FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER
|
|
- Hannah Lindsey
- 5 years ago
- Views:
Transcription
1 FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER 31 st May 2010 Disclaimer This document has been prepared and made available solely for information purposes and consultation under the National Electricity Rules. It has been prepared with all due care and skill for the purposes of the National Electricity Rules and nothing in this document can be or should be taken as a recommendation in respect of any possible investment. This document does not purport to contain all of the information that a prospective investor or participant or potential participant in the NEM, or any other person or interested parties may require. In preparing this document, it is not possible nor is it intended for EnergyAustralia to have regard to the investment objectives, financial situation and particular needs of each person who reads or uses this document. In all cases, anyone proposing to rely on or use the information in this document should independently verify and check the accuracy, completeness, reliability and suitability of that information and the reports and other information relied on by EnergyAustralia in preparing this document, and should obtain independent and specific advice from appropriate experts or other sources. Accordingly, Energy Australia make no representations or warranty as to the accuracy, reliability, completeness or suitability for particular purposes of the information in this document other than for the regulatory purposes of the National Electricity Rules. EnergyAustralia and its employees, agents and consultants shall have no liability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or implied) arising out of, contained in or derived from, or for any omissions from, the information in this document, except insofar as liability under any New South Wales and Commonwealth statute cannot be excluded
2 TABLE OF CONTENTS EXECUTIVE SUMMARY INTRODUCTION Purpose and Scope Background IDENTIFICATION OF NEED FOR AUGMENTATION Applied Service Standard Subtransmission Substations (Urban/Non-Urban) Zone Substations and Overhead Lines (Urban/Non-Urban) Underground Sub-transmission Cables (Urban/Non-Urban) Description of Network Constraints Capacity Issues at Green Square Zone Substation Asset Condition Issues Applicable National Electricity Rules Requirements OPTIONS Demand Management Installation of a 3 rd transformer at Green Square zone substation ECONOMIC ANALYSIS OF OPTIONS CONCLUSION APPENDIX A ECONOMIC ANALYSIS OF BASE CASE...10 Page 2 of 10
3 EXECUTIVE SUMMARY This paper has been prepared to report on the assessment of options for the compliance of the Green Square load area within EnergyAustralia s Eastern Suburbs electricity supply network, in accordance with clause (h) of the National Electricity Rules (the Rules). The work proposed by this report involves augmentation expenditure of under $10 million and is regarded by the Rules as a new small dual-function network asset. Accordingly, EnergyAustralia has not previously consulted on this project. The Green Square Zone additional transformer is classified as a dual-function asset under Chapter 6 of the National Electricity Rules (rules). The rules (clauses and 5.6.6) requires that, where analysis indicates that any relevant technical limits of a distribution system will be exceeded, the Distribution Network Service Provider must notify any affected Registered Participants of these limitations and the expected time for corrective action and consult with affected Registered Participants and interested parties on possible options to address the projected limitations. The timing of the proposed work is primarily driven by the need to address upcoming load constraint and would thus be regarded as a reliability augmentation project. Substantial load growth in the Green Square load area has resulted in a capacity constraint at Green Square 132/11kV zone substation (ZS). To ensure a safe and reliable electricity supply for existing customers, EnergyAustralia is providing additional capacity to meet forecast load demands and mitigate energy at risk. The provision of additional capacity is required to meet network performance requirements set by EnergyAustralia in accordance with Schedule 5.1 of the Rules. This report covers the following issues: Section 1 of the paper provides a description of the Green Square load area. Section 2 presents EnergyAustralia s service standards for the area and describes, in detail, the nature of the load growth in the area, the issues affecting the supply network in the area and the need for augmentation of supply to the area. Section 3 outlines the possible options to address the issues affecting the supply network including options for supply system development. A build and a non-build option are described: Demand Management Installation of a 3 rd transformer at Green Square ZS Section 4 presents the results of economic analysis of the supply side options considered. Section 5 concludes that the most cost effective strategy within the regulatory test is the option of Installation of a 3 rd transformer at Green Square ZS. EnergyAustralia s recommended action is to upgrade Green Square ZS by installing a 3rd transformer at an estimated cost of $3.95 million. This recommendation is made based on the least cost test to provide additional capacity for the upcoming load constraint. Page 3 of 10
4 1. INTRODUCTION 1.1. Purpose and Scope This Final Report has been prepared to meet the requirements of clause (h) of the Rules and to advise registered participants and interested parties on specific development work proposed by EnergyAustralia for its Eastern Suburbs electricity supply area. It includes: A discussion of supply system limitations identified by EnergyAustralia that have led to the necessity of identifying possible options for augmentation of the distribution network in the area; A discussion of the service standard that has been adopted for planning purposes; A description of options identified for development of the electricity supply in the area; and A detailed cost effectiveness analysis of each of these options, carried out in accordance with the requirements of the regulatory test Background The Eastern Suburbs load area extends from Surry Hills in the north-west, south to Bunnerong North and west as far as Marrickville. The Eastern Suburbs network is supplied from the inner metropolitan transmission network at Surry Hills Sub-transmission Substation (STS), Bunnerong STS and from TransGrid s Beaconsfield West Bulk Supply Point (BSP). It includes 132kV and 33kV assets and with twenty substations, it is one of the largest network areas in EnergyAustralia s franchise area. Page 4 of 10
5 Figure 1 below is a geographic diagram of the Eastern Suburbs area. Figure 1: Eastern Suburbs Load Area Green Square 132/11kV ZS is located in the central portion of the Eastern Suburbs supply area and is currently supplied by Beaconsfield West BSP. Figure 2 below indicate the schematic overview of the area. Figure 2: System Diagram around Green Square Zone Substation Page 5 of 10
6 2. IDENTIFICATION OF NEED FOR AUGMENTATION 2.1. Applied Service Standard EnergyAustralia is required to comply with service standards that are specified in the Design, Reliability and Performance Licence Conditions (Licence Conditions), which were imposed on NSW distributors by the Minister for Energy on 1 October The design planning criteria are specified in Schedule 1 of the Licence Conditions and reliability standards are specified in Schedules 2 and 3. For existing network, a distributor must be as compliant as practicable with these requirements by 1 July 2014 and fully compliant by 1 July All new network elements must comply with these requirements. The service standards that are applicable to a consideration of supply constraints affecting the Green Square load area are summarised below. For further details refer to the Licence Conditions or to EnergyAustralia s Network Management Plan Subtransmission Substations (Urban/Non-Urban) With all elements in service, the thermal capacity is required to meet at least 115% of forecast demand. For a failure of a single critical element (i.e. N-1 conditions) within a subtransmission substation, the forecast demand is not to exceed the thermal capacity. Recovery of load should be within one minute Zone Substations and Overhead Lines (Urban/Non-Urban) With all elements in service, the thermal capacity is required to meet at least 115% of forecast demand. Following a failure of a single critical element (i.e. N-1 conditions), the network must be designed to recover supply within one minute for systems supplying >10MVA, and otherwise, within best practice repair times. For systems that supply >10MVA, the forecast demand of a zone substation or overhead feeder network may exceed the N-1 capacity for up to 1% of the year i.e. a total aggregate time of 88 hours per annum, up to a maximum of 20% above the N-1 capacity Underground Sub-transmission Cables (Urban/Non-Urban) The forecast demand of an underground feeder network may not exceed the N-1 capacity at any time Description of Network Constraints Load Forecast EnergyAustralia has previously published details of its load forecasts and the timing of loads exceeding technical limits of the system in its Annual Electricity System Development Review. The load forecast includes committed spot loads and normal levels of load growth. The timing of the constraint for Green Square ZS is shown below and is based on the forecast projected from the summer 2008/09 and winter 2009 actual loads Capacity Issues at Green Square Zone Substation Green Square Zone Substation is forecast to exceed its licence capacity by 5.6 MVA in summer 2011/12 and 17.5 MVA in summer 2012/13. Diagram below shows the load forecast of Green Square Zone Substation. Page 6 of 10
7 Green Square Zone Substation (based on actuals from Summer 2008/09 & Winter 2009) Actuals Forecast MVA Year Winter Load Winter Limit Summer Load Summer Limit '04 '05 '06 '07 '08 '09 '10 '11 '12 '13 '14 '15 '16 Actual Forecast Winter Load Limit Summer 03/04 04/05 05/06 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16 Load Limit (Note: Green Square ZS was commissioned in November 2005.) Asset Condition Issues 11kV compound switchgear at neighbouring Mascot Zone has been prioritised for replacement by The 33kV HSL feeders 328, 332, 360, and 337 between Bunnerong STSS and Mascot Zone are required to be replaced. Feeder 337 is planned for retirement by Feeders 328,332 & parts of 360 are to be replaced before Reconstruction of Mascot Zone to 132/11kV is driven primarily by condition of 11kV switchgear. The replacement will also address the 33kV cable condition issues. Significant 11kV load transfer from Mascot to Green Square is required to facilitate the reconstruction of Mascot Zone. The proposed completion date of Mascot Zone reconstruction is planned to be December Page 7 of 10
8 2.3. Applicable National Electricity Rules Requirements Green Square ZS and its associated transformers are classified as dual-function system assets by the National Electricity Rules (the Rules). The proposed development strategy for the Green Square ZS involves expenditure of less than $10 million which is regarded by the Rules as a small dual-function network asset. The new capacity provided by the proposed work will be used to address upcoming load constraint and would thus be considered a growth driven augmentation. EnergyAustralia has analysed the cost-effectiveness and feasibility of a range of options to resolve the load constraint at Green Square ZS. 3. OPTIONS EnergyAustralia has identified four Area Plan strategies for the Eastern Suburbs load area. The transformer installation project at Green Square is common across all analysed supply strategies. In accordance with this, a build and a non-build option were considered, these two options are described below Demand Management A Demand Management screening test was carried out in November 2009, investigating for any demand management solution to defer the 3rd transformer installation at Green Square ZS. The Demand Management screening test concluded that the 3rd transformer installation at Green Square ZS could not be cost effectively deferred due to the level of load growth at the Green Square load area Installation of a 3 rd transformer at Green Square zone substation This option involves installation of the 3rd 50MVA transformer in Green Square ZS, which will increase its license capacity to 126MVA. The total capital cost of this work is estimated to be $3.95M, with a NPC of $3.86M. This project is expected to be completed by summer 2011/12, hence enabling compliance in summer 2011/ ECONOMIC ANALYSIS OF OPTIONS An economic analysis has been carried out for the period 2009/10 to 2018/19. It involves the comparison of options by carrying out a Net Present Costs (NPC) analysis. An economic analysis of base case is shown in Appendix A. Four supply strategies were identified and analysed for the Eastern Suburbs load area. This project of installing a 3rd transformer is common across all four supply strategies in the Eastern Suburbs load area as per the 2009 to 2014 Regulatory Determination, and there is no other viable alternative option. Page 8 of 10
9 Sensitivity analysis of the base case was considered, however it is not presented due to the fact that there is only one viable option, and this option is common to all strategies. 5. CONCLUSION EnergyAustralia intends to upgrade Green Square ZS by installing a 3rd transformer at an estimated cost of $3.95M. The transformer installation project at Green Square is common across all four supply strategies in the Eastern Suburbs load area. There is no other viable alternative option. This work is forecast to be completed by Oct This service availability date may change if the project is affected by circumstances beyond EnergyAustralia's control, such as changes in the timing of customer load increases or other issues such as: delays in the approval process, equipment supply difficulties, unforeseen technical constraints, acts of God, and industrial action. Page 9 of 10
10 6. APPENDIX A ECONOMIC ANALYSIS OF BASE CASE Discount Rate 8.5% NPC ($k) Total ($k) 2009/ / / / / / / / / /2019 3rd Tx at Green Square 3,642 3, , O&M Total 3,863 3, , Note: The estimates are based on 2009/10 real dollars ($k) Page 10 of 10
Addressing reliability requirements in the Flemington substation load area
Addressing reliability requirements in the Flemington substation load area Notice on screening for non-network options May 2018 Title of Contents DISCLAIMER... 1 1 INTRODUCTION... 2 2 FORECAST LOAD AND
More informationErgon Energy Corporation Limited
Ergon Energy Corporation Limited Final Report Emerging Distribution Network Limitations in the Central Toowoomba Area 16 May 2013 Disclaimer While care was taken in preparation of the information in this
More informationSUPPLY TO SYDNEY CBD AND INNER SUBURBS: FINAL COST EFFECTIVENESS ANALYSIS EXECUTIVE SUMMARY. Final Report for TransGrid and EnergyAustralia
SUPPLY TO SYDNEY CBD AND INNER SUBURBS: FINAL COST EFFECTIVENESS ANALYSIS EXECUTIVE SUMMARY Final Report for TransGrid and EnergyAustralia Prepared by NERA February 2000 Sydney Project Team: Greg Houston
More informationErgon Energy Corporation Limited 4 June 2010
Ergon Energy Corporation Limited 4 June 2010 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation Limited
More informationRIT-T: Project Specification Consultation Report. Powering Sydney s Future
RIT-T: Project Specification Consultation Report Powering Sydney s Future 11 October 2016 1. Executive Summary Powering Sydney - now and into the future A reliable, affordable and sustainable electricity
More informationDraft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report
Draft Project Assessment Report RIT-D Report This report presents the network limitations at Dromana zone substation and the distribution feeder network within the Dromana / Mornington supply areas, including
More informationInterconnection Feasibility Study
XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION
More informationInterconnection Feasibility Study
XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY
More informationPowering Sydney s Future. TransGrid 330kV Cable Route Selection Process Summary
Powering Sydney s Future TransGrid 330kV Cable Route Selection Process Summary Contents Contents... 2 1. Executive summary... 3 2. Drivers for the project... 3 3. Options considered... 3 4. 330kV cable
More informationInterconnection Feasibility Study
XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION
More informationELECTRICITY STATEMENT OF OPPORTUNITIES For the National Electricity Market
ELECTRICITY STATEMENT OF OPPORTUNITIES For the National Electricity Market EXECUTIVE BRIEFING 2010 Preface I am pleased to introduce AEMO s 2010 Electricity Statement of Opportunities (ESOO), which presents
More informationTRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018
TRIP OF ERARING POWER STATION No. 1 GENERATOR TRANSFORMER AND ERARING VALES POINT 330 KV LINE ON 31 JANUARY 2018 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: May
More informationLOCAL PLANNING REPORT
Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared
More informationGENERATION EXPANSION PLAN FOR THE 2014 NATIONAL TRANSMISSION NETWORK DEVELOPMENT PLAN
GENERATION EXPANSION PLAN FOR THE 2014 NATIONAL TRANSMISSION NETWORK DEVELOPMENT PLAN Published: December 2014 Disclaimer AEMO has made every effort to ensure the quality of the information in this publication
More informationCustomer Capital Contributions Policy
TasNetworks Customer Capital Contributions Policy Effective 1 July 2014 Tasmanian Networks Pty Ltd ABN 24 167 357 29 Page 1 of 25 Tasmanian Networks Pty Ltd ABN 24 167 357 299 1-7 Maria Street Lenah Valley
More informationTasNetworks Distribution Connection Pricing Policy Final AER approved Commencing 1 July 2017
TasNetworks Distribution Connection Pricing Policy Final AER approved Commencing 1 July 2017 Page 1 of 54 Copyright This document is protected by copyright vested in Tasmanian Networks Pty Ltd. No part
More informationCOST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES
COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission
More informationPowering Sydney s Future Project Assessment Draft Report Summary
This is the second stage of the formal RIT-T process for Powering Sydney s Future. A reliable, affordable and sustainable electricity supply is essential for our way of life. If you live, work or operate
More informationBlack Start Procurement Methodology
Issue 1 Revision Black Start Procurement Methodology Produced in accordance with Standard Condition C16 of the National Grid Transmission Licence Effective from 1 st April 2017 to 31 st March 2018 DOCUMENT
More informationErgon Energy Corporation Limited 12 November 2009
Ergon Energy Corporation Limited 12 November 2009 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation
More informationGUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION
Level 2, 35 Spring St Melbourne 3000, Australia Telephone +61 3 9651 0222 +61 3 1300 664 969 Facsimile +61 3 9651 3688 GUIDANCE PAPER: FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE N JURISDICTION 14 FEBRUARY
More informationAUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS
AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further
More informationLower Mornington Peninsula Supply Area
Final Project Assessment Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including the preferred option to address those limitations.
More informationWater NSW Reporting Manual
Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968
More informationFY18 RESULTS PRESENTATION
FY18 RESULTS PRESENTATION DISCLAIMER This presentation has been prepared by rhipe Limited ACN 112 452 436 (RHP). Each Recipient of this presentation is deemed to have agreed to accept the qualifications,
More informationNEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017
NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 Published: July 2017 IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 3.13.6A(a) of the National Electricity
More informationInterconnection System Feasibility Study
Interconnection System Feasibility Study Zonnebeke Wind Project Report No: T&S Planning 2015-053 November 2015 FINAL British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority
More informationINFORMATION RELEASE. TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates
INFORMATION RELEASE TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates OVERVIEW This Information Release is intended to provide an overview of the transmission constraints
More informationRing Fencing Guideline
Ring Fencing Guideline Issue number 1 Status Final Date of approval 20/12/2017 Disclaimer This template is for generating internal and external document belonging to AusNet Services and may or may not
More informationNational Electricity Market Demand Forecasting Methodology. November Issues Paper
National Electricity Market Demand Forecasting Methodology November 2018 Issues Paper Important notice PURPOSE The publication of this Issues Paper commences AEMO s consultation on the effectiveness of
More informationLower Mornington Peninsula Supply Area
Non Network Options Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including options and technical characteristics of non-network options
More informationOutage Protocol: Explanatory note
Outage Protocol: Explanatory note This is the version of the outage protocol (previously in section VII of part F of the Electricity Governance Rules 2003) that the Authority is required to publish by
More informationTotal Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19
Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19 Date: 19 October 2015 Prepared by: Regulation and Investment Management DM 12392512 Contents Introduction... 2 1.1 Revised
More informationRegulatory 4 March 2011Test - Request for Information
Ergon Energy Corporation Limited Regulatory 4 March 2011Test - Request for Information Emerging Distribution Network Limitations in the South Mackay Area 28 October 2013 Ergon Energy Corporation Limited
More informationErgon Energy Corporation Limited
Ergon Energy Corporation Limited Request for Information Emerging Distribution Network Limitations in the Palm Island Area 1 May 2012 Disclaimer While care was taken in preparation of the information in
More informationDEMAND SIDE PARTICIPATION 2016 NATIONAL ELECTRICITY FORECASTING REPORT
2016 NATIONAL ELECTRICITY FORECASTING REPORT Published: September 2016 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about estimated demand side participation in the National
More information18,000+ ACTIVE USERS. AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE
18,000+ ACTIVE USERS AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE A Leading Payment Solutions & Technology Partner In Asia-Pacific SOUTH EAST ASIA 2 Our Markets $120B Singapore retail & online
More informationFor personal use only 18,000+ ACTIVE USERS $600M+ TRANSACTION VALUE. AGM PRESENTATION November 2017
18,000+ ACTIVE USERS AGM PRESENTATION November 2017 $600M+ TRANSACTION VALUE A Leading Payment Solutions & Technology Partner In Asia-Pacific SOUTH EAST ASIA 2 Our Markets $120B Singapore retail & online
More informationMethodology & Learning Report. Work package 2.1: Dynamic thermal rating of assets Primary Transformers
Flexible Networks for a Low Carbon Future Methodology & Learning Report Work package 2.1: Dynamic thermal rating of assets Primary Transformers May 2015 Contents 1 Executive Summary 2 2 Background 3 3
More informationNATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS
NATIONAL ELECTRICITY MARKET GUIDE TO GENERATOR EXEMPTIONS & CLASSIFICATION OF GENERATING UNITS PREPARED BY: AEMO Markets and Strategy & Innovation VERSION: 2.2 EFFECTIVE DATE: 20 March 2018 STATUS: FINAL
More informationOTHERLEVELS HOLDINGS LIMITED JANUARY 2018 INVESTOR UPDATE
OTHERLEVELS HOLDINGS LIMITED JANUARY 2018 INVESTOR UPDATE Execution In H1 FY18 Platform Investment Positive Operating Cash Flow Core strategy Customer Growth Positive Operating Cash Flow Record cash receipts
More informationMAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN
MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN APPLICATION NOTICE (ABN 41 094 482 416) December 2007 COPYRIGHT ElectraNet - All Rights Reserved This document is protected by copyright vested in
More informationDalrymple Substation Upgrade
Dalrymple Substation Upgrade RIT-T: Project Assessment Conclusions Report Version 1 ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,
More informationSystem Impact Study for. 1 January January 2016
System Impact Study for OASIS 72401305 Long-term Point to Point Transmission Service Request On the LM BPAT Path 1 January 2011 1 January 2016 Report No: SPPA2009-113 May 2009 System Planning & Performance
More informationInvitation for Expression of Interest to provide Flexible Services 3 April 2018
Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Flexible Services Expression of Interest/3 April 2018 Page 1 of 21 VERSION HISTORY Version Date Author Status Comments 1.0
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationEVALUATION REPORT RFP-ER 005/06
EVALUATION REPORT RFP-ER 005/06 On reinforcement options to address projected network constraints described in RFP 005/06 Projected Distribution Network constraints: Electricity Supply to the Wudinna to
More informationDemand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18
Demand Side Engagement Strategy Version 2.0 Effective Date: 08/02/18 Document management Version control Date Version Description Author 16/07/2013 0.1 Initial Draft. Y. Jayathilaka 23/07/2013 0.2 Revised
More informationCitiPower Amended Revised Proposed Tariff Structure Statement
CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 This page is intentionally left blank. 2 CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 Table of Contents
More informationAustralia s leading magnetite producer Southdown Magnetite Project. Russell Clark Managing Director & CEO February 2012
Australia s leading magnetite producer Southdown Magnetite Project Russell Clark Managing Director & CEO February 2012 Disclaimer The material in this presentation ( material ) is not and does not constitute
More informationCommunity and Stakeholder Consultation Report. Powering Sydney s Future
Community and Stakeholder Consultation Report Powering Sydney s Future Early Engagement July 2017 1. Executive Summary Powering Sydney s Future (the Project) aims to secure a reliable, safe and economical
More informationCLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5)
CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5) 1. PURPOSE AEMO has prepared this document to clarify AEMO s interpretation of particular clauses in Schedule 5.2 of the National
More informationDUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA
DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic
More informationMANAGING THE RISK OF TRANSFORMER BUSHING FAILURE
MANAGING THE RISK OF TRANSFORMER BUSHING FAILURE 11 December 2018 Copyright and Disclaimer Copyright in this material is owned by or licensed to ElectraNet. Permission to publish, modify, commercialise
More informationThe Stock Exchange of Hong Kong Limited. Practice Note 21
The Stock Exchange of Hong Kong Limited Practice Note 21 to the Rules Governing the Listing of Securities (the Exchange Listing Rules ) Issued pursuant to rule 1.06 of the Exchange Listing Rules DUE DILIGENCE
More informationWaypoints Sequence Extension API
Waypoints Sequence Extension API Release Notes Version 2.0.0 Waypoints Sequence Extension API Release Notes 2 Contents Contents Legal Notices...3 Document Information... 4 Overview...5 Known Issues...
More informationPerformance Reporting Criteria
Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5
More informationProject Specification Consultation Report
Project Specification Consultation Report 8 May 2018 Addressing the secondary systems condition risks at Dan Gleeson Substation Disclaimer While care was taken in preparation of the information in this
More informationBIG UNLIMITED FY18 Q1 4C UPDATE OCT 2017
BIG UNLIMITED FY18 Q1 4C UPDATE OCT 2017 WHAT IS BIG BIG (ASX: BIG) is the parent company of Big Review TV Ltd. Big Review TV are innovative disruptors in the online video space. They are a video driven
More information18/05/2018. Mr John Pierce Chair Australian Energy Market Commission PO Box A2449 Sydney NSW Lodged online via:
ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/05/2018 Mr John Pierce Chair Australian Energy Market Commission PO Box A2449
More informationA GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS.
A GUIDE TO WORKING SAFELY AROUND VECTOR S ELECTRICITY, GAS AND COMMUNICATIONS NETWORKS. Date of issue 27/01/2017 Date of next review 29/01/2018 Page 1 V4 18/07/2018 CONTENTS CONTENTS... 2 WORKING SAFELY...
More informationDistribution - Reset RIN, Basis of Preparation
L Distribution - Reset RIN, 2019-2024 Basis of Preparation Introduction TasNetworks (Tasmanian Networks Pty Ltd, ABN 24 167 357 299) is the owner and operator of the electricity distribution network in
More informationAudit and Review Guidelines: Electricity and Gas Licences
Audit and Review Guidelines: Electricity and Gas Licences April 2014 This document is available from the Economic Regulation Authority s website at www.erawa.com.au. For further information, contact: Economic
More informationTENDER AND EVALUATION PROCESS FOR CONTESTABLE AUGMENTATIONS
TENDER AND EVALUATION PROCESS FOR CONTESTABLE AUGMENTATIONS PREPARED BY: Transmission Services Department VERSION: 1 RELEASE DATE: 1 July 2010 Au1hol,an Enargy Marla! ap.rotr:w lkl A~N o,. 012 010 321
More informationNova Scotia Power System Operator (NSPSO)
Nova Scotia Power System Operator (NSPSO) Market Procedure MP-09 Outage Planning and Approval Effective Date: 2008 12 31 Wholesale Market Procedure MP-09 Table of Contents Page 1 Document Control and General
More informationNetwork Support and Control Ancillary Service (NSCAS) Quantity Procedure
Network Support and Control Ancillary Service (NSCAS) Quantity Procedure PREPARED BY: PLANNING VERSION: 1.0 DATE: 12 DECEMBER 2011 FINAL This document has been created by the Planning Department and will
More informationENERGEX Network Management Plan Part A 2008/09 to 2012/13 FINAL
Part A 2008/09 to 2012/13 FINAL ENERGEX Limited, Australia This work is copyright. Material contained in this document may be reproduced for personal, in-house or noncommercial use, without formal permission
More informationLOW POWER FACTOR AT WINGHAM TS ASSESSMENT
LOW POWER FACTOR AT WINGHAM TS ASSESSMENT Date: October 18 th, 2016 Prepared and Reviewed by: Sacha Constantinescu, P.Eng Transmission Planner System Planning Jerry Vo Distribution Planner Distribution
More informationAncillary Service. the WEM System Management. June 2018
Ancillary Service Report for the WEM 2018-19 June 2018 System Management Important notice PURPOSE AEMO publishes the Wholesale Electricity Market Ancillary Services report under clause 3.11.13 of the Wholesale
More informationService Standards for Western Power Corporation s South West Interconnected System
Service Standards for Western Power Corporation s South West Interconnected System Report prepared for Economic Regulation Authority Western Australia Contents 1 Executive summary 3 2 Introduction 7 2.1
More informationFringe-of-Grid PV Projects - Normanton Solar Farm
Fringe-of-Grid PV Projects - Normanton Solar Farm All-Energy Conference 2016 October 5, 2016 Josh Currah Project Manager, Energy Business www.canadiansolar.com Safe Harbor Statement This presentation has
More informationTransmission System Security and Planning Standards
ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2
More informationEnvironmental impact methodology
Environmental impact methodology For US professional investors only - June 2016 Second edition 1 Environmental impact methodology for the 2 Scope and reporting boundaries 3 Methodology 4 Exclusions and
More informationHow to set up a sewer mining scheme
Sewer Mining How to set up a sewer mining scheme With a growing population and highly variable rainfall over the catchments, water recycling is making an increasingly important contribution to our water
More informationPRELIMINARY REVENUE PROPOSAL
PRELIMINARY REVENUE PROPOSAL 2019-2023 ElectraNet // September 2016 Preliminary Revenue Proposal 2019-2023 // Page 2 This Preliminary Revenue Proposal is intended to promote effective early engagement
More informationWIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION
WIND AND SOLAR FARMS TESTING REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION PREPARED BY: AEMO Operations Department Systems Performance & Commercial VERSION: 1.0 EFFECTIVE DATE: 5 October 2018 STATUS:
More informationJemena Electricity Networks (Vic) Ltd
Jemena Electricity Networks (Vic) Ltd Flemington Zone Substation RIT-D Stage 2: Draft Project Assessment Report Public 16 December 2016 An appropriate citation for this paper is: Flemington Zone Substation
More informationChanges to the MCR &Tips for Implementation: The Minimum Competency Code 2011 Lisa Knox Enterprise Risk Services 17 November 2011
Changes to the MCR &Tips for Implementation: The Minimum Competency Code 2011 Lisa Knox Enterprise Risk Services 17 November 2011 Overview Background CBI Themed Inspections - Lessons Learned Key Changes
More informationThe Role of Transmission System Operator in the Context of Energy Security the Case of Poland
The Role of Transmission System Operator in the Context of Energy Security the Case of Poland Waldemar Dolega Institute of Electrical Power Engineering; The Wroclaw University of Technology Wroclaw, Poland
More informationNEM EVENT SCHEDULING ERROR INTERMITTENT AGC FAILURES DECEMBER 2012
NEM EVENT SCHEDULING ERROR INTERMITTENT AGC FAILURES DECEMBER PREPARED BY: Market Operations and Performance DOCUMENT REF: NEM ER 13/001 DATE: 19 March 2013 FINAL Legal Notices Disclaimer This document
More informationSubmission to the Economic Regulation Authority
Submission to the Economic Regulation Authority APPROVAL OF NEW FACILITIES INVESTMENT Installation of a second 330/132 kv transformer at Kemerton Terminal and construction of a 132 kv transmission line
More informationXXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan
XXXXX Bremner Trio Small Hydro Project Interconnection Facilities Study and Project Plan June 25, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights
More informationFor personal use only
Go to View / Master / Slide Master. Insert, position and crop pictures on this Master Slide behind Vision Graphic element. MASTERMYNE GROUP AGM OPERATIONS UPDATE NOVEMBER 2017 www.mastermyne.com.au Overview
More informationELECTRICITY SUPPLY - POWER QUALITY AND RELIABILITY Code of Practice
ICS 29.240:03.120 Zambian Standard ELECTRICITY SUPPLY - POWER QUALITY AND RELIABILITY Code of Practice Part 2: Measurement and Reporting Procedures ZAMBIA BUREAU OF STANDARD DATE OF PUBLICATION This Zambian
More informationFeasibility Study for the Q MW Solar Project
Feasibility Study for the Q195 74.9 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC
More informationElectricity Market Design Principles
Electricity Market Design Principles Identifying long-term market design principles to support a sustainable energy future for Australia Executive Summary 19 April 2018 KPMG.com.au Important Notice If
More informationFuture Matters US Disclosure
Disclaimer This presentation has been prepared by Samsung Electronics Co., Ltd. (the "Company"). It does not purport to contain all the information that a prospective investor may require in connection
More informationPOWERNET LIMITED LINE PRICING METHODOLOGY
POWERNET LIMITED LINE PRICING METHODOLOGY FOR THE ELECTRICITY INVERCARGILL LIMITED NETWORK AS AT 1 APRIL 2018 THE ELECTRICITY INVERCARGILL LIMITED NETWORK AS AT 1 APRIL 2018 TABLE OF CONTENTS 1. GLOSSARY
More informationJemena Gas Networks (NSW) Ltd
Jemena Gas Networks (NSW) Ltd 2015-20 Access Arrangement Information Rule considerations in setting network tariffs Public 30 June 2014 TABLE OF CONTENTS TABLE OF CONTENTS 1. Introduction... iv 2. Stand-alone
More informationAncillary Services Fee Based Services Application and Price Guide
Ancillary Services Fee Based Services Application and Price Guide 2018-19 As approved by the Australian Energy Regulator Disclaimer TasNetworks (which, for the purposes of this disclaimer, includes all
More informationDATA AND MODEL REQUIREMENTS FOR GENERATING SYSTEMS OF LESS THAN 30 MW
DATA AND MODEL REQUIREMENTS FOR GENERATING SYSTEMS OF LESS THAN 30 MW PREPARED BY: Network Models Systems Capability VERSON: Final DATE: 28 June 2013 Australian Energy Market Operator Ltd ABN 94 072 010
More informationSOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS
SOUTH AUSTRALIAN DEMAND FORECASTS SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: July 2017 IMPORTANT NOTICE Purpose The South Australian Advisory Functions are independent reports prepared by the Australian
More informationExhibit to Agenda Item #1
Exhibit to Agenda Item #1 Board Directors Meeting Wednesday,, scheduled to begin at 5:30 p.m. Customer Service Center, Rubicon Room Powering forward. Together. Agenda 2016 SD-4 annual monitoring report
More informationInvesting for Future Generations Our Five Year Network Plan
Investing for Future Generations Our Five Year Network Plan 2009 2014 EnergyAustralia Investing for Future Generations Investing for Future Generations Our Five Year Network Plan: 2009 2014 Contents 2
More informationCitiPower Connection Policy
CitiPower Connection Policy Version control Version Comment 1.0 Published 1 July 2016 1.1 Published 1 January 2017 2 CitiPower Connection policy 1 January 2017 Table of Contents 1 INTRODUCTION... 5 1.1
More informationWEM OPERATIONAL CONTINGENCIES VERSION 3.0
WEM OPERATIONAL CONTINGENCIES VERSION 3.0 Published: November 2015 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about AEMO s contingency procedures to deal with Market
More informationPROPOSED NEW LARGE NETWORK ASSET ADELAIDE CENTRAL REGION SOUTH AUSTRALIA
` PROPOSED NEW LARGE NETWORK ASSET ADELAIDE CENTRAL REGION SOUTH AUSTRALIA FINAL REPORT ElectraNet Pty Ltd (ABN 41 094 482 416) 10 July 2009 COPYRIGHT ElectraNet and ETSA Utilities - All Rights Reserved
More informationAEP Transmission Local Planning Assumptions, Models, and Criteria
AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States
More informationPSE&G Assumptions Overview. November 2018
PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group
More information