Assessment of Load Shed Service for Import (LSSi) Product

Size: px
Start display at page:

Download "Assessment of Load Shed Service for Import (LSSi) Product"

Transcription

1 Assessment of Load Shed Service for Import (LSSi) Product Date: March 27, 2014 Prepared by: Prepared for: Mike Law Jenny Chen Senior Market Design Specialist Vice President, Market Services

2 Table of Contents 1 Executive Summary Background Assessment of LSSi Product Design Features Operational Assessment of LSSi Increase in Intertie Capability Learning Obtained Through Using LSSi and Potential Modifications to LSSi Contract Next Steps... 14

3 1 Executive Summary Load Shed Service for Imports (LSSi) is a transmission system reliability product developed by the AESO as part of the efforts to fulfill its intertie restoration obligation as mandated by legislation. LSSi is provided by loads that agree to be tripped following the frequency drop caused by the sudden loss of imports coming across the WECC connected interties (the AB-B.C. intertie and Montana Alberta Tie Line or MATL) due to intertie contingencies. This load shedding allows for arrest and recovery from frequency decay, and preserves system stability. LSSi is used to manage frequency risk so that import intertie capability can be increased, allowing additional scheduled imports to access the Alberta market without compromising system reliability. Historically, the AESO has used a number of under-frequency mitigation services to provide system reliability. These services included Import Load Remedial Action Scheme, Brazeau Fast Ramp and Load Shed Service. However, the AESO was unable to competitively contract these services in sufficient volume needed for import intertie restoration. The AESO attempted to competitively contract two other products (Load Shed Requirement and Fast Ramp Service) for the purpose of increasing intertie scheduling capability, but the Expression of Interest for both products was determined to be noncontestable due to a low level of responses. These unsuccessful procurement attempts necessitated the need for LSSi to be developed. LSSi was developed as part of the broader intertie restoration process, and also through demand response discussions that occurred in LSSi has a design feature that no other under-frequency mitigation services previously designed or implemented by the AESO have included, i.e. the providers are allowed to determine whether to make LSSi volumes available in a given hour, and one part of the LSSi payment is linked to availability. This feature reduces the risks of providing the service and incents providers to contract the service with the AESO. As a result, in late 2011, the AESO was able to successfully contract the needed volume through competitive procurement. The AESO contracted LSSi to increase import intertie capability in Q With LSSi in use for two years now, the AESO conducted an assessment of the product. The assessment focuses on evaluating the product design features of LSSi that enable increased import capability, as well as the learning obtained through using LSSi. The assessment also identifies potential areas where modifications to the contracts may be made in order to better achieve desired outcomes. LSSi, as a tool to restore intertie capability, became effective in November In 2012, the import Available Transfer Capability (ATC) of the AB B.C. intertie reached 700 MW, 1 higher than the maximum import ATC posted in each of the five years prior to the use of LSSi. The increased import capability achieved with LSSi enabled over 100,000 MWh of additional imports to gain access to the Alberta market in the 12-month period between April 1, 2012 and March 31, The experience of using LSSi to restore import intertie capability helped the AESO identify areas where possible modifications to the product may be beneficial. The areas examined by the AESO for possible modification include: Decreased available volume of LSSi at higher price levels No modification suggested. Stability of available LSSi volumes between T-85 and T-20 Modification considered: Require commitment to LSSi availability volume at T-85 minutes prior to a delivery hour. 1 The System Controller arms LSSi based on Table 10 of Information Document ID# R. According to this table, without LSSi, in the hours where the ATC reached 700 MW, the ATC would have been lower. Page 1

4 Manual tripping of LSSi load through System Controller s directive Modification considered: Require manual tripping in all contracts. Payments for LSSi availability when AB B.C. intertie is on outage or other transmission limitations mean that LSSi cannot increase import capability Modification considered: Eliminate availability payments when system import capability is limited to a level below which LSSi could be utilized to increase capability. Clarity in compliance Modification considered: Clarify compliance terms under which contracts may be terminated. Overall, the AESO intends to continue the use of LSSi as part of the intertie restoration program, as physical infrastructure solutions which may mitigate the frequency risk are still deemed to be impractical to implement in the short to medium term. As part of the broader intertie restoration program, the AESO is conducting an intertie system operating limit study. Based on the results of the study, the amount of LSSi arming volume required at various load and schedule levels will be reviewed and updated. This will be used to inform the volume of LSSi targeted to be contracted in the next RFP process. 2 Background The AESO uses LSSi to help manage frequency risk associated with increased intertie capability, and to enhance the access of in-merit imports to the Alberta market. Intertie restoration is mandated by the Electric Utilities Act (EUA) and Transmission Regulation, and directed by the Transmission Development Policy. Section 16 of the Transmission Regulation mandates the AESO to restore interties that existed in August 2004 to or near to their path ratings. Further, subsection 15(e)(i) states that the AESO must plan a transmission system that is sufficiently robust so that 100% of the time, transmission of all anticipated inmerit electric energy referred to in section 17(c) of the Act can occur when all transmission facilities are in service. Subsection 17(c) of the EUA includes scheduled exchanges of electric energy and ancillary services between the interconnected electric system in Alberta and electric systems outside Alberta Finally, the Transmission Development Policy provides direction for the AESO in its intertie restoration efforts. It states Transmission internal to Alberta should be reinforced so that under normal conditions, the existing inter-ties can import and export power on a continuous basis, in accordance with their design capability. As per the mandate described above, LSSi is a product developed to aid the AESO in fulfilling its intertie restoration obligation. The intent of LSSi is to increase the import capability of the Alberta system available for use by market participants. LSSi is a load shed service provided by loads that agree to be tripped in certain circumstances following the frequency drop caused by the loss of the WECC connected interties in order to arrest and recover from frequency decay, and preserve system stability. Use of LSSi to increase import capability is consistent with the overall goal, as laid out in legislation and policy, of implementing an unconstrained transmission system to enable wholesale market competition. The AESO historically has contracted a number of services to manage under-frequency situations, including those caused by intertie contingencies. For various reasons, the AESO has been unable to competitively procure a sufficient volume of these services. As an alternative, LSSi was developed through consultation with industry stakeholders. The under-frequency mitigation services that the AESO has contracted before are described below. Page 2

5 Import Load Remedial Action Scheme (ILRAS) 2 ILRAS was an armable ancillary service provided by interruptible loads that would be automatically tripped following the loss of the AB B.C. intertie. In 2006, the AESO issued a request for Expressions of Interest (EOI) to competitively procure ILRAS. However, since the total volume offered by all EOI respondents was less than the AESO s required volume, the EOI was determined to be non-contestable. In January 2007, the existing ILRAS contract was altered to only being used to enable imports during energy supply shortfall events. In October 2007, the AESO proposed that ILRAS be provided by distribution companies as a mandatory service also to facilitate in market imports, i.e. the imports that are not for the purpose to alleviate energy shortfall situation. However, the proposal was rejected by stakeholders. Subsequently, the AESO formed an ILRAS working group to further explore solutions. Based on an under-frequency study, the AESO concluded that ILRAS could be combined with another under-frequency service, Load Shed Service (LSS), into a single service called Load Shed Requirements (LSR). 3 The working group stated that both LSR and a fast ramp service were required to increase AB B.C. intertie capability, and reached a general agreement that a competitive process should be utilized initially to attempt to procure the requirements for LSR and a fast ramp service. 4 In the meantime, the ILRAS contract for energy supply shortfall events remained in effect. This ILRAS contract expired in June Brazeau Fast Ramp (BFR) BFR was an always armed ancillary service 5 provided by TransAlta s Brazeau facility to help arrest and recover from frequency decay. The BFR contract was established bilaterally between the AESO and TransAlta. The contract was not renewed when it expired in 2008, 6 as the ILRAS working group suggested that a fast ramp service be procured competitively. Load Shed Service (LSS) LSS was an ancillary service provided by loads that agreed to be automatically tripped when the frequency of Alberta Interconnected Electric System (AIES) dropped to 59.5 Hz. LSS agreements also allowed for manual curtailment of the loads following a trip of the AB B.C. intertie. 7 LSS was permanently armed and generally used in combination with ILRAS load to allow higher import levels on the AB B.C. intertie. In June 2008, based on the suggestion of the ILRAS working group to competitively procure LSR and Fast Ramp Service (FRS), the AESO issued an EOI for 485 MW of LSR and 150 MW FRS. In the EOI, the AESO stated that both services are ancillary services that would be used to manage frequency risk when increased imports on the AB B.C. intertie are scheduled. 8 Both LSR and FRS were designed as armable products and loads were also invited to respond to the EOI of FRS. However, due to insufficient responses to supply all of the LSR and FRS needed, it was determined that the market for LSR and FRS was not contestable. In 2009, the AESO undertook a broader stakeholder consultation on intertie restoration, and new services to restore intertie capability were evaluated in the consultation. In the same year, the Demand Response 2 This was also referred to as Interruptible Load Remedial action Scheme in the past. However, the current AESO s Consolidated Authoritative Document uses the term Import Load Remedial Action Scheme. 3 The AESO, Meeting minutes for Working Group Session on Interruptible Load Remedial Action Scheme (ILRAS), April 17, The AESO, Meeting minutes for Working Group Session on Interruptible Load Remedial Action Scheme (ILRAS), April 17, The AESO ILRAS Working Group Presentation, December 6, AESO Responses to Information Requests, July 13, The AESO, Under-frequency Mitigation Services Procurement Plan, August 11, 2005, P1. 8 Request for Expressions of Interest ( EOI ) 485 MW of Load Shedding Requirements Service and 150 MW of Fast Ramp Service, June 4, Page 3

6 Working Group (DRWG) identified a revised form of LSS, referred to LSSi, to be a potential product for intertie restoration and greater participation by loads. 9 In March 2010, the AESO published its Alberta Intertie Restoration Initiative Discussion Paper (the Discussion Paper). In the Discussion Paper, the AESO examined the legislation and policy background and outlined preliminary options for import and export restoration. Although ILRAS, LSR and FRS could all technically provide intertie restoration service, the unsuccessful EOI of these products suggested that they were not viable competitive options. In addition, due to an expected lengthy development and implementation period, infrastructure solutions for intertie restoration were not deemed to be viable options in the short or medium term. Hence, the AESO recommended the LSSi product as a tool to manage frequency risk when increasing intertie import capability. Subsequent stakeholder comments on the Discussion Paper assisted the AESO in formulating recommendations on intertie restoration. In October 2010, the AESO published the Intertie Restoration Recommendation Paper (the Recommendation Paper), in which the AESO recommended proceeding with the LSSi product as a priority. 10 In the Recommendation Paper, the AESO recommended that LSSi be made available to increase import ATC in order to facilitate in market imports. 11 In November 2010, the AESO released a request for an EOI to provide up to 485 MW of LSSi. Multiple industrial and commercial sectors, as well as several demand response aggregators responded to the EOI. The respondents indicated an aggregate capability to supply between 700 MW and 800 MW of LSSi capacities. Based on the successful response to the EOI, the AESO started an LSSi procurement process in March 2011 by issuing the Request for Proposals for Load Shed Services for Imports (the RFP). As the result of the RFP, at the end of 2011, a total of 432 MW of LSSi from six load participants, including a load aggregator, was contracted with the AESO. As of January 31, 2014, the total contracted LSSi was 479 MW Assessment of LSSi Product Design Features LSSi has a number of design features that were established by the contract structure set out by the AESO s Load Shed Service for Import (LSSi) Requirements (LSSi Requirements), the RFP and LSSi Agreements signed between the providers and the AESO. Collectively, these documents assign rights and obligations to the contracting parties, establish the payment structure, and specify the measurement of actual volume of LSSi. Assignment of Rights and Obligations The LSSi contract gives the LSSi providers the right to determine whether to make LSSi available in a given hour. Furthermore, the current LSSi contract allows the providers to adjust available volumes until they are armed for a particular delivery period by the AESO. The LSSi contract assigns to the AESO the right to determine whether to use the product. LSSi is armed by the System Controller as required, based on scheduled flows and Alberta Internal Load (AIL). To maintain compliance with LSSi Requirements, LSSi providers are obligated to follow an arming dispatch from the System Controller. In addition, the LSSi Requirements also require that the committed amount of load be disconnected from the AIES within 0.2 seconds (12 cycles) of the frequency reaching Hz (+/ Hz) and that once the LSSi scheme is armed, the actual volume that will be tripped by 9 Alberta Demand Response Initiative Discussion Paper, October, 22, 2009, P The AESO, Intertie Restoration, October 7, 2010, P9. 11 The AESO, Intertie Restoration, October 7, 2010, P9. 12 With LSSi contracts in place, the LSS program was discontinued. Page 4

7 the LSSi scheme remains within 95 per cent to 120 per cent of the dispatched volume. 13 These requirements impose the obligations on loads armed for LSSi to be in the position of providing the service and ready to be tripped in the event an intertie contingency causes a significant frequency drop. LSSi Payment Structure The LSSi payment structure consists of a three-part payment scheme, which includes an availability payment, an arming payment and a tripping payment. The availability payment is paid to LSSi providers in the hours when they choose to offer LSSi. The availability payment is paid based on the lowest availability volume within the hour and availability price. In the current LSSi contract, the availability price is set at $5/MW. The arming payment is paid to LSSi providers in the hours when their LSSi facilities are armed. Arming payment is based on a fixed price agreed to between the AESO and each individual LSSi provider. In addition, there is a minimum arming guarantee payment, should actual armed volumes fall below a minimum threshold. The tripping payment is paid to LSSi providers in the event that their armed load is tripped off when the AB B.C. intertie trip causes the frequency to drop. In the current LSSi contract, the tripping price is set at $1000/MW. Measurement of LSSi Volume Technically, loads that provide LSSi have to consume electricity in order to be in a position that enables them to mitigate frequency risk and hence provide intertie restoration service through load shed. The availability volume, armed volume and trip volume used to calculate LSSi payments are all measured based on the real power consumption of LSSi providers. Therefore, electricity consumption is a necessary condition for loads to provide LSSi and receive payments. The design features of LSSi make it different from other under-frequency service products used or designed by the AESO in the past. Table 1 compares LSSi to the other under-frequency products described above. 13 The AESO, Load Shed Service for Import (LSSi) Requirements, P4. Page 5

8 Table 1: Summary Table of Under-Frequency Mitigation Services the AESO has Designed LSSi ILRAS BFR LSS LSR FRS Used when frequency drops following intertie trip Used following intertie trip Used when frequency is at 59.5 Hz for 1.5 seconds Used when frequency drops following intertie trip Used when frequency drops following intertie trip Used when frequency drops following intertie trip Voluntary product: The service is available only if providers declare availability to System Controllers, but providers do not have to declare availability The service was available when loads were consuming, no need to declare availability to System Controller No need to declare availability The service was available when loads were consuming, no need to declare availability to System Controller The service was available when loads were consuming, no need to declare availability to System Controller No need to declare availability Armable by System Controller Armable by System Controller Always armed Always armed Armable by System Controller Armable by System Controller Load trip triggered automatically when frequency drops to 59.5 Hz or by directive from the System Controller following an intertie contingency Load trip triggered automatically by AB B.C. intertie trip Generation ramp triggered by frequency at 59.5 Hz for 1.5 seconds Load trip triggered automatically when frequency drops to 59.5 Hz or by the directive from the System Controller Load trip triggered automatically when frequency drops to 59.5 Hz Generation ramp triggered automatically by frequency drop to 59.5 Hz Competitively procured Not competitively procured Not competitively procured Competitively procured EOI not contestable EOI not contestable In Service Expired Expired Replaced by LSSi Not Procured Not Procured Unlike the other under-frequency services, LSSi contracts allow providers to decide whether to make the service available in real time, and use of the availability payment incents providers to make the service available. This design feature encouraged participation in the EOI and RFP and made it possible for the AESO to competitively procure the service with sufficient volume for intertie restoration. LSSi contracts also allow the AESO to dispatch the offered LSSi based on the need to reliably manage the grid in real time. It gives the AESO the right to not use the service when it is not needed. This feature provides operational flexibility in import ATC restoration. In addition, the current LSSi contracts associate a portion of the total payments, i.e. arming payment, with the usage of the service. This limits Page 6

9 unnecessary payments when the service is not used. This feature did not exist with the LSS or BFR used in the past, as these services were always armed. 4 Operational Assessment of LSSi In 2013, the AESO conducted an operational impact assessment of LSSi for the period of April 1, 2012 to March 31, The AESO estimated metrics based on LSSi availability, arming volumes, the pool price, ATC and import schedules. The analysis was intended to examine the effectiveness of the product and identify possible areas of improvement for the LSSi contracts. As LSSi is an ancillary service intended to enable increased import scheduling capability, the AESO s analysis does not include a cost-benefit analysis of the use of LSSi. 4.1 Increase in Intertie Capability The AESO started to arm LSSi as a tool to increase import capability in Q In 2012, the import ATC of the AB B.C. intertie reached 700 MW, higher than the maximum import ATC posted in each of the 5 years prior to the implementation of LSSi. The AESO conducted an operational impact assessment of LSSi for the period from April 1, 2012 to March 31, Out of the 8,760 hours in the period, at least 100 MW of LSSi was offered and available to be armed for 85 per cent of the hours. (see Figure 1). Figure 1: LSSi Availability Duration Curve in All Hours April 1, 2012 to March 31, 2013 Using Table 10 of Information Document Available Transfer Capability and Transfer Path Management ID # R, the AESO created an estimate of the amount of additional import capability that could have been enabled through LSSi on the AB B.C. intertie. This was done by calculating the import capability for a given hour based on the load level in that hour, assuming that all available LSSi for that hour was armed, and the ability of achieving higher import ATC by arming LSSi was not limited by other constraints in the transmission system. This was then compared to the calculated import capability, assuming no LSSi was available. Based on this analysis, the available LSSi during the assessment period had the potential to increase import capability by an average of nearly 80 MW (see Figure 2). Page 7

10 Figure 2: Increased Potential Import Capability Due to Availability of LSSi Assuming No Other Transmission Constraints It is possible that other factors in the transmission system may prevent the available LSSi from reaching its full potential in increasing import capability. For example, if the Langdon Static Var Compensator (SVC) is out of service, arming LSSi may not be able to facilitate a higher import schedule. In a situation like this, the full potential of available LSSi in increasing import ATC would be limited by other constraints in the transmission system. However, even with other transmission constraints during the study period taken into account, the available LSSi between April 1, 2012 and March 31, 2013 had the potential to increase import capability by an average of over 60 MW (see Figure 3). Page 8

11 Figure 3: Increased Potential Import Capability Due to Availability of LSSi With Other Transmission Constraints Taken into Account Between April 1, 2012, and March 31, 2013, LSSi was armed to manage frequency risk and therefore enable increased intertie schedules in 2,059 hours, 24 per cent of the total hours in the period. Arming of LSSi over this period enabled over 103,000 MWh of additional imports to gain access to the Alberta market. This means that in every hour when LSSi was armed, an average of 50 MW of additional scheduled imports were enabled. Table 2 is a summary of intertie restoration facilitated by LSSi from April 1, 2012 to March 31, Page 9

12 Availability/Capacity Arming/Energy Table 2: Summary Data of Intertie Restoration Facilitated by LSSi April 1, 2012 to March 31, 2013 Number of Hours When LSSi was Armed 2,059 Average Volume Armed (MW) 137 Average Additional Import Schedule Achieved in Each Hour When LSSi was Armed (MW) 50 Total Additional Import Schedule Achieved (MWh) 103,077 Number of Hours When LSSi was Available* 8,551 Average Available LSSi Volume in Each Hour When LSSi was Available (MW) 192 Average Increase in Import Capability Achieved by LSSi (MW)** 60 Total Additional Import Schedule that could have been Achieved (MWh)** 527,691 Average Increase in Import Capability that could have been Achieved by LSSi (MW)*** 79 Total Additional Import Schedule that could have been Achieved (MWh)*** 687,950 *Only considers the hours when enough LSSi was available to increase the allowable schedule level for a given load level. **Taking into account of the transmission constraints that could have limited the use of LSSi during the period. ***Assuming there were no other transmission constraints that could have limited the use of LSSi during the period. 4.2 Learning Obtained Through Using LSSi and Potential Modifications to LSSi Contract With increased experience in using LSSi to increase intertie import capability, the AESO gained more insight into a number of aspects of the product. As described below, the AESO has examined these issues in more detail and identified the following potential modifications to the LSSi contracts, which may be included in the next round of contracting taking place in Before finalizing these changes, the AESO intends to solicit and review stakeholder feedback. Overall, as physical infrastructure solutions to address the issue are still deemed to be impractical to implement in the short to medium term, the AESO intends to continue the use of LSSi as a tool to mitigate frequency risk resulting from higher levels of import flows and hence advance the goals of the intertie restoration program. Decreased available volume of LSSi at higher price levels Since LSSi providers have the right to determine whether to make LSSi available in real time, the amount of increased import potential created through the LSSi product for a particular hour cannot be known ahead of time. This is because loads are required to consume electricity in order to be in a position to provide LSSi and the consumption of price-responsive loads who may also be LSSi providers may be impacted by the pool price. For a given hour, if the anticipated pool price exceeds the value of electricity to a particular load, the load may decide to reduce consumption and hence be unavailable to offer LSSi in that hour. Therefore, the total available LSSi volume may decrease as the anticipated pool price increases. Page 10

13 While LSSi was offered and available to increase import ATC for the majority of the hours when needed, LSSi availability data show that the total available volume varied at different price levels. However, a portion of LSSi volume was not sensitive to pool price levels. For example, Figure 4 shows that at pool prices above $300/MWh (approximately five per cent of all hours), on average 50 MW of LSSi was available. Figure 4: LSSi Availability (Average MW) and Proportion of Hours with LSSi Armed at Different Price Levels While it may be desirable to have more LSSi available during high-price hours so that intertie capability can potentially be further increased in these hours, the arming of LSSi (associated with import offers) does not necessarily coincide with high-price hours, as LSSi was also armed to increase import ATC during low-price hours. The green bars in Figure 4 depict the percentage of the hours when LSSi was armed out of the total number of hours when the pool price fell into the price ranges indicated by the horizontal axis. It can be seen that between April 1, 2012 and March 31, 2013, out of all the hours when the pool price was between $0 and $50, LSSi was armed 24 per cent of the time; whereas out of all the hours when the pool price was between $950 and $1000, LSSi was armed 18 per cent of the time. By design, LSSi is a voluntary product and providers have no obligation to make volumes available in any particular hour. The fact that the providers include both price-responsive loads and non-price-responsive loads suggests with reasonable certainty that volume will be available without requiring loads that would otherwise curtail to remain in the market. Since the LSSi contract gives providers the right to make LSSi offer decisions in real time and the availability is paid with an availability payment, compared with other under-frequency services used or designed by the AESO prior to LSSi, providers are incented to make the service available because of the availability payment. As there is a relatively limited amount of load with the economic desire, flexibility and technical ability to curtail as per the required specifications, the design features of LSSi appear to have had the benefit of incenting loads to bring enough volume to the RFP process to enable competitive procurement of the service. The successful procurement of LSSi in 2011 was a step forward in the AESO s intertie restoration efforts after continued procurement of previously utilized under-frequency Page 11

14 related products had proven untenable. In addition, as this is a new product, it is expected that more loads will consider this program in due course. Given the availability and arming patterns observed to date as well as the contracting considerations described above, the AESO does not recommend any changes in the requirements or the three-part payment structure of LSSi to address the issue of price-responsive load curtailment. Stability of available LSSi volumes between T-85 and T-20 Since LSSi providers do not have to lock down their offered volumes, the available LSSi volume at the time when it is required to be armed may not be consistent with the volume offered at an earlier point in time. This may be a concern because the AESO s ATC allocation rule involves the allocation of ATC at 85 minutes before the delivery hour (T-85) when maximum potential available system import capability is calculated based on available LSSi at that time; whereas the arming of LSSi occurs around 20 minutes before the delivery hour (T-20). Should the LSSi volume available for arming subsequently decrease between T-85 and T-20, import limits may decrease, thus invalidating the T-85 ATC allocation and requiring curtailments of e-tags when finalizing the delivery hour schedule. In order to better understand the issue, the AESO examined the potential impact of LSSi availability changes between T-85 and T-20 on import capability. If there are frequent occurrences where the change in LSSi availability volume between T-85 and T-20 affects maximum potential import capability, this may suggest a need to increase the firmness of LSSi availability between T-85 and T-20 so that the import ATC allocation can reasonably represent the actual import ATC. Figure 5: Distribution of Potential Decrease to Import ATC due to Change in LSSi Availability between T-85 and T-20 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% MW Figure 5 plots the distribution of the potential decrease to import ATC due to decreases in LSSi availability between T-85 and T-20 during the period April 1, 2012 to March 31, The potential impact on the import ATC is calculated by taking the difference between the maximum import ATC that could have been achieved at the actual load level in each hour assuming all available LSSi at T-85 were armed, and the maximum import ATC that could have been achieved in the same hour assuming all Page 12

15 available LSSi at T-20 were armed. 14 Figure 5 indicates that in those cases where LSSi availability stayed the same or decreased from T-85 to T-20, the change in LSSi availability would have potentially decreased the ATC by at least 25 MW approximately15 per cent of the time. Modification Considered: The AESO is considering changing the LSSi contract terms to require lockdown of availability volume at T-85. While locking down of availability to some degree reduces the flexibility that the providers currently have, it is expected to also remove the chances of the ATC allocation at T-85 being invalidated due to a change in LSSi availability. The objective of this modification would be to reduce curtailments of e-tags when finalizing the delivery hour schedule and better facilitate import transactions by improving certainty around the ATC posted at T-85. Manual Tripping of LSSi load through System Controller s directive As per ISO OPP 402 Supplemental and Spinning Reserve Services, Alberta contingency reserve requirements for trips of the interties are reduced by armed LSSi volumes. In those circumstances where an intertie or combination of interties is the single largest contingency, the ability to manually trip armed LSSi loads in the event of a contingency ensures that LSSi can be used to offset reserve requirements as per OPP 402. The initial LSSi Agreements defined Trip as the disconnection of the Contracted Load from the System within 0.2 seconds (twelve (12) cycles) of the frequency reaching Hz (+/-0.02 Hz). 15 As a result, Trip did not specifically include directives from the System Controller (i.e. ability to manually trip upon an intertie contingency, even at frequencies above Hz) as a way of tripping load as per OPP 402. In 2013, most LSSi Agreements were renegotiated to add manual trip as a way of tripping load when the agreements were renewed. With the revision, Trip also includes the disconnection of LSSi loads within 10 minutes of receiving a directive from the System Controller. Modification Considered: The AESO proposes to revise LSSi contract requirements to include a requirement that loads be able to be manually tripped by the System Controller in the event of an AB B.C. intertie contingency. Payments for LSSi availability when AB B.C. intertie is on outage or LSSi cannot increase import capability The AESO observed that LSSi was offered and the availability payment was made to the providers when the AB B.C. intertie was on scheduled outage, despite the fact that LSSi could not have been used in this situation to increase import capability. In addition, there were other circumstances in which import capability was limited to a level where LSSi could not have been employed to increase import capability due to other conditions on the transmission grid. The current LSSi Agreements do not preclude payments made to LSSi providers when LSSi is unable to be used to increase intertie capability. In these situations, availability payments to the providers are essentially payments for a service that cannot be employed by the AESO to increase import capability. Modification Considered: The AESO proposes to revise the LSSi Agreement so that availability payments are not made during periods when maximum import capability is below the threshold at which LSSi would be armed to enable increased import capability. The objective of this potential revision is to avoid availability payments for LSSi service that cannot be used to increase import capability. Clarity in Compliance 14 This is a hypothetical case that assumes no other transmission constraints would limit the intertie restoration potential of the available LSSi. 15 LSSi Agreement Page 13

16 The LSSi Agreement could be enhanced by distinguishing non-compliance based on providers compliance efforts and the impact of the non-compliance on the system, as opposed to treating all noncompliance events equally and allowing them to carry equal weight in contributing to the termination of a provider s LSSi Agreement. Based on service provider input, the AESO agrees that, as a general principle, greater clarity regarding the relationship between non-compliance violations and LSSi Agreement terminations would help providers better understand the AESO s expectations of compliance practices. This would reduce unnecessary risks to LSSi Agreements. Modification Considered: The AESO proposes to establish guidelines that specify the AESO s expectations and criteria. For example, if LSSi providers can demonstrate they have made best efforts in compliance and have taken all necessary actions to minimize the impact of issues (i.e. removing themselves from the LSSi market by offering their availability at zero until the issue is resolved; addressing mitigating measures in a timely fashion) and if the non-compliance event does not pose a reliability risk, the non-compliance event may not count as a violation that contributes to a potential termination of the LSSi Agreements. The objective of providing greater clarity is to encourage LSSi providers to make best efforts in compliance and reduce unnecessary risks to the Agreement. 5 Next Steps As part of the broader intertie restoration program, the AESO is conducting a joint intertie system operating limit (SOL) study with BC Hydro. The study will examine various alternatives for increasing import and export capacity. 16 The study is designed to examine different SOL violation mitigation strategies. These strategies include ancillary services solutions, such as LSSi, and wires solutions such as HVDC converters on interties. The study is expected to help identify different alternatives to restore interties and include them in the intertie restoration tool kits. The AESO is also reviewing and updating the operating horizon intertie limit studies. Included in this work is a comprehensive review of required LSSi arming volumes at various load levels and scheduled import volumes. Based on of the results of this study, Table 10 of Information Document ID# R will be reviewed and updated. An initial update of this Information Document, including Table 10, was posted on January 30, 2014 and further study work is ongoing. Once the review and update are complete, the AESO is expected to be in a better position to assess the amount LSSi that needs to be contracted in conjunction with other intertie restoration alternatives. The update of Table 10 is expected to be completed in Q The current LSSi Agreements expire at the end of As the AESO intends to continue to procure LSSi, stakeholder feedback is requested on the suggested contract modifications contained in this review. Taking this feedback into consideration, the AESO will propose and then finalize a revised LSSi contract. Following this, procurement of LSSi via an RFP process, likely for the period, is expected to occur in Q Next steps in the LSSi procurement process are expected to proceed as follows: Q2 2014: Information session and stakeholder comments on LSSi review and suggested contract changes. Revised contract language proposed and finalized. Determination of desired contracting volumes made based on updated LSSi studies. Q3 Q4 2014: RFP process held and contracts finalized for a January 2015 start. 16 The AESO, Intertie Restoration: Response to Recommendation Paper Stakeholder Comments and Next Steps, July 10, 2012, P7. Page 14

17 Stakeholder comments on the suggested contract modifications are requested by April 17, Comments received will be considered in the contract development process prior to the RFP. The AESO requests that comments be ed to Should you have any questions, please contact Ruppa by or by phone at Page 15

AESO Practices for System Access Service. May 31, 2013

AESO Practices for System Access Service. May 31, 2013 AESO Practices for System Access Service May 31, 2013 Table of Contents 1 Purpose... 3 2 Introduction... 3 3 Practices for System Access Service... 4 3.1 Conditions for System Access Service... 4 3.2 Rationale

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Requirements for the Provision of Load Shedding Service for Import Version 4.0

Requirements for the Provision of Load Shedding Service for Import Version 4.0 LOAD SHED SERVICE for IMPORT (LSSi) Requirements Requirements for the Provision of Load Shedding Service for Import Version 4.0 This document outlines the eligibility criteria and requirements that an

More information

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017 Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix N... 2 Pseudo-Tie Protocol... 2 1. Pseudo-Ties of Generating Units to the CAISO Balancing Authority Area... 2 1.1 Consistency with NERC/WECC Requirements... 2 1.2 CAISO Operating,

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

Non-BM Balancing Services Volumes and Expenditure

Non-BM Balancing Services Volumes and Expenditure Non-BM Balancing Services Volumes and Expenditure Table of Contents Background... 1 Summary of Total Non-BM Service Provision... 2 Total Ancillary Services Expenditure... 2 Frequency Response... 3 Dynamic

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 3 3.1. Order of Steps... 3 3.2. Restricted

More information

Non-BM Balancing Services Volumes and Expenditure

Non-BM Balancing Services Volumes and Expenditure Non-BM Balancing Services Volumes and Expenditure Table of Contents Background... 1 Summary of Total Non-BM Service Provision... 2 Total Ancillary Services Expenditure... 2 Frequency Response... 3 Dynamic

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal

Energy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3

More information

Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8

Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8 Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8 Impact of Net Demand Variability Reference Case and High Cogen scenario Background Dispatching to

More information

AESO Stakeholder Update on Mothball Outages. July 25, 2016

AESO Stakeholder Update on Mothball Outages. July 25, 2016 AESO Stakeholder Update on Mothball Outages July 25, 2016 Agenda 1. Background Issues Rationale 2. Mothball Rule Definition of Mothball Outage Overview of Section 306.7 3. Mothball Outages in the Market

More information

Policy Direction for Alberta s Capacity Market Framework

Policy Direction for Alberta s Capacity Market Framework Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity

More information

2. Market Operations Overview

2. Market Operations Overview 2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static

More information

6.1.9 IFM Initial Conditions

6.1.9 IFM Initial Conditions 6.1.9 IFM Initial Conditions A Generating Unit that was committed in the previous day s Day-Ahead Market (IFM or RUC) run (TD-2 for TD-1) but was de-committed before HE24 would normally be considered initially

More information

California Grid Operations: Current Conditions and Future Needs

California Grid Operations: Current Conditions and Future Needs California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify

More information

Exploring the Impacts of California s Renewable Portfolio Standard

Exploring the Impacts of California s Renewable Portfolio Standard Exploring the Impacts of California s Renewable Portfolio Standard System Planning Committee April 2010 Table of Contents Purpose... 1 Vocabulary... 1 System Planning Committee s Initial Assessment...

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Comparison between sequential selection and co-optimization between energy and ancillary service markets

Comparison between sequential selection and co-optimization between energy and ancillary service markets Comparison between sequential selection and co-optimization between energy and ancillary service markets Date: Tuesday, November 7, 2017 Draft for discussion Click here to enter names of people copied

More information

Net Demand Variability (NDV) Summary

Net Demand Variability (NDV) Summary Net Demand Variability (NDV) Summary Executive Summary: This document provides a summary of the Net Demand Variability (NDV) work presented to the Energy and Ancillary Service (EAS) workgroup in WG meetings

More information

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION Published: AUGUST 2016 DRAFT REPORT CONSULTATION ON AMENDMENTS TO THE WIND ENERGY CONVERSION MODEL (ECM) GUIDELINES

More information

Contingency Modeling Enhancements Issue Paper

Contingency Modeling Enhancements Issue Paper Contingency Modeling Enhancements Issue Paper March 11, 2013 California ISO Contingency Modeling Enhancements Issue Paper Table of Contents I. Executive Summary... 3 II. Plan for Stakeholder Engagement...

More information

ISO REVISED STAGING PLAN NO. 7

ISO REVISED STAGING PLAN NO. 7 ID Work Item Description 2 COMPLETE HIM Server An archival database is to be created for permanent historical storage of bidding, price and schedule data. HIM is defined in section 3.2.5 of the SI DSOW:

More information

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the FERC ELECTRIC TARIFF First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 3.1 Nature of Relationship. Each Participating

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

Northwest Power and Conservation Council NW Power Markets Symposium Products & Transactions

Northwest Power and Conservation Council NW Power Markets Symposium Products & Transactions Northwest Power and Conservation Council NW Power Markets Symposium Products & Transactions Presented by: John Wilkinson John.Wilkinson@MorganStanley.com 604-658-8132 July 2013 Disclaimer: The information

More information

Incremental Black Start RFP Response Template & General Information

Incremental Black Start RFP Response Template & General Information Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section

More information

Frequency Response. Straw Proposal

Frequency Response. Straw Proposal Frequency Response Straw Proposal October 12, 2015 Table of Contents 1. Executive Summary... 3 2. Stakeholder Process and Timetable... 4 3. The New Frequency Response Obligation... 4 3.1. Frequency Response

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date:

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date: A. Introduction 1. Title: Emergency Operations 2. Number: EOP-011-1 3. Purpose: To address the effects of operating Emergencies by ensuring each Transmission Operator and Balancing Authority has developed

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement September 8, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-126: Needs Identification Document

More information

155 FERC 61,111 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

155 FERC 61,111 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 155 FERC 61,111 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Puget Sound Energy,

More information

3. Overview of Market Instruments

3. Overview of Market Instruments 3. Overview of Market Instruments 3.2 Ancillary Services Bids Four types of Ancillary Services are used by CAISO in its markets Regulation Up, Regulation Down, Spinning Reserve, and Non-Spinning Reserve.

More information

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day. Proposed Tariff Revisions Attachment K-Appendix and Schedule 1 of the Operating Agreement Generator Offer Flexibility Senior Task Force Revisions Related To Make-Whole and Lost Opportunity Cost Payments

More information

REVENUE SUFFICIENCY GUARANTEES AND COST ALLOCATION William W. Hogan i May 25, 2006

REVENUE SUFFICIENCY GUARANTEES AND COST ALLOCATION William W. Hogan i May 25, 2006 REVENUE SUFFICIENCY GUARANTEES AND COST ALLOCATION William W. Hogan i May 25, 2006 Introduction These comments address the Revenue Sufficiency Guarantee (RSG) and associated cost allocation issues discussed

More information

Board Staff Discussion Paper

Board Staff Discussion Paper Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction

More information

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design To enhance competition in wholesale electric markets and broaden the benefits

More information

Functional Entity Roles and Responsibilities

Functional Entity Roles and Responsibilities Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 4: Forward Capacity Auction Prepared by: Alberta Electric System Operator Date: January 26, 2018 Table of Contents

More information

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation MRTU Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation CRR Educational Class #2 CAISO Market Operations Why are LMPs important to the CRR Allocation & Settlement Process The CRR revenue

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Dynamic Transfers Revised Draft Final Proposal

Dynamic Transfers Revised Draft Final Proposal Dynamic Transfers Revised Draft Final Proposal Provided in Support of 2009-2011 Stakeholder Process to Consider Expansion of Dynamic Transfer Services in ISO Tariff Revised February 18, 2011 CAISO/M&ID/Dynamic

More information

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE Department of Market Monitoring ACKNOWLEDGEMENT The following members of the Department of Market Monitoring contributed to this report Eric Hildebrandt Keith

More information

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents

More information

SETTLEMENTS & BILLING BUSINESS PRACTICE

SETTLEMENTS & BILLING BUSINESS PRACTICE SETTLEMENTS & BILLING BUSINESS PRACTICE In this Section: Overview Daily Settlement Reports Monthly Invoice and Payment Terms Resale of Transmission Rights Transfer of Transmission Rights Redirect of Transmission

More information

SAM 2.0 Stakeholder Comment Matrix

SAM 2.0 Stakeholder Comment Matrix SAM 2.0 Stakeholder Comment Matrix The AESO welcomes stakeholder input on the working group conclusions and discussion context contained in Section 5 of SAM 2.0. Please review the following instructions

More information

Demand Response and Scarcity Pricing

Demand Response and Scarcity Pricing Item #/ Check When Complete Demand and Scarcity Pricing Begin End Category Sub-Category Order 719 Summary Draft Status SPP Notes References Assignment 41 47 63 Demand Allow DR to provide ancillary services

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 5310 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 1 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 2 3.1. Reporting Requirements/...

More information

Draft Whitepaper to Platte River Board of Directors

Draft Whitepaper to Platte River Board of Directors Draft Whitepaper to Platte River Board of Directors Report on Organized Power Markets RTOs and ISOs Presented for the October 2016 Board Meeting Overview This report on the potential formation of a regional

More information

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007

ISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007 ISO-NE FCM Capacity Market Design Scott M. Harvey October 9, 2007 Summary The ISO-NE FCM capacity market design embodies many improvements over the prior ISO-NE capacity market. Five of these improvements

More information

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Docket No. RM16-5-000 Regional Transmission Organizations ) and Independent System Operators

More information

Issues in the Determination of Tariffs for Ancillary Services

Issues in the Determination of Tariffs for Ancillary Services Issues in the Determination of Tariffs for Ancillary Services Abstract: This paper will begin with a description of ancillary services and then go on to describe the types of ancillary services that are

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

144 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON REHEARING AND COMPLIANCE. (Issued July 18, 2013)

144 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON REHEARING AND COMPLIANCE. (Issued July 18, 2013) 144 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony Clark. PJM

More information

Introduction to RRG Drafting Team Proposal

Introduction to RRG Drafting Team Proposal November 17, 2003 Introduction to RRG Drafting Team Proposal SUMMARY This introduction will review the overall task the RRG drafting team took on, set out the overall guiding principles it used, and describe

More information

Introduction to the Energy Imbalance Market (EIM Module 1)

Introduction to the Energy Imbalance Market (EIM Module 1) Introduction to the Energy Imbalance Market (EIM Module 1) Cynthia Hinman Lead Client Trainer Webinar July 25, 2013 The information contained in these materials is provided for general information only

More information

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF

Southern California Edison Company SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF SOUTHERN CALIFORNIA EDISON COMPANY WHOLESALE DISTRIBUTION ACCESS TARIFF Original Sheet No. TABLE OF CONTENTS. Applicability.... Definitions.... Nature of Distribution Service.... Term.... Distribution

More information

Powerex Comments on CAISO October 31, 2013 Revised Draft Order No. 764 Tariff Changes. Submitted By Company Date Submitted Gifford Jung

Powerex Comments on CAISO October 31, 2013 Revised Draft Order No. 764 Tariff Changes. Submitted By Company Date Submitted Gifford Jung Powerex Comments on CAISO October 31, 2013 Revised Draft Order No. 764 Tariff Changes Submitted By Company Date Submitted Gifford Jung 604-891-6040 Powerex Corp. November 12, 2013 I. INTRODUCTION Powerex

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

Business Practice Manual for Market Operations

Business Practice Manual for Market Operations Business Practice Manual for Market Operations Version 5354 Revised: July 13October 30, 2017 Page 1 of 345 Approval History Approval Date: March 23, 2009 Effective Date: March 31, 2009 BPM Owner: David

More information

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh. 1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh. There is no target for MW of renewable capacity (except in

More information

GC022 - Frequency Response

GC022 - Frequency Response Stage 01: Grid Code GC022 - Frequency Response What stage is this document at? 01 02 03 Workgroup Report Industry Consultation Report to the Authority This Workgroup investigated the technical requirements

More information

System Management Standard. System Restart Services. (System Restart Standard)

System Management Standard. System Restart Services. (System Restart Standard) System Management System Management Standard System Restart Services (System Restart Standard) This Standard is a guide to the acquisition of System Restart Services. 1 October 2014 Table of contents 1.

More information

Update on FERC, NERC, DOE & Congress John P. Hughes President & CEO Electricity Consumers Resource Council Washington DC

Update on FERC, NERC, DOE & Congress John P. Hughes President & CEO Electricity Consumers Resource Council Washington DC Council of Industrial Boiler Owners Technical Focus Group, Energy & Environmental Committee Meetings September 12-13, 2017 Arlington, Virginia Update on FERC, NERC, DOE & Congress John P. Hughes President

More information

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for a common set of requirements, in accordance with Article

More information

Day-ahead ahead Scheduling Reserve (DASR) Market

Day-ahead ahead Scheduling Reserve (DASR) Market Day-ahead ahead Scheduling Reserve (DASR) Market Agenda Implementation Overview of the DASR Market Market Clearing Process Market Clearing Example Performance Compliance Market Settlements Appendix: emkt

More information

Presentation on Draft SCED RFP

Presentation on Draft SCED RFP Presentation on Draft SCED RFP Pre-RFP Release Conference October 9, 2014 Presenters: Eric Espenhorst, Seattle City Light Erin Apperson, Puget Sound Energy Robb Davis, BPA Roger Bentz, BPA Kevin Holland,

More information

Consultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project

Consultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project Consultation on DS3 System Services Market Ruleset DS3 System Services Implementation Project 15 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO

More information

Flexible Ramping Product Cost Allocation Straw Proposal

Flexible Ramping Product Cost Allocation Straw Proposal Flexible Ramping Product Cost Allocation Straw Proposal March 15, 2012 Flexible Ramping Product Cost Allocation Straw Proposal Table of Contents 1 Introduction... 3 2 Prior discussion on Flexible Ramping

More information

Impact of EIM Imports on Carbon and REC accounting. Clare Breidenich Western Power Trading Forum Regional Issues Forum September 7, 2017

Impact of EIM Imports on Carbon and REC accounting. Clare Breidenich Western Power Trading Forum Regional Issues Forum September 7, 2017 Impact of EIM Imports on Carbon and REC accounting Clare Breidenich Western Power Trading Forum Regional Issues Forum September 7, 2017 Treatment of Electricity Imports under California Cap and Trade Program

More information

Request for Proposal: Controlled System Separation Feasibility Study

Request for Proposal: Controlled System Separation Feasibility Study Request for Proposal: Controlled System Separation Feasibility Study I. INTRODUCTION A. Overview The New York Independent System Operator ( NYISO ) is requesting proposals for professional services from

More information

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016) (Modifications Issued on August 11, 2016) 1 List of Contents Introduction Purpose of Document Overview of Transmission Services in New England Definitions Applicable Schedules Services Applicable to these

More information

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009 Effective Date: 26 August 2011 Expiry Year: 2015 Original signed by: APPROVED

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Policy Initiatives Catalog

Policy Initiatives Catalog Prepared by Market and Infrastructure Policy November 8, 2017 CAISO/M&ID/MIP Table of Contents 1 Introduction... 4 2 Initiative Categorization... 5 3 Stakeholder Submissions... 6 3.1 Submissions Incorporated...

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

DESIGNING A COMPETITIVE BIDDING PROCESS, AND ENSURING

DESIGNING A COMPETITIVE BIDDING PROCESS, AND ENSURING CAPACITY MECHANISMS WORKING GROUP 14 APRIL 2015 DESIGNING A COMPETITIVE BIDDING PROCESS, AND ENSURING COMPETITION BETWEEN NEW AND EXISTING CAPACITY This paper compiles the requirements in the Guidelines

More information

Revision to ISO Transmission Planning Standards

Revision to ISO Transmission Planning Standards Revision to ISO Transmission Planning Standards Market and Infrastructure Policy Straw Proposal REVISED DRAFT May 28, 2014 Revision to ISO Transmission Planning Standards May 28, 2014 Straw Proposal Table

More information

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144 Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of

More information

Renewable Integration at ERCOT

Renewable Integration at ERCOT Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external

More information

Dumfries and Galloway Developer Forum. Welcome and Introduction. Pearse Murray

Dumfries and Galloway Developer Forum. Welcome and Introduction. Pearse Murray 8 TH June 2017 Dumfries and Galloway Developer Forum Welcome and Introduction Pearse Murray Agenda Introduction Pearse Murray NGET Update Julian Leslie KTR Project Update Colin Brown Q&A www.spenergynetworks.co.uk

More information

Electricity Authority Work Programme. 1 July June June 2017

Electricity Authority Work Programme. 1 July June June 2017 Work Programme 1 July 2017 30 June 2018 30 June 2017 Contents Executive summary... 3 Introduction and purpose... 4 Programme A: Evolving technologies and business models... 7 Programme B: Consumer choice

More information

X Accept as requested X Change to Existing Practice Accept as modified below Decline

X Accept as requested X Change to Existing Practice Accept as modified below Decline 1. RECOMMENDED ACTION: EFFECT OF EC VOTE TO ACCEPT RECOMMENDED ACTION: X Accept as requested X Change to Existing Practice Accept as modified below Status Quo Decline 2. TYPE OF DEVELOPMENT/MAINTENANCE

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long Term Procurement Plans Rulemaking 13 12 010

More information

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Matteo Leonardi 22 May 2013 Liberalized markets versus monopolies Production Transmission distribution

More information

Stakeholder Process: Commitment Cost Bidding Improvements. Summary of Submitted Comments

Stakeholder Process: Commitment Cost Bidding Improvements. Summary of Submitted Comments Stakeholder Process: Commitment Cost Bidding Improvements Attachment A Summary of Submitted Comments Two stakeholder initiatives are consolidated into one memo as both propose market improvements to ISO

More information

Solutions for Power Generation

Solutions for Power Generation EM SG SOLutions Solutions for Power Generation Energy Management Smart Grid Solutions Solutions for Power Generation Overview Power Applications Generation Planning and Trading Summary Page 2 Solutions

More information

Regional Flexibility Markets

Regional Flexibility Markets CAISO Contingency Modeling Alternative: Regional Flexibility Markets March 2014 Southern California Edison Outline Concerns with the CAISO s N-1-1 proposal Alternative approach: Regional Flexibility Markets

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information