Operations Model Follow-up. February 18, 2015

Size: px
Start display at page:

Download "Operations Model Follow-up. February 18, 2015"

Transcription

1 Operations Model Follow-up February 18, 2015

2 Key Takeaways Follow-up for questions raised at January Operations Models presentation 2

3 Network Model RTLODFC Real-Time Line Outage Distribution Factor Calculator Backup to the RTCA Does not require a State Estimator solution to run Alstom EMP version 2.6, RTLODFC is a standard product MISO has customized Integrated NETSENS 3

4 Network Model How is sub-transmission distinguished from transmission in the Network Model? There is no flag in the MISO Network Model to distinguish between sub-transmission and transmission This designation is different within each area MISO monitors all equipment within the Bulk Electric System definition MISO monitors equipment that has been turned over to MISO function control (Appendix H designation) for overloads and redispatch 4

5 Commercial Model SSR (System Support Resource) information part of Attachment B generator registration? No. 5

6 DART Model State Estimator Powerflow solution Losses Calculation RTCA Contingent Solution Constraints identified Clogger Calculates generator shift factors for constraint Assigns benefit or penalty to the constraint DART Includes constraint in next solution Unit Dispatch System (UDS) optimizes dispatch Assigns financial component 6

7 Current case FTR/ARR Model Current quarterly network model used for base of monthly auctions all incoming equipment doublemodeled as necessary FTRs are settled against Day-Ahead prices. Important to utilize the same model base Modify base each month by applying planned outages to more accurately reflect system conditions Granularity of monthly auctions ensure stakeholders are not restricted for months outside of the outage period 7

8 Future Cases FTR/ARR Model Yearly cases built in March using MOD projects submitted by TO. Assumptions made on system conditions could impact FTR funding shortfalls where MISO can only fund a portion of the expected FTR value. 8

9 MOD Basecase Daily Offline Outage Coordination Studies Basecase plus SDX outages, forecast, dispatch What is the Generation Dispatch file? Merit order list of how to move generation Contains generator type and historical position MISO created 9

10 MOD Basecase - TSP Transmission Security Planning (TSP) Models Primary Function Provide Day-Ahead and Forward Reliability Assessment Commitment (FRAC) process with constraints necessary to produce a reasonable unit commitment. Build a next day model and post analysis results (S Case) Determine and post Reserve requirements MOD Basecase downloaded quarterly (same as Network Model) Unit additions for any planning vs operating model discrepancies Unit deletions by request only. MOD updates to be submitted as well Limit and impedance updates per WebTool submittals (done daily) Idevs created to split busses to simulate key breaker outages All units turned off 10

11 MOD Basecase - IDC Additional information requested on Pseudo BAs removed Not applicable for IDC case builds Used for AFC models Modification zone number changed to match control area number per IDC requirements. 11

12 Available Flowgate Capability (AFC) Models Begins with Seasonal IDC model (example Nov 2014) Build 5 Seasonal AFC Models each season Hourly/Daily models current IDC seasonal model Updated monthly based on IDC changes Winter0 6 months out Summer0 12 months out Winter 18 months out Summer 24 months out Model base additions Apply Transmission Service Requests (TSRs), Outages, and Load Forecast to calculate AFC Block HVDC tie and use pseudo BA/pseudo generator to capture TSRs 12

13 AFC time horizons Operating AFC Models hourly/daily model (hours 1-48) Planning I hourly/daily model (hour 49-day 7) Planning II hourly/daily model (day 8-31) Study/monthly Winter0/Summer0/Winter/Summer (month 2-36) 13

Available Transfer Capability Implementation Document TP-OP-005-r15 Effective Date: AUG Purpose. 2 Scope. 3 Definitions

Available Transfer Capability Implementation Document TP-OP-005-r15 Effective Date: AUG Purpose. 2 Scope. 3 Definitions 001-1 R3.1 001-1 R1 R1.1 R1.2 001-1 R3.5 1 Purpose MISO has elected to utilize a flow-based approach for the evaluation of transmission service requests ( TSRs ). The Available Flowgate Capacity Methodology

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Double-Counting 7. Next Steps 2 Overview Purpose Provide a status update on

More information

Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE

Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE Joint and Common Market II. MISO/PJM FTR COORDINATION UPDATE 1 Background and Status At the September 20 th JCM, MISO and PJM discussed the approach for FTR coordination Outage Coordination Both PJM and

More information

Available Transfer Capability Implementation Document TP-OP-005-r18 Effective Date: DEC Purpose. 2 Scope. 3 Definitions

Available Transfer Capability Implementation Document TP-OP-005-r18 Effective Date: DEC Purpose. 2 Scope. 3 Definitions 001-1a R3.1 001-1a R1 1 Purpose MISO has elected to utilize a flow-based approach for the evaluation of transmission service requests ( TSRs ). The Available Flowgate Capacity Methodology used requires

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM pseudo ties

More information

Transmission Reliability Margin Implementation Document TP-PL-002-r9 Effective Date: JUL Purpose. 2 Scope.

Transmission Reliability Margin Implementation Document TP-PL-002-r9 Effective Date: JUL Purpose. 2 Scope. 1 Purpose This document describes the terms and methodologies used in the calculation of Transmission Reliability Margin (TRM). Specifically, the document describes the following: The Methodology For Calculation

More information

Proposed Procedures to Deliver External Capacity between MISO and PJM

Proposed Procedures to Deliver External Capacity between MISO and PJM Proposed Procedures to Deliver External Capacity between MISO and PJM Presented to: Joint and Common Market Michael Wander MISO IMM February 18, 2016 Introduction This presentation summarizes a proposal

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. PJM Update 4. MISO Update 5. Congestion Overlap Solution 6. Next Steps 2 Overview Purpose Provide a status update on MISO-PJM

More information

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the North American

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

Transmission Reliability Margin Implementation Document TP-PL-002-r10 Effective Date: JUL Purpose. 2 Scope.

Transmission Reliability Margin Implementation Document TP-PL-002-r10 Effective Date: JUL Purpose. 2 Scope. 1 Purpose This document describes the terms and methodologies used in the calculation of Transmission Reliability Margin (TRM). Specifically, the document describes the following: The Methodology For Calculation

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

Available Transfer Capability Implementation Document (ATCID)

Available Transfer Capability Implementation Document (ATCID) Available Transfer Capability Implementation Document (ATCID) Revision History Revision Date Revised By Comments 0 03/31/2011 Scott Parker Original document Wade Richards James Sharpe 1 07/8/2011 Scott

More information

ATTACHMENT C. Methodology to Assess Available Transfer Capability

ATTACHMENT C. Methodology to Assess Available Transfer Capability ATTACHMENT C Methodology to Assess Available Transfer Capability Part I - Colorado River Storage Project Management Center, Desert Southwest Region, Rocky Mountain Region, and Sierra Nevada Region (1)

More information

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017

Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Joint and Common Market PSEUDO TIE UPDATE AUGUST 22, 2017 Agenda 1. Overview 2. MISO Update 3. PJM Update 4. JOA Changes Joint Filing 5. Congestion Overlap 6. Next Steps Appendix 2 Overview Purpose Provide

More information

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization - 1 - Introduction The North American Electric Reliability Council (NERC) requires every

More information

Dispatchable Intermittent Resource (DIR) Workshop

Dispatchable Intermittent Resource (DIR) Workshop Dispatchable Intermittent Resource (DIR) Workshop April 13, 2011 DIR Registration April Peterson 1 Market Participant v. Asset Owner Market Participant represents the highestlevel data component of Commercial

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

Freeze Date Straw Proposal Draft 5/18/2017

Freeze Date Straw Proposal Draft 5/18/2017 Freeze Date Straw Proposal Draft 5/18/2017 0 Table of Contents 1.0 Introduction... 2 2.0 Executive Summary... 2 3.0 Existing Process Background... 2 4.0 Design Components... 5 4.1.0 4.2.0 4.3.0 4.4.0 4.5.0

More information

Coordinated Planning / Deliverability Studies

Coordinated Planning / Deliverability Studies PJM-MISO Stakeholder JCM Briefing June 30, 2005 Coordinated Planning / Deliverability Studies Version 1.0 6/28/05 Discussion Overview Deliverability Study Processes in PJM and MISO Current Coordination

More information

Transmission Reliability Margin Implementation Document (TRMID) NERC Reliability Standards MOD Transmission Reliability Margin

Transmission Reliability Margin Implementation Document (TRMID) NERC Reliability Standards MOD Transmission Reliability Margin Transmission Reliability Margin Implementation Document (TRMID) NERC Reliability Standards MOD-008-1 Transmission Reliability Margin Revision History Revision Date Revised By Comments 0 03/31/2011 Kale

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report February 28, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report August 22, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

INCREMENTAL AUCTION REVENUE RIGHTS

INCREMENTAL AUCTION REVENUE RIGHTS Joint and Common Market INCREMENTAL AUCTION REVENUE RIGHTS Brian Chmielewski Manager, Market Simulation November 27, 2018 Overview Purpose Provide stakeholders with an update on the MISO-PJM plan for enhanced

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

MTEP18 Transfer Analysis Scope. PSC June 12 th 2018

MTEP18 Transfer Analysis Scope. PSC June 12 th 2018 MTEP18 Transfer Analysis Scope PSC June 12 th 2018 1 Transfer Analysis Study is driven by NERC standard FAC-013-2 Purpose To ensure that Planning Coordinators have a methodology for, and perform an annual

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008)

Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008) Interregional Agreements --> MISO-JOA Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008) Effective Date: 5/30/2016

More information

South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, Version 5.0

South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, Version 5.0 South Carolina Public Service Authority Transmission Reliability Margin Implementation Document (TRMID) April 1, 2017 Version 5.0 Document Change History Version Date of Change Description of Change 0.0

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning

ATC Stakeholder Update 2019 PROMOD Study Assumptions. Tom Dagenais Todd Tadych ATC Economic Planning ATC Stakeholder Update 2019 PROMOD Study Assumptions Tom Dagenais Todd Tadych ATC Economic Planning 7-10-09 1 Agenda / Introduction MISO RGOS Model Description MISO RGOS Model History and Background MISO

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007 MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 12, 2007 Report submitted to NERC on: July 26, 2007. This report is submitted

More information

PJM M2M Market Flow Proposal. October 2014

PJM M2M Market Flow Proposal. October 2014 PJM M2M Market Flow Proposal October 2014 Table of Contents 1. Introduction... 1 2. M2M Market Flow... 1 3. Real-Time Balancing Congestion and M2M payments... 3 4. Firm Flow Entitlement Impact of Market

More information

FERC Order 841 Electric Storage Resource Compliance Straw Proposal Overview

FERC Order 841 Electric Storage Resource Compliance Straw Proposal Overview FERC Order 841 Electric Storage Resource Compliance Straw Proposal Overview Market Subcommittee Planning Advisory Committee Reliability Subcommittee Resource Adequacy Subcommittee June 6, 2018 Purpose

More information

IMM Quarterly Report: Fall 2017

IMM Quarterly Report: Fall 2017 IMM Quarterly Report: Fall 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics December 5, 2017 Highlights and Findings: Fall 2017 The MISO markets performed competitively this fall,

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

October 18, Southwest Power Pool, Inc., Docket No. ER Submission of Tariff Revisions

October 18, Southwest Power Pool, Inc., Docket No. ER Submission of Tariff Revisions October 18, 2013 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

Transmission Service Request

Transmission Service Request PJM Manual 2: Transmission Service Request Revision: 12 Effective Date: December 03, 2012 Prepared by Transmission Service Department PJM 2012 2011 PJM iii Revision 11, Effective Date: 04/01/2011 Table

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

Ensuring Resource Availability meets Need (RAN) in MISO. MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design

Ensuring Resource Availability meets Need (RAN) in MISO. MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design Ensuring Resource Availability meets Need (RAN) in MISO MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design Purpose & Key Takeaways Purpose: Discuss MISO s Resource Availability

More information

Special NERC Operating Committee Meeting

Special NERC Operating Committee Meeting 5/21/2013 Special NERC Operating Committee Meeting Chairman s Opening Remarks May 15, 2013 Purpose of Meeting and Success Definition WORKING MEETING NO VOTING A Successful Meeting = Identify concerns with

More information

MISO PJM Cross-Border Planning

MISO PJM Cross-Border Planning MISO PJM Cross-Border Planning July 24, 2014 MISO-PJM JCM Planning Coordination Issues 2 At a previous JCM meeting, several issues related to planning coordination were raised: Market Efficiency Planning

More information

IMM Quarterly Report Supplement: December Highlights and Other Issues

IMM Quarterly Report Supplement: December Highlights and Other Issues IMM Quarterly Report Supplement: December Highlights and Other Issues MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics February 3, 2017 Highlights and Findings: December 2016 Natural

More information

Flowgate 3707, an OTDF Flowgate, consists of the following elements.

Flowgate 3707, an OTDF Flowgate, consists of the following elements. MISO Investigation Report on the Level 5 TLR Event Lore-Turkey River 161kV for the outage of Wempletown-Paddock 345kV Flowgate 3707 February 8, 2002 Report issued: February 25, 2002 This report is submitted

More information

EIPC Roll-Up Powerflow Model

EIPC Roll-Up Powerflow Model EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights

More information

Presentation 1. GridEx III. Reliability Coordinator Participation Brief. Operating Reliability Subcommittee meeting. May 5-6, 2015

Presentation 1. GridEx III. Reliability Coordinator Participation Brief. Operating Reliability Subcommittee meeting. May 5-6, 2015 Presentation 1 GridEx III Reliability Coordinator Participation Brief Operating Reliability Subcommittee meeting May 5-6, 2015 Agenda Objectives Timeline and status of GridEx III planning Active and Observing

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Hourly values for at least the next 48 hours. Daily values for at least the next 31 calendar days.

Hourly values for at least the next 48 hours. Daily values for at least the next 31 calendar days. A. Introduction 1. Title: Available Transmission System Capability 2. Number: MOD-001-1a 3. Purpose: To ensure that calculations are performed by Transmission Service Providers to maintain awareness of

More information

Industry Perspectives on FERC Standard Market Design

Industry Perspectives on FERC Standard Market Design Industry Perspectives on FERC Standard Market Design By Dr. Roberto F. Paliza Midwest Independent Transmission System Operator, Inc. IEEE Summer Meeting July 23, 2002 Chicago, IL Overview MISO Markets

More information

Description of Current Draft: This is the first draft of the proposed standard posted for stakeholders comment.

Description of Current Draft: This is the first draft of the proposed standard posted for stakeholders comment. Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Demand Response Data Task Force Draft Report Outline and Work Plan

Demand Response Data Task Force Draft Report Outline and Work Plan Demand Response Data Task Force Draft Report Outline and Work Plan DRDTF Objectives: 1. Identify how the Demand Response (DR) resource data will be used by NERC Work backward from NERC s operational needs

More information

Manual No. 010 Business Practices Manual Network and Commercial Models

Manual No. 010 Business Practices Manual Network and Commercial Models Manual No. 010 Network and Commercial Models Disclaimer This document is prepared for informational purposes only to support the application of the provisions of the Open Access Transmission, Energy and

More information

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator: ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

PJM Overview: PJM Structure and Cross-Border Examples PJM 2010

PJM Overview: PJM Structure and Cross-Border Examples PJM 2010 PJM Overview: PJM Structure and Cross-Border Examples 1 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 614 millions of people served 51 peak load in megawatts

More information

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring

More information

U. S. SPOT MARKET REGULATION

U. S. SPOT MARKET REGULATION U. S. SPOT MARKET REGULATION NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION & MICHIGAN PUBLIC SERVICE COMMISSION TBILISI, GEORGIA November 30,

More information

MISO-PJM JOA Biennial Review

MISO-PJM JOA Biennial Review MISO-PJM JOA Biennial Review Midcontinent ISO PJM Interconnection 1/20/2016 1. Background On January 4, 2011, Midwest 1 Independent Transmission System Operator, Inc. (MISO) and PJM Interconnection, LLC

More information

Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals

Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals Midwest ISO TDU Sector October 2010 Midwest ISO Advisory Committee Hot Topic Adequate Price Signals October 13, 2010 The Municipal, Cooperative and Transmission Dependent Utilities (TDUs) welcome the opportunity

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

OUTAGE COORDINATION PROCESS

OUTAGE COORDINATION PROCESS OUTAGE COORDINATION PROCESS October 3, 2016 www.peakrc.com. Classification: Public Page 0 of 67 Effective Date: Apr 01, 2017 Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

OUTAGE COORDINATION PROCESS

OUTAGE COORDINATION PROCESS OUTAGE COORDINATION PROCESS March 13, 2017 www.peakrc.com. Classification: Public Page 0 of 68 Effective Date: Apr 01, 2017 Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

PJM Market Efficiency Window and Mid-Cycle Update

PJM Market Efficiency Window and Mid-Cycle Update PJM Market Efficiency Window and Mid-Cycle Update Nicolae Dumitriu Sr. Lead Engineer, Market Simulation Market Efficiency Process Enhancement Task Force Education Session September 7 th, 2018 Education

More information

Standard MOD Flowgate Methodology

Standard MOD Flowgate Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Methodology for Calculating Operating Limits for Generators

Methodology for Calculating Operating Limits for Generators Page 1 of 6 Methodology for Calculating Operating Limits for Generators I. Generator Operating Limit Definition The Generator Operating Limit (GOL) for a generator establishes a pathspecific, directional,

More information

JCM Drill Down Report. May 27, 2015

JCM Drill Down Report. May 27, 2015 JCM Drill Down Report May 27, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool 2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

ITP Year 20 Assessment Scope

ITP Year 20 Assessment Scope ITP 20 Year Scope 1 ITP Year 20 Assessment Scope January 6, 2010 Approved by TWG January 5, 2010 Endsored by ESWG January 5, 2010 Table of Contents Overview... 4 Objective... 4 Modeling... 5 1. Economic...

More information

MOD Demand and Energy Data

MOD Demand and Energy Data A. Introduction 1. Title: Demand and Energy Data 2. Number: MOD-031-1 3. Purpose: To provide authority for applicable entities to collect Demand, energy and related data to support reliability studies

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

PJM Manual 14F: Competitive Planning Process Revision: 0 Effective Date: June 23, Prepared by PJM

PJM Manual 14F: Competitive Planning Process Revision: 0 Effective Date: June 23, Prepared by PJM PJM Manual 14F: Competitive Planning Process Revision: 0 Effective Date: June 23, 2017 Prepared by PJM PJM 2017 Table of Contents Table of Contents Table of Exhibits...5 Approval...6 Current Revision...7

More information

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve

Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Price Formation Education 4: Shortage Pricing and Operating Reserve Demand Curve Patricio Rocha Garrido Lisa Morelli Laura Walter Disclaimer This is not a committee meeting. This session is for educational

More information

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:

More information

2007 STATE OF THE MARKET REPORT

2007 STATE OF THE MARKET REPORT 2007 STATE OF THE MARKET REPORT FOR THE MIDWEST ISO Prepared by: INDEPENDENT MARKET MONITOR FOR THE MIDWEST ISO 2007 State of the Market Report List of Tables Table of Contents I. Executive Summary...

More information

JCM Drill Down Report. February 19, 2015

JCM Drill Down Report. February 19, 2015 JCM Drill Down Report February 19, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

Transmission Planning Procedures and Planning Criteria TDOG108

Transmission Planning Procedures and Planning Criteria TDOG108 Transmission Division Operating Guidelines Transmission Planning Procedures and Planning Criteria TDOG108 Page 1 of 33 Approved by: William R. Kaul, Vice President Transmission Approved date: 10/13/16

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP PJM 2017 2 Dispatch Rate Definition:

More information

FTR Forfeitures. Brian Chmielewski Manager, Market Simulation Market Implementation Committee August 8, PJM 2018

FTR Forfeitures. Brian Chmielewski Manager, Market Simulation Market Implementation Committee August 8, PJM 2018 FTR Forfeitures Brian Chmielewski Manager, Market Simulation Market Implementation Committee August 8, 2018 Overview The purpose of this presentation is to explain a potential inconsistency in the FTR

More information

Peak West-wide System Model Validation Activities

Peak West-wide System Model Validation Activities Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model

More information

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination The 2011 Probabilistic Assessment was a pilot study performed by SPP at NERC s request to voluntarily conduct an assessment to determine reliability indices using probabilistic methods. The majority of

More information

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017 Centralized Energy & Operating Reserves Markets: A MISO perspective 1st International Conference on Large-Scale Grid Integration of Renewable Energy in India Durgesh Manjure, MISO Energy September 6, 2017

More information

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Conforming Changes to Requirements in s None Coordination with revisions proposed in other standards projects The IROL SDT proposes retiring

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Pseudo-Tie Congestion Overlap

Pseudo-Tie Congestion Overlap Pseudo-Tie Congestion Overlap Tim Horger Director, Energy Market Operations Markets & Reliability Committee March 22, 2018 Congestion Overlap Background Pseudo-Tie Market-to-Market congestion overlap between

More information

SPP-ITO LG&E/KU Stakeholder Meeting

SPP-ITO LG&E/KU Stakeholder Meeting . Southwest Power Pool, Inc. SPP-ITO LG&E/KU Stakeholder Meeting.......... November 18, 2009 SPP-ITO LG&E/KU Stakeholder Meeting November 18, 2009 Hyatt Regency Louisville 320 W Jefferson Louisville, KY

More information

CARIS Procedure Development and Simulation Model Evaluation

CARIS Procedure Development and Simulation Model Evaluation CARIS Procedure Development and Simulation Model Evaluation Bill Lamanna Manager Long Term Planning New York Independent System Operator ESPWG Meeting NYISO September 16, 2009 Draft 1 for discussion only

More information

PJM/MISO Joint and Common Market Stakeholder Meeting. June 2, 2005 Wilmington, DE

PJM/MISO Joint and Common Market Stakeholder Meeting. June 2, 2005 Wilmington, DE PJM/MISO Joint and Common Market Stakeholder Meeting June 2, 25 Wilmington, DE Agenda Morning Meeting Objectives Review of March 3, 25 FERC Order Market-to-Market Coordination Update Stakeholder Process

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

Southern Company Services ATCID Version 1.2 Available Transfer Capability Implementation Document (ATCID) ATCID Revision Log

Southern Company Services ATCID Version 1.2 Available Transfer Capability Implementation Document (ATCID) ATCID Revision Log Available Transfer Capability Implementation Document (ATCID) ATCID Revision Log Date Description of Change 3/30/11 Initial Version (Version 1) 2/20/12 Enhancements to Attachment B (Version 1.1) 12/17/13

More information

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017 MISO 2018 Series Dispatch Update MOD-032 Users Group October 3, 2017 1 Objective MTEP17 Dispatch Process MTEP18 Dispatch Updates Reminder Station Service Load Modeling Enhancements Wind Capacity Credit

More information

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets Scott Harvey Member: California Market Surveillance Committee Folsom, California May 19, 2014 TOPICS ISO New England PJM MISO New York ISO

More information

Load RSG Exemptions Emergency Procedures. October 29, 2013

Load RSG Exemptions Emergency Procedures. October 29, 2013 Load RSG Exemptions Emergency Procedures October 29, 2013 Presentation Summary Purpose Summarize the outcome of discussions in the RSC regarding exemption of Load during Emergencies Key Takeaways The RSC

More information