Feasibility of Parachute Recovery Systems for Small UAVs

Size: px
Start display at page:

Download "Feasibility of Parachute Recovery Systems for Small UAVs"

Transcription

1 Feasibility of Parachute Recovery Systems for Small UAVs Kirk Graham Stewart Cartwright University of New South Wales Australian Defence Force Academy School of Aerospace, Civil and Mechanical Engineering Canberra, ACT 2600, Australia Damage to model UAV research aircraft, whether it is structural or systems damage can be costly. To combat this problem this project focuses on determining the mechanical feasibility of a parachute recovery system for small model UAV research aircraft. The economic feasibility of such a system will also be briefly considered. The findings of this project indicate that a PRS is capable of recovering these aircraft within an appropriate altitude. The low cost of implementation for a PRS also make it financially cost effective. This project extends from the initial task of designing and constructing a model aircraft for competition in the SAE Aero Design Competition. The design criteria for this competition were to develop a remote control aircraft with set engine and geometric limitations to lift maximum payload up to a takeoff weight of 25 kg. NOMENCLATURE m = mass [kg] g = gravity [ms -2 ] C d = drag coefficient S = surface area [m 2 ] D o = nominal parachute diameter [m] D p = inflated parachute diameter [m] a = semi-major axis length [m] b = semi-minor axis length [m] V = velocity [ms -1 ] F d x t f n C x X 1 A dv/dt dθ/dt θ β PRS UAV SAE ADFA = density [kg/m 3 ] = drag force [N] = parachute filling distance [m] = parachute filling time [s] = canopy fill constant = opening force coefficient = opening force reduction factor = ballistic parameter = acceleration = rate of change of attitude = attitude angle = power of filling function = Parachute Recovery System = Unmanned Aero Vehicle = Society of Automotive Engineers = Australian Defence Force Academy 1

2 CONTENTS Nomenclature... 1 I. Introduction... 3 A. Aim... 3 B. Scope... 3 C. Background & Justifications... 3 D. Methodology... 4 E. Assumptions and Limitations... 4 F. Management... 4 II. Literature Review... 5 A. Canopy Shape... 5 B. Parachute Activation... 5 C. Inflation Characteristics... 6 D. Parachute Filling Distance... 7 E. Attachment Considerations... 7 F. Summary... 7 III. Concept Selection... 8 A. Introduction... 8 B. Concept 1 Uncontrolled Deployment... 9 C. Concept 2 Ballistic Deployment... 9 D. Concept 3 Spring Release E. Concept 4 Pilot Chute Deployment F. Conclusion IV. System Design A. Parachute System Configuration B. Canopy Sizing C. Pilot Chute Design D. Initiation Method E. Containment F. Deployment Bag G. Canopy Inflation Predictions H. Summary V. Testing and Analysis A. Introduction B. Method C. Results and Validation D. Analysis E. Summary VI. Cost Benefit Analysis A. Purpose B. Scope C. Proposed System D. Costs E. Benefits F. Summary VII. Conclusion A. Concluding Remarks B. Future Direction C. Recommendations VIII. Acknowledgements References

3 I. Introduction A. Aim The aim of this project is to determine if a Parachute Recovery System is a mechanically and economically feasible method of safely recovering the ADFA SAE aero UAV from flight failure. An aircraft parachute recovery system (PRS) is a procedure that relies on the deployment of a parachute to aerodynamically decelerate an aircraft allowing for a safer touchdown (Knacke, 1992). B. Scope This project ultimately began with group design and construction of the ADFA SAE Aero UAV. Once completed individual projects were selected for all group members. The scope of this individual project begins with the examination of existing PRSs, and a review of the principles involved with PRS design. The development of initial concepts will follow, then a focus on system design. More detailed design of the chosen concept will be pursued with the aid of experimental results, gathered through testing. The testing results will be aimed at determining the mechanical feasibility of the PRS. The ability to safely recover UAVs in the event of flight failure is of significant importance. Research will also go into the benefit of a PRS for such small research UAV platforms. A determination of how beneficial such a system will be to small UAV research will try to be reached by carrying out a brief cost time benefit analysis. The revised tasks within the scope of this thesis are listed below; Obtain design details and develop the design requirements analysis. (Group) Design and construct the aircraft. (Group) Flight test the aircraft. (Group) Review existing parachute recovery systems. (Individual) Design a system suitable for this aircraft. (Individual) Test validity of design. (Individual) Determine feasibility of the design. (Individual) The ultimate goal of this project is to determine if a PRS can safely recover this small balsa constructed UAV within an appropriate altitude. Because radio controlled aircraft operate at low altitudes it is unknown if a parachute can open quickly enough to save the aircraft. Furthermore, is it worth the school of ACME investing in a system that may turn out to be more expensive than the UAV itself? C. Background & Justifications The initial task leading up to this project was to design, build and test a UAV to compete in the 2008 SAE Aero East Competition. This task was predominantly undertaken by three students, at the Australian Defence Force Academy Christopher Kourloufas, Gerad Markham and Kirk Cartwright. The design report for this vehicle is attached in ANNEX A. Each student was entrusted with different aspects of the UAV design, and once completed; individual project research was undertaken in different areas pertaining to the aforementioned UAV. 3 Figure 1 - ADFA SAE Aero UAV

4 The design and construction of the ADFA SAE aero UAV was completed in early march 2008, after several months of work. As demonstrated in Fig. 1 the UAV consisted of a canard design, powered by a single piston engine, with conventional tricycle undercarriage. After the construction of the UAV, there was reluctance for the flight testing to begin for fear of damage to the aircraft as a result of flight failure. This reluctance stemmed from the need for an intact aircraft fuselage to be tested within the scope of another student s thesis project. It was suggested that a PRS could be used to reduce the risk of total aircraft damage if flight failure were to occur. The justification for this individual project stems from this need to reduce the risk of total aircraft damage during flight testing. Furthermore, the University of New South Wales at the Australian Defence Force Academy already owns and operates several small UAV research aircraft similar in size and weight to the ADFA SAE Aero UAV. Further justification for this project is a direct result of damage to one of these aircraft, during a flight test. The damaged aircraft was a small research UAV with a gross weight of no more than 25kg, which crashed due to radio controlled interference. Damage caused to the aircraft was considerably costly, and the inability to continue testing caused delays in research. D. Methodology The overall goal of this project is to determine the mechanical and economic feasibility of a PRS for the ADFA SAE Aero UAV. The methodology used to reach this goal is to; 1. Carry out preliminary design of a suitable PRS for the ADFA SAE Aero UAV. 2. Develop a method of testing the effectiveness of this design 3. Test the design. 4. Analyse the test results to determine the mechanical feasibility of the design. 5. Undergo a brief cost benefit analysis as a supporting document to determine the economic feasibility. This methodology outlines the basic structure of this project. E. Assumptions and Limitations To ensure that the basic requirements for the PRS remain the same throughout the design process, it will be assumed that the ADFA SAE Aero UAV is the dominant aircraft that the system is designed for. This will provide a constant base aircraft to design from. The adaptability of the PRS to different platforms will still be considered during the design process. Due to the scope of this project, coupled with the time constraints associated with its completion, the design will be limited in its depth and detail. The project will be more focused on the overall system design, with an underlying goal of determining the feasibility of a PRS. The design however, must be sufficiently in depth to determine both the mechanical and economic feasibility of a PRS for use on small research UAVs. F. Management Appropriate management documentation has been attached in ANNEX G 4

5 II. Literature Review PRSs are not a new concept, and there has been significant research undertaken into several of the more complex problems associated with their design. While keeping the aims of the project in mind, this literature review summarizes some of the research that has occurred in this area. Parachute terminology is used quite extensively throughout this review, so to aid understanding; a diagram of parachute parts is attached in ANNEX B. A. Canopy Shape Principally, UAV PRSs use three different canopy shapes; cruciform or cross-type canopies, hemispherical canopies and parafoils (Wyllie, 2001). Parafoils are gliding parachutes, designed to be steerable, allowing for a small level of navigation after deployment. Their internal cell structure is ram-air inflated which forces the parafoil into a classic airfoil shape. To operate as intended parafoils need to stay inflated and are therefore constructed out of a low porosity fabric (Wyllie, 2001). This causes an increase in the opening shock forces experienced during inflation and a complex reefing mechanism is generally required to reduce these loads. Deployment is further complicated by the need to protect the control line servos from these opening loads (Wyllie, 2001). A follow on effect of inputting systems to reduce parachute opening loads causes a much slower deployment speed and therefore greater height loss during deployment. Cruciform canopies are the simplest of the three canopy shapes consisting of two pieces of rectangular cloth overlaid and sewn together as shown in Fig. 1. These canopies have the smallest drag coefficients, and lower opening forces. The small opening Figure 2 - Cruciform Canopy Configuration (Wyllie, 2001). forces, attributed to gentler parachute inflation, means that the falling body losses more height before full inflation is attained. Cruciform canopies produce lower oscillation than hemispherical canopies, which is one of the reasons they have been researched for use in precision airdrop systems are used as drogue stabilizing parachute (Keith Stein, 2001). Hemispherical canopies have high drag and opening force coefficients (Wyllie, 2001), affording them the advantage of better reliability on opening. Hemispherical non-steerable parachutes are used for aircraft recovery because their simplicity enhances their reliability. Simplicity pertains not only to the parachutes reliability but also to ease of construction and packing, an imperative requirement for this project. B. Parachute Activation Parachute activation refers to the method of deployment prior to inflation. It can be assumed that a key factor of parachute deployment systems is reliability. Three principal deployment methods are forced ejection systems, drogue or pilot parachute systems, and rocket extraction systems (Huckins, 1970). Forced ejections systems are common extraction methods due to their simplicity. The mortar, catapult, and pressure bellows are examples of mechanisms designed to produce a forced ejection of the packed parachute (Huckins, 1970). These systems tend to be heavy and they also produce high reaction loads, which is important when considering the platform in which the system will fire. Parachute deployment using a drogue or pilot parachute has numerous advantages. The system is quite flexible since the parachute extraction force is applied continuously over the entire deployment sequence, and the system is also lighter. This system relies on aerodynamic force to extract the main parachute, thus problems may arise due to pilot chute interference with the wake turbulence of the descending body (known in skydiving as hesitation ). Used in tandem, individual extraction systems increase their effectiveness as demonstrated by the Gemini Spacecraft, which used a drogue gun to launch a drogue parachute to stabilize the re-entry vehicle, until a height at which the pilot chute was extracted, pulling out the main chute (Vincze, 1966). 5

6 A rocket extraction system for parachute deployment has all the advantages of a drogue parachute system, but does have a slight weight penalty. Furthermore, the rocket extraction system produces very light reaction loads, and is only slightly dependent on the characteristics of the vehicle wake (Huckins, 1970). The rocket extraction does however increase the risk of damaging the parachute fabric on extraction, and has the added complexities of dealing with pyrotechnics. C. Inflation Characteristics In view of the fact that parachute inflation is a very complex and unsteady process, it is well known that parachute theory is a difficult problem in the aerodynamic field (Calvin, 1984). PRSs in UAVs require parachute inflation to be reliable and quick, to ensure minimum loss of height during opening. In manned PRSs, such as the Ballistic Recovery System (BRS) used in the Cirrus SR20 (Ballistic Recovery Systems Inc.), complex dis-reefing mechanisms are put it place to slow the inflation process and reduce shock forces caused by the opening canopy. The process of dis-reefing shown below in Fig. 2 is done to reduce the forces felt by the manned occupants, and is important for unmanned PRS design from s structural integral aspect. Figure 3 - Dis-Reefing of a Hemispherical Canopy (Cao & Xu, 2004). Reefing a parachute slows the inflation, meaning more height loss, however there is another reason for reefing a parachute aside from reducing shock forces. There is a phenomenon called wake recontact, sometimes called canopy collapse. This phenomenon occurs when the parachute decelerates the payload so rapidly that the air behind the parachute catches up to the canopy: causing it to deform ( collapse ) and lose drag (Peterson, Strickland, & Higuchi, 1996). One of the single most important aspects in aiding the canopy inflation process is the use of a parachute deployment bag. A deployment bag ensures a controlled deployment phase. The deployment bag also ensures a lines first deployment. This ensures that the canopy only begins inflation after the suspension lines have reached full stretch. If a lines first deployment is not followed the canopy often gets tangled in the suspension lines and fails to inflate ending in catastrophic PRS failure. The increase in drag area of the parachute canopy during the opening process causes a deceleration of the recovery vehicle. A simulation of the deceleration experienced by the recovery vehicle was carried out and a plot of a typical g-loading experienced is shown in fig 11. This plot will be referred to later in this document, when the g-loading curve for this PRS is plotted. Figure 4 - G-Loading Plot Experienced by a Recovery Vehicle During Canopy Inflation (Mohaghegh & Jahannama, 2008). 6

7 D. Parachute Filling Distance Parachute filling distance is defined as the distance required for the parachute canopy to open, taken from the point of initial line stretch to full inflation. Fig. 4 demonstrates this definition (Mohaghegh & Jahannama, 2008). Mueller and Scheubel reasoned that, based on the continuity law, parachutes should open within a fixed distance, because a given conical volume of air in front of the canopy is required to inflate the canopy (Knacke, 1992). With the confirmation of drop tests the parachute filling distance was found to be proportional to the inflated parachute diameter D p, multiplied by the canopy fill constant n, as shown in Eq. 1 below (Mohaghegh & Jahannama, 2008). Figure 5 - Canopy Filling Distance Diagram (Mohaghegh & Jahannama, 2008). (1) The canopy fill constant, typical for each parachute type, is an indicator of the filling distance as a multiple of nominal parachute diameter. Having found the canopy filling distance only one further step is required to determine the canopy filling time. Given speed is distance over time, the canopy filling time is simple given as Eq. 2 (Mohaghegh & Jahannama, 2008). Canopy filling distance and canopy filling time are very important in PRS because they are a direct reflection of how much height loss may occur during the inflation process. Small UAV research aircraft have to operate at low altitudes and it is therefore imperative that the campy opens is a short distance. E. Attachment Considerations The attachment of the parachute to the UAV directly affects the operation of the system. The attachment points determine the behaviour of the aircraft during canopy inflation, and also the attitude at which the UAV will fall once inflation is complete and the PRS is in the steady state condition. Conventional PRSs deploy in such a way that the aircraft falls undercarriage first in order to protect the airframe; however this is not always the case. The Phoenix UAV, for example, has a PRS that allows the aircraft to roll over and land upside down (Wyllie, 2001). This is done to protect some of the sensor equipment underneath the aircraft. Manipulation of the aircraft attitude during steady state descent is generally achieved by changing the position of the PRSs attachments in relation to the aircrafts centre of gravity. This allows the designer the freedom to choose how the aircraft touches down; main undercarriage, or nose wheel first for example. In general however, PRSs are attached at several points with the centre of gravity of the aircraft roughly in the middle to keep the system balanced. From a structural perspective it is important to make sure that the attachments are connected to structurally sound aircraft fixtures, able to handle the large forces that can be experienced due to the rapid deceleration of the aircraft during canopy inflation. The attachments to the aircraft are also vitally important during the inflation stage, where careful placement of the attachment points can protect the parachute canopy from entering the wake of the aircraft. If the parachute is attached forward of the centre of gravity, deployment will cause a strong pitch up moment forcing the canopy into the wake of the aircraft. This situation may even cause the to aircraft fall backwards through the suspension lines, tangling the parachute. When attached behind the centre of gravity it causes a pitching down moment allowing the canopy to inflate in the free stream air and also stopping the aircraft from stalling. If used carefully the attachment method can be instrumental in controlling the pitch dynamics of the aircraft during the deployment cycle. F. Summary It is apparent from the literature review that there has been extensive research carried out on the subject of PRSs. There is little research however available on the use of PRSs for small balsa constructed UAV aircraft. There have been PRSs used for large scale UAVs, but the research available for UAVs under 25kg is very limited. (2) 7

8 III. Concept Selection A. Introduction The purpose of this chapter is to consider the different concepts available for the design of a PRS. Each concept will have merits, however the design will be chosen on its suitability for balsa wood constructed model aircraft.the requirements of the PRS will give the design process a direction. Listed here are the PRS customer requirements. These requirements have been used to generate engineering specifications, attached in ANNEX C 1. Minimise Damage to airframe on ground impact 2. Deploy Reliably 3. Minimal impact on aircraft aerodynamic stability when attached 4. Capable of decelerating a 25kg payload within respectable g-loading limits 5. The possibility of adaptation for different aircraft 6. Light weight 7. Minimal Height loss during parachute inflation The first stage of a PRS is the deployment phase. Parachute deployment denotes the sequence of events that begins with the opening of a parachute compartment and continues with the extraction of the parachute until the canopy and the suspension lines are stretched behind the recovery vehicle and the canopy is ready to start the inflation process. The deployment system must achieve this sequence of events in a progressive manner so as to reduce the shock forces felt by the UAV. The system must also and more importantly release the parachute into the airflow with sufficient speed so as to allow inflation to occur before the UAV losses to much altitude. This requirement is of significant importance to the design of this PRS as it is to be utilised for low altitude recovery of small model UAVs. A good parachute deployment system provides the following benefits as outline by the PRS Design Manual (Knacke, 1992): 1. Minimizes the parachute snatch force by controlling incrementally the deployment of the parachute, and by keeping the parachute canopy closed until line stretch occurs. 2. Keeps Tension on all parts of the deploying parachute. 3. Minimizes opening time. 4. Supports uniform deployment. Once the deployment phase is complete the system is ready for inflation and the most problem prone phase of the working system is over. It is apparent why the selection of the deployment system defines and directs the remainder of the PRS design. Four separate parachute deployment system concepts will be analysed, the best system for the use on the ADFA SAE Aero UAV will be selected for further design. 8

9 B. Concept 1 Uncontrolled Deployment This method of deployment essentially releases the parachute into the free-stream and the forward moving airflow does the work in opening the parachute to full inflation. It is therefore given the name uncontrolled deployment. The simplified diagram below demonstrates an uncontrolled deployment. Figure 6 - Uncontrolled Deployment (Cartwright, 2008). The appeal of this method of deployment for use on a UAV is its simplistic and lightweight design. An uncontrolled deployment would allow for a very fast developmental phase and also reduce the cost of the overall PRS. Furthermore, this deployment method could be constructed with very few components and would in turn allow the PRS to occupy a very small proportion of the recovery vehicle. This system is not without its downfalls however. Due to the uncontrolled nature of this concept, there has been research that has shown it is only effective for parachutes less than 5 feet in diameter (Knacke, 1992). When larger parachutes are released using this method it results in high shock forces and partial canopy inflation prior to the full line stretch of the suspension lines. It is possible to account for these problems by clever design of a complicated reefing system and sophisticated packing methods; however this would undermine the simplicity of the system which was one of the major reasons for its consideration. C. Concept 2 Ballistic Deployment Ballistic deployment refers to the deployment of a parachute by the use of some kind of pyrotechnics. There are two main types of ballistic deployment systems, and although they are subtly different their principle is essentially the same. The diagram below shows the two main ballistic deployment systems, rocket deployment on the left and drogue gun deployment on the right. Figure 7 - Ballistic Deployment 9 (Cartwright, 2008).

10 Rocket deployment uses an angled nozzle rocket to pull out the main parachute. This is a very high speed deployment, and has been used successfully for larger aircraft PRS. The benefit of the rocket deployment system is that it provides a constant pulling force over the whole deployment cycle. The disadvantages of this system are numerous when considering the type of vehicle in which it is intended for. The small balsa constructed ADFA SEA Aero UAV does not have a large amount of space in which a rocket could be mounted. Rockets also produce very hot exhaust gasses that may be an added risk for the internal balsa structure and electronic equipment such as servos. Drogue gun deployment is a method that fires a weighted slug from a drogue gun to pull out the main parachute in a very similar way to the rocket deployment system. This method is advantages in that the explosive energy is contained within the drogue gun and it leaves with the slug in the form of kinetic energy. As shown in the diagram above the slug is tethered to the main deployment bag and pulls out the main parachute from its compartment within the UAV. Unlike rocket deployment the slug relies on its inertia to provide the pulling force needed over the whole deployment. Problems with this method may arise due to the large reaction forces that occur due to the large slug being fired from the drogue gun. The simple balsa frame would struggle to support the drogue gun and damage may occur during deployment. Ballistic deployment has its merits with regards to a favourable deployment time. Having a fast deployment is paramount for low level UAVs and ballistic deployment has proven effective in this area. The complexity of ballistic deployment however, makes it less of a viable option for such a small scale recovery vehicle. The lack of space within the ADFA SAE Aero UAV also means that the system must have as few components as possible. Another consideration is the overall weight of a ballistic system, which, if installed, would require the aircraft to sacrifice this weight in the form of its payload carrying capacity. D. Concept 3 Spring Release This spring release method, represented diagrammatically below, was an attempt to combine the high speeds associated with ballistic deployment with the simplicity of the uncontrolled deployment. This concept uses a high powered spring internally mounted to eject the main parachute into the free stream airflow. Figure 8 - Spring Release Method (Cartwright, 2008). The side effect of using the spring release method is the weight of the internal mechanical components. One possible solution is to use compressed air instead of a mechanical spring however, problems also may arise with mounting the system within the ADFA SAE UAV fuselage, and although much less than a ballistic deployment the reaction force may still prove significant. One further point to note is that force provided by the spring to deploy the parachute must be significant enough to complete the whole deployment. Unlike a Rocket deployment where the force extracting the parachute is constant throughout the extraction phase, the spring release mechanism merely ejects the parachute and allows the airflow to complete the unfurling process. This reduces the reliability and repeatability of the deployment. 10

11 E. Concept 4 Pilot Chute Deployment The final concept to discuss is the method of pilot chute deployment. During this method of deployment a small parachute called a pilot chute is used to drag out the main parachute as demonstrated in the diagram below. Figure 9 - Pilot Chute Deployment (Cartwright, 2008). The pilot chute, which is generally about a quarter of the size of the main parachute, is small enough that it can be released at high speeds without producing large shock forces. The pilot chute then helps to decelerate the fore body while pulling out the main parachute so that when the main canopy opens the speed is slowed enough such that the shock forces are significantly reduced when compared to an uncontrolled deployment. The pilot chute utilises the drag force it creates when in the free airstream to deploy the main parachute and as a result has the benefit of having a constant force throughout the whole deployment phase. This does mean however, that at the very slow speeds the pilot chute can fail to produce enough drag to deploy the main parachute fully. This is one of the reasons that some aircraft PRSs have an operational envelope that defines its limitations. The issue of containment space is less of a problem using this method. Because the pilot chute is made of the same material as the main canopy it can be folded to take up very little space within the fuselage of the recovery vehicle. This naturally applies to the weight of the PRS. Because the pilot chute is made of lightweight material the overall deployment system is very light. The simplicity of this system is a direct result of the number of components required for its function. The deployment system is essentially two parachutes of different sizes opened one after the other. The construction and installation of it is therefore greatly simplified and as a result the cost is reduced. Using a pilot chute for the main parachute deployment does however, have a certain unknown quality to its function. Because the parachutes are different sizes, unique to their specific function; and the recovery vehicle has a known range of speeds defined by its operational envelope, the inflation times and distances are not known with great accuracy. For this type of deployment system testing would be required to determine the feasibility for use on a small balsa UAV. F. Conclusion Four concepts have been introduced within this chapter and one will be selected for further design. Uncontrolled deployment is easily the least complex system and would require very little detailed design. It would be a cost effective design and would require very few resources to take it from concept to construction. The possible complications do however make this a poor choice for further design. The over simplification of the deployment leads to a loss of tension on the suspension lines and canopy which causes entanglement between different parts of the parachute. The speed of a ballistic deployment system would provide a good range of altitudes from which the aircraft could be recovered. The better performance achieved in deployment speed is far outweighed by the increased complexity of the design. Both rocket and drogue gun methods also increase the risk of damaging the aircraft during the violent deployment phase. Ballistic deployment methods carry an inherent risk and as a result the expense of its 11

12 implementation is significantly increased. Unfortunately this makes it a poor choice of deployment system for this type of UAV. To make the PRS a viable option it is necessary to make it as cost effective as possible. The goal behind the spring release method was to reduce the risk of a ballistic deployment by using a mechanical type system to release the parachute into the free airstream. The side effect of using an internal spring system is that a large force must be produced at the start of the deployment to allow the parachute to complete its full unfurling process. This large force has to occur over a very small period of time, resulting in large impulse, which the fuselage was not deigned to handle. To produce a large impulse it would require the use a large and heavy spring system that would make this method of deployment a bad choice for an aircraft application. The final concept shows the most promise for further development. It is the method that uses a pilot chute to extract the main parachute. This system is simple, lightweight and has the potential to be very cost effective. There is however the question of inflation times and distances, and testing will be required to confirm if it is a feasible system. Pilot chute deployment is used primarily for personnel parachutes, which is a testament to their reliability, an important factor considering its intended purpose as an emergency recovery system. The table below is a method of comparing the individual concepts to help with an informed selection. Each concept is ranked against the amended system requirements. The essential requirements carry greater weight in the selection process and are therefore doubled within the table. The best concept for a given system requirement is given a score of 1 and the worst a score of 4. The values attained are summed and the concept with the smallest total number is the concept that best fulfils all system requirements. Table 1 below is the results of the concept selection analysis. Concept 1 Uncontrolled Concept 2 Ballistic Concept 3 Spring Concept 4 Pilot Chute Reliability* Speed of Deployment* Lines First Deployment* Complexity Reaction Forces on Aircraft Adaptability to Other Aircraft Weight Cost Results Table 1 Concept Selection table (Cartwright, 2008). This method of selection confirms what the logic predicts, that concept 4 the pilot chute deployment system is the best system for this application with a score of 19. Ballistic deployment is the second choice; however its complexity rules it out as a viable option. 12

13 IV. System Design A. Parachute System Configuration During the conceptual design phase outlined in chapter 4 of this document, it was decided that the PRS would use a pilot chute deployment method. A more detailed breakdown of the parachute recovery system configuration is represented below. Figure 10 - PRS Layout (Cartwright, 2008). 1. Recovery Vehicle 2. Shock Force Attenuation Bridle 3. Main Parachute Riser 4. Main Parachute Swivel 5. Main Parachute Suspension Lines 6. Main Canopy 7. Main Parachute Deployment Bag 8. Pilot Chute Bridle 9. Pilot Chute Swivel 10. Pilot Chute A. Main Canopy Shape Understanding that this PRS is to be used as a lower atmosphere, subsonic aerodynamic decelerator steers the choice of parachute canopy shape to three different options. These options are Para foil, Cruciform, and hemispherical parachutes. As discussed in the literature review parafoil shaped designs, common in sports parachutes, are steerable systems, unnecessary for this application. The parafoil design also adds unnecessary complexity to the construction of the intended PRS. Cruciform or hemispherical parachutes are more commonly used in aircraft recovery systems. This PRS will use a hemispherical parachute design due to the larger drag coefficient than the cruciform parachute allowing for the use of a smaller parachute for the same descent speed. The cruciform parachute has a smaller opening force coefficient which means less shock force occurs during parachute inflation; however this is outweighed by the reliability of the hemispherical parachute. Hemispherical parachutes also have a lower canopy filling constant which reduces filling distance. Therefore less height is lost during inflation. Further reasons for choosing a hemispherical parachute shape are listed below. 1. Ease of construction. 2. Ease of packing. 3. Better consistency on opening. 4. Large inflation shock forces acceptable due to unmanned aircraft. 5. Large Drag coefficient. 13

14 One negative aspect of using hemispherical parachutes is their tendency to oscillate. Oscillation is a result of an unstable parachute where the vortex shedding initiates a rocking motion back and forth. Hemispherical parachutes often have a tendency to have large oscillations, up to ± 30. Research has shown however that these oscillations only occur at the higher descent velocities ( 9m/s), which is as much as 4 m/s faster than the descent velocity this PRS is designed to achieve. B. Canopy Sizing Having decided that the canopy shape will be hemispherical, the initial canopy sizing can be evaluated with the objective of calculating inflated parachute diameter. Parachutes rely on the aerodynamic drag force, represented by Eq. (3), to slow the descent of a body. Assuming that the parachute is in a steady state descent means that the drag forces F d can be equated to the weight of the descending body, as represented by Eq. (4). Rearranging Eq. (4) for surface area yields Eq. (5). (3) (4) The unknowns in Eq. (5) are, payload mass m, and descent velocity V. All other variables in the equation are already known quantities, ρ=1.225kg/m 3, C D =0.7(standard for hemispherical parachutes) (Knacke, 1992), and g=9.81m/s. Payload mass can be reasoned out by understanding that the ADFA SAE Aero UAV gross weight must not exceed 55lbs ( 25kg), therefore m=25kg. The descent velocity can be obtained from historical data, which shows that aircraft PRSs have descent velocities between 4-6 m/s (Wyllie, 2001). Taking the average and using 5 m/s for V means that surface area can be quantified. Now that surface area is calculated the nominal parachute diameter can be found. The nominal diameter of a parachute is simply a reference diameter found by using Eq. (6), (Knacke, 1992) below. (5) Using table 5-1 (Knacke, 1992), found in ANNEX D, the ratio between inflated diameter D p and nominal diameter D o for a hemispherical parachute is highlighted. This allows for the calculation of the inflated diameter using the Eq. (7) below. (7) The excel spreadsheet shown in table 1 was used to calculate the parachute data, using the equations outlined previously. The excel spreadsheet shows that for a 5m/s rate of descent, a parachute with a 3.56m inflated diameter is required. Research has shown that this method of parachute sizing is highly accurate, and conforms well to the results of parachute drop tests. Knowing the Canopy Sizing (6) Parameter Value Units Mass kg Gravity 9.81 m/s^2 Density 1.23 kg/m^3 Descent Velocity 5.00 m/s Drag Coefficient 0.70 Surface Area Required m^2 Nominal Parachute Diameter 5.40 m 14 Inflated Parachute Diameter 3.56 m Table 2 - Main Canopy Sizing Data (Cartwright, 2008).

15 parachute dimensions it was possible to purchase a hemispherical parachute of the appropriate size. The parachute was purchased early as it was known that testing would be required before the conclusion of this project. The main canopy cost a total of $350 including suspension lines and mounting bracket. C. Pilot Chute Design The pilot chute is a small parachute designed to pull out the main parachute during the deployment phase. Now that the main parachute has been sized and purchased the pilot chute can be designed using the main parachute data. Two different methods have been used to confirm the size requirement of the pilot parachute. The first method of sizing uses historical data from many parachute tests to determine a Pilot-to-main parachute drag area ratio. Table 3, right is taken from the Parachute Recovery System Design Manual, and was used to get a first estimate of the pilot chute size. Table 3 - Pilot-to-Main-Parachute Drag Area Ratio (Knacke, 1992). The first method estimated that a pilot chute with an inflated diameter of 0.62m was required. Pilot Chute Sizing Parameter Value Units Main Parachute Mass 1.40 kg The second method is a mathematical Gravity 9.81 m/s^2 method similar to that of the calculation of the main parachute size. Given that Density 1.23 kg/m^3 the main canopy had been purchased we Descent Velocity 4.00 m/s could get an accurate weight by a simple Drag Coefficient 0.70 measurement. The parachute including bridle has a total weight of 1.4 kg. Knowing the weight of the main Surface Area Required 2.00 m^2 parachute and assuming the worst case scenario, that the pilot chute must have the ability to pull out the main parachute Nominal Parachute Diameter 1.60 m at the stall condition of the aircraft (approx. 4 m/s), it is a simple Inflated Parachute Diameter 1.05 m calculation to solve for a surface area. This calculation was performed in parallel to the main canopy sizing method using Microsoft Excel and is displayed in table 4. The mathematical calculation determined that a hemispherical pilot chute of 1.05m diameter would be required for a successful deployment at stall speed. This size is 40% larger than the pilot chute diameter determined using statistical data. To ensure the reliability in deployment of the PRS and to build in another level of safety it was decided to use the larger of the two values. Hence the pilot chute is set at a diameter of 1.05 meters. The pilot chute was also purchased so that its reliability could be tested at a later stage within the scope of this project. D. Initiation Method From the conceptual design chapter a pilot chute system was selected for use as the deployment method. The initiation system is characterized by the functions of the PRS that occur up to and including deployment of the pilot chute. Several simultaneous actions must occur prior to the start of the deployment process. First the PRS must be initiated by the observer on the ground. A signal will be sent to the UAV that will release the pilot chute and also kill the engine. The engine will be killed to prevent line tangling in case the suspension lines come in the vicinity of the propeller. 15

16 The pilot chute is ejected by using a very lightweight spring mechanism. The spring is sewn into the pilot chute crown area and collapses for easy storage at the rear of the aircraft fuselage just behind the aft bulkhead. The pilot chute spring is compressed and held in place by the release hatch. The release hatch is pinned closed and a small electronic servo is mounted in place to release the hatch when required. The diagram right shows the folded pilot chute and spring aft of the rear bulkhead. The entire PRS is initiated by the pulling of a pin which holds the release hatch to the recovery vehicle. The hatch falls away as the pilot chute is sprung into the free airflow and the deployment process begins. The servo that pulls the release pin to activate the system is run off an independent power Figure 11 - Folded Pilot Chute and Compressed Release Spring Inside Release Hatch (Cartwright, 2008). source and is also wired in to an independent radio receiver. This is to try and avoid accidental parachute release by radio interference. E. Containment Now that the main parachute and pilot chute have been purchased, elements of how the system will be contained within the aircraft can be considered. To ensure that the PRS has no effect on the aircraft during normal flying operations, an internal storage will be used. The ADFA SAE Aero UAV does not have large amounts of fuselage space. By looking at the constructed fuselage the best location for containment can be determined. The newly designed fuselage for the ADFA SAE Aero UAV, designed by Christopher Kourloufas is shown below. Figure 12 - ADFA SAE Aero UAV Fuselage (Cartwright, 2008). The different sections annotated above indicate the lack of space within the main fuselage section. The two sections where it would be possible to fit the parachute internally are the internal electronics mounting space, or over the wing carry through section. To facilitate deployment it is important that the parachute be in a location where it can deploy quickly into the free airstream and be unaffected by aircraft appendages such as the wings or canards. This makes the obvious choice for the parachute containment at the rear of the aircraft, such that it can deploy already 16 Figure 13 - ADFA Final SAE Thesis Aero Fuselage Report 2008, with PRS UNSW@ADFA Location (Kourloufas, 2008).

17 free and clear of the wings, avoiding possible suspension line tangling. Figure 13 is a sectioned cut-away of the fuselage design which indicates the PRS location within the UAV. Knowing the location of containment produces the need to design a method of storing the parachutes. This requires the design of a deployment bag. F. Deployment Bag Using a Parachute deployment bag has many advantages. It allows for a repeatable parachute unfurling process and as a result increases the reliability of deployment. It has been shown to provide the most frequent and successful method of producing a controlled deployment (Knacke, 1992). A deployment bag also permits easy handling, packing, rigging and storage of the parachute assembly. The deployment bag contains the parachute and holds it until it is ready to be unfurled. This means that it must have a few very specific qualities to allow for a good controlled deployment. Firstly the deployment bag must be light. The pilot parachute attaches to this bag and pulls it out of the containment area, so the lighter the bag the smaller the pilot chute required. The deployment bag must also have a low porosity. This ensures that the main parachute canopy can easily slide past the bag when unfurling is required. The deployment bag also ensures that the canopy only inflates after the suspension lines are at full stretch. As brought up in the literature review, a lines first deployment is imperative to reduce shock forces and ensure reliable canopy inflation. Generally speaking a deployment bag is specifically made for the main parachute. In this case an existing product was available that adequately performed all of the necessary functions of a deployment bag. A 2.4 Litre plastic bottle was found to be an excellent deployment bag for this situation. The bottle was light, cheap, fitted perfectly into the allowable space, and has a sufficiently low porosity to allow the parachute to unfurl quickly. The deployment bag encompasses the main parachute into a small space and has the added benefit of easily being attached to the pilot chute. Figures show the deployment bag, and its location within the PRS. Figure 14 - Unpacked Main Parachute and Deployment Bag (Cartwright, 2008). Figure 15 - Main Parachute Packed in Deployment Bag (Cartwright, 2008). Figure 16 - Main Parachute in Deployment Bag with Pilot Chute Attached (Cartwright, 2008). The final requirement for the deployment bag is to ensure a lines first deployment. This is achieved by using a method called skirt hesitation. This design uses a tensioned band around the suspension lines at the base of the deployment bag. It is demonstrated in the figure 17. This red band prevents the skirt of the parachute leaving the deployment bag until line stretch occurs. At line stretch the suspension lines are pulled out from underneath the band and the parachute can be deployed. G. Canopy Inflation Predictions The canopy inflation process is by far the most complex aspect of the PRS. There are several mathematical models to help predict the effect of the canopy inflation process and some of these models will be utilised within this preliminary design chapter, however the Figure 17 - Deployment Bag with Red Sirt Hesitation Band (Cartwright, 2008). 17

18 canopy inflation process must, and will be supported by testing. The reason for such focus on the canopy inflation process is to try and answer the question will this PRS deploy quickly enough before the aircraft looses too much altitude. There is also a need to calculate the opening forces of the canopy for the use in stress analysis of both the parachute and airframe. As discussed in the literature review regarding canopy inflation time and distances, a simple equation exists to give estimate the canopy inflation time. This equation is shown below; D o is the parachute nominal diameter calculated earlier this chapter. V is the velocity at line stretch and n is the canopy filling constant. Using this technique the first estimation of canopy filling time for both the main parachute and the pilot chute was calculated for different deployment velocities and displayed in the Figure 18. This mathematical prediction of canopy filling time indicates that for speeds above 5m/s both parachutes will inflate in less than 5 seconds. (8) Based on the continuity law parachutes should open within a fixed distance; because a given collum of air in front of the canopy must be used to inflate it. This distance is proportional to the diameter of the parachute (Knacke, 1992) and by using the equation below; Figure 18 - Mathematically Predicted Canopy Inflation Times (Cartwright, 2008). A constant value or parachute opening distance for the main canopy of m is predicted. This equation was also applied to the pilot chute and a much smaller canopy inflation distance of 4.21m was calculated. This method of calculating canopy inflation time and distance is used only as an initial estimate for the design. Given that it predicts the main canopy will inflate in a distance as little as 14.25m it provides evidence that this PRS design will deploy to full inflation even at low altitudes. It is imperative that these initial estimates however be validated by testing. Now that inflation times and distances have been estimated, parachute opening forces should also be considered. The inflation distance calculation gave an indication as to whether the canopy could open within a given altitude. Canopy opening force calculations will help determine whether or not a small balsa constructed UAV can handle the opening forces of a parachute at a given deployment speed. This force calculation will be important in trying to determine the mechanical feasibility of this PRS. There are several methods of determining the maximum canopy opening force. The method used here is known as the Pflanz Method, which was developed during WWII by E. Pflanz (Knacke, 1992). This method makes the assumption that the aircraft if flying on a horizontal path at the time of deployment. The first problem is to determine how much velocity decays from the UAV after the parachute is deployed but prior to the commencement of canopy inflation. This is done by using the equation below; (9) (10) 18

19 Velocity decay was found to occur prior to the inflation process. The magnitude of the velocity decay was taken away from the initial deployment speed and the resultant was used in the remainder of the opening force calculation. The amended velocity was now appropriate to use within the force equation below; The force equation above is very similar to the standard drag force equation 3. The different variables are the opening force coefficient C x and the force reduction factor X 1. The opening force coefficient is a tabulated value in ANNEX D, and the force reduction factor is found by calculating the dimensionless ballistic parameter, A using the equation shown. (11) The force reduction factor can now be found by using the relationship between force reduction factor and the dimensionless ballistic parameter A displayed in ANNEX E. Using this value for force reduction factor the parachute opening force can be determined for given deployment velocities and was graphed using excel to give the graph in figure 19. The mathematical data predicts a peak parachute opening force of approximately 800N at 20m/s deployment velocity. This indicates that even for lightweight recovery vehicles there is a substantial canopy opening force. Because this force occurs within the short time that the canopy inflates it is often referred to as the shock force. A deployment at 20m/s will produce considerable shock force and the (12) Figure 19 Mathematically Predicted Parachute Opening/Shock Forces for Different Deployment Speeds (Cartwright, 2008). maths indicates that a shock force attenuation system may be required. This may be in the form of an aerodynamic reefing system, or even a simple system such as an elastic riser to absorb some of the shock force during opening. H. Summary The major components of the PRS have been designed within this chapter. These components include the main canopy, pilot chute and deployment bag. At the very least these systems needed to be designed prior to determining if it were possible for a PRS to safely recover the UAV. To begin to understand if the PRS can safely recover the UAV in an appropriate altitude some preliminary calculations were made to determine the parachute filling times and opening distance. Canopy opening force predictions were also made which seem to indicate that the PRS may produce too much opening force for the airframe to handle. More accurate predictions about how much altitude will be lost and the amount of force the airframe will receive during a parachute deployment, need to be made. The chapter to follow is aimed at answering these questions so that an indication of the feasibility of the PRS can be deduced. 19

20 V. Testing and Analysis A. Introduction Due to the nature of the flight envelope of small model UAV research aircraft questions arise as to the suitability of PRSs. The mathematical calculations in the previous chapter seem to indicate that it is possible for a parachute canopy to fully inflate without losing to much altitude. These calculations are only an estimate however and testing needs to occur to back up the mathematics. This chapter describes the appropriate strategies, and methodologies used to plan, and execute testing of the parachute opening characteristics, to determine their mechanical feasibility for model aircraft. The objectives of the testing is to gain an insight into the; Parachute inflation times. Parachute inflation distances. Parachute reaction to wake flow. Confirmation of parachutes structural integrity. Parachute Recovery System Reliability and Repeatability. Deployment method verification. B. Method The most common method of testing parachutes is in the wind tunnel. This off coarse is the safest method and produces good reliable results. Unfortunately you are limited by the size of the parachute that can fit inside a wind tunnel, and using a smaller model parachute can compromise the dynamic similarity and give meaningless results. For this reason, along with the limited resources that are available at the Australian Defence Force Academy, a simple method designed to reproduce the effects of a wind tunnel test. The basic test approach will involve dynamic parachute testing. The method will make use of a motor vehicle to induce different parachute opening speeds. The parachute will be contained in the deployment bag until the vehicle reaches the appropriate deployment speed. Once this occurs the parachute will be deployed and allowed to inflate, while being recorded for analysis. This will be repeated several times at different deployment velocities. A frame by frame demonstration of the parachute inflation process resulting from the testing method is displayed in ANNEX F. C. Results and Validation The testing occurred on a calm day to ensure that the results would be as reliable as possible. All of the test runs were filmed for later analysis. The freeze frame image in figure 20 illustrates the fully inflated canopy during a test run and demonstrates how the testing was carried out. Runs were conducted, at 10km/h and increased in 10km/h intervals until 50km/h was reached. Each deployment speed was repeated several times so that an average of the results could be attained. The average of the results is displayed in table 4. Deployment Speed (km/h) Inflation Time (s) Inflation Distance (m) Table 3 - Experimental Results (Cartwright, 2008). 20 Figure 20 - Captured Image from Dynamic Test Run (Cartwright, 2008).

rocket s apogee. When this ejection occurs, the balloon and canister will no longer be

rocket s apogee. When this ejection occurs, the balloon and canister will no longer be 4.0 Drogue Chute The balloon and electronics canister will be ejected from the balloon near the rocket s apogee. When this ejection occurs, the balloon and canister will no longer be attached to the rocket

More information

Harness Mounted Drogue Chute Operator s Manual

Harness Mounted Drogue Chute Operator s Manual Harness Mounted Drogue Chute Operator s Manual May 5, 1999 - First Edition Copyright 1999 by Sport Kites, Inc. dba Wills Wing, Inc. All rights reserved. No part of this manual may be reproduced in any

More information

PROJECT. The University of Akron. NASA Flight Readiness Review. 12 March 2018

PROJECT. The University of Akron. NASA Flight Readiness Review. 12 March 2018 PROJECT The University of Akron NASA Flight Readiness Review 12 March 2018 Rail Exit velocity of 23 Ft/s Corkscrew flight up to 960 Ft Ballistic crash landing near launch site The University of Akron College

More information

Pneumatic Mortar Development for the NASA/Orion Capsule Drogue Parachute System

Pneumatic Mortar Development for the NASA/Orion Capsule Drogue Parachute System 21st AIAA Aerodynamic Decelerator Systems Technology Conference and Seminar 23-26 May 2011, Dublin, Ireland AIAA 2011-2598 Pneumatic Mortar Development for the NASA/Orion Capsule Drogue Parachute System

More information

International Journal of Advance Engineering and Research Development DESIGN AND SIMULATION OF AUTONOMOUS PARACHUTE SYSTEM FOR UNMANNED AERIAL VEHICLE

International Journal of Advance Engineering and Research Development DESIGN AND SIMULATION OF AUTONOMOUS PARACHUTE SYSTEM FOR UNMANNED AERIAL VEHICLE Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 06, June -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 DESIGN

More information

Low Cost HALO Cargo Airdrop Systems

Low Cost HALO Cargo Airdrop Systems 2th AIAA Aerodynamic Decelerator Systems Technology Conference and Seminar 4-7 May 29, Seattle, Washington AIAA 29-291 Low Cost HALO Cargo Airdrop Systems James Sadeck 1, Justin Riley 2, Kenneth J.

More information

PROJECT. The University of Akron. NASA Critical Design Review. 12 March 2018

PROJECT. The University of Akron. NASA Critical Design Review. 12 March 2018 PROJECT The University of Akron NASA Critical Design Review 12 March 2018 Air brake deployment just after rail exit as rocket fishtailed Corkscrew flight up to ~900 feet Ballistic crash landing near launch

More information

PROJECT. The University of Akron. NASA Critical Design Review. 26 January 2018

PROJECT. The University of Akron. NASA Critical Design Review. 26 January 2018 PROJECT The University of Akron NASA Critical Design Review 26 January 2018 Flawless Flight Motor detached during recovery during parachute inflation Detachment caused a fin to break off airframe Airframe

More information

University of Florida Rocket Team Critical Design Review

University of Florida Rocket Team Critical Design Review University of Florida Rocket Team Critical Design Review Agenda Overview Concept of Operations Launch Vehicle Dimensions Mass Statement and mass margin Launch Vehicle Key Design Features Motor Choice Stability

More information

University of Florida Rocket Team Flight Readiness Review

University of Florida Rocket Team Flight Readiness Review University of Florida Rocket Team Flight Readiness Review Agenda Overview Concept of Operations Mass Statement and Margin Launch Vehicle Launch Vehicle Dimensions Key Design Features Vehicle Integration

More information

TRAJECTORY ANALYSIS FOR THE HY-V SCRAMJET FLIGHT EXPERIMENT AND THE EFFECTS OF A RECOVERY SYSTEM

TRAJECTORY ANALYSIS FOR THE HY-V SCRAMJET FLIGHT EXPERIMENT AND THE EFFECTS OF A RECOVERY SYSTEM TRAJECTORY ANALYSIS FOR THE HY-V SCRAMJET FLIGHT EXPERIMENT AND THE EFFECTS OF A RECOVERY SYSTEM Amanda I. Smith University of Virginia, Charlottesville, Virginia 22904 Dr. Christopher P. Goyne, Advisor

More information

Milestone Review Flysheet

Milestone Review Flysheet Review Flysheet Vehicle Properties Motor Properties Total Length (in) 104 Motor Manufacturer Aerotech Diameter (in) 4.02 Motor Designation K1103X Gross Lift Off Weigh (lb) 13.176 Max/Average Thrust (lb)

More information

System Level Design. Tasks: Aerodynamic Analysis, Atmospheric Measurements. Three Subsystems: Recovery Structural Aerodynamics and Flight Stability

System Level Design. Tasks: Aerodynamic Analysis, Atmospheric Measurements. Three Subsystems: Recovery Structural Aerodynamics and Flight Stability System Level Design Tasks: Aerodynamic Analysis, Atmospheric Measurements Three Subsystems: Recovery Structural Aerodynamics and Flight Stability Significant Features: Drag flap control system Vehicle

More information

Executive Summary. Team Jarts Rocket Design. Brett Foster, Joe Hintz, Eric Logisz, Cameron Schulz. Milwaukee School of Engineering

Executive Summary. Team Jarts Rocket Design. Brett Foster, Joe Hintz, Eric Logisz, Cameron Schulz. Milwaukee School of Engineering Team Jarts Rocket Design Brett Foster, Joe Hintz, Eric Logisz, Cameron Schulz Milwaukee School of Engineering Executive Summary The objective of the 2013 Wisconsin Space Grant Consortium collegiate rocket

More information

Georgia Tech CDR VTC Slides. Project Simple Complexity Critical Design Review VTC Slides January 2015

Georgia Tech CDR VTC Slides. Project Simple Complexity Critical Design Review VTC Slides January 2015 Georgia Tech CDR VTC Slides Project Simple Complexity 2014-2015 Critical Design Review VTC Slides January 2015 1 Agenda 1. Team Overview (1 Min) 2. Changes Since Preliminary Design Review (PDR) (1 Min)

More information

NUSPACE. Northeastern University Scientific Payloads: AtmosphericMeasurement and Controlled-Descent Experiment. Flight Readiness Review

NUSPACE. Northeastern University Scientific Payloads: AtmosphericMeasurement and Controlled-Descent Experiment. Flight Readiness Review NUSPACE Northeastern University Scientific Payloads: AtmosphericMeasurement and Controlled-Descent Experiment Flight Readiness Review Final CDLE Design ATMOS Design and Dimensions ATMOS Components situated

More information

Separation Flight Tests of a Small Unmanned Air Vehicle from a C-130 Transport Aircraft

Separation Flight Tests of a Small Unmanned Air Vehicle from a C-130 Transport Aircraft Small Unmanned Air Vehicle from a C-130 Transport Aircraft David W. Roberts & Aaron D. Judy Integrated Systems Evaluation, Experimentation, and Test Dept Naval Air Systems Command Patuxent River, MD 20670

More information

Drogue Activated System (DAS)

Drogue Activated System (DAS) NAA MILITARY PRODUCT CATALOG Drogue Activated System (DAS) North American Aerodynamics, Inc. Quality products since 1964 1803 North Main Street, ROXBORO, NC 27573 - PHONE 336-599-9266 FAX 336-599-9442

More information

Critical Design Review

Critical Design Review Critical Design Review University of Illinois at Urbana-Champaign NASA Student Launch 2016-2017 Illinois Space Society 1 Overview Illinois Space Society 2 Launch Vehicle Summary Illinois Space Society

More information

Flight Readiness Review Presentation

Flight Readiness Review Presentation Flight Readiness Review Presentation THE UNIVERSITY OF MISSISSIPPI ROCKET REBELS UNIVERSITY STUDENT LAUNCH INITIATIVE The Launch Vehicle 3/9/2017 2016-2017 USLI FLIGHT READINESS REVIEW 2 Vehicle Layout

More information

Critical Design Review Presentation

Critical Design Review Presentation Critical Design Review Presentation THE UNIVERSITY OF MISSISSIPPI ROCKET REBELS UNIVERSITY STUDENT LAUNCH INITIATIVE Vehicle Layout and Dimensional Data Structure and Propulsion Total Length 111 in Outer

More information

NASA Student Launch 2017

NASA Student Launch 2017 NASA Student Launch 2017 Critical Design Review Presentation SOCIETY OF AERONAUTICS AND ROCKETRY January 18th, 2017 1 Final Launch Vehicle Dimensions Property Quantity Diameter (in) 6 Length (in) 145 Projected

More information

MSC NASTRAN AEROELASTICITY FOR AIRCRAFT CERTIFICATION

MSC NASTRAN AEROELASTICITY FOR AIRCRAFT CERTIFICATION SESSION TITLE WILL BE COMPLETED BY MSC SOFTWARE MSC NASTRAN AEROELASTICITY FOR AIRCRAFT Robert Lind (TLG Aerospace, USA); Steve Muenzberg (TLG Aerospace, USA) Robert Lind, Engineering Manager SUMMARY MSC

More information

Investigation of Orion Re-Entry Drogue Chute Aerodynamic Characteristics

Investigation of Orion Re-Entry Drogue Chute Aerodynamic Characteristics 50th AIAA Aerospace Sciences Meeting including the New Horizons Forum and Aerospace Exposition 09-12 January 2012, Nashville, Tennessee AIAA 2012-0270 Investigation of Orion Re-Entry Drogue Chute Aerodynamic

More information

PIA TS 135. Parachute Industry Association (PIA) TECHNICAL STANDARD 135

PIA TS 135. Parachute Industry Association (PIA) TECHNICAL STANDARD 135 Parachute Industry Association (PIA) TECHNICAL STANDARD 135 MINIMUM PERFORMANCE STANDARDS FOR PERSONNEL PARACHUTE ASSEMBLIES AND COMPONENTS 1. SCOPE: This document defines the minimum performance standards

More information

EPSRC Centre for Doctoral Training in Industrially Focused Mathematical Modelling

EPSRC Centre for Doctoral Training in Industrially Focused Mathematical Modelling EPSRC Centre for Doctoral Training in Industrially Focused Mathematical Modelling Swarm Robotics in Bearing-Only Formations Joseph Field Contents 1. Introduction... 2 2. Formulating the Problem... 3 Glossary

More information

DESIGN AND TESTING OF THE KISTLER LANDING SYSTEM PARACHUTES

DESIGN AND TESTING OF THE KISTLER LANDING SYSTEM PARACHUTES DESIGN AND TESTING OF THE KISTLER LANDING SYSTEM PARACHUTES Anthony P. Taylor *, Robert J. Sinclair, Richard D. Allamby, M.B.E. Irvin Aerospace Inc., Santa Ana, California 9274 The Kistler Landing system

More information

Milestone Review Flysheet

Milestone Review Flysheet Milestone Review Flysheet 2017-2018 Institution University of Alabama in Huntsville Milestone Critical Design Re Vehicle Properties Total Length (in) Diameter (in) Gross Lift Off Weigh (lb.) Airframe Material(s)

More information

SOFT RECOVERY SYSTEMS FOR GUN- FIRED PROJECTILE COMPONENTS

SOFT RECOVERY SYSTEMS FOR GUN- FIRED PROJECTILE COMPONENTS SOFT RECOVERY SYSTEMS FOR GUN- FIRED PROJECTILE COMPONENTS Item Type text; Proceedings Authors Fritch, Paul L.; Spinelli, Carmine J. Publisher International Foundation for Telemetering Journal International

More information

Milestone Review Flysheet

Milestone Review Flysheet Review Flysheet Vehicle Properties Motor Properties Total Length (in) 115 Motor Manufacturer Cesaroni Diameter (in) 7.5 Motor Designation L1115 Gross Lift Off Weigh (lb) 40.9 Max/Average Thrust (lb) 385.1/251.6

More information

Entry, Descent, and Landing System Design for the Mars Gravity Biosatellite

Entry, Descent, and Landing System Design for the Mars Gravity Biosatellite Entry, Descent, and Landing System Design for the Mars Gravity Biosatellite Ashley M. Korzun Georgia Institute of Technology Space Systems Design Laboratory 26 June 2008 Atlanta, Georgia Christine Hartzell

More information

Harvard-Westlake School Preliminary Design Review. Summary

Harvard-Westlake School Preliminary Design Review. Summary Harvard-Westlake School Preliminary Design Review Summary Team Summary Harvard-Westlake School North Hollywood, California Teachers o Mr. Jacob Hazard o Ms. Karen Hutchison Mentor o Mr. Rick Dickinson

More information

PDR: CanSat-1.

PDR: CanSat-1. PDR: CanSat-1 masacontact@umich.edu Preliminary Design Review Presenters: Aaron Skiba - skiba@umich.edu Patrick Kellam - pjkellam@umich.edu Britton Bush - britbush@umich.edu Leslie Davies - Jeremy Jones

More information

EARTHQUAKE-RESISTANT BRIDGE COMPETITION STUDENT GUIDELINES

EARTHQUAKE-RESISTANT BRIDGE COMPETITION STUDENT GUIDELINES EARTHQUAKE-RESISTANT BRIDGE COMPETITION STUDENT GUIDELINES A PROJECT DEVELOPED FOR THE UNIVERSITY CONSORTIUM ON INSTRUCTIONAL SHAKE TABLES Developed by: Kurt McMullin Assistant Professor Department of

More information

University of Florida Rocket Team Preliminary Design Review

University of Florida Rocket Team Preliminary Design Review University of Florida Rocket Team Preliminary Design Review Agenda Overview Mission Statement Concept of Operations Summary Vehicle Subsystems Motor Choice Flight Dynamics and Simulations Payloads Target

More information

ROCKET CONTEST CONTEST TERMS AND CONDITIONS

ROCKET CONTEST CONTEST TERMS AND CONDITIONS ROCKET CONTEST CONTEST TERMS AND CONDITIONS Terms and Definitions: Payload: Any system circling an orbit or falling in trajectory from a specific altitude designed to complete a scientific/commercial/military

More information

S.T.E.M. Integrated Robotics Detailed Outline

S.T.E.M. Integrated Robotics Detailed Outline S.T.E.M. Integrated Robotics Detailed Outline Unit 1: An Introduction to Drones Time: 4 Days Lesson 1.1 Introduction to MINDS-i 1. A brief intro of how MINDS-i defines STEM education and STEM Integrated

More information

CAR High Power Rocket. Level 4 Certification Process

CAR High Power Rocket. Level 4 Certification Process Canadian Association of Rocketry Level 4 Certification Process CAR High Power Rocket Level 4 Certification Process Version: 1.61 - Updated: September 20, 2009 Page 1 of 13 Contents 1. Introduction... 3

More information

ALSET - Japanese Air Launch System Concept and Test Plan

ALSET - Japanese Air Launch System Concept and Test Plan ALSET - Japanese Air Launch System Concept and Test Plan Yuichi Noguchi, Takashi Arime and Seiji Matsuda IHI AEROSPACE Co., Ltd. yuichi-noguchi@iac.ihi.co.jp Tomioka-shi, Gunma, Japan Takayoshi Fuji Japan

More information

Control and Stability in Aircraft Conceptual Design

Control and Stability in Aircraft Conceptual Design Gnat Control and Stability in Aircraft Conceptual Design W. H. Mason YF-17 graphics from Joe Chambers F-104 T-45 Based on AIAA Paper 93-3968, Control Authority Assessment in Aircraft Conceptual Design,

More information

Hydro Electric Power (Hydel Power)

Hydro Electric Power (Hydel Power) Operating Principle Hydro Electric Power (Hydel Power) Hydro-electric power is generated by the flow of water through turbine, turning the blades of the turbine. A generator shaft connected to this turbine

More information

Rotary Air Force Marketing, Inc. Presents: THE RAF 2000 ROTOR STABILATOR PATENT PENDING

Rotary Air Force Marketing, Inc. Presents: THE RAF 2000 ROTOR STABILATOR PATENT PENDING Presents: THE RAF 2000 ROTOR STABILATOR PATENT PENDING Box 1236,1107-9 th St W Kindersley, Saskatchewan S0L 1S0 Canada Tel: 306-463-6030, Fax: 306-463-6032 Email: info@raf2000.com Web: http://www.raf2000.com

More information

ROCKET CONTEST CONTEST TERMS AND CONDITIONS

ROCKET CONTEST CONTEST TERMS AND CONDITIONS ROCKET CONTEST CONTEST TERMS AND CONDITIONS Terms and Definitions: Payload: Any system circling an orbit or falling in trajectory from a specific altitude designed to complete a scientific/commercial/military

More information

CTY FLIGHT SCIENCE SYLLABUS

CTY FLIGHT SCIENCE SYLLABUS CTY FLIGHT SCIENCE SYLLABUS Day 1. 1. Introductions 2. Honor Code 3. Lab Safety 4. Determine current knowledge 5. Determine students experiences with flight 1. Scientific vs. Engineering Method 2. Variables

More information

PROGRESS REPORT Document

PROGRESS REPORT Document SAE AERO DESIGN WEST THE WRIGHT STUFF By AARON LOSTUTTER, ADAM NELESSEN, JACOB VINCENT, ZEV VALLANCE, AND BRANDON PEREZ Team 10 PROGRESS REPORT Document Submitted towards partial fulfillment of the requirements

More information

FOREWORD PRODUCT SPECIFICATIONS MAIN CHARACTER MAIN ACCESSORIES SAFETY PROCEDURES BEFORE FLIGHT LIMITATIONS OF FLYING AREA ASSEMBLING THE AIRCRAFT

FOREWORD PRODUCT SPECIFICATIONS MAIN CHARACTER MAIN ACCESSORIES SAFETY PROCEDURES BEFORE FLIGHT LIMITATIONS OF FLYING AREA ASSEMBLING THE AIRCRAFT FOREWORD PRODUCT SPECIFICATIONS MAIN CHARACTER MAIN ACCESSORIES SAFETY PROCEDURES BEFORE FLIGHT LIMITATIONS OF FLYING AREA ASSEMBLING THE AIRCRAFT SETUP OF THE TRANSMITTER THE USAGE OF THE CHARGER VALUABLE

More information

Drone Adjustment Play Block Coding System for Early Childhood

Drone Adjustment Play Block Coding System for Early Childhood , pp.122-126 http://dx.doi.org/10.14257/astl.2017.145.24 Drone Adjustment Play Block Coding System for Early Childhood Yeon-Jae Oh 1, Young-Sang Suh 2 and Eung-Kon Kim 1 1 Department of Computer Engineering,

More information

Georgia Tech NASA Flight Readiness Review Teleconference

Georgia Tech NASA Flight Readiness Review Teleconference Georgia Tech NASA Flight Readiness Review Teleconference Agenda 1. 2. 3. 4. 5. 6. 7. 8. Project KRIOS - FRR TEAM OVERVIEW Georgia Tech Team Overview Work Breakdown Structure Project KRIOS - FRR CHANGES

More information

Team RPGs Flight Readiness Review

Team RPGs Flight Readiness Review Team RPGs Flight Readiness Review 1 Length 89.50 Diameter 6.00 Weight 6.75/15.3 Fin Span 22.00 Center of Gravity 51.4/57.44 Center of Pressure 70.33 Static Stability 3.20/2.11 2 1. The rocket is designed

More information

Concept Paper. Unmanned Aerial Surveillance for Perimeter Security Missions

Concept Paper. Unmanned Aerial Surveillance for Perimeter Security Missions BUSTER Concept Paper Unmanned Aerial Surveillance for Perimeter Security Missions Aerostat Introduction. This paper is submitted to demonstrate a family of concepts for providing aerial surveillance in

More information

Auto Pilot Controlled Flying Wing (UAV) For QRF (Quick Reaction Armed Forces)

Auto Pilot Controlled Flying Wing (UAV) For QRF (Quick Reaction Armed Forces) IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 6 Ver. II (Nov. - Dec. 2015), PP 43-47 www.iosrjournals.org Auto Pilot Controlled Flying

More information

NASA s Student Launch Initiative :

NASA s Student Launch Initiative : NASA s Student Launch Initiative : Seniors 8 Juniors 2 Sophomores 6 Interdisciplinary 2 Preliminary Design Review Payload: Fragile Material Protection Freshman 5 1 Agenda 1. Team Overview 2. 3. 4. I. Airframe

More information

Final Publishable Summary

Final Publishable Summary FANTASSY Future Aircraft design following the carrier-pod concept as an enabler for co-modal seamless transport, passenger safety and environmental sustainability FP7-309070 Final Publishable Summary Grant

More information

Available online at ScienceDirect. Procedia Engineering 112 (2015 )

Available online at  ScienceDirect. Procedia Engineering 112 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 112 (2015 ) 430 435 7th Asia-Pacific Congress on Sports Technology, APCST 2015 Effect of porosity of badminton shuttlecock on

More information

8/28/2018. UAS110 Intro to UAV Systems 1: Overview and Background. UAS110 Intro to Unmanned Aerial Systems. Initial Definitions: UAV

8/28/2018. UAS110 Intro to UAV Systems 1: Overview and Background. UAS110 Intro to Unmanned Aerial Systems. Initial Definitions: UAV UAS110 Intro to Unmanned Aerial Systems 1: Overview & Background 2018 J. Sumey California University of PA rev. 8/28/18 Initial Definitions: UAV UAV = Unmanned Aerial Vehicle def: an unmanned (uninhabited)

More information

P11562 MIS Frame and Stabilization Module Detailed Design Review

P11562 MIS Frame and Stabilization Module Detailed Design Review P11562 MIS Frame and Stabilization Module Detailed Design Review Rob Bingham Matt Moore Karen Smith KGCOE MSD Technical Review Agenda Meeting Purpose: Review and receive feedback for the design of P11562

More information

Trial version. Thermal Expansion of Solids. How can an engineer assess the expansion characteristics of a rail to produce an optimal design?

Trial version. Thermal Expansion of Solids. How can an engineer assess the expansion characteristics of a rail to produce an optimal design? Thermal Expansion of Solids How can an engineer assess the expansion characteristics of a rail to produce an optimal design? Thermal Expansion of Solids page: 1 of 10 Contents Initial Problem Statement

More information

FORMATION FLIGHT OF FIXED-WING UAVS USING ARTIFICIAL POTENTIAL FIELD

FORMATION FLIGHT OF FIXED-WING UAVS USING ARTIFICIAL POTENTIAL FIELD FORMATION FLIGHT OF FIXED-WING UAVS USING ARTIFICIAL POTENTIAL FIELD Yoshitsugu Nagao*and Kenji Uchiyama* *Department of Aerospace Engineering, Nihon University csyo1217@g.nihon-u.ac.jp, uchiyama@aero.cst.nihon-u.ac.jp

More information

Wind Tunnel Evaluation of 6 feet Spanned Mini Aerial Vehicle (Kadet)

Wind Tunnel Evaluation of 6 feet Spanned Mini Aerial Vehicle (Kadet) Wind Tunnel Evaluation of 6 feet Spanned Mini Aerial Vehicle (Kadet) Kailash Kotwani, Hemendra Arya, K Sudhakar Center for Aerospace System and Design Engineering Department of Aerospace Engineering Indian

More information

gravity (9.8 m/s2) the person is experiencing 1g. If for example, the mass of this person is 85

gravity (9.8 m/s2) the person is experiencing 1g. If for example, the mass of this person is 85 Complete Environmental Monitoring UltraShock What Does the UltraShock Do? The UltraShock is a portable data logger designed to record the following environmental variables: shock (g-force; impact/acceleration),

More information

Typical Aerospace Teams and Tasks. Aerospace Design Teams Emphasizing Conceptual Design

Typical Aerospace Teams and Tasks. Aerospace Design Teams Emphasizing Conceptual Design Typical Aerospace Teams and Tasks W.H. Mason Typical Aerospace Organization Responsibilities of each team member The RFPs in, what now? slide 1 Aerospace Design Teams Emphasizing Conceptual Design Classical

More information

2002 Design Task: (Option 1) High Performance Multi-Role Unmanned Aerial Vehicle (UAV)

2002 Design Task: (Option 1) High Performance Multi-Role Unmanned Aerial Vehicle (UAV) AERO 4400 Aircraft Design 3 2002 Design Task: (Option 1) High Performance Multi-Role Unmanned Aerial Vehicle (UAV) 6 credit points Assessment: This task, with four (4) hand-in assignments (detailed separately)

More information

NASA SL Flight Readiness Review

NASA SL Flight Readiness Review NASA SL Flight Readiness Review U N I V E R S I T Y O F A L A B A M A I N H U N T S V I L L E C H A R G E R R O C K E T WORKS M A R C H 9, 2 0 1 7 Presentation Summary Project Overview Readiness and Design

More information

Autonomous Precision Delivery of 42,000 Pounds (19,000 kg) Under One Parachute

Autonomous Precision Delivery of 42,000 Pounds (19,000 kg) Under One Parachute 20th AIAA Aerodynamic Decelerator Systems Technology Conference and Seminar 4-7 May 2009, Seattle, Washington AIAA 2009-2928 Autonomous Precision Delivery of 42,000 Pounds (19,000 kg) Under One Parachute

More information

CHAPTER - 1 INTRODUCTION

CHAPTER - 1 INTRODUCTION CHAPTER - 1 INTRODUCTION Development of Space Launch vehicle is critical for the selfreliant programme of space endeavor of any country. The development of Space launch vehicles is with indigenous effort

More information

Design of a High-g Unmanned Aerial Vehicle Structure

Design of a High-g Unmanned Aerial Vehicle Structure Design of a High-g Unmanned Aerial Vehicle Structure Seth S. Kessler, S. Mark Spearing and Greg A. Kirkos TECHNOLOGY LABORATORY FOR ADVANCED COMPOSITES Department of Aeronautics and Astronautics Massachusetts

More information

APP - Aircraft Performance Program

APP - Aircraft Performance Program Introduction APP - Aircraft Performance Program Introduction APP is an aircraft-performance calculation program, specifically designed to provide a fast and easy way to evaluate aircraft performance. Another

More information

NU HOPE. Northeastern University. High-altitude Object Protection Experiment

NU HOPE. Northeastern University. High-altitude Object Protection Experiment NU HOPE Northeastern University High-altitude Object Protection Experiment Agenda Overview of Vehicle Properties Stability Analysis Launch Vehicle Sections and Systems Booster Stage Interstage system Payload

More information

The Edge Protection Federation Containment Systems Product Specification, Test Methods

The Edge Protection Federation Containment Systems Product Specification, Test Methods The Edge Protection Federation Containment Systems Product Specification, Test Methods Revision 2 August 2016 This Standard defines how the Edge Protection Federation defines Containment. This document

More information

Instruction Manual ODY-1012

Instruction Manual ODY-1012 Ages 8+ Instruction Manual ODY-1012 INCLUDED CONTENTS: 1 Fuselage Cover 2 Main Frame / Cage 3 Main Blades (x 4) 4 3.7 Rechargeable Lithium Battery 5 USB Charging Cable 6 Radio Transmitter Thank you for

More information

Analytical Analysis for Enhancement of Performance and Efficiency for Different Blade of HAWT by Computer Program

Analytical Analysis for Enhancement of Performance and Efficiency for Different Blade of HAWT by Computer Program Analytical Analysis for Enhancement of Performance and Efficiency for Different Blade of HAWT by Computer Program 1 Hemant Rav Patel, 2 Dr. V.N. Bartaria, 3 Dr. A.S. Rathore 1 Department of Mechanical

More information

Integrated Product Developmenta Key to Affordability

Integrated Product Developmenta Key to Affordability Integrated Product Developmenta Key to Affordability Gunnar Holmberg Future Products and Technology Saab AB (publ.) Abstract Integrated Product Development (IPD) has been a major approach to improve performance

More information

Post Stall Landing for Field Retrieval of UAVs

Post Stall Landing for Field Retrieval of UAVs Post Stall Landing for Field Retrieval of UAVs W.J.Crowther K.Prassas University of Manchester Abstract The post stall landing manoeuvre enables a conventional fixed wing flight vehicle to be delivered

More information

Photovoltaic (PV) Arrays

Photovoltaic (PV) Arrays y l n O s r e b m e M S H n B o I i t r u b Fo i r t s i D l a n r e t x E Not for Photovoltaic (PV) Arrays Wind Performance of Ballasted PV Arrays on Low-Slope Commercial Roofs October 2015 Executive

More information

Advantages of Composite Materials in Aircraft Structures

Advantages of Composite Materials in Aircraft Structures Advantages of Composite Materials in Aircraft Structures Muniyasamy Kalanchiam, and Moorthy Chinnasamy Abstract In the competitive environment of aircraft industries it becomes absolutely necessary to

More information

In partnership with. Sponsors

In partnership with. Sponsors 2 nd Annual AUVSI Student UAV Competition In partnership with Sponsors 2004 MISSION, SCORING AND RULES OBJECTIVE The goals of this competition are to challenge a new generation of undergraduate university

More information

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure C.Y. Shao Shanghai Municipal Engineering Design & Research General Institute (Group) Co. Ltd.,

More information

Universal TAU-II Redirective, Non-Gating, Crash Cushion

Universal TAU-II Redirective, Non-Gating, Crash Cushion TB 010925 Rev. 2 Page 1 of 10 Product Specification Universal TAU-II Redirective, Non-Gating, Crash Cushion I. General The Universal TAU-II system is a Redirective, Non-Gating Crash Cushion in accordance

More information

Payload Separation System. Concept Generation and Selection Document

Payload Separation System. Concept Generation and Selection Document Payload Separation System By Benjamin Dirgo, Mark Majkrzak, Jason McCall, Matthew Mylan, Kate Prentice, Alen Younan Team 11 Concept Generation and Selection Document Submitted towards partial fulfillment

More information

System development of an experimental rocket for launching campaign organized by French association Planete Sciences

System development of an experimental rocket for launching campaign organized by French association Planete Sciences System development of an experimental rocket for launching campaign organized by French association Planete Sciences Minoru Sasaki 1, Noriaki Nakano 2 and Satoru Ohmayu 1 1 Department of Human and Information

More information

COANDA A NEW AIRSPACE PLATFORM FOR UAVS R J

COANDA A NEW AIRSPACE PLATFORM FOR UAVS R J COANDA A NEW AIRSPACE PLATFORM FOR UAVS R J Collins My paper is entitled "Coanda - A new airspace platform for UAVs" and whilst it is confined to UAVs I expect it will become clear that it may have wider

More information

Towed Body Altitude Stabilization and States Estimation in Aerial Recovery of Micro Air Vehicles

Towed Body Altitude Stabilization and States Estimation in Aerial Recovery of Micro Air Vehicles Towed Body Altitude Stabilization and States Estimation in Aerial Recovery of Micro Air Vehicles Liang Sun and Randal W. Beard In this paper, we present two strategies to stabilize the altitude of the

More information

Tacho Lycos PDR Presentation. November 14, 2016

Tacho Lycos PDR Presentation. November 14, 2016 Tacho Lycos PDR Presentation November 14, 2016 Overview Vehicle Summary Flight Data Avionics Recovery System Payload Target Differentiation System (TDS) Upright Landing System (ULS) Compliance 2 Vehicle

More information

Rolling processes. Fig. (5-1)

Rolling processes. Fig. (5-1) Page1 Rolling processes 5-1 introduction: Rolling is the process of reducing the thickness or changing the cross section of a long workpiece by compressive forces applied through a set of rolls, as shown

More information

Advances in Airframe Load Monitoring Methodology for Individual Aircraft Tracking

Advances in Airframe Load Monitoring Methodology for Individual Aircraft Tracking Advances in Airframe Load Monitoring Methodology for Individual Aircraft Tracking Oleg Levinski, David P. Conser Aerospace Division, Defence Science and Technology Group, 506 Lorimer Street, Fishermans

More information

Finite Element Analysis of Carbon Fibre Reinforced Aircraft Wing

Finite Element Analysis of Carbon Fibre Reinforced Aircraft Wing IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 11, Issue 4 Ver. V (Jul- Aug. 2014), PP 12-16 Finite Element Analysis of Carbon Fibre Reinforced

More information

AN INBOARD-WING ARRANGEMENT FOR HIGH-CAPACITY AIRLIFT AND SEALIFT VEHICLES

AN INBOARD-WING ARRANGEMENT FOR HIGH-CAPACITY AIRLIFT AND SEALIFT VEHICLES 1 AN INBOARD-WING ARRANGEMENT FOR HIGH-CAPACITY AIRLIFT AND SEALIFT VEHICLES M. Leroy Spearman NASA Langley Research Center Hampton, Virginia USA 23681 NATO Research and Technology Agency Applied Vehicle

More information

FAA APPROVED ROTORCRAFT FLIGHT MANUAL SUPPLEMENT

FAA APPROVED ROTORCRAFT FLIGHT MANUAL SUPPLEMENT FAA APPROVED ROTORCRAFT FLIGHT MANUAL SUPPLEMENT STC SR01943SE R/N S/N Cargo Hook Kit 1 of 22 Record of Revisions Rev. Date (s) Reason for Revision 0 Dec. 5, 2008 All Initial Release. 1 Sept. 10, 2015

More information

Comparisons of the Impact Responses of a 1/5-Scale Model and a Full-Scale Crashworthy Composite Fuselage Section

Comparisons of the Impact Responses of a 1/5-Scale Model and a Full-Scale Crashworthy Composite Fuselage Section Comparisons of the Impact Responses of a 1/5-Scale Model and a Full-Scale Crashworthy Composite Fuselage Section Karen E. Jackson and Edwin L. Fasanella Karen H. Lyle k.e.jackson@larc.nasa.gov, e.l.fasanella@larc.nasa.gov

More information

Dynamics of a River Kite Power Production System with a Kinetic Energy Storage Device

Dynamics of a River Kite Power Production System with a Kinetic Energy Storage Device Proceedings of the International Conference of Control, Dynamic Systems, and Robotics Ottawa, Ontario, Canada, May 15-16 2014 Paper No. 55 Dynamics of a River Kite Power Production System with a Kinetic

More information

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim

More information

Modelling Dynamic Skyline Tensions in Rigging Configurations: North Bend, South Bend, and Block in the Bight Case Studies

Modelling Dynamic Skyline Tensions in Rigging Configurations: North Bend, South Bend, and Block in the Bight Case Studies Modelling Dynamic Skyline Tensions in Rigging Configurations: North Bend, South Bend, and Block in the Bight Case Studies Hunter Harrill 1 and Rien Visser 2 Abstract In New Zealand the proportion of forest

More information

Numerical Simulation of the Aerodynamic Performance of a H-type Wind Turbine during Self-Starting

Numerical Simulation of the Aerodynamic Performance of a H-type Wind Turbine during Self-Starting Numerical Simulation of the Aerodynamic Performance of a H-type Wind Turbine during Self-Starting Wei Zuo a, Shun Kang b Key Laboratory of Condition Monitoring and Control for Power Plant Equipment, Ministry

More information

Testing and analysis of masonry arches subjected to impact loads

Testing and analysis of masonry arches subjected to impact loads Testing and analysis of masonry arches subjected to impact loads Paulo B. Lourenço, Tibebu Hunegn and Pedro Medeiros Department of Civil Engineering, ISISE, University of Minho, Guimarães, Portugal Nuno

More information

Chapter 2. Current Design Practice

Chapter 2. Current Design Practice Chapter 2 Current Design Practice This chapter reviews current South African practices for the design of power line towers (SABS 0280: 2001 - Overhead power lines for conditions prevailing in Southern

More information

University of Colorado Department of Aerospace Engineering Sciences ASEN 4018 Aerospace Senior Projects 1. Conceptual Design Document (CDD)

University of Colorado Department of Aerospace Engineering Sciences ASEN 4018 Aerospace Senior Projects 1. Conceptual Design Document (CDD) 2014 University of Colorado Department of Aerospace Engineering Sciences ASEN 4018 Aerospace Senior Projects 1 Conceptual Design Document (CDD) MODEFLIER Mode-Demonstrating Flying Laboratory: Instruction

More information

DLR HABLEG HIGH ALTITUDE BALLOON LAUNCHED EXPERIMENTAL GLIDER

DLR HABLEG HIGH ALTITUDE BALLOON LAUNCHED EXPERIMENTAL GLIDER DLR HABLEG HIGH ALTITUDE BALLOON LAUNCHED EXPERIMENTAL GLIDER Sven Wlach (1), Marc Schwarzbach (2), Maximilian Laiacker (3) (1) DLR - Institute of Robotics and Mechatronics, Oberpfaffenhoffen, Germany,

More information

PAL-V Starts Selling Its Commercial Models

PAL-V Starts Selling Its Commercial Models PAL-V Starts Selling Its Commercial Models 13 th of February 2017 This week, flying car manufacturer PAL-V has officially started the sales of its commercial models, the Liberty Pioneer and Liberty Sport.

More information

Tube Hydroforming 4.0: Opportunities Created by Efficient Processing

Tube Hydroforming 4.0: Opportunities Created by Efficient Processing Tube Hydroforming 4.0: Opportunities Created by Efficient Processing Tube Hydroforming - A Brief History Since arriving on the automotive scene as a way to make structural parts in the late 1980's, tube

More information

Solar Flat Plate Thermal Collector

Solar Flat Plate Thermal Collector Solar Flat Plate Thermal Collector 1 OBJECTIVE: Performance Study of Solar Flat Plate Thermal Collector Operation with Variation in Mass Flow Rate and Level of Radiation INTRODUCTION: Solar water heater

More information