windows,

More information

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity.

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity. ORDINANCE NO. AN ORDINANCE AMENDING ORDINANCE NO. 1060 KNOWN AS THE WILLMAR ZONING ORDINANCE BY ADDING SECTION 11 RELATING TO WIND ENERGY CONVERSION SYSTEMS (WECS) The City of Willmar does ordain as follows:

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information

Ackers Adventure, Golden Hillock Road, Sparkbrook, Birmingham, B11 2PY. Erection of a 22m high (ground to blade tip) wind turbine

Ackers Adventure, Golden Hillock Road, Sparkbrook, Birmingham, B11 2PY. Erection of a 22m high (ground to blade tip) wind turbine Committee Date: 20/03/2014 Application Number: 2013/08552/PA Accepted: 27/11/2013 Application Type: Full Planning Target Date: 22/01/2014 Ward: South Yardley Ackers Adventure, Golden Hillock Road, Sparkbrook,

More information

Provision of Rail Passenger Services (Scotland) Bill [AS INTRODUCED]

Provision of Rail Passenger Services (Scotland) Bill [AS INTRODUCED] Provision of Rail Passenger Services (Scotland) Bill [AS INTRODUCED] CONTENTS Section 1 Circumstances where rail passenger services to be deemed to be provided more economically and efficiently if provided

More information

APPENDIX R SHADOW FLICKER REPORT

APPENDIX R SHADOW FLICKER REPORT APPENDIX R SHADOW FLICKER REPORT Shadow Flicker Study Palo Alto Wind Energy Project - Palo Alto County, Iowa Prepared for: Palo Alto Wind Energy LLC One South Wacker Drive Suite 1800 Chicago, Illinois

More information

Position paper on wind turbines and public health

Position paper on wind turbines and public health Position paper on wind turbines and public health Item type Authors Publisher Report Health Service Executive (HSE); HSE Public Health Medicine Environment and Health Group Health Service Executive (HSE)

More information

Shadow Flicker Issues and their Handling for Wind Farm Approval in Germany

Shadow Flicker Issues and their Handling for Wind Farm Approval in Germany Shadow Flicker Issues and their Handling for Wind Farm Approval in Germany Wind Power and human health June 23rd 2016, Warsaw Oliver Thomas, BBB Umwelttechnik GmbH 2 Company History, Founders and Company

More information

Wind Turbine Site Survey Report: Example NAME

Wind Turbine Site Survey Report: Example NAME Wind Turbine Site Survey Report: Example NAME ADDRESS POST CODE Prepared by: Steve Forss An introduction... The purpose of our site surveys? In order to maintain our high standards and obligations to getting

More information

Building Quality Metrics. Mark Birse, Deputy Director & Head of Inspectorate

Building Quality Metrics. Mark Birse, Deputy Director & Head of Inspectorate Building Quality Metrics Mark Birse, Deputy Director & Head of Inspectorate Indicators of mature Quality Culture: Led from the top, empowered from below Communication of priorities To personnel To shareholders

More information

State code 23: Wind farm development

State code 23: Wind farm development 23.1 Purpose statement The purpose of the code is to protect individuals, communities and the environment from adverse impacts as a result of the construction, operation and decommissioning of wind farm

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

In May of 2011, Council completed a three year project to develop regulations for largescale wind turbines in the County.

In May of 2011, Council completed a three year project to develop regulations for largescale wind turbines in the County. Municipality of the County of Kings Report to the Planning Advisory Committee Large-Scale Wind Turbine Policy, Post-PPM Report Prepared by Planning Services May 14 th, 2012 1. BACKGROUND In May of 2011,

More information

2011 ALBERTA FARM LAND ASSESSMENT MINISTER S GUIDELINES

2011 ALBERTA FARM LAND ASSESSMENT MINISTER S GUIDELINES 2011 ALBERTA FARM LAND ASSESSMENT MINISTER S GUIDELINES Alberta Queen's Printer holds copyright on behalf of the Government of Alberta in right of Her Majesty the Queen for all Government of Alberta

More information

Copyright in the typographical arrangement and design rests with the Crown.

Copyright in the typographical arrangement and design rests with the Crown. Duties on relevant authorities to have regard to the purposes of National Parks, Areas of Outstanding Natural Beauty (AONBs) and the Norfolk and Suffolk Broads Guidance Note Department for Environment,

More information

3. The maximum generating capacity of the Development shall not exceed 560MW at any time.

3. The maximum generating capacity of the Development shall not exceed 560MW at any time. Our ref: 12.04.09.04/227C DEPARTMENT OF ENERGY AND CLIMATE CHANGE ELECTRICITY ACT 1989 (Section 36) CONSTRUCTION AND OPERATION OF A WIND FARM GENERATING STATION KNOWN AS DUDGEON OFF THE COAST OF NORFOLK

More information

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary 22871-G8.indd greec01 Dec 2009 December 2009 Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty

More information

Consultation

Consultation Best value: new draft statutory guidance Consultation www.communities.gov.uk Best value: new draft statutory guidance Consultation April 2011 Department for Communities and Local Government Department

More information

Climate Change The UK Programme 2006

Climate Change The UK Programme 2006 Climate Change The UK Programme 2006 Climate Change The UK Programme 2006 Presented to Parliament by the Secretary of State for the Environment, Food and Rural Affairs by Command of Her Majesty Presented

More information

Planning and Development Briefs: A Guide to Better Practice

Planning and Development Briefs: A Guide to Better Practice Planning and Development Briefs: A Guide to Better Practice On 5th May 2006 the responsibilities of the Office of the Deputy Prime Minister (ODPM) transferred to the Department for Communities and Local

More information

DEPARTMENT FOR CULTURE, MEDIA AND SPORT BROADCASTING

DEPARTMENT FOR CULTURE, MEDIA AND SPORT BROADCASTING DEPARTMENT FOR CULTURE, MEDIA AND SPORT BROADCASTING An Agreement Between Her Majesty s Secretary of State for Culture, Media and Sport and the British Broadcasting Corporation Presented to Parliament

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 12 th June 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Good Documentation Practice Session 2

Good Documentation Practice Session 2 Good Documentation Practice Session 2 Good Documentation Practice A refresher EU GMP Chapter 4: Documentation Required GMP documentation: Site Master File Instructions: Specifications Manufacturing Formulae,

More information

Clustering: The grouping of wind turbines positioned or occurring closely together around a particular dwelling.

Clustering: The grouping of wind turbines positioned or occurring closely together around a particular dwelling. Section *.** Commercial/Utility Grade Wind Energy Systems PROPOSED BY CO BOARD 1-16-18 *.**.01Purpose: It is the purpose of this regulation to promote the safe, effective and efficient use of commercial/utility

More information

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES SECTION 1601 Wind Energy Installation In any zoning district, a conditional use permit or building permit may be granted to allow a wind energy conversion

More information

Appendix D: A selection of slides from presentations at local Community Council meetings

Appendix D: A selection of slides from presentations at local Community Council meetings Appendix D: A selection of slides from presentations at local Community Council meetings Hill of Ochiltree Wind Farm Public Consultation Pre-Application Consultation Report Facilitating Change (UK) Limited

More information

MCS 020. MCS Planning Standards. For permitted development installations of wind turbines and air source heat pumps on domestic premises

MCS 020. MCS Planning Standards. For permitted development installations of wind turbines and air source heat pumps on domestic premises MCS 020 MCS Planning Standards For permitted development installations of wind turbines and air source heat pumps on domestic premises This Standard is the property of Department of Energy and Climate

More information

Science 30 Unit D: Energy and the Environment

Science 30 Unit D: Energy and the Environment Science 30 Unit D: Energy and the Environment Chapter 2 Assignment Summary Science 30 Unit D: Energy And The Environment Chapter 2 Assignment Total Possible Marks 52 For Teacher s Use Only Your Mark Teacher

More information

APPENDIX M COMMUNITY ENGAGEMENT

APPENDIX M COMMUNITY ENGAGEMENT APPENDIX M COMMUNITY ENGAGEMENT Project Benefits Millbrook Community Wind The Future is Green Provincial Energy Independence This project will be one of many steps to fulfill Nova Scotia s goal of 40%

More information

Councillors, Officers and Stakeholders in the New Council Constitutions. Findings from the 2005 ELG Sample Survey

Councillors, Officers and Stakeholders in the New Council Constitutions. Findings from the 2005 ELG Sample Survey Councillors, Officers and Stakeholders in the New Council Constitutions Findings from the 2005 ELG Sample Survey Councillors, Officers and Stakeholders in the New Council Constitutions October 2006 Department

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 4 th July 2018 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Disclosure of information to trade unions for collective bargaining purposes

Disclosure of information to trade unions for collective bargaining purposes www.acas.org.uk 1 Disclosure of information to trade unions for collective bargaining purposes Acas Code of Practice 2 Published by TSO (The Stationery Office), part of Williams Lea Tag, and available

More information

Environmental issues and impacts for wind power

Environmental issues and impacts for wind power Environmental issues and impacts for wind power Prof John Twidell AMSET Centre UK EU/Thailand Seminar, Bangkok; Oct 4 & 5 2012 Now on the Board of Westmill Windfarm, near Oxford, UK University science

More information

Whynotts Community Wind

Whynotts Community Wind Whynotts Community Wind Project Benefits Investing in Local Communities Local Community Education Once constructed, the project will fund The Whynotts Community Renewable Education Program. This program

More information

Taking Forward the UK Climate Change Bill: The Government Response to Pre-Legislative Scrutiny and Public Consultation

Taking Forward the UK Climate Change Bill: The Government Response to Pre-Legislative Scrutiny and Public Consultation October 2007, Taking Forward the UK Climate Change Bill: The Government Response to Pre-Legislative Scrutiny and Public Consultation, Executive Summary (Minister s Forward and Executive Summary) https://www.parliament.uk/documents/upload/cm7225-

More information

South Branch Wind Farm Acoustic Audit - Emission Summary for Public Distribution

South Branch Wind Farm Acoustic Audit - Emission Summary for Public Distribution South Branch Wind Farm Acoustic Audit - Emission Summary for Public Distribution Introduction The South Branch Wind Farm (project) operates 10 Siemens SWT-3.0-113 wind turbines located within the Township

More information

REPORT OF THE ASSISTANT DIRECTOR OF PLANNING AND DEVELOPMENT MANAGEMENT

REPORT OF THE ASSISTANT DIRECTOR OF PLANNING AND DEVELOPMENT MANAGEMENT PLANNING AND ENVIRONMENT COMMITTEE 11 NOVEMBER 2010 ITEM 7 REPORT OF THE ASSISTANT DIRECTOR OF PLANNING AND DEVELOPMENT MANAGEMENT BACKGROUND PAPERS GENERAL STATEMENT The background papers to the reports

More information

MHRA GDP Symposium. Novotel London West, London 8 & 10 December #GMDPevents

MHRA GDP Symposium. Novotel London West, London 8 & 10 December #GMDPevents MHRA GDP Symposium Novotel London West, London 8 & 10 December 2015 Complex Business Models - Outsourced Activities Presented by: Jacqueline Masayi, GDP Inspector Background Increased complexities of the

More information

Fermanagh and Omagh District Council

Fermanagh and Omagh District Council Fermanagh and Omagh District Council Planning Committee Meeting 9 April 2015 Report by Principal Planning Officer K/2014/0186/F: Proposed installation of a wind turbine on a tubular tower with a blade

More information

Office of Kingston Town Planner 26 Evergreen Street Kingston, Massachusetts fax

Office of Kingston Town Planner 26 Evergreen Street Kingston, Massachusetts fax Office of Kingston Town Planner 26 Evergreen Street Kingston, Massachusetts 02364 781-585-0549 fax 781-585-0543 tbott@kingstonmass.org TO: Henny M. Walters, Health Agent Paul Armstrong, Building Inspector/Zoning

More information

Presented to Parliament by the Prime Minister by Command of Her Majesty. July Cm

Presented to Parliament by the Prime Minister by Command of Her Majesty. July Cm Government Response to the Intelligence and Security Committee s Report of Session 2013-14: Foreign involvement in the Critical National Infrastructure Presented to Parliament by the Prime Minister by

More information

Knockendurrick Wind Farm Proposal

Knockendurrick Wind Farm Proposal Knockendurrick Wind Farm Proposal Planning Application and Environmental Statement Non Technical Summary September 2013 Energy for everyone s benefit of the proposed site showing 132m turbines. View from

More information

Seneca Wind Cluster. Non Technical Summary May 2013 SENECA GLOBAL ENERGY

Seneca Wind Cluster. Non Technical Summary May 2013 SENECA GLOBAL ENERGY Seneca Wind Cluster Non Technical Summary May 2013 SENECA GLOBAL ENERGY Non-Technical Summary This document presents a Non Technical Summary (NTS) of the Environmental Statement (ES), which has been submitted

More information

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...

More information

BBC Royal Charter Bill [HL]

BBC Royal Charter Bill [HL] BBC Royal Charter Bill [HL] EXPLANATORY NOTES Explanatory notes to the Bill, prepared by the Member in charge of the Bill, Lord Lester of Herne Hill, are published separately as HL Bill 34 EN. HL Bill

More information

Climate Change and Sustainable Energy Bill

Climate Change and Sustainable Energy Bill Climate Change and Sustainable Energy Bill CONTENTS Purposes and reports 1 Purposes 2 Annual report on greenhouse gas emissions 3 Fiscal and economic report Microgeneration 4 National targets for microgeneration

More information

Ironstone Quarry Wind Energy Project Environmental Statement

Ironstone Quarry Wind Energy Project Environmental Statement Ironstone Quarry Wind Energy Project Environmental Statement Non Technical Summary April 2011 Introduction Waste Recycling Group (WRG) Ltd is seeking permission to construct and operate a four turbine

More information

SECTION SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM

SECTION SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM SECTION 14-18.5 SPECIAL REQUIREMENTS FOR WIND ENERGY CONVERSION SYSTEM Purpose The purpose of this section is to set forth a process for permitting wind energy facilities with a rated capacity of 100 kw

More information

Shadow Flicker Regulations and Guidance: New England and Beyond

Shadow Flicker Regulations and Guidance: New England and Beyond Shadow Flicker Regulations and Guidance: New England and Beyond Richard Lampeter, INCE Senior Scientist Epsilon Associates, Inc. rlampeter@epsilonassociates.com New England Wind Energy Education Project

More information

Healthy Bees. Protecting and improving the health of honey bees in England and Wales. March 2009

Healthy Bees. Protecting and improving the health of honey bees in England and Wales. March 2009 www.defra.gov.uk www.wales.gov.uk Healthy Bees Protecting and improving the health of honey bees in England and Wales March 2009 Department for Environment, Food and Rural Affairs Nobel House 17 Smith

More information

ECMC Annual Network meeting

ECMC Annual Network meeting ECMC Annual Network meeting May 2017 Dr Kirsty Wydenbach Senior Clinical Assessor / CTU Deputy Unit Manager MHRA approach to assessing early phase cancer study protocols 2 in prinicpal no different to

More information

Application No: Location: 4 John Ball Walk, Colchester, CO1 1YE. Scale (approx): 1:1250

Application No: Location: 4 John Ball Walk, Colchester, CO1 1YE. Scale (approx): 1:1250 Application No: 146455 Location: 4 John Ball Walk, Colchester, CO1 1YE Scale (approx): 1:1250 The Ordnance Survey map data included within this publication is provided by Colchester Borough Council of

More information

Scottish Government Consultation on Permitted Development Rights for Microgeneration. Response for WWF Scotland

Scottish Government Consultation on Permitted Development Rights for Microgeneration. Response for WWF Scotland Scottish Government Consultation on Permitted Development Rights for Microgeneration Response for WWF Scotland WWF and Homes WWF has extensive experience in the housing sector, first focusing on new homes

More information

CHAPTER 8 Energy Efficiency, and Renewable Energy. Kildare County Development Plan , Volume 1

CHAPTER 8 Energy Efficiency, and Renewable Energy. Kildare County Development Plan , Volume 1 Chapter 6 Rural Housing Strategy CHAPTER 8 Energy Efficiency, and Renewable Energy 157 8 ENERGY EFFICIENCY AND RENEWABLE ENERGY 8.1 Background The development of renewable energy sources is a priority

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

Welcome. Welcome to our Open House for the. Kent Hills Wind Farm Expansion

Welcome. Welcome to our Open House for the. Kent Hills Wind Farm Expansion Welcome Welcome to our Open House for the Kent Hills Wind Farm Expansion Please visit our displays providing information on this proposed expansion to New Brunswick s first wind farm. We have staff available

More information

Presented to Parliament by the Secretary of State for Communities and Local Government by Command of Her Majesty. October 2016 CM 9345

Presented to Parliament by the Secretary of State for Communities and Local Government by Command of Her Majesty. October 2016 CM 9345 Government Response to the Communities and Local Government Select Committee report: Government Interventions: the use of Commissioners in Rotherham Metropolitan Borough Council and the London Borough

More information

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob,

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob, William Cundiff From: Sent: To: Cc: Subject: Attachments: neexpansion@aol.com Tuesday, September 28, 2010 12:10 PM wcundiff@douglasma.org szisk@douglasma.org; pbrown@brown-brown-pc.com; info@americanprowind.com;

More information

5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES

5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES WIND ENERGY CONVERSION FACILITIES BYLAW TOWN OF CHESTER Adopted at November 13, 2006 Special Town Meeting Approved by Attorney General on March 27, 2007 5.6- LAND-BASED WIND ENERGY CONVERSION FACILITIES

More information

solar wind hydro biomass Trusted project delivery and aftercare for kW turbines

solar wind hydro biomass Trusted project delivery and aftercare for kW turbines solar wind hydro biomass Trusted project delivery and aftercare for 50-500kW turbines The Renewable Energy Association Installer of the Year 2012 Trusted expertise Dulas staff were very helpful and provided

More information

Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010

Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010 Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010 Objectives of Open House: Introduce Wainfleet Wind Energy Inc. and IPC Energy. Present an overview of Wainfleet Wind

More information

ATLANTIC ARRAY OFFSHORE WINDFARM INITIAL CONSULTATION AVIATION INTERESTS

ATLANTIC ARRAY OFFSHORE WINDFARM INITIAL CONSULTATION AVIATION INTERESTS ATLANTIC ARRAY OFFSHORE WINDFARM AVIATION INTERESTS Document Information Document title Author Produced by Atlantic Array Offshore Windfarm Initial Consultation Andrew Radforth, Cyrrus Limited Cyrrus Ltd

More information

Code of practice on disciplinary and grievance procedures. Code of Practice 1

Code of practice on disciplinary and grievance procedures. Code of Practice 1 Code of practice on disciplinary and grievance procedures Code of Practice 1 Published by TSO (The Stationery Office), part of Williams Lea Tag, and available from: Online www.tsoshop.co.uk Mail, Telephone,

More information

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS 1.0 INTRODUCTION This is prepared for the Jericho Rise Wind Farm (hereafter, the Project ) pursuant to the New York State Environmental Quality Review Act (SEQRA) and its implementing regulations, 6 NYCRR

More information

National Physical Laboratory Hampton Road Teddington Middlesex United Kingdom TW11 0LW

National Physical Laboratory Hampton Road Teddington Middlesex United Kingdom TW11 0LW NPL REPORT DEPC MPE 007 Methodology for determining the resistance of welded corrosion resistant alloys to stress corrosion using the four-point bend method A Turnbull and W Nimmo NOT RESTRICTED NOVEMBER

More information

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 LOCAL LAW FILING NEW YORK STATE DEPARTMENT OF STATE 41 State Street, Albany NY 12231 Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 A Local Law entitled Non-Commercial Wind Power Facilities Law

More information

Government s Response to the Transport, Local Government and the Regions Committee Report: The New Towns: Their Problems and Future

Government s Response to the Transport, Local Government and the Regions Committee Report: The New Towns: Their Problems and Future Government s Response to the Transport, Local Government and the Regions Committee Report: The New Towns: Their Problems and Future Cm 5685 5.00 Crown Copyright 2002 The text in this document (excluding

More information

Biodiversity Offsetting Pilots

Biodiversity Offsetting Pilots www.defra.gov.uk Biodiversity Offsetting Pilots Guidance for developers March 2012 Crown copyright 2012 You may re-use this information (not including logos) free of charge in any format or medium, under

More information

Planning Policy Guidance 13: Transport

Planning Policy Guidance 13: Transport Planning Policy Guidance 13: Transport On 5th May 2006 the responsibilities of the Office of the Deputy Prime Minister (ODPM) transferred to the Department for Communities and Local Government. Department

More information

Kentish Flats Offshore Wind Farm

Kentish Flats Offshore Wind Farm Kentish Flats Offshore Wind Farm A pure spot on the Map of the World Kentish Flats Offshore Wind Farm features 30 wind-powered turbines each with a nominal rated capacity of 3 MW making a net capacity

More information

Proposed Revisions to. Wind Energy Development Guidelines Targeted Review in relation to Noise, Proximity and Shadow Flicker December 11 th 2013

Proposed Revisions to. Wind Energy Development Guidelines Targeted Review in relation to Noise, Proximity and Shadow Flicker December 11 th 2013 Proposed Revisions to Wind Energy Development Guidelines 2006 Targeted Review in relation to Noise, Proximity and Shadow Flicker December 11 th 2013 1 Contents Page Introduction 3 Revision to Noise sections

More information

Wind Energy Ordinances

Wind Energy Ordinances INFORMATION GUIDE: Wind Energy Ordinances Wind turbines are multiplying across the U.S., and most are installed in rural areas overlooking crops, cattle, timber, and lakes. Rural communities have experienced

More information

WITHERNWICK WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY S T E P H E N S O N H A L L I D A Y

WITHERNWICK WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY S T E P H E N S O N H A L L I D A Y S T E P H E N S O N H A L L I D A Y ENVIRONMENTAL PLANNING - LANDSCAPE ARCHITECTURE WITHERNWICK WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY MARCH 2007 WITHERNWICK WIND FARM ENVIRONMENTAL STATEMENT

More information

Challenges to Wind Development Review of Representative Wind Projects & Wind Project Siting Concerns

Challenges to Wind Development Review of Representative Wind Projects & Wind Project Siting Concerns Challenges to Wind Development Review of Representative Wind Projects & Wind Project Siting Concerns Massachusetts Wind Working Group Meeting Wednesday, October 17 th, 2012 Held At Aeronautica Windpower

More information

Treaty Series No. 19 (2014) Exchange of Letters. Paris, 20 April [The Exchange of Letters entered into force on 31 March 2014]

Treaty Series No. 19 (2014) Exchange of Letters. Paris, 20 April [The Exchange of Letters entered into force on 31 March 2014] The Exchange of Letters was previously published as France No. 1 (2011) Cm 8146 Treaty Series No. 19 (2014) Exchange of Letters between the Government of the United Kingdom of Great Britain and Northern

More information

Page 1 of 6 770-54 Wind and solar energy systems. [Added 6-15-2009 by Ord. No. 2009-06] A. Purpose and intent. It is the general purpose and intent of the City to balance the need for clean, renewable

More information

Interim Results: Health and Safety Impacts from Large Scale Wind Turbines

Interim Results: Health and Safety Impacts from Large Scale Wind Turbines Interim Results: Health and Safety Impacts from Large Scale Wind Turbines Submitted by Janis Rod and Wendy Heiger Bernays Presented at the Special PAC Meeting (1pm, ) Scope of our work Objectives Provide

More information

18/00368/FUL 32 PARK GARDENS, HAWKWELL, SS5 4HE PROPOSED REAR EXTENSION AND ROOF ALTERATIONS INCLUDING THE CREATION OF AN EXTENDED FRONT DORMER

18/00368/FUL 32 PARK GARDENS, HAWKWELL, SS5 4HE PROPOSED REAR EXTENSION AND ROOF ALTERATIONS INCLUDING THE CREATION OF AN EXTENDED FRONT DORMER 18/00368/FUL 32 PARK GARDENS, HAWKWELL, SS5 4HE PROPOSED REAR EXTENSION AND ROOF ALTERATIONS INCLUDING THE CREATION OF AN EXTENDED FRONT DORMER APPLICANT: ZONING: PARISH: WARD: MR DANIEL SMITH RESIDENTIAL

More information

Proposed Blackhillock Substation Expansion. Public Exhibition

Proposed Blackhillock Substation Expansion. Public Exhibition Proposed Blackhillock Substation Expansion Public Exhibition 9 February 2012 Blackhillock Substation Expansion: Pre Application Consultation The proposals are for the redevelopment of the existing substation

More information

Cheshire, MA SMALL WIND ENERGY SYSTEMS 12.0 SMALL WIND ENERGY SYSTEMS

Cheshire, MA SMALL WIND ENERGY SYSTEMS 12.0 SMALL WIND ENERGY SYSTEMS 12.0 12.1 Purpose The purpose of this section is to provide a permitting process for small wind energy systems (SWES) for individual homeowners so that they may be utilized in a cost-effective, efficient,

More information

Chapter 750 WIND POWER GENERATION FACILITIES

Chapter 750 WIND POWER GENERATION FACILITIES Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements

More information

Integrating applied ecology & planning policy: the case of micro-turbines & wildlife conservation. Kirsty Park, University of Stirling

Integrating applied ecology & planning policy: the case of micro-turbines & wildlife conservation. Kirsty Park, University of Stirling Integrating applied ecology & planning policy: the case of micro-turbines & wildlife conservation Kirsty Park, University of Stirling Application of Ecology Requires collaboration between scientists, policy

More information

WIND ENERGY CONVERSION SYSTEMS

WIND ENERGY CONVERSION SYSTEMS CHAPTER 159 WIND ENERGY CONVERSION SYSTEMS 159.01 Purpose and Intent 159.05 Location 159.02 Definitions 159.06 Design and Technical Standards 159.03 General Regulations 159.07 Abandonment and Removal Procedure

More information

IECRE OPERATIONAL DOCUMENT

IECRE OPERATIONAL DOCUMENT IECRE OD-551-16 Edition 1.0 2017-11-07 IECRE OPERATIONAL DOCUMENT IEC System for Certification to Standards relating to Equipment for use in Renewable Energy applications (IECRE System) Assessment of RETLs

More information

Circular No: 07/12. Welsh Government. Guidance. The Town and Country Planning (Notification) (Wales) Direction 2012

Circular No: 07/12. Welsh Government. Guidance. The Town and Country Planning (Notification) (Wales) Direction 2012 Circular No: 07/12 Welsh Government Guidance The Town and Country Planning (Notification) (Wales) Direction 2012 Date of issue: 30 July 2012 The Town and Country Planning (Notification) (Wales) Direction

More information