1 Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed by the electric systems of the NWPP Agreement Signatories. This area includes the states of Washington, Oregon, Idaho, Montana, Utah, and Wyoming; portions of northern California and northern Nevada; and the Canadian provinces of British Columbia and Alberta. The NWPP is a collective voice for the coordination of operating reliability issues, addressing both adequacy and transmission reliability for consumers within the area. The NWPP, as well as NERC and the WECC, set reliability criteria and policies for the entities within their respective areas. The NWPP participants implement these criteria and policies in a coordinated and collective manner. The NWPP committees have a long-standing history of cooperatively working together to address problems. They are also forums to coordinate the operation and planning of the area s bulk electric system. It is within these committees that detailed discussion and debate results in the NWPP programs related to the reliable operation and planning of the area s hydro/thermal resources and interconnected transmission grid. Under the guidance of the NWPP, the area s entities have developed regional reliability processes and procedures to assure interconnected system reliability through regional coordination. These processes and procedures have been extremely effective in maintaining coordination, communications, and system reliability. The NERC Reliability Standards and requirements explicitly state that the Reliability Coordinator (RC) is now ultimately responsible for some of these regional processes and procedures. The RC can delegate these functions to other entities but must maintain the responsibility to comply with the standards and requirements. The NWPP consists of twenty balancing authorities which are obligated to comply with any Peak RC requested directive(s). This document describes the NWPP area s processes and procedures that are in place and have been effective in maintaining system reliability. The operating reliability processes include: coordinated (transmission) outage processes, seasonal evaluation of transmission constraints and system operating limits (SOL), next day reliability analysis, automated contingency reserve sharing, coordinated under-frequency load shedding programs, coordinated under-voltage load shedding programs, power and reactive sign conventions, energy emergency plan, interconnection clearance and hold terminology, and coordinated communication during critical operating conditions. The planning processes include: Coordinated hydro planning, drought coordination planning, transmission expansion, area coordination, transmission adequacy, and long-range significant outage planning.

2 The following information summarizes the existing NWPP process and procedures. Individual Balancing Authorities (BA), Transmission Operators (TO), and Peak RC can use this information as documentation for future NERC Readiness Audits and FM certifications. Operating Processes Outage Coordination The NWPP coordinated outage (transmission) system) was designed to assure that outages could be coordinated among all stakeholders (operators, maintenance personnel, transmission users, and operations planners) in an open process. This process had to assure that proper operating studies were accomplished and transmission impacts and limits known, to fulfill a requirement from the 1996 west coast disturbances that the system be operated only under studied conditions. The RC is involved in the outage coordination process and has direct access to the outage data base. Monthly Coordination The process requires NWPP members to designate significant facilities that if out of service by itself or in conjunction with another outage, will impact system capabilities. The significant facilities are defined and updated annually by the NWPP members. The scheduled outage of these critical facilities is posted on a common database. All utilities post proposed significant outages on Peak RC s Coordinated Outages System (COS). Outages are to be submitted to the COS at least 45 days ahead of the month they are proposed to occur so they can be viewed by interested entities. The involved entities then facilitate the NWPP coordination of all these outages. Entities can comment on the preliminary impacts and schedules may be adjusted to maximize reliability and minimize market impacts. If coincidental outages cause too severe of an impact, the requesting utilities work together to adjust schedules accordingly. Priority is given to the outages that were posted first, taking into account comments received from interested parties with each transmission operator making decisions for their lines. A final outage plan is posted with estimated path capabilities 30 days prior to the month in which the outages will occur. Detailed operational transfer capability studies are then performed and the limits for each affected path are posted at least 15 days prior to the outage. Emergency outages can be requested outside these schedule guidelines. Emergency outages are coordinated among adjacent utilities to minimize system exposure. Utilities can use the COS system to ensure system topology is correct for next day studies. As transmission operators increase the amount of short term outages in addition to the significant outages, the Peak RC will be able to use the final outage schedule in its real-time system analysis. This coordinated outage process has been very effective. The outage information is used by NWPP member utilities to perform system studies to maximize system reliability.

3 Semi-annual planning - Long-Range Significant Outage Planning (LRSOP) The NWPP staff facilitates outage meetings every six months with each utilities outage coordinator to discuss proposed longer term outages. Utilities discuss anticipated outages needed for time critical construction and periods where transmission capacity may need to be maximized. The outages are posted on the Peak RC COS and on the individual companies OASIS sites. Specific responsibilities of LRSOP include: Share outage information with all parties affected by outages of significant equipment (i.e. equipment that affects the transfer capability of rated paths). Information is shared two times each year for a minimum of a six-month period. The first meeting each year coordinates outages for July through December. The second meeting coordinates outages for January through June. Review the outage schedules to insure that needed outages can be reliably accomplished with minimal impact on critical transmission use. Outage coordinators are to post the outages on the Coordinated Outages System within the applicable timeframes. Northwest Operation and Planning Study Group A recommendation of the 1996 west coast disturbances was the requirement to not operate in conditions that have not been studied. This requirement, lead to the formalization of a study and review process to determine seasonal operating transfer capability (OTC) also known as system operating limits (SOL) limits for critical paths in WECC. The NWPP entities had, through a cooperative working relationship, shared information prior to the formalization of the process. The initial focus for this effort was the California-Oregon Intertie (COI) because this path was involved in both 1996 disturbances. The seasonal study process was eventually expanded from the COI to all WECC paths listed in the WECC path rating catalog. The WECC created the Operating Transfer Capability Policy Committee (OTCPC) and corresponding SOL study and review process. This process divided the WECC into regional study groups that are responsible to perform and approve seasonal studies on significant paths in their region to determine the maximum SOL. The NWPP formalized the Northwest Operation and Planning Study Group (NOPSG), which is composed of the path operators and/or owners of critical NW transmission paths and any other interested NWPP members. The results of NOPSG seasonal studies and SOLs are provided by the respective Tops to the Peak RC. The NOPSG process is available on the NWPP website in the Operating Committee area and Transmission Planning Committee area.

4 Next Day Operating Studies Additional path curtailments may be required depending upon current system conditions and outages. These curtailment studies are performed by the individual path operators based on the outage schedule developed through the COS process. According to the COS process, these studies are performed at least 15 days prior to the outage. Individual path operators and transmission owners may also perform updated next day studies to capture emergency outage requests and current system conditions such as generation dispatch to determine if the SOL studies and limits are still accurate. Based on these studies, additional SOL curtailments may be made by the path operators. The modified SOL s are posted on the individual transmission owners OASIS and the Peak RC is notified. The Peak RC also performs system studies to ensure interconnected system reliability. The Peak RC performs real-time system thermal studies to evaluate current operating conditions across the entire Interconnection. The Peak RC is in the process of incorporating real-time voltage tools to complement the thermal analysis currently being performed. Transient stability analysis capability is planned in the future. When the Peak RC observes real-time reliability problems they contact the path operator to discuss the issue and work on a solution. The Peak RC will make a directive for action if there is an imminent reliability threat and the balancing authority does not eliminate the reliability issue within an appropriate time frame. Contingency Reserve Sharing Procedure As permitted by NERC and WECC criteria and standards, the Operating Committee of the NWPP has instituted a Reserve Sharing Program for contingency reserve and established a permanent committee, the Reserve Sharing Group (RSG) Committee to oversee the Reserve Sharing Program. Those who participate in a RSG are better positioned to meet the NERC disturbance control standard because they have access to a deeper and more diverse pool of shared reserve resources. Also, an increase in efficiency is obtained since the shared reserve obligation for the group as a whole is less than the sum of each participant s reserve obligation computed separately. By sharing contingency reserve, the participants are entitled to use not only their own internal reserve resources, but to call on other participants for assistance if internal reserve does not fully cover a contingency. The reserve sharing process for the NWPP has been automated. A manual backup process is in place if communication links are down or the computer system for reserve sharing is not functioning correctly. The NWPP is designated as a reserve sharing group (RSG) as provided under WECC Operating Reliability Criteria. Each member of the RSG is required to maintained its allocated share of the NWPP RSG s contingency reserve obligation (CRO) or the most severe single contingency (MSSC) whichever is greater. The combined allocated share of the members CRO must be larger than the RSG MSSC. If not, then each allocated share of the member s CRO is proportionally increased until this requirement is met. When any RSG member loses generation they have the right to

5 request assistance reserves from the other RSG members as long as they have first committed their allocated share CRO. A request is sent via the member s energy management system to the central computer. The computer then distributes the request proportionally among members within the RSG. Each member may be called to provide reserve up to its allocated share of the CRO. Critical transmission paths are monitored in this process to ensure SOL limits are not exceeded. If a transmission path SOL is exceeded the automated program redistributes the request among RSG members that are delivering reserve along non-congested paths. Settlement for energy delivered under the reserve sharing program can either be settled financially based on the Powerdex hourly Mid-C market index or by return of like energy. If a reserve request fails due to various reasons, backup procedures are in place to fully address the requirements. Coordinated Underfrequency Load Shedding (UFLS) programs Following the 1996 west coast disturbances, The WECC implemented a west-wide coordinated off-nominal frequency load shedding and restoration plan (the Plan). The Plan consist of three micro plans, one is the he NWPP coordinated the UFLS program for the NWPP area. The NWPP UFLS program is designed to arrest frequency that may result in an uncontrolled failure of components of the Western s Interconnection (WI). The program is coordinated with all areas of the WI to prevent unbalanced load shedding which may result in high transmission loading and extreme voltage deviations. In addition, the plan is designed to protect generating equipment and transmission facilities against damage and leave the system in a condition to permit rapid restoration. Through the WECC UFLS Review Group, the NWPP entities annually review the effectiveness of the design, implementation, and documentation of the UFLS program, and make any necessary changes based on current system conditions. Dynamic planning models are used to determine the effectiveness of the UFLS plan. Voltage Issues Work Group (VI) The VI work group membership is open to all NWPP Operating Committee (OC) members. Specific responsibilities of VI work group include: Facilitate the process to address voltage issues across multiple balancing authorities within the NWPP. Participate in studies to determine impacts of voltage issues and develop guidelines to resolve the problem. Develop and publish methodology and final reports Power and Reactive Sign Conventions The lack of a common standard for metering sign conventions may lead to confusion, which may cause multiple sites to follow opposing conventions. The NWPP has developed a document that provides for a common standard from which to base designs, installations, and written contracts.

6 Energy Emergency Plan (EEP) The overarching purpose of the EEP is to increase the area's ability to avoid a power emergency or longer-term adequacy problem by promoting area coordination and communications. The EEP is aimed at promoting actions, in advance, to avoid potential short-term emergencies and longer-term energy adequacy problems in the NWPP area. These actions are targeted to alleviate the need for the Reliability Coordinator to declare a NERC Energy Emergency Alert level 1, 2, or 3 as defined in NERC Reliability Standard. The EEP is designed to be invoked when the area has a high degree of confidence that a future short-term power emergency or a long-term energy adequacy problem would adversely affect reliability within the NWPP. The EEP is not intended to supplant any entity's authority, but rather it provides the framework for how the utilities, governmental agencies, and other entities will work together should an emergency situation be anticipated as a result of severe weather conditions and/or unexpected outages of transmission or generating facilities that impact load-resource balance. The EEP focuses on area actions and is intended to work with and complement current governmental regulations and policies in place for individual balancing authorities and load serving entities. The intended audience for the EEP is operating entities, near-term planners, and policy makers in the electric power industry as well as the area's governments. It provides objectively defined criteria for communicating emergency warnings and warnings of longer-term area energy adequacy problems within the area that are based on analysis of the load and resource situation. The EEP identifies generic area actions when these warnings are declared, describes the roles and responsibilities of the parties involved, and lays out a communication plan for keeping all stakeholders informed throughout the potential crisis. It is expected that individual entities will use the EEP as a procedural framework for identifying the individual actions they will be able to take when either warnings of power emergencies or warnings of energy adequacy problems are declared. Interconnection Clearance and Hold Terminology The NWPP Operating Committee determined that a common terminology is desirable when Clearances or Holds are required on equipment interconnecting two or more utilities. The NWPP Terminal Clearance assures the requesting Grid Operator/Dispatcher that the terminal or source is open, properly cleared and tagged according to local procedures, and that it will not be energized until a release is given by the Grid Operator/Dispatcher receiving the Terminal Clearance. The NWPP Terminal Hold assures the requesting Grid Operator/Dispatcher that the terminal or source on "hold" has relays in service to provide protection in the event of a fault; and, once tripped out of service, will not be re-energized, automatically or

7 manually, until the Grid Operator/Dispatcher receiving the Terminal Hold has advised that all personnel and materials are in the clear and it is safe to energize. Coordinated Communication during Critical Operating Conditions Entities responsible for operating the bulk electric system within the Northwest Power Pool (NWPP) area have dealt with various conditions over the last few decades. During these times, the Northwest electric industry s expertise, communication, coordination, and cooperation are unique and have served this area and its consumers well. The elements of the NWPP s plan to handle coordinated communications incorporate the following elements: New U.S. Federal Energy Regulatory Commission regulations are in place that enhance market competition, but restrict the ways in which the various elements of our industry may communicate. The Peak RC is staffed to conduct a wide area view and therefore increase the vision, awareness, and effectiveness of balancing authority operators, especially during times of duress. Reliability Standards and procedures have been adopted by North American Electric Reliability Council (NERC) to mitigate and communicate reliability problems, including Energy Emergencies. Coordinated communications provide support to the NWPP entities with respect to public communications during critical operating conditions. Coordinated communications may include, but are not limited to the following: 1) Facilitating meetings of the communications support team, 2) Acting as a liaison between the communications support team and other parties, 3) Representing the NWPP area s entities in public communications and the media, and 4) Providing talking points and other communication aids to the NWPP entities and area policy-makers. Planning Processes Coordinated Hydro Planning The 1997 Pacific Northwest Coordinating Agreement (97 PNCA) requires the development of an annual plan for the coordinated operations of the Coordinated hydroelectric systems as defined by the 97 PNCA. By factoring in weather, river flows and water needed for fish spills, the Coordinating Group s (CG) annual plan estimates how much power will be generated by the Coordinated System s

8 hydroelectric facilities and helps the CG plan for any shortfall. Through this work the NWPP is able to provide seasonal forecast of the area s power requirements and determine whether there will be enough power generated to meet those needs. Drought Coordination Planning Through the CG a forum exists to develop plans to address the area s power requirements under drought conditions and formulate plans to assure power is generated to meet the area s requirements. Transmission Expansion Planning Serve as Forum for open discussion. Develop guidelines for assessing the reliability and efficient development of the transmission system in the NWPP area. Collection and coordination of member s data. Seasonal Assessment. Support underfrequency load shedding simulations. Summary The NWPP Agreements, and any Procedures, Process, Plans, Charters, and Reports sufficiently meet the goal of cooperatively working together to address problems, and the coordination of the reliable operation and planning of the area s bulk electric system. The NWPP documents are reviewed at least annually to assure they meet industry changes and requirements and are available to all NWPP participants committee representatives on the NWPP Website portal Resources section as they relate to each respective Committee.

Functional Entity Roles and Responsibilities

Functional Entity Roles and Responsibilities Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 Project 2014-03 Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 This mapping document showing the translation of Requirements in the following currently-enforceable

More information

NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC)

NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC) NORTHWEST POWER POOL Reliability through Cooperation 2006 2 NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC) NERC is a not-for-profit company formed as a result of the Northeast blackout in 1965 to promote

More information

NERC Reliability Functional Model

NERC Reliability Functional Model NERC Reliability Functional Model Function Definitions and Responsible Entities Version 3 Approved by Standing Committees: Operating Committee: December 6, 2006 Planning Committee: December 6, 2006 Standards

More information

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization - 1 - Introduction The North American Electric Reliability Council (NERC) requires every

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Agenda Item 3.b.i ORS Meeting September 7-8, 2016 RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Introduction The Southern Company Services is the Southeastern

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

Approved by Standing Committees Approved by Board of Trustees

Approved by Standing Committees Approved by Board of Trustees Reliability Functional Model Function Definitions and Responsible Entities Prepared by the Functional Model Working Group Version 4 Approved by Standing Committees Approved by Board of Trustees August

More information

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations Updated October 2, 2014 System Operator Transmission - Senior interconnected system. Maintains the Western Electricity Coordinating Council (WECC) Coordinated Outage System (COS), documents standardized

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

Load Shed Philosophy

Load Shed Philosophy APPLICABILITY: Reliability Coordinator I. Background While time limits exist for mitigation of the exceedance of certain types of system operating limits, events can occur quickly necessitating a responsive

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

Loads and Resources Methods and Assumptions

Loads and Resources Methods and Assumptions Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1

More information

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation Observations and Information Sharing Date: June, 2015 Prepared by: AESO Table of Contents Executive Summary...

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 3 3.1. Order of Steps... 3 3.2. Restricted

More information

Job Descriptions. Title & Job Functions: Transmission Function Employees

Job Descriptions. Title & Job Functions: Transmission Function Employees Job Descriptions In accordance with its Standards of Conduct Implementation and Compliance Procedures, City Utilities of Springfield, Missouri will post on these pages the job titles and job descriptions

More information

Energy Imbalance Market

Energy Imbalance Market IISii Energy Imbalance Market Draft Final Proposal September 23, 2013 CAIS[Type text] [TyIISIISIpe tiext]iso [Type text] Table of Contents 1. Executive Summary... 1 2. Introduction... 10 2.1. New Terms...

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION NORTH AMERICAN ) Docket No. RR07-11- ELECTRIC RELIABILITY CORPORATION ) ) COMPLIANCE FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Appendix A3: Northeast Power Coordinating Council (NPCC) 2018 CMEP Implementation Plan

Appendix A3: Northeast Power Coordinating Council (NPCC) 2018 CMEP Implementation Plan Appendix A3: Northeast Power Coordinating Council (NPCC) 2018 CMEP Implementation Plan This Appendix contains the CMEP Implementation Plan (IP) for NPCC as required by the NERC Rules of Procedure (ROP).

More information

NORTHWEST POWER POOL. Energy Emergency Plan

NORTHWEST POWER POOL. Energy Emergency Plan NORTHWEST POWER POOL Energy Emergency Plan Revised August 2017 Table of Contents I. Background... 3 II. Purpose... 3 III. Potential Actions of the Emergency Plan... 4 IV. Key Plan Components and Definitions...

More information

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015

Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Appendix 5B Statement of Compliance Registry Criteria Revision 5.2 Effective: October 15, 2015 Statement of Compliance Registry Criteria (Revision 5.2) Summary This document describes how the North American

More information

Reliability Coordinator Plan

Reliability Coordinator Plan APPLICABILITY: Reliability Coordinator I. Purpose Peak Reliability s Reliability Coordinator (RC) Plan describes the processes implemented as the Reliability Coordinator responsible for coordinating and

More information

NERC-led Review Panel Decision on the Request by Orange Grove Energy, L.P.

NERC-led Review Panel Decision on the Request by Orange Grove Energy, L.P. NERC-led Review Panel Decision on the Request by Orange Grove Energy, L.P. The North American Electric Reliability Corporation (NERC)-led Review Panel (Panel) has completed its evaluation of the request

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 655 CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 656 ANCILLARY SERVICES REQUIREMENTS PROTOCOL Table of Contents ASRP 1

More information

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations The following table provides a mapping of the recommendations applicable to the Reliability

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

FERC Directives in Order 693 Addressed in IROL Implementation Plan

FERC Directives in Order 693 Addressed in IROL Implementation Plan The following Interconnection Reliability Operating Limit (IROL) standards were under development when the Version 0 project was initiated: IRO-008 Reliability Coordinator Operational Analyses and Real-time

More information

Implementation Plan IRO Reliability Coordination Current Day Operations

Implementation Plan IRO Reliability Coordination Current Day Operations Implementation Plan IRO-005-4 Reliability Coordination Current Day Operations Approvals Required IRO-005-4 Reliability Coordination Current Day Operations Prerequisite Approvals None Revisions to Glossary

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated Standard FAC-008-1 Facility Ratings Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018

WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018 WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018 Introduction The Data Subcommittee compiles eleven steady state and dynamic base cases (base cases) to meet WECC s requirements

More information

Reliability Functional Model Technical Document Version 6

Reliability Functional Model Technical Document Version 6 Reliability Functional Model Technical Document Version 6 Prepared by the Functional Model Advisory Group Approved by the Standards Committee: [Month, Year] NERC Report Title Report Date I Table of Contents

More information

PRC-006, PRC-007, and PRC-009 Mapping to Proposed Continent-Wide Standard

PRC-006, PRC-007, and PRC-009 Mapping to Proposed Continent-Wide Standard PRC-006, PRC-007, and PRC-009 Mapping to PRC-006: Development and Documentation of Regional UFLS Programs Requirement in the Existing PRC Standards Standard R1: Each Regional Organization shall develop,

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION Operating Policies and Procedures Emergency System Operations OPP 804 Issued:2008-11-13 Supersedes Interim OPP Effective:2008-05-01 804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION 1. Purpose To

More information

Standard IRO a Reliability Coordination Current Day Operations

Standard IRO a Reliability Coordination Current Day Operations A. Introduction 1. Title: Reliability Coordination Current Day Operations 2. Number: IRO-005-3.1a 3. Purpose: must be continuously aware of conditions within its Reliability Coordinator Area and include

More information

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo

More information

Procedure No. Operating Version No. Procedure Effective Date System Emergency Notice Templates Distribution Restriction: None 1.

Procedure No. Operating Version No. Procedure Effective Date System Emergency Notice Templates Distribution Restriction: None 1. No. 4420C 1. Detail 1.1. Purpose and Distribution The California ISO sends System Emergency notices when adverse grid or market conditions require activation of the California ISO Electrical Emergency

More information

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING Operating Policies and Procedures Reporting OPP 1304 Issued: 2016-08-30 Supersedes: 2007-12-03 1. Purpose 1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING To establish processes for reporting AIES

More information

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING Operating Policies and Procedures Reporting OPP 1304 Issued: 2016-08-30 Supersedes: 2007-12-03 1. Purpose 1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING To establish processes for reporting AIES

More information

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards Mapping Document Project 2007-06.2 Phase 2 of System Protection Coordination Revisions or Retirements to Already Approved Standards This mapping document explains how each of the existing Requirements

More information

Standard FAC System Operating Limits Methodology for the Planning Horizon

Standard FAC System Operating Limits Methodology for the Planning Horizon Standard FAC-010-1 System Operating Limits Methodology for the Planning Horizon Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will

More information

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY

More information

SIERRA NEVADA REGION TRANSMISSION FUNCTION EMPLOYEES

SIERRA NEVADA REGION TRANSMISSION FUNCTION EMPLOYEES SIERRA NEVADA REGION TRANSMISSION FUNCTION EMPLOYEES Vice President of Operations: Reports to Senior Vice President / al Manager Manages and directs SNR s power system operations Manages work activities

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Appendix 5B. Statement of Compliance Registry Criteria

Appendix 5B. Statement of Compliance Registry Criteria Appendix 5B Statement of Compliance Registry Criteria Revision 5.1 Effective: July 1, 2014 (as noted below) The highlighted terms Bulk Electric System and Load in this document will become effective as

More information

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

System Impact Study and Facilities Study Process Manual For Cleco Power LLC System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 8.1 By Peak Reliability February 24, 2017 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

Document Updated: 12/5/2018

Document Updated: 12/5/2018 Vice President Energy Delivery Document Updated: 12/5/2018 * Blue shading indicates a qualifying Transmission Function Employee Manager System Operations Manager Substation Supervisor System Control Supervisor

More information

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View

2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Innovations in Bulk Power System Reliability Assessment: A North American View M.G.

More information

Energy Imbalance Market

Energy Imbalance Market IISII Energy Imbalance Market 3 rd Revised Straw Proposal August 13, 2013 CAIS[Type text] [TyIISIIpe tiext]iso [Type text] Table of Contents 1. Executive Summary... 1 2. Introduction... 9 2.1. New Terms...

More information

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date:

A. Introduction Balancing Authority Reliability Coordinator Transmission Operator. 5. Effective Date: A. Introduction 1. Title: Emergency Operations 2. Number: EOP-011-1 3. Purpose: To address the effects of operating Emergencies by ensuring each Transmission Operator and Balancing Authority has developed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Reading, Understanding, and Following NERC Standards

Reading, Understanding, and Following NERC Standards Reading, Understanding, and Following NERC Standards September 15, 2011 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Outline Philosophy behind standards Reading standards

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS RAMU

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Project Revision of TOP/IRO Reliability Standards Resolution of Issues and Directives

Project Revision of TOP/IRO Reliability Standards Resolution of Issues and Directives Project 2014-03 - Revision of TOP/IRO Reliability Standards Resolution of Issues and Directives The following table contains a list of all FERC directives, industry issues, and Independent Expert Review

More information

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Conforming Changes to Requirements in s None Coordination with revisions proposed in other standards projects The IROL SDT proposes retiring

More information

Frequently Asked Questions August 2013

Frequently Asked Questions August 2013 Frequently Asked Questions August 2013 General What is the Bulk-Power System or Bulk Electric System? NERC defines the Bulk-Power System as the electricity power generation facilities combined with the

More information

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria 5/1/2018 OC Meeting PJM Manual M36 System Restoration A.1 Critical Black Start Criteria A.1.1 Goal PJM and its stakeholders have developed requirements for the amount and redundancy of Black Start generation

More information

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept.

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept. Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF A COMMISSION ) INVESTIGATION INTO THE FEASIBILITY ) OF PUBLIC SERVICE COMPANY OF NEW ) MEXICO BECOMING A MEMBER OF THE ) Case No. 17-00261-UT

More information

PJM TO/TOP Matrix of Shared or Assigned Tasks

PJM TO/TOP Matrix of Shared or Assigned Tasks PJM TO/TOP Matrix of hared or ssigned Tasks Revision 07 pproved by the TO/TOP Matrix ubcommittee: October 18, 2013 pproved by the Transmission Owners greement-dministrative Committee: November 27, 2013

More information

Reliability Coordinator Area System Operating Limit Methodology

Reliability Coordinator Area System Operating Limit Methodology Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power

More information

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0 Western Interconnection Seasonal Operations Planning Rev. 3.0 Issued March 26, 2019 Effective May 1, 2019 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Assessment of Load Shed Service for Import (LSSi) Product

Assessment of Load Shed Service for Import (LSSi) Product Assessment of Load Shed Service for Import (LSSi) Product Date: March 27, 2014 Prepared by: Prepared for: Mike Law Jenny Chen Senior Market Design Specialist Vice President, Market Services Table of Contents

More information

Proposed Resource Loss Protection Criteria

Proposed Resource Loss Protection Criteria Proposed Resource Loss Protection Criteria Background and Current Methodologies The Resource Loss Protection Criteria (RLPC) is the respective Interconnection design resource loss in MW, which is used

More information

Energy Management and Planning in Greek Non Interconnected Islands

Energy Management and Planning in Greek Non Interconnected Islands Energy Management and Planning in Greek Non Interconnected Islands Andreas Vlachos Director, Long-term Energy Planning, RAE Framework overview 2 Framework Overview Laws 3468/2006 (Provisions for Renewables),

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

Full Network Model Expansion Second Revised Straw Proposal

Full Network Model Expansion Second Revised Straw Proposal October 30, 2013 Table of Contents 1 Changes from 9/11/2013 revised straw proposal... 3 2 Executive summary... 3 3 Introduction and purpose... 5 4 Plan for stakeholder engagement... 8 5 Scope of initiative...

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 30. Bid And Self-Schedule Submission For All CAISO Markets... 2 30.1 Bids, Including Self-Schedules... 2 30.1.1 Day-Ahead Market... 2 30.1.2 Real-Time Market... 2 30.2 Bid Types... 3

More information

Comments Received and Peak Response. General Comments

Comments Received and Peak Response. General Comments Response to Comments IRO-010-2 Data Request and Specifications for Data Provision Version 12 Document February 21, 2017 Peak Reliability (Peak) would like to thank those who responded to the request for

More information

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...

More information

Briefing on intertie deviation settlement proposal

Briefing on intertie deviation settlement proposal Briefing on intertie deviation settlement proposal Brad Cooper Manager, Market Design Policy EIM Governing Body Meeting General Session January 24, 2019 Management proposes to revise the intertie transaction

More information

A separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period.

A separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period. October 3, 2011 NPCC Full and General Members; Please find attached a draft of the NPCC Regional Standard PRC-006-NPCC-1 Automatic Underfrequency Load Shedding which has been posted to the NPCC Website

More information

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Business Operations, Engineering & Process, has primary responsibility for the overall planning, operations and control

More information

Table of Contents-Quick Reference

Table of Contents-Quick Reference Table of Contents-Quick Reference PURPOSE...3 RESPONSIBILITIES...3...5 1. ISO ELECTRICAL EMERGENCY PLAN...5 1.1. Stage 1 Emergency Notice...5 1.1.1. Notify Emergency Response Team...5 1.1.2. Notify Market

More information

PACIFICORP S ENERGY IMBALANCE MARKET ENTITY PROPOSAL. September 13, 2013 Revised October 18, 2013

PACIFICORP S ENERGY IMBALANCE MARKET ENTITY PROPOSAL. September 13, 2013 Revised October 18, 2013 PACIFICORP S ENERGY IMBALANCE MARKET ENTITY PROPOSAL September 13, 2013 Revised October 18, 2013 This document outlines PacifiCorp s Energy Imbalance Market ( EIM ) Entity proposal ( EIM Entity Proposal

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

STATE OF THE INTERCONNECTION DIGEST

STATE OF THE INTERCONNECTION DIGEST SUMMER 217 STATE OF THE INTERCONNECTION DIGEST The State of the Interconnection is a snapshot of evolving trends in the Western Interconnection. Beginning in 217, the Western Electricity Coordinating Council

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

Standard EOP Capacity and Energy Emergencies

Standard EOP Capacity and Energy Emergencies A. Introduction 1. Title: Capacity and Energy Emergencies 2. Number: EOP-002-2 3. Purpose: To ensure Reliability Coordinators and Balancing Authorities are prepared for capacity and energy emergencies.

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information