Single and Multiple Outage Statistics in Turkish National Power Transmission System
|
|
- Rudolf Fitzgerald
- 6 years ago
- Views:
Transcription
1 Single and Multiple Outage Statistics in Turkish National Power Transmission System Aydogan Ozdemir, Mustafa Bagriyanik, Ilim Erden Department of Electrical Engineering Istanbul Technical University Istanbul, TURKEY (ozdemiraydo, Yener Akkaya APK Devision Turkish National Power Transmission Company Ankara, TURKEY Abstract Detection of failure propagation and prevention of cascading outages is crucial to maintain power system reliability and security. Multiple outage and cascading failures have been one of the most important problems of Turkish National Power transmission system. Past records show that the Thrace part of the system has suffered from this multiple outages. This paper presents the initial phase of the project involving analysis, mitigation and prevention of multiple outages in the region. It is a statistical outage analysis of a 7 year period between It is concentrated on the occurrences and the durations of the outages. Keywords-outage, outage duration, multiple outage, cascading failures I. INTRODUCTION Network interconnections over the years due to economical development and the population growth have increased the steady-state operational efficiency of the system. In addition, non-utility generators, independent power producers and several reactive power control devices have brought the system to a new stage. However, all those improvements have also increased the operational uncertainty, making the system dynamic behavior more complicated, and expanding the impact of local power grid failure into region electrical network nearby, which is more likely to lead to blackouts caused by cascading outages. Right-of-way restrictions and limitations on building new transmission lines have increased transmission line loading and such an operation close to the stability limits have increased the probability of cascading event occurrences as well as system blackout risks. Cascading outages in a power system occur when one or more of the partially or completely failed element shifts their load to nearby elements in the system. Those nearby elements are then subjected beyond their capacity so they become overloaded and shift their load onto other elements. These events are rare events and it is generally difficult to predict combinations of individual events such as single line outages. There have been several efforts to estimate the rare-event probabilities and to develop new methods, technologies and tools in order to better understand, predict, prevent and restore the cascading outages as well as to mitigate the effects of cascading outages [1-4]. Risk based reliability studies has been conducted due to the number of severe blackout events occurred across the globe in the recent years Power systems are normally designed to maintain the secure operating state in case of all N-1 contingencies as well as in case of some N-2 contingencies. However, incorrect settings of protective relays as well as protection system maloperations may destroy this secure operation and result in cascading events. Recent studies show that the power protection system plays an important role not only in any possible initial triggering, but in further propagating the disturbances. Since the protection system outages have critical impact on power system reliability, the researchers have concentrated on the reliability of protection systems to identify the protection outage effects on power systems, and to enhance power system reliability considering the protection failures. [5,6] It is clear that data collection is the initial phase of development of new models, methods, technologies and tools in order to better understand, predict prevent and restore the cascading outages [9,10]. This study presents single and multiple outage statistics of Turkish National Power Transmission System-Thrace Part. It is the initial part of an ongoing project involving analysis, mitigation and prevention of cascading events. The data belongs to a 7 year period between Single outages and their classifications were later followed by multiple outage statistics. II. TURKISH NATIONAL ELECTRIC POWER SYSTEM AND THE THRACE SECTION Turkish electricity transmission system has a total transmission capacity of MVA. It is composed of 154 kv and 380 kv sub-systems. In addition there are some 220 kv Interconnection lines connecting Turkish system to Georgia, to Armenia, to Bulgaria and to Greece. Thrace part of Turkish National Power Transmission System is the most power consuming part of Turkey (30-35 %). There are 174 buses, 267 transmission lines/hv cables, 65 transformers. 154 kv system comprises 4-5 islands under normal operating conditions. This project is supported by Turkish Electricity Transmission Company
2 The protection system includes 40 line differential relays for cables, 453 distance relays and 447 overcurrent relays. The system is fed at several locations by the Turkish National Electric Power Transmission System and there are some internal power plants. Past records showed that the number of outages in this part of Turkish National Power Transmission system was more than it was expected and also more than the number of outages at the other parts of the system. In addition, several cascading events were also experienced, especially in adverse weather conditions. Therefore, LOLE and the other reliability indexes were greater than the similar indexes for this type of systems. III. OUTAGE STATISTICS Outage data statistics were collected for the following categories: kv power transmission lines/cables, kv power transmission lines/cables, - 66 kv sub-transmission lines, - HV/Medium Voltage Power transformers, kv/154 kv auto transformers. Transmission line/cable outages include both the failures along their length and the station oriented failures at both ends. The number of outages and outage durations are summarized in Table I-II for each category. The tables include both the single and the multiple outages. Note that the outages include both the momentary and the sustained outages, whereas outage durations are the average values of sustained outages. Outage numbers and the outage durations include all the single outages and the multiple outages. It is clear that both the number of outages and the outage durations are high in 2001 and Actually this is because of multiple outages occurred in these years is the best year, showing the minimum number of outages and outage durations. On the other hand, the number of outages shows more uniform variation when compared with outage durations. 6 different conductor configurations and 9 different conductor configurations are used in 380 kv system and 154 kv system, respectively. Average failure numbers per year per 100 km line length and average outage durations per outage are illustrated for each type of transmission lines/cables are illustrated in Figure 1-4. Figure 1. Number of outages per year per 100 km of each 380 kv transmission line types TABLE I. NUMBER OF OUTAGES DURING PERIOD σ 380 kv lines kv lines/cables kv subtr.lines Power Transf Autotrf TOTAL Figure 2. Average outage durations per outage for 380 kv transmission lines TABLE II. OUTAGE DURATIONS DURING PERIOD [HOURS] σ 380 kv lines kv lines/cables kv subtr.lines Power Transf Autotrf TOTAL Figure 3. Outages per year per 100 km of each 154 kv transmission line/cable types
3 versus transmission line/cable lengths is illustrated in Figure 5 and 6 for 380 kv system and 154 kv system respectively. Note that all the single and multiple outages are taken into account while constructing the regression lines. Both the 154 kv and the 380 kv transmission line/cable outage rates are much greater than the conventional values used in power transmission reliability analysis. Figure 4. Average outage durations for several 154 kv transmission lines and cables Both the annual failures per 100 km and the average outage durations show a uniform distribution for 380 kv system. However, there are significant differences between the outage durations and annual outages per 100 km of 154 kv transmission components. It is mainly because of cable (K1000) failures and multiple outages Average outage duration of sustained outages is illustrated in Table III for the transmission lines and the transformers. Outage durations of transformer outages are greater than the outage durations of the transmission lines/cables. It is interesting that the outage duration of a 154 kv transmission line/cable is greater than the outage duration of 380 kv transmission line. Figure 5. Annual outage numbers versus transmissin line/cable length for 380 kv system TABLE III. AVERAGE AUTAGE DURATION OF SUSTAINED OUTAGES [HOURS:MINUTES] Σ 380 kv lines 2:04 4:04 4:06 3:59 2:50 2:04 1:32 2:57 1: kv 3:05 5:01 3:43 lines/cables 2:57 6:41 2:15 3:31 3:53 1:23 66 kv 1:23 2:52 0:48 subtr.lines 4:22 4:33 2:00 2:00 2:34 1:19 Power Transf. 4:51 6:21 4:56 10:42 12:20 15:38 8:12 9:00 3:46 Autotrf. 3:22 1:30 0:54 2:38 4:32 3:22 3:57 2:53 1:12 The outage rates of transmission lines/cables are estimated by using the scatter diagram-regression analysis method [7]. The regression method provides a means for making confidence statements about line outage. Number of outages Figure 6. Annual outage numbers versus transmissin line/cable length for 154 kv system It is well known that there is strong correlation between the outages, outage durations and the atmospheric conditions. Outage numbers and outage durations for each month are illustrated for the transmission lines and the transformers in Table IV and V. TABLE IV. AVERAGE NUMBER OF PERMANENT OUTAGES DURING PERIOD Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec AVG 380 kv lines kv lines/cables kv subtrans. lines Power Transformers Autotransformers TOTAL
4 TABLE V. PERMANENT OUTAGE DURATIONS DURING PERIOD [HOURS:MINUTES] Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Σ AVG 380 kv lines 50:08 58:48 36:02 19:47 28:16 68:21 76:10 51:08 29:00 20:57 24:06 115:07 577:56 48: kv lines/cables 438:59 161:46 53:40 81:41 136:45 101:11 108:48 170:38 86:57 178:08 266:02 284: :35 172:27 66 kv subtrans. lines 40:16 26:23 101:37 3:10 2:42 20:19 5:10 9:37 15:45 2:20 63:25 58:44 349:32 29:07 Power Transformers 245:47 154:04 117:03 61:23 51:57 111:22 123:55 139:08 103:06 186:26 69:07 231: :43 132:53 Autotransformers 20:27 5:50 13:17 6:33 9:58 16:29 18:50 10:13 17:18 5:51 8:03 26:34 159:28 13:17 TOTAL 795:39 406:53 321:40 172:37 229:39 317:43 332:56 380:45 252:08 393:45 430:45 716: :16 395:56 It seems that there are two critical periods for the outages; namely, winter period (November, December, January) and summer period (July and August). Summer outages are more than the winter outages. However, outage durations are much longer in winter time. The followings can be written for the outages. - Both the outage numbers and the outage durations are greater than they should be. - The system experiences more failures in Summer time, but the outage durations are much longer in winter times. - Annual outage duration is 4585 hours which corresponds 52% of overall operating period. Therefore, (N-1) criteria is not a secure operation condition. - The insufficiency is more clear during winter period. Total outage duration in January is 107% (795 hours) of operating time. - It is obvious that the system reliability level will be more critical if periodic maintenance tasks are taken into account. - The number of related (dependent) outages is high. They should be minimized by using improved protection coordination. IV. SINGLE AND MULTIPLE OUTAGES A multiple outage event is defined as the outages in which one outage occurrence is the consequence of another outage occurrence, or in which multiple outage occurrences were initiated by a single incident, or both [8]. High outage numbers and long outage durations in the region were assigned to be one of the indications of intensive multiple outages in the system. Therefore, outage records are classified as single and multiple outages. Table VI and VII illustrates the number and the duration of single and multiple outages in the region during period. Multiple outages are grouped with respect to the number of outages in the event. For example represents the multiple outage events including 4, 5 or 6 single outages. Table VIII shows the average duration of single and multiple outages. Table VI and Table VII show that 60% of overall outages are single (independent) outages and 75% of total outage duration comes from single outages. On the other hand, average duration of multiple outages decrease with increasing outage numbers in a multiple outage. TABLE VI. SINGLE AND MULTIPLE OUTAGES AVG Single Total TABLE VII. TOTAL SINGLE AND MULTIPLE OUTAGE DURATIONS [HOURS] Single Total TABLE VIII. AVERAGE DURATION OF SINGLE AND MULTIPLE OUTAGES [HOURS:MINUTES] Single 3:16 4:55 3:54 4:56 7:43 6:13 4:02 5: :44 6:26 2:46 2:31 2:20 1:13 1:26 2: :55 1:43 2:16 2:02 4:25 0:45 0:41 1: :46 0:36 0:46 0:10 1:28 2:36 0:36 1: :34 1:06 0:40 1:07 0:57 0:31 1:16 1:02 Single outage statistics that will be used for chance outage modeling of power transmission components can better be constructed from single outage data. Table IX and X illustrates the single outage statistics of 154 kv and 380 kv power transmission systems. The followings can be derived from the comparison of Tables IX and X with Tables I and II. Average single outages are approximately 60% of overall outages. All components show more uniform distribution besides 66 kv sub-transmission lines and autotransformers.
5 66 kv sub-transmission lines show more multiple outages due to their radial structure. 154 kv power transmission lines/cables are more effected from multiple-outages when compared with 380 kv transmission lines. Multiple-outages of 66 kv sub transmission system are longer. Duration of multiple outages is shorter. TABLE IX. NUMBER OF SINGLE OUTAGES DURING PERIOD 380 kv lines kv lines/cables kv subtr.lines Power Transf Autotrf TOTAL TABLE X. DURATION OF SINGLE OUTAGES DURING PERIOD [HOURS] 380 kv lines kv lines/cables kv subtr.lines Power Transf Autotrf TOTAL Final statistics regarding seasonal variation of cascading outages are illustrated in Table XI. Here cascading outages are assumed as the multiple outages including 10 or more outaged components. TABLE XI. SEASONAL VARIATON OF CASCADING OUTAGES (10+ OUTAGES) J F M A M J Jl A S O N D T TOT Table XI shows that there are again two critical periods for cascading outages; namely, summer and winter periods. Although the table shows that there are more cascading outages during the summer time, the duration of winter cascading periods are longer. This is a global result and more quantitative information will be given whenever outage duration statistics of cascading outages are finished. V. CONCLUSIONS AND DISCUSSION This study has presented single and multiple outage statistics of a critical part of Turkish national power transmission system. First, all outages and outage durations are presented on a component basis. Their seasonal variation and outage number versus transmission line/cable length were introduced. The results have showed that the system was seriously affected from multiple outages. Then, multiple outage statistics were introduced. The followings can be derived from this initisl attempt. Outage numbers and the outage durations are greater than they should be. (N-1) criteria cannot be accepted as a secure operation condition. (N-2) criteria should be satisfied, especially for winter period. The system experiences more failures in Summer time, but the failure durations are much longer in winter times. High number of outages and long outage durations don t give enough chance for periodic maintenance tasks. The number of related (dependent) outages is high. Radial structure of 66 kv sub-transmission system is the most critical one from related outages. High multi-outages are because of insufficiency in 154 kv system. 154 kv system should be extended buy additional transmission facilities. In addition, protection system should be improved, if required. The authority prefers multi-island operation under normal operating conditions because of high short circuit currents. Such an operation decreases the steady state security of the system as well as increases the number of local-cascading outages. Improved protection coordination and better islandingmode configuration is required to minimize the multiple outages in the system. ACKNOWLEDGMENT The authors would like to thank the Turkish National Electric Power Transmission Company for their support and encouragement for the study. References [1] H. Hu, X. Du, C. Xu, F. Zhao, X. Lin, Z. Bo, Risk Assessment of Cascading Failure in Power Systems Based on Uncertainty Theory, IEEE PES General Meeting, pp.1-5, July 2011, Detroit, USA. [2] J. Chen, J. S. Thorp, I. Dobson, Cascading dynamics and mitigation assessment in power system disturbances via a hidden failure model, Electrical Power and Energy Systems, vol. 27, no.4, pp , 2005 [3] S.P. Wang, A. Chen, C.W. Liu, C.H. Chen, and J. Shortle, Rare-event Splitting Simulation for Analysis of Power System Blackouts, IEEE PES General Meeting, pp. 1-7, July 2011, Detroit, USA
6 [4] H. Ren, I. Dobson, Using transmission line outage data to estimate cascading failure propagation in an electric power system. IEEE Trans.Circuits and Systems Part II, 2008, vol. 55, no. 9, pp [5] A.Ozdemir, M.Bagriyanik, I Ilisu, O. Gul, A.Kaypmaz, Y.Akkaya, Impacts of protection system misoperation on the reliability of Turkish National Power Transmission System, International Conference on Advanced Power System Automation and Protection APAP2011, October 16-20, 2011, Beijing-CHINA [6] J.S. Thorp, A.G.Phadke, S.H. Horowitz, S.Tamronglak, Anatomy of power system disturbances: importance sampling, International Journal of Electrical Power & Energy Systems, vol. 20, no. 2, pp , February [7] A.D.Patton, Determination and Analysis of Data for Reliability Studies, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-87 no. 1, pp , January [8] IEEE Standard Terms for Reporting and Analyzing Outage Occurrences and Outage States of Electrical Transmission Facilities, IEEE Std [9] R. B. Adler, S. L. Daniel, C. R. Heising, M. G. Lauby, R. P. Ludorf, T. S. White, An IEEE Survey Of U.S. And Canadian Overhead Transmission Outages At 230 kv and Above, IEEE Transactions on Power Delivery, vol. 9, no. 1, pp , January [10] Data Analysis Task Force, Working Group on Statistics of Line Outages, General Systems Subcommittee, Transmission & Distribution Committee, R. B. Adler (Chairman), S. L. Daniel, Jr., C. R. Heising, M. G. Lauby, R. P. Ludorf, T. S. White, vol. 9, no. 1, pp , January 1994.
CASCADING failure is the process by which initial outages
IEEE TRANSACTIONS ON CIRCUITS AND SYSTEMS II: EXPRESS BRIEFS, VOL. 55, NO. 9, SEPTEMBER 2008 927 Using Transmission Line Outage Data to Estimate Cascading Failure Propagation in an Electric Power System
More informationLoad Shedding Control Strategy in an Electric Distribution System
Load Shedding Control Strategy in an Electric Distribution System Cattareeya Suwanasri, Thanapong Suwanasri, and Nuttapong Prachuab Abstract This paper proposed the load shedding control planning in a
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationElectric Forward Market Report
Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08
More informationFERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA
FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA The following information submitted for this Part 4 of FERC Form No. 715 consists of PJM's current Planning Criteria, and each member
More informationLONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION
LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION www.teias.gov.tr CONTENT Overview of Turkish Transmission System Load and Generation Forecasts Preparing
More informationMitigating Extraordinary Events using Wide Area Monitoring Applications
2, rue d Artois, F-75008 PARIS 53 RECIFE 20 http : //www.cigre.org Mitigating Extraordinary Events using Wide Area Monitoring Applications E. JOHANSSON, K. UHLEN, G. KJØLLE Norwegian University of Science
More informationRisk Evaluation of Meridian Substation Transformers
BCTC-SPA-R008 August 8, 2005 Risk Evaluation of Meridian Substation Transformers Wenyuan Li System Planning and Performance Assessment BCTC August, 2005 1 Reliability Evaluation of Meridian Substation
More informationFundamentals of Transmission Operations
Fundamentals of Transmission Operations Equipment Outages PJM State & Member Training Dept. Objectives At the end of this presentation the Learner will be able to: Identify how weather may influence outage
More informationIdentification of Critical Lines in Power System Based on Optimal Load Shedding
Energy and Power Engineering, 2017, 9, 261-269 http://www.scirp.org/journal/epe ISSN Online: 1947-3818 ISSN Print: 1949-243X Identification of Critical Lines in Power System Based on Optimal Load Shedding
More informationTHE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks
THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Issued by: Review Cycle: Asset Management & Regulation, ESB Networks Three years Contents 1.0 Introduction....3 1.1 Definitions...3 1.2 Aim of Planning...5
More informationedart Roadmap As of February 21 st, 2018
edart Roadmap As of February 21 st, 2018 www.pjm.com Background edart (electronic Dispatcher Application and Reporting Tool) is suite of electronic applications used to facilitate dispatcher-to-dispatcher
More informationOperations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018
Operations Report Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average
More informationFacility Study. 100MW Solar Photovoltaic Generation Interconnection. Lake County, Florida
Facility Study 100MW Solar Photovoltaic Generation Interconnection Lake County, Florida October 30 st, 2012 This document and any attachments hereto ( document ) is made available by Progress Energy Company
More informationWoking. q business confidence report
Woking q1 business confidence report Woking q1 report headlines saw a new record in company registrations in Woking when compared to any previous. was a record quarter for company registrations in Woking
More informationedart Roadmap As of November 13 th, PJM 2017
edart Roadmap As of November 13 th, 2017 Background edart (electronic Dispatcher Application and Reporting Tool) is suite of electronic applications used to facilitate dispatcher-todispatcher communications,
More informationPOWER SYSTEM DYNAMICS AND CONTROL
POWER SYSTEM DYNAMICS AND CONTROL 1 POWER SYSTEM DYNAMICS AND CONTROL INTRODUCTION Electric power system comprises components and systems like Generators, transformers, transmission lines and distribution
More informationReview of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group
Review of Interconnection Assistance Reliability Benefits May 12, 1999 NPCC CP-5 Working Group NORTHEAST POWER COORDINATING COUNCIL WORKING GROUP CP-5 REVIEW OF INTERCONNECTION ASSISTANCE RELIABILITY BENEFITS
More informationMeter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager
Meter Data Management System (MDMS) Sharing Ricky Ip CLP Manager Agenda Introduction Objectives Critical Success Factors Change Management Lessons Learned 2 CLP Power Hong Kong Limited (CLP Power) is the
More informationSchedule 2 TECHNICAL INFORMATION
Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity
More informationPlatte River Power Authority. Ten-Year Transmission Plan ( )
Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.
More informationTHE IMPACT OF RESTRUCTURING URBAN AND SUBURBAN DISTRIBUTION GRIDS WITH SMART GRID APPROACHES ON SYSTEM RELIABILTY
THE IMPACT OF RESTRUCTURING URBAN AND SUBURBAN DISTRIBUTION GRIDS WITH SMART GRID APPROACHES ON SYSTEM RELIABILTY Matej REJC Gerhard HAFNER Alfred EINFALT, Andreas LUGMAIER Siemens AG - Austria Wiener
More informationStandards de planification du NERC
Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council
More informationUniversity of Michigan Eco-Driving Index (EDI) Latest data: August 2017
University of Michigan Eco-Driving Index () http://www.ecodrivingindex.org Latest data: August 2017 Developed and issued monthly by Michael Sivak and Brandon Schoettle Sustainable Worldwide Transportation
More informationThe Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009
The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 Growth of Wind Generation in ERCOT MW 12,000 10,000 8,000
More informationOperations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018
Operations Report Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 5.0 4.5 4.0 On-Peak Average
More informationOptimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events
IWAIS XIV, China, May 0 Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events Asim Haldar, Ph.D, P.Eng. ahaldar@nalcorenergy.com
More informationDUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA
DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic
More informationTrends in Streamflow and Water Level in Xiang River Basin in China
DRH-CASiFiCA Collaboration Meeting, Feb,, 8, Beijing Trends in Streamflow and Water Level in Xiang River Basin in China Bo CHEN Key Laboratory of Environmental Change and Natural Disaster, Ministry of
More informationDISTRIBUTION FEEDER PROTECTION WITH AND WITHOUT PV SYSTEM
DISTRIBUTION FEEDER PROTECTION WITH AND WITHOUT PV SYSTEM 1 PADMAVATHY.P, 2 PARTHASARATHY.S Department of Electrical and Electronics Engineering, Valliammai Engineering College, Anna University, Chennai.
More informationAESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS
APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,
More informationTo Study the Adequacy Assessment of Chitradurga distribution substation using MCS
To Study the Adequacy Assessment of Chitradurga distribution substation using MCS Shruthi.M 1, S.B.Karajgi 2 PG Scholar, Department of Electrical and Electronics, SDMCET, Dharwad, India 1 Professor, Department
More informationOvercoming Barriers to Power Purchasing from Very Small Renewable Energy Producers
from Very Small Renewable Energy Producers W. *, W. Limpananwadi**, B. Kamonsin** and P. Sripattananon** * Department of Electrical Engineering, Chiang Mai University, Chiang Mai 50200 THAILAND Email:worawit@doe1.eng.cmu.ac.th
More informationPotential Benefits of Regional Integration: Markets and Institutions
2 Potential Benefits of Regional Integration: Markets and Institutions Zoltán Tihanyi MAVIR ZRt. Electricity Market Integration 2.0 in Central and South East Europe Budapest, 30.05.2017 3 Contents The
More informationAESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)
(R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric
More informationTransmission System Security and Planning Standards
ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2
More information2017 KEY INSIGHTS ON. Employee Attendance and Tardiness
2017 KEY INSIGHTS ON Employee Attendance and Tardiness THE AVERAGE NUMBER OF MINUTES THAT EMPLOYEES IN THE XIMBLE SYSTEM ARE LATE IS MINUTES. 114.2 MINUTES Statistical sample of 263258 clock-in records,
More informationImpacts of the EU ETS on Electricity Prices
Impacts of the EU ETS on Electricity Prices Prof. P. Capros E3Mlab - NTUA, kapros@central.ntua.gr Presented to Final Meeting of ETRES - Life Project Athens, March 31, 2006 The EU ETS - definition Cap and
More informationOptimal Location of Star and Delta connected Capacitor Bank for Loss Minimization in a Five Bus Power System
Optimal Location of Star and Delta connected Capacitor Bank for Loss Minimization in a Five Bus Power System Manaskant Mishra Tanmay Rout Shaswat Chirantan Dr. S. C. Swain Associate Professor School of
More informationNERC PLANNING STANDARDS
NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation
More informationModeling, Monitoring and Mitigating Geomagnetically Induced Currents
21, rue d Artois, F 75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Modeling, Monitoring and Mitigating Geomagnetically Induced Currents Jeff Fleeman, Qun
More informationCalifornia Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring
k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends
More informationAn Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004
Independent Electricity Market Operator : An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004 January 6, 2003 Public This page intentionally left blank. IMO_REP_0093v1.1
More informationTertiary reserve: 15 min 1 h
DESCRIPTION OF THE REQUIRED POSITIVE TERTIARY RESERVE ENERGY ABSTRACT Eva Marie Kurscheid Transmission system operators need tertiary to guarantee reliable grid operation. The used tertiary energy varies
More informationElectricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)
For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold
More informationStandard Development Roadmap
Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:
More informationChapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero
Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories Learning Objectives At the end of the class the student will be able to: 1. Describe the production budget process
More informationCompliance Analysis Report FAC Facilities Ratings Methodology FAC Establish and Communicate Facility Ratings
Compliance Analysis Report FAC-008-1 Facilities Ratings Methodology FAC-009-1 Establish and Communicate Facility Ratings February 19, 20 Background The NERC Board of Trustees Compliance Committee (BOTCC)
More informationCOURSE LISTING. Courses Listed. Training for Applications with Integration in SAP Business One. 27 November 2017 (07:09 GMT) Advanced
Training for Applications with Integration in SAP Business One Courses Listed Advanced TB1000 - SAP Business One - Logistics TB1100 - SAP Business One - Accounting TB1200 - SAP Business One - Implementation
More informationImpact of Wind Energy System Integration on the Al-Zawiya Refinery Electric Grid in Libya
Journal of Power and Energy Engineering, 26, 4, -2 http://www.scirp.org/journal/jpee ISSN Online: 2327-59 ISSN Print: 2327-588X Impact of Wind Energy System Integration on the Al-Zawiya Refinery Electric
More informationWind Update. Renewable Energy Integration Lessons Learned. March 28, 2012
Wind Update Renewable Energy Integration Lessons Learned March 28, 212 Contents Summary Review of Historical Wind Growth and Output Impact of Wind on Operations Wind Curtailments Dispatchable Intermittent
More informationConsequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis
Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis VIJAY VITTAL, FELLOW, IEEE Invited Paper The electric utility industry is undergoing
More informationWILEY A JOHN WILEY & SONS, INC., PUBLICATION
POWER DISTRIBUTION SYSTEM RELIABILITY Practical Methods and Applications Ali A. Chowdhury Don O. Koval IEEE PRESS SERIES ON POWER ENGINEERING IEEE Press WILEY A JOHN WILEY & SONS, INC., PUBLICATION Preface
More informationPJM Roadmap for edart
PJM Roadmap for edart As of March 15, 2017 Background edart (electronic Dispatcher Application and Reporting Tool) is suite of electronic applications used to facilitate dispatcher-todispatcher communications,
More informationOperations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018
Operations Report Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, 2019 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average Off-Peak
More informationBELLS POND-WAITAKI TRANSMISSION CONSTRAINT - PROPOSED APPROACH INFORMATION DOCUMENT
BELLS POND-WAITAKI TRANSMISSION CONSTRAINT - PROPOSED APPROACH INFORMATION DOCUMENT CONTINGENCY PLANS NET BENEFIT ANALYSIS Transpower New Zealand Limited October 2016 i Table of Contents Proposal Summary...
More informationStandard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities
These definitions will be posted and balloted along with the standard, but will not be restated in the standard. Instead, they will be included in a separate Definitions section containing definitions
More informationBioclimatic Design Approach Integration into Architectural Design: a Library Case Study
PLEA 2016 Los Angeles - 36 th International Conference on Passive and Low Energy Architecture. Cities, Buildings, People: Towards Regenerative Environments Bioclimatic Design Approach Integration into
More informationScheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015
Scheduled Outages and Service Interruptions in Connecticut Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015 1 Topics Profiles of Connecticut EDCs SAIDI and SAIFI Interruptions
More informationApril 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403
AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination
More informationCONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 8
CONTENTS Forward... 4 Executive Summary... 5 The Council s Resource Adequacy Standard... 7 Recent Adequacy Assessments... 8 2023 Resource Adequacy Assessment...10 Sensitivity Analysis...10 Monthly Analysis...12
More informationMARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018
HVDC Utilisation In late 2016 we published a report covering what restricts HVDC north transfer 1. We are now publishing monthly updates on the market aspects that restricted HVDC north transfer, and some
More informationProject Risk Management Bootcamp. Contents are subject to change. For the latest updates visit
Bootcamp Page 1 of 7 Why Attend The overall aim of this program is to enable participants to plan, manage and control project risks. Moreover, participants will be able to develop project risk management
More informationISO New England Inc. February /19 ICR Related Values 1
ISO New England Installed Capacity Requirement, Local Sourcing Requirements and Capacity Requirement Values for the System-Wide Capacity Demand Curve for the 2018/19 Capacity Commitment Period ISO New
More informationMont Belvieu NGL Infrastructure
Mont Belvieu NGL Infrastructure September 24, 2012 www.enterpriseproducts.com All rights reserved. Enterprise Products Partners L.P. Mike Smith Senior Vice President Forward Looking Statements This presentation
More informationRELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016
Agenda Item 3.b.i ORS Meeting September 7-8, 2016 RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Introduction The Southern Company Services is the Southeastern
More informationAdministration Division Public Works Department Anchorage: Performance. Value. Results.
Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationThe Efficient and Productive Administrator. Contents are subject to change. For the latest updates visit
The Efficient and Productive Page 1 of 7 Why Attend Organizations are experiencing rapid changes which are creating several challenges to modern administrators. Most notably is the need for administrators
More informationModeling Your Water Balance
Modeling Your Water Balance Purpose To model a soil s water storage over a year Overview Students create a physical model illustrating the soil water balance using glasses to represent the soil column.
More informationPJM Report on TLR Level 5A Activity For April 1 7, 2003
April 23, 2003 Mr. Dave Hilt Director Compliance NERC 116-390 Village Blvd. Princeton Forrestal Village Princeton, NJ PJM Report on TLR Level 5A Activity For April 1 7, 2003 Dear Mr. Hilt: PJM has been
More informationReliability Analysis of Power Distribution System: a Case Study
Reliability Analysis of Power Distribution System: a Case Study Prakash T Dept of Electrical and Electronics, DACG (Govt) Polytechnic, Chikkamagaluru, India Abstract As the electricity plays very important
More informationEast Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria
East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission
More informationPJM White Paper. Transource Independence Energy Connection Market Efficiency Project
PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability
More informationDr. Rahul Walawalkar Vice President, Emerging Tech & Markets, Customized Energy Solutions Ltd.
Capturing the value of Smarter Grids Dr. Rahul Walawalkar Vice President, Emerging Tech & Markets, Customized Energy Solutions Customized Energy Solutions Ltd. 1528 Walnut Street, 22 nd Floor Philadelphia,
More informationSECTION 8. RISK MANAGEMENT AND MITIGATION
argue strongly for a systematic purchasing approach such as NWE describes below in its hedging proposals). Actual resource acquisition decisions, while utilizing some perspectives from long-term forecasts,
More informationAGENDA ITEM D6. Climate Outlook
AGENDA ITEM D6 DATE: June 1, 2016 TO: Matt Jordan, General Manager FROM: Alison Adams, Chief Technical Officer SUBJECT: Regional Water Supplies and Member Demands Status Report SUMMARY: RECOMMENDATION:
More informationAncillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks
1 Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks Linwei Chen, Haiyu Li, Steve Cox, and Kieran Bailey Presented by Dr Haiyu Li haiyu.li@manchester.ac.uk Senior
More informationToward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper
Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...
More informationTRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA
TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision
More informationUK Link Committee Meeting. xoserve Report Pack SEPTEMBER 2009
UK Link Committee Meeting xoserve Report Pack SEPTEMBER 20 Contents Page 2 Report A IS Faults logged by Shippers Page 3 Report B UK-LINK Business Support Agreement Report Summary Page 4 Report C Mod 565
More informationPERSONAL DAYS LETTER TO NON-BARGAINING EMPLOYEES February 19, 2018
2018-19 PERSONAL DAYS LETTER TO NON-BARGAINING EMPLOYEES Dear Members of the Administrative Professional Officers (APOs), Exempt Support Staff (ESS), Excluded Professionals, and Senior Administration employee
More informationComparison of water drainage and nitrate leaching under three land use types in the North China Plain
1 Comparison of water drainage and nitrate leaching under three land use types in the North China Plain 2016 SWAT Conference Reporter: Sun Chengchun Co-worker: Chen Shufeng; Wu Wenliang Email: sunspringer@gmail.com
More informationPrevention of Cascading Outages in Con Edison s Network
1 Prevention of Cascading Outages in Con Edison s Network M. Koenig, Member, IEEE, P. Duggan, Senior Member, IEEE, J. Wong, Member, IEEE, M. Y. Vaiman, Member, IEEE, M. M. Vaiman, Member, IEEE, M. Povolotskiy
More informationClimate Change and Resiliency: Perspectives from Metrolinx
Climate Change and Resiliency: Perspectives from Metrolinx Dr. Quentin Chiotti Senior Advisor, Sustainability ACT CANADA SUSTAINABLE MOBILITY SUMMIT OCTOBER 31, 2017 TDM AND CLIMATE RESILIENCY: VICTORIA
More informationB-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS
Draft 7/15/14 rev7 1 B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS A. Reliability Rule NYCA transmission facilities in the NYS Bulk Power System shall be planned to operate reliably over a
More informationCritical Load Serving Capability by Microgrid using 100% Renewable Energy
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Critical Load Serving Capability by Microgrid using 100% Renewable Energy P. PENKEY,
More informationAEP Guidelines for Transmission Owner Identified Needs
AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal
More informationComparison of Statistical and Dynamic Downscaling methods for Hydrologic Applications in West Central Florida
Comparison of Statistical and Dynamic Downscaling methods for Hydrologic Applications in West Central Florida Wendy Graham and Syewoon Hwang, University of Florida Water Institute Alison Adams and Tirusew
More information18 Month Outlook. An Assessment of the Reliability and Operability of the Ontario Electricity System FROM OCTOBER 2016 TO MARCH 2018
18 Month Outlook An Assessment of the Reliability and Operability of the Ontario Electricity System FROM OCTOBER 2016 TO MARCH 2018 Executive Summary The outlook for the reliability of Ontario s electricity
More informationTPL Transmission System Planned Performance for Geomagnetic Disturbance Events
A. Introduction 1. Title: Transmission System Planned Performance for Geomagnetic Disturbance Events 2. Number: TPL-007-1 3. Purpose: Establish requirements for Transmission system planned performance
More informationLow SCR Wind Identification and Mitigation. Will Lovelace MIPSYCON 2015 November 11 th, 2015
Low SCR Wind Identification and Mitigation Will Lovelace MIPSYCON 2015 November 11 th, 2015 System Background - Diagram System Background - Diagram System Background - Description 199.5 MW wind farm on
More informationEU Phase 3 Update. Chris Logue Gas Markets Manager
EU Phase 3 Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Chris Logue Gas Markets Manager
More informationDECISIONS on operating transfer limits and transmission
1144 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 2, MAY 2004 Hydro Turbine-Governor Model Validation in Pacific Northwest Dmitry Kosterev Abstract This paper presents an approach for generator model
More informationREGIONAL FORECASTING OF GENERATION FROM SMALL HYDROPOWER PLANTS
REGIONAL FORECASTING OF GENERATION FROM SMALL HYDROPOWER PLANTS Professor Ånund Killingtveit NTNU/CEDREN Workshop on Hydro Scheduling in Competitive Electricity Markets Trondheim, Norway, September 17-18
More informationNYSRC RELIABILITY RULES For Planning And Operating the New York State Power System
NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System Version 18 January 5, 2007 NYSRC RELIABILITY RULES For Planning and Operating the New York State Power System Version
More informationHealthcare Facilities: Planning for Increasing Extreme Heat Events
Proceedings of the 014 Industrial and Systems Engineering Research Conference Y. Guan and H. Liao, eds. Healthcare Facilities: Planning for Increasing Extreme Heat Events Ahmad Rabanimotlagh, Michael Overcash,
More informationIntegration of Photovoltaic Generation in a Microgrid: Spinning Reserve Analysis
1 Integration of Photovoltaic Generation in a Microgrid: Spinning Reserve Analysis Luis E. Luna, Member IEEE, Horacio Torres, Senior Member IEEE, Andrés Pavas, Senior Member IEEE Department of Electrical
More informationTransmission Planning Procedures and Planning Criteria TDOG108
Transmission Division Operating Guidelines Transmission Planning Procedures and Planning Criteria TDOG108 Page 1 of 33 Approved by: William R. Kaul, Vice President Transmission Approved date: 10/13/16
More informationNORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014
NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014 27.10.2015 REGIONAL GROUP NORDIC Table of Contents 1 SUMMARY... 3 2 INTRODUCTION AND BACKGROUND... 4 3 SCOPE... 5 4 METHODS, DEFINITIONS
More information