1 Time Table and Train Order Dispatching Lessons Burnt Hills and Big Flats Railroad Employee Training Photos by author DISPATCHER Steve Prevette Burnt Hills & Big Flats RR
2 Introduction This presentation is a set of lessons learned from implementing TT&TO over the past two years on my home layout I HAVE MADE COMPROMISES! You may or may not agree with them Oriented to Single Track TT&TO Example of TT&TO Dispatcher training
3 Your Host Layout The Burnt Hills and Big Flats is a 20 x 30 ft N scale layout, 1970 NYO&W Have always done operations Dispatched with simplified track warrants closer to mother may I? Fixed location radios 5 to 7 operators Moved from Washington state to South Carolina in 2009 See Kalmbach GMR to be published this year
4 ft x 6 ft N Scale
5 2009 Today 20 ft x 30 ft
6 New Location, New Crew
7 New Location, New Crew New crew size usually 8 to 12 Larger crew size, need more jobs Oral orders were getting forgotten, unfamiliarity with layout Crew did not like using radios One layout in the existing group was planning on going TT&TO
8 Initial Trial Manual train order signals at 7 locations Based upon David Barrow idea Green/Green, Red/Green, Red/Red signals Manually placed in brass tube by dispatcher All trains run as Extras Crews given Form 19 s and Clearance Forms by operators based upon orders given by Dispatcher
9 Initial Lessons Manual signals worked Operating signals from Custom Signals installed
10 Initial Lessons All trains as Extras created a LOT of Train Orders Created a Schedule with 12 Scheduled Trains Went to pre-printed Form G s (run extra) to cover the remaining extra trains Added yard limits for two towns that had lots of interactions between local switching and through trains
11 Compromises! All model railroading is a compromise We cut out boring, strenuous tasks We simplify procedures and paperwork You may or may not agree with my compromises, but here goes... THUMBTACK ON CAR
12 Pre-Printed Orders The dispatcher starts with pre-printed Form G (Run Extra from A to B) Train Orders for all trains expected to be run Pre-printed Clearance Form A s with some non-prototype info DCC two digit channel Point of Origination and Termination Call Time
13 No Order Dictation My operators do not find repeating back orders and writing them to be fun Dispatcher hands written orders to the operators, who then post at train order signals Gives flexibility when there are not enough crew to man all operators Keeps communications lines open for OS reports (consider the compressed distances)
14 No Register Books I should have at least three register stations Sidney (north end of division and adjacent to staging) Big Flats (adjacent to southern staging) Mayfield (division point) At the beginning of the session any pending trains are announced, and upon completion of any scheduled train This will probably be the next compromise to be undone
15 What the Train Crews Get Small Clipboard Schematic on back, Schedule on Front Train Order(s) Clearance Form A Train Instructions
16 Crew Clipboard
17 What the Train Crews Get
18 White Flag for Extras Small square of white paper rubber cemented to engine
19 Employee Training The following is the Dispatcher Training Power Point Also made Operator and Crew Training Want to avoid Death By Power Point You may find this example useful for your own purposes Intent is to quickly overview this part of the presentation
20 Burnt Hills and Big Flats Railroad Employee Training DISPATCHER
21 Topics Scranton Division Overview Scheduled and Routine Extra Trains Limitations at Cadosia and Pleasant Mount Dispatcher Communications Standard Train Orders Yard Limits and Branches Trainsheet and Train Order Log
22 Dispatcher Duties 1. Ensure safe movement of trains over the Main Track 2. Promote efficient flow of traffic to allow the railroad to make revenue 0/11/archival-photos-dispatcher.html
23 Burnt Hills and Big Flats R.R. NORTHERN DIVISION Norwich Y N O R T H Northwest Branch Sidney Yard Sidney Burnt Hills Cadosia Starlight Pleasant Mount Mayfield Yards Mason Capouse Branch Cayuga Jct (CJ) Big Flats S Y Y Y Y GX Tower S Unadilla S Y S Delaware & Hudson Delhi Branch Northwest Jct (NB) Carbondale E-L Crossing Capouse Jct (CP) Scranton (CNJ) The Main Track Northern Division Sidney to Norwich Scranton Division Mayfield to Sidney Big Flats to Scranton Capouse Jct to Big Flats Y Sibley Jct Coxton Yard (LV) Hampden Yard Y Taylor Yard (E-L) SCRANTON DIVISION
24 Burnt Hills and Big Flats R.R. NORTHERN DIVISION Norwich Y N O R T H Northwest Branch Sidney Yard Sidney Burnt Hills Cadosia Starlight Pleasant Mount Mayfield Yards Mason Capouse Branch Cayuga Jct (CJ) Big Flats S Y Y Y Y GX Tower S Unadilla S Y S Delaware & Hudson Delhi Branch Northwest Jct (NB) Carbondale E-L Crossing Capouse Jct (CP) Scranton (CNJ) NOT Main Track Within Sidney Yard Limits Delhi Branch Northwest Branch Within Mayfield Yard Limits Within Hampden Yard Limits Any passing siding or secondary tracks Y Sibley Jct Coxton Yard (LV) Hampden Yard Y Taylor Yard (E-L) SCRANTON DIVISION
25 Northern Division On the prototype, Sidney NY was a division point, though the division s primary yard was in Norwich, 25 miles to the north On the model, Sidney yard limits butt against Norwich Staging Scranton dispatcher (for model purposes) will authorize movements into and out of Norwich staging
26 Train Schedule The schedule authorizes movement of trains No train orders are required to run schedule Safe movement is handled by the train crews Superiority is by Class and/or Direction The dispatcher may alter the schedule by issuing train orders if needed for efficiency Train has fallen behind schedule Lower class train has a priority movement
27 BH&BF Passenger Trains 14, 15, 16, 17 Passenger fan trips Taylor Yard (E-L) to Burnt Hills and return 15 minute station stops at Starlight and Pleasant Mount Note there is no siding at Pleasant Mount, train will block main while stopped
28 BH&BF First Class Freight Trains 84 & 87 (D&H/LV run through) Between Coxton Yard (LV) & Sidney (D&H) Reverse direction in Sidney Yard service in Mayfield Provides Washington DC to Portland ME service 81 & 88 (LV run through) Between Coxton Yard (LV) & Syracuse Yard service in Mayfield
29 BH&BF First Class Trains 81, 88 84, 87 14, 15, 16, 17
30 BH&BF Second Class Trains 92, 95 93, & 95 Between Mayfield and Syracuse Yard service at Norwich 93 & 94 Between Mayfield and Utica Yard service at Norwich
31 Siding Length SECOND CLASS SOUTHWARD BH&BF Train Schedule FIRST CLASS Burnt Hills and Big Flats Southern Division Timetable No. 11 Milepost NORTHWARD FIRST CLASS SECOND CLASS SM-95 UM-93 SL-81 NE NE-84 LS-88 MU-94 MS-92 Cars DAILY DAILY DAILY DAILY DAILY DAILY STATIONS DAILY DAILY DAILY DAILY DAILY DAILY 15 8:05 AM 8:10 PM 1:55 AM A 5: DN -R Sidney YL A 5:20 5:20 8:25 9:35 AM PM AM AM PM PM South Unadilla 91.7 PM -- PM AM AM PM 16 8:10 8:15 2:00 5:15 D 1:00 D 4:30 DN Burnt Hills 73.5 A 12:15 A 3:50 5:15 5:15 8:20 9:33 P, Y 9 8:12 8:17 2:02 5:25 1:02 4:32 DN Cadosia :13PM 3:48 5:13 5:10 8:18 9: :15 8:20 2:05 5:30 D 1:25 D 4:45 D Starlight 48.0 D 12:10 D 3:45 5:10 5:00 8:15 9:25 P D 1:40 D 5:00 Pleasant Mount 33.7 D 11:55 D 3:30 P AM PM AM AM PM PM DN Northwest Jct 20.3 AM PM PM AM AM PM 16 8:20 8:25 2:10 5:40 1:45 5:05 Carbondale :30 3:15 5:05 4:55 8:05 9:20 16 A 8:25 A 8:30 D 2:50 D 6:20 1:50 5:15 DN-R Mayfield YL :25 3:10 D 5:00 D 4:50 8:00 9:15 TF AM PM AM AM PM PM Mason 5.7 AM PM PM AM AM PM :55 6:25 1:55 5:20 DN Capouse Jct :20 3:05 4:20 4: Scranton Siding Length SECOND CLASS SOUTHWARD FIRST CLASS Capouse Branch Timetable No. 11 Milepost NORTHWARD FIRST CLASS SL-81 NE NE-84 LS-88 Cars DAILY DAILY DAILY DAILY STATIONS DAILY DAILY DAILY DAILY SECOND CLASS 3:05 6:25 2:05 5:20 DN Capouse Jct :20 3:05 4:20 4:10 AM AM PM PM DN-R Cayuga Jct 11.3 AM PM PM AM :15 PM 5:25 PM Big Flats YL :15 AM 3:00 PM A 3:15 A 6: Sibley Jct :15 PM 4:00 AM
32 Covers Scranton to Sidney, and the Capouse Branch Right (north) side read up from bottom A before time is arrival, D is departure Schedule Notes Siding Length Burnt Hills and Big Flats Southern Division Timetable No. 11 Milepost SM-95 UM-93 SL-81 NE NE-84 LS-88 MU-94 MS-92 Cars DAILY DAILY DAILY DAILY DAILY DAILY STATIONS DAILY DAILY DAILY DAILY DAILY DAILY 15 8:05 AM 8:10 PM 1:55 AM A 5: DN -R Sidney YL A 5:20 5:20 8:25 9:35 AM PM AM AM PM PM South Unadilla 91.7 PM -- PM AM AM PM 16 8:10 8:15 2:00 5:15 D 1:00 D 4:30 DN Burnt Hills 73.5 A 12:15 A 3:50 5:15 5:15 8:20 9:33 P, Y 9 8:12 8:17 2:02 5:25 1:02 4:32 DN Cadosia :13PM 3:48 5:13 5:10 8:18 9: :15 8:20 2:05 5:30 D 1:25 D 4:45 D Starlight 48.0 D 12:10 D 3:45 5:10 5:00 8:15 9:25 P D 1:40 D 5:00 Pleasant Mount 33.7 D 11:55 D 3:30 P AM PM AM AM PM PM DN Northwest Jct 20.3 AM PM PM AM AM PM 16 8:20 8:25 2:10 5:40 1:45 5:05 Carbondale :30 3:15 5:05 4:55 8:05 9:20 16 A 8:25 A 8:30 D 2:50 D 6:20 1:50 5:15 DN-R Mayfield YL :25 3:10 D 5:00 D 4:50 8:00 9:15 TF AM PM AM AM PM PM Mason 5.7 AM PM PM AM AM PM :55 6:25 1:55 5:20 DN Capouse Jct :20 3:05 4:20 4: Scranton Siding Length SECOND CLASS SECOND CLASS SOUTHWARD SOUTHWARD FIRST CLASS FIRST CLASS Capouse Branch Timetable No. 11 Milepost NORTHWARD FIRST CLASS NORTHWARD FIRST CLASS SL-81 NE NE-84 LS-88 Cars DAILY DAILY DAILY DAILY STATIONS DAILY DAILY DAILY DAILY 3:05 6:25 2:05 5:20 DN Capouse Jct :20 3:05 4:20 4:10 AM AM PM PM DN-R Cayuga Jct 11.3 AM PM PM AM :15 PM 5:25 PM Big Flats YL :15 AM 3:00 PM A 3:15 A 6: Sibley Jct :15 PM 4:00 AM Left column shows car length of sidings Middle column left: Operator (D = day, N = night); R = Register station Middle column right: YL = Yard Limit Right column: P = Passenger Station, Y = wye, TF = Turning Facility SECOND CLASS SECOND CLASS
33 Extra Trains Coal and Transfers Coal Trains two each direction Norwich/Mayfield Transfers two each direction with block setout and pickup at Sidney D&H/Mayfield Transfers three each direction LV/Mayfield Transfers four each direction E-L/Mayfield Transfers four each direction
34 BH&BF Coal Trains c Oswego Coal c Both Coal Trains have yard service in Norwich Utica Coal
35 BH&BF Transfers (Extra Trains) Norwich Transfer D&H Transfer LV Transfer E-L Transfer
36 Extra Trains - Locals Big Flats Mine Run shuttles between Mayfield, Scranton, and Big Flats as needed Northwest Mine Run two round trips Mayfield to Northwest Branch and return Burnt Hills Local two round trips Mayfield to Sidney and return, service to Starlight, Cadosia, Burnt Hills and S. Unadilla Sidney Local Norwich to Mayfield and return. Switches Sidney industries. Delhi Branch Norwich to Delhi and return
37 Sidney Local Delhi Branch Locals NW Branch Burnt Hills Local Big Flats / Scranton Local
38 Dispatcher Information Dispatcher receives a table with notes on the expected sequence of trains to be run Call Time Train Name Engine North Engine South Origination Destination NOTES 3:00 PM 16/17 DH 16 DH 16 EL Taylor 3 EL Taylor 3 EL to Burnt Hills and return. Station stops at Pleasant Mount & Starlight. Passenger. 3:00 D&H South 3:30 BF Mine Run 3:45 Sidney South DH 2310 D&H 3 Mayfield Changes direction in Sidney Mayfield Mayfield Works Mason / Big Flats and Scranton as needed 35 Norwich 4 Mayfield Works Sidney Industries & Yard
39 Station Notes Cadosia siding only holds 9 cars. Generally not a good option for meets Pleasant Mount has no siding, but trains 14, 15, 16, 17 do stop there, blocking the main
40 Cadosia The Cadosia siding is only 9 cars long The Burnt Hills Local can have as many as 12 cars, clearing for a meet or pass while switching in Cadosia may pose difficulties
41 Dispatcher Communications FORMAL Train orders to the train crews via operators, authorizing movement of trains INFORMAL: Clearance Form A s O.S. reports from operators Information to and from operators Information to and from yardmasters
42 Form G Train Order This train order authorizes Extra trains Example for northward coal train follows: Order addressed to the conductor and engineer (C&E) of the engine at Mayfield since the extra does not yet exist The expected Form G s have been pre-printed Engine 27 Run Extra Mayfield to Norwich
43 Trains in Opposing Directions The Dispatcher does not need to provide protection for scheduled trains against extras The Dispatcher MUST provide protection for opposing extras: Hold the Form G until opposing train terminates A Meet Order A Right Over Order
44 Extra 27 North Scenario 1 The dispatcher is ready to give the Form G to the engine 27, but notes that No. 17 is running southward from Burnt Hills. Are any additional orders needed? No! Extra 27 North must study the schedule and determine their meeting location with No. 17
45 Extra 27 North Scenario 2 The dispatcher is ready to give the Form G to the engine 27, but notes that Extra 20 South is authorized to run southward from Sidney. Are any additional orders needed? Yes! Form S-A example (addressed to both trains): Extra 20 South take siding and meet Extra 27 North at Starlight
46 Extra 27 North Scenario 2 Modified Form G example: After Extra 20 South has arrived at Mayfield, Eng 27 run extra Mayfield to Norwich Form S-C example to do same thing: Extra 20 South has right over Extra 27 North Sidney to Mayfield
47 Meet Orders To date, no more than two meet or right over orders have been needed per session The locals are sequenced to stay out of each other s way The scheduled trains don t need meet orders Yard Limits at Sidney and Big Flats also reduce need for orders Must plan ahead and provide orders at least one station prior to meeting location
48 Extras in the Same Direction The Dispatcher has NO safety responsibilities for trains going the same direction If a train is stopped, it sends out a flagman to protect the rear of the train The stopped train does not have to allow a following extra train to pass it The Dispatcher MAY order a train to allow another to pass it for efficiency purposes using a Form B
49 Extra 27 North Scenario 3 The dispatcher is ready to give the Form G to the engine 27, but notes that Extra 32 North is switching in Burnt Hills. Are any additional orders needed? No, these two extras are running in the same direction. Extra 32 North should have a flagman at the south end of Burnt Hills
50 Extra 27 North Scenario 3 If the dispatcher wants to ensure the coal extra is not delayed by the local switching in Burnt Hills, the Dispatcher may either: Unofficially advise the Burnt Hills operator to tell the local to clear up Or issue a Form B order: Extra 27 North pass Extra 32 North at Burnt Hills
51 Yard Limits Big Flats There are Yard Limits at Big Flats When the Big Flats Mine Run is switching in Big Flats, then Extras and Scheduled Trains meet or pass the local under Rule 93, no train orders needed. Trains run at Restricted Speed within yard See
52 Yard Limits Mayfield The Mayfield Yards are controlled by the Yardmaster There are call-on signals operated by the Yardmaster at yard entrances Dispatcher does not control movements within the yards All extra trains (northward and southward) terminate at Mayfield, there are no run through extras
53 Yard Limits Sidney Yard Limits at Sidney allow multiple trains to operate within the area without dispatcher attention The Burnt Hills Local ends its run switching in Sidney. Once it arrives at Sidney, and prior to receiving the run extra order for Sidney to Mayfield, their switching does not have to be protected by the dispatcher
54 Branches There are no train order stations at Scranton, Delhi, or on the Northwest Branch Form G orders to Scranton must include and return to Capouse Junction Form G orders to Northwest Branch must include and return to Northwest Junction From G orders to Delhi should include and return to Burnt Hills The pre-printed Form G s cover these requirements
55 Branches Often the Northwest Mine Run will be ready to depart Mayfield, and there is a southward extra on the main north of Carbondale If the dispatcher wants the NW Mine Run to run Mayfield to Carbondale prior to arrival of the southward extra in Mayfield, send a right over Form S-C order: Extra 34 North has right over Extra 27 South Mayfield to Carbondale
56 Branches If extra 34 North enters the Northwest Branch prior to arrival of the southward extra (the dispatcher will know this from the OS report), the southward extra should be notified using a Form V: Extra 34 North has passed Carbondale The same situation could arise with Scranton and Delhi, but has not happened yet
57 Changing Orders An order may be modified ONCE using a Form P order: Extra 27 North take siding and meet Extra 7 South at Starlight instead of Burnt Hills An order may be cancelled (annulled) using a Form L order: Order No 2 is annulled
58 Basic Order Overview A BH&BF operating session may be successfully completed with just these types of orders: Eng 27 Run Extra Mayfield to Norwich Extra 32 North take siding and meet Extra 35 South at Burnt Hills Extra 32 North has right over Extra 35 South Mayfield to Burnt Hills Order No 11 is Annulled
59 Basic Order Forms A. Meet: No. take siding and meet No. at B. Pass: No. pass No. at C. Right Over No. has right over No. to (locations) E. Time: No. run mins late to (locations) No. wait at until (time) No. wait at for No. G. Extra: Eng. run extra to L. Annul Order No. is annulled P. Supersede instead of (A train order should only be superseded once. After that, annul it) V. Register No. has passed (location)
60 What if a Scheduled Train is Delayed? All scheduled trains have run on schedule to date If the dispatcher does want to advance an opposing train over the scheduled train, the dispatcher may use a Meet or Right Over order Also, the dispatcher may use a form S-E: No 87 run 45 minutes late Sidney to Mayfield
61 Keeping Track of Trains and Orders Currently, we use a spreadsheet to track train orders, versus a hard bound book A spreadsheet map is used to track the clearances and progress of trains, based upon OS reports Prototypical paper forms are available for those who prefer the paper forms Purpose is to keep track of train locations, meet points, and potential conflicts
62 Train Order Log Copy of log from six fast hours (two sessions): Number C&E At Directions Completed No longer active Run Extra Mayfield to Northwest Branch 27 Eng 34 Mayfield and return to Northwest Jct 12:17 PM X 28 Eng DH4023 NW Jct Run Extra Carbondale to Mayfield 2:45PM X 29 Eng DH2310 Sidney Run Extra Sidney to Mayfield 2:55 PM X 30 Eng 19 Mayfield Run Extra Mayfield to Big Flats 3:00 PM X 31 Eng 35 Norwich Run Extra Norwich to Mayfield 3:50 PM X 32 Eng 14 Big Flats Run Extra Big Flats to Mayfield 4:25 PM X 33 X35South / X34North Burnt Hills / Mayfield Extra 34 North has right over Extra 35 South Mayfield to Carbondale 4:40PM X 34 Eng 34 Mayfield Run Extra Mayfield to Northwest Branch and return to Northwest Jct 4:50 PM X 35 Eng 19 Mayfield Run Extra Mayfield to Scranton and return to Capouse Jct 4:55 PM X 36 Eng 14 Capouse Jct Run Extra Capouse Jct to Mayfield 6:00 PM X Completed is time order issued to Operator
63 Spreadsheet Map Extra 32 North is in Burnt Hills, with authorization to run to Sidney
64 Spreadsheet Map Green arrows advance a train along the map Red X clears the train from the track section Advance each train from origination to the limit of its movement authorization Clear the track sections behind the train as OS reports are received Track sections within Yard Limits are pink
65 Train Sheet Burnt Hills and Big Flats Railroad DISPATCHER'S RECORD OF MOVEMENT OF TRAINS SOUTHWARD Scranton Division TRAIN ENGINE ENGINE ENGINEER CONDUCTOR Arr. Lv. Arr. Lv. Arr. Lv. Mile Post Station Office Designation Arr. Lv. Arr. Lv SIDNEY (D&H Crossing) SI 3.0 MILES 91.7 SOUTH UNADILLA 18.2 MILES 73.5 BURNT HILLS WN 19.5 MILES 54.0 CADOSIA HD 6.0 MILES 48.0 STARLIGHT SR 14.3 MILES Above is a section of the trainsheet used to record progress of trains at stations.
66 Goal BH&BF Management hopes some employees will be interested in the Dispatcher job This will increase flexibility and give some job rotation Dispatching can be the most prototypically correct jobs available
Burnt Hills and Big Flats Railroad Employee Training DISPATCHER
Burnt Hills and Big Flats Railroad Employee Training DISPATCHER Dispatcher Duties 1. Ensure safe movement of trains over the Main Track 2. Promote efficient flow of traffic to allow the railroad to make
More informationBurnt Hills and Big Flats Railroad Employee Training MAYFIELD YARDMASTER
Burnt Hills and Big Flats Railroad Employee Training MAYFIELD YARDMASTER Railroad Yardmaster Duties Tulsa, OK Frisco Yard Office http://www.loc.gov/pictures/resource/fs a.8d44978/ Railroad yardmasters
More informationBurnt Hills and Big Flats Railroad Employee Training MAYFIELD YARDMASTER
Burnt Hills and Big Flats Railroad Employee Training MAYFIELD YARDMASTER Railroad Yardmaster Duties Tulsa, OK Frisco Yard Office http://www.loc.gov/pictures/resource/fs a.8d44978/ Railroad yardmasters
More informationDesign for Operations Lessons from Rocks and Water Steve Prevette Burnt Hills & Big Flats RR
Design for Operations Lessons from Rocks and Water Steve Prevette Burnt Hills & Big Flats RR Photos by author Intro This is a refinement of a clinic given last year in Atlanta We will look at considerations
More informationTimetable and Trainorder TT&TO. An Overview and american Adaptation
Timetable and Trainorder TT&TO An Overview and american Adaptation Inhaltsverzeichnis / Table of Content 1. Overview of TT&TO Operation 2. FREMO american TT&TO guide 2.1 Timetable 2.2 Extra Trains 2.3
More informationYARDMASTERS GUIDE. South Central Region
PRR RDG WM YARDMASTERS GUIDE No. 7 Effective 12:01 AM, EASTERN STANDARD TIME, Wednesday, June 13, 1956 South Central Region FOR THE GOVERNMENT OF EMPLOYEES ONLY Jeffry A. Warner Superintendent Section
More informationDispatch Your Trains! Elements of Train Dispatching, a how to clinic By Steve Breezy Gust and Rick Kang
Dispatch Your Trains! Elements of Train Dispatching, a how to clinic By Steve Breezy Gust and Rick Kang Most of us enjoy, appreciate, and strive to model detailed rolling stock, motive power, structures,
More informationIntroduction to Model Railroad Operations
Introduction to Model Railroad Operations Based on original by: Dave Cochrun & Kathy Sparks Revised by: Marshall Abrams Visit the Abrams Railroad Empire at http://abrams-railroad.potomac-nmra.org/ 1 Welcome!
More informationIntroduction to Model Railroad Operations
Introduction to Model Railroad Operations Based on original by: Dave Cochrun & Kathy Sparks Revised by: Marshall Abrams April 2, 2011 1 Welcome! Why Operations? You ve built your empire, what do you do
More informationKCS 3 rd Subdivision. Dispatch Console Operating Instructions. Console Orientation. CTC System Orientation (center screen)
1 Dispatch Console Operating Instructions KCS 3 rd Subdivision Dispatch Console Operating Instructions Console Orientation The Dispatch Console consists of three screens, from left to right: Left screen:
More informationThe Train Order Operator R. Kang
The Train Order Operator (Station Agent-Telegrapher) by Rick Kang edited C. Comstock Job Description Liaison between Train and Engine Crews and Train Dispatcher via Telegraph or Telephone and Radio, Eyes
More informationSOUTHERN PACIFIC RAILROAD RULES OF OPERATION
Contents 2.0 RAILROAD RADIO RULES... 3 2.1 Transmitting... 3 2.2 Required Identification... 3 2.3 Repetition... 3 2.4 Over... 3 2.5 Out... 3 2.6 Communication Not Understood Incomplete... 4 2.8 Acknowledgment...
More informationWorking the eastbound way freight on the HO Maumee Route
>> A day on Working the eastbound way freight on the HO Maumee Route 5:30 a.m. We start our day at the Yard engine terminal on Bill Darnaby s HO Maumee Route. Our engine, Mikado no. 521, is waiting for
More informationCard Order Update Training March 2011
Card Order Update Training March 2011 TOPICS Operations Why, What & How Call Board Yards & Permissions Operating Tips Manifests Interactive Lessons Card Order Basics What are we trying to do? Railroads
More informationGETTING STARTED IN MODEL RAILROAD OPERATIONS: A SIMPLE SWITCH LIST SYSTEM Arthur Boyd C&P Junction October 2013
GETTING STARTED IN MODEL RAILROAD OPERATIONS: A SIMPLE SWITCH LIST SYSTEM Arthur Boyd C&P Junction October 2013 From Train Layout to Model Railroad As model railroaders, we make models of the real thing
More informationOPERATOR TRAINING MANUAL
Pine Creek Railway OPERATOR TRAINING MANUAL Overview The Pine Creek Railway (PCRY) is a freelance Ohio model railroad set in the mid 1970 s period. It is a single-track point-to-point style railroad with
More informationCONTENTS OPERATING SCHEDULES...18 TRANSPORTATION SCHEDULES...20
v 11. BACKGROUND KNOWLEDGE - 1 THE TERRITORY...1 ACTIVITIES...4 12. PEOPLE - 7 13. TRAFFIC - 14 FREIGHT TRAINS...14 PASSENGER TRAINS...16 INTERCITY TRAINS...17 REGIONAL TRAINS...17 COMMUTER TRAINS...17
More informationOperating Sessions Co-Hosted by the Garden State And Hudson Valley Divisions
Operating Sessions Co-Hosted by the Garden State And Hudson Valley Divisions 1 To Table of Contents Table of Contents Layout Operating Schedule... 3 Dave Abeles: Conrail s Onondaga Cutoff... 4 Craig Bisgeier:
More informationCard Order Basics. What is It?
Card Order Basics Card Order Basics What is It? An advanced scheme for operating a model railroad Allows for a realistic means of determining what car goes to what location & when Uses individual pieces
More informationCORA REVISION: AMTRAK
THE BELT RAILWAY COMPANY OF CHICAGO Office of General Manager Transportation May 31, 2006 Notice No. 4 **In Effect 12:01 AM June 1, 2006** TO ALL CONCERNED: All Notices issued from January 1, 2004 through
More informationOperating Rules. Making multiple tail room moves. For holding tail room at an
1.0 Definitions BUFFALO LINE Operating Rules 1.0a Prototype derived definitions. Term head room holding head room tail room holding tail room foul double drilling set out pick up constrained restricted
More informationBNSF OPERATIONS TESTING REFERENCE GUIDE Remote Operations Testing /Audit Supplement April 01, 2008
BNSF OPERATIONS TESTING REFERENCE GUIDE Remote Operations Testing /Audit Supplement April 01, 2008 INTRODUCTION Operations testing is mandated by federal regulation and BNSF policy to determine extent
More informationHow to use card cards to enhance running your Railroad
How to use card cards to enhance running your Railroad Operations is simulating the day-to-day activities of a real railroad Picking up freight, Assembling trains, Delivering cars to consignees, Sorting
More informationOperations on the Pennsylvania Southern Railroad
Operations on the Pennsylvania Southern Railroad Presented by Bob Weinheimer MMR National Model Railroad Association Cleveland 2014 July, 2014 Operations on the Pennsylvania Southern Introduction Layout
More informationNational Model Railroad Association
NMRA - AP Chief Dispatcher http://nmra.org/education/achievement/ap_dispatch.html National Model Railroad Association Home :: Achievement Program :: Chief Dispatcher Achievement Program Chief Dispatcher
More informationNWP Op Session Orientation
NWP Op Session Orientation Welcome to my rendition of the Northwestern Pacific. This layout is the third incarnation of this concept; construction started in 2003 and the beginnings of operation began
More informationGreat Northwestern Railway Company
GENERAL CODE OF OPERATING RULES For The Great Northwestern Railway Company (ABBREVIATED) OPERATING DEPARTMENT Revision 4 Effective April 15, 1973 Great Northwestern Railway Rules and Regulations Page 2
More informationHeavener Yard Yardmaster s Playbook
Heavener Yard Yardmaster s Playbook Warning: Do not drive or operate heavy equipment or machinery while using this guide. May cause drowsiness and/or extreme boredom. Welcome to Heavener Yard on the Kansas
More informationRailroad Operation Basics. Clinic By Charlie Stapleton May 27, 2008
Railroad Operation Basics Clinic By Charlie Stapleton May 27, 2008 UNION PACIFIC RAILROAD KANSAS DIVISION OPERATIONS. AM Station call letters are as follows: KC = Kansas City TK = Topeka MN = Manhattan
More informationNORAC OPERATING RULES Eighth Edition January 1, 2003 Northeast Operating Rules Advisory Committee SPEEDS
NAC OPERATING RULES Eighth Edition January 1, 2003 Northeast Operating Rules Advisory Committee The Definitions and Rules Listed Apply to Operating in the Chicago Area AUTOMATIC BLOCK SIGNAL SYSTEM (ABS)
More informationA Quick & Easy Start for Operations. A Clinic for Beginners
A Quick & Easy Start for Operations A Clinic for Beginners Operations: Meaning and Myths Operation includes: Purposeful movement of rail cars and trains Simulation of some aspects of real railroading Fun
More informationFROM FREELANCE TO PROTOTYPE
FROM FREELANCE TO PROTOTYPE Ways to improve your layout s representation of the prototype without doing a total makeover GAYLORD GILL OCTOBER 2018 1 Model Railroading A Continuum Toylike appeals to the
More information2. Q. In the event a member of yard crew consisting of a foreman and one
1 Article I (Crew Consist) 1. Q. Does this agreement affect the Initiated Act I of 1972 which repealed Arkansas' railroad crew laws? A. No. 2. Q. In the event a member of yard crew consisting of a foreman
More informationWe are driving according to the official Amtrak timetable. You can check the schedule anytime opening the session info window.
SESSIONS FOR MARIAS PASS ROUTE AMTRAK NR. 8 ENGINEERS EXPERIENCE Hello and welcome on board of the Amtrak Nr. 8 - Empire Builder. The train left Portland (OR) yesterday at 4:40 PM and is now approaching
More informationCar Orders without the Numbers or Operation without Aggravation
Car Orders without the Numbers or Operation without ggravation Earl T. Hackett, Jr. Introduction and Credits This is an operating system introduced to me at a Regional Meet in Grand Rapids by Dan Hinel
More informationTools and techniques to create an operating scheme
Tools and techniques to create an operating scheme BY DOUG LEE MEMBER OF LAYOUT DESIGN (LDSIG) AND OPERATIONS (OpSIG) SPECIAL INTEREST GROUPS PRESENTED TO CALGARY MODEL RAILWAY SOCIETY OCTOBER 14 2018,
More informationStandard 6 by 4 inch index card
Midnight Beer Train First train of session or begins once Afternoon Yard Job ends Begins in Humboldt Yard Pick up transfer engine at Yard Office Find switch list for outbound trains left by Yard Crew Collect
More informationSubpart C_Roadway Worker Protection
[Code of Federal Regulations] [Title 49, Volume 4] [Revised as of October 1, 2007] From the U.S. Government Printing Office via GPO Access [CITE: 49CFR214] [Page 168-177] TITLE 49--TRANSPORTATION CHAPTER
More informationRAILROAD & CO. +Street. Version 9. Manual
RAILROAD & CO. +Street Version 9 Manual September 2017 RAILROAD & CO. +Street Control of Car Systems Version 9 Manual September 2017 Copyright Freiwald Software 1995-2017 Contact: Freiwald Software Kreuzberg
More informationDAILY OPERATING BULLETIN NO In Effect: 16:04 (A) Temporary Speed Restrictions and Other Conditions in effect: (B) Work Zones:
The Belt Railway Company of Chicago DAILY OPERATING BULLETIN NO. 10359 In Effect: 01/25/2018 @ 16:04 (A) Temporary Speed Restrictions and Other Conditions in effect: Kenton Line MT1 MT2 MT3 WL SR 001 MP
More informationTucson & Southwestern Railroad Company
Tucson & Southwestern Railroad Company RULES AND REGULATIONS OF THE OPERATING DEPARTMENT SECOND EDITION Revised April 2, 2013 Effective Monday, December 1, 1952 Notes: Copy No. This book is the property
More informationRoadway Worker Protection (RWP) 49 CFR Part 214 Subpart C and Railroad Communications
Federal Railroad Administration Roadway Worker Protection (RWP) 49 CFR Part 214 Subpart C and Railroad Communications 220.11 RWP 2010 Federal Railroad Administration 1 Presentation Notes This presentation
More informationOroville Track Change Proposal December 21, 2012 Robert Schott
Oroville Track Change Proposal December 21, 2012 Robert Schott SMRHS Board of Directors: Please consider this proposal to change the track and industrial configuration at Oroville. I believe this proposal
More informationA Sophisticated Transit Signal Priority System How it Works
A Sophisticated Transit Signal Priority System How it Works Ron Stewart, P. Eng. Associate Director IBI Group, 230 Richmond Street West, 5 th Floor Toronto, ON M5V 1V5 Canada Phone: 416-596-1930 Fax: 416-596-0644
More informationLayout design element. in N scale. It was time for a new railroad to realize new objectives. By Daryl Kruse//Photos by the author
Layout design element Modeling UP s in N scale It was time for a new railroad to realize new objectives By Daryl Kruse//Photos by the author 16 Model Railroad Planning 2013 Geneva Sub 1. In the model and
More informationINDIANA HARBOR BELT RAILROAD COMPANY
Page 1 of 7 INDIANA HARBOR BELT RAILROAD COMPANY BULLETIN ORDER NO. S-25 December 30, 2015 Effective 0001, Sunday, January 3, 2016 Last General Order in effect: 301 A) Operating Manuals 1. Timetable Authority
More informationUNION PACIFIC RAILROAD COMPANY
ST. LOUIS TIMETABLE NO. 5 EFFECTIVE May 27, 2013 CHESTER SUBDIVISION GENERAL ORDER NO. 20 PURPOSE: SI-07: Add Talk On Arrival and Defect Only to selected detectors.. Previous Changes: SI-07: Delete Talk
More informationYosemite Valley Railroad Company
STANDARD CODE OF Yosemite Valley Railroad Company RULES AND REGULATIONS OPERATING DEPARTMENT N o 280 THIS BOOK is the property of YOSEMITE VALLEY RAILROAD CO. and is loaned to NAME EMPLOYED AS Who hereby
More informationShipperConnect User s Guide. Electronic Customer Interface for Rail Shippers
ShipperConnect User s Guide Electronic Customer Interface for Rail Shippers Copyright Copyright 2006 RMI. All Rights Reserved. Printed in the United States of America. RMI - Delivered under license agreement.
More informationLayout Design for Operations. Steve Davis Tom Vanden Bosch
Layout Design for Operations Steve Davis Tom Vanden Bosch What IS Model RR Operations? OUR Opinion: A model railroad designed for Operations is designed to replicate the look, feel, purpose and tasks of
More informationUNION PACIFIC RAILROAD COMPANY CIRCULAR UP 6602-A (Replaces Circular SP 4593-series)
1 st Revised Title UNION PACIFIC RAILROAD COMPANY CIRCULAR UP 6602-A (Replaces Circular SP 4593-series) GENERAL LOADING RULES, ACCESSORIAL CHARGES AND FUEL SURCHARGE FOR COAL TRAINS ORIGINATING IN COLORADO
More informationSection 3: Railroads and Anhydrous Ammonia Transport. Lesson Goal
Section 3: Railroads and Anhydrous Ammonia Transport 60 min. Lesson Goal After completing this lesson, the student shall have the knowledge and skills to help them respond to rail transportation emergencies
More informationOperations Analysis using Simulation Modeling to Evaluate Capacity Requirements. for Direct Intermodal Rail Facilities at the Port of Long Beach
Operations Analysis using Simulation Modeling to Evaluate Capacity Requirements for Direct Intermodal Rail Facilities at the Port of Long Beach Beth C. Kulick Sr. Professional, TranSystems Corporation
More informationMODELING THE CEMENT MILLS OF THE BANGOR & PORTLAND BRANCH
MODELING THE CEMENT MILLS OF THE BANGOR & PORTLAND BRANCH Modeling examples of the Portland Cement Mills RPM Valley Forge 2014 By Paul Cappelloni AGENDA Background Portland Cement Process Traffic In and
More information2015 HDR, all rights reserved.
2015 HDR, all rights reserved. How do you Spell Capacity on a Railroad? - A Primer on Railroad Operations Design Kevin Keller, PE HDR Engineering, Inc. 2015 HDR, all rights reserved. Outline Introduction
More informationFreight Car Handling and Distribution
Freight Car Handling and Distribution by Anthony Thompson Freight trains of loaded and empty cars, freight yards with a variety of cars among the yard tracks, local freight switching at industries, and
More informationAll reservations are based upon availability. Due to the limited number of buses, special event services may not always be available.
Parking & Transportation Services is pleased to provide shuttle rentals on a first come, first serve basis to any university department or group affiliated with Florida Atlantic University (FAU), for university
More informationHow Paratransit Software Improves Trip Booking
How Paratransit Software Improves Trip Booking 1 The Secrets To Better Trip Booking Much of the information that we try to express in our day-to-day communication is with regards to the major differences
More informationA Waybill Based Operating SYSTEM
L O T H L O R I E N L i n e s MandY The Mechanicsburg and York Railroad Article for The Dispatcher s Office -- OPSSIG quarterly publication. A Waybill Based Operating SYSTEM A few years ago, after starting
More informationTable of Contents. Installation. Introduction. Knowing your Train. Route Timetable. Trackside Signs. Game Credits
2 Table of Contents Installation. 3 Introduction. 4 History. 5 Knowing your Train. 6 Route Timetable. 8 Trackside Signs. 9 Signals...10 Game Credits...11 3 Installation If you are reading this document,
More informationRail Freight and Passenger
Take Care of the System Critical Investments in the areas of: Rail Freight rehabilitate rail bridges o Rail Bridge Inventory Database... $0.5 - $1.0 million (one time) Rail Freight rail replacement and
More informationWILL NOT BE ACCEPTED.)
Parking & Transportation Services is pleased to provide shuttle rentals on a first come, first serve basis to any university department or group affiliated with the University of Memphis, for university
More informationtrain and engine movement from C&NW tracks to Westward main track. Normal indication of Signal 3587 is STOP and will SPECIAL INSTRUCTIONS-continued
SPEED RESTRICTIONS SUBDIVISION 5 MPH MP 335 Pole 31 to MP 358 Pole 25 (Except as shown below) 20 East 18th Street to West 16th Street Des Moines 10 MP 358 Pole 25 to MP 363 Pole 3 30 MP 365 Pole 11 to
More informationARTICLE 29- ROAD-YARD MOVEMENTS. Section A - Road-Yard Movements
gz ARTICLE 29- ROAD-YARD MOVEMENTS Section A - Road-Yard Movements Art. Art. Art. Art. Art. 36, Sec. 33, Sec. l7, Sec. 36, Sec. 33, Sec. A Bkm B Cdr F Bkm B Bkrn A Cdr Art. 33, Sec. C Cdr MIA eff. 1116162
More informationEP US RAIL SERVICE ISSUES - DATA COLLECTION
1. System-Average Train Speed by Train Type for the Reporting Week (MPH) Intermodal 31.7 AAR train speed measure. Calculated by dividing train-miles by total Grain unit 24.0 hours from origin to destination,
More information~Contractor Services Group~ Vol. 1 Issue
Vol. 1 Issue 9 7.01.2014 Message to Install Partners 4 th of July Readiness Quiz! Top Provider Performers Recognition ~ In Home Compliance Corner: ~ COS Process ~ Verifying Product Availability Dates ~
More informationTGBO Q&A Final. TGBO are applicable on main tracks (including signalled sidings and signalled tracks) outside of DOB limits.
General What is a Tabular General Bulletin Order (TGBO)? A document providing, in a tabular format, the information or instructions contained in each GBO, which affect a specific train or engine within
More informationThe High Cost of Paper How paper-based processes take time and money out of service-based businesses.
Intuit powered by Corrigo Field Service Management ES Special Report: The High Cost of Paper How paper-based processes take time and money out of service-based businesses. trademarks of Intuit, Inc. in
More informationSpecial edition paper Development of a Total Operation Management System
Development of a Total Operation Management System Keita Hara*, Hisashi Kojima*, Fumihiko Henda* and Takashi Watanabe* Among the various tasks involved when a train schedule is disrupted, transmitting
More informationAccount Walkthrough 2017
Account Walkthrough 2017 Contents Version 2.0 The Dashboard Page 2 Viewing Bookings Page 3 Managing the Booking Flow My Pricing Page 4 Mileage Rates Uplifts for Larger Vehicles Page 5 Minimum Fares Mileage
More informationLOCAL FREIGHT SERVICE
RULE 23: LOCAL FREIGHT SERVICE LOCAL FREIGHT SERVICE a) Trains loading or unloading way freight handling supply trains, working battery cars, spotting stock cars to load or unload, spotting and unloading
More informationTHE BELT RAILWAY COMPANY OF CHICAGO. Train Dispatcher Rules & Instructions
THE BELT RAILWAY COMPANY OF CHICAGO Train Dispatcher Rules & Instructions EFFECTIVE 00:01, June 1, 2006 TABLE OF CONTENTS Supervision 3 Duties of Train Dispatchers 3 Records Kept 3 Notification of Clerical
More informationChanges to the ATAB 6 Mass Casualty Incident Response. Draft to ATAB 6 Committee September Accepted by ATAB-6 October 27, 2015
Changes to the ATAB 6 Mass Casualty Incident Response Draft to ATAB 6 Committee September 2015 Accepted by ATAB-6 October 27, 2015 Prepared by: Peter Mackwell EMT-P Mass Casualty Incident Plan Initial
More informationLinkage of a conventional line dispatch system with the Shinkansen dispatch system
Computers in Railways XII 121 Linkage of a conventional line dispatch system with the Shinkansen dispatch system Y. Yoshino Administration Division, Transportation Department, Kyushu Railway Company, Japan
More informationKWT Charge Schedule. Optional Services Catalog Customer Switching and Accessorial Services
Charge Schedule Item 6000 Intra-Plant Switch ^$350 Item 6010 Intra-Terminal Switch ^$400 Item 6020 Inter-Terminal Switch ^$400 Item 6210 Diversion/Re-consignment ^$400 Item 6040 Error Moves ^$550 KWT 7006-7
More informationKansas Rural Transit ITS Deployment
Kansas Rural Transit ITS Deployment Evaluation Prepared for the ENTERPRISE Pooled Fund Study January, 2008 Table of Contents 1. Introduction... 1 2. Evaluation Goals... 1 3. Deployed Transit Systems...
More informationMacroscopic and Microscopic Simulation for the Evaluation of People Mover Systems. Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany
Macroscopic and Microscopic Simulation for the Evaluation of People Mover Systems Dr.-Ing. Peter Mott Sven Beller PTV AG, Karlsruhe, Germany 1. Introduction This paper is intended to show how a comprehensive
More informationNon-Emergency Medical Transportation
HOW TO REQUEST Non-Emergency Medical Transportation This a guide on how to use the transportation benefits offered by the HUSKY Health Program Table of Contents Important Resources 3 What Is NEMT? 3 Who
More information[Docket No. FRA ; Notice No. 1] [Draft Safety Advisory ] Draft Safety Advisory Related to Temporary Signal Suspensions
This document is scheduled to be published in the Federal Register on 04/23/2018 and available online at https://federalregister.gov/d/2018-08406, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION
More informationDRAFT RAIL OPERATION REPORT DOCUMENT 6.7. The Northampton Gateway Rail Freight Interchange Order 201X. Regulation No: 5 (2) (q)
DRAFT RAIL OPERATION REPORT DOCUMENT 6.7 The Northampton Gateway Rail Freight Interchange Order 201X Regulation No: 5 (2) (q) DRAFT RAIL OPERATION REPORT OCTOBER 2017 www.northampton-gateway.co.uk Report
More informationTECHNICAL MEMORANDUM. DRAFT Existing Freight Operations along Cotton Belt Corridor between DFW Airport and Plano, TX
TECHNICAL MEMORANDUM To: DART/URS Cotton Belt Project Staff From: URS/Stantec Date: October 11, 2010 (revised 12/30/13) RE: DRAFT Existing Freight Operations along Cotton Belt Corridor between DFW Airport
More informationRailroading Merit Badge Workbook
Merit Badge Workbook This workbook can help you but you still need to read the merit badge pamphlet. This Workbook can help you organize your thoughts as you prepare to meet with your merit badge counselor.
More informationSkills of Highly Effective Freight Brokers
Atex Freight Broker Training, Inc. Skills of Highly Effective Freight Brokers John D Thomas www.atexfreightbrokertraining.com www.atexfreightbrokerhomestudy.com Introduction Just as in any other business,
More informationR&D on Signal Control Systems and Transport Operations Systems
Interpretive Article R&D on Signal Control Systems and Transport Operations Systems General Manager (Information Technology), Advanced Railway System Development Center Tamotsu Kato In railway transport
More informationDevelop Performance Measures
Develop Performance Measures A performance measure is used to measure output or outcome, such as assessing the impact of corrective actions on safety. They enable stakeholders to monitor changes in system
More informationBNSF Railway. Moving you Forward
BNSF Railway Moving you Forward Northwestern University Transportation Center April 15, 2010 All slides are copyright 2010, BNSF Railway Company, All Rights Reserved. No part of this publication may be
More informationTrends in the U.S. Rail Network. Mike McClellan Vice President Industrial Products Midwest Association of Rail Shippers July 15, 2014 Lake Geneva, WI
Trends in the U.S. Rail Network Mike McClellan Vice President Industrial Products Midwest Association of Rail Shippers July 15, 2014 Lake Geneva, WI 1 The Dynamics in US Rail Freight Traffic The (Growing)
More informationNational Transportation Safety Board Washington, D.C. 20594 Safety Recommendation Date: JAN 1 2 2012 In reply refer to: R-11-1 0 Mr. Dennis R. Pierce National President Brotherhood of Locomotive Engineers
More informationCrowd Management at Stations A good practice guide
Crowd Management at Stations A good practice guide Issue: 01 October 2004 http://www.rssb.co.uk The negative effects of crowds may be more than service delays and unhappy passengers. Crowding can also
More informationGCOR. General Code of Operating Rules. Transition Guide. Effective April 1, 2015
GCOR General Code of Operating Rules Transition Guide Effective April 1, 2015 This guide contains changes from the GCOR Sixth Edition to the GCOR Seventh Edition in effect April 1, 2015 These rules herein
More informationNomination for Virginia Railway Express 2013 Rail Disaster Drill. Category: Emergency Preparedness- Rail Security Awarding
Nomination for Virginia Railway Express 2013 Rail Disaster Drill Category: Emergency Preparedness- Rail Security Awarding Attachments: 1 Letter from Fairfax Fire and Rescue Introduction Virginia Railway
More informationINDIANA HARBOR BELT RAILROAD COMPANY. BULLETIN ORDER NO. S-32 August 31, 2018
Page 1 of 6 INDIANA HARBOR BELT RAILROAD COMPANY BULLETIN ORDER NO. S-32 August 31, 2018 Effective: 0600 Sunday September 02, 2018 General Orders in effect: NONE A. Operating Manuals 1. Timetable Authority:
More informationReducing the response times of emergency vehicles in Queensland
Reducing the response times of emergency vehicles in Queensland John a a Transmax Pty Ltd Abstract To address a growing and ageing population in Queensland and increased demand for emergency services,
More informationFAIR LABOR STANDARDS ACT TRAVEL: DETERMINING COMPENSABLE TIME FOR NON-EXEMPT EMPLOYEES Created by MU HRS 04/2005 Updated by CMU 10/2016
FAIR LABOR STANDARDS ACT TRAVEL: DETERMINING COMPENSABLE TIME FOR NON-EEMPT EMPLOYEES Created by MU HRS 04/2005 Updated by CMU 10/2016 Under the Fair Labor Standards Act (FLSA) a non-exempt employee must
More informationRunning Trains with JMRI s Dispatcher
Running Trains with JMRI s Dispatcher Dave Duchamp Dick Bronson (Co- Presenter) Bob Jacobsen (Co- Presenter) What is Dispatcher? Dispatcher provides functionality and organizes information for dispatching
More informationROADWAY WORKER PROTECTION
ROADWAY WORKER PROTECTION 1 TRAINING This training explains the ON-Track Safety requirements for ALL roadway workers and is presented in two (2) modules: Basic Requirements EIC Qualification All instructions
More informationWe have now introduced a new layout when you first load up the app as can be seen in the image below.
Dean Taxis New App User Guide After lots of testing and customer feedback sessions, Dean Taxis is pleased to announce its new and improved booking app. This will be getting rolled out over the next week
More informationMemorandum of Agreement between BNSF Railway and the Brotherhood of Locomotive Engineers and Trainmen
Memorandum of Agreement between BNSF Railway and the Brotherhood of Locomotive Engineers and Trainmen Pursuant to BNSF s letter dated February 24, 2017, a multi-directional pool will be established at
More informationWheeling and Lake Erie Railway Co. TARIFF WE A GENERAL RULES FOR UNLOADING AND HANDLING OF BULK COMMODITY TRAINS
Original Title Page TARIFF WE 40341-A GENERAL RULES FOR UNLOADING AND HANDLING OF BULK COMMODITY TRAINS Issued : October 7, 2002 Effective: October 7, 2002 (except as otherwise provided herein) Amended
More informationCCKY Charge Schedule. Optional Services Catalog Customer Switching and Accessorial Services
Charge Schedule Item 6000 Intra-Plant Switch ^$350 Item 6010 Intra-Terminal Switch ^$400 Item 6020 Inter-Terminal Switch ^$400 Item 6210 Diversion/Re-consignment ^$400 Item 6040 Error Moves ^$550 Item
More information