Planning and replanning the master production schedule under demand uncertainty
|
|
- Elmer Strickland
- 6 years ago
- Views:
Transcription
1 Int. J. Production Economics 78 (2002) 323}334 Planning and replanning the master production schedule under demand uncertainty Ou Tang*, Robert W. GrubbstroK m Department of Production Economics, Linko( ping Institute of Technology, S Linko( ping, Sweden Received 12 April 2000; accepted 21 August 2000 Abstract The Master Production Schedule (MPS) is essential in maintaining customer service levels and stabilising production planning in a Material Requirements Planning (MRP) environment. Traditionally, an MPS is derived from a demand forecast and aggregate production plan but the associated cost to cover demand uncertainty is usually not considered. Another di$culty in the MPS is its planning frequency. Frequent changes in the MPS reduce productivity whereas a long-term frozen MPS results in a poor service level and an unfavourable inventory situation. This paper "rst investigates the possibility to establish a method for planning the MPS under stochastic demand. Secondly, it aims to evaluate the value of replanning actions. Finally, it provides a model for estimating appropriate MPS parameters such as the length of the replanning interval and the length of the interval to freeze the plan Elsevier Science B.V. All rights reserved. Keywords: Master production schedule; Stochastic demand; Planning and replanning; Production-inventory system 1. Introduction * Corresponding author. Paper presented at the Eleventh International Working Seminar on Production Economics, Igls/ Innsbruck, Austria, 21}25 February, Tel.: # ; fax: # address: rwg@ipe.liu.se, ou.tang@ipe.liu.se (O. Tang). The Master Production Schedule (MPS) is essential in maintaining customer service levels and stabilising production planning within a Material Requirements Planning (MRP) environment. Usually, an MPS will face the pressure to replan because of the changes of operational circumstances. There are basically two conditions which lead to replanning. First, there is a rolling e!ect due to the extension of the planning period. Secondly, when demand is uncertain, there is always a forecast error, and, therefore the old plan has to be modi"ed to adapt to new information to keep the production cost low and maintain the service level. When the MPS is further used for material requirements planning (MRP), frequent changes in the MPS lead to schedule adjustments in the system. Such adjustments of plans also have an augmented e!ect in an assembly system, and this is often referred to as system nervousness. Nervousness may become an obstacle in the implementation of MRP and even cause a collapse of the whole system. Therefore, to reduce the instability of the schedule becomes an important objective in planning the MPS. In one of our previous studies [1], production rescheduling has been addressed under the assumption that the cost of rescheduling is determined externally. A decision tree method was applied /02/$ - see front matter 2002 Elsevier Science B.V. All rights reserved. PII:S ( 0 0 )
2 324 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323}334 to study the bene"t from rescheduling. The Net Present Value approach was used and the planning time is on a continuous scale. In this paper, we "rst investigate the possibility to establish a method for planning the MPS under stochastic demand. Secondly, we provide a model for replanning MPS assuming the lower-level schedule change cost is known. Then, using a similar method as in GrubbstroK m and Tang [1] and taking into account the schedule change cost, we provide a model for estimating appropriate MPS parameters such as the length of intervals to replan and freeze. Finally, we provide numerical examples and draw some conclusions in a summary. 2. Previous research in MPS Basically, two approaches have been suggested to improve the quality of an MPS, namely freezing the MPS and adding some safety stock into the forecast. When its operation and planning conditions such as forecasting quality, lot sizing policy, operation cost etc. are given, a high-quality MPS is to select a proper planning horizon and a replanning frequency as well as a safety stock. Lin and Krajewski [2] provided a framework for studying the MPS. First they presented the concepts of a forecast window (planning horizon), a frozen interval and a replanning interval and discussed their relationships. Generally, the cost of the MPS has been divided into two parts, a forecast error cost and an MPS change cost. The latter has the same properties as in the similar approach by Carlson et al. [3], in which schedule change cost is a piecewise continuous function of time. The total cost of the MPS model depends on the forecast window and the frozen interval and replanning interval. But it should be reminded that the MPS change cost is more complicated and di$cult to estimated in reality when di!erent lot-sizing policies and a multi-level system are considered. However, in order to build an analytical model, we adopted this simpli"cation in our study. An alternative and more frequently used measure for MPS quality is in terms of its stability. Sridharan et al. [4] suggested a measure of instability, which is a function of the method used to freeze the MPS, the proportion of the MPS frozen and the length of the planning horizon. This instability definition has been followed in other studies [5,2,6,7]. Still, stability is usually used together with other system performance measures, like the service level. In a similar way, Inderfurth [8] provided a de"nition of stability for this type of system. In most of the MPS studies, simulation is used due to the complexity of the problem. Analysis of Variance (ANOVA) is usually applied to determine the system performance when di!erent operation policies are tested. Capacity constraints are often excluded from MPS studies, the only exception being Kern and Wei [7]. In the following subsection, we provide a literature overview of the areas of freezing the MPS and safety stocks in MPS Freezing the MPS A rolling planning horizon is to replan MPS each period whenever information is updated. This tracks the development of demand closely, but generates instability. One solution to avoid this is to freeze a portion of the planning horizon to stabilise the schedule. In a single-level deterministic demand case, freezing this portion beyond 50% of the planning horizon could reduce the instability but increases cost tremendously [9,4]. For the demand uncertainty case, the forecast quality has a large in#uence on the optimal frozen interval and planning horizon [10]. Sridharan and Berry [11] point out that a long MPS frozen interval may increase the need for safety stocks and enlarges the lot-sizing costs at the MPS level. In a multi-level system, freezing the MPS is the most e!ective way to reduce instability and reduce total costs [6]. This result is di!erent from single-level and deterministic studies. In Kadipasaoglu's study in 1995 [12], it is indicated that freezing the MPS provides a bene"t in the stochastic case only. The length of the frozen interval is recommended to cover the cumulative lead time. The freezing portion depends on the planning horizon. A longer planning horizon actually may worsen the MRP performance in a demand uncertainty situation, whereas improve its performance in a deterministic case [10].
3 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} Chung and Krajewski [13] study the interface between aggregate planning and master production planning in a hierarchical planning environment. They concluded that the cost structure of aggregate planning has a high in#uence on the replanning frequency of the MPS Safety stocks The safety stock is used to provide a bu!er for uncertainty in the MPS. However, safety stocks should be applied with great care. Maintaining a safety stock level should not be the objective of scheduling the MPS. An MPS that allows safety stocks to be added to inventory merely in the initial scheduling can create derive more bene"ts from its operation than an MPS that carefully tracks safety stocks and reschedules accordingly. There are also studies considering safety stocks on both MPS and component levels in order to provide a #exible schedule in a multi-level system [14]. Metters [15] studies di!erent strategies for using the safety stock. An explicit approach distinguishes the safety stock from normal demand and lets this amount of stock battle the uncertainty. A new order (replanning) is trigged only when there is a real stockout. On the other hand, an implicit approach triggers a new order whenever an inventory falls down to the safety stock level. Metters also recommends a third approach, namely the stable safety policy. In this case, an explicit approach is used when there is no order in the old schedule and implicit approach when there is an order in the old schedule. Similarly, Sridharan and LaForge [5] provide an intelligent safety policy concept which does not permit a scheduling of the MPS solely for the purpose of meeting a safety stock. Even though a safety stock increases the service level, it does not necessarily provide a stable MPS. In fact, a high safety to meet demand increases instability. Studies by Sridharan and LaForge [5] and Metters [15] support such a conclusion. Hsu and El-Najdawi [16] carried out a study concerning how to determine the safety stock level. They incorporated safety stocks into the lot-sizing policies. Four techniques to determine the optimal safety stock level are examined and compared. Nevertheless, in all the studies we have mentioned above, the level of safety stocks is considered as a constant. In a situation where a portion of the planning horizon is frozen, we suggest that the level of safety stock should vary for the reason that the forecast quality is impaired along with time. Our previous studies show that the level of safety stock follows a square root of time relation when demand is a renewal process [17]. 3. The planning decision The objective of planning is to determine the production volume for a given demand forecast and an initial net inventory R. The initial net inventory is de"ned as the di!erence between cumulative production and cumulative demand so that it is either positive or negative. Instead of using techniques like exponential smoothing, we here use statistical methods for forecasting. Since our objective in this study is to investigate the planning and replanning problem under uncertainty, we use the variance of the demand forecast to express the forecasting error (forecast quality). Another assumption we have adopted is that the setup cost is relatively low. This results in a setup in each time period so that we do not need to consider the impact from the lot-sizing policy. Because of this, the system instability due to the rolling horizon e!ect is reduced. At any time, the following relation holds for a production-inventory system with backlogging: B "DM!PM #S!R. (1) However here the time period is discrete, thus i"1, 2, 2. In each interval, we must also have the following relation: E(B )"E(DM )!PM #E(S )!R. (2) Because of the uncertainty in demand, there is either an excess inventory when the cumulative production level is high, or stockouts when there is a shortage of supply. It is apparent from Eq. (1) that the system service level depends not on the demand forecast error in each period, but on the forecast error of cumulative demand. When replanning is not possible within a frozen interval, the error will
4 326 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323}334 be accumulated. Our previous studies [17] have shown that the optimal safety stock may vary and be a function of time in the continuous-time case. We assume that external cumulative demand DM at the end of the ith period follows a probability density function, which depends on time explicitly: for x(0, Pr(x)DM (x#dxi)" 0 (3) f (x)dx for x*0. Its cumulative probability function, denoted F (x), is assumed to be less than unity for "nite values of x, and is shown to have the following property. Lemma 1. F (x)(f (x). Proof. Writing g as the density function for demand during the (i#1)th period, i.e. for D,we have F (x)"pr(dm #D )x) " F (y) ) g (x!y)dy )F (x) ) g (x!y)dy)f (x). Necessary for the equality to hold, we need g (x!y)dy"1, which is impossible for a "nite x. Hence the inequality is strict.. Since setup costs are disregarded, the objective of the planning is here interpreted as minimising the uncertainty cost C (a term adopted from [2]) E(C )" (h E(S )#b E(B )) " ((h #b )E(S )#b (E(DM )!PM!R )), (4) with E(S )" M (PM #R!x) f (x)dx, (5) subject to the constraints PM *PM *0 for i"1, 2, 2, n!1, (6) where h and b are the unit holding cost and stockout cost for period i, respectively, and n is the planning horizon. The Lagrangean function of this minimisation problem with the constraints Eq. (6) is " ((h #b )E(S )#b (E(DM )!PM!R )) # ξ (PM!PM ), (7) where the ξ are nonnegative Lagrangean multipliers. The necessary Kuhn}Tucker conditions for the optimal solution are "(h #b )F (PM #R )!b #ξ!ξ *0 PM for i"1, 2, 2, n, (8) "PM!PM )0 for i"1, 2, ξ 2, n!1, (9) together with the complementarily conditions PM ) "0 for i"1, 2, PM 2, n, (10) ξ ) "0 for i"1, 2, ξ 2, n!1, (11) where for convenience we de"ne ξ "ξ "0. Hence F (PM )* b #ξ!ξ for i"1, 2, h #b 2, n, (12) with equality whenever PM '0. We "rst note that due to the non-decreasing property of the PM, the optimal sequence will start with a (possibly empty) subset PM "PM "2"0 followed by a second (possibly empty) subset PM, PM,2, PM '0. A strict inequality in Eq. (12) can therefore only be valid for the "rst of these subsets (if it is nonempty). In Theorem 1 we provide a su$cient condition for determining the structure of the sequence PM, PM, 2, PM. Theorem 1. If the ratio between unit stockout cost and unit holding cost is non-decreasing in time, i.e.
5 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} (b /h )*(b /h ), i"1, 2, 2, n!1, then we have the following conditions regarding the production sequence. If F (R )'b /(h #b ), then PM "PM "2"PM " 0; if F (R )(b /(h #b ), then PM, PM, 2, PM '0. Hence, this theorem o!ers a means for deciding where the sequence of positive cumulative production levels should start. Proof of Theorem 1. Assume (i) that F (R )' b /(h #b ), then b /(h #b ))b /(h #b )( F (R )(F (R ) for 1)i(j. Based on Eq. (12), we always need F (R #PM )*(b!ξ )/(h #b ). If PM '0, then F (R #PM )"(b!ξ )/(h #b )'F (R )'b /(h #b ) which creates a contradiction since ξ *0. Hence we obtain PM "0. Based again on Eq. (12), we always need F (R #PM )*(b!ξ #ξ )/(h #b ). If PM '0, then F (R #PM )"(b!ξ #ξ )/(h # b )'F (R )'b /(h #b ). This requires!ξ #ξ '0, therefore ξ '0, which creates a contradiction. Hence we obtain PM "0. Following the same procedure for i"3, 4,2, we end up with PM "0. Assume (ii) that F (R )(b /(h #b ). Then F (R )(F (R )(2(F (R )(b /(h #b ) (b /(h #b ) for all j)i(n. Since F (R # PM )*(b #ξ )/(h #b )*b /(h #b )'F (R ), we must have PM '0. If we assume PM "0 and take into account F (R #PM )*(b!ξ #ξ )/ (h #b ), we obtain b /(h #b )'F (R )* (b!ξ #ξ )/(h #b ), which leads to!ξ # ξ (0. Therefore ξ '0 and we have PM "PM "0. With PM "0 and b /(h #b )' F (R )*(b!ξ #ξ )/(h #b ), we obtain!ξ #ξ (0 and therefore ξ '0. Hence we have PM "PM "0. By repeating the above procedure, we obtain PM "0, which contradicts PM '0. Therefore we "nally obtain PM, PM, 2, PM '0. Theorem 2. We assume as in Theorem 1 that the ratio between unit stockout cost and unit holding cost is non-decreasing in time, i.e. b /h )b /h for i"1, 2, 2, n!1. If PM, is the earliest positive cumulative production, then the multipliers from j!1 onwards are all zero, i.e. ξ "ξ "ξ " 2"ξ "0. Proof. PM being the earliest positive production requires ξ "0. We rearrange Eq. (12) as an equality for i"j and i"j#1: F (PM #R )# ξ!ξ " b, h #b h #b F (PM #R )# ξ!ξ " b. h #b h #b Since the right-hand member is nondecreasing, so must the left-hand member also be. Assume that ξ '0, then PM "PM ; and therefore F (PM #R )(F (PM #R ), which implies (ξ!ξ )/(h #b )'(ξ!ξ )/(h #b ). Therefore, also ξ '0, which creates PM " PM. Continuing this process, we end up with!ξ /(h #b )'0, which contradicts the nonnegativity of the multipliers. Therefore we conclude that ξ "0. Analogously we get ξ "0, etc. Hence, no multiplier ξ, for i*j!1, may be positive. This concludes our proof.. By using Theorems 1 and 2, we are now in a position to construct a solution procedure to the stated problem of minimising the uncertainty cost. This procedure is stated in the following theorem. Theorem 3. As before, we assume a non-decreasing sequence of unit cost ratios b /h )b /h, i" 1, 2, 2, n!1. The solution PMH to the minimisation problem Eq. (4) subject to the constraints Eq. (6) then satisxes PMH "0 if F (R )' b, h #b F (PMH #R )" b if F (R )) b. h #b h #b If all F (x) are monotonically increasing functions, the solution must be unique. Proof of Theorem 3 follows immediately from our previous results. The theorem shows that this
6 328 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323}334 optimal planning model is essentially an extension of the Newsboy problem. 4. The replanning decision The objective of replanning is to determine a rescheduled production volume in each period P, i"¹#1, ¹#2,2, for a given demand forecast, and initial net inventory R at the replanning point based on the old production plan P and the schedule change cost δ, so that the total cost can be minimised. The total cost C consists of the uncertainty cost, as discussed in the previous section, and the rescheduling cost C : C "C #C. (13) The rescheduling cost is the sum of the schedule change costs in di!erent time periods. In a practical setting, we would assume that the schedule change cost depends on the lot-sizing policy, the product structure, the rescheduling time desired, and the rescheduling quantity desired. In this study, our focus is on the MPS level. Thus we use a single schedule change cost function to take care of the aggregate information of negative e!ects of rescheduling on the lower levels. Here we assume that the schedule change cost is a function of the rescheduling time and that it is proportional to the quantity being changed. This is in accordance with the unit change cost concept in Lin and Krajewski [2]. As a result from Tang and GrubbstroK m [18] where control theory was applied, this type of cost should be a function of time as well. With this in mind, we de"ne the schedule change cost as δ " (P!P )φ if P *P, (14)!P )γ if P (P, where φ and γ both are nonincreasing functions of the time period i. This means that in order to reschedule, whether adding orders or cancelling the orders, it is always at least as expensive to change the earlier schedule as the latter one. In practical terms, these costs may relate to the time fences, which are the guidelines to note various restrictions in schedule changes related to lowerlevel items. Fig. 1. Cost structure for replanning. At a certain time, the schedule change cost is therefore a monotonically decreasing function when P (P and a monotonically increasing function when P 'P. This is illustrated in Fig. 1. Quite often in practice, to cancel an order is easier than adding an new order, so γ could then be assumed to be smaller than φ. Lemma 2. Let y (z) and y (z) be two functions of z, each having a unique minimum at z and z, respectively, and no other local minima. Then any linear combination of y (z) and y (z) with positive coezcients will have a unique minimum in the interval between z and z. The proof of this proposition is trivial. Regarding the optimal replanning decision, we state the following theorem. Theorem 4. If all F (x) are monotonically increasing, the total cost function of replanning (Eq. (13)) is convex. Then the optimal replanning decision P falls into the interval between the old production plan P and P*, the latter being the optimal solution when minimising the uncertainty cost based only on the initial net inventory R and demand forecast, see Fig. 1. Proof. The proof follows from Lemma 2 and our assumption regarding the monotonic behaviour of the schedule change cost with respect to P!P.
7 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} Combining Eqs. (13) and (14), we may write the total cost as C "E(C )#C " ((h#b )E(S )#b (E(DM )!PM!R )#δ ). (15) Its "rst-order derivative is thus C " ((h #b )F (PM #R )!b ) P if PH'P, # φ!γ if PH(P. (16) Regarding the solution to the optimal replanning decisions, we have the following theorem. Theorem 5. (i) If PH 'P and (C /P ) '0, then we have the optimal solution P "P. (ii) If PH 'P and (C /P ) (0, then the optimal P is such that (C /P ) "0. (iii) If PH 'P and (C /P ) H '0, then the optimal solution becomes P "PH. (iv) If PH (P and (C /P ) H (0 and (C / P ) (0, then the optimum will be P "P. (v) If PH (P and (C /P ) H (0, and (C /P ) '0, then the optimal value of P is such that (C /P ) "0. Proof. The proof is obtained from Theorem 4 and the de"nition of the schedule change cost in combination with Kuhn}Tucker conditions. Based on Theorems 3 and 5, we propose the following solution procedure to obtain the optimal replanning decision. (i) Start from i"¹#1. (ii) Calculate the unique solution P* according to Theorem 3. (iii) Compare P* and P and calculate P according to Theorem 5. (iv) Increase i one step and repeat the steps (ii)}(iii), if i is smaller than the planning horizon ¹#n. 5. The planning and replanning model Essentially establishing the MPS is a dynamic planning and replanning process. Fig. 2 illustrates the decision scheme following a similar interpretation as in Lin and Krajewski [2]. The replanning interval is the time period until when no replanning is under consideration. However, due to certain production constraints in practice, such as the rescheduling time fence, a portion of the old plan needs to be "xed. Sometimes, because of unfavourable economic consequences or system performance, part of the old plan needs to be kept. The total length of the "xed part of the old plan is called the frozen interval. During the time intervals beyond the frozen interval, the production plan is allowed to be changed to improve the performance of the system by using the knowledge of the state that was realised at the replanning time. In GrubbstroK m and Tang [1], a decision tree method was used to address the rescheduling problem. Here we follow the same methodology for the planning and replanning problem. However, an explicit schedule change cost has been added and the decision tree has been changed correspondingly. As in Fig. 3, the replanning may take place at time ¹. The sequences of production decisions prior to and at this point are denoted p and those beyond this point are denoted p. Let d and d represent stochastic sequences of a demand process, before and after the possible replanning time ¹ (Fig. 4). With this notation, the following planning and replanning schemes can be interpreted in the form of a decision tree. At time 0, we make a decision Fig. 2. Planning and replanning scheme (adapted from Lin and Krajewski, [2]).
8 330 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} Numerical examples Fig. 3. Decision tree diagram for the planning and replanning processes. concerning the production plan p followed by p.as shown in Section 3, this requires to determine P*, for i"1, 2,2,¹, and P* for i"¹#1, ¹#2,2,¹#n. At the replanning point, a state of the net inventory R will be realised based on the outcome of the previous sequence of demand DM. We now use the replanning model given in Section 4 to decide P for i"¹#1, ¹#2,2, ¹#n. The rescheduling cost in the current model, depends on the state at which replanning occurs (essentially on R ) and this cost will be di!erent for di!erent states in general. This is one of the major di!erences from our previous study in GrubbstroK m and Tang [1]. The optimal frozen interval ¹ is therefore P "P, for all ¹(i)¹#¹. (17) The gain from replanning is the di!erence between total costs for replanning and total costs for the stay alternative. As illustrated in GrubbstroK m and Tang [1], this gain has a non-negative value C "C (R, P )!C (P R, P )*0. (18) In this equation, the state R is a result of cumulative demand DM according to Eq. (1). Since cumu- lative demand at the replanning point ¹ has a cumulative density function F (x), the expected gain from replanning is therefore E(C (¹))" C (x)df (x). (19) Similarly, we obtain the expected value of the frozen interval ¹ from E(¹ )" ¹ (x)df (x). (20) Below, we provide numerical examples to illustrate the models of previous sections. We assume that external demand follows a Stuttering Poisson process [19], in which the interval between demand events obeys an exponential distribution and the event size is geometrically distributed. The probability density function of cumulative demand at the end of the ith time period is therefore for M"0, f (M)"e e (λi) j! M!1 j!1 β(1!β) for M"1, 2,2,. (21) where λ and β are constants. The random variable M, cumulative demand, has the mean μ"λi/β and variance σ"λi(2!β)/β. This shows that for such a type of compound Poisson process, both the mean and variance of cumulative demand increase proportionally with the time period. Given the production parameters b, h, λ, β, we calculate the optimal MPS according to the model of Section 3. The safety stock SS equals the di!erence between cumulative production and expected cumulative demand immediately prior to the time of production. A "rst example is given in Table 1, which shows that the optimal safety stock increases monotonically with time, even if the demand forecast is constant in each time period. The resulting production volume is then used for the purpose of the MPS in this system. According to this production plan, the production volumes tend to be close to constant except for the "rst few periods, and they are all higher than expected demand. The increasing contribution to E(C ) shows that the system needs to pay more to cover increasing uncertainty in later time periods. Tables 2 and 3 o!er examples of the replanning model for a positive and negative initial net inventory, respectively. The frozen intervals are 1 and 3 time periods, respectively. The schedule change cost structure is of course the major component in#uencing the frozen interval. In our examples we assume a decay function Φe for adding an order
9 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} Table 1 The planning decisions with b"30, h"1, λ"5, β"0.5 i E(D) (Forecasting) PM P (MPS) SS E(S ) E(B ) E(C ) and Θe for cancelling an order. But we would be able to use any other form of schedule change cost in our replanning model. It is shown in Table 3 that the "rst two periods are frozen due to the high change cost even though stockouts exist there. In the event of a very tight production environment, within which where rescheduling is impossible, we may assign the schedule change cost an in"nitely large value so that the optimal solution always becomes identical to the old plan according to the decision rules of Theorem 5. We use di!erent values of Φ and Θ in the schedule change cost function to represent the rescheduling #exibility of the system. These vary according as costs are high (10000), (medium) 1000, (low) 100 and 50, 5, 0.5. Demand uncertainty is indicated by assigning di!erent values to λ and β. But we retain the expected demand rate as a constant. As illustrated in Fig. 5, the expected gain from replanning increases when the forecast error is raised. An optimal replanning interval is shown to exist. However, this optimal value Table 2 Replanning decision with b"30, h"1, λ"5, β"0.5, R"40 i!t E(D) φ γ P* P P (MPS) (Forecasting)
10 332 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323}334 Table 3 Replanning decision with b"30, h"1, λ"5, β"0.5, R"!40 i!t E(D) φ γ P* P P (MPS) (Forecasting) Fig. 4. Expected gain from replanning vs. replanning interval on di!erent uncertainty levels. Mean demand rate"10, b"30, h"1, n"30. does not change very much with the forecast error. It remains between 11 and 12 time periods in these particular examples given by Fig. 5. Fig. 6 shows that the forecast error does not have an obvious impact on the length of the frozen interval. Intuitively, a lower schedule change cost brings more of a gain from replanning (Fig. 7). Again, from Fig. 7, we observe the existence of an optimal replanning interval and that the sequence of optimal replanning intervals is insensitive to the schedule change cost. However, the schedule change cost has a signi"cant impact on the length of the frozen interval. We have also studied examples with di!erent planning horizons. The planning horizon has a large impact on the optimal replanning interval (Figs. 8}10). With a longer planning horizon, the replanning interval is prolonged as well. Nevertheless, Figs. 8 and 10 also show that neither forecasting, nor the schedule change cost have any important in#uence on the length of the replanning interval. Fig. 5. Expected frozen interval vs. replanning interval on di!erent uncertainty levels. Mean demand rate"10, b"30, h"1, n"30. Fig. 6. Expected gain from replanning vs. replanning interval on di!erent schedule change cost levels. b"30, h"1, λ"5, β"0.5, n"30. When we study the optimal replanning interval, Fig. 9 again shows that the forecast error has little e!ect on the frozen interval. It seems as if the only
11 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323} Fig. 7. Expected frozen interval vs. replanning interval on di!erent schedule change cost levels. b"30, h"1, λ"5, β"0.5, n"30. Fig. 9. Expected frozen interval vs. planning horizon on di!erent uncertainty levels when the replanning interval is optimal. Mean demand rate"10, b"30, h"1. Fig. 8. Optimal replanning interval vs. planning horizon on di!erent uncertainty levels. Mean demand rate"10, b"30, h"1. Fig. 10. Optimal replanning interval vs. planning horizon on di!erent schedule change cost levels. b"30, h"1, λ"5, β"0.5. major factor changing the frozen interval is the schedule change cost (Fig. 11). 7. Summary In this paper, we have studied planning and replanning problems at the MPS level. First, we have applied our previous research "ndings about safety stocks in an MPS system. We provide a model for MPS planning in which the safety stock is determined and is shown to be an increasing function of time. Secondly, we developed a model for replanning in which the scheduling change cost is considered and for which an e$cient solution procedure was presented. This provides Fig. 11. Expected frozen interval vs planning horizon on di!erent schedule change cost levels when the replanning interval is optimal. b"30, h"1, λ"5, β"0.5.
12 334 O. Tang, R.W. Grubbstro( m / Int. J. Production Economics 78(2002) 323}334 the possibility for further studying replanning when several alternative replanning points are considered. The numerical examples demonstrate procedures to solve the optimal replanning interval and to estimate the expected frozen interval. An interesting "nding is that the forecast error appears to be of little importance to either of them when the safety stock bu!er is optimised according to our planning model. But how to determine the optimal planning horizon still remains an open question. In this paper, we have assumed that there is only one replanning point inside of the "rst planning horizon. In future studies, it is of interest to remove this assumption. Simulation studies may be needed for dynamic replanning problems, in which replanning decisions may be interpreted following the model in Section 4. Only after that, the interrelationship between the replanning interval, the frozen interval and the planning horizon may become more transparent. Another remaining point for discussion is the schedule change costs. If in the real world multilevel production system we could develop principles for aggregating the information necessary for estimating the rescheduling cost, our replanning model in Section 4 would become more important for practical uses. References [1] R.W. GrubbstroK m, O. Tang, Modelling rescheduling activities in a multi-period production}inventory system, International Journal of Production Economics 68 (2) 123}135. [2] N.-P. Lin, L.J. Krajewski, A model for master production scheduling in uncertain environments, Decision Sciences 23 (1992) 839}861. [3] R.C. Carlson, J.V. Jucker, D.H. Kropp, Less nervous MRP systems:a dynamic economic lot-sizing approach, Management Science 25 (8) (1979) 754}761. [4] V. Sridharan, W.L. Berry, V. Udayabhanu, Measure master production schedule stability under rolling planning horizons, Decision Sciences 19 (1988) 147}166. [5] V. Sridharan, R.L. LaForge, The impact of safety stock on schedule instability, cost and service, Journal of Operations Management 8 (4) (1989) 327}347. [6] S.N. Kadipasaoglu, V. Sridharan, Alternative approach for reducing schedule instability in multistage manufacturing under demand uncertainty, Journal of Operations Management 13 (1995) 193}211. [7] G.M. Kern, J.C. Wei, Master production rescheduling policy in capacity constrained just-in-time make-to-stock environments, Decision Sciences 27 (2) (1996) 365}387. [8] K. Inderfurth, Nervousness in inventory control:analytical results, OR Spektrum 16 (1994) 113}123. [9] V. Sridharan, W.L. Berry, V. Udayabhanu, Freezing the master production schedule under rolling planning horizons, Management Science 33 (9) (1987) 1137}1148. [10] X. Zhao, T.S. Lee, Freezing the master production schedule for material requirements planning systems under demand uncertainty, Journal of Operations Management 11 (1993) 185}205. [11] V. Sridharan, W.L. Berry, Freezing the master production schedule under demand uncertainty, Decision Sciences 21 (1990) 97}120. [12] S.N. Kadipasaoglu, The e!ect of freezing the master production schedule on cost in multilevel MRP system, Production and Inventory Management 36 (1995) 30}36. [13] C.-H. Chung, L.J. Krajewski, Replanning frequencies for master production schedules, Decision Sciences 17 (1986) 263}273. [14] C.A. Yano, R. Carlson, Interaction between frequency of rescheduling and the role of safety stock in material requirements planning systems, International Journal of Production Research 25 (2) (1987) 221}232. [15] R.D. Metters, A method for achieving better customer services, lower costs, and less instability in master production schedules, Production and Inventory Management 34 (1993) 61}65. [16] J.I. Hsu, M.K. El-Najdawi, Integrating safety stock and lot-sizing policies for multi-stage inventory systems under uncertainty, Journal of Business Logistics 12 (2) (1991) 221}238. [17] R.W. GrubbstroK m, O. Tang, Further developments on safety stocks in an MRP system applying Laplace transforms and input}output analysis, International Journal of Production Economics 60}61 (1999) 381}387. [18] O. Tang, and R. W. GrubbstroK m, Rescheduling considerations for production planning using control theory, Paper for Presentation at the Fifteenth International Conference on Production Research, Limerick, Ireland, 9}13 August, [19] G. Hadley, T.M. Whitin, Analysis of Inventory System, Prentice-Hall, Englewood Cli!s, NJ, 1963.
New lot-sizing formulations for less nervous production schedules
Computers & Operations Research 27 (2000) 1325}1345 New lot-sizing formulations for less nervous production schedules Osman Kazan, Rakesh Nagi, Christopher M. Rump* Department of Industrial Engineering,
More informationManufacturing and remanufacturing strategies under uncertain product demand
UNIVERSITY OF GRAZ Manufacturing and remanufacturing strategies under uncertain product demand Marc Reimann, Gernot Lechner Working Paper 2011-02 November 16, 2011 Subsequently published as: Reimann, M.,
More informationUsing Multi-chromosomes to Solve. Hans J. Pierrot and Robert Hinterding. Victoria University of Technology
Using Multi-chromosomes to Solve a Simple Mixed Integer Problem Hans J. Pierrot and Robert Hinterding Department of Computer and Mathematical Sciences Victoria University of Technology PO Box 14428 MCMC
More informationFreezing issue on stability master production scheduling for supplier network: Decision making view
Freezing issue on stability master production scheduling for supplier network: Decision making view, 2 Azizah Aisyati 1, TMA Ari Samadhi 1, Anas Ma ruf 1 a nd Andi Cakravastia 1 1 Department of Industrial
More informationDetermination of the Number of Kanbans and Batch Sizes in a JIT Supply Chain System
Transaction E: Industrial Engineering Vol. 17, No. 2, pp. 143{149 c Sharif University of Technology, December 2010 Research Note Determination of the Number of Kanbans and Batch Sizes in a JIT Supply Chain
More informationEvaluating the Impact of the Nature of Lot-sizing Rules On MRP System Performance
Evaluating the Impact of the Nature of Lot-sizing Rules On MRP System Performance Chrwan-jyh Ho, Department of Management Science and Information Systems, Spears School of Business, Oklahoma State University,
More informationNew Results for Lazy Bureaucrat Scheduling Problem. fa Sharif University of Technology. Oct. 10, 2001.
New Results for Lazy Bureaucrat Scheduling Problem Arash Farzan Mohammad Ghodsi fa farzan@ce., ghodsi@gsharif.edu Computer Engineering Department Sharif University of Technology Oct. 10, 2001 Abstract
More informationThis is a refereed journal and all articles are professionally screened and reviewed
Advances in Environmental Biology, 6(4): 1400-1411, 2012 ISSN 1995-0756 1400 This is a refereed journal and all articles are professionally screened and reviewed ORIGINAL ARTICLE Joint Production and Economic
More informationProduction planning in automotive powertrain plants: A case study
International journal of production research (accepted, 27 March 2017) Production planning in automotive powertrain plants: A case study Idris Lalami, Yannick Frein, Jean-Philippe Gayon Univ. Grenoble
More informationOperations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Module - 01 Lecture - 08 Aggregate Planning, Quadratic Model, Demand and
More informationA Single Item Non Linear Programming (NLP) Economic Order Quantity Model with Space Constraint
A Single Item Non Linear Programming (NLP) Economic Order Quantity Model with Space Constraint M. Pattnaik Dept. of Business Administration Utkal University, Bhubaneswar, India monalisha_1977@yahoo.com
More informationA reactive decision-making approach to reduce instability in a Master Production Schedule
A reactive decision-making approach to reduce instability in a Master Production Schedule Carlos Herrera, Sana Belmokhtar Berraf, André Thomas, Victor Parada To cite this version: Carlos Herrera, Sana
More informationNet Requirements Plan. The logic of net requirements. MRP Planning Sheet. Gross Requirements Schedule
Net Requirements Plan The logic of net requirements Gross Requirements Schedule MRP Planning Sheet Safety Stock BOMs, inventory records, purchase and production quantities may not be perfect Consideration
More informationA Simple EOQ-like Solution to an Inventory System with Compound Poisson and Deterministic Demand
A Simple EOQ-like Solution to an Inventory System with Compound Poisson and Deterministic Demand Katy S. Azoury San Francisco State University, San Francisco, California, USA Julia Miyaoka* San Francisco
More informationOptimisation of perishable inventory items with geometric return rate of used product
22nd International Congress on Modelling and Simulation, Hobart, Tasmania, Australia, 3 to 8 December 2017 mssanz.org.au/modsim2017 Optimisation of perishable inventory items with geometric return rate
More informationON THE OPTIMALITY OF ORDER BASE-STOCK POLICIES WITH ADVANCE DEMAND INFORMATION AND RESTRICTED PRODUCTION CAPACITY
ON THE OPTIMALITY OF ORDER BASE-STOCK POLICIES WITH ADVANCE DEMAND INFORMATION AND RESTRICTED PRODUCTION CAPACITY J. Wijngaard/F. Karaesmen Jacob Wijngaard (corresponding author) Faculty of Management
More informationProcurement of Common Components in a. Stochastic Environment. Ramesh Srinivasan. Rangarajan Jayaraman. James A. Rappold y. Robin O.
Procurement of Common Components in a Stochastic Environment Ramesh Srinivasan Rangarajan Jayaraman James A. Rappold y Robin O. Roundy z Sridhar Tayur x (November 1992; Revised September 1998) Abstract
More informationThe Core Pareto Optimality and Social Welfare Maximizationty
The Core Pareto Optimality and Social Welfare Maximizationty Econ 2100 Fall 2017 Lecture 14, October 19 Outline 1 The Core 2 Core, indiviual rationality, and Pareto effi ciency 3 Social welfare function
More informationOn the Selection of Customer Service Metrics in Inventory Control
On the Selection of Customer Service Metrics in Inventory Control Guijarro E 1, Babiloni E, Cardós M, Estellés S Abstract Customer service metrics have been largely studied in literature due to their importance
More informationSpatial Discrimination, Nations' Size and Transportation Costs
Spatial Discrimination, Nations' Size and Transportation Costs Kai Andree Abstract In this paper we develop a spatial Cournot trade model with two unequally sized countries, using the geographical interpretation
More informationModelling input}output workload control for dynamic capacity planning in production planning systems
Int. J. Production Economics 68 (2000) 73}93 Modelling input}output workload control for dynamic capacity planning in production planning systems Brian G. Kingsman* Department of Management Science, The
More informationA Study on MRP with Using Leads Time, Order Quality and Service Level over a Single Inventory
A Study on MRP with Using Leads Time, Order Quality and Service Level over a Single Inventory Seyed Hassan Shojaie, Payame Noor University, Po Box 19395-3697,tehran,Iran Abbas Bahoosh, School of Humanities,
More informationRISK-POOLING EFFECTS OF DIRECT SHIPPING IN A ONE-WAREHOUSE N-RETAILER DISTRIBUTION SYSTEM
RISK-POOLING EFFECTS OF DIRECT SHIPPING IN A ONE-WAREHOUSE N-RETAILER DISTRIBUTION SYSTEM Sangwook Park* I. Introduction N. The Model U. Model and Assumptions V. Concludin~ remarks ID. Previous Study I.
More informationSection 1: Introduction
Multitask Principal-Agent Analyses: Incentive Contracts, Asset Ownership, and Job Design (1991) By Bengt Holmstrom and Paul Milgrom Presented by Group von Neumann Morgenstern Anita Chen, Salama Freed,
More informationOptimal Ordering Policy Under Acceptance Sampling Plan and Trade Credit Financing
ransaction E: Industrial Engineering Vol. 17, No. 2, pp. 120{128 c Sharif University of echnology, December 2010 Optimal Ordering Policy Under Acceptance Sampling Plan and rade Credit Financing Abstract.
More information1 Introduction 1. 2 Forecasting and Demand Modeling 5. 3 Deterministic Inventory Models Stochastic Inventory Models 63
CONTENTS IN BRIEF 1 Introduction 1 2 Forecasting and Demand Modeling 5 3 Deterministic Inventory Models 29 4 Stochastic Inventory Models 63 5 Multi Echelon Inventory Models 117 6 Dealing with Uncertainty
More informationUniversity of Groningen. Investment evaluation with respect to commercial uncertainty Broens, Douwe Frits
University of Groningen Investment evaluation with respect to commercial uncertainty Broens, Douwe Frits IMPORTANT NOTE: You are advised to consult the publisher's version (publisher's PDF) if you wish
More informationA Decision-Making Process for a Single Item EOQ NLP Model with Two Constraints
American Journal of Business, Economics and Management 205; 3(5): 266-270 Published online September 7, 205 (http://www.openscienceonline.com/journal/ajbem) A Decision-Making Process for a Single Item
More informationA comparative analysis of utilizing activity-based costing and the theory of constraints for making product-mix decisions
Int. J. Production Economics 63 (2000) 1}17 A comparative analysis of utilizing activity-based costing and the theory of constraints for making product-mix decisions Robert Kee*, Charles Schmidt University
More informationDeriving the Exact Cost Function for a Two-Level Inventory System with Information Sharing
Journal of Industrial and Systems Engineering Vol. 2, No., pp 4-5 Spring 28 Deriving the Exact Cost Function for a Two-Level Inventory System with Information Sharing R. Haji *, S.M. Sajadifar 2,2 Industrial
More informationOPTIMIZATION AND OPERATIONS RESEARCH Vol. IV - Inventory Models - Waldmann K.-H
INVENTORY MODELS Waldmann K.-H. Universität Karlsruhe, Germany Keywords: inventory control, periodic review, continuous review, economic order quantity, (s, S) policy, multi-level inventory systems, Markov
More informationInventory Management
Inventory Management Materials planning AGGREGATE PLANNING Master Production Schedule (MPS) MATERIALS PLANNING The planning of materials requirements consists of the determination of: What How much and
More informationCompetition: Boon or Bane for Reputation Building. Behavior. Somdutta Basu. October Abstract
Competition: Boon or Bane for Reputation Building Behavior Somdutta Basu October 2014 Abstract This paper investigates whether competition aids or hinders reputation building behavior in experience goods
More informationLOT SIZING IN MRP. Week Gross requirements Scheduled receipts Projected available balance Net Requirements
LOT SIZING IN MRP The net data is subjected lot sizing Lot sizes developed can satisfy the net for one or more weeks The basic trade-off involves the elimination of one or more setups at the expense of
More informationA revised and improved version of the MRP algorithm: Rev MRP Marco D Avino 1,a, Alfredo Bregni 2,b, Massimiliano Maria Schiraldi 3,c
Applied Mechanics and Materials Vol. 328 (2013) pp 276-280 Online available since 2013/Jun/27 at www.scientific.net (2013) Trans Tech Publications, Switzerland doi:10.4028/www.scientific.net/amm.328.276
More informationChapter 2 Forecasting
Chapter 2 Forecasting There are two main reasons why an inventory control system needs to order items some time before customers demand them. First, there is nearly always a lead-time between the ordering
More informationLot Sizing and Lead Time Quotations in Assembly Systems
Transaction E: Industrial Engineering Vol. 16, No. 2, pp. 100{113 c Sharif University of Technology, December 2009 Lot Sizing and Lead Time Quotations in Assembly Systems Abstract. F. Kianfar 1 and G.
More informationUniversity of Groningen. Effective monitoring and control with intelligent products Meyer, Gerben Gerald
University of Groningen Effective monitoring and control with intelligent products Meyer, Gerben Gerald IMPORTANT NOTE: You are advised to consult the publisher's version (publisher's PDF) if you wish
More informationA Robust Optimization Model for Lot Sizing with Dynamic Demands
A Robust Optimization Model for Lot Sizing with Dynamic Demands Aurora Rostenila Department of Industrial Engineering Universitas Katolik Parahyangan (UNPAR), Bandung, Indonesia Tel: (+62) 203-2655, Email:
More informationOn the evaluation of the cost efficiency of nonresponse rate reduction efforts - some general considerations
WORKING PAPER SERIES WORKING PAPER NO 5, 2006 ESI On the evaluation of the cost efficiency of nonresponse rate reduction efforts - some general considerations by Sara Tångdahl http://www.oru.se/esi/wps
More informationOperations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Module - 1 Lecture - 7 Aggregate Planning, Dynamic Programming, Backordering
More informationDiscrete and dynamic versus continuous and static loading policy for a multi-compartment vehicle
European Journal of Operational Research 174 (2006) 1329 1337 Short Communication Discrete and dynamic versus continuous and static loading policy for a multi-compartment vehicle Yossi Bukchin a, *, Subhash
More informationCost performance and bullwhip effect in a hybrid manufacturing and remanufacturing system with different control policies
International Journal of Production Research, Vol. 44, Nos. 18 19, 15 September 1 October 26, 3847 3862 Cost performance and bullwhip effect in a hybrid manufacturing and remanufacturing system with different
More informationEconomics of Co-design: The Role of Product Lines
Economics of Co-design: The Role of Product Lines Amit Basu Southern Methodist University abasu@cox.smu.edu Sreekumar Bhaskaran Southern Methodist University sbhaskar@cox.smu.edu March 21, 2014 Abstract
More informationThe Price of Anarchy in an Exponential Multi-Server
The Price of Anarchy in an Exponential Multi-Server Moshe Haviv Tim Roughgarden Abstract We consider a single multi-server memoryless service station. Servers have heterogeneous service rates. Arrivals
More informationAn Integrated Model for a Two-supplier Supply Chain with Uncertainty in the Supply
Tusculum College From the SelectedWorks of university of science & culture Fall 011 An Integrated Model for a Two-supplier Supply Chain with Uncertainty in the Supply Mehdi Sajadifar Available at: https://works.bepress.com/universityofscienceculture_usc/4/
More informationIowa State University. Ames, IA Warren B. Powell. Department of Civil Engineering and Operations Research. Princeton University
Models and Algorithms for Distribution Problems with Uncertain Demands Raymond K.-M. Cheung Department of Industrial and Manufacturing Systems Engineering Iowa State University Ames, IA 50011 Warren B.
More informationInternational Journal for Management Science And Technology (IJMST)
Volume 3; Issue 2 Manuscript- 3 ISSN: 2320-8848 (Online) ISSN: 2321-0362 (Print) International Journal for Management Science And Technology (IJMST) VALIDATION OF A MATHEMATICAL MODEL IN A TWO ECHELON
More informationA numerical study of expressions for fill rate for single stage inventory system with periodic review.
University of Louisville ThinkIR: The University of Louisville's Institutional Repository Electronic Theses and Dissertations 8-2013 A numerical study of expressions for fill rate for single stage inventory
More informationINDEPENDENT DEMAND SYSTEMS: PROBABILISTIC MODELS Introduction
INDEPENDENT DEAND SYSTES: PROAILISTIC ODELS Introduction Demand and Lead-Time are treated as random variable The models in this section assumes that the average demand remains approximately constant with
More information(s, S) POLICY FOR UNCERTAIN SINGLE PERIOD INVENTORY PROBLEM
International Journal of Uncertainty, Fuzziness and Knowledge-Based Systems Vol. 21, No. 6 (213) 945 953 c World Scientific Publishing Company DOI: 1.1142/S2184885135438 (s, S) POLICY FOR UNCERTAIN SINGLE
More informationCOORDINATING DEMAND FORECASTING AND OPERATIONAL DECISION-MAKING WITH ASYMMETRIC COSTS: THE TREND CASE
COORDINATING DEMAND FORECASTING AND OPERATIONAL DECISION-MAKING WITH ASYMMETRIC COSTS: THE TREND CASE ABSTRACT Robert M. Saltzman, San Francisco State University This article presents two methods for coordinating
More informationHow to Cite or Link Using DOI
Computers & Operations Research Volume 39, Issue 9, September 2012, Pages 1977 1987 A stochastic production planning problem with nonlinear cost Lixin Tang a,,, Ping Che a, b,, a, c, Jiyin Liu a Liaoning
More informationThe Mixed Strategy Equilibria and Adaptive Dynamics in the Bar Problem
The Mixed Strategy Equilibria and Adaptive Dynamics in the Bar Problem John Q. Cheng SFI WORKING PAPER: 1996-08-063 SFI Working Papers contain accounts of scientific work of the author(s) and do not necessarily
More informationProduction Planning under Uncertainty with Multiple Customer Classes
Proceedings of the 211 International Conference on Industrial Engineering and Operations Management Kuala Lumpur, Malaysia, January 22 24, 211 Production Planning under Uncertainty with Multiple Customer
More informationOptimal Inventory Allocation under Substitutable Demand
Optimal Inventory Allocation under Substitutable Chi-Yang Tsai Department of Industrial Engineering and Management Yuan Ze University, Taoyuan, Taiwan Tel: (+886) 3-463-8800, Email: iecytsai@saturn.yzu.edu.tw
More informationA Method for Determining Inventory Policy Parameters for a Single Product under Limited Space
A Method for Determining Inventory Policy Parameters for a Single Product under Limited Space Doan Trinh Nguyen #1, Jirachai Buddhakulsomsiri #2, Kanokwan Singha #3 # School of Manufacturing Systems and
More informationThe Inuence of Dierent Workload. Descriptions on a Heuristic Load. Balancing Scheme. Thomas Kunz. December 1991
The Inuence of Dierent Workload Descriptions on a Heuristic Load Balancing Scheme Thomas Kunz December 1991? TI-6/91 Institut fur Theoretische Informatik Fachbereich Informatik Technische Hochschule Darmstadt
More informationA SURVEY ON SUPPLY PLANNING UNDER UNCERTAINTIES IN MRP ENVIRONMENTS
A SURVEY ON SUPPLY PLANNING UNDER UNCERTAINTIES IN MRP ENVIRONMENTS Alexandre Dolgui 1, Aly Ould Louly 2 and Caroline Prodhon 2 1 Scientific Methods for Industrial Management Dept. Division for Industrial
More informationThe Dynamic Transshipment Problem
The Dynamic Transshipment Problem Yale T. Herer 1 and Michal Tzur 2 1 Faculty of Industrial Engineering and Management, Technion-Israel Institute of Technology, Haifa 32000, Israel 2 Department of Industrial
More informationA Note on Convexity of the Expected Delay Cost in Single Server Queues
A Note on Convexity of the Expected Delay Cost in Single Server Queues Kristin Fridgeirsdottir Sam Chiu Decision Sciences, London Business School, Regent Park, London, NW 4SA, UK, kristin@london.edu Department
More informationHow to determine the X in RPI-X regulation: a user's guide
Telecommunications Policy 24 (2000) 63}68 How to determine the X in RPI-X regulation: a user's guide Je!rey I. Bernstein, David E. M. Sappington * Department of Economics, Carleton University and NBER,
More informationSimulation-Based Analysis and Optimisation of Planning Policies over the Product Life Cycle within the Entire Supply Chain
From the SelectedWorks of Liana Napalkova June, 2009 Simulation-Based Analysis and Optimisation of Planning Policies over the Product Life Cycle within the Entire Supply Chain Galina Merkuryeva Liana Napalkova
More informationDepartment of Computer Science and Engineering, University of
Optimizing the BAC-End Strategy for Sequencing the Human Genome Richard M. Karp Ron Shamir y April 4, 999 Abstract The rapid increase in human genome sequencing eort and the emergence of several alternative
More informationOPERATING SYSTEMS. Systems and Models. CS 3502 Spring Chapter 03
OPERATING SYSTEMS CS 3502 Spring 2018 Systems and Models Chapter 03 Systems and Models A system is the part of the real world under study. It is composed of a set of entities interacting among themselves
More informationCompetitive Analysis of Incentive Compatible On-line Auctions
Competitive Analysis of Incentive Compatible On-line Auctions Ron Lavi and Noam Nisan Theoretical Computer Science, 310 (2004) 159-180 Presented by Xi LI Apr 2006 COMP670O HKUST Outline The On-line Auction
More informationA simple model for low flow forecasting in Mediterranean streams
European Water 57: 337-343, 2017. 2017 E.W. Publications A simple model for low flow forecasting in Mediterranean streams K. Risva 1, D. Nikolopoulos 2, A. Efstratiadis 2 and I. Nalbantis 1* 1 School of
More informationThe Role of Items Quantity Constraint to Control the Optimal Economic Order Quantity
Modern Applied Science; Vol. 11, No. 9; 2017 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education The Role of Items Quantity Constraint to Control the Optimal Economic
More informationPrinciples of Inventory Management
John A. Muckstadt Amar Sapra Principles of Inventory Management When You Are Down to Four, Order More fya Springer Inventories Are Everywhere 1 1.1 The Roles of Inventory 2 1.2 Fundamental Questions 5
More informationHow to manage robust tactical planning with an APS (Advanced Planning Systems)
J Intell Manuf (2007) 18:209 221 DOI 10.1007/s10845-007-0015-y How to manage robust tactical planning with an APS (Advanced Planning Systems) Patrick Genin André Thomas Samir Lamouri Received: May 2005
More informationOperations Research Models and Methods Paul A. Jensen and Jonathan F. Bard. Inventory Level. Figure 4. The inventory pattern eliminating uncertainty.
Operations Research Models and Methods Paul A. Jensen and Jonathan F. Bard Inventory Theory.S2 The Deterministic Model An abstraction to the chaotic behavior of Fig. 2 is to assume that items are withdrawn
More informationRevised MRP for reducing inventory level and smoothing order releases: a case in manufacturing industry
Production Planning & Control, 2013 http://dx.doi.org/10.1080/09537287.2013.764579 Revised MRP for reducing inventory level and smoothing order releases: a case in manufacturing industry Marco D Avino*,
More informationEFFECTS OF DETERIORATING INVENTORY ON LOT-SIZING: A COMPARATIVE ANALYSIS OF HEURISTICS FOR MRP SYSTEMS
EFFECTS OF DETERIORATING INVENTORY ON LOT-SIZING: A COMPARATIVE ANALYSIS OF HEURISTICS FOR MRP SYSTEMS Johnny C. Ho, Dept. of Information and Decision Sciences, University of Texas at El Paso, El Paso,
More informationPresence of Grouping. Complementarities
Service Revenue Management in the Presence of Grouping Complementarities by Mohammadreza Farahani A thesis presented to the University of Waterloo in fulllment of the thesis requirement for the degree
More informationSystematic dynamics analysis on bullwhip effects of closed-loop supply chain supported by information system
Acta Technica 62 (2017), No. 5B, 985992 c 2017 Institute of Thermomechanics CAS, v.v.i. Systematic dynamics analysis on bullwhip effects of closed-loop supply chain supported by information system Lin
More informationRevenue management under demand uncertainty: the case for a robust optimization approach
Revenue management under demand uncertainty: the case for a robust optimization approach Aurélie Thiele Lehigh University aurelie.thiele@lehigh.edu Air Products Allentown, PA August 10, 2006 What is revenue
More informationA reverse discount model for dynamic demands. Abhishek Chakraborty. Indian Institute of Management Calcutta
A reverse discount model for dynamic demands Abhishek Chakraborty Indian Institute of Management Calcutta Diamond Harbour Road, Joka, Kolkata-700104, India Email: abhishekc08@iimcal.ac.in and Ashis Chatterjee
More informationMathematical Modeling and Analysis of Finite Queueing System with Unreliable Single Server
IOSR Journal of Mathematics (IOSR-JM) e-issn: 2278-5728, p-issn: 2319-765X. Volume 12, Issue 3 Ver. VII (May. - Jun. 2016), PP 08-14 www.iosrjournals.org Mathematical Modeling and Analysis of Finite Queueing
More informationEuropean Journal of Operational Research
European Journal of Operational Research 214 (2011) 179 198 Contents lists available at ScienceDirect European Journal of Operational Research journal homepage: www.elsevier.com/locate/ejor Invited Review
More informationOman College of Management and Technology
Oman College of Management and Technology Course 803303 PIS Chapter 7 Material Requirements Planning (MRP) CS/MIS Department What is MRP? (Material Requirements Planning) Is a basic tool for performing
More informationSTATISTICAL TECHNIQUES. Data Analysis and Modelling
STATISTICAL TECHNIQUES Data Analysis and Modelling DATA ANALYSIS & MODELLING Data collection and presentation Many of us probably some of the methods involved in collecting raw data. Once the data has
More informationComputing small-fleet aircraft availabilities including redundancy and spares
University of Nebraska - Lincoln DigitalCommons@University of Nebraska - Lincoln U.S. Air Force Research U.S. Department of Defense 2002 Computing small-fleet aircraft availabilities including redundancy
More informationOshoring in a Knowledge Economy
Oshoring in a Knowledge Economy Pol Antras Harvard University Luis Garicano University of Chicago Esteban Rossi-Hansberg Stanford University Main Question Study the impact of cross-country teams formation
More informationAn Inventory Model with Demand Dependent Replenishment Rate for Damageable Item and Shortage
Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 9, 2014 An Inventory Model with Demand Dependent Replenishment Rate for Damageable
More informationISSN: International Journal of Innovative Research in Technology & Science(IJIRTS)
Algorithm for Supply Chain Management: to Suite the Present Industrial Need Dr.Ram Karan Singh 1 Professor, Department of Civil Engineering, King Khalid University, Kingdom of Saudi Arabia; A. Shanmuganathan
More informationDepartment of Economics, University of Michigan, Ann Arbor, MI
Comment Lutz Kilian Department of Economics, University of Michigan, Ann Arbor, MI 489-22 Frank Diebold s personal reflections about the history of the DM test remind us that this test was originally designed
More informationInventory Model Involving Controllable Lead Time through New Approach
Proceedings of the 2012International Conference on Industrial Engineering and Operations Management Istanbul, Turkey, July3 6, 2012 Inventory Model Involving Controllable Lead Time through New Approach
More informationEuropean Journal of Operational Research
European Journal of Operational Research 203 (2010) 526 531 Contents lists available at Scienceirect European Journal of Operational Research journal homepage: www.elsevier.com/locate/ejor Short Communication
More informationINVENTORY MANAGEMENT IN HIGH UNCERTAINTY ENVIRONMENT WITH MODEL REFERENCE CONTROL
INVENTORY MANAGEMENT IN HIGH UNCERTAINTY ENVIRONMENT WITH MODEL REFERENCE CONTROL Heikki Rasku Hannu Koivisto Institute of Automation and Control, Tampere University of Technology, P.O.Box 692, Tampere,
More informationPlanning Nervousness in Product Segmentation: Literature Review and Research Agenda
Planning Nervousness in Product Segmentation: Literature Review and Research Agenda Ann-Louise Andersen, Nicolai Præstholm, Kjeld Nielsen, Thomas Brunø To cite this version: Ann-Louise Andersen, Nicolai
More informationBusiness Quantitative Analysis [QU1] Examination Blueprint
Business Quantitative Analysis [QU1] Examination Blueprint 2014-2015 Purpose The Business Quantitative Analysis [QU1] examination has been constructed using an examination blueprint. The blueprint, also
More informationThe integration of online and offline channels
The integration of online and offline channels Zihan Zhou, Qinan Wang Nanyang Business School, Nanyang Technological University, Nanyang Avenue, Singapore 69798 zzhou6@e.ntu.edu.sg Abstract We study a
More informationModeling of competition in revenue management Petr Fiala 1
Modeling of competition in revenue management Petr Fiala 1 Abstract. Revenue management (RM) is the art and science of predicting consumer behavior and optimizing price and product availability to maximize
More informationIncorporating demand uncertainty and forecast error in supply chain planning models
Journal of the Operational Research Society (2011) 62, 483 --500 2011 Operational Research Society Ltd. All rights reserved. 0160-5682/11 www.palgrave-journals.com/jors/ Incorporating demand uncertainty
More informationC. Wohlin, P. Runeson and A. Wesslén, "Software Reliability Estimations through Usage Analysis of Software Specifications and Designs", International
C. Wohlin, P. Runeson and A. Wesslén, "Software Reliability Estimations through Usage Analysis of Software Specifications and Designs", International Journal of Reliability, Quality and Safety Engineering,
More informationStochastic Lot-Sizing: Maximising Probability of Meeting Target Profit
F1 Proceedings of the 2012 International Conference on Industrial Engineering and Operations Management Istanbul, Turkey, July 3 6, 2012 Stochastic Lot-Sizing: Maximising Probability of Meeting Target
More informationPlanning. Planning Horizon. Stages of Planning. Dr. Richard Jerz
Planning Dr. Richard Jerz 1 Planning Horizon Aggregate planning: Intermediate-range capacity planning, usually covering 2 to 12 months. Long range Short range Intermediate range Now 2 months 1 Year 2 Stages
More informationBehavioral-Based Advertising
Behavioral-Based Advertising Qiaowei Shen (Peking University) J. Miguel Villas-Boas (University of California, Berkeley) November, 016 E-mail addresses: qshen@gsm.pku.edu.cn, and villas@haas.berkeley.edu.
More informationStochastic Single Machine Family Scheduling To Minimize the Number of Risky Jobs
Stochastic Single Machine Family Scheduling To Minimize the Number of Risky Jobs Gökhan Eğilmez Ͼ, Gürsel A. Süer Industrial and Systems Engineering Department Russ College of Engineering and Technology
More informationDOCUMENTOS DE TRABAJO Serie Economía
DOCUMENTOS DE TRABAJO Serie Economía Nº 252 FIRM-PROVIDED TRAINING AND LABOR MARKET POLICIES FELIPE BALMACEDA Firm-Provided Training and Labor Market Policies Felipe Balmaceda 1 September 30, 2008 1 I
More information