Distributed Energy Resources (DER) Update Behind the Meter Generation (BtMG) Visibility

Size: px
Start display at page:

Download "Distributed Energy Resources (DER) Update Behind the Meter Generation (BtMG) Visibility"

Transcription

1 Distributed Energy Resources (DER) Update Behind the Meter Generation (BtMG) Visibility MIC-DER Special Session Andrew Ford Model Management Dept. PJM Interconnection

2 Impact of DER on PJM processes Address system issues to avoid manual load dump Request for DER output Example local capacity shortage in MI where DER can mitigate (Sturgis) Operational awareness understand grid situation for future dispatch actions & communication Example PEPCO low voltage issue that resulted in DER output which appeared as load drop. Improve real time and long term forecast or better understand forecast errors Improve RTEP load flow studies Administer Non-Retail Behind the Meter Generation ( NRBTMG ) rules DER represents BTMG/NRBTMG (including batteries) not transparent or controlled by PJM (Does not include generation that went through PJM queue OR participates through DR) 2

3 2013 Sept. Behind-the-Meter Event 46 Excessive line flow and load observed Sturgis Load (MW) Action 2: City of Sturgis implements Voluntary Customer Load Curtailment Action 1: City of Sturgis starts 6 MW behind-themeter unit Reduced load and line flow observed 37 11:00 12:00 13:00 14:00 3

4 Behind-the-Meter Generation Data Collection Scope : Transmission Owners Public Utility Commissions Behind-the-Meter facilities includes batteries Details collected: Energy Information Agency BTM Database Generator Attribute Tracking System Location, capacity, nearest substation, time-to-start, mode of operation. Number of identified units: ~425 units Total capacity of identified units: ~3500 MW 4

5 Data Options being considered EMS Data modeling Energy Management System modeling attributes: Visibility on individual single line Shows connectivity Telemetry can indicate operation Negative load to not negatively impact State Estimator solution Tabular list based on BTM naming Visibility and Operational Awareness Coordinated effort to enhance communications during critical operational periods DIMA Data modeling Dispatch Interactive Map Application (DIMA), visually shows area maps for Weather, Line Outages, Demand Resources, Gas Pipeline, and BtMG resources. 5

6 Behind-the-Meter Visibility at PJM Behind-the-meter plants added to display Dispatch Interactive Map Application (DIMA) 6

7 Behind-the-Meter Visibility at PJM Ability to search for behind-the-meter plants in specific zone Dispatch Interactive Map Application (DIMA) 7

8 BtMG Technical information and Data submission Two Items: 1. BtMG PJM Position Technical Paper 2. Data submission form 8

9 High Level Process Overview: EMS processing PJM Manual 3A, Section and Appendix D has specifics. EMS Real-Time Model 9

10 BES Location EMS Node Location 10

11 EMS Discussion Example 11

12 BtMG Data Form Description of each data entry field is given in PJM Manual 3A, Appendix D. 12

13 Non-Retail Behind the Meter Generation ( NRBTMG ) What is NRBTMG? BTMG that is used by municipal electric systems, electric cooperatives, and electric distribution companies to serve load Total amount eligible to net generation against load is capped. Should operate during maximum emergency generation events Current PJM process Members should notify PJM of NRBTMG and associated output. Model in EMS or maintain separate list, depending on level of information. 13

14 Next Steps 1. Develop and enhance process to keep information accurate and current (need TO/EDC assistance) EMS vs DIMA to manage the information Non-Retail Behind the Meter Generation and retail Behind the Meter Generation reporting process. Evaluate enhancements to BtMG form 2. Refine load forecast process with DER information, as applicable. 3. Coordinate with MIC-DER special session regarding process enhancements and changes. Work in progress more to follow 14

Integrating DER in PJM Transmission Operations and Planning

Integrating DER in PJM Transmission Operations and Planning Integrating DER in PJM Transmission Operations and Planning NRRI Webinar: Case Studies in Utility Integrated Distributed Resources Planning and Doing October 11, 2017 Andrew Levitt Senior Market Strategist

More information

Technical Analysis of Operational Events and Market Impacts During the September 2013 Heat Wave

Technical Analysis of Operational Events and Market Impacts During the September 2013 Heat Wave During the September 2013 Heat Wave PJM Interconnection December 23, 2013 Contents 1 Executive Summary... 4 2 Introduction... 7 3 Load Shed Event Assessments... 11 3.1 Pigeon River 1 Load Shed Event (September

More information

Capacity Performance Training. March 16, 2015

Capacity Performance Training. March 16, 2015 Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

Expanded Metering and Telemetry Options Phase 2. Distributed Energy Resource Provider (DERP) Draft Final Proposal

Expanded Metering and Telemetry Options Phase 2. Distributed Energy Resource Provider (DERP) Draft Final Proposal Expanded Metering and Telemetry Options Phase 2 Distributed Energy Resource Provider (DERP) June 10, 2015 Table of Contents 1 Introduction... 4 2 Summary of key advances, revisions to the revised straw

More information

Benefits from Generation and Storage on the Distribution System

Benefits from Generation and Storage on the Distribution System Benefits from Generation and Storage on the Distribution System Andrew Levitt Senior Market Strategist Emerging Markets Special MRC Meeting DER Aug 24, 2016 Generation/Storage Resource Location and Types

More information

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Matteo Leonardi 22 May 2013 Liberalized markets versus monopolies Production Transmission distribution

More information

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017

MISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017 MISO 2018 Series Dispatch Update MOD-032 Users Group October 3, 2017 1 Objective MTEP17 Dispatch Process MTEP18 Dispatch Updates Reminder Station Service Load Modeling Enhancements Wind Capacity Credit

More information

LOAD SERVING ENTITIES PJM REGION

LOAD SERVING ENTITIES PJM REGION Intra-PJM Tariffs --> RELIABILITY ASSURANCE AGREEMENT PJM Interconnection, L.L.C. Rate Schedule FERC No. 44 RELIABILITY ASSURANCE AGREEMENT Among LOAD SERVING ENTITIES in the PJM REGION Effective Date:

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

Public Benefit Programs: Energy Efficiency and Renewable Energy in Deregulated Energy Markets

Public Benefit Programs: Energy Efficiency and Renewable Energy in Deregulated Energy Markets Public Benefit Programs: Energy Efficiency and Renewable Energy in Deregulated Energy Markets James Gallagher, Director Office of Electricity and Environment NYS PSC 1 Demand Management Programs in A Vertically

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

SPP at a Glance. Located in Little Rock. Approximately 600 employees

SPP at a Glance. Located in Little Rock. Approximately 600 employees SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment

More information

Network Model to Transmission Outage Ticket Linkage Functionality

Network Model to Transmission Outage Ticket Linkage Functionality Network Model to Transmission Outage Ticket Linkage Functionality Ron DeLoach March 2016 DMS/eDUG Joint Meeting Presentation Objective New functionality to link cut-in transmission tickets to Network Model

More information

An Introduction to Interconnection Policy in the United States

An Introduction to Interconnection Policy in the United States An Introduction to Interconnection Policy in the United States I. Introduction to Interconnection Policy II. History of Interconnection Policy III. PJM Interconnection Procedures IV. ferc small generator

More information

Solar Integration into the PJM Grid

Solar Integration into the PJM Grid Solar Integration into the PJM Grid Ken Schuyler Manager, Renewable Services PJM Interconnection September 14, 2017 Integrating Solar in PJM PJM Background PJM Initiatives to Address Impacts Analysis of

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Capacity Performance Training. June 24, 2015

Capacity Performance Training. June 24, 2015 Capacity Performance Training June 24, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members:

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members: 2750 Monroe Blvd. Audubon, PA 19403 May 4, 2017 PLANNING COMMITTEE Dear Committee Members: 2017 PJM RESERVE REQUIREMENT STUDY - DETERMINATION OF THE PJM INSTALLED RESERVE MARGIN, FORECAST POOL REQUIREMENT

More information

2016 Fall Reliability Conference MRO

2016 Fall Reliability Conference MRO 2016 Fall Reliability Conference MRO CAISO s Coordination, Tracking, and Monitoring Distributed Energy Resources Amber Motley; Manager, Short Term Forecasting November 2 nd, 2016 California ISO Overview

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

PJM PROMOD Overview. August 1, PJM

PJM PROMOD Overview. August 1, PJM PJM PROMOD Overview August 1, 2017 Market Analysis Software PROMOD PROMOD is a fundamental electric market simulation solution It incorporates future demand, generating unit operating characteristics,

More information

The Transformation of the New England Electric Grid and the Importance of Situational Awareness Tools

The Transformation of the New England Electric Grid and the Importance of Situational Awareness Tools SEPTEMBER 26, 2017 SPRINGFIELD, MA The Transformation of the New England Electric Grid and the Importance of Situational Awareness Tools North American SynchroPhasor Initiative NASPI Work Group Meeting

More information

Distributed Solar Generation Update

Distributed Solar Generation Update Distributed Solar Generation Update Load Analysis Subcommittee November 15, 2017 Topics Review of Process to incorporate Distributed Solar Generation into the Long-Term Forecast Identical process to last

More information

The Integration of Price Responsive Demand into PJM. Wholesale Power Markets and System Operations. Paul Centolella and Andrew Ott 1.

The Integration of Price Responsive Demand into PJM. Wholesale Power Markets and System Operations. Paul Centolella and Andrew Ott 1. The Integration of Price Responsive Demand into PJM Wholesale Power Markets and System Operations Paul Centolella and Andrew Ott 1 March 9, 2009 I. Introduction A number of states and utilities are pursuing

More information

Introduction to the PJM Markets

Introduction to the PJM Markets Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility

More information

Solar and Smart Grid Training Design, Installation, Business Saving Energy Together

Solar and Smart Grid Training Design, Installation, Business  Saving Energy Together Solar and Smart Grid Training Design, Installation, Business www.imaginesolar.com Classroom Instruction Lab Exercises Photovoltaic Modules Lab Exercises Photovoltaic Modules Solar Site Analysis Solar Site

More information

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018

PJM Manual 14E: Additional Information for Upgrade and Transmission Interconnection Projects Revision: 05 Effective Date: April 1, 2018 PJM Manual 14E: Additional Information for Upgrade and Transmission Revision: 05 Effective Date: April 1, 2018 Prepared by System Planning Division Department PJM 2018 Table of Contents Table of Contents

More information

Southern California Edison

Southern California Edison Southern An Edison International An Edison Company International Serving Company Customers Serving for over Customers 125 Years for over 125 Years Serves a population Serves a population of more of than

More information

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017 Prepared by System Planning Department PJM 2017 Table of Contents Table of Contents

More information

X Accept as requested X Change to Existing Practice Accept as modified below Decline

X Accept as requested X Change to Existing Practice Accept as modified below Decline 1. RECOMMENDED ACTION: EFFECT OF EC VOTE TO ACCEPT RECOMMENDED ACTION: X Accept as requested X Change to Existing Practice Accept as modified below Status Quo Decline 2. TYPE OF DEVELOPMENT/MAINTENANCE

More information

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo

More information

Reserve Market. PJM State & Member Training Dept. PJM /06/2016

Reserve Market. PJM State & Member Training Dept. PJM /06/2016 Reserve Market PJM State & Member Training Dept. PJM 2016 Objectives Define Reserve products Explain the Reserve requirements Calculate Reserve offers PJM 2016 2 Reserves Reserves are additional generation

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal

More information

Distributed Energy Resources and the Distribution System Planning Process PEPCO HOLDINGS LLC September 23, 2016

Distributed Energy Resources and the Distribution System Planning Process PEPCO HOLDINGS LLC September 23, 2016 Distributed Energy Resources and the Distribution System Planning Process PEPCO HOLDINGS LLC September 23, 2016 Table of Contents 1 Background... 4 2 Procedural History... 5 3 Scope of this Report... 7

More information

Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017

Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017 Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017 What is a Microgrid? US Department of Energy Microgrid Exchange Group Definition: A group of interconnected loads

More information

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP

More information

PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 03 Effective Date: November 17, Prepared by PJM Forward Market Operations

PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 03 Effective Date: November 17, Prepared by PJM Forward Market Operations PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 03 Effective Date: November 17, 2016 Prepared by PJM Forward Market Operations PJM 2016 Table of Contents Table of Contents Approval...5

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix N... 2 Pseudo-Tie Protocol... 2 1. Pseudo-Ties of Generating Units to the CAISO Balancing Authority Area... 2 1.1 Consistency with NERC/WECC Requirements... 2 1.2 CAISO Operating,

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources Future Market Options Sai Moorty ERCOT 1 North American Bulk Power Grids The ERCOT Region is one of 3 grid interconnections in USA-Canada The ERCOT grid: Covers 75% of Texas

More information

PJM Reserve Market. PJM State & Member Training Dept. PJM /27/2015

PJM Reserve Market. PJM State & Member Training Dept. PJM /27/2015 PJM Reserve Market PJM State & Member Training Dept. Objectives Students will be able to: Identify the process and procedures for participating in the Real Time Reserve Market Reserves Overview What are

More information

Distributed Energy Resources: Maintaining Reliability & Integrating New Technology Solar Stakeholder Collaborative for the District of Columbia

Distributed Energy Resources: Maintaining Reliability & Integrating New Technology Solar Stakeholder Collaborative for the District of Columbia Distributed Energy Resources: Maintaining Reliability & Integrating New Technology Solar Stakeholder Collaborative for the District of Columbia August 30, 2016 - Morning Session 1 Welcome to Pepco Holdings

More information

ERCOT in 2018: Challenges & Opportunities

ERCOT in 2018: Challenges & Opportunities ERCOT in 2018: Challenges & Opportunities Bill Magness President & CEO ERCOT Texas-Germany Bilateral Dialogue on Challenges and Opportunities in the Electricity Market February 27, 2108 What is ERCOT?

More information

SCHEDULE 6A Black Start Service

SCHEDULE 6A Black Start Service SCHEDULE 6A Black Start Service References to section numbers in this Schedule 6A refer to sections of this Schedule 6A, unless otherwise specified. To ensure the reliable restoration following a shut

More information

Emergency Management Policy

Emergency Management Policy Emergency Management Policy Effective from 19 June 2016 1. Background 1.1 This Policy is the emergency management policy, which the system operator is required to prepare and publish under clause 7.3(3)

More information

Analysis of the 2019/2020 RPM Base Residual Auction

Analysis of the 2019/2020 RPM Base Residual Auction Analysis of the 2019/2020 RPM Base Residual Auction The Independent Market Monitor for PJM August 31, 2016 Monitoring Analytics 2016 www.monitoringanalytics.com Introduction This report, prepared by the

More information

Incremental Black Start RFP Response Template & General Information

Incremental Black Start RFP Response Template & General Information Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section

More information

Anne Pramaggiore President & Chief Executive Officer ComEd

Anne Pramaggiore President & Chief Executive Officer ComEd Anne Pramaggiore President & Chief Executive Officer ComEd Utility of the Future 3 trends are disrupting the utility industry requiring us to respond differently than we have before 1 Climate change is

More information

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US Amy Rose, Ph.D. Energy Analyst National Renewable Energy Laboratory US RE policies & regulations are set at multiple levels

More information

Electrification and its Implications for the California Electricity System

Electrification and its Implications for the California Electricity System Electrification and its Implications for the California Electricity System Lorenzo Kristov, Ph.D. Principal, Market & Infrastructure Policy EPRI-IEA Workshop: Challenges in Electricity Decarbonization

More information

New England Electricity Outlook

New England Electricity Outlook O C T O B E R 2 1, 2 0 1 6 S O U T H P O R T L A N D, M E New England Electricity Outlook Environmental and Energy Technology Council of Maine (E2Tech) Eric Johnson D I R E C T O R, E X T E R N A L A F

More information

Job Descriptions. Title & Job Functions: Transmission Function Employees

Job Descriptions. Title & Job Functions: Transmission Function Employees Job Descriptions In accordance with its Standards of Conduct Implementation and Compliance Procedures, City Utilities of Springfield, Missouri will post on these pages the job titles and job descriptions

More information

Distributed Energy Resources Market Design Concept Proposal

Distributed Energy Resources Market Design Concept Proposal Distributed Energy Resources Market Design Concept Proposal A Report by the New York Independent System Operator December 2017 Table of Contents OVERVIEW... 4 DISTRIBUTED ENERGY RESOURCES... 8 Dispatchable

More information

Section 5: Network Integration Transmission Service Accounting. 5.1 Network Integration Transmission Service Accounting Overview

Section 5: Network Integration Transmission Service Accounting. 5.1 Network Integration Transmission Service Accounting Overview Section 5: Network Integration Transmission Service Accounting Welcome to the Network Integration Transmission Service Accounting section of the PJM Manual for Open Access Transmission Tariff Accounting.

More information

Transmission Expansion Advisory Committee. Reliability Analysis Update

Transmission Expansion Advisory Committee. Reliability Analysis Update Transmission Expansion Advisory Committee Reliability Analysis Update June 11, 2015 Deactivation Update Generation Deactivations 3 Deactivation Status Unit(s) FPL MH50 (50.8MWs) - UPDATED AES Beaver Valley

More information

Utility 2.0 Long Range Plan 2016 Annual Update Prepared for Long Island Power Authority. December 29, 2016

Utility 2.0 Long Range Plan 2016 Annual Update Prepared for Long Island Power Authority. December 29, 2016 Utility 2.0 Long Range Plan 2016 Annual Update Prepared for Long Island Power Authority December 29, 2016 Table of Contents Executive Summary... 2 Section 1 Utility 2.0 Plan Filings... 4 1.1. 2014 Filings...

More information

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking 15-03-011 and CAISO ESDER 2 Stakeholder Initiative Issue Paper May 2-3, 2016 April 14, 2016 Table of Contents

More information

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The 1 2 3 4 LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The Transmission Provider will calculate and post the Planning

More information

RATE 665 RENEWABLE FEED-IN TARIFF

RATE 665 RENEWABLE FEED-IN TARIFF NORTHERN INDIANA PUBLIC SERVICE COMPANY Third Revised Sheet No. 104 Superseding Second Revised Sheet No. 104 TO WHOM AVAILABLE No. 1 of 11 Sheets This is a rate that is a voluntary offer available to any

More information

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

ISO New England Available Transfer Capability. Implementation Document. Version 1.0 ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6

More information

The Smart Grid - Constant Energy in a World of Constant Change. Smart Grids and Energy Storage - MicroGrids. Unrestricted

The Smart Grid - Constant Energy in a World of Constant Change. Smart Grids and Energy Storage - MicroGrids. Unrestricted The Smart Grid - Constant Energy in a World of Constant Change Smart Grids and Energy Storage - MicroGrids Answers for infrastructure and cities. Unrestricted 1 What is a MicroGrid? A group of interconnected

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

2017 Distributed Energy Resources (DER) that participate in PJM Markets as Demand Response. PJM Demand Side Response Operations

2017 Distributed Energy Resources (DER) that participate in PJM Markets as Demand Response. PJM Demand Side Response Operations 217 Distributed Energy Resources (DER) that participate in PJM Markets as Demand Response PJM Demand Side Response Operations January, 218 217 Distributed Energy Resources (DER) in PJM Demand Response

More information

MAUI SMART GRID PROJECT

MAUI SMART GRID PROJECT MANAGING DISTRIBUTION SYSTEM RESOURCES FOR IMPROVED SERVICE QUAILTY AND RELIABILTY, TRANSMISSION CONGESTION RELIEF, AND GRID SUPPORT FUNCTIONS MAUI SMART GRID PROJECT or Hawaii Natural Energy Institute

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison Innovation & Grid Modernization at ComEd Laura García García Grid Strategy & Analytics Commonwealth Edison ComEd, An Exelon Company 2 Our Customers: 4 million electric customers in northern Illinois, including

More information

PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, Prepared by Capacity Market Operations

PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, Prepared by Capacity Market Operations PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, 2017 Prepared by Capacity Market Operations PJM 2017 Table of Contents Table of Contents Table of Exhibits...9 Approval...10 Current

More information

2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS

2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS California Independent System Operator 2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS May 3, 2017 Local Capacity Technical Analysis Overview and Study Results I. Executive Summary

More information

Improving the way we price our network services. Consultation paper

Improving the way we price our network services. Consultation paper Improving the way we price our network services Consultation paper October 2015 Table of Contents 1 Overview... 4 2 Background... 6 3 Purpose... 7 4 Network tariff strategy... 7 4.1 Network tariff reform

More information

SAM 3.0 Stakeholder Comment Matrix

SAM 3.0 Stakeholder Comment Matrix SAM 3.0 Stakeholder Comment Matrix The AESO welcomes stakeholder input on the working group provisional recommendations and discussion context contained in Section 5 of SAM 3.0. Please review the following

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

Volatility Prediction and Management by Active Network Management & Future Generation Management. Siemens, Sept 8 th 2017

Volatility Prediction and Management by Active Network Management & Future Generation Management. Siemens, Sept 8 th 2017 Volatility Prediction and Management by Active Network Management & Future Generation Management Siemens, Sept 8 th 2017 Table of contents To follow Current scenario and upcoming challenges in distribution

More information

EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results

EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results EPA s Clean Power Plan Proposal Review of PJM Analyses Preliminary Results Paul Sotkiewicz Chief Economist Muhsin Abdur-Rahman Senior Engineer, Market Simulation Members Committee Webinar November 17,

More information

Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014

Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014 Regional Transmission Organizations D. William VanderLaan Illinois Commerce Commission January 30, 2014 History of Regional Transmission Organizations (RTOs) RTOs grew out of FERC Order Nos. 888/889 where

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1)

Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1) Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1) Date of Last Change to the Provided Information - September 1 st, 2017 Director, Transmission Operations The employee

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the FERC ELECTRIC TARIFF First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 3.1 Nature of Relationship. Each Participating

More information

LMP Calculation and Uplift

LMP Calculation and Uplift LMP Calculation and Uplift Anthony Giacomoni January 29, 2018 PJM 2017 Session Objectives Review fundamentals of locational marginal pricing (LMP) and uplift Review simple locational marginal pricing and

More information

Dynamic Transfers Revised Draft Final Proposal

Dynamic Transfers Revised Draft Final Proposal Dynamic Transfers Revised Draft Final Proposal Provided in Support of 2009-2011 Stakeholder Process to Consider Expansion of Dynamic Transfer Services in ISO Tariff Revised February 18, 2011 CAISO/M&ID/Dynamic

More information

CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA.

CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA. CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA. National Energy Regulatory Agency ANRE Kiev, Jun 2013 Sector challenges Lack of own energy resources (natural gas, oil, coal);

More information

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Evolution of Con Edison efforts in Energy Efficiency and Demand Management: Innovative programs and technologies, and their impacts on customers, contractors and the markets Con Edison Con Edison - Overview

More information

CAISO s Plan for Integration of Renewable Resources

CAISO s Plan for Integration of Renewable Resources CAISO s Plan for Integration of Renewable Resources July 21, 2008 CEC 33% Renewables Workshop Presented by David Hawkins Program Tracks 2008-9 CAISO Work Plan Track 1 - Develop Operational Tools Wind and

More information

Business Practice Manual for Market Operations

Business Practice Manual for Market Operations Business Practice Manual for Market Operations Version 4748 Revised: July 19, 2016September 1, 2016 Page 1 of 326 Approval History Approval Date: March 23, 2009 Effective Date: March 31, 2009 BPM Owner:

More information

Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead

Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead Harvard Electricity Policy Group 68 th Plenary Session Paul M. Sotkiewicz, Ph.D. Chief Economist PJM Interconnection October

More information

Fundamentals of Transmission Operations

Fundamentals of Transmission Operations Fundamentals of Transmission Operations Equipment Outages PJM State & Member Training Dept. Objectives At the end of this presentation the Learner will be able to: Identify how weather may influence outage

More information

Dynamic Price, Product and Messaging Specification

Dynamic Price, Product and Messaging Specification 1 2 3 4 5 6 7 8 9 Retail Dynamic Price, Product and Messaging Specification (DRAFT -2) Draft Memo to OASIS Energy Interoperation TC by Ed Cazalet (original Sept 10, 2009, updated October 11, 2009) During

More information

Demand Response and Scarcity Pricing

Demand Response and Scarcity Pricing Item #/ Check When Complete Demand and Scarcity Pricing Begin End Category Sub-Category Order 719 Summary Draft Status SPP Notes References Assignment 41 47 63 Demand Allow DR to provide ancillary services

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144 Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of

More information

Fundamentals of Transmission Operations

Fundamentals of Transmission Operations Fundamentals of Transmission Operations Telecommunications PJM State & Member Training Dept. PJM 2014 9/10/2013 Objectives The student will be able to: Explain the back-up satellite phone testing requirements

More information

Session 1 DER Integration and Grid control

Session 1 DER Integration and Grid control Workshop Smart Grid Standardisation May 16th 2013 Session 1 DER Integration and Grid control Giorgio Franchioni RSE Italy The EU strategy and the proliferation of DERs EU 2020 Strategy Energy-Climate Targets

More information

Load Management Performance Report 2015/2016

Load Management Performance Report 2015/2016 Load Management Performance Report 2015/2016 August 2016 PJM has made all efforts possible to accurately document all information in this report. However, PJM cannot warrant or guarantee that the information

More information

Energy Imbalance Market Overview

Energy Imbalance Market Overview Energy Imbalance Market Overview Presentation to: Portland General Electric EIM OATT Stakeholder Meeting David Timson Account Manager CAISO Strategic Alliances October 14, 2016 Topics for Discussion ISO

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 No. 4120 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1 Background... 3 2.2 Scope/ Applicability... 4 3. PROCEDURE DETAIL... 4 3.1 General Information... 4 3.2

More information

Presentation on Draft SCED RFP

Presentation on Draft SCED RFP Presentation on Draft SCED RFP Pre-RFP Release Conference October 9, 2014 Presenters: Eric Espenhorst, Seattle City Light Erin Apperson, Puget Sound Energy Robb Davis, BPA Roger Bentz, BPA Kevin Holland,

More information

Considerations in Microgrid Control and Communications

Considerations in Microgrid Control and Communications 1 Considerations in Microgrid Control and Communications Al Valdes Managing Director, Smart Grid Technologies University of Illinois at Urbana-Champaign With contributions from Frank Borth, Alejandro Dominguez-Garcia,

More information