TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada

Size: px
Start display at page:

Download "TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada"

Transcription

1 TURNER VALLEY GAS PLANT SITE PROTECTION AND REMEDIATION Mike McCrank, P.Eng. Project Engineer, Stantec Consulting Ltd., Calgary, Alberta, Canada INTRODUCTION The Historic Turner Valley Gas Plant is located on the north bank of the Sheep River approximately 60 km southwest of Calgary, Alberta. The facility was used for petroleum production and refining from approximately 1914 to 1985 after which it was decommissioned. The plant became a historic site in 1989 and a national historic site in Independent environmental studies of the gas plant site identified the following four major contaminants: asbestos & biohazards, mercury, sulphur, and hydrocarbons. Prior to the commencement of this project, all of the contaminants had been remediated or safely managed, with the exception of the hydrocarbons. The objective of this project was to specifically address the potential migration of hydrocarbons from the gas plant site into the adjacent Sheep River. Figure 1. Turner Valley Gas Plant (photo circa 1914). Stantec Consulting Ltd. (Stantec) was the lead consultant of a design team that produced a conceptual design for the site protection and remediation of the hydrocarbon contaminated groundwater at the Turner Valley Gas Plant. The design team included several sub-consultants that provided specialized engineering design services for the different components for the project. The sub-consultants and their roles included:

2 MPE Engineering Ltd. - Design of erosion protection works and river isolation works, construction supervision of erosion protection works. Thurber Engineering Ltd. - Geotechnical design of slurry wall, QA/QC monitoring of slurry wall and clay berm construction. Waterline Resources Inc. - Hydrogeological study of the project area. Key to the project design was a plan to isolate and remediate the hydrocarbon contaminated groundwater prior to any release into the adjacent Sheep River. The design includes: a geotechnically designed bentonite slurry wall (cut-off wall) to isolate and divert the groundwater of the lower terrace; a weeping tile system to divert the groundwater of the middle and upper terraces; an erosion protection system to protect the site from periodic flooding events on the Sheep River; and a treatment corridor to remediate hydrocarbon impacts on the groundwater prior to its release into the river. The conceptual design was approved by Alberta Infrastructure and Transportation. Stantec was then retained to facilitate the completion of remedial work at the Gas Plant. Stantec s role was to prepare a scope of work, prepare contract specifications, aid in tendering the construction contract, provide consulting services during execution of the contract, inspect work completed and collect and analyze samples where required. Tendering of the construction contract was conducted on a public basis. Alberta Infrastructure awarded the contract to the successful bidder, Quantum Remediation, A Division of Quantum Murray LP. INNOVATION The intent of this project was to design a system which would contain and remediate hydrocarbon impacts in the groundwater at the Turner Valley Gas Plant. The concept of contaminant containment is not new or innovative, and neither is the concept of remediation. However, designing a containment and remediation system, especially for such a large area, is innovative and requires many innovative techniques and ideas. Some of the innovative concepts that were utilized in this project included the following: Develop a treatment system to remediate multiple hydrocarbon contaminants, including: BTEX, PAH s and F1 to F4 Hydrocarbons. Passive flow, the treatment corridor is gravity fed and under normal operating conditions, requires no energy to move water through the system. The system can operate in times of flood events on the adjacent Sheep River, despite negative head pressures. Automated treatment system components notify operators remotely of component failures. Expandable system, the treatment corridor was designed to accommodate new technologies as they may be developed. Monitoring wells for environmental sampling double as performance monitors for each component of the system.

3 BTEX F1 & F2 PAHs F1 & F2 BTEX & F1 PAHs Figure 2. Theory of design components. DESIGN Major components of the work include the design of a Containment System, a Treatment System, Erosion Protection Works and a Monitoring Network. Containment Structure Containment of hydrocarbons present in the soil and groundwater on site was accomplished through the construction of an impermeable bentonite slurry wall surrounding the eastern (riverbank) portion of the site. The wall averts groundwater from discharging into the adjacent Sheep River. The bentonite wall extends from the southernmost edge of the site along the river to the northern boundary and then to the west to tie into the slope of the middle terrace. The alignment of the bentonite slurry wall is dictated by the placement of the erosion protection works installed to control flooding and erosion from the river. The wall was aligned to be directly beneath the erosion protection berm and has been placed as close to the river as possible. The bentonite slurry wall generally consists of a trench excavated from ground surface to bedrock that is backfilled with a designed mixture of soils and bentonite. The slurry wall is approximately 1 m wide and depth varies depending on the depth of bedrock (generally between 2 m and 5 m below ground surface). Backfill material is designed such that the completed wall has a permeability no greater than 1 x 10-6 cm/s. The upper edge of the slurry wall ties into the clay erosion protection berm.

4 Figure 3. Typical cross section of the slurry wall and erosion protection works. Although the containment wall restricts water from passing through it s alignment, the groundwater would flow around or over a containment structure without a discharge point. By placing a discharge point in the lowest corner of the containment structure (northeast corner) the groundwater flow is controlled to pass through a treatment system where it is remediated prior to release into the Sheep River. In addition to the cut-off wall, a weeping tile system (perforated PVC pipe) extends west along the northern boundary of the site to collect groundwater from the upper terrace and drain into the containment area of the cut-off wall. The linear length of the weeping tile system is 400 m, including approximately 250 m that was placed below the Town of Turner Valley s existing sanitary sewer line. Treatment System The treatment system designed to address the hydrocarbons and PAHs found in the soils and groundwater is a subsurface corridor through which groundwater must flow before leaving the site. In conjunction with the cut-off wall, overall contaminant treatment system forms a funnel and gate system whereby the contaminated groundwater is directed through a single point release from the site. A treatment corridor was constructed in the northeast corner of the site (most downgradient corner) through which groundwater passively flows, is treated to meet the Canadian Water Quality Guidelines for the Protection of Aquatic Life (CCME 2001, freshwater), and is released at a single point into the Sheep River. The treatment corridor generally consists of a subsurface concrete vault into which treatment media and systems were installed. Groundwater enters the vault through the western (open) end, travels through the vault across the treatment components, and is discharged through a pipe at the eastern end of the system. Three main treatment components were installed within the treatment corridor, an oil / water separator (or skimmer), an air sparging unit, and activated carbon cells. Through the use of these three treatment components the discharge criteria will be met prior to release of groundwater into the adjacent Sheep River. The oil water separator is designed as a vertically orientated T-joint constructed of 300mm pipe in a manhole, which confines all free phase hydrocarbons to the upgradient side of the separator. In conjunction with the oil / water separator the free phase hydrocarbons isolated to the upgradient side of the separator are collected into an

5 independently floating passive hydrocarbon skimmer. The floating skimmer can contain 2 liters of hydrocarbon and can be easily replaced and / or drained during routine inspection / operation of the system. Figure 4. Conceptual model of treatment corridor. The sparging unit consists of a 5 hp blower motor attached to a series of perforated pipes located across the floor of the vault, downstream of the oil / water separator. This provides a curtain of air through which the groundwater will flow. Aeration of the water aids in volatilizing the dissolved light-end hydrocarbons (such as BTEX, F1 and F2) as well as increasing the dissolved oxygen content. The increase in dissolved oxygen serves to facilitate microbial growth to break down any remaining dissolved hydrocarbons. Downstream from the aeration curtain, sheets of geotextile were loosely hung to provide a media on which a microbial community is anticipated to develop. The effectiveness of the microbial community with respect to hydrocarbon degradation is not concretely known, nor relied upon, however some further hydrocarbon degradation is expected. Pelletized activated carbon serves as the final treatment for any residual dissolved hydrocarbons and dissolved PAHs. Water passing through the vault is forced (using only the natural gravity driven head available) through activated carbon cells. Over time the activated carbon will become less effective as it s available bonding sites become occupied with PAHs and other materials. A series of two cells were installed in order to

6 provide redundancy in the treatment system. Only one cell will be utilized at any given time as the limited head available precludes passing water through both cells simultaneously. Following the activated carbon, groundwater is then suitable for discharge to the Sheep River. The discharge level of the water will be controlled in order to convey greater water level control to the upgradient treatment components. Water will normally be passively discharged (gravity flow) into the adjacent river. However, in order to prevent backflow through the system in times of flood in the Sheep River, a one-way valve was installed in the discharge pipe. During flood conditions, when this one-way valve is closed, a water level activated pump will maintain the water levels at the discharge point in the treatment corridor. Utilizing this discharge control, groundwater treatment can continue even during flood conditions. In conjunction with the discharge control, a knife valve was installed such that the entire system can be stopped manually and all discharge to the river prevented. The pump that controls the water level in the discharge system can also be redirected to load tanks or trucks rather than pumping to the river. Guidelines to be met for the release of groundwater into the adjacent Sheep River are the CCME guidelines for the protection of freshwater aquatic life. Discharge water quality is monitored monthly for these specific parameters to ensure compliance with the discharge criteria. Erosion Protection Works The construction of the erosion protection works, as designed by MPE Engineering Ltd. (MPE), consists of a compacted clay berm and rip rap bank protection. The berm and riprap bank protection extends the entire length of the property boundary along the edge of the Sheep River. The berm height was designed to provide a minimum 0.5 meters of freeboard above the water levels experienced during the June 2005 flood event. The portion of the berm above the original river bank elevation was constructed using compacted impervious clay material. Average height of the berm varies from 1.0 m to 2.5 m. Average channel velocities (during a flood event) vary from 2.5 m/s to 4.5 m/s, therefore the rock riprap placed was blasted limestone. The average height of the riprap is approximately 5.5 m. The riprap extends from the top of the berm and is keyed into the underlying bedrock. Monitoring Network A monitoring network of shallow groundwater wells is established along the cut-off wall, the weeping tile system and within the treatment corridor.

7 A total of 13 monitoring wells were installed along the alignment of the cut-off wall. Five pairs of wells were installed along the cut-off wall of the lower terrace and three wells were installed along the weeping tile of the upper terrace. One well in the upper terrace could not be paired due to the density and location of utilities in the area. One well from each pair is located just inside of the cut-off wall and the other is on the riverside of the cut-off wall. Three of the paired monitoring wells along the cut-off wall are monitored for water level elevations on an ongoing basis through the use of pressure transducers installed in each well. A difference in water levels between each pair of wells will establish the effectiveness of the cut-off wall in isolating the groundwater from the river. A total of four monitoring wells were installed along the walls of the treatment corridor. One is situated in the oil / water separator, and one downstream of each of the treatment systems (oil / water separator, air sparger system and the activated carbon cells). This arrangement allows for the collection of detailed operational information of the treatment system to facilitate fine-tuning of the treatment as well as to confirm that discharge criteria is being met. Chemical parameters are monitored in all of the wells as part of the containment system monitoring. Samples collected will be analyzed to detection levels sufficiently low for comparison against the applicable guidelines for the protection of freshwater aquatic life (CCME 2001). Monitoring wells located on the river-side of the cut-off wall are available for risk management of the soils and groundwater that will remain outside of the containment structure. DEGREE OF DIFFICULTY Many design and construction challenges were encountered while working in Hell s Half Acre. The history of the site, both natural and anthropogenic, provided numerous issues to contend with throughout the life of the project. The natural site conditions found on-site that influenced the overall design of the project included the following: Natural Gas Seeps and Flares in the area provide a continual source of contaminants and are an environmental health and safety concern to the workers on site. Multiple River Terraces and associated groundwater regimes resulted in the requirement for the weeping tile system and an extension to the slurry wall.; The proximity to the Sheep River and the associated Spring flooding events that have historically flooded the site; Coarse granular material, causing difficulties with the trenching operations and cut-off wall construction; Weather, the majority of the project operations were conducted during the winter months;

8 Ice flows resulting from southwest Alberta s constant freezing and thawing temperature patterns were constantly threatening the river isolation works. The anthropogenic history of the site also caused numerous issues with the design and construction of the project, including: Burried Debris and Pipelines, unknown construction history and a lack of asbuilt drawings resulted in many finds. Active Pipelines and Utilities in the area meant many line locates, crossing agreements and safe work practices. National Historic Site Designation meant all structures required protection as much as possible. Multiple Contaminants required constant monitoring of environment, health and safety issues. In addition to the complications listed above, the scale of the project and the relatively short time frame required to finish the construction meant that the Project Team had to work together to ensure the project could be completed to the project specifications. Approximately 60,000 tonnes of material were imported to the site. Construction began in early September, 2006 and Substantial Completion was attained in May, MANAGEMENT OF RISK Contaminated Soils Outside of Containment Area Alignment of the containment wall was located as close to the river as possible, however there were impacted soils by the former use of the site that remain outside of the containment structure. During excavation associated with the erosion protection works all soils handled were screened, analytically and aesthetically, during handling. All impacted soils were segregated and stockpiled within the contained area. Potentially impacted soils remaining outside of the containment structure are to be risk managed as a whole under a separate scope of work. The characteristics and extent of the soil and groundwater impacts were documented and assessed during the construction activities. Using this data as well as data collected from the adjacent Sheep River, a risk management plan is currently being developed such that residual impacts will be managed. River Protection During Construction Works relating to construction of the cut-off wall were at no time within the banks of the river. However, during construction of the cut-off wall significant amounts of bentonite mud and slurry were present on site adjacent to the Sheep River. Accidental releases into the river were prevented through the construction and maintenance of the river isolation works, established prior to the start of construction of the cut-off wall and maintained as necessary throughout the life of the project. This ensured that, in case of a spill or failure,

9 all sediment would be isolated from the river, and could be remediated before it could impact the adjacent river. Additional erosion control measures were implemented for any stockpiled soil located on site. Primarily, all spoil material was placed inside of the cut-off wall and drainage was managed to remain within the containment area. Results The treatment system at the Turner Valley Gas Plant has only been in operation for a few months, however, preliminary results are showing that the containment system and the treatment system are operating as expected. Groundwater levels inside of the containment system are elevated above those outside of the cut-off wall, indicating that the groundwater is effectively being diverted through the funnel and gate design. Also, environmental analytical trends are indicating that the treatment system is effectively removing hydrocarbon contaminants from the groundwater prior to release to the Sheep River. As monitoring continues over the next few years, the treatment system will be adjusted so that it can perform at optimal conditions.

In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure

In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure In-Situ Containment and Treatment of a Free Phase Hydrocarbon Plume beneath Plant Infrastructure M. Brewster 1, S. Penny 1, B. Odell 1 and T. Jorgensen-Nelson 2 Abstract A very shallow (1 2 m deep) hydrocarbon

More information

2010 Symposium ~ IMWA 2010 ~ Mid-Conference Excursion 5 Belinda Campbell, David Forrester. Sydney Tar Ponds and Collieries

2010 Symposium ~ IMWA 2010 ~ Mid-Conference Excursion 5 Belinda Campbell, David Forrester. Sydney Tar Ponds and Collieries ~ IMWA 2010 ~ 2010 Symposium Conference Theme: Mine Water & Innovative Thinking Mid-Conference Excursion 5 Belinda Campbell, David Forrester Sydney Tar Ponds and Collieries International Mine Water Association

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park

Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park Feasibility Study for Groundwater Availability for Spring Creek Creation at Squalicum Creek Park Prepared for: City of Bellingham Public Works Department Environmental Resource Division 210 Lottie St.

More information

INVESTIGATION AND REMEDIATION STRATAGIES FOR A DNAPL IMPACTED SITE IN STRATIFIED SOILS. Christopher Reiss

INVESTIGATION AND REMEDIATION STRATAGIES FOR A DNAPL IMPACTED SITE IN STRATIFIED SOILS. Christopher Reiss INVESTIGATION AND REMEDIATION STRATAGIES FOR A DNAPL IMPACTED SITE IN STRATIFIED SOILS Christopher Reiss Overview DNAPL Intro Case Study: DNAPL Site History Field Investigation Program Pilot Testing program

More information

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location Maryland Department of the Environment Site Location FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) This 2.4581-acres site (Site) consists of four parcels of

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

SOIL REMEDIATION OF A FORMER POWER PLANT SITE IN TULITA, NORTHWEST TERRITORIES

SOIL REMEDIATION OF A FORMER POWER PLANT SITE IN TULITA, NORTHWEST TERRITORIES SOIL REMEDIATION OF A FORMER POWER PLANT SITE IN TULITA, NORTHWEST TERRITORIES Yvan Pouliot 1, Nicolas Moreau 2 and Eric Thomassin-Lacroix 1 1 Biogenie S.R.D.C. Inc., Northern Office 2 Biogenie S.R.D.C.

More information

Christopher Gaule 1, Kenneth J. Goldstein 2,and Curtis A. Heckelman 3. Abstract

Christopher Gaule 1, Kenneth J. Goldstein 2,and Curtis A. Heckelman 3. Abstract Dual Reactive Barrier Walls for the Remediation of CHC Contamination, Watervliet Arsenal, New York: Design and Installation of an Innovative Technology Abstract Christopher Gaule 1, Kenneth J. Goldstein

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

Sydney Tar Ponds & Coke Ovens Remediation Project

Sydney Tar Ponds & Coke Ovens Remediation Project Sydney Tar Ponds & Coke Ovens Remediation Project Roger Larkin, P.Eng. Project Director October 15-17, 17, 2008 The Fairmont Banff Springs Banff, Alberta BANFF SYDNEY SYDNEY Cape Breton Island: One of

More information

Outfall at Lagoon between Lake of the Isles and Lake Calhoun

Outfall at Lagoon between Lake of the Isles and Lake Calhoun Outfall at Lagoon between Lake of the Isles and Lake Calhoun Prepared for City of Minneapolis April 17, 2013 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601

More information

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0 PROTOCOL 15 FOR CONTAMINATED SITES Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil Version 1.0 Prepared pursuant to Section 64 of the Environmental Management

More information

Suggested Stormwater Management Practices For Individual House Lots

Suggested Stormwater Management Practices For Individual House Lots Suggested Stormwater Management Practices For Individual House Lots These practices are necessary to satisfy the water quantity and water quality criteria of the Rappahannock Stormwater Ordinance. These

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Niagara Falls Storage Site Safety Measures During Remediation

Niagara Falls Storage Site Safety Measures During Remediation Niagara Falls Storage Site Safety Measures During Remediation On-Site Worker Protection Community and Environmental Protection Transportation and Disposal Safety Fully enclosed Retrieval Facility Regular

More information

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and

More information

SECTION TRENCHING

SECTION TRENCHING SECTION 31 23 17 TRENCHING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating trenches for utilities and utility structures. 2. Bedding. 3. Backfilling and compacting to subgrade elevations.

More information

FINAL REPORT COME BY CHANCE SECURE LANDFILL GROUNDWATER DRAINAGE SYSTEM. Submitted to:

FINAL REPORT COME BY CHANCE SECURE LANDFILL GROUNDWATER DRAINAGE SYSTEM. Submitted to: FINAL REPORT COME BY CHANCE SECURE LANDFILL GROUNDWATER DRAINAGE SYSTEM Submitted to: Department of Environment and Conservation 4 th Floor West Block, Confederation Building P.O. Box 8700 St. John s,

More information

Appendix 4. Soil Management Plan

Appendix 4. Soil Management Plan Appendix 4 Soil Management Plan Soil Management Plan This Soil Management Plan (SMP) has been developed for the Giscome Quarry and Lime Plant Project. The SMP is a living document and will be updated as

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES MINNESOTA WETLAND RESTORATION GUIDE BLOCKING AND FILLING SURFACE DRAINAGE DITCHES TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-1 Publication Date: 10/14/2015 Table of Contents Introduction Application

More information

SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B

SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B SCHEDULE 3.1 DETAILED CONSTRUCTION PLAN Part B: Narrative Area B SCHEDULE 3-1 DETAILED CONSTRUCTION PLAN Part B Narrative: Work Area B We will carry out the excavation for Work Area B as per Company s

More information

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes. 1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined

More information

DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES

DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES Todd White, M.Sc., P.Geol. and Douglas A. Sweeney, M.Sc., P.Eng. SEACOR Environmental Inc. INTRODUCTION

More information

Wilmette - Background

Wilmette - Background Reducing Basement Backups through Intergovernmental Cooperation and Design-Build Presented By Michael N. Young, P.E. Brigitte Ann Berger, P.E. Wilmette - Background North Shore Suburb of Chicago 5 Square

More information

Bioremediation System Integration to Contain/Treat a Known Perchlorate Source Area

Bioremediation System Integration to Contain/Treat a Known Perchlorate Source Area Paper L-11, in: Bruce M. Sass (Conference Chair), Remediation of Chlorinated and Recalcitrant Compounds 2006. Proceedings of the Fifth International Conference on Remediation of Chlorinated and Recalcitrant

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

Design and Installation of a Permeable Treatment Wall at the DOE West Valley Site Lisa Durham Argonne National Laboratory

Design and Installation of a Permeable Treatment Wall at the DOE West Valley Site Lisa Durham Argonne National Laboratory Design and Installation of a Permeable Treatment Wall at the DOE West Valley Site Lisa Durham Argonne National Laboratory DOE West Valley Site IDN and ENVIRONET Training Course Western New York Nuclear

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

Memorandum For: Ms. Lee Ann Smith, Chair, POWER Action Group Protecting Our Water and Environmental Resources

Memorandum For: Ms. Lee Ann Smith, Chair, POWER Action Group Protecting Our Water and Environmental Resources Memorandum For: Ms. Lee Ann Smith, Chair, POWER Action Group Protecting Our Water and Environmental Resources From: FSA Date: June 20, 2018 Frank Anastasi, P.G., Community Technical Advisor (NC LG-2459;

More information

Case Study: Overcoming challenges and obstacles to remediate a former de-waxing facility in Richmond, BC

Case Study: Overcoming challenges and obstacles to remediate a former de-waxing facility in Richmond, BC Tyler Joyce, C. Tech. Stantec Kate Schendel, M.Sc., P.Ag. Vancouver Fraser Port Authority Case Study: Overcoming challenges and obstacles to remediate a former de-waxing facility in Richmond, BC Agenda

More information

RISK MANAGEMENT OF A FORMER SALT STORAGE YARD

RISK MANAGEMENT OF A FORMER SALT STORAGE YARD RISK MANAGEMENT OF A FORMER SALT STORAGE YARD Robert S. Nichols, B.Sc., P.Eng. and Trent Parks, Ph.D., P.Chem. Abstract A risk management plan was developed by Matrix Solutions Inc. (Matrix) and implemented

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Appendix 14-I Description of Stream Crossing for Electrical Interconnect Appendix 14-I Description of Stream Crossing for Electrical Interconnect 14.0 Ecology Appendix 14-I CPV Valley Energy Project Description of Stream Crossing for Electrical Interconnect The CPV Valley Energy

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Preliminary Design Report: Prices Subdivision Drainage Improvements & Wastewater Servicing

Preliminary Design Report: Prices Subdivision Drainage Improvements & Wastewater Servicing B.5.1 Preliminary Design Report: Prices Subdivision Drainage Improvements & Wastewater Servicing --Greenland Consulting Engineers-- 1 The Study Location (Prices Subdivision) consists of the lots fronting

More information

AERATED POND REVIEW CHECKLIST

AERATED POND REVIEW CHECKLIST Water Quality AERATED POND REVIEW CHECKLIST Wastewater Technical Review and Guidance FACILITY NAME Water/Wastewater/#5.04, May 2001 DATE CONSULTING ENGINEER SITE INSPECTION (DATE & INSPECTOR) PLANNING

More information

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE

11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11 HYDROLOGY, HYDROGEOLOGY AND DRAINAGE 11.1 introduction 11.1.1 The objective of this section and the statements presented is to assess the existing hydrological and hydrogeological conditions to understand

More information

Permeable Pavement Facilities and Surfaces

Permeable Pavement Facilities and Surfaces Permeable Pavement Facilities and Surfaces This checklist is intended to highlight items critical to the performance of permeable pavement facilities and surfaces that need to be addressed in the design

More information

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA)

#47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) #47 CASE STUDY INSTALLATION OF A SOIL-BENTONITE CUTOFF WALL THROUGH AN ABANDONED COAL MINE (GROVE CITY, PA) by Michael J. Carey Michael J. Fisher Steven R. Day Presented at: International Containment Technology

More information

Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging

Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging James J. Serpico (&) Geotechnical Services, Maser Consulting P.A.,

More information

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan EIS Techni cal Support Document 20-12 Magino Project Environmental Impact Statement Technical Support Document 20-12 Rev. No. Revision Date Approved 0 Document issued for EIS Table of Contents SECTION

More information

(this cover page left intentionally blank)

(this cover page left intentionally blank) 4. Siting the Well (this cover page left intentionally blank) 4. Siting the Well Chapter Table of Contents Chapter Table of Contents Chapter Description... 4 Regulatory Requirements Well Siting... 4 Relevant

More information

Conceptual Site Models for Environmental Investigations and Remediation

Conceptual Site Models for Environmental Investigations and Remediation Remediation Technology Symposium (RemTech) 2012 Conceptual Site Models for Environmental Investigations and Remediation October 18, 2012 Tai T. Wong, P.Eng. Authors and Presenter Authors: James Carss,

More information

SECTION SOILS REPORT

SECTION SOILS REPORT SECTION 02300 SOILS REPORT 1. GENERAL: 1.1 All work included under this heading shall be subject to the General Conditions of the entire operation. This Contractor is required to refer especially thereto.

More information

Central Region GeoHazard Assessment H597:02, km Slide May 2011 Site Inspection and Instrumentation Monitoring Report

Central Region GeoHazard Assessment H597:02, km Slide May 2011 Site Inspection and Instrumentation Monitoring Report Alberta Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 July 14, 2011 Mr. Dennis Grace, P.Eng. Construction Engineer Dear Mr. Grace: Central Region GeoHazard Assessment H597:02,

More information

Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California

Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California TECHNICAL MEMORANDUM Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California DATE: April 14, 2004 Pacific Gas and Electric Company (PG&E) is undertaking an expedited

More information

Boise City Public Works General Drainage Plan Review Requirements Checklist

Boise City Public Works General Drainage Plan Review Requirements Checklist Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres

More information

Enhanced Anaerobic Bioremediation Using CAP18 as a Polishing Application for CVOC Impacted Groundwater

Enhanced Anaerobic Bioremediation Using CAP18 as a Polishing Application for CVOC Impacted Groundwater www.burnsmcd.com Author: Presented Date: Walter McClendon, Martha Hildebrandt and John Hesemann, Burns & McDonnell John Shimp, Directorate of Public Works, Fort Riley, Kan. Bradden Bigelow, Environmental

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

Lessons Learned from the Installation and Monitoring of a Permeable Reactive Barrier at the Lake City Army Ammunition Plant, Independence, MO

Lessons Learned from the Installation and Monitoring of a Permeable Reactive Barrier at the Lake City Army Ammunition Plant, Independence, MO Lessons Learned from the Installation and Monitoring of a Permeable Reactive Barrier at the Lake City Army Ammunition Plant, Independence, MO Presented by Kevin Keller, PG, CGWP - Shaw E&I, Inc. Thomas

More information

Intended users: City and County public works Young engineers Developers Public officials and other non-engineers

Intended users: City and County public works Young engineers Developers Public officials and other non-engineers 1 2 3 4 Intended users: City and County public works Young engineers Developers Public officials and other non-engineers The Decision Tree distills information from many manuals and sources into one spot,

More information

Slurry Trench / Diaphragm Walls

Slurry Trench / Diaphragm Walls UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Slurry Trench / Diaphragm Walls CM 420 TEMPORARY

More information

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

Application of Mulch Biowall for Anaerobic Treatment of Perchlorate in Shallow Groundwater

Application of Mulch Biowall for Anaerobic Treatment of Perchlorate in Shallow Groundwater Paper G-04, in: G.B. Wickramanayake and H.V. Rectanus (Chairs), In Situ and On-Site Bioremediation 2009. Tenth International In Situ and On-Site Bioremediation Symposium (Baltimore, MD; May 5 8, 2009).

More information

5.14 CONTAMINATED MATERIALS

5.14 CONTAMINATED MATERIALS 5.14 CONTAMINATED MATERIALS 5.14.1 Introduction Contaminated materials are toxic or potentially harmful substances that may be present in soil, groundwater, and building materials. Contaminated materials

More information

Central Region GeoHazard Assessment Site C8 SH597:02 East of Blackfalds May 2007 Site Assessment and Instrumentation Monitoring Report

Central Region GeoHazard Assessment Site C8 SH597:02 East of Blackfalds May 2007 Site Assessment and Instrumentation Monitoring Report Alberta Infrastructure & Transportation Central Region #401, 4902 51 Street Red Deer, Alberta T4N 6K8 May 18, 2007 Mr. Alain Momedi, P.Eng. Project Engineer Dear Mr. Momedi: Central Region GeoHazard Assessment

More information

C-1. Infiltration System

C-1. Infiltration System C-1. Infiltration System Design Objective An infiltration system captures surface stormwater runoff and allows it to infiltrate into the soil. This SCM is typically the work horse of a runoff volume match

More information

The last update was March 4, 2016.

The last update was March 4, 2016. From: To: Subject: Date: Long Lake Stewardship longlakesudbury@gmail.com LONG LAKE STEWARDSHIP - Gold Mine Site Reclamation Work - Project Update May 29, 2017 6:14:57 PM Hello - Some of you will remember

More information

RAPID INFILTRATION BASINS REVIEW CHECKLIST

RAPID INFILTRATION BASINS REVIEW CHECKLIST Water Quality RAPID INFILTRATION BASINS REVIEW CHECKLIST Wastewater Technical Review and Guidance FACILITY NAME Water/Wastewater/#5.65, May 2001 DATE CONSULTING ENGINEER SITE INSPECTION (DATE & INSPECTOR)

More information

GROUNDWATER MODELING OF A PERMEABLE REACTIVE BARRIER TO ENHANCE SYSTEM PERFORMANCE

GROUNDWATER MODELING OF A PERMEABLE REACTIVE BARRIER TO ENHANCE SYSTEM PERFORMANCE GROUNDWATER MODELING OF A PERMEABLE REACTIVE BARRIER TO ENHANCE SYSTEM PERFORMANCE K.C. Scott, P.G., and D. J. Folkes, P.E. EnviroGroup Limited, 7208 South Tucson Way, Suite 125, Englewood, CO 80112; Phone:

More information

APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES

APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES Mitch Kenaschuk, P.Eng. Peter Olmsted, M.Sc.,P.Eng. October 2004 OUTLINE Introduction Regulatory Framework and Methodology Vapour

More information

Pond Closure - Case Study[TP1]

Pond Closure - Case Study[TP1] 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Pond Closure - Case Study[TP1] By Pedro J Amaya, P.E. (1) (1) Civil Engineering and Geotechnical Engineering

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

WASTE TREATMENT LAGOON

WASTE TREATMENT LAGOON 359-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE STANDARD WASTE TREATMENT LAGOON (No.) CODE 359 DEFINITION A waste treatment impoundment made by constructing an embankment and/or excavating

More information

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES 1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE LATEST EDITION OF THE STANDARD PLANS OF THE CITY OF LA QUINTA, THE LATEST EDITION OF THE STANDARD SPECIFICATIONS

More information

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring 14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring An effective monitoring program provides results to: indicate whether the facility is working as expected and that the assumptions used in the assessment

More information

Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007

Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007 Page 1 of 6 Proceedings of the 10 th Australia New Zealand Conference on Geo-Mechanics, Common Ground Brisbane Australia, October 2007 Vertical groundwater barriers for contaminated site reclamation Christopher

More information

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage

More information

3.7 GROUNDWATER AND SOILS Introduction Environmental Setting Applicable Regulations Impacts and Mitigation Measures

3.7 GROUNDWATER AND SOILS Introduction Environmental Setting Applicable Regulations Impacts and Mitigation Measures . GROUNDWATER AND SOILS 0.. Introduction.. Environmental Setting.. Applicable Regulations.. Impacts and Mitigation Measures... Project Impacts and Mitigation... Proposed Project... Construction Impacts

More information

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES 1 1 1 0 1 0 1 0 1 SECTION 1. STRUCTURAL EXCAVATION FOR STRUCTURES BASED ON DFD MASTER SPECIFICATION DATED /1/1 P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

2.BACKGROUND SITE INFORMATION

2.BACKGROUND SITE INFORMATION 2.BACKGROUND SITE INFORMATION A. Site History The site is located in the south-central portion of Scott County and more specifically in Oneida, Tennessee. In the early 1950s, a cross-tie treatment facility

More information

Category 1 Waste Rock Stockpile Groundwater Containment System

Category 1 Waste Rock Stockpile Groundwater Containment System Memorandum To: Jennifer Saran, Poly Met Mining Inc. Project: 23690862.00-042-008 1.0 Introduction The Co-Lead Agencies have requested a summary of the four containment systems that are planned for the

More information

Steve Mailath, M.Sc., P.Geol. April 10, 2014 WATER NATURAL RESOURCES ENVIRONMENT INFRASTRUCTURE ENERGY

Steve Mailath, M.Sc., P.Geol. April 10, 2014 WATER NATURAL RESOURCES ENVIRONMENT INFRASTRUCTURE ENERGY IN-SITU REMEDIATION OF HYDROCARBON IMPACTED GROUNDWATER IN PERMAFROST TERRAIN AT A REMOTE SITE. TIBBITT TO CONTWOYTO WINTER ROAD, NORTHWEST TERRITORIES Steve Mailath, M.Sc., P.Geol. April 10, 2014 WATER

More information

IN THE MATTER of a CONTRAVENTION. of the OIL AND GAS ACTIVITIES ACT. [SBC 2008] Chapter 36. Before. The BC OIL & GAS COMMISSION. Case File

IN THE MATTER of a CONTRAVENTION. of the OIL AND GAS ACTIVITIES ACT. [SBC 2008] Chapter 36. Before. The BC OIL & GAS COMMISSION. Case File IN THE MATTER of a CONTRAVENTION of the OIL AND GAS ACTIVITIES ACT [SBC 2008] Chapter 36 before The BC OIL & GAS COMMISSION Case File 2017-061 BETWEEN The BC Oil & Gas Commission AND Pavilion Energy Corporation

More information

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR All the documents shown today are in the MN Stormwater Manual on the page titled 2018 Construction Stormwater Permit Public Notice and Public Informational

More information

SECTION RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES

SECTION RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES SECTION.0500 - RISK-BASED ASSESSMENT AND CORRECTIVE ACTION FOR NON-UST PETROLEUM RELEASES 15A NCAC 02L.0501 PURPOSE AND SCOPE (a) The purpose of this Section is to establish procedures for risk-based assessment

More information

SEPA Environmental Checklist Mercer Island Center for the Arts. Attachment F Geotechnical Supplemental Memo

SEPA Environmental Checklist Mercer Island Center for the Arts. Attachment F Geotechnical Supplemental Memo SEPA Environmental Checklist Mercer Island Center for the Arts Attachment F Geotechnical Supplemental Memo January 2017 MEMORANDUM DATE: May 6, 2015 TO: FROM: RE: CC: Katie Oman, Mercer Island Center for

More information

Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A

Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A BF 73649 E/W Bridge Culverts Highway 15 Crossing Astotin Creek Bridge

More information

Construction and Maintenance Challenges with Sudbury s Sewage Rock Tunnel

Construction and Maintenance Challenges with Sudbury s Sewage Rock Tunnel Construction and Maintenance Challenges with Sudbury s Sewage Rock Tunnel Trenchless Technology Road Show 2014 Niagara Falls Robert Langlois, P.Eng Associate/Project Manager TRENCHLESS TECHNOLOGY ROADSHOW

More information

MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018

MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018 MNA CLOSURE STRATEGY AT A REDEVELOPED MGP SITE IN FLORIDA Jacksonville Recycling Facility Former MGP Site in Florida September 2018 Steven R Sagstad and Jeff Manuszak Jacksonville Recycling Site History

More information

VISUAL SITE INSPECTION REPORT

VISUAL SITE INSPECTION REPORT VISUAL SITE INSPECTION REPORT - 2016 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00318 DECEMBER 20, 2016 PREPARED

More information

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving. SECTION 312000 - EARTH MOVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Excavating and filling for rough grading the Site. 2. Preparing subgrades for walks, curbs, pavements, and turf and grasses.

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

In-Situ Remediation of Brine Impacted Soils and Groundwater Using Hydraulic Fracturing, Desalinization and Recharge Wells

In-Situ Remediation of Brine Impacted Soils and Groundwater Using Hydraulic Fracturing, Desalinization and Recharge Wells In-Situ Remediation of Brine Impacted Soils and Groundwater Using Hydraulic Fracturing, Desalinization and Recharge Wells Craig Robertson, M.Sc., P.Geol. 1, Ion Ratiu, M.Sc. 2, and Gordon H. Bures, M.Eng.,

More information

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station Annual Inspection Report CCR Surface Impoundment MidAmerican Energy Company, Louisa Generating Station Final January 15, 2016 Annual Inspection Report CCR Surface Impoundment Prepared for MidAmerican Energy

More information

patersongroup Phase I - Environmental Site Assessment Vacant Land, Strandherd Drive at Kennevale Drive Ottawa, Ontario Prepared For Regional Group

patersongroup Phase I - Environmental Site Assessment Vacant Land, Strandherd Drive at Kennevale Drive Ottawa, Ontario Prepared For Regional Group Geotechnical Engineering patersongroup Environmental Engineering Hydrogeology Geological Engineering Materials Testing Building Science Vacant Land, Strandherd Drive at Kennevale Drive Ottawa, Ontario

More information

EFFECTIVE AND EASILY MAINTAINED TREATMENT SOLUTIONS

EFFECTIVE AND EASILY MAINTAINED TREATMENT SOLUTIONS EFFECTIVE AND EASILY MAINTAINED TREATMENT SOLUTIONS When it rains, surface runoff carries pollutants, suspended solids and hydrocarbons. Floating debris is swept through collection systems in subsurface

More information

Geotechnical, Hydrological and Environmental Assessment

Geotechnical, Hydrological and Environmental Assessment Geotechnical, Hydrological and Environmental Assessment Presented by Moustafa Gouda, P.E., D. GE, F.ACSE Director of Geotechnical & Environmental Engineering Services Maser Consulting P.A. Planning Board

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

CCP Annual Inspection Report

CCP Annual Inspection Report CCP Annual Inspection Report Brickhaven No. 2 Mine Tract A Structural Fill DWM Permit 1910, DEMLR Permit 19-25 Charah, Inc. Moncure, North Carolina October 2016 This page intentionally left blank. Charah,

More information

Tighes Hill Remediation Project Update

Tighes Hill Remediation Project Update 3 September 2015 Tighes Hill Remediation Project Update This presentation includes forward-looking statements. Actual future conditions (including economic conditions, energy demand, and energy supply)

More information

Scheduling Maintenance for Dry Ponds

Scheduling Maintenance for Dry Ponds Visual Inspection for Sedimentation Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

Section Fill Placement Tender No. [ ] Page 1

Section Fill Placement Tender No. [ ] Page 1 Tender No. [ ] Page 1 1.0 GENERAL 1.1 GENERAL.1 This section specifies placement requirements for fill materials specified in Section 02330 Earthwork Materials, except for [Waste Fill, Gravel Armour, Riprap,

More information