Colorado PUC E-Filings System

Size: px
Start display at page:

Download "Colorado PUC E-Filings System"

Transcription

1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DOCKET NO. 1A E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP, FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A POWER PLANT CONSISTING OF A 0 MW SIMPLE CYCLE COMBUSTION TURBINE AND ASSOCIATED BALANCE OF PLANT PURSUANT TO COMMISSION DECISION NO. C1-1. Colorado PUC E-Filings System DIRECT TESTIMONY OF CHRISTOPHER BURKE ON BEHALF OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP April 0, 01

2 DIRECT TESTIMONY OF CHRISTOPHER BURKE I. INTRODUCTION AND QUALIFICATIONS Q. PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A. My name is Christopher Burke. My business address is S. Victoria Ave, Pueblo, Colorado 0. Q. BY WHOM ARE YOU EMPLOYED AND IN WHAT CAPACITY? A. I am employed by Black Hills/Colorado Electric Utility Company, LP (the Company or Black Hills) as the Vice President Colorado Utility Operations. Q. ON WHOSE BEHALF ARE YOU TESTIFYING? A. I am testifying on behalf of Black Hills. Q. WHAT ARE YOUR DUTIES AND RESPONSIBILITIES AS VICE PRESIDENT COLORADO UTILITY OPERATIONS? A. I am responsible for the financial and overall operational performance of the Company s electric and gas operations in the state of Colorado. My employment history and expertise is provided in Appendix A. Q. HAVE YOU PREVIOUSLY TESTIFIED BEFORE THIS COMMISSION? A. Yes. 1 II. PURPOSE OF TESTIMONY 1 Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY? 1

3 A. The purpose of my testimony is to describe Black Hills service territory, its current generating resources, its load growth, and the local impact of an LM000 1 turbine addition at the existing Pueblo Airport Generating Station (PAGS). Q. WHAT IS YOUR RECOMMENDATION? A. Based on load growth, energy usage and local economic impact, I recommend that the Commission approve the proposed build of the LM000 as proposed in this docket. I believe that the addition of this resource is consistent with the Black Hills Clean Air-Clean Jobs Act (CACJA) Plan and will result in a reasonable rate impact for our customers. III. BLACK HILLS OVERVIEW Q. PLEASE DESCRIBE BLACK HILLS AND ITS SERVICE TERRITORY. A. The Company provides electric utility service to 1 communities in Colorado with approximately,00 customers. This service territory encompasses all or part of Crowley, Custer, El Paso, Fremont, Otero, Pueblo, and Teller counties. Our electric generating resources are located in each of the three largest communities served within this service territory: Pueblo, Cañon City, and Rocky Ford. 1 IV. CURRENT GENERATING RESOURCES 1 0 Q. PLEASE DESCRIBE THE COMPANY S CURRENT GENERATING RESOURCES. 1 All references herein to LM000 or General Electric LM000 or GE LM000 do not represent a commitment to purchase; but instead, represent a proposal for a 0 MW simple-cycle, aeroderivative gas-fired turbine that will be defined by the Company s vendor selection process.

4 A. Black Hills owns seven generating facilities located within its certificated service territory. Of these facilities, only one is coal-fired, the Clark Station in Cañon City. That facility is scheduled to retire by the end of 01. The Clark Station is a dual-unit, coal-fired plant with MW of nameplate capacity, and is scheduled to retire by December 1, 01. This complies with the Commission s Decision issued pursuant to the CACJA (see Decision No. C-, in Docket No. M-E). Decision No. R1- granted a CPCN to decommission Clark Station by 01. The remaining six plants owned by Black Hills are: (1) PAGS, with two GE LMS0 gas turbines built in 0 and operational in January 01; () the gas-fired Pueblo #, a steam turbine built in ; () the gas-fired Pueblo #, a steam turbine built in 1; () the oil-fired Pueblo Airport Industrial Park (AIP) Diesel units built in 001; () the Pueblo Diesels #1- built in 1; and, () the Rocky Ford Diesels #1- built in 1. A summary of the seven plants and nameplate capacity is provided below, in Table 1: 1

5 Table 1 Generating Plant Fuel Location 1 Pueblo Airport Generating Station (PAGS), Units #1- Natural Gas Nameplate Capacity MW Year Installed Pueblo 0 W.N. Clark (Clark Station), Units #1- (retires Dec. 1, 01) Coal Cañon City 0 1, 1 Pueblo # (steam turbine) Natural Gas Pueblo, 001 Pueblo # (steam turbine) Natural Gas Pueblo 0 1 AIP Diesel Oil Pueblo 001 Diesel #1- Oil Pueblo 1 Diesel #1- Oil Rocky Ford 1 Total V. LOAD GROWTH AND DSM PROGRAMS The replacement capacity of Clark Station is MW as referenced in Black Hills Clean Air- Clean Jobs Act Plan (Docket No. M-E). The actual capacity is now 0 MW because one set of cables was removed from each phase of Clark Station Unit 1 in 0, reducing the unit s capability from 1 MW to 1 MW.

6 1 1 Q. WHAT IS YOUR CHARACTERIZATION OF LOAD GROWTH WITHIN THE BLACK HILLS SERVICE TERRITORY? A. As actual load growth projections are described in detail in the Black Hills 01 ERP filing, I would like to describe our load growth from a very important, qualitative perspective. At my direction, our Director of Energy Services works regularly and closely with our industrial customers to ensure that each customer s load accretions are well-understood. Based on this process, we are confident that our projections for growth within our service territory are as accurate as they can possibly be. Our annual (summer) peak has increased in four of the past five years, and in June of 01, Black Hills customer loads set a new summer peak of 00 MW. These annual peaks are outlined in Table below. Table Year Date New System Peak Demand MW Annual Increase 01 Tuesday, June 00 % 0 Monday, July 1 % 0 Monday, July 1 % 00 Friday, August We expect future peak demand growth to continue based on our understanding of customer load accretions. As a consequence, this consistently increasing peak

7 load growth underscores the need for firm, cost-effective generating resources to meet future peak demand. The LMS0 turbines at PAGS are utility-owned peaking resources designed for this purpose, and the LM000 turbine addition, proposed in this CPCN proceeding and identified contemporaneously as a resource option in our 01 ERP, will also serve as a utility-owned peaking resource for new loads beginning in 01. Over the short-term, and depending upon market conditions, wholesale power markets can present economically viable supplies of capacity for customers. Q. WHAT PROGRAMS IMPACT THE USE OF RESOURCES? A. It is important to note the role played by demand-side management (DSM) in our resource planning efforts. Conceptually, effective DSM means that a kilowatt of capacity saved by our customers translates to a kilowatt of capacity that does not need to be produced or acquired by the Black Hills on behalf of our customers. With this backdrop in mind, the Black Hills DSM Program has achieved positive results since its inception. In 00, the Commission mandated that Black Hills implement a DSM program that would document savings of % of the 00 total kwh usage by 01. That goal amounts to savings of 1,00 MWh. The program has exceeded relevant benchmarks for the past two years, and at the current trajectory, the total savings is projected to be,00 MWh by the end of the 01 program year. More detailed information concerning our DSM program can be found in the Company s multi-year Demand Side Management Plan filed with the Commission in Docket 1A-0E.

8 VI. LOCAL IMPACT OF LM000 TURBINE ADDITION Q. WHAT IS THE IMPACT TO THE LOCAL ECONOMY OF THE LM000 TURBINE ADDITION AT PAGS? A. Development of an LM000 turbine addition at PAGS would benefit the local economy in our service territory. As discussed in detail in the testimony of Dr. Mary Jo Kealy, the project would create construction jobs on average for a 1- month duration. Of that total, about 0-0% will be local workers. It would also create a permanent, full-time career opportunity for a technician. All things being equal, Black Hills would prefer to develop projects within rather than outside its service territory, because of the favorable impact such projects have on the local economy. Additionally, this project would raise property tax revenues for Pueblo County. As an example, the increased property tax revenue from PAGS was substantial enough to eliminate the need for a local Pueblo school district to issue new debt to fund a significant school expansion and upgrade project as reported in The Pueblo Chieftain on September, 01 in an article titled Bond issue gets Black Hills boost. Such a local economic benefit would have been lost had this capacity been sourced via a power purchase agreement rather than as a locallydeveloped project. I would anticipate that local development of the LM000 resource recommended in our accompanying ERP would produce commensurate benefits for the local Pueblo economy. Constructing the project will involve local and non-local expenditures for materials, equipment and labor and will generate additional sales and use tax

9 revenues for the state, county, and city. In addition, the local expenditures will be a direct benefit to the local economy. More detailed discussion of the local economic impact can be found within the testimony and exhibit of Dr. Mary Jo Kealy. VII. CONCLUSION 1 1 Q. WHAT IS YOUR RECOMMENDATION? A. I recommend that the Commission issue a CPCN for the construction of an LM000 at PAGS to replace the utility s capacity that will be retired this year pursuant to the CACJA. The development of this LM000 project will provide positive benefits to the local economy and generate additional property, sales and use tax revenues. Q. DOES THIS CONCLUDE YOUR TESTIMONY? A. Yes.

10 Appendix A Statement of Qualifications Christopher Burke Mr. Burke graduated from the United States Naval Academy in May, 1, with a Bachelor of Science degree in General Engineering. He subsequently completed Naval Nuclear Propulsion Training and served as a Nuclear Engineer and Surface Warfare Officer aboard nuclear powered warships. He left active duty military service in September of 1 to commence graduate studies. In May, 1, Mr. Burke completed graduate studies at the Colgate Darden Graduate School of Business and the University of Virginia School of Law, and received joint Masters of Business Administration and Juris Doctorate degrees. Mr. Burke has 1 years work experience. Upon graduation in 1, he began work as a management consultant for A.T. Kearney in Alexandria, VA, where he provided consulting services to Fortune 00 clients in manufacturing and supply chain operations. Subsequently, he worked in similar roles for an e-procurement start-up company, Campbell Soup Company, and America Online. Mr. Burke joined the utility industry in September, 00, as the plant manager of Alliant Energy s 0 MW coal-fired generation station in Ottumwa, IA. From 00 to 00, he worked as the Director of Business and Financial Performance for the Generation Business Unit in Cedar Rapids, IA, where he provided leadership over O&M and capital budgeting; strategic planning; monthly closing processes; rate case support; regulatory reporting; performance management including EBIT; competitive benchmarking efforts; cost accountability, financial performance improvement initiatives; and business decision support. From 00 to 0, Mr. Burke worked as Director of Energy Market Operations in Madison, WI, where he oversaw the corporation s operational performance within the Midwest Independent System Operator (MISO) and Pennsylvania-Jersey-Maryland (PJM) electric power markets, including asset 1

11 optimization strategies, fuel clause cost performance and decision support systems integration. Mr. Burke left Alliant Energy in April 0 to join Black Hills Corporation and he assumed his current role, Vice President Colorado Utility Operations, in May 0.

Before the Public Utilities Commission of the State of South Dakota. In the Matter of the Application of Black Hills Power, Inc.

Before the Public Utilities Commission of the State of South Dakota. In the Matter of the Application of Black Hills Power, Inc. Direct Testimony Mark Lux Before the Public Utilities Commission of the State of South Dakota In the Matter of the Application of Black Hills Power, Inc. For the Phase In of Rates Regarding Construction

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF ITS 0 ELECTRIC RESOURCE PLAN ) ) )

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * RE: IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF A NUMBER OF STRATEGIC ISSUES

More information

House Energy and Public Utilities Committee March 15, Kendal Bowman Vice President, Regulatory Affairs and Policy

House Energy and Public Utilities Committee March 15, Kendal Bowman Vice President, Regulatory Affairs and Policy House Energy and Public Utilities Committee March 15, 2017 Kendal Bowman Vice President, Regulatory Affairs and Policy At A Glance North Carolina 112 years of service 3.3 million retail customers in 83

More information

House Energy and Public Utilities Committee March 8, Kendal Bowman Vice President, Regulatory Affairs and Policy

House Energy and Public Utilities Committee March 8, Kendal Bowman Vice President, Regulatory Affairs and Policy House Energy and Public Utilities Committee March 8, 2017 Kendal Bowman Vice President, Regulatory Affairs and Policy At A Glance North Carolina 112 years of service 3.3 million retail customers in 83

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * RE: IN THE MATTER OF ADVICE LETTER NO. -ELECTRIC FILED BY PUBLIC SERVICE COMPANY OF COLORADO TO REPLACE COLORADO PUC NO.

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * ) ) ) ) ) ) DIRECT TESTIMONY AND EXHIBITS OF SUSAN ARIGONI BEHALF OF

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * ) ) ) ) ) ) DIRECT TESTIMONY AND EXHIBITS OF SUSAN ARIGONI BEHALF OF BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR

More information

GUAM PUBLIC UTILTIES COMMISSION DOCKET NO DIRECT TESTIMONY OF KEMM C. FARNEY ON BEHALF OF GUAM POWER AUTHORITY.

GUAM PUBLIC UTILTIES COMMISSION DOCKET NO DIRECT TESTIMONY OF KEMM C. FARNEY ON BEHALF OF GUAM POWER AUTHORITY. GUAM PUBLIC UTILTIES COMMISSION DOCKET NO. 0- DIRECT TESTIMONY OF KEMM C. FARNEY ON BEHALF OF GUAM POWER AUTHORITY Hagatna, Guam October 0, 0 Guam Power Authority Direct Testimony Farney Page DIRECT TESTIMONY

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION OF ) OKLAHOMA GAS AND ELECTRIC COMPANY ) FOR APPROVAL OF A GENERAL CHANGE IN ) DOCKET NO. -0-U RATES AND TARIFFS ) Direct

More information

DIRECT TESTIMONY BRUCE C. HARRINGTON. On Behalf of MISSISSIPPI POWER COMPANY BEFORE THE MISSISSIPPI PUBLIC SERVICE COMMISSION DOCKET NO.

DIRECT TESTIMONY BRUCE C. HARRINGTON. On Behalf of MISSISSIPPI POWER COMPANY BEFORE THE MISSISSIPPI PUBLIC SERVICE COMMISSION DOCKET NO. DIRECT TESTIMONY OF BRUCE C. HARRINGTON On Behalf of MISSISSIPPI POWER COMPANY BEFORE THE MISSISSIPPI PUBLIC SERVICE COMMISSION DOCKET NO. 0-AD-01 Q. Would you please state your name, position and business

More information

Before the South Dakota Public Utilities Commission of the State of South Dakota

Before the South Dakota Public Utilities Commission of the State of South Dakota Direct Testimony Laura A. Patterson Before the South Dakota Public Utilities Commission of the State of South Dakota In the Matter of the Application of Black Hills Power, Inc., a South Dakota Corporation

More information

Bill Fehrman President and CEO

Bill Fehrman President and CEO Bill Fehrman President and CEO A graduate of the University of Nebraska in Lincoln and with a master s degree in business administration from Regis University, Bill joined MidAmerican Energy in 2007 after

More information

Xcel Energys. PUBLIC SERVICE COMPANY

Xcel Energys. PUBLIC SERVICE COMPANY Xcel Energys. - PUBLIC SERVICE COMPANY IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF ITS ELECTRIC AND NATURAL GAS DEMAND-SIDE MANAGEMENT (DSM) PLAN FOR CALENDAR

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC

More information

PJM Analysis of the EPA Clean Power Plan

PJM Analysis of the EPA Clean Power Plan PJM Analysis of the EPA Clean Power Plan PJM Interconnection October 6, 2016 PJM CPP Study Objectives Evaluate potential impacts to: Resource adequacy Transmission system operations PJM energy and capacity

More information

DIRECT TESTIMONY OF JEFFREY M. MAY (ELECTRIC AND GAS PROCUREMENT)

DIRECT TESTIMONY OF JEFFREY M. MAY (ELECTRIC AND GAS PROCUREMENT) BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR AUTHORIZATION TO IMPLEMENT A REVENUE DECOUPLING

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG 15-

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG 15- STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Liberty Utilities (EnergyNorth Natural Gas) Corp. d/b/a Liberty Utilities Petition for Expansion of Franchise to the Towns of Pelham and Windham,

More information

REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY

REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY PETITION OF PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE D/B/A EVERSOURCE ENERGY

More information

All Source Request for Proposals Interim Summary

All Source Request for Proposals Interim Summary All Source Request for Proposals Interim Summary Introduction and Request for Proposal Overview Northern Indiana Public Service Company ( NIPSCO ) does business in the State of Indiana as a regulated public

More information

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION DOCKET NO. ~ 3 -E ~ FLORIDA POWER & LIGHT COMPANY IN RE: FLORIDA POWER & LIGHT COMPANY S PETITION TO DETERMINE NEED FOR MODERNIZATION OF PORT EVERGLADES PLANT

More information

Generation Attributes Tracking System

Generation Attributes Tracking System Monetizing Green Energy through Certificates Generation Attributes Tracking System 2006 New Jersey Clean Energy Conference September 18, 2006 New Brunswick, NJ PJM as Part of the Eastern Interconnection

More information

Regulatory Commission s ( Commission ) Office of Energy Market Regulation issued on

Regulatory Commission s ( Commission ) Office of Energy Market Regulation issued on 2750 Monroe Blvd. Audubon, PA 19403-2497 Chenchao Lu Counsel T: (610) 666-2255 F: (610) 666-8211 Chenchao.Lu@pjm.com The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First

More information

EEI Financial Conference November 6 8, 2016

EEI Financial Conference November 6 8, 2016 EEI Financial Conference November 6 8, 2016 Safe Harbor This presentation contains statements that may be considered forward looking statements, such as management s expectations of financial objectives

More information

RR8 - Page 377 of 495

RR8 - Page 377 of 495 DOCKET NO. APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY FOR AUTHORITY TO CHANGE RATES PUBLIC UTILITY COMMISSION OF TEXAS DIRECT TESTIMONY of SHAWN M. WHITE on behalf of SOUTHWESTERN PUBLIC SERVICE

More information

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER I SOCALGAS AMI VISION AND POLICY

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER I SOCALGAS AMI VISION AND POLICY Application No.: A.0-0-0 Exhibit No.: SCG 1 Date: March, 00 Witness: Michelle M. Mueller SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER I SOCALGAS AMI VISION AND POLICY Errata

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. DocketNo. DG 16- DIRECT TESTIMONY FRANCISCO C. DAFONTE DAVID B.

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. DocketNo. DG 16- DIRECT TESTIMONY FRANCISCO C. DAFONTE DAVID B. C C Liberty Utilities It.f I EXHIBIT- STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION DocketNo. DG - Liberty Utilities (EnergyNorth Natural Gas) Corp. d/b/a Liberty Utilities Keene Division

More information

) ) ) ) ) ) ) ) UPDATED DIRECT TESTIMONY OF JIMMIE I. CHO SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

) ) ) ) ) ) ) ) UPDATED DIRECT TESTIMONY OF JIMMIE I. CHO SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.1-1-01 Exhibit No.: Witness: Jimmie I. Cho Application of Southern California Gas Company (U 0 G and San Diego Gas & Electric Company (U 0 G For Authority To Recover North-South Project

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION American Electric Power Service Corporation ) Docket No. ER0- -000 On behalf of: ) Appalachian Power Company ) Columbus Southern

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. 18A- G IN THE MATTER OF THE VERIFIED JOINT APPLICATION OF BLACK HILLS GAS DISTRIBUTION, LLC, BLACK HILLS/COLORADO GAS UTILITY

More information

STATE OF MARYLAND OFFICE OF PEOPLE S COUNSEL

STATE OF MARYLAND OFFICE OF PEOPLE S COUNSEL PAULA M. CARMODY PEOPLE S COUNSEL THERESA V. CZARSKI DEPUTY PEOPLE S COUNSEL STATE OF MARYLAND OFFICE OF PEOPLE S COUNSEL 6 Saint Paul Street, Suite 2102 Baltimore, Maryland 21202 (410) 767-8150 (800)

More information

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION DOCKET NO EI

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION DOCKET NO EI BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION DOCKET NO. 00-EI IN RE: TAMPA ELECTRIC COMPANY S PETITION FOR AN INCREASE IN BASE RATES AND MISCELLANEOUS SERVICE CHARGES DIRECT TESTIMONY AND EXHIBIT OF LORRAINE

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF THE APPLICATION OF ) PUBLIC SERVICE COMPANY OF NEW MEXICO ) FOR APPROVAL OF A CERTIFICATE OF PUBLIC ) CONVENIENCE AND NECESSITY FOR A

More information

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION PRE-FILED DIRECT TESTIMONY OF NICHOLAS S. UCCI ON BEHALF OF THE RHODE ISLAND OFFICE OF ENERGY RESOURCES APRIL, 0 Page of 0 0

More information

Miller, Canfield, Paddock and Stone, P.L.C. One Michigan Avenue, Suite 900 Lansing, Michigan TEL (517) FAX (517)

Miller, Canfield, Paddock and Stone, P.L.C. One Michigan Avenue, Suite 900 Lansing, Michigan TEL (517) FAX (517) Founded in 1852 by Sidney Davy Miller SHERRI A. WELLMAN TEL (517) 483-4954 FAX (517) 374-6304 E-MAIL wellmans@millercanfield.com Miller, Canfield, Paddock and Stone, P.L.C. One Michigan Avenue, Suite 900

More information

Technical Assistance between ERERA, WAGPA, NARUC, and OPSI Activity No. 2; Abuja, Nigeria June Overview of OPSI

Technical Assistance between ERERA, WAGPA, NARUC, and OPSI Activity No. 2; Abuja, Nigeria June Overview of OPSI Technical Assistance between ERERA, WAGPA, NARUC, and OPSI Activity No. 2; Abuja, Nigeria 21-23 June 2011 Overview of OPSI Dr. Rajnish Barua Executive Director OPSI Overview of Presentation 2 Description

More information

Powering Beyond. Europe Investor Meetings March 20 22, 2018

Powering Beyond. Europe Investor Meetings March 20 22, 2018 Powering Beyond Europe Investor Meetings March 20 22, 2018 Safe Harbor This presentation contains statements that may be considered forward looking statements, such as management s expectations of financial

More information

October 20, Please contact me should you or your Staff have any questions regarding this filing. Sincerely,

October 20, Please contact me should you or your Staff have any questions regarding this filing. Sincerely, William P. Cox Senior Attorney Florida Power & Light Company 00 Universe Boulevard Juno Beach, FL 0-00 (1) 0- (1) 1-1 (Facsimile) Will.Cox@fpl.com October 0, 01 -VIA ELECTRONIC FILING- Ms. Carlotta S.

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY The 2016 SD Electricity Supply Resource Procurement Plan The 2016 South Dakota Electricity Supply Resource Procurement Plan ( Plan ) evaluates NorthWestern Energy s ( NorthWestern

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP. Direct Testimony of Mark R. Tallman

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP. Direct Testimony of Mark R. Tallman Docket No. UE Exhibit Witness: Mark R. Tallman BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP March 0 Tallman/i DIRECT TESTIMONY OF MARK R. TALLMAN TABLE OF CONTENTS QUALIFICATIONS... PURPOSE

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG DIRECT TESTIMONY DAVID B. SIMEK AND GREGG H.

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG DIRECT TESTIMONY DAVID B. SIMEK AND GREGG H. w C C IT Liberty Utilities STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Distribution Service Rate Case DIRECT TESTIMONY OF DAVID B. SIMEK AND GREGG H. THERRIEN April, 0 THIS PAGE INTENTIONALLY

More information

Making Sense of U.S. Energy Markets

Making Sense of U.S. Energy Markets Making Sense of U.S. Energy Markets Task Force on Energy Supply National Conference of State Legislators Richard McMahon Vice President, Energy Supply and Finance January 14, 2017 Wholesale Markets RTO/ISO

More information

Public Utility District No. 1 of Snohomish County, Washington Electric System Customers, Energy Sales, and Peak Demand Year Ended December 31,

Public Utility District No. 1 of Snohomish County, Washington Electric System Customers, Energy Sales, and Peak Demand Year Ended December 31, Customers, Energy Sales, and Peak Demand Average Number of Customers Residential 294,178 297,175 301,639 305,916 309,761 Commercial 30,011 30,280 30,524 30,793 31,046 Industrial 79 77 76 74 77 Other 313

More information

CHAPTER 3 EXISTING PORTFOLIO RESOURCES

CHAPTER 3 EXISTING PORTFOLIO RESOURCES CHAPTER 3 EXISTING PORTFOLIO RESOURCES Existing Portfolio Resources Discussion NorthWestern uses a mixture of resources to meet the existing energy and capacity needs of its South Dakota customers and

More information

Capacity Performance FAQ Response

Capacity Performance FAQ Response PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum

More information

STANDARD CONTRACT RIDERS - (Continued) RIDER NO. 9 DAY-AHEAD HOURLY PRICE SERVICE

STANDARD CONTRACT RIDERS - (Continued) RIDER NO. 9 DAY-AHEAD HOURLY PRICE SERVICE THIRD REVISED PAGE NO. 89 CANCELLING SECOND REVISED PAGE NO. 89 RIDER NO. 9 DAY-AHEAD HOURLY PRICE SERVICE Day-ahead hourly price service provides large commercial and industrial customers with the ability

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Page 1 of 13 ATTACHMENT A Introduction In Decision No. C16-0127 (issued on February 16, 2016), Public Service Company of Colorado ( Public Service or the Company ) was directed to file technical assumptions

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY The 2014 South Dakota Integrated Resource Plan This Plan provides the outline of a disciplined economic evaluation of supply (energy and capacity) for addressing the next 10

More information

Philadelphia s Grays Ferry Steams Ahead

Philadelphia s Grays Ferry Steams Ahead Volume 88 Number 2 Second Quarter 2002 Philadelphia s Grays Ferry Steams Ahead Featuring Optimizing Shiftworker Performance, Health, Safety High Marks for University System Efficiency Baltimore Systems

More information

Non-Technical Summary

Non-Technical Summary Non-Technical Summary I. Introduction Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc. ( Vectren ) engaged in a planning exercise during 2016 to evaluate its electric

More information

ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY

ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY DRAFT Report ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Navajo Tribal Utility Authority August 2007 DRAFT NAVAJO TRIBAL UTILITY AUTHORITY ELECTRIC COST OF SERVICE AND RATE DESIGN STUDY Table of Contents

More information

Rocky Mountain Power Docket No Witness: Joelle R. Steward BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Joelle R. Steward BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 13-035-184 Witness: Joelle R. Steward BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Joelle R. Steward Cost of Service

More information

Exhibits for Testimony of George W. Evans May 10, 2013 Docket No

Exhibits for Testimony of George W. Evans May 10, 2013 Docket No Exhibits for Testimony of George W. Evans May 10, 2013 Docket No. 36498 Exhibit No. Description SACE-GWE-1 Resume of George W. Evans SACE-GWE-2 Gaston 1-4 Fuel Switch to Natural Gas versus Retirement (Public

More information

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version

More information

STATE OF VERMONT PUBLIC UTILITY COMMISSION

STATE OF VERMONT PUBLIC UTILITY COMMISSION STATE OF VERMONT PUBLIC UTILITY COMMISSION Case No. --INV Investigation into the petition of Green Mountain Power Corporation's tariff filing requesting an overall rate increase in the amount of.%, to

More information

PJM s Experience with the RPM Capacity Market

PJM s Experience with the RPM Capacity Market PJM s Experience with the RPM Capacity Market 2013 Austin Electricity Conference Panel 1: Are Capacity Market Necessary to Ensure Adequate Generating Reserve Paul M. Sotkiewicz, Ph.D. Chief Economist PJM

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG DIRECT TESTIMONY JOHN LOWSON. August 1, 2014

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DG DIRECT TESTIMONY JOHN LOWSON. August 1, 2014 STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Docket No. DG -0 Liberty Utilities (EnergyNorth Natural Gas) Corp. d/b/a Liberty Utilities Distribution Service Rate Case DIRECT TESTIMONY

More information

Department of Legislative Services

Department of Legislative Services Department of Legislative Services Maryland General Assembly 2008 Session HB 377 FISCAL AND POLICY NOTE Revised House Bill 377 (The Speaker, et al.) (By Request Administration) Economic Matters and Ways

More information

2018 Integrated Resource Plan Executive Summary

2018 Integrated Resource Plan Executive Summary 2018 Integrated Resource Plan Executive Summary At NIPSCO, we re proud that our work provides the energy that northern Indiana families and businesses rely on to power their daily lives. We work each day

More information

Successful Outcomes for Projects and Clients

Successful Outcomes for Projects and Clients Peter Flagg Contact information: pflagg@projectstrategies.ca 250 727-9217 Project Strategies Successful Outcomes for Projects and Clients Mr. Flagg is an Information Management and Organization Engineering

More information

Welcome. Napanee Generating Station Jobs Information Session

Welcome. Napanee Generating Station Jobs Information Session Welcome Napanee Generating Station Jobs Information Session Napanee Generating Station Jobs Information Session Why are we here? To provide you with information regarding: Future employment opportunities

More information

SECOND Quarter REPORT

SECOND Quarter REPORT SECOND Quarter REPORT FISCAL YEAR 2015 www.austinenergy.com BENEFITS OF PUBLIC POWER Austin Energy Regional Science Festival Austin Energy is the eighth largest publicly owned utility in the nation, and

More information

Entergy Arkansas, Inc Integrated Resource Plan. Follow-Up Materials June 18, 2018 entergy-arkansas.com/irp

Entergy Arkansas, Inc Integrated Resource Plan. Follow-Up Materials June 18, 2018 entergy-arkansas.com/irp Entergy Arkansas, Inc. 2018 Integrated Resource Plan Follow-Up Materials June 18, 2018 entergy-arkansas.com/irp Follow-up Materials to the 2018 IRP Stakeholder Meeting The following information is provided

More information

Contract For Biomass-Fueled Generation. Presentation to the Gainesville City Commission May 7, 2009

Contract For Biomass-Fueled Generation. Presentation to the Gainesville City Commission May 7, 2009 Contract For Biomass-Fueled Generation Presentation to the Gainesville City Commission May 7, 2009 Presentation Outline Project History And Description Market Changes Adjustments To Original Proposal Economic

More information

Nuclear Energy Institute Testimony for the Record Senate Public Utilities Committee State of Ohio June 8, 2017

Nuclear Energy Institute Testimony for the Record Senate Public Utilities Committee State of Ohio June 8, 2017 Nuclear Energy Institute Testimony for the Record Senate Public Utilities Committee State of Ohio June 8, 2017 Good afternoon. I would like to thank Chairman Beagle and the Public Utilities Committee for

More information

STATE OF MAINE PUBLIC UTILITIES COMMISSION. Docket No

STATE OF MAINE PUBLIC UTILITIES COMMISSION. Docket No STATE OF MAINE PUBLIC UTILITIES COMMISSION Docket No. 00- Analysis of Central Maine Power Company Petition for a Certificate of Public Convenience and Necessity to Construct a kv Transmission Line Between

More information

GATS Subscriber Group Meeting 2010 PJM EIS

GATS Subscriber Group Meeting 2010 PJM EIS GATS Subscriber Group Meeting Thursday, May 20, 2010 Agenda Welcome and Introductions GATS Status Update Administrative Updates PJM EIS Website Upgrades Enhancements Subscriber Feedback State Updates Next

More information

RATE DS-4 LARGE GENERAL DELIVERY SERVICE

RATE DS-4 LARGE GENERAL DELIVERY SERVICE d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential

More information

Island Park Energy Center A Repowering of E.F. Barrett Power Station Informational Open House

Island Park Energy Center A Repowering of E.F. Barrett Power Station Informational Open House Island Park Energy Center A Repowering of E.F. Barrett Power Station Informational Open House Project Proposal and Development Schedule Table Tripod Boards Project Proposal National Grid, under its current

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION WEST PENN POWER COMPANY DOCKET NO. R Direct Testimony of Thomas J.

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION WEST PENN POWER COMPANY DOCKET NO. R Direct Testimony of Thomas J. West Penn Statement No. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION WEST PENN POWER COMPANY DOCKET NO. R-0- Direct Testimony of Thomas J. Dolezal List of Topics Addressed Cost of Service Studies

More information

Installed Capacity Market

Installed Capacity Market Installed Capacity Market Going Forward Costs Input Template Instructions Data Submission Template for Going Forward Cost and Physical Withholding Review March 2014 Table of Contents Table of Contents...

More information

Before the Minnesota Public Utilities Commission State of Minnesota

Before the Minnesota Public Utilities Commission State of Minnesota Direct Testimony and Schedules Scott L. Weatherby Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Northern States Power Company for Authority to

More information

MidAmerican Energy Company. Second Annual Report of Carbon Reduction Cost Recovery Rider

MidAmerican Energy Company. Second Annual Report of Carbon Reduction Cost Recovery Rider MidAmerican Energy Company Second Annual Report of Carbon Reduction Cost Recovery Rider Background On July 9, 2010, MidAmerican Energy Company (MidAmerican) filed with the Iowa Utilities Board (Board)

More information

STATE OF MICHIGAN BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * *

STATE OF MICHIGAN BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * * STATE OF MICHIGAN BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * * In the matter of the application of ) MICHIGAN GAS UTILITIES CORPORATION ) for authority to increase retail natural gas rates )

More information

Appendix D Minimum Requirements. For Request For Proposals For Long-Term, Supply-Side Developmental Resources in In Amite South DRAFT

Appendix D Minimum Requirements. For Request For Proposals For Long-Term, Supply-Side Developmental Resources in In Amite South DRAFT ESI Draft 7/14/2014 Appendix D Minimum Requirements For 2014 Request For Proposals For Long-Term, Supply-Side Developmental Resources in In Amite South Formatted: Font color: Black Formatted: Font: Tahoma

More information

Ohio Energy. Workshop FF. Best Practices for Offsite Renewable Solutions Meeting Sustainability & Renewable Energy Goals through Purchasing Solutions

Ohio Energy. Workshop FF. Best Practices for Offsite Renewable Solutions Meeting Sustainability & Renewable Energy Goals through Purchasing Solutions Ohio Energy Workshop FF Best Practices for Offsite Renewable Solutions Meeting Sustainability & Renewable Energy Goals through Purchasing Solutions Wednesday, February 21, 2018 11:15 a.m. to 12:30 p.m.

More information

PREPARED DIRECT TESTIMONY OF BRUCE M. WETZEL SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED DIRECT TESTIMONY OF BRUCE M. WETZEL SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.1-0- Exhibit No.: Witness: Bruce M. Wetzel Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Natural Gas

More information

Strategic Sourcing Manager: Academic Services and Equipment

Strategic Sourcing Manager: Academic Services and Equipment Strategic Sourcing Manager: Academic Services and Equipment Position Number 00022192 Department: Campus: Strategic Procurement Services SWS Date of Issue: August 2013 I. Primary Purpose of Position The

More information

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-2, SUB 1089 BEFORE THE NORTH CAROLINA UTILITIES COMMISSION In the Matter of ) Application of Duke Energy Progress, LLC for a ) MOTION TO

More information

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) PREFILED TESTIMONY OF STEVE COSTELLO ON BEHALF OF GREEN MOUNTAIN POWER. April 14, 2017

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) PREFILED TESTIMONY OF STEVE COSTELLO ON BEHALF OF GREEN MOUNTAIN POWER. April 14, 2017 STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. Tariff filing of Green Mountain Power requesting an all-in.% increase in its rates, effective January, 0 ) ) ) PREFILED TESTIMONY OF STEVE COSTELLO ON BEHALF

More information

Catalogue no X. Electric Power Generation, Transmission and Distribution

Catalogue no X. Electric Power Generation, Transmission and Distribution Catalogue no. 57-202-X Electric Power Generation, Transmission and Distribution 2006 How to obtain more information For information about this product or the wide range of services and data available from

More information

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference Andrew Ott Sr. Vice President, Markets March 5, 2013 26% of power generation

More information

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager:

Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: FAQs from 2017-08-30 Q: What do I do if I need more information? A: Check back with this FAQ page periodically. If your question is not here, contact the RFP manager: PSCo2017AllSource@xcelenergy.com Q:

More information

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION NORTHERN UTILITIES, INC DIRECT TESTIMONY OF PAUL M. NORMAND

THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION NORTHERN UTILITIES, INC DIRECT TESTIMONY OF PAUL M. NORMAND THE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION DG -0 NORTHERN UTILITIES, INC DIRECT TESTIMONY OF PAUL M. NORMAND ACCOUNTING COST OF SERVICE STUDY MARGINAL COST OF SERVICE STUDY RATE

More information

WESCO International. Dave Schulz, Senior Vice President and Chief Financial Officer Raymond James 39 th Annual Investors Conference, March 7, 2018

WESCO International. Dave Schulz, Senior Vice President and Chief Financial Officer Raymond James 39 th Annual Investors Conference, March 7, 2018 WESCO International Dave Schulz, Senior Vice President and Chief Financial Officer 2 Safe Harbor Statement All statements made herein that are not historical facts should be considered as forward-looking

More information

Ricker Cunningham Ashurst Way Littleton, Colorado voice

Ricker Cunningham Ashurst Way Littleton, Colorado voice Ricker Cunningham www.rickercunningham.com 10959 Ashurst Way Littleton, Colorado 80130 303.458.5800 voice 12 September 2018 Mr. Jariah Walker Executive Director Colorado Springs Urban Renewal Authority

More information

Blue Ridge Power Agency Legal Counsel Request for Statements of Qualifications

Blue Ridge Power Agency Legal Counsel Request for Statements of Qualifications Town of Bedford City of Danville City of Martinsville City of Radford Town of Richlands City of Salem Virginia Polytechnic Institute and State University Central Virginia Electric Cooperative Blue Ridge

More information

CHAPTER 7. ENERGY AND NATURAL RESOURCES

CHAPTER 7. ENERGY AND NATURAL RESOURCES CHAPTER 7. ENERGY AND NATURAL RESOURCES 7.1. HOW WERE ENERGY AND NATURAL RESOURCES IN THE COMBINED STUDY AREA EVALUATED? This chapter describes at a programmatic level the types of energy resources used

More information

Appendix D Minimum Requirements For Developmental Resources For

Appendix D Minimum Requirements For Developmental Resources For Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc. Entergy Services, Inc. July 13, 2016 MINIMUM REQUIREMENTS FOR

More information

Integrated Resource Plan Public Advisory Group

Integrated Resource Plan Public Advisory Group Integrated Resource Plan Public Advisory Group Meeting 11 November 16, 2017 Recap of IRP Process, Assumptions For Resource Options, Preliminary Results, Development of Most Cost-Effective Portfolio Meeting

More information

IMPACT OF CLOSING NAVAJO GENERATING STATION ON ARIZONA POWER MARKETS

IMPACT OF CLOSING NAVAJO GENERATING STATION ON ARIZONA POWER MARKETS IMPACT OF CLOSING NAVAJO GENERATING STATION ON ARIZONA POWER MARKETS Prepared for: Arizona Corporation Commission Mr. Seth Schwartz President schwartz@evainc.com August 2018 Energy Ventures Analysis 1901

More information

Prefiled Testimony of Chris Neme

Prefiled Testimony of Chris Neme STATE OF VERMONT PUBLIC SERVICE BOARD Petition of Vermont Gas Systems, Inc., for a certificate of public good, pursuant to 0 V.S.A., authorizing the construction of the Addison Natural Gas Project Phase

More information

State Energy Efficiency Resource Standard (EERS) Activity

State Energy Efficiency Resource Standard (EERS) Activity State Energy Efficiency Resource Standard (EERS) Activity November 2010 Standard Voluntary Goal Standard/Goal Combined EERS/RES Twenty-four states have enacted energy savings goals, or Energy Efficiency

More information

Capacity Revenues for Existing, Base Load Generation in the PJM Interconnection

Capacity Revenues for Existing, Base Load Generation in the PJM Interconnection Capacity Revenues for Existing, Base Load Generation in the PJM Interconnection A Pennsylvania Case Study Prepared by: Paul Peterson, David White, and Bruce Biewald 22 Pearl Street, Cambridge, MA 02139

More information

before the ure is Martha States, the Section for America. wind turbines for equipment. states. Our Vestas-American Wind

before the ure is Martha States, the Section for America. wind turbines for equipment. states. Our Vestas-American Wind Testimony of Martha Wyrsch, President, before the Senate Finance Subcommittee on Energy, Natural Resources & Infrastruct ure December 14, 2011 Chairman Bingaman, Ranking Member Cornyn and members of the

More information

BEFORE THE ARIZONA CORPORATION COMMISSION

BEFORE THE ARIZONA CORPORATION COMMISSION COMMISSIONERS DOUG LITTLE, Chairman BOB STUMP TOM FORESE BOB BURNS ANDY TOBIN BEFORE THE ARIZONA CORPORATION COMMISSION IN THE MATTER OF THE APPLICATION OF EPCOR WATER ARIZONA INC. FOR A DETERMINATION

More information

Re: PJM Interconnection, L.L.C. Docket Nos. ER , ER , ER Settlement Compliance Filing

Re: PJM Interconnection, L.L.C. Docket Nos. ER , ER , ER Settlement Compliance Filing Sebrina M. Greene Rockland Electric Company 4 Irving Place, 1875-S, New York, NY 10003 Tel.: 212-460-3228 Email: greenes@coned.com SUBMITTED VIA ELECTRONIC FILING December 28, 2017 Hon. Kimberly D. Bose

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND * * * * * * * * * * * * *

BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND * * * * * * * * * * * * * BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND IN THE MATTER OF THE APPLICATION OF MD SOLAR 2, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 27.5 MW SOLAR PHOTOVOLTAIC GENERATING

More information