FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER

Size: px
Start display at page:

Download "FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER"

Transcription

1 FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER 31 st May 2010 Disclaimer This document has been prepared and made available solely for information purposes and consultation under the National Electricity Rules. It has been prepared with all due care and skill for the purposes of the National Electricity Rules and nothing in this document can be or should be taken as a recommendation in respect of any possible investment. This document does not purport to contain all of the information that a prospective investor or participant or potential participant in the NEM, or any other person or interested parties may require. In preparing this document, it is not possible nor is it intended for EnergyAustralia to have regard to the investment objectives, financial situation and particular needs of each person who reads or uses this document. In all cases, anyone proposing to rely on or use the information in this document should independently verify and check the accuracy, completeness, reliability and suitability of that information and the reports and other information relied on by EnergyAustralia in preparing this document, and should obtain independent and specific advice from appropriate experts or other sources. Accordingly, Energy Australia make no representations or warranty as to the accuracy, reliability, completeness or suitability for particular purposes of the information in this document other than for the regulatory purposes of the National Electricity Rules. EnergyAustralia and its employees, agents and consultants shall have no liability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or implied) arising out of, contained in or derived from, or for any omissions from, the information in this document, except insofar as liability under any New South Wales and Commonwealth statute cannot be excluded

2 TABLE OF CONTENTS EXECUTIVE SUMMARY INTRODUCTION Purpose and Scope Background IDENTIFICATION OF NEED FOR AUGMENTATION Applied Service Standard Subtransmission Substations (Urban/Non-Urban) Zone Substations and Overhead Lines (Urban/Non-Urban) Underground Sub-transmission Cables (Urban/Non-Urban) Description of Network Constraints Capacity Issues at Green Square Zone Substation Asset Condition Issues Applicable National Electricity Rules Requirements OPTIONS Demand Management Installation of a 3 rd transformer at Green Square zone substation ECONOMIC ANALYSIS OF OPTIONS CONCLUSION APPENDIX A ECONOMIC ANALYSIS OF BASE CASE...10 Page 2 of 10

3 EXECUTIVE SUMMARY This paper has been prepared to report on the assessment of options for the compliance of the Green Square load area within EnergyAustralia s Eastern Suburbs electricity supply network, in accordance with clause (h) of the National Electricity Rules (the Rules). The work proposed by this report involves augmentation expenditure of under $10 million and is regarded by the Rules as a new small dual-function network asset. Accordingly, EnergyAustralia has not previously consulted on this project. The Green Square Zone additional transformer is classified as a dual-function asset under Chapter 6 of the National Electricity Rules (rules). The rules (clauses and 5.6.6) requires that, where analysis indicates that any relevant technical limits of a distribution system will be exceeded, the Distribution Network Service Provider must notify any affected Registered Participants of these limitations and the expected time for corrective action and consult with affected Registered Participants and interested parties on possible options to address the projected limitations. The timing of the proposed work is primarily driven by the need to address upcoming load constraint and would thus be regarded as a reliability augmentation project. Substantial load growth in the Green Square load area has resulted in a capacity constraint at Green Square 132/11kV zone substation (ZS). To ensure a safe and reliable electricity supply for existing customers, EnergyAustralia is providing additional capacity to meet forecast load demands and mitigate energy at risk. The provision of additional capacity is required to meet network performance requirements set by EnergyAustralia in accordance with Schedule 5.1 of the Rules. This report covers the following issues: Section 1 of the paper provides a description of the Green Square load area. Section 2 presents EnergyAustralia s service standards for the area and describes, in detail, the nature of the load growth in the area, the issues affecting the supply network in the area and the need for augmentation of supply to the area. Section 3 outlines the possible options to address the issues affecting the supply network including options for supply system development. A build and a non-build option are described: Demand Management Installation of a 3 rd transformer at Green Square ZS Section 4 presents the results of economic analysis of the supply side options considered. Section 5 concludes that the most cost effective strategy within the regulatory test is the option of Installation of a 3 rd transformer at Green Square ZS. EnergyAustralia s recommended action is to upgrade Green Square ZS by installing a 3rd transformer at an estimated cost of $3.95 million. This recommendation is made based on the least cost test to provide additional capacity for the upcoming load constraint. Page 3 of 10

4 1. INTRODUCTION 1.1. Purpose and Scope This Final Report has been prepared to meet the requirements of clause (h) of the Rules and to advise registered participants and interested parties on specific development work proposed by EnergyAustralia for its Eastern Suburbs electricity supply area. It includes: A discussion of supply system limitations identified by EnergyAustralia that have led to the necessity of identifying possible options for augmentation of the distribution network in the area; A discussion of the service standard that has been adopted for planning purposes; A description of options identified for development of the electricity supply in the area; and A detailed cost effectiveness analysis of each of these options, carried out in accordance with the requirements of the regulatory test Background The Eastern Suburbs load area extends from Surry Hills in the north-west, south to Bunnerong North and west as far as Marrickville. The Eastern Suburbs network is supplied from the inner metropolitan transmission network at Surry Hills Sub-transmission Substation (STS), Bunnerong STS and from TransGrid s Beaconsfield West Bulk Supply Point (BSP). It includes 132kV and 33kV assets and with twenty substations, it is one of the largest network areas in EnergyAustralia s franchise area. Page 4 of 10

5 Figure 1 below is a geographic diagram of the Eastern Suburbs area. Figure 1: Eastern Suburbs Load Area Green Square 132/11kV ZS is located in the central portion of the Eastern Suburbs supply area and is currently supplied by Beaconsfield West BSP. Figure 2 below indicate the schematic overview of the area. Figure 2: System Diagram around Green Square Zone Substation Page 5 of 10

6 2. IDENTIFICATION OF NEED FOR AUGMENTATION 2.1. Applied Service Standard EnergyAustralia is required to comply with service standards that are specified in the Design, Reliability and Performance Licence Conditions (Licence Conditions), which were imposed on NSW distributors by the Minister for Energy on 1 October The design planning criteria are specified in Schedule 1 of the Licence Conditions and reliability standards are specified in Schedules 2 and 3. For existing network, a distributor must be as compliant as practicable with these requirements by 1 July 2014 and fully compliant by 1 July All new network elements must comply with these requirements. The service standards that are applicable to a consideration of supply constraints affecting the Green Square load area are summarised below. For further details refer to the Licence Conditions or to EnergyAustralia s Network Management Plan Subtransmission Substations (Urban/Non-Urban) With all elements in service, the thermal capacity is required to meet at least 115% of forecast demand. For a failure of a single critical element (i.e. N-1 conditions) within a subtransmission substation, the forecast demand is not to exceed the thermal capacity. Recovery of load should be within one minute Zone Substations and Overhead Lines (Urban/Non-Urban) With all elements in service, the thermal capacity is required to meet at least 115% of forecast demand. Following a failure of a single critical element (i.e. N-1 conditions), the network must be designed to recover supply within one minute for systems supplying >10MVA, and otherwise, within best practice repair times. For systems that supply >10MVA, the forecast demand of a zone substation or overhead feeder network may exceed the N-1 capacity for up to 1% of the year i.e. a total aggregate time of 88 hours per annum, up to a maximum of 20% above the N-1 capacity Underground Sub-transmission Cables (Urban/Non-Urban) The forecast demand of an underground feeder network may not exceed the N-1 capacity at any time Description of Network Constraints Load Forecast EnergyAustralia has previously published details of its load forecasts and the timing of loads exceeding technical limits of the system in its Annual Electricity System Development Review. The load forecast includes committed spot loads and normal levels of load growth. The timing of the constraint for Green Square ZS is shown below and is based on the forecast projected from the summer 2008/09 and winter 2009 actual loads Capacity Issues at Green Square Zone Substation Green Square Zone Substation is forecast to exceed its licence capacity by 5.6 MVA in summer 2011/12 and 17.5 MVA in summer 2012/13. Diagram below shows the load forecast of Green Square Zone Substation. Page 6 of 10

7 Green Square Zone Substation (based on actuals from Summer 2008/09 & Winter 2009) Actuals Forecast MVA Year Winter Load Winter Limit Summer Load Summer Limit '04 '05 '06 '07 '08 '09 '10 '11 '12 '13 '14 '15 '16 Actual Forecast Winter Load Limit Summer 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16 Load Limit (Note: Green Square ZS was commissioned in November 2005.) Asset Condition Issues 11kV compound switchgear at neighbouring Mascot Zone has been prioritised for replacement by The 33kV HSL feeders 328, 332, 360, and 337 between Bunnerong STSS and Mascot Zone are required to be replaced. Feeder 337 is planned for retirement by Feeders 328,332 & parts of 360 are to be replaced before Reconstruction of Mascot Zone to 132/11kV is driven primarily by condition of 11kV switchgear. The replacement will also address the 33kV cable condition issues. Significant 11kV load transfer from Mascot to Green Square is required to facilitate the reconstruction of Mascot Zone. The proposed completion date of Mascot Zone reconstruction is planned to be December Page 7 of 10

8 2.3. Applicable National Electricity Rules Requirements Green Square ZS and its associated transformers are classified as dual-function system assets by the National Electricity Rules (the Rules). The proposed development strategy for the Green Square ZS involves expenditure of less than $10 million which is regarded by the Rules as a small dual-function network asset. The new capacity provided by the proposed work will be used to address upcoming load constraint and would thus be considered a growth driven augmentation. EnergyAustralia has analysed the cost-effectiveness and feasibility of a range of options to resolve the load constraint at Green Square ZS. 3. OPTIONS EnergyAustralia has identified four Area Plan strategies for the Eastern Suburbs load area. The transformer installation project at Green Square is common across all analysed supply strategies. In accordance with this, a build and a non-build option were considered, these two options are described below Demand Management A Demand Management screening test was carried out in November 2009, investigating for any demand management solution to defer the 3rd transformer installation at Green Square ZS. The Demand Management screening test concluded that the 3rd transformer installation at Green Square ZS could not be cost effectively deferred due to the level of load growth at the Green Square load area Installation of a 3 rd transformer at Green Square zone substation This option involves installation of the 3rd 50MVA transformer in Green Square ZS, which will increase its license capacity to 126MVA. The total capital cost of this work is estimated to be $3.95M, with a NPC of $3.86M. This project is expected to be completed by summer 2011/12, hence enabling compliance in summer 2011/ ECONOMIC ANALYSIS OF OPTIONS An economic analysis has been carried out for the period 2009/10 to 2018/19. It involves the comparison of options by carrying out a Net Present Costs (NPC) analysis. An economic analysis of base case is shown in Appendix A. Four supply strategies were identified and analysed for the Eastern Suburbs load area. This project of installing a 3rd transformer is common across all four supply strategies in the Eastern Suburbs load area as per the 2009 to 2014 Regulatory Determination, and there is no other viable alternative option. Page 8 of 10

9 Sensitivity analysis of the base case was considered, however it is not presented due to the fact that there is only one viable option, and this option is common to all strategies. 5. CONCLUSION EnergyAustralia intends to upgrade Green Square ZS by installing a 3rd transformer at an estimated cost of $3.95M. The transformer installation project at Green Square is common across all four supply strategies in the Eastern Suburbs load area. There is no other viable alternative option. This work is forecast to be completed by Oct This service availability date may change if the project is affected by circumstances beyond EnergyAustralia's control, such as changes in the timing of customer load increases or other issues such as: delays in the approval process, equipment supply difficulties, unforeseen technical constraints, acts of God, and industrial action. Page 9 of 10

10 6. APPENDIX A ECONOMIC ANALYSIS OF BASE CASE Discount Rate 8.5% NPC ($k) Total ($k) 2009/ / / / / / / / / /2019 3rd Tx at Green Square 3,642 3, , O&M Total 3,863 3, , Note: The estimates are based on 2009/10 real dollars ($k) Page 10 of 10

Addressing reliability requirements in the Flemington substation load area

Addressing reliability requirements in the Flemington substation load area Addressing reliability requirements in the Flemington substation load area Notice on screening for non-network options May 2018 Title of Contents DISCLAIMER... 1 1 INTRODUCTION... 2 2 FORECAST LOAD AND

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Final Report Emerging Distribution Network Limitations in the Central Toowoomba Area 16 May 2013 Disclaimer While care was taken in preparation of the information in this

More information

SUPPLY TO SYDNEY CBD AND INNER SUBURBS: FINAL COST EFFECTIVENESS ANALYSIS EXECUTIVE SUMMARY. Final Report for TransGrid and EnergyAustralia

SUPPLY TO SYDNEY CBD AND INNER SUBURBS: FINAL COST EFFECTIVENESS ANALYSIS EXECUTIVE SUMMARY. Final Report for TransGrid and EnergyAustralia SUPPLY TO SYDNEY CBD AND INNER SUBURBS: FINAL COST EFFECTIVENESS ANALYSIS EXECUTIVE SUMMARY Final Report for TransGrid and EnergyAustralia Prepared by NERA February 2000 Sydney Project Team: Greg Houston

More information

Ergon Energy Corporation Limited 4 June 2010

Ergon Energy Corporation Limited 4 June 2010 Ergon Energy Corporation Limited 4 June 2010 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation Limited

More information

RIT-T: Project Specification Consultation Report. Powering Sydney s Future

RIT-T: Project Specification Consultation Report. Powering Sydney s Future RIT-T: Project Specification Consultation Report Powering Sydney s Future 11 October 2016 1. Executive Summary Powering Sydney - now and into the future A reliable, affordable and sustainable electricity

More information

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report Draft Project Assessment Report RIT-D Report This report presents the network limitations at Dromana zone substation and the distribution feeder network within the Dromana / Mornington supply areas, including

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY

More information

Powering Sydney s Future. TransGrid 330kV Cable Route Selection Process Summary

Powering Sydney s Future. TransGrid 330kV Cable Route Selection Process Summary Powering Sydney s Future TransGrid 330kV Cable Route Selection Process Summary Contents Contents... 2 1. Executive summary... 3 2. Drivers for the project... 3 3. Options considered... 3 4. 330kV cable

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

ELECTRICITY STATEMENT OF OPPORTUNITIES For the National Electricity Market

ELECTRICITY STATEMENT OF OPPORTUNITIES For the National Electricity Market ELECTRICITY STATEMENT OF OPPORTUNITIES For the National Electricity Market EXECUTIVE BRIEFING 2010 Preface I am pleased to introduce AEMO s 2010 Electricity Statement of Opportunities (ESOO), which presents

More information

TRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018

TRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018 TRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: May

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared

More information

GENERATION EXPANSION PLAN FOR THE 2014 NATIONAL TRANSMISSION NETWORK DEVELOPMENT PLAN

GENERATION EXPANSION PLAN FOR THE 2014 NATIONAL TRANSMISSION NETWORK DEVELOPMENT PLAN GENERATION EXPANSION PLAN FOR THE 2014 NATIONAL TRANSMISSION NETWORK DEVELOPMENT PLAN Published: December 2014 Disclaimer AEMO has made every effort to ensure the quality of the information in this publication

More information

Customer Capital Contributions Policy

Customer Capital Contributions Policy TasNetworks Customer Capital Contributions Policy Effective 1 July 2014 Tasmanian Networks Pty Ltd ABN 24 167 357 29 Page 1 of 25 Tasmanian Networks Pty Ltd ABN 24 167 357 299 1-7 Maria Street Lenah Valley

More information

TasNetworks Distribution Connection Pricing Policy Final AER approved Commencing 1 July 2017

TasNetworks Distribution Connection Pricing Policy Final AER approved Commencing 1 July 2017 TasNetworks Distribution Connection Pricing Policy Final AER approved Commencing 1 July 2017 Page 1 of 54 Copyright This document is protected by copyright vested in Tasmanian Networks Pty Ltd. No part

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

Powering Sydney s Future Project Assessment Draft Report Summary

Powering Sydney s Future Project Assessment Draft Report Summary This is the second stage of the formal RIT-T process for Powering Sydney s Future. A reliable, affordable and sustainable electricity supply is essential for our way of life. If you live, work or operate

More information

Black Start Procurement Methodology

Black Start Procurement Methodology Issue 1 Revision Black Start Procurement Methodology Produced in accordance with Standard Condition C16 of the National Grid Transmission Licence Effective from 1 st April 2017 to 31 st March 2018 DOCUMENT

More information

Ergon Energy Corporation Limited 12 November 2009

Ergon Energy Corporation Limited 12 November 2009 Ergon Energy Corporation Limited 12 November 2009 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation

More information

GUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION

GUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION Level 2, 35 Spring St Melbourne 3000, Australia Telephone +61 3 9651 0222 +61 3 1300 664 969 Facsimile +61 3 9651 3688 GUIDANCE PAPER: FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE N JURISDICTION 14 FEBRUARY

More information

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further

More information

Lower Mornington Peninsula Supply Area

Lower Mornington Peninsula Supply Area Final Project Assessment Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including the preferred option to address those limitations.

More information

Water NSW Reporting Manual

Water NSW Reporting Manual Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968

More information

FY18 RESULTS PRESENTATION

FY18 RESULTS PRESENTATION FY18 RESULTS PRESENTATION DISCLAIMER This presentation has been prepared by rhipe Limited ACN 112 452 436 (RHP). Each Recipient of this presentation is deemed to have agreed to accept the qualifications,

More information

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 Published: July 2017 IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 3.13.6A(a) of the National Electricity

More information

Interconnection System Feasibility Study

Interconnection System Feasibility Study Interconnection System Feasibility Study Zonnebeke Wind Project Report No: T&S Planning 2015-053 November 2015 FINAL British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority

More information

INFORMATION RELEASE. TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates

INFORMATION RELEASE. TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates INFORMATION RELEASE TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates OVERVIEW This Information Release is intended to provide an overview of the transmission constraints

More information

Ring Fencing Guideline

Ring Fencing Guideline Ring Fencing Guideline Issue number 1 Status Final Date of approval 20/12/2017 Disclaimer This template is for generating internal and external document belonging to AusNet Services and may or may not

More information

National Electricity Market Demand Forecasting Methodology. November Issues Paper

National Electricity Market Demand Forecasting Methodology. November Issues Paper National Electricity Market Demand Forecasting Methodology November 2018 Issues Paper Important notice PURPOSE The publication of this Issues Paper commences AEMO s consultation on the effectiveness of

More information

Lower Mornington Peninsula Supply Area

Lower Mornington Peninsula Supply Area Non Network Options Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including options and technical characteristics of non-network options

More information

Outage Protocol: Explanatory note

Outage Protocol: Explanatory note Outage Protocol: Explanatory note This is the version of the outage protocol (previously in section VII of part F of the Electricity Governance Rules 2003) that the Authority is required to publish by

More information

Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19

Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19 Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19 Date: 19 October 2015 Prepared by: Regulation and Investment Management DM 12392512 Contents Introduction... 2 1.1 Revised

More information

Regulatory 4 March 2011Test - Request for Information

Regulatory 4 March 2011Test - Request for Information Ergon Energy Corporation Limited Regulatory 4 March 2011Test - Request for Information Emerging Distribution Network Limitations in the South Mackay Area 28 October 2013 Ergon Energy Corporation Limited

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Request for Information Emerging Distribution Network Limitations in the Palm Island Area 1 May 2012 Disclaimer While care was taken in preparation of the information in

More information

DEMAND SIDE PARTICIPATION 2016 NATIONAL ELECTRICITY FORECASTING REPORT

DEMAND SIDE PARTICIPATION 2016 NATIONAL ELECTRICITY FORECASTING REPORT 2016 NATIONAL ELECTRICITY FORECASTING REPORT Published: September 2016 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about estimated demand side participation in the National

More information

18,000+ ACTIVE USERS. AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE

18,000+ ACTIVE USERS. AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE 18,000+ ACTIVE USERS AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE A Leading Payment Solutions & Technology Partner In Asia-Pacific SOUTH EAST ASIA 2 Our Markets $120B Singapore retail & online

More information

For personal use only 18,000+ ACTIVE USERS $600M+ TRANSACTION VALUE. AGM PRESENTATION November 2017

For personal use only 18,000+ ACTIVE USERS $600M+ TRANSACTION VALUE. AGM PRESENTATION November 2017 18,000+ ACTIVE USERS AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE A Leading Payment Solutions & Technology Partner In Asia-Pacific SOUTH EAST ASIA 2 Our Markets $120B Singapore retail & online

More information

Methodology & Learning Report. Work package 2.1: Dynamic thermal rating of assets Primary Transformers

Methodology & Learning Report. Work package 2.1: Dynamic thermal rating of assets Primary Transformers Flexible Networks for a Low Carbon Future Methodology & Learning Report Work package 2.1: Dynamic thermal rating of assets Primary Transformers May 2015 Contents 1 Executive Summary 2 2 Background 3 3

More information

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS

NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS PREPARED BY: AEMO Markets and Strategy & Innovation VERSION: 2.2 EFFECTIVE DATE: 20 March 2018 STATUS: FINAL

More information

OTHERLEVELS HOLDINGS LIMITED JANUARY 2018 INVESTOR UPDATE

OTHERLEVELS HOLDINGS LIMITED JANUARY 2018 INVESTOR UPDATE OTHERLEVELS HOLDINGS LIMITED JANUARY 2018 INVESTOR UPDATE Execution In H1 FY18 Platform Investment Positive Operating Cash Flow Core strategy Customer Growth Positive Operating Cash Flow Record cash receipts

More information

MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN

MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN APPLICATION NOTICE (ABN 41 094 482 416) December 2007 COPYRIGHT ElectraNet - All Rights Reserved This document is protected by copyright vested in

More information

Dalrymple Substation Upgrade

Dalrymple Substation Upgrade Dalrymple Substation Upgrade RIT-T: Project Assessment Conclusions Report Version 1 ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

System Impact Study for. 1 January January 2016

System Impact Study for. 1 January January 2016 System Impact Study for OASIS 72401305 Long-term Point to Point Transmission Service Request On the LM BPAT Path 1 January 2011 1 January 2016 Report No: SPPA2009-113 May 2009 System Planning & Performance

More information

Invitation for Expression of Interest to provide Flexible Services 3 April 2018

Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Flexible Services Expression of Interest/3 April 2018 Page 1 of 21 VERSION HISTORY Version Date Author Status Comments 1.0

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

EVALUATION REPORT RFP-ER 005/06

EVALUATION REPORT RFP-ER 005/06 EVALUATION REPORT RFP-ER 005/06 On reinforcement options to address projected network constraints described in RFP 005/06 Projected Distribution Network constraints: Electricity Supply to the Wudinna to

More information

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18 Demand Side Engagement Strategy Version 2.0 Effective Date: 08/02/18 Document management Version control Date Version Description Author 16/07/2013 0.1 Initial Draft. Y. Jayathilaka 23/07/2013 0.2 Revised

More information

CitiPower Amended Revised Proposed Tariff Structure Statement

CitiPower Amended Revised Proposed Tariff Structure Statement CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 This page is intentionally left blank. 2 CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 Table of Contents

More information

Australia s leading magnetite producer Southdown Magnetite Project. Russell Clark Managing Director & CEO February 2012

Australia s leading magnetite producer Southdown Magnetite Project. Russell Clark Managing Director & CEO February 2012 Australia s leading magnetite producer Southdown Magnetite Project Russell Clark Managing Director & CEO February 2012 Disclaimer The material in this presentation ( material ) is not and does not constitute

More information

Community and Stakeholder Consultation Report. Powering Sydney s Future

Community and Stakeholder Consultation Report. Powering Sydney s Future Community and Stakeholder Consultation Report Powering Sydney s Future Early Engagement July 2017 1. Executive Summary Powering Sydney s Future (the Project) aims to secure a reliable, safe and economical

More information

CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5)

CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5) CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5) 1. PURPOSE AEMO has prepared this document to clarify AEMO s interpretation of particular clauses in Schedule 5.2 of the National

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information

MANAGING THE RISK OF TRANSFORMER BUSHING FAILURE

MANAGING THE RISK OF TRANSFORMER BUSHING FAILURE MANAGING THE RISK OF TRANSFORMER BUSHING FAILURE 11 December 2018 Copyright and Disclaimer Copyright in this material is owned by or licensed to ElectraNet. Permission to publish, modify, commercialise

More information

The Stock Exchange of Hong Kong Limited. Practice Note 21

The Stock Exchange of Hong Kong Limited. Practice Note 21 The Stock Exchange of Hong Kong Limited Practice Note 21 to the Rules Governing the Listing of Securities (the Exchange Listing Rules ) Issued pursuant to rule 1.06 of the Exchange Listing Rules DUE DILIGENCE

More information

Waypoints Sequence Extension API

Waypoints Sequence Extension API Waypoints Sequence Extension API Release Notes Version 2.0.0 Waypoints Sequence Extension API Release Notes 2 Contents Contents Legal Notices...3 Document Information... 4 Overview...5 Known Issues...

More information

Performance Reporting Criteria

Performance Reporting Criteria Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5

More information

Project Specification Consultation Report

Project Specification Consultation Report Project Specification Consultation Report 8 May 2018 Addressing the secondary systems condition risks at Dan Gleeson Substation Disclaimer While care was taken in preparation of the information in this

More information

BIG UNLIMITED FY18 Q1 4C UPDATE OCT 2017

BIG UNLIMITED FY18 Q1 4C UPDATE OCT 2017 BIG UNLIMITED FY18 Q1 4C UPDATE OCT 2017 WHAT IS BIG BIG (ASX: BIG) is the parent company of Big Review TV Ltd. Big Review TV are innovative disruptors in the online video space. They are a video driven

More information

18/05/2018. Mr John Pierce Chair Australian Energy Market Commission PO Box A2449 Sydney NSW Lodged online via:

18/05/2018. Mr John Pierce Chair Australian Energy Market Commission PO Box A2449 Sydney NSW Lodged online via: ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/05/2018 Mr John Pierce Chair Australian Energy Market Commission PO Box A2449

More information

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS.

A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. Date of issue 27/01/2017 Date of next review 29/01/2018 Page 1 V4 18/07/2018 CONTENTS CONTENTS... 2 WORKING SAFELY...

More information

Distribution - Reset RIN, Basis of Preparation

Distribution - Reset RIN, Basis of Preparation L Distribution - Reset RIN, 2019-2024 Basis of Preparation Introduction TasNetworks (Tasmanian Networks Pty Ltd, ABN 24 167 357 299) is the owner and operator of the electricity distribution network in

More information

Audit and Review Guidelines: Electricity and Gas Licences

Audit and Review Guidelines: Electricity and Gas Licences Audit and Review Guidelines: Electricity and Gas Licences April 2014 This document is available from the Economic Regulation Authority s website at www.erawa.com.au. For further information, contact: Economic

More information

TENDER AND EVALUATION PROCESS FOR CONTESTABLE AUGMENTATIONS

TENDER AND EVALUATION PROCESS FOR CONTESTABLE AUGMENTATIONS TENDER AND EVALUATION PROCESS FOR CONTESTABLE AUGMENTATIONS PREPARED BY: Transmission Services Department VERSION: 1 RELEASE DATE: 1 July 2010 Au1hol,an Enargy Marla! ap.rotr:w lkl A~N o,. 012 010 321

More information

Nova Scotia Power System Operator (NSPSO)

Nova Scotia Power System Operator (NSPSO) Nova Scotia Power System Operator (NSPSO) Market Procedure MP-09 Outage Planning and Approval Effective Date: 2008 12 31 Wholesale Market Procedure MP-09 Table of Contents Page 1 Document Control and General

More information

Network Support and Control Ancillary Service (NSCAS) Quantity Procedure

Network Support and Control Ancillary Service (NSCAS) Quantity Procedure Network Support and Control Ancillary Service (NSCAS) Quantity Procedure PREPARED BY: PLANNING VERSION: 1.0 DATE: 12 DECEMBER 2011 FINAL This document has been created by the Planning Department and will

More information

ENERGEX Network Management Plan Part A 2008/09 to 2012/13 FINAL

ENERGEX Network Management Plan Part A 2008/09 to 2012/13 FINAL Part A 2008/09 to 2012/13 FINAL ENERGEX Limited, Australia This work is copyright. Material contained in this document may be reproduced for personal, in-house or noncommercial use, without formal permission

More information

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT LOW POWER FACTOR AT WINGHAM TS ASSESSMENT Date: October 18 th, 2016 Prepared and Reviewed by: Sacha Constantinescu, P.Eng Transmission Planner System Planning Jerry Vo Distribution Planner Distribution

More information

Ancillary Service. the WEM System Management. June 2018

Ancillary Service. the WEM System Management. June 2018 Ancillary Service Report for the WEM 2018-19 June 2018 System Management Important notice PURPOSE AEMO publishes the Wholesale Electricity Market Ancillary Services report under clause 3.11.13 of the Wholesale

More information

Service Standards for Western Power Corporation s South West Interconnected System

Service Standards for Western Power Corporation s South West Interconnected System Service Standards for Western Power Corporation s South West Interconnected System Report prepared for Economic Regulation Authority Western Australia Contents 1 Executive summary 3 2 Introduction 7 2.1

More information

Fringe-of-Grid PV Projects - Normanton Solar Farm

Fringe-of-Grid PV Projects - Normanton Solar Farm Fringe-of-Grid PV Projects - Normanton Solar Farm All-Energy Conference 2016 October 5, 2016 Josh Currah Project Manager, Energy Business www.canadiansolar.com Safe Harbor Statement This presentation has

More information

Transmission System Security and Planning Standards

Transmission System Security and Planning Standards ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2

More information

Environmental impact methodology

Environmental impact methodology Environmental impact methodology For US professional investors only - June 2016 Second edition 1 Environmental impact methodology for the 2 Scope and reporting boundaries 3 Methodology 4 Exclusions and

More information

How to set up a sewer mining scheme

How to set up a sewer mining scheme Sewer Mining How to set up a sewer mining scheme With a growing population and highly variable rainfall over the catchments, water recycling is making an increasingly important contribution to our water

More information

PRELIMINARY REVENUE PROPOSAL

PRELIMINARY REVENUE PROPOSAL PRELIMINARY REVENUE PROPOSAL 2019-2023 ElectraNet // September 2016 Preliminary Revenue Proposal 2019-2023 // Page 2 This Preliminary Revenue Proposal is intended to promote effective early engagement

More information

WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION

WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION PREPARED BY: AEMO Operations Department Systems Performance & Commercial VERSION: 1.0 EFFECTIVE DATE: 5 October 2018 STATUS:

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Flemington Zone Substation RIT-D Stage 2: Draft Project Assessment Report Public 16 December 2016 An appropriate citation for this paper is: Flemington Zone Substation

More information

Changes to the MCR &Tips for Implementation: The Minimum Competency Code 2011 Lisa Knox Enterprise Risk Services 17 November 2011

Changes to the MCR &Tips for Implementation: The Minimum Competency Code 2011 Lisa Knox Enterprise Risk Services 17 November 2011 Changes to the MCR &Tips for Implementation: The Minimum Competency Code 2011 Lisa Knox Enterprise Risk Services 17 November 2011 Overview Background CBI Themed Inspections - Lessons Learned Key Changes

More information

The Role of Transmission System Operator in the Context of Energy Security the Case of Poland

The Role of Transmission System Operator in the Context of Energy Security the Case of Poland The Role of Transmission System Operator in the Context of Energy Security the Case of Poland Waldemar Dolega Institute of Electrical Power Engineering; The Wroclaw University of Technology Wroclaw, Poland

More information

NEM EVENT SCHEDULING ERROR INTERMITTENT AGC FAILURES DECEMBER 2012

NEM EVENT SCHEDULING ERROR INTERMITTENT AGC FAILURES DECEMBER 2012 NEM EVENT SCHEDULING ERROR INTERMITTENT AGC FAILURES DECEMBER PREPARED BY: Market Operations and Performance DOCUMENT REF: NEM ER 13/001 DATE: 19 March 2013 FINAL Legal Notices Disclaimer This document

More information

Submission to the Economic Regulation Authority

Submission to the Economic Regulation Authority Submission to the Economic Regulation Authority APPROVAL OF NEW FACILITIES INVESTMENT Installation of a second 330/132 kv transformer at Kemerton Terminal and construction of a 132 kv transmission line

More information

XXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan

XXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan XXXXX Bremner Trio Small Hydro Project Interconnection Facilities Study and Project Plan June 25, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights

More information

For personal use only

For personal use only Go to View / Master / Slide Master. Insert, position and crop pictures on this Master Slide behind Vision Graphic element. MASTERMYNE GROUP AGM OPERATIONS UPDATE NOVEMBER 2017 www.mastermyne.com.au Overview

More information

ELECTRICITY SUPPLY - POWER QUALITY AND RELIABILITY Code of Practice

ELECTRICITY SUPPLY - POWER QUALITY AND RELIABILITY Code of Practice ICS 29.240:03.120 Zambian Standard ELECTRICITY SUPPLY - POWER QUALITY AND RELIABILITY Code of Practice Part 2: Measurement and Reporting Procedures ZAMBIA BUREAU OF STANDARD DATE OF PUBLICATION This Zambian

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q195 74.9 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Electricity Market Design Principles

Electricity Market Design Principles Electricity Market Design Principles Identifying long-term market design principles to support a sustainable energy future for Australia Executive Summary 19 April 2018 KPMG.com.au Important Notice If

More information

Future Matters US Disclosure

Future Matters US Disclosure Disclaimer This presentation has been prepared by Samsung Electronics Co., Ltd. (the "Company"). It does not purport to contain all the information that a prospective investor may require in connection

More information

POWERNET LIMITED LINE PRICING METHODOLOGY

POWERNET LIMITED LINE PRICING METHODOLOGY POWERNET LIMITED LINE PRICING METHODOLOGY FOR THE ELECTRICITY INVERCARGILL LIMITED NETWORK AS AT 1 APRIL 2018 THE ELECTRICITY INVERCARGILL LIMITED NETWORK AS AT 1 APRIL 2018 TABLE OF CONTENTS 1. GLOSSARY

More information

Jemena Gas Networks (NSW) Ltd

Jemena Gas Networks (NSW) Ltd Jemena Gas Networks (NSW) Ltd 2015-20 Access Arrangement Information Rule considerations in setting network tariffs Public 30 June 2014 TABLE OF CONTENTS TABLE OF CONTENTS 1. Introduction... iv 2. Stand-alone

More information

Ancillary Services Fee Based Services Application and Price Guide

Ancillary Services Fee Based Services Application and Price Guide Ancillary Services Fee Based Services Application and Price Guide 2018-19 As approved by the Australian Energy Regulator Disclaimer TasNetworks (which, for the purposes of this disclaimer, includes all

More information

DATA AND MODEL REQUIREMENTS FOR GENERATING SYSTEMS OF LESS THAN 30 MW

DATA AND MODEL REQUIREMENTS FOR GENERATING SYSTEMS OF LESS THAN 30 MW DATA AND MODEL REQUIREMENTS FOR GENERATING SYSTEMS OF LESS THAN 30 MW PREPARED BY: Network Models Systems Capability VERSON: Final DATE: 28 June 2013 Australian Energy Market Operator Ltd ABN 94 072 010

More information

SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS

SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: July 2017 IMPORTANT NOTICE Purpose The South Australian Advisory Functions are independent reports prepared by the Australian

More information

Exhibit to Agenda Item #1

Exhibit to Agenda Item #1 Exhibit to Agenda Item #1 Board Directors Meeting Wednesday,, scheduled to begin at 5:30 p.m. Customer Service Center, Rubicon Room Powering forward. Together. Agenda 2016 SD-4 annual monitoring report

More information

Investing for Future Generations Our Five Year Network Plan

Investing for Future Generations Our Five Year Network Plan Investing for Future Generations Our Five Year Network Plan 2009 2014 EnergyAustralia Investing for Future Generations Investing for Future Generations Our Five Year Network Plan: 2009 2014 Contents 2

More information

CitiPower Connection Policy

CitiPower Connection Policy CitiPower Connection Policy Version control Version Comment 1.0 Published 1 July 2016 1.1 Published 1 January 2017 2 CitiPower Connection policy 1 January 2017 Table of Contents 1 INTRODUCTION... 5 1.1

More information

WEM OPERATIONAL CONTINGENCIES VERSION 3.0

WEM OPERATIONAL CONTINGENCIES VERSION 3.0 WEM OPERATIONAL CONTINGENCIES VERSION 3.0 Published: November 2015 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about AEMO s contingency procedures to deal with Market

More information

PROPOSED NEW LARGE NETWORK ASSET ADELAIDE CENTRAL REGION SOUTH AUSTRALIA

PROPOSED NEW LARGE NETWORK ASSET ADELAIDE CENTRAL REGION SOUTH AUSTRALIA ` PROPOSED NEW LARGE NETWORK ASSET ADELAIDE CENTRAL REGION SOUTH AUSTRALIA FINAL REPORT ElectraNet Pty Ltd (ABN 41 094 482 416) 10 July 2009 COPYRIGHT ElectraNet and ETSA Utilities - All Rights Reserved

More information

AEP Transmission Local Planning Assumptions, Models, and Criteria

AEP Transmission Local Planning Assumptions, Models, and Criteria AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States

More information

PSE&G Assumptions Overview. November 2018

PSE&G Assumptions Overview. November 2018 PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group

More information