1 SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS APPROVED: "----- DATE: 11/14/16 REVISION: Policy The SFPUC Infrastructure Construction projects may require the services of an independent third party to observe and confirm the quality of Contract supplied materials and equipment at the Vendor's fabrication facility. This CM Procedure applies to all personnel working on the SFPUC Infrastructure projects during construction to the extent that their work is affected by these SFPUC Infrastructure CM Procedures and does not conflict with specific San Francisco Public Utilities Commission (SFPUC) policies or the Contract under which the Work is executed. 2.0 Description This procedure defines the requirements, roles and responsibilities for the Supplier Quality Surveillance (SQS) and the surveillance process implementation. 2.1 SOS Overview SQS is a component of Quality Management which is performed at the supplier manufacture or fabrication facility SQS activities are performed for both the (a) City furnished materials and equipment, and (b) Contractor provided materials and equipment. 2.2 Quality Control Activities The SQS Plan activities are NOT a substitute for Quality Control Plan activities performed by SFPUC Suppliers or Contractors at the Vendor's fabrication facility, and no liability is incurred for SQS activities. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 1 of 18

2 3.0 Definitions 3.1 Equipment List The Equipment List is a table of major mechanical and electrical equipment required by a Construction Contract and City furnished equipment. An Equipment List is prepared with the draft SQS Plan for review and approval. Typical information can include the following: Equipment Identification with Tag Number if available; Item Description; Reference Drawing; Specification Reference; Provider (Contractor or City); Comments (including additional item description information); Recommendation for SQS Plan (indicates if part of SQS). Refer to Attachment for draft Equipment List sample. 3.2 Factory Acceptance Tests Factory Acceptance Tests are verifications that specific equipment and their components conform to the performance criteria specified in the Contract Documents Factory Acceptance Tests occur before the materials or equipment are delivered to the construction site SFPUC Infrastructure personnel have the primary responsibility to witness and document the Factory Acceptance Tests The CMB Manager may authorize Independent Third Party Participation /Witness of Factory Acceptance Tests. 3.3 Quality Assurance (QA) Quality Assurance is the element of Quality Management that requires development and implementation of a system of processes and procedures that will enable the SFPUC Infrastructure Team to provide confidence that the products and work meet the quality requirements of the Contract Documents. Quality Assurance surveillance is conducted to verify conformance to specific contract or procedural requirements. 3.4 Quality Control (QC) Quality Control is the element of Quality Management that requires development and implementation of a system of processes and procedures that will enable the Contractor (or Vendor) to verify that the work as constructed complies with the requirements of the Contract Documents Quality Control emphasizes testing as one of the available tools to uncover defects or non-compliance of products to specifications which are made part of the Contract or Purchase Order. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 2 of 18

3 3.4.2 Prior to equipment fabrication, the Contractor or City PO Vendor (Supplier) submits a Quality Control Plan that describes the system for controlling the quality of the parts and materials for SFPUC approval. 3.5 Supplier Quality Supplier Quality is the element of Quality Management that requires development and implementation of a system of processes and procedures that will enable the Supplier to provide confidence that the products and work meet the quality requirements of the Contract Documents. 3.6 SQS Reports SQS Reports are prepared by the SQS Surveillance personnel based on their surveillance of equipment fabrication and/or assembly at the Vendor s fabrication facility and then sent to the SQS Coordinator for review and distribution; refer to Attachment Supplier Quality Surveillance (SQS) SQS is the Progressive Quality system observation at Sources of Manufacture for materials and equipment, specific to the users applied standards, specifications and good Quality Practice prior to Vendor shipment, site arrival, user inspection and purchaser Final Acceptance. 3.8 SQS Non-Compliance Report An SQS Non-Compliance Report is prepared by SQS Surveillance personnel for observed quality deficiencies or non-conformance to specification requirements, refer to Attachment After notification and review of SQS Non-Compliance, the RE prepares and issues a SFPUC Non-Compliance Report to the Contractor in compliance with the Contract Documents The Project Engineer is responsible to issue SFPUC Non- Compliance Reports for City Furnished Materials and Equipment to the Vendor in compliance with the Contract Documents. 3.9 Supplier Quality Surveillance (SQS) Plan The SQS Plan is a description of specification requirements that will be surveilled, and Vendor documentation that will be reviewed, at the Supplier/Vendor or Sub-Vendor fabrication facility. A sample SQS Plan is provided on Attachment Responsibilities 4.1 Contractor The Construction Contractor is responsible for executing the Work to meet all of the requirements of the Contract. The Construction Contractor is SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 3 of 18

4 responsible for Quality Control and Material Testing (as required by the Contract), and for providing verification that the products and services meet these requirements. 4.2 CMB Manager The CMB Manager manages the Construction and Closeout Phases of all SFPUC Infrastructure Projects. The CMB Manager may authorize an independent third party surveillance of Contractor provided materials and equipment. The CMB Manager is responsible for approving the SQS Plan for City furnished and Contractor provided items prepared by the SQS Manager or the PM/PE. 4.3 Resident Engineer (RE) The RE manages the Construction Contract; verifies that the construction work is completed in conformance to the Contract Documents; and determines when contractual action is required related to a quality issue. The RE is responsible for providing Vendor information necessary to plan and execute SQS activities and for following up with the Contractor to address any reported quality non-conformances or deficiencies resulting from SQS activities. The RE coordinates directly with the SQS Manager and/or SQS Surveillance personnel for Contractor furnished quality or production schedule issues at the Vendor s fabrication facility. 4.5 Project Engineer (PE) The Project Engineer oversees the development of the technical specifications and the quality requirements specified therein. The PE is also responsible for defining the quality requirements for vendors providing City furnished materials and equipment, the storage requirements, and the requirements for acceptance and verification by the Contractor The PE serves as the primary point of contact with the Engineer(s) of Record for the project for all Vendor quality issues The PE is responsible for conducting and/or arranging for Factory Acceptance Test(s) witness and documentation performed by the SFPUC Infrastructure CM Team. 4.6 Project Manager (PM) The PM works with the PE to review and provide input to the draft Equipment List and draft SQS Plan. The PM is also responsible for providing all Vendor information, from the PE, to the SQS Coordinator for City furnished materials and equipment upon award of a Purchase Order. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 4 of 18

5 4.7 Program Quality Manager (PQM) For major capital improvement programs, the individual functioning in the role of the Program Quality Manager develops the requirements, business processes, procedures and training for quality assurance applications during construction. In the absence of the PQM the PCM will take over this role The PQM monitors and audits compliance by the CM Teams with quality assurance procedures and requirements and consistent enforcement of the Contract terms related to quality The PQM assists the SQS Coordinator with monitoring the construction contract Notice to Proceed dates and obtaining from the RE Vendor information for SQS items The PQM assist with follow-up and resolution of SQS Non- Conformances and deficiencies reported by SQS Surveillance personnel. 4.8 Construction Manager (CM) The CM directs the CM team members, including managing the REs and implementation resources. 4.9 Supplier Quality Surveillance (SQS) Coordinator The SQS Coordinator is responsible for the SQS coordination efforts throughout multiple projects or multiple fabrication sites within a project and include: Interfaces with PM and PE for SQS Plan comments and notifies SQS Manager of any issues needed for resolution; Coordinates and manages any Sub-Consultant firms providing direct SQS support services; Notifies designated SFPUC RE of SQS Pre-Surveillance Meeting; Assigns SQS Surveillance personnel for all initial, interim and final surveillance; Distributes SQS Reports and Non-Compliance to SFPUC Project Engineer, PM, CM and PQM. Is responsible for preparing the draft Equipment List and SQS Plan. Maintains the SQS files for their assigned project purchase orders until completion of the assignment for turnover to the SFPUC SQS Surveillance Inspector SQS Manager and SQS Surveillance Inspector conduct periodic observation and inspection of the designated City furnished and Contractor furnished equipment and material at the source of fabrication and assembly other than the construction site. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 5 of 18

6 SQS Surveillance Inspector shall: 4.11 Vendor Review SFPUC approved Project SQS Plan and develop surveillance plans for each item and Vendor. Arrange for the Pre-Surveillance Meeting with Vendor and notify the SQS Coordinator. Conduct Pre-Surveillance Meeting with each Vendor and/or Contractor to review quality requirements and Vendor QC plans, and fabrication schedules. Conduct an independent third party quality surveillance and fabrication progress status for each item pursuant to the SQS Plan approved by the SFPUC. Witness equipment performance Factory Acceptance Tests, if requested. Prepare and submit SQS Surveillance Reports including SQS Non-Compliance Reports to SQS Coordinator. Notify SQS Coordinator of critical issues or additional follow-up QA activities required. The Vendor (aka: Supplier) provides the contract materials and equipment to the Contractor to complete the Work The Vendor and Sub-Vendor (if needed) provide the following materials and equipment information through the RE (for Contractor furnished) or PE (for City furnished) to the SQS Coordinator for each SQS item: Factory Name, Location, Contact Representative Name and Telephone Number; Purchase Order (without contract price), specifications and Quality Control requirements; Scope of Supply; Material or Equipment Data Sheets (for each item identified by Tag Number); Inspection and Test Plans; Factory Acceptance Test Procedure; Vendor Fabrication Schedules; Same information as above required for Sub-Vendors of major components. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 6 of 18

7 The Project Engineer is the Vendor contact for City Furnished Materials and Equipment until acceptance by the RE at the Construction site. 5.0 Implementation 5.1 SQS Plan Development and Approval Project Manager provides 95% Construction drawings and specifications, and final drawings and specifications for City furnished equipment to SQS Coordinator. (Project Manager is also responsible for providing any bid addenda to the SQS Coordinator that changes drawings or specifications.) SQS Manager submits Draft Equipment List to PM and PE for review PM and PE review draft Equipment List and PM forwards comments to SQS Coordinator SQS Manager discusses any differences with PM for decision SQS Manager updates Draft Equipment List and drafts SQS Plan SQS Coordinator submits documents to CMB Manager for approval CMB Manager obtains input from PM and PE, approves SQS Plan and returns to the SQS Coordinator SQS Manager updates SQS Plan as needed and SQS Coordinator sends final version to the PM and CMB Manager. 5.2 Pre-SQS Plan Implementation SFPUC issues Purchase Order /Construction Contract NTP RE provides the Vendor Information to the SQS Coordinator from the Contractor, refer to Attachment Project Manager provides the City awarded Purchase Order and Vendor information for City furnished equipment to the SQS Coordinator SQS Coordinator develops Task Assignments for surveillance activities and assigns the SQS Surveillance Inspector for all initial, interim and final surveillance activities. 5.3 SQS Plan Implementation The designated SQS Surveillance Inspector arranges for the Pre- Surveillance Meeting with each Vendor and/or Contractor, notifies the SQS Coordinator. The SQS Coordinator notifies the designated RE and PE for their optional attendance. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 7 of 18

8 5.3.2 The SQS Surveillance Inspector conduct the Pre-Surveillance Meeting to review quality requirements, Vendor QC Plans and fabrication schedules SQS Surveillance Inspector perform surveillance activities at Vendor s fabrication facility. 5.4 SQS Reporting The SQS Surveillance Inspector submits SQS Reports to the SQS Coordinator; refer to Attachment The SQS Reports include discussion of activities observed, fabrication progress, deficiencies observed and any Non- Compliance Reports deemed necessary by the SQS Surveillance personnel. 5.5 Factory Acceptance Tests Factory Acceptance Tests are in-factory testing that verify specific equipment components conformance to the required performance specified by the Contract Documents before the equipment is delivered to the construction site Factory Acceptance Tests are witnessed and documented by an SQS Surveillance Report by the Project Engineer or designee The CMB Manager can authorize the SQS Surveillance Inspector to participate in Factory Acceptance Tests 5.6 SQS Plan Close-out The SQS Coordinator transmits the SQS files to the RE at the completion of the project assignment. 6.0 Other Procedural Requirements 6.1 SQS Plan Develop Supplier Quality Surveillance (SQS) Plan (for each project). 6.2 SQS Vendor Shop Schedule Incorporate SQS Vendor Shop Schedule into CM Schedule. 6.3 Transfer of Responsibility Transfer City Furnished Materials and Equipment responsibilities from Project Engineer to RE at Work Site. 6.4 SQS Exceptions PE shall notify and provide documentation to RE any SQS item exception allowed at the Vendor Shop which was deferred to the Field. SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 8 of 18

9 7.0 References 7.1 Technical Specifications Section Product Requirements Section Owner-Furnished Products 7.2 CM Procedures No. 015 City Furnished Materials and Equipment No. 028 Construction Quality Management 7.3 Others SFPUC Infrastructure Construction Management Plan 8.0 Attachments Draft Equipment List Sample Supplier Quality Surveillance (SQS) Plan Sample Pre-Surveillance Meeting Report Sample Form Contractor Provided Vendor Information- AWWA C504 Butterfly Valves SQS Report Sample Format SQS Non-Conformance Report Revision Control Log SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 9 of 18

10 Attachment Draft Equipment List Sample SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 10 of 18

11 Attachment Page 1 of 2 SQS Plan/Check List Sample SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 11 of 18

12 Attachment Page 2 of 2 SQS Plan/Check List Sample SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 12 of 18

13 Attachment Page 1 of 2 Pre-Surveillance Meeting Report Sample Form SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 13 of 18

14 Attachment Page 2 of 2 Pre-Surveillance Meeting Report Sample Form SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 14 of 18

15 Attachment Contractor Provided Vendor Information- AWWA C504 Butterfly Valves SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 15 of 18

16 Attachment SQS Report Sample Format SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 16 of 18

17 Attachment SQS Non-Conformance Report SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 17 of 18

18 Attachment Revision Control Log Revision No. Revision Date What changed? Rev 0 11/14/16 Signed SFPUC Infrastructure CM Procedure No. 032, Revision 0, Page 18 of 18

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEM ENT APPROVED: PROCEDURE NO.: 026 DATE: 08I109 TITLE: SQS

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT BUSINESS PROCESSES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT BUSINESS PROCESSES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT BUSINESS PROCESSES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: BUSINESS PROCESS NO.: 000 DATE: 03/16/09

More information

Quality Assurance Policy and Procedures

Quality Assurance Policy and Procedures 650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 01 40 00 QUALITY REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Quality control and control of installation. Tolerances. References. Labeling. Mock-up requirements. Testing and inspection

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26

NR CHECKLIST Rev. 1. QAM IMP References NBIC Part 3, 1.8 Y N Y N a. Organization. Company Name/Certificate Number: Page 1 of 26 Company Name/Certificate Number: Page 1 of 26 a. Organization a.1. Has the Organizational Structure of the program identified the levels of management responsible for the Quality System Program, including

More information

Revision 3. Construction Management Plan. Rebuilding Today for a Better Tomorrow

Revision 3. Construction Management Plan. Rebuilding Today for a Better Tomorrow Revision 3 Construction Management Plan Rebuilding Today for a Better Tomorrow March 2009 Contents Section 1 WSIP Organization 1.1 Introduction and Purpose 1 1.2 Scope 2 1.3 Description of the 2 1.4 Construction

More information

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018 1.0 SCOPE This document establishes the quality program requirements for an organization providing engineering

More information

Transbay Transit Center Program

Transbay Transit Center Program Transbay Transit Center Program Quality Management System Manual Revision 1 September 2013 Quality Management System Manual Revision 1 September 2013 Prepared for the Transbay Joint Powers Authority

More information

SECTION 6.2: CONTRACT MANAGER

SECTION 6.2: CONTRACT MANAGER : Section 287.057(15), Florida Statutes, requires the department, for each contractual service contract, to designate an employee to be responsible for enforcing the performance of the contract terms and

More information

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017

Association of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017 Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program

More information

Page 1 / 11. Version 0 June 2014

Page 1 / 11. Version 0 June 2014 Page 1 / 11 CORRESPONDENCE MATRIX NQSA NSQ-100 version 0 NUCLEAR SAFETY AND QUALITY MANAGEMENT SYSTEM REQUIREMENTS Model for quality management in design & development, manufacturing, erection, commissioning

More information

ITER Quality Assurance

ITER Quality Assurance US ITER Central Solenoid Vendor Meeting ITER Quality Assurance by John Mashburn USIPO QA Manager 1 QA Topics ITER s Nuclear License Graded Approach Proposal QA Items Quality Plan Specific to Contract Manufacturing

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual February 2010 Page 1 of 6 Table of Contents 1.0 Purpose 2.0 Scope 3.0 Quality System Requirements 4.0 Supplier Assessments 5.0 Advance Product Quality Planning 6.0 First Article

More information

MANUAL QUALITY CONTROL & QUALITY ASSURANCE

MANUAL QUALITY CONTROL & QUALITY ASSURANCE MANUAL QUALITY CONTROL & QUALITY ASSURANCE METROTEC ENGINEERING LLC P.O. BOX: 26045, DUBAI U.A.E TEL : 043889771 FAX:043889772 E Mail: metrotecengg@yahoo.com info@metrotec.ae Web: www.metrotec.ae 2 TABLE

More information

QUALITY ADMINISTRATIVE PROCEDURE

QUALITY ADMINISTRATIVE PROCEDURE NYE COUNTY NUCLEAR WASTE REPOSITORY PROJECT OFFICE QUALITY ADMINISTRATIVE PROCEDURE TITLE: Procurement of Items and Services REVISION: 1 DATE: PAGE: 1 of 8 PROCEDURE NUMBER: QAP-7.1 SUPERSEDES: Revision

More information

INSPECTION SYSTEM REQUIREMENTS

INSPECTION SYSTEM REQUIREMENTS MILITARY SPECIFICATIONS MIL-I-45208A INSPECTION SYSTEM REQUIREMENTS This specification has been approved by the Department of Defense and is mandatory for use by all Agencies. 1. SCOPE 1.1 Scope. This

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

ALL-IN-ONE CLOUD BASED CITIZEN SERVICE PLATFORM FOR PERMITTING, LICENSING, INSPECTIONS, AND ENFORCEMENT

ALL-IN-ONE CLOUD BASED CITIZEN SERVICE PLATFORM FOR PERMITTING, LICENSING, INSPECTIONS, AND ENFORCEMENT City of McMinnville, Community Development Department ALL-IN-ONE CLOUD BASED CITIZEN SERVICE PLATFORM FOR PERMITTING, LICENSING, INSPECTIONS, AND ENFORCEMENT Bid Document Nolan Ming 10/11/2017 ALL-IN-ONE

More information

2.2. The Seller shall be responsible for achieving and maintaining a quality performance level of either:

2.2. The Seller shall be responsible for achieving and maintaining a quality performance level of either: 2.0. Supplier Quality Performance: 2.1. When requested by Boeing, Seller agrees to work with Boeing to develop and implement processes designed at improving Seller s quality performance. Process will include

More information

Definitions contained in the above mentioned document and industry regulations are applicable herein.

Definitions contained in the above mentioned document and industry regulations are applicable herein. Quality Specification TEC-1021 21May12 Rev E Global Quality Management System Supplement for Various International Nuclear Quality Assurance Criteria, Regulations, and Requirements 1. SCOPE 1.1. Content

More information

Regulations of the Euromate Quality Management- and Social Compliance Process

Regulations of the Euromate Quality Management- and Social Compliance Process May 12th, 2009 Regulations of the Euromate Quality Management- and Social Compliance Process Dear valued Business Partner, Lux and Euromate are responsible for the global sourcing and development of private

More information

Quality Assurance Manual

Quality Assurance Manual Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved: VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Revisions to Chapter VII of Manual of Instructions Materials Acceptance and Materials Notebook Program NUMBER: MD 407-17

More information

ISO 9001:2008 and AS9100 Rev. C. Supplier Quality Manual

ISO 9001:2008 and AS9100 Rev. C. Supplier Quality Manual ISO 9001:2008 and AS9100 Rev. C Supplier Quality Manual ffective Date: Section I Supplier (same as xternal Provider) xpectations 1.0 Introduction 2 of 7 This Supplier Quality Manual (SQM) has been created

More information

Quality Supplier Requirements for Beckwith Electric Co., Inc.

Quality Supplier Requirements for Beckwith Electric Co., Inc. Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality

More information

Quality Management System

Quality Management System Quality Management System 6.1 Quality Q-Codes () 6.1 Quality Q-Codes Quality Clauses The following quality control clauses apply when specifically noted on the Gear Technology purchase order: Q1- Material

More information

SUPPLIER QUALITY REQUIREMENTS

SUPPLIER QUALITY REQUIREMENTS SUPPLIER QUALITY REQUIREMENTS TABLE OF CONTENTS 1) PURPOSE PG 2 2) KINNEAR PURCHASE ORDER PG 2 3) USE AND COMMUNICATION PG 2 4) SUPPLIER APPROVAL PG 2 5) GENERAL REQUIREMENTS PG 3 SQD Rev 2 2014-08-13

More information

Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70

Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70 Controlled By: QA Mgr. / Gen. Mgr. Effective Date: 3/31/2014 FORM-70 RUSSTECH PURCHASE ORDER CLAUSES RPOC 1000 EARLY DELIVERY OK "Time is of the essence for performance under this Purchase Order. Seller

More information

FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM

FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM FAIRFIELD GLOBAL SUPPLIER QUALITY PROGRAM 1 QA.101 rev. 3-2012 PURPOSE OF THIS STANDARD Fairfield is committed to continuous product quality improvement. Our management team is convinced that only with

More information

STANDARD QUALITY ASSURANCE PROVISIONS FOR PURCHASED MATERIALS

STANDARD QUALITY ASSURANCE PROVISIONS FOR PURCHASED MATERIALS 1. GOVERNMENT/CUSTOMER SOURCE INSPECTION: a. Government/Customer inspection is required prior to shipment from your plant. Upon receipt of this order, promptly notify the Government/Customer representative

More information

Title: PROCUREMENT QUALITY REQUIREMENTS CWCDS Dayton, OH

Title: PROCUREMENT QUALITY REQUIREMENTS CWCDS Dayton, OH Page 1 of 7 QUALITY CLAUSES Clause A - Quality System Requirements All references to the term "Government" in any of the documents referenced below shall be replaced with the term "Curtiss Wright Controls

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual 1 1. Introduction Scope Purpose Application Implementation 2. Purchasing Expectations Terms and Conditions Engineering / Technical Support Customer Support Resources Pricing Consistent

More information

Appendix QI. Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items

Appendix QI. Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items Intra-Lockheed Martin Work Transfer Agreement (IWTA) Quality Requirements for Deliverable Items REVISION RECORD The latest issue to this document is the version that is available on the Lockheed Martin

More information

PMA Quality Assurance Manual Rev. 2 Date 12 Feb 2016

PMA Quality Assurance Manual Rev. 2 Date 12 Feb 2016 PMA Quality Assurance Manual Date Aviation Technical Services, Inc. 3121 109 th Street SW Everett, WA 98204 425-423-3371 2600 West Casino Road Everett, WA 98204 10315 Airport Road Everett, WA 98204 www.atsmro.com

More information

Work Instruction PUI Supplier Request for Nonconforming Material (Rev 1)

Work Instruction PUI Supplier Request for Nonconforming Material (Rev 1) 1.0 Purpose To provide Insitu suppliers a method to request Insitu s authority to supply/ship nonconforming material (NCM). This document defines how the Supplier Nonconforming Material Request (NCMR)

More information

2012 VIRGINIA INDUSTRIALIZED BUILDING SAFETY REGULATIONS

2012 VIRGINIA INDUSTRIALIZED BUILDING SAFETY REGULATIONS 13VAC5-91-10. Definitions. The following words and terms when used in this chapter shall have the following meanings unless the context clearly indicates otherwise. Administrator means the Director of

More information

CORPORATE QUALITY SYSTEM PROCEDURE

CORPORATE QUALITY SYSTEM PROCEDURE Number: JVICQC-1.0 Revision: 6 11/29/2011 Page 1 of 10 Approvals Author Quality System Manager Name: Randy Bennett Doyle Cassity Signature: Date: 11/29/2011 11/29/2011 Electronic versions of this procedure

More information

Quality Manual ISO 9001:2000

Quality Manual ISO 9001:2000 Quality Manual ISO 9001:2000 Page 2 of 23 TABLE OF CONTENTS COVER PAGE...1 TABLE OF CONTENTS...2 SIGNATURES...3 QUALITY POLICY...4 INTRODUCTION...5 CORPORATE PROFILE...9 4.O QUALITY MANAGEMENT SYSTEM...10

More information

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A

QUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production

More information

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC.

1.2 The engineer will provide Quality Assurance (QA) inspection. The role of QA is to verify the performance of the QC. Quality Management Quality Management is a pro-active and efficient method of incorporating quality into the planning and scheduling of all project activities. The contractor works together with the engineer

More information

TEXAS DEPARTMENT OF TRANSPORTATION

TEXAS DEPARTMENT OF TRANSPORTATION TEXAS DEPARTMENT OF TRANSPORTATION SPECIFICATION NO. PREVENTIVE MAINTENANCE AND REPAIR SERVICES FOR APOGEE BUILDING AUTOMATION MANAGEMENT SYSTEM PUBLICATION This specification is a product of the Texas

More information

SURPLUS USABLE PERSONAL PROPERTY

SURPLUS USABLE PERSONAL PROPERTY SURPLUS USABLE PERSONAL PROPERTY Request for Technical Proposal Number 18-0340 STEP ONE OF TWO - STEP SOLICITATION October 10, 2017 Surplus Usable Property Requirements and Criteria for Technical Proposals

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL DATE: February 24, 2015 Shimizu North America LLC 909 3rd Avenue, 28th Floor New York, NY 10022 RFP Queries (646) 205-4722 Fax (212) 223-1930 PROJECT: The Japan Foundation New York

More information

Interim Turnover Check List

Interim Turnover Check List Page 1 of 4 Quality Control Checklist Index 01701 - Interim Turnover Check List THIS CHECKSHEET IS NOT INTENDED TO BE ALL INCLUSIVE BUT TO BE A GUIDE TO CRITICAL ISSUES AND CAUSE QUESTIONS TO BE ASKED.

More information

Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering. July 17, 2011

Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering. July 17, 2011 Design-Builder Quality Control System Paul Moyer, P.E., Gill Engineering July 17, 2011 Project Quality Assurance Program Quality Assurance All those planned and systematic actions necessary to provide

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

Work Instruction PUI Supplier Request for Nonconforming Material (Rev 2)

Work Instruction PUI Supplier Request for Nonconforming Material (Rev 2) 1.0 Purpose To provide Insitu suppliers a method to request Insitu s authority to supply/ship nonconforming material (NCM). This document defines how the Supplier Nonconforming Material Request (NCMR)

More information

Bulk Metals Qualified Suppliers List for Distributors (QSLD) Criteria and Provisions

Bulk Metals Qualified Suppliers List for Distributors (QSLD) Criteria and Provisions Bulk Metals Qualified Suppliers List for Distributors (QSLD) Criteria and Provisions PREFACE The DLA Troop Support Construction and Equipment Supply Chain (C & E) has instituted a Qualified Suppliers List

More information

1880 Highway 116 P.O. Box 53 Caryville, TN Fax

1880 Highway 116 P.O. Box 53 Caryville, TN Fax 1880 Highway 116 P.O. Box 53 Caryville, TN 37714 865-426-2141 800-274-2100 Fax 865-426-2011 www.a-s.com Descriptions and specifications contained herein were in effect at the time this publication was

More information

CALCULATION COVER SHEET

CALCULATION COVER SHEET Doc. No.: DQP410FA Rev. Page DQP410FA - 1 of 1 CALCULATION COVER SHEET Calculation Title: Calculation Number: Total Number of Pages (including cover sheet): Total Number of Computer Runs: Prepared

More information

Terms & Conditions Case Study:

Terms & Conditions Case Study: EDUCATION & RESEARCH FOUNDATION Terms & Conditions Case Study: The Tale of TED Electric Supply This research study has been generously sponsored by the NAED Education & Research Foundation s Channel Advantage

More information

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT Desk Audit of Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT-90-5001-02.1 Reviewed by: Element Requirements Applicable 1. Is a quality policy defined

More information

RESIDENT ENGINEER S MANUAL

RESIDENT ENGINEER S MANUAL Peninsula Corridor Joint Powers Board 1250 San Carlos Avenue San Carlos, California 94070-1306 RESIDENT ENGINEER S MANUAL Revision 2 Page 1 of 336 Caltrain Standard Manual RESIDENT ENGINEER S MANUAL Manual

More information

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms.

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms. Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms August 29, 2017 2017 by Texas Department of Transportation 512/506-5808 All

More information

Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan)

Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan) Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:

More information

MBCI Weathertightness WARRANTIES

MBCI Weathertightness WARRANTIES MBCI Weathertightness WARRANTIES WEATHERTIGHTNESS WARRANTIES MBCI believes if the building owner has to file a claim against the roof manufacturer s Weathertightness Warranty, then someone has not done

More information

NAVSEA STANDARD ITEM. 2.2 ANSI/ISO/ASQ Q , Quality Management Systems - Requirements

NAVSEA STANDARD ITEM. 2.2 ANSI/ISO/ASQ Q , Quality Management Systems - Requirements NAVSEA STANDARD ITEM ITEM NO: 009-04 DATE: 30 JUL 2015 CATEGORY: I 1. SCOPE: 1.1 Title: Quality Management System; provide 2. REFERENCES: 2.1 Standard Items 2.2 ANSI/ISO/ASQ Q9001-2008, Quality Management

More information

SHELTON INDUSTRIAL PATTERN INC.

SHELTON INDUSTRIAL PATTERN INC. Defintions: Seller : Supplier of materials, parts and or services that support production Supplies : materials, parts that support production FOD : Foreign Object Debri / Damage 1. Quality Management System

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual Document No. F-PM010 Rev 3 Owner Supplier Quality Page 1 OF 11 TABLE OF CONTENTS 1.0 Purpose 3 2.0 Scope... 3 3.0 Quality System Requirements... 3 4.0 Approved Supplier List (ASL).

More information

Supplier Requirements Retail Information Svcs LLC Fastener Division

Supplier Requirements Retail Information Svcs LLC Fastener Division Supplier Requirements Retail Information Svcs LLC Fastener Division REVISION : 1 PAGE 1 of 11 TABLE OF CONTENT SECTION PAGE Supplier Evaluation and Selection Process 3 Supplier Performance Evaluation 4

More information

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1. PROBUILD SUBCONTRACTOR QUALITY MANAGEMENT GUIDE Section Two Project Specific Quality Management Plans Version No 1. PREFACE This document has been developed to assist subcontractors to meet Probuild s

More information

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION

ROUND LAKE AREA SCHOOLS DISTRICT 116: LIMITED COMMISSIONING GUIDELINES INTRODUCTION INTRODUCTION Commissioning (Cx) is a quality assurance process that works to ensure the design intent of a building is fully realized. It requires a systematic approach to review, verify, and document

More information

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev - February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February

More information

Corrective Action(s) System Procedure

Corrective Action(s) System Procedure Page: 1 of 7 Corrective Action(s) System Procedure Page: 2 of 7 1.0 PURPOSE AND SCOPE 1.1 Purpose 1.1.1 To define the methods for preventive action, nonconformance trend identification, customer complaints/concerns

More information

City of Olivette Request for Qualifications Furniture Procurement and Installation April 26, 2016

City of Olivette Request for Qualifications Furniture Procurement and Installation April 26, 2016 General Information The City of Olivette (City) is seeking a qualified firm to provide procurement, installation, and warranty service related to furnishings and furniture at the City s new Municipal Center.

More information

ASA-100 QUALITY MANUAL

ASA-100 QUALITY MANUAL Your Company Name ASA-100 QUALITY MANUAL Origination Date: XXXX Document Identifier: Date: Document Revision: QMS-00 Quality Manual Latest Revision Date Abstract: This quality manual describes (your Company's)

More information

External Provider Quality Requirements QCS-001 Processing Sources

External Provider Quality Requirements QCS-001 Processing Sources Page 1 of 11 The latest issue to this document is the version that is available on the Lockheed Martin Logistics Services Supplier Quality Management website: http://www.lockheedmartin.com/us/suppliers/bu-info/aeronautics/sustainment-services.html

More information

TABLE OF CONTENTS F 600 SEWER CONSTRUCTION SECTION NO. SUBJECT DATE

TABLE OF CONTENTS F 600 SEWER CONSTRUCTION SECTION NO. SUBJECT DATE 6/92 F 600 TABLE OF CONTENTS F 600 SEWER CONSTRUCTION SECTION NO. SUBJECT DATE F 610 RESPONSIBILITIES OF THE ENGINEER June-92 F 611 REVISION OF PLANS " F 612 INTERPRETATION OF SEWER PROJECT PLANS AND "

More information

STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC

STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC PREPARED BY: Metropolitan Washington Airports Authority Washington Dulles International Airport Engineering

More information

Janitorial QA/QC Manual Sample

Janitorial QA/QC Manual Sample Janitorial QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Janitorial Services Operating Policies

More information

SIKORSKY AIRCRAFT TOOLING BULLETIN SA7303 December 15, 2015

SIKORSKY AIRCRAFT TOOLING BULLETIN SA7303 December 15, 2015 Sikorsky Aircraft Tooling Bulletin Page 1 of 9 1.0 INTRODUCTION: Most Special Tooling (ST) used by Sikorsky suppliers is provided by Sikorsky or through Government funding. This document establishes supplier

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

AS9003A QUALITY MANUAL

AS9003A QUALITY MANUAL Your Logo AS9003A QUALITY MANUAL Origination Date: (month/year) Document Identifier: Date: Document Status: Document Link: AS9003A Quality Manual Latest Revision Date Draft, Redline, Released, Obsolete

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Conflict of Interest Language

Conflict of Interest Language Project Development - Design Services The Consultant and subconsultants shall disclose in the Transmittal Letters that accompany the Statement of Qualifications (SOQ), all contracts or projects for which

More information

SUPPLIER GUIDELINES MANUAL

SUPPLIER GUIDELINES MANUAL 1.0 INTRODUCTION 1.1 This guidelines manual defines the minimum requirements for Supreme Machined Products Co.; Inc. LTD (to be referenced as Supreme throughout the document) Supplier s and does not supersede

More information

Quality Manual. AARD Spring & Stamping Quality Manual

Quality Manual. AARD Spring & Stamping Quality Manual Quality Manual Page 1 of 25 AARD Spring & Stamping QM/5.0 Title: QM 5.0 AARD Spring & Stamping Quality Manual Copy Approval Date: 1/27/2011 Reviewer(s): Sign / Print Title Date Dan Wheeler Document Originator

More information

INTRODUCTION. New Mather Metal Incorporated specializes in manufacturing quality stabilizer bars for suspension systems for the automotive industry.

INTRODUCTION. New Mather Metal Incorporated specializes in manufacturing quality stabilizer bars for suspension systems for the automotive industry. INTRODUCTION Welcome to, New Mather Metal Inc. (NMMI) New Mather Metal Incorporated specializes in manufacturing quality stabilizer bars for suspension systems for the automotive industry. You can view

More information

Quality Management System Manual

Quality Management System Manual This Page 1 of 47 of the Quality Management System Manual If issued as a controlled copy, the serial number of this copy is Quality Management System Manual Certified to AS9100 Revision C Printed copies

More information

SANAS Transition Policy: ISO/IEC 17020: 2012

SANAS Transition Policy: ISO/IEC 17020: 2012 SANAS Transition Policy: ISO/IEC 17020: 2012 CONTENTS 1 Introduction 2 Transition to ISO/IEC 17020 3 Specific changes in requirements Appendix A: Summary of changes Appendix B: Cross References: ISO/IEC

More information

Guidelines. on imports of organic products into the European Union

Guidelines. on imports of organic products into the European Union EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR AGRICULTURE AND RURAL DEVELOPMENT Directorate H. Sustainability and quality of agriculture and rural development H.3. Organic farming 15.12.2008 Guidelines on

More information

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy POLICY MANUAL FOR ISO 9001:2008 Document: PM-9001:2008 Date: April 7, 2015 REVIEWED BY: Tim Powers DATE: 4-7-2015 APPROVED BY: C._Bickford Uncontrolled Copy DATE: 4-7-2015 1.0 GENERAL ISS: 1 REV: E Page:

More information

2017 Archaeology Audit Program Procedure Manual. April 2017

2017 Archaeology Audit Program Procedure Manual. April 2017 2017 Archaeology Audit Program Procedure Manual April 2017 Table of Contents Contents Table of Contents... 2 1.0 Introduction and Scope... 3 2.0 Audit Objectives... 3 3.0 Audit Procedures... 4 3.1 Audit

More information

There is an inspection report prepared after the Digester cleaning was carried out.

There is an inspection report prepared after the Digester cleaning was carried out. TERMS OF REFERENCE FOR CONSTRUCTION MANAGEMENT AND INSPECTION FOR THE REPAIRS AND GASPROOFING OF DIGESTER NO.2 AT THE GUELPH WASTEWATER TREATMENT PLANT BACKGROUND The work generally consists of Repairs

More information

Vendor Qualification Survey

Vendor Qualification Survey 1200 West 96 th St Minneapolis, MN 55431 Ph: 952-888-7900 Fax: 952-888-2719 Vendor Qualification Survey Vendor Information Company Name: Date: Address: City: Phone Number: email address: Product or Service

More information

Main Building Auditorium

Main Building Auditorium Main Building Auditorium Theatre and Lighting Upgrade Moberly Area Community College 101 College Avenue Moberly, Missouri This document contains all necessary instructions and specifications to perform

More information

ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1

ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 ASME As a Help to Export! Our Topic today: Nuclear Quality Assurance ASME NQA 1 Karte: Wikipedia CIS GmbH Experts in ASME Code Consulting CIS GmbH Consulting Inspection Services 3 rd Party Inspection Training

More information

Supplier Quality Assurance Requirements

Supplier Quality Assurance Requirements Supplier Quality Assurance Requirements Supplier Quality Assurance Requirements ARQM 005.3 Issue Date: 17/12/2013 1 1 Table of Contents 1. Table of Contents...2 2. Purpose.3 3. General Requirements 3 4.

More information

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Review MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Introduction to Quality Management Dave Ahlvers, P.E. Review of Job Special Provision & Terms Dennis

More information

Design-Builder Peformance Evaluation (DBPE)

Design-Builder Peformance Evaluation (DBPE) Design-Builder Peformance Evaluation (DBPE) There are five (5) major components of the DBPE document. Each component has multiple categories to facilitate performance evaluation for the Design-Builder,

More information

Supplier Quality Manual

Supplier Quality Manual ALLIANCE ELECTRONICS DISTRIBUTOR Supplier Quality Manual 22412 Gilberto Rd. Rancho Santa Margarita, CA 92688 INTRODUCTION Welcome to Alliance Electronics Distributor (AED) Alliance Electronics Distributor

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS December 15, 2014 Secured Document Shredding Services Project 2014-2015 Due 10:00 AM CST/CDT Tuesday, January 20, 2015 Company Name: Contact Information: Printed Name & Title Address,

More information

FLYSHEET 100 Rev. 14 QUALITY SYSTEM REQUIREMENTS

FLYSHEET 100 Rev. 14 QUALITY SYSTEM REQUIREMENTS FLYSHEET 100 Rev. 14 QUALITY SYSTEM REQUIREMENTS In addition to the applicable Quality System Code incorporated in this contract, Seller shall comply with the requirements of Section 2.0, titled Additional

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: PROCEDURE NO.: 015 DATE: 08I'4I09 TITLE: CONSTRUCTION

More information