1 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC RESOURCE PLAN, AND () APPROVAL OF ITS 0-0 RES COMPLIANCE PLAN. DIRECT TESTIMONY OF Colorado PUC E-Filings System ERIC M. EGGE ON BEHALF OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP June, 0
2 Table of Contents SECTION PAGE I. INTRODUCTION AND QUALIFICATIONS... II. PURPOSE OF TESTIMONY... III. PLANNING RESERVE MARGIN... IV. AVAILABILITY OF SEASONAL FIRM MARKET POWER... V. AVAILABILITY OF ECONOMY ENERGY... VI. COLORADO JOINT DISPATCH...
3 DIRECT TESTIMONY OF ERIC M. EGGE I. INTRODUCTION AND QUALIFICATIONS Q. PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A. My name is Eric M. Egge. My business address is Plant Street, Rapid City, South Dakota 0-0. Q. BY WHOM ARE YOU EMPLOYED AND IN WHAT CAPACITY? A. I am employed as the Director of Generation Dispatch and Power Marketing for Black Hills Power. My educational background, employment history and 0 0 expertise are provided in Appendix A. Q. ON WHOSE BEHALF ARE YOU TESTIFYING? A. I am testifying on behalf of Black Hills/Colorado Electric Utility Company, LP, d/b/a Black Hills Energy ( Black Hills or the Company ). Q. PLEASE DESCRIBE YOUR RESPONSIBILITIES AS DIRECTOR OF GENERATION DISPATCH AND POWER MARKETING. A. As the Director of Generation Dispatch and Power Marketing, I lead a group of employees all with the ultimate goal of providing reliable low cost power for Black Hills Energy South Dakota; Black Hills Energy Wyoming; and Black Hills. We provide generation dispatch and load following operations for these utilities in a -hour -day operation center. I am also responsible for providing energy marketing services for Black Hills Energy South Dakota, Black Hills and Black Hills Wyoming, LLC (Black Hills Corporation s unregulated, independent power producing subsidiary).
4 II. PURPOSE OF TESTIMONY Q. WHAT IS THE PURPOSE OF YOUR TESTIMONY? A. The purpose of my testimony is to support the planning reserve margin used in the Company s 0 Electric Resource Plan (ERP) and the assumptions regarding the availability of seasonal firm market power for the Company s system. III. PLANNING RESERVE MARGIN 0 0 Q. WHAT IS THE PLANNING RESERVE MARGIN USED IN THE COMPANY S 0 ERP? A. The 0 ERP assumes a % planning reserve margin. Q. WHAT IS THE PURPOSE OF PLANNING RESERVE? A. Planning reserve is the amount of capacity that an electric utility holds in reserve above its peak load requirements. A planning reserve margin is a percentage applied to the expected peak load to determine the minimum additional capacity that an electric utility should plan for to ensure that it will meet its peak load obligations in the event of an unforeseen loss of generating resources, extreme weather, or other unexpected conditions. Q. WHAT WAS THE PLANNING RESERVE MARGIN THE COMPANY USED IN ITS 0 ERP? A. The Company used a % planning reserve margin in its 0 ERP.
5 0 Q. HAS THE COMPANY HAD A RESERVE MARGIN STUDY CONDUCTED SINCE ITS 0 RESOURCE PLAN? A. No. The Company conducted a study in 00 that concluded that the appropriate reserve margin to use for planning purposes was between 0 and 0 percent. However, for purposes of the 0 ERP the Company used a planning reserve margin of % that was approved by the Commission in the Company s 0 ERP proceeding (Proceeding No. A-0E). The Company believes a % reserve margin is appropriate. The Company s peak requirement is expected to be approximately 00 MW in 0 and its largest single outage risk is 00 MW. As a member of the Rocky Mountain Reserve Group (RMRG), the Company has the ability to rely on the RMRG for up to two hours after a forced outage of any of its generating units. Thereafter, the Company will be required to replace the lost capacity and, as I discuss in my testimony, there is currently capacity available in the market to address that situation. 0 IV. AVAILABILITY OF SEASONAL FIRM MARKET POWER Q. WHAT IS SEASONAL FIRM MARKET POWER? A. Seasonal firm market power is firm energy supply that may be available in the market from time to time. It is considered firm because the supply is nonrecallable and, if the supply is interrupted, the buyer will be compensated by the seller for all reasonable costs to replace the interrupted energy.
6 0 0 Q. WHAT ARE THE ASSUMPTIONS USED IN THE 0 ERP REGARDING THE AVAILABILITY OF SEASONAL FIRM MARKET POWER? A. The 0 ERP assumes capacity is available for seasonal firm market purchase for hours per day, six days a week, in MW blocks, up to MW through 0, then adjusted to 0 MW through the remainder of the planning period. Q. WHY IS MW THROUGH 0 A REASONABLE ASSUMPTION FOR THE COMPANY? A. It is a reasonable assumption based upon the WECC 0 Power Supply Assessment. The Assessment shows a reserve margin deficit for the Rocky Mountain and Southwest areas beginning in 0; therefore, it is reasonable to assume that MW would be available in the Rocky Mountain area up until the reported reserve margin deficit in 0. Q. WHAT ARE THE TRANSMISSION LIMITATIONS WITH REGARD TO DELIVERING POWER TO THE COMPANY? A. The primary transmission limitation is the import capacity available to the Company. While the Company has been successful in procuring energy at Midway, the direct interconnection to the transmission grid directly north of the Company s system, there is a limit to the volume of energy available at that location. Midway is the trading hub for this area, and is a well-used interconnection with direct access to Public Service Company of Colorado, Colorado Springs Utilities, the WAPA-Colorado River Storage Project, Tri-State Generation and Transmission Association, Inc., and Black Hills.
7 0 0 Q. WHAT OTHER FACTORS INFLUENCE THE SELECTION OF MW AS A REASONABLE ASSUMPTION FOR SEASONAL FIRM MARKET POWER? A. The Company is a small utility with a peak demand of approximately 00 MW. The Company believes that MW of seasonal firm market power, which represents almost 0 percent of its peak load and which exceeds its reserve margin, is a reasonable assumption that limits the risk associated with relying on seasonal firm market power. Finally, as discussed earlier in my testimony, the % planning reserve margin covers 0 MW of capacity. Therefore, while we believe the MW assumption is reasonable, we do not believe a higher assumption would be prudent for the Company. Q. WHY IS 0 MW STARTING IN 0 A REASONABLE ASSUMPTION FOR THE COMPANY? A. Again, referring to the 0 WECC Power Supply Assessment, it reported limited planning reserves beginning in 0 for the Rocky Mountain area. However, the assessment also reported a planning reserve surplus in the Northwest, indicating availability of seasonal firm market power, but at lower anticipated volumes assuming limited transmission availability from the Northwest area to the Rocky Mountain area.
8 0 Q. WHAT CONTINGENCIES ARE ASSOCIATED WITH ASSUMING THE AVAILABILITY OF SEASONAL FIRM MARKET POWER? A. There are two contingencies: availability and price. As supplies tighten, price will go up. Therefore, we can use price as an advance indicator of tightening availability. Q. DOES THE 0 ERP PREFERRED PLAN RELY UPON SEASONAL FIRM MARKET PURCHASES DURING THE RAP? A. No. Black Hills Preferred Plan does not include the addition of any new capacity resources, seasonal firm or conventional, during the RAP; therefore, a contingency plan for the acquisition of new resources or replacement resources in the event that resources are not developed in accordance with a Commissionapproved plan is not required. Consequently, Black Hills is seeking a waiver from this requirement. 0 V. AVAILABILITY OF ECONOMY ENERGY Q. WHAT IS ECONOMY ENERGY AND HOW IS IT DIFFERENT FROM SEASONAL FIRM MARKET POWER? A. Seasonal firm market power provides capacity; economy energy does not. Economy energy is energy (sold without capacity) that may be available in the market from time-to-time and which is more economical to purchase than the incremental cost of a utility s own resources. Economy energy is not firm energy. The selling party may recall an economy energy transaction at any time and,
9 0 therefore, the buying party must maintain sufficient contingency reserve to replace recalled supply. Q. PLEASE DESCRIBE THE ASSUMPTIONS IN THE MODELING FOR THE AVAILABILITY OF ECONOMY ENERGY. A. The model was allowed to purchase non-firm or economy energy up to 0 MW from the marketplace. The price for that economy energy was based on ABB s WECC 0 Fall Reference Case forecast for the CO-East and Palo Verde (PV) spot markets. Q. WHY IS THE ASSUMPTION OF THE AVAILABILITY OF 0 MW OF ECONOMY ENERGY APPROPRIATE? A. The Company has adequate quick start resources in the Pueblo area to back up 0 MW of economy energy purchases. These resources include 0 MW of utility-owned generation resources at the Pueblo Airport Generating Station. As mentioned previously, economy energy is not firm energy and, therefore, the selling party may recall an economy energy transaction at any time. Thus, the Company may be required to cover the amount of the economy energy purchase in a short period of time in the event it is recalled with little notice. 0 Q VI. COLORADO JOINT DISPATCH WHAT IS THE JOINT DISPATCH AGREEMENT? A. The Joint Dispatch Agreement ( JDA ) is an arrangement between the Company, Public Service Company of Colorado and Platte River Power Authority for the purposes of balancing the combined sub-hourly demand utilizing the most
10 0 economic resources among the parties. Each party is still required to enter the operating hour with sufficient resources to supply their own load, either with their own generating resources or market purchases. In addition, JDA energy is nonfirm and utilizes the lowest priority transmission service and cannot be counted as capacity or used to make a reserve call should it be curtailed. The parties to the JDA are currently in the process of implementing the systems necessary to administer and operate the agreement. Q. WILL THE JOINT DISPATCH AGREEMENT IMPACT THE 0 ERP RESULTS? A. No. Because the service only is utilized for economic dispatch within the operating hour, it doesn t impact the Company s long-term resource planning with respect to the transmission system or generating supply. Further, as the JDA is a non-firm energy product utilizing lowest priority transmission service, it cannot be counted as capacity. Q. DOES THIS CONCLUDE YOUR TESTIMONY? A. Yes.
11 Appendix A Statement of Qualifications Eric Egge Mr. Egge graduated from North Dakota State University in 000 with a Bachelor of Science degree in Electrical Engineering. He is a Registered Professional Engineer in the State of South Dakota. Mr. Egge has years of electric utility industry experience in the areas of transmission operations, regional reliability coordination, long-range transmission planning, NERC and FERC regulatory compliance, and wholesale power markets including years with Black Hills Corporation. He was promoted to his current position Director of Generation Dispatch & Power Marketing in January 0.
With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development
With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
1 2 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA 3 4 5 6 Order Instituting Rulemaking to Oversee the Resource Adequacy Program, Consider Program Refinements, and Establish Annual Local
More informationXcel Energys. PUBLIC SERVICE COMPANY
Xcel Energys. - PUBLIC SERVICE COMPANY IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF ITS ELECTRIC AND NATURAL GAS DEMAND-SIDE MANAGEMENT (DSM) PLAN FOR CALENDAR
More informationColorado PUC E-Filings System
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC
More informationColorado PUC E-Filings System
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DOCKET NO. 1A E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP, FOR A CERTIFICATE OF PUBLIC CONVENIENCE
More informationColorado PUC E-Filings System
Page 1 of 13 ATTACHMENT A Introduction In Decision No. C16-0127 (issued on February 16, 2016), Public Service Company of Colorado ( Public Service or the Company ) was directed to file technical assumptions
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Public Service Company of Colorado ) Docket No.
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Exhibit PSC- Page of Public Service Company of Colorado ) Docket No. ER- -000 PREPARED TESTIMONY OF TERRI K. EATON XCEL ENERGY SERVICES
More information2011 WIND LIMIT STUDY
2011 WIND LIMIT STUDY PREPARED FOR THE PUBLIC SERVICE COMPANY OF COLORADO 2011 ELECTRIC RESOURCE PLAN OCTOBER 31, 2011 TABLE OF CONTENTS SECTION 1 STUDY OBJECTIVE... 5 SECTION 2 SUMMARY... 5 SECTION 3
More informationColorado PUC E-Filings System
Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF ITS 0 ELECTRIC RESOURCE PLAN ) ) )
More informationPJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia
PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *
Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * RE: IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF A NUMBER OF STRATEGIC ISSUES
More informationTable of Contents Page i
2012 Integrated Resource Plan Table of Contents I. Executive Summary... 1 II. Recent Trends in Electrical Load Growth... 4 III. System Load Forecast... 7 IV. Current Resources... 12 V. Load/Resource Balance
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of John A. Cupparo
Docket No. 0- Exhibit No. PPL/00 Witness: John A. Cupparo BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Populus to Terminal Transmission Line November 00 Cupparo/ 0 Q. Please
More informationWholesale Electricity Concepts. A. David Cormie P. Eng. Division Manager Power Sales and Operations Manitoba Hydro May 2010
Wholesale Electricity Concepts A. David Cormie P. Eng. Division Manager Power Sales and Operations Manitoba Hydro May 2010 Topics Electricity Accounting Losses Firm Capacity Energy Reserves Products 2
More informationDraft Whitepaper to Platte River Board of Directors
Draft Whitepaper to Platte River Board of Directors Report on Organized Power Markets RTOs and ISOs Presented for the October 2016 Board Meeting Overview This report on the potential formation of a regional
More informationCHAPTER 6 - Load Forecast & Resource Plan
CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching
More informationOrganized Markets in WECC. Status Update and Implications for Planning 2/1/18
Organized Markets in WECC Status Update and Implications for Planning 2/1/18 Agenda Regional Markets Update Regional Market Activity EIM CAISO Mountain West Peak Reliability / PJM Implications for 2018
More informationUpdated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations
Updated October 2, 2014 System Operator Transmission - Senior interconnected system. Maintains the Western Electricity Coordinating Council (WECC) Coordinated Outage System (COS), documents standardized
More informationKey Issues and Consideration in Market Design, Operational and Oversight
Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities
More informationATTACHMENT C Methodology to Assess Available Transmission Capability
Improvement and Power District Revised Sheet No. 107 ATTACHMENT C Methodology to Assess Available Transmission Capability This methodology is excerpted from the report Determination of Available Transfer
More informationWholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission
Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets
More informationComments of Powerex Corp. on Draft Regional Resource Adequacy Framework Proposal Submitted by Company Date Submitted
Comments of Powerex Corp. on Draft Regional Resource Adequacy Framework Proposal Submitted by Company Date Submitted Mike Benn 604.891.6074 Powerex Corp. January 11, 2017 Powerex appreciates the opportunity
More informationFred Stoffel. Tri-State Generation and Transmission Association, Inc. May 19, Utility Resource Planning Fundamentals
Fred Stoffel Tri-State Generation and Transmission Association, Inc. May 9, 202 Tri-State Overview Tri-State is a not-for-profit, wholesale power supplier owned by 44 electric cooperatives and public power
More informationDefinitions O - P. Open Access Same-Time Information System (OASIS) or PJM Open Access Same-time Information System:
Definitions O - P Offer Data: Offer Data shall mean the scheduling, operations planning, dispatch, new resource, and other data and information necessary to schedule and dispatch generation resources and
More informationLoads and Resources Methods and Assumptions
Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1
More informationComments of Powerex Corp. on Day-Ahead Market Enhancements Phase 2
Comments of Powerex Corp. on Day-Ahead Market Enhancements Phase 2 Submitted by Company Date Submitted Mike Benn 604.891.6074 Powerex Corp. April 4, 2019 Powerex appreciates the opportunity to comment
More informationCalifornia ISO Summer Loads and Resources Operations Assessment April 10, Grid Assets California ISO Version 3.0.
California Independent System Operator Corporation 2006 Summer Loads and Resources Operations Assessment April 10, 2006 Grid Assets Version 3.0 Table of Contents I. Executive Summary...2 Table 1 2006 ISO
More informationBefore the Public Utilities Commission of the State of South Dakota. In the Matter of the Application of Black Hills Power, Inc.
Direct Testimony Mark Lux Before the Public Utilities Commission of the State of South Dakota In the Matter of the Application of Black Hills Power, Inc. For the Phase In of Rates Regarding Construction
More informationColorado PUC E-Filings System
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. 18A- G IN THE MATTER OF THE VERIFIED JOINT APPLICATION OF BLACK HILLS GAS DISTRIBUTION, LLC, BLACK HILLS/COLORADO GAS UTILITY
More informationAppendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT
Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load
More informationIntroduction to the PJM Markets
Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility
More informationBROCHURE. Portfolio Planning Advisory Services Expert advice to help you turn energy markets strategies into actionable results
BROCHURE Portfolio Planning Advisory Services Expert advice to help you turn energy markets strategies into actionable results 2 BROCHURE PORTFOLIO PL ANNING ADVISORY SERVICES How do you make confident
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * ) ) ) ) ) ) DIRECT TESTIMONY AND EXHIBITS OF SUSAN ARIGONI BEHALF OF
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR
More informationOrganized Markets in WECC 4/18/18
Organized Markets in WECC 4/18/18 Agenda Regional Markets Update Regional Market Activity EIM CAISO Mountain West Peak Reliability / PJM Implications for Resource Planning Resource adequacy Resource selection
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Public Service Company of Colorado ) Docket No.
Page of UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Public Service Company of Colorado ) Docket No. ER- -000 PREPARED TESTIMONY OF JOHN WELCH XCEL ENERGY SERVICES INC. ON BEHALF
More informationFERC Electric Compliance Program: FERC Standards of Conduct Compliance Procedures for Black Hills Corporation s Transmission Providers
FERC Electric Compliance Program: FERC Standards of Conduct Compliance Procedures for Black Hills Corporation s Transmission Providers 1.0 PURPOSE 1.1 To set forth Black Hills Corporation s ( Black Hills
More informationEnergy Market Overview
Energy Market Overview Mashiur Bhuiyan, PhD October 19, 2016 Disclaimer: This presentation is for informational purposes only and is not intended to provide advice or recommendation on any transaction
More informationSeminar on African Electrical Interconnection. Module 7 - Market Operational Structures
Seminar on African Electrical Interconnection Module 7 - Market Operational Structures Module 7 - Market Operational Structures Contents 1) Power Market Principles 2) Major Operational Issues 3) Transmission
More informationATTACHMENT DD. Reliability Pricing Model
OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.
More informationWholesale Electricity Transactions A State Regulatory Perspective
Wholesale Electricity Transactions A State Regulatory Perspective Presentation to the Oregon Public Utility Commission Steve Johnson, Senior Commission Policy Advisor Washington Utilities and Transportation
More informationTrailblazer Pipeline Company LLC Docket No. RP Exhibit No. TPC-0080
Trailblazer Pipeline Company LLC Docket No. RP- -000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Trailblazer Pipeline Company LLC ) ) ) Docket No. RP- -000 SUMMARY OF PREPARED
More informationDemand Response Availability Data Systems Definitions
Demand Response Availability Data Systems Definitions August 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents Table of
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * *
Page of BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO * * * * * RE: IN THE MATTER OF ADVICE LETTER NO. -ELECTRIC FILED BY PUBLIC SERVICE COMPANY OF COLORADO TO REPLACE COLORADO PUC NO.
More information2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005
2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 IEP Objectives Means Objectives Ends (Fundamental) Objectives Agenda Items No net imports
More informationPJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017
PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ELECTRIC STORAGE PARTICIPATION ) IN REGIONS WITH ORGANIZED ) DOCKET NO. AD16-20-000 WHOLESALE ELECTRIC MARKETS ) ) RESPONSE OF THE
More informationPREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY
Application No: A.1-0- Exhibit No.: Witness: Jeff Huang Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Natural Gas Rates
More informationWestern Electricity Coordinating Council WECC Glossary of Terms and Naming Conventions Updated: December 6, 2016
Table of Contents Western Electricity Coordinating Council WECC Glossary of Terms and Naming Conventions Updated: December 6, 2016 Overview/Glossary Characteristics... 2 Terms Developed Using the WECC
More informationBEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP. Direct Testimony of Mark R. Tallman
Docket No. UE Exhibit Witness: Mark R. Tallman BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON PACIFICORP March 0 Tallman/i DIRECT TESTIMONY OF MARK R. TALLMAN TABLE OF CONTENTS QUALIFICATIONS... PURPOSE
More informationTransmission Reliability Margins. Table of Contents. Purpose. Operating Procedure
Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 TRM Value Determination... 3 3.2 TRM Instructions...
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.
Investigation No. -0-0 Exhibit No. Witnesses: Joseph P. Hoerner and Shayleah J. LaBray BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Chapter Direct Testimony of Joseph P.
More informationWhitepaper on PJM Forward Energy Reserve. A Centralized Call Option Market Proposal
Whitepaper on PJM Forward Energy Reserve A Centralized Call Option Market Proposal Jeff Bladen Manager, Retail Markets January 26, 2005 Docs #304175v1 2005 PJM Interconnection Table of Contents Forward
More information3.2 Market Buyers Spot Market Energy Charges.
3.2 Market Buyers. 3.2.1 Spot Market Energy Charges. (a) The Office of the Interconnection shall calculate System Energy Prices in the form of Day-ahead System Energy Prices and Real-time System Energy
More informationIssues in the Determination of Tariffs for Ancillary Services
Issues in the Determination of Tariffs for Ancillary Services Abstract: This paper will begin with a description of ancillary services and then go on to describe the types of ancillary services that are
More informationCurrent Language Proposed Revisions Rationale
1. RAA, Schedule 8.1, Paragraph H (Annexation of service territory by Public Power Entity) 2. In the event a Public Power Entity that is an FRR Entity annexes service territory to include load from a Party
More informationPlatte River Power Authority. Ten-Year Transmission Plan ( )
Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.
More informationAncillary Service Markets
Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;
More informationSTATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION
STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION Rock Island Clean Line LLC ) ) Petition for an Order granting Rock Island ) Clean Line a Certificate of Public Convenience ) and Necessity pursuant to Section
More informationTable of Contents. I. Introduction V. Administration... 12
UM XXXX / PGE / 100 Goodspeed / i Table of Contents I. Introduction... 1 II. Summary of Results... 4 III. Comparison with Utility Scale Proxy... 8 IV. Integration... 11 V. Administration... 12 VI. Qualifications...
More informationPOTENTIAL MARKET CHANGES IN THE WESTERN INTERCONNECTION
POTENTIAL MARKET CHANGES IN THE WESTERN INTERCONNECTION A View from Peak s Pike Caitlin Liotiris November 7, 2017 State of Play in the Western Interconnection Group of utilities located mostly in Colorado
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationLOAD SERVING ENTITIES PJM REGION
Intra-PJM Tariffs --> RELIABILITY ASSURANCE AGREEMENT PJM Interconnection, L.L.C. Rate Schedule FERC No. 44 RELIABILITY ASSURANCE AGREEMENT Among LOAD SERVING ENTITIES in the PJM REGION Effective Date:
More informationWorkshop H. PJM Basics: An Introduction to PJM Interconnection and How its Energy and Capacity Markets Operate
Workshop H PJM Basics: An Introduction to PJM Interconnection and How its Energy and Capacity Markets Operate Tuesday, February 19, 2019 1:45 p.m. to 3 p.m. Biographical Information Adam J. Keech, Executive
More informationMaking Sense of U.S. Energy Markets
Making Sense of U.S. Energy Markets National Conference of State Legislators Task Force on Energy Supply Philip Pettingill, Director Regional Integration January 14, 2017 Two-thirds of the United States
More informationImpacts Associated with EPA Regulations and Gas- Electric Infrastructure Analysis
Impacts Associated with EPA Regulations and Gas- Electric Infrastructure Analysis Platts Transmission Planning & Development Conference, Washington, DC September 11, 2012 John Lawhorn MISO Overview Regional
More informationOutstanding Unresolved Issues
Public Advisory Group Special Session on Analysis for 2018 IRP Outstanding Unresolved Issues as of January 11, 2018 1/11/2018 1 New Issues 1/11/2018 2 Weighted Average Cost of Capital (WACC) should be
More informationIntegrating Renewable Energy Into the Western U.S. Grid: Challenges and Opportunities
Integrating Renewable Energy Into the Western U.S. Grid: Challenges and Opportunities Meeting of the Washington Utilities and Transportation Commission and Energy Regulatory Commission of Thailand Lisa
More informationEnergy Markets - The Basics
Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.
More informationBoardman to Hemingway Transmission Line Project
Transmission Line Project Purpose and Need Meeting Summary South Advisory Area July 8, 2009 Four Rivers Cultural Center 676 SW 5th Avenue Ontario, OR 97914 Table of Contents Introduction... 3 Welcome and
More information2016 Summer Reliability Assessment
Table of Contents Preface... 3 Overview... 5 FRCC... 6 MISO... 7 MRO-Manitoba Hydro... 8 MRO-SaskPower... 9 NPCC-Martimes... 10 NPCC-New England... 11 NPCC-Ontario... 13 NPCC- Québec... 14 PJM... 15 SERC...
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service
More informationTPL 001 AB 0 System Performance Under Normal Conditions
Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure
More informationCon Edison s Brooklyn Queens Demand Management Program
Building Bridges to Net Zero Con Edison s Brooklyn Queens Demand Management Program A Targeted Approach to Load Mitigation in High Growth Neighborhoods Presented by: Eric Kanterman 1 AGENDA What Is Targeted
More informationFrom: Keith Casey, Vice President, Market and Infrastructure Development
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: August 18, 2011 Re: Briefing on Renewable
More informationTRANSMISSION SYSTEM OPERATIONAL AND RELIABILITY BENEFITS TOOL ( SBT ) SBT Workgroup Kick-Off Workshop July 29, Let s turn the answers on.
TRANSMISSION SYSTEM OPERATIONAL AND RELIABILITY BENEFITS TOOL ( SBT ) SBT Workgroup Kick-Off Workshop July 29, 2013 Let s turn the answers on. Agenda SBT Team SBT Background SBT Overview Workgroup Approach
More informationLS Power. Southwest Intertie Project (SWIP) North. NTTG Stakeholder Meeting April 12, Bringing Energy Forward
LS Power Southwest Intertie Project (SWIP) North NTTG Stakeholder Meeting April 12, 2016 LS Power LS Power is a power generation and transmission group Power Generation Transmission Acquisition Over 32,000
More informationTable of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.
Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6
More informationDescription of Current Draft: This is the first draft of the proposed standard posted for stakeholders comment.
Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:
More informationAppendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b
Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b [Appendix 9C1B, Interchange Transaction Reallocation During TLR Levels 3a and 5a ] [Appendix 9C1C, Interchange Transaction
More informationHelp guide ABB Ability Renewable Insights
ISSUED JULY 2018 Help guide ABB Ability Renewable Insights This guide contains essential information needed to operate Renewable Insights. Find tab-by-tab explanations of each dashboard including descriptions
More informationREDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY
REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY PETITION OF PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE D/B/A EVERSOURCE ENERGY
More informationOverview of Issues at the Western Electricity Coordinating Council (WECC)
energy strategies Overview of Issues at the Western Electricity Coordinating Council (WECC) Focusing on those Issues Impacting Independent Generators Presented to The California Independent Energy Producers
More informationPACIFIC POWER A DIVISION OF PACIFICORP
PACIFIC POWER A DIVISION OF PACIFICORP NE Multnomah, Suite 000 Portland, Oregon June 0, 01 VIA ELECTRONIC FILING Public Utility Commission of Oregon 01 High Street SE, Suite 0 Salem, OR 01- Attn: RE: Filing
More informationSenate Bill 350 Study
Senate Bill 350 Study Volume VII: Ratepayer Impact Analysis PREPARED FOR PREPARED BY July 8, 2016 Senate Bill 350 Study The Impacts of a Regional ISO-Operated Power Market on California List of Report
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Oversee the Resource Adequacy Program, Consider Program Refinements, and Establish Annual Local and Flexible
More informationin the NYISO s Market Administration and Control Area Services Tariff ( Services Tariff ).
NYISO 15-25 2015/2016 ICAP Demand Curve Reset RFP 1.3 RFP Objectives, Scope, and Deliverables The objective of this Request for Proposal is to select a consultant to conduct a study of the parameters,
More information2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005
2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability
More informationReforms to Improve Gas-Electric Coordination Mark R. Haskell, Floyd L. Norton, IV, Brett A. Snyder April 29, 2014
Reforms to Improve Gas-Electric Coordination Mark R. Haskell, Floyd L. Norton, IV, Brett A. Snyder April 29, 2014 www.morganlewis.com Presentation Overview Revisions to the operating and scheduling processes
More informationPresentation on Draft SCED RFP
Presentation on Draft SCED RFP Pre-RFP Release Conference October 9, 2014 Presenters: Eric Espenhorst, Seattle City Light Erin Apperson, Puget Sound Energy Robb Davis, BPA Roger Bentz, BPA Kevin Holland,
More informationNew Brunswick Electricity Business Rules. Chapter 3 Reliable Operations
New Brunswick Electricity Business Rules Chapter 3 Reliable Operations TABLE OF CONTENTS CHAPTER 3 RELIABLE OPERATIONS... 2 3.0 System Operator Roles and Responsibilities... 2 3.1 Reliability Assessments...
More informationAn Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004
Independent Electricity Market Operator : An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004 January 6, 2003 Public This page intentionally left blank. IMO_REP_0093v1.1
More informationOverland Consulting Ash Street, Suite 215 Leawood, KS
Robert F. Welchlin, CPA, Director Overland Consulting 11551 Ash Street, Suite 215 Leawood, KS 66211 913-599-3323 rwelchlin@overlandconsulting.com GENERAL Regulatory consultant to the telecommunications,
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Exhibit No.: Commissioner: Peevey Administrative Law Judges: Wetzell and Gottstein Witness: Robert Sparks BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking
More informationAncillary Service Markets
Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;
More informationSRP TRANSMISSION FUNCTION JOB DESCRIPTIONS. October 2010
1 SRP TRANSMISSION FUNCTION JOB DESCRIPTIONS October 2010 The Salt River Project consists of two organizations: the Salt River Project Agricultural Improvement and Power District (SRP), an agricultural
More informationCalifornia s Solar Buildout: Implications for Electricity Markets in the West
California s Solar Buildout: Implications for Electricity Markets in the West EPIS Electric Market Forecasting Conference Las Vegas, Nevada September 7, 2017 Arne Olson, Partner Agenda Report From the
More informationATTACHMENT C. Methodology to Assess Available Transfer Capability
ATTACHMENT C Methodology to Assess Available Transfer Capability Part I - Colorado River Storage Project Management Center, Desert Southwest Region, Rocky Mountain Region, and Sierra Nevada Region (1)
More informationZero Net Carbon Portfolio Analysis
Zero Net Carbon Portfolio Analysis Prepared for: Platte River Power Authority December 5, 2017 This Report was produced by Pace Global, a Siemens business ( Pace Global ) and is meant to be read as a whole
More informationImpacts from Peak Load Reductions in Markets and Long-Range Planning
JUNE 21, 2016 BOSTON, MA Impacts from Peak Load Reductions in Markets and Long-Range Planning MA Energy Efficiency Advisory Council Eric Winkler, Ph.D. TECHNICAL MANAGER, SYSTEM PLANNING Overview of Presentation
More information