C& D landfill Burrell Demolition Ltd : Response to Section 92 Requests : Leachate Management

Size: px
Start display at page:

Download "C& D landfill Burrell Demolition Ltd : Response to Section 92 Requests : Leachate Management"

Transcription

1 Opus International Consultants Ltd Whakatane Office Concordia House, Pyne Street PO Box 800, Whakatane 3158 New Zealand 4th October 2013 t: f: w: Christine Morgan C&D Landfill Ltd 2 Landfill Road Happy Valley Wellington Dear Christine C& D landfill Burrell Demolition Ltd : Response to Section 92 Requests : Leachate Management We have reviewed leachate management for the proposed western extension of the C &D landfill and advise as follows: 1. Water Quality Monitoring to Date Water quality is monitored at 4 sample locations as shown on the attached figure Water Quality Sample Locations : -Site 1 - upstream of current south C & D fill - Site 2 - Discharge from culvert outfall from western gully - Site 3 Careys Gully stream downstream of western gully - Site 4 Seep area above landfill access road None of these sites are a true representation of the leachate or drainage water sourced solely from the C & D fill, but do give an indication of the nature of leachate to be expected from the extension fill. Monitoring results are appended. Site 1 is upstream of any landfill influence and is characterised by high water quality with low levels of dissolved salts (conductivity ms/m) and very low levels of dissolved metals. Site 2 at the downstream toe is understood to be sampling a mixture of clean water from the upstream western gully, drainage from the historic Wellington City closed landfill and the C & D southern fills. This sample site shows some landfill influence with higher alkalinity and conductivity (42-49 ms/m) and higher metal levels. Iron and manganese in particular are considerably higher than the upstream sample (7.56 g/m 3 and g/m 3 respectively on 4 March 2013). Notably ammoniacal nitrogen levels are still very

2 low. This site does not therefore explicitly establish the character of leachate from the C & D fill. Site 3 picks up flow from both branches of the Carey Gully stream and so also includes potential influences from the Wellington City Council landfills. Site 4 being the seep has higher alkalinity and conductivity again (180 g/m 3 and 68 ms/m respectively). Iron and manganese are in a similar range to Site 2. The seep has slightly elevated ammoniacal nitrogen at g/m 3. This is indicative of leachate (albeit quite dilute) from a fill containing organic material. However it is not clear from the location whether this site is solely sourced from C & D or may include some old municipal mixed refuse. 2. Expected Character of Construction & Demolition site leachate Leachates from construction and demolition type landfills are variable reflecting the particular waste stream entering the site. In particular the proportions of organic matter (as wood and wood products, vegetation, cardboard and paperboard) can vary widely from site to site. This makes prediction of a leachate composition on the basis of published data from other sites uncertain. However the following generalisations can be made 1 : If levels of organic matter are low, say less than 5% by weight then nitrogen levels (as ammoniacal nitrogen or nitrate) will be low relative to municipal waste fills Levels of dissolved salts from the major anions and cations will be elevated, showing up as higher conductivity and TDS (total dissolved solids) A major contributor to TDS is often sulphate and calcium sourced from dissolution of plasterboard 2. Sulphate levels in excess of 1,000 g/m3 are not uncommon for construction and demolition landfills with large inputs of plasterboard. If sulphate reducing bacteria are present sulphate will be converted to H 2S (hydrogen sulphide) Dissolved iron and manganese levels are commonly elevated being mobilised from residual metal items and from incoming soil. Unless the site is taking soil from contaminated sites then hydrocarbon levels would be very low A range of heavy metals may be present including commonly zinc, copper, lead and mercury. These will be sourced from miscellaneous items in the waste mix, lead paint residue, small electrical items etc but are generally found at low levels. Boron may be elevated if substantial quantities of boric treated framing timber are present. Page 2

3 Referring to the proposed waste acceptance criteria in the C & D Landfill Management Plan Sections and Acceptable and Unacceptable Materials, the following points are relevant: While the site predominantly accepts inert materials such as soil from site excavations and demolition rubble ie brick and concrete, a range of other materials are listed in the site acceptance criteria, including - Sheet roofing material - Framing timber which may be treated - Steels in form of rebar and tendon - Galvanised steel - Plasterboard - Plastics eg as electrical fittings and packaging - Floor coverings adhering to concrete and timber - Asphalt - Electrical wiring as part of mixed demolition loads - Cardboard packaging While most of the materials disposed are essentially inert in the landfill, a number of items in the above list do have potential to release contaminants to leachate. Importantly, the waste acceptance criteria limit the organic content as woodwaste, vegetation and all other packaging, carpet etc to a maximum of 5% by weight. C&D advise that in practice actual wood waste content of the loads would be considerably less, but they do wish to maintain the 5% limit to allow some contingency for mixed loads such as from site clearing or slip material. Waste is sorted as received to maximise the recovery of useful materials and in particular metal items. However it is inevitable that some items will not be recoverable being too small or mixed with general rubble. Overall therefore the waste stream can be expected to generate a leachate with elevated levels of major anions/cations, but low levels of nutrients, heavy metals and organic contaminants. While there are no specific measurements of leachate from the existing fill, the water quality observations noted above generally support this conclusion. Should the proportion of organic materials rise above 5% then it would be expected that levels of ammoniacal nitrogen in the leachate will start to rise. 3. Leachate quantity The quantity of leachate generated from the proposed fill will be a function of: - Area of the fill surface ie rainwater catchment - Extent of temporary and permanent capping on the fill which is able to shed water to stormwater (as opposed to allowing it to percolate into the fill) - Inflow of surface water from upslope catchments Page 3

4 - Inflow from groundwater sources The direct catchment area is 3.68 ha for Stage 1W. The average annual rainfall at the site is estimated to be 1450mm approx., being some 1.17 x the kelburn gauge rainfall, reflecting the proximity of the site to the south coast (NZET 4 1/10/2013 Section 3.1), ranging from 700mm in a very dry year to 2100 mm in a peak wet year. The peak monthly rainfalls are from May to August being typically mm /month. The relatively small fill platform and large vertical lift will limit the practicality of placing intermediate capping. For leachate assessment purposes a conservative (ie high) position has been taken of assuming all the Stage 1w area of 3.68 ha is open to incident rainfall. The nature of the C & D fill material being rubble and open graded means it will tend to be permeable to incident rainfall with little runoff except in heavy rains and on compacted access roads. Inflow from the upper catchment slopes is to be managed by contour stormwater drains. These will intercept the water and shed it clear as stormwater with minimal contribution to water percolating into the fill (NZET 4 Section 4.4 discusses the contour interceptor drains). Inflow from groundwater sources is expected from the infilled colluvium gullies that feed into the main western gully. These gully features will be traversed by the contour drains. It is proposed to excavate into, or more likely tap into these with horizontal well points, to intercept water draining down the interface between the colluvium and the greywacke. This will minimise the volume of groundwater reaching the gully floor. However realistically it is not expected to be feasible to intercept all the flow in these gullies and so no reliance on interception has been made in assessing groundwater contributions. On the basis of the above assumptions the following conservative assessment of the groundwater/leachate quantity for Stage 1W is approximately 250 m 3 per day (3.0 l/s approx.) as an annual average, derived as: - 30% of incident annual rainfall on the 3.68 ha of landfill area below the contour stormwater drains making some 44 m 3 /day. - A net 300mm of annual rainfall being the groundwater component from the colluvial gullies of the upslope catchments (25 ha) making some 205 m 3 /day. The actual evapotranspiration at Kelburn is 852 mm/yr leaving typically 596 mm for surface runoff and groundwater contribution. Typically around 20% of precipitation in a well vegetated catchment with rainfall of around mm shows as stream flow 3. This leaves 300mm for the subsurface flow component. Note this is probably on the high side, with more typically 10% of incident rainfall contributing to groundwater flows. The water flow from the fill will therefore be a mixture of leachate from the fill and groundwater and thus be diluted approx. 4:1. While flows will vary with season and rainfall, the fill mass and groundwater contribution will attenuate the peak flows from individual rainfall events. For the purpose of sizing outfall pumps and pipework etc a peak of 4x the base flow is assumed, but would need to be confirmed by final design. Page 4

5 4. Proposed Leachate Management Strategy Recognising that there are uncertainties over both the quantity and contaminant levels of leachate which may be generated by the proposed C & D fill, a tiered management approach is proposed as follows: (i) (ii) (iii) (iv) (v) (vi) (vii) Prior to filling commencing, construct a groundwater/leachate collection system into the gully base (Figures 1-3). This will consist of a toe dam at the downstream end of each stage to pick up groundwater/leachate flow off the greywacke basement and direct it into a collection pipe. The gully floor is steep at a 1:5 longitudinal gradient. The alluvial fill depth is variable, from 0- approx 2.0 m. A site at the toe will be selected with moderate width and minimal alluvial depth at which to construct the toe detail. A toe bund of low permeability material such as compacted weathered greywacke or waste concrete will be constructed onto the base rock to intercept the downslope leachate/groundwater flow (Figure 2) Running up the base of the main gully will be a highly permeable rubble filled trench. This will pick up water infiltrating down through the main fill, plus any side inflows from the paleogullies (specific side taps included as needed) The combined groundwater/leachate flow will be directed into a lined retention pond at the head of Stage 2 including a flow measurement and water quality monitoring point. From the retention pond direct flow through a constructed wetland prior to discharge to the Western gully stream, subject to compliance with discharge conditions after reasonable mixing. Minimise contribution of upslope catchment to water entering the fill using contour drains as per NZET 4 Cap and grass completed fill areas as soon as feasible, including using intermediate capping, so more surface water can be shed to the contour drains and clear of the fill at an early point Provide contingency system for discharge of groundwater/leachate to sewer as trade waste should a direct discharge not be in compliance. This will be subject to detailed design. Two options arise, being either to pump the flow away via the South C & D fill, or (preferred) to construct a new contour access bench and pipeline down to the existing culvert. Note that this bench will be required in future as part of the Stage 2 stormwater control. In either case the flows are predicted to be quite manageable even allowing for peaking in wet weather. Page 5

6 5. Lining of the Fill It is not proposed to line the gully base and sides beneath the proposed fill, apart from the localised treatment at the toe stage to intercept groundwater/leachate flow. The rationale for this is: (i) (ii) (iii) The hydrogeological assessment (GeoScience October ) identifies that the gully base is the primary end point of groundwater flow from the rock mass, primarily from the colluvium filled gullies. Ie any flow component of groundwater out into the surrounding rock mass will be (a) very small in quantity and (b) reliant upon travel through weathering features such as shear zones and fissures and be relatively slow. Provision of a high permeability flow path with a rubble filled trench in the valley floor will engineer a preferential flow path that is orders of magnitude higher in transmissivity than the rock mass. Therefore flow from the fill into the surrounding country will be minor provided the base of the fill is well drained. The leachate is predicted to have low levels of contaminants and to be at or close to a level allowing direct discharge after wetland treatment 6. Monitoring The following monitoring is proposed for the groundwater/leachate discharge: (i) (ii) (iii) (iv) Weekly recording of flow at a v-notch weir on the discharge (if to stream) or by flow meter on pump (if pumped) Weekly conductivity of discharge Quarterly key indicator parameters of EC, ph, Ammoniacal nitrogen, nitrate nitrogen, DRP, Chloride, Potassium, Iron, Sulphate, Boron Annual full suite of above plus metals (as dissolved) Arsenic, Cadmium, Copper, Chrome, Lead, Manganese, Nickel, Zinc, also BOD 5, TPH and organics (semivoc) 7. Future Staging Stage 1W is discrete and quite separate from any past activity on site and can be effectively managed as described. Data collected from Stage 1W will be quite specific to the effects of the C &D fill and will be used to inform leachate management of future stages. At this stage the following is envisaged: (i) Stage 1N upstream of the land bridge This will be filled with selected inert soil and rubble with minimal leachate generating potential until the level of the land bridge runs out into the gully floor. At that point future flows of stormwater and leachate can be directed across the fill. In addition more Page 6

7 area will be available on the completed fill for construction of (lined) treatment ponds for leachate from the upslope Stages 1W, 2W and 3W (NZET Section 4.2). (ii) Stage 2 With Stage 1N complete as above the toe detail from Stage 1W can then be replicated for Stage 2. For this stage a large area is available on Stage 1 N for further leachate treatment and simple gravity flow is available for discharge. (iii) Stage 3 Stage 3 is an overlay of Stages 1W and 2 and can rely upon the infrastructure for Stage Landfill Gas The C & D fill will be a minor generator of landfill gas. Contributors to landfill gas would be the small organic content. Wood as stumps and framing timber would be very slow to degrade. Only finer material such as vegetation, packaging, textiles (carpets) etc would contribute to any degree. However with an overall organic content limited to 5% inclusive of wood and stumps, the remaining fraction is small. Plasterboard may contribute to H 2S generation through action of sulphate reducing bacteria. Receptors for landfill gas will be limited to site staff on the fill itself. Their exposure would be trivial compared to personnel working on a normal refuse landfill. The nearest public receptors would be walkers on the ridge top tracks some 100m horizontally and 200m vertically above in a very exposed location. Or the recycling area some 300m down the gully on the other side of the main landfill access road. On this basis we conclude the landfill gas generation to be of less than minor impact and that no further specific analysis is warranted. References 1 : Melendez, B. A. (1996). A study of leachate generated from construction and demolition waste landfills. MS thesis, Dept. of Envir. Engrg. Sci., University of Florida, Gainesville, Fla 2: Townsend, Jang & Thurn, 1999 Simulation of Construction & Demolition Waste leachate, J. Environ Eng 125(11) 3: Fahey & Rowe 1992, in The Physical Environment A New Zealand Perspective Ed Sturman & Spronken-Smith, OUP : NZET 2013: C& D Landfill Burrell Demolition Ltd Response to S92 requests Stormwater 5: Geoscience 2013, C&D Landfill Expansion Geotechnical Assessment Page 7

8 Attachments Figures Water Quality Sample Locations Figure C 4 : GeoScience Stage 1W Plan Figure 1 : Landfill Toe Detail and cross sections Water Quality Data Yours faithfully Peter Askey Principal Environmental Engineer Page 8

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:

More information

Stage One North Detail Refer to Geoscience Drawings

Stage One North Detail Refer to Geoscience Drawings Stormwater and Leachate Treatment Stage One North Detail Refer to Geoscience Drawings Morning glory bell mouth spillway Pe r i me ter d Spreader Bar rain Sediment Retention, Stormwater Detention Pond Area

More information

W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program

W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program W12A Landfill Groundwater, Leachate, Water Well, Landfill Gas and Surface Water Quality Monitoring Program The groundwater, leachate, water well, landfill gas and surface water monitoring programs are

More information

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT

THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT THE GOVERNMENT OF MALAYSIA PRIME MINISTER S DEPARTMENT ECONOMIC PLANNING UNIT THE STUDY ON INTEGRATED URBAN DRAINAGE IMPROVEMENT FOR MELAKA AND SUNGAI PETANI IN MALAYSIA FINAL REPORT VOL. 5: TECHNICAL

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

Appendix D. Erosion Management Sub- Plan

Appendix D. Erosion Management Sub- Plan Appendix D Erosion Management Sub- Plan DRENNAN SOLAR ENERGY FACILITY EROSION MANAGEMENT PLAN PRODUCED FOR ERM ON BEHALF OF SOLAIREDIRECT BY Simon.Todd@3foxes.co.za JUNE 2013 PURPOSE The purpose of the

More information

Sustainable management of Christchurch's waterways and wetlands using stormwater soakage disposal

Sustainable management of Christchurch's waterways and wetlands using stormwater soakage disposal Impacts of Urban Growth on Surface Water and Groundwater Quality (Proceedings of IUGG 99 Symposium HS5, Birmingham, July 1999). IAHS Publ. no. 259, 1999. 365 Sustainable management of Christchurch's waterways

More information

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11 Appendix 11 Erosion and Sediment Control Management Plan Appendix 11 OTAIKA QUARRY - PROPOSED OVERBURDEN DISPOSAL AREA Application for Land Use Consent and Assessment of Environmental Effects Otaika Quarry

More information

CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING

CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING CCE AWARD SUBMISSION BARRIE LANDFILL RECLAMATION AND RE-ENGINEERING 2 CCE AWARD SUBMISSION GOLDER ASSOCIATES LTD. SUMMARY The City of Barrie landfill was impacting water resources and required remediation.

More information

New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan

New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan New England Quarry Resource Recovery Centre Landfill Nr Ivybridge, Devon Environmental Permit (EP) Application Surface Water Management Plan February 2011 Ref: 402.0036.00463/SWMP Viridor i Ref: 407-0036-00463/SWMP

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

Physiographic zones. and water quality

Physiographic zones. and water quality Southland Physiographic zones Peat Wetlands Technical information Physiographic zones are part of the Water and Land 2020 & Beyond project that aims to maintain and improve water quality in the Southland

More information

AS/NZS 1547:2012 and DIR ADJUSTMENT for SIZING ON-SITE WASTEWATER DRIP IRRIGATION AREAS on SLOPING SITES

AS/NZS 1547:2012 and DIR ADJUSTMENT for SIZING ON-SITE WASTEWATER DRIP IRRIGATION AREAS on SLOPING SITES AS/NZS 1547:2012 and DIR ADJUSTMENT for SIZING ON-SITE WASTEWATER DRIP IRRIGATION AREAS on SLOPING SITES 1.0 AS/NZS 1547 Table M2, DIR slope adjustment factors On-Site NewZ has received queries related

More information

Bioreactor Landfill Design

Bioreactor Landfill Design Bioreactor Landfill Design Timothy Townsend, PhD, PE Department of Environmental Engineering Sciences University of Florida ttown@ufl.edu Bioreactor Landfill Design Modern landfill design entails many

More information

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment

Globeville Landing Outfall Surface Water. December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Globeville Landing Outfall Surface Water December 12, 2017 Andrew Ross, Jon Novick Denver Department of Public Health & Environment Introductions Andrew Ross Environmental Program Manager, DDPHE Jon Novick

More information

Environmental Management System

Environmental Management System Environmental Management System Moreton Bay Research Station (MBRS) Water Management Program 1. Program Scope The Water Management Program incorporates all the water used throughout the Moreton Bay Research

More information

To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER

To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER To reduce the environmental impact we should ISOLATE or CONTAIN the waste in an IMPERMEABLE BARRIER 1 COMPONENTS OF ENGINEERED LANDFILL a) A Liner System b) A Leachate Collection Facility c) A Gas Control

More information

CENTRAL COAST POST-CONSTRUCTION REQUIREMENTS IMPLEMENTATION GUIDANCE SERIES 1

CENTRAL COAST POST-CONSTRUCTION REQUIREMENTS IMPLEMENTATION GUIDANCE SERIES 1 CENTRAL COAST POST-CONSTRUCTION REQUIREMENTS IMPLEMENTATION GUIDANCE SERIES 1 SERIES ISSUE #2: DECENTRALIZED STORMWATER MANAGEMENT TO COMPLY WITH RUNOFF RETENTION POST-CONSTRUCTION STORMWATER CONTROL REQUIREMENTS

More information

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and

San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons and San Francisco State University Site 1 Vegetated Infiltration Basin Monitoring Report: Rainy Seasons 2011-12 and 2012-13 Project Overview San Francisco State University (SFSU) has implemented several green

More information

ZONING ORDINANCE FOR THE ZONED UNINCORPORATED AREAS ARTICLE 1500 OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS

ZONING ORDINANCE FOR THE ZONED UNINCORPORATED AREAS ARTICLE 1500 OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS 1500.01 GENERAL REQUIREMENTS 1500.02 NATURE OF STORM WATER FACILITIES 1500.03 DRAINAGE EASEMENTS 1500.04 STORM WATER MANAGEMENT

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent Slope Drains DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [1] Slope drains can act as outlet

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent Slope Drains DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [1] Slope drains can act as outlet

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS March 18, 2003 This page left blank intentionally. March 18, 2003 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method

More information

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives

Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

Farming Challenges and Opportunities

Farming Challenges and Opportunities RURAL Farming Challenges and Opportunities Managing water and nutrient at the farm and paddock scale Roger MacGibbon National Technical Director Opus Rural November 2016 Opus Rural Our Rural team comprises

More information

Webinar Overview. Presenter: Moderator: Length of Webinar: (1) hour Questions: For More Information or Comments: Amanda Ludlow Principal Scientist

Webinar Overview. Presenter: Moderator: Length of Webinar: (1) hour Questions: For More Information or Comments: Amanda Ludlow Principal Scientist Webinar Overview Presenter: Amanda Ludlow Principal Scientist Moderator: Tanya Bissell Length of Webinar: (1) hour Questions: Mid & Post Presentation Please submit via the viewing panel For More Information

More information

Reference Guideline #1. Hydrogeological Impact Assessment

Reference Guideline #1. Hydrogeological Impact Assessment Reference Guideline #1 Hydrogeological Impact Assessment Reference Guideline #1 Hydrogeological Impact Assessment Hydrogeological assessments are required for some subdivision applications when triggered

More information

Flow Diversion Banks: General

Flow Diversion Banks: General Flow Diversion Banks: General DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Flow diversion

More information

6.5 The Present Situation Water Quality Stormwater quality is currently being improved by:

6.5 The Present Situation Water Quality Stormwater quality is currently being improved by: 6.5 The Present Situation 6.5.1 Water Quality Stormwater quality is currently being improved by: o o o o The SPE project. The project is driven by the 11 resource consents for the discharge of wastewater-contaminated

More information

the 2001 season. Allison brought high winds and street flooding to Houston, after

the 2001 season. Allison brought high winds and street flooding to Houston, after Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of

More information

TRANSFORMING LEACHATE MANAGEMENT AT THE KIMBRIKI RESOURCE RECOVERY CENTRE, SYDNEY, AUSTRALIA

TRANSFORMING LEACHATE MANAGEMENT AT THE KIMBRIKI RESOURCE RECOVERY CENTRE, SYDNEY, AUSTRALIA TRANSFORMING LEACHATE MANAGEMENT AT THE KIMBRIKI RESOURCE RECOVERY CENTRE, SYDNEY, AUSTRALIA S. DEVER*, B. LAU*, AND A. ROBERTS** * Kimbriki Environmental Enterprises Pty Ltd & University of New South

More information

Inflow pipe. Drain. Drain

Inflow pipe. Drain. Drain Inflow pipe Screened overflow Drain Foul flush diverter Screened intake Manhole cover Maximum water level Seal Inspection cover Possible local drainage through screen Drain Bottom sloped Screened outlet

More information

Permeable Pavement Facilities and Surfaces

Permeable Pavement Facilities and Surfaces Permeable Pavement Facilities and Surfaces This checklist is intended to highlight items critical to the performance of permeable pavement facilities and surfaces that need to be addressed in the design

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

Erosion Control Inspection Form

Erosion Control Inspection Form Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection

More information

[1] Level spreaders can release sheet flow down steep slopes, but the level spreader itself must be constructed across a level gradient.

[1] Level spreaders can release sheet flow down steep slopes, but the level spreader itself must be constructed across a level gradient. Level Spreaders DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Level spreaders can release

More information

Physiographic zones. and water quality

Physiographic zones. and water quality Southland Physiographic zones Central Plains Technical information Physiographic zones are part of the Water and Land 2020 & Beyond project that aims to maintain and improve water quality in the Southland

More information

Mother Nature s Treatment Methods:

Mother Nature s Treatment Methods: Mother Nature s Treatment Methods: Using Passive Treatment for a Variety of Wastewater Streams Brian Tornes, PE History of Wastewater Treatment Background The Start of Sanitation Evidence of Sewers as

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

C & D Landfill Burrell Demolition Ltd

C & D Landfill Burrell Demolition Ltd Page1 New Zealand Environmental Technologies Ltd Phone: (04) 526 4109, (04) 5267589; Fax: (04) 526-4190; Mobile: 0274 492 837 81 Gillespies Road, PO Box 40-339 Upper Hutt, Wellington Email: office@nzet.net.nz;

More information

Block & Aggregate Drop Inlet Protection

Block & Aggregate Drop Inlet Protection Block & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

POTABLE WATER SUPPLY DEFINITIONS

POTABLE WATER SUPPLY DEFINITIONS Definitions POTABLE WATER SUPPLY DEFINITIONS AQUIFER. A porous, water-bearing geologic formation. Generally restricted to materials capable of yielding an appreciable supply of water. BASIN. A natural

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent

More information

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2

Holcim (Australia) Pty Limited. Lynwood Quarry Groundwater Monitoring Program Revision 2 Holcim (Australia) Pty Limited Lynwood Quarry Groundwater Monitoring Program Revision 2 June 2011 Lynwood Quarry Groundwater Monitoring Program Revision 2 Prepared by on behalf of Holcim (Australia) Pty

More information

SWANA 2017 Leachate Basics and Quality Changes with Organics Removal. Steve Johnson M.Eng., P.Eng.

SWANA 2017 Leachate Basics and Quality Changes with Organics Removal. Steve Johnson M.Eng., P.Eng. SWANA 2017 Leachate Basics and Quality Changes with Organics Removal Steve Johnson M.Eng., P.Eng. May 2017 2 Landfills that take over 10,000 tonnes per year? How many of you have leachate collection systems?

More information

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116 (i) Site Name and Ownership Information: HISTORY OF CONSTRUCTION 40 CFR 257.73(c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY Site Name: Site Location: Site Address: Owner: Owner Address:

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

Hydromodification Management Measures

Hydromodification Management Measures Chapter 7 Hydromodification Management Measures This Chapter summarizes the requirements for controlling erosive flows from development projects. 7.1 Why Require Hydromodification Management? Changes in

More information

Assessment and Restoration of the BP Llandarcy Refinery Landfill Martin Chapple, URS Corporation Ltd., Bristol, UK

Assessment and Restoration of the BP Llandarcy Refinery Landfill Martin Chapple, URS Corporation Ltd., Bristol, UK Assessment and Restoration of the BP Llandarcy Refinery Landfill Martin Chapple, URS Corporation Ltd., Bristol, UK 25th May 2004 History of the Llandarcy Refinery Commissioned in 1921 UK s oldest refinery

More information

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream

What is runoff? Runoff. Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream What is runoff? Runoff Runoff is often defined as the portion of rainfall, that runs over and under the soil surface toward the stream 1 COMPONENTS OF Runoff or STREAM FLOW 2 Cont. The types of runoff

More information

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage

More information

PRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc.

PRELIMINARY MUNICIPAL SERVICING REPORT NORTHWOODS SUBDIVISION. Prepared for: North Grassie Properties Inc. PRELIMINARY MUNICIPAL SERVICING REPORT SUBDIVISION Prepared for: North Grassie Properties Inc. Prepared by: Stantec Consulting Ltd. 905 Waverley St. Winnipeg, MB R3T 5P4 July 2012 File: 116808030 SUBDIVISION

More information

LETHBRIDGE WASTE AND RECYCLING CENTRE PROJECT SUMMARY

LETHBRIDGE WASTE AND RECYCLING CENTRE PROJECT SUMMARY LETHBRIDGE WASTE AND RECYCLING CENTRE PROJECT SUMMARY 1.1 Location and Site Description The Lethbridge Waste and Recycling Centre is located approximately in the SW ¼ 4-10-21-W4. The proposed expansion

More information

River Channel Characteristics

River Channel Characteristics River Channel Characteristics Storages and Transfers in Drainage Basins Precipitation Evapotranspiration SURFACE STORAGE INTERCEPTION STORAGE CHANNEL STORAGE Soil Moisture Storage Aeration Zone Storage

More information

TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION

TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION 1 TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION Draft 2/08/10 (Revised 02-14-11,Revised 02-21-11, Revised 03-03-11, Revised 04-19-11, Revised 04-20-11, Revised 05-05-11, Revised 05-09-11). DEFINITIONS

More information

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE

FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY 405 TWEEDSMUIR AVENUE FUNCTIONAL SERVICING AND STORMWATER MANAGEMENT STUDY FOR CITY OF OTTAWA PROJECT NO.: 11-532 FOR TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Existing Conditions... 2 1.2 Required Permits / Approvals...

More information

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds Section 8: Amended Soil Mounds 8. Amended Soil Mounds 8. Amended Soil Mounds 8.1 Design...95 8.2 Installation...96 8.3 Inspection...101 8.4 Operation...101 8.5 Common technical issues...105 8.6 Case study...105

More information

Fabric Drop Inlet Protection

Fabric Drop Inlet Protection Fabric Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Block

More information

Modelling Stormwater Contaminant Loads in Older Urban Catchments: Developing Targeted Management Options to Improve Water Quality

Modelling Stormwater Contaminant Loads in Older Urban Catchments: Developing Targeted Management Options to Improve Water Quality Modelling Stormwater Contaminant Loads in Older Urban Catchments: Developing Targeted Management Options to Improve Water Quality Frances J. CHARTERS 1, Thomas A. COCHRANE 1, Aisling D. O SULLIVAN 1 1

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

Applying landforming to reclamation: A case study in Central Appalachia

Applying landforming to reclamation: A case study in Central Appalachia Applying landforming to reclamation: A case study in Central Appalachia Leslie Hopkinson, John Quaranta April 12, 2017 Department of Civil and Environmental Engineering West Virginia University WEST VIRGINIA

More information

SECURE Energy Services Inc. Proposed Conklin Class II Landfill Portions of: NE W4, SE W4 and NW W4

SECURE Energy Services Inc. Proposed Conklin Class II Landfill Portions of: NE W4, SE W4 and NW W4 26 February 2016 RE: SECURE Energy Services Inc. Proposed Conklin Class II Landfill Portions of: NE 23-76-8W4, SE 26-76-8W4 and NW-24-76-8W4 Dear Sir or Madam, SECURE Energy Services Inc. ( SECURE ) is

More information

Management of geotechnical risks for some tunnels in the Wellington Region

Management of geotechnical risks for some tunnels in the Wellington Region Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Management of geotechnical risks for some tunnels in the Wellington Region David Stewart Opus International

More information

Magino Project Environmental Impact Statement. Technical Support Document Environmental Monitoring Plan

Magino Project Environmental Impact Statement. Technical Support Document Environmental Monitoring Plan Magino Project Environmental Impact Statement Technical Support Document 20-13 Rev. No. Revision Date Approved 0 Document issued for EIS Table of Contents SECTION 1.0 Purpose of the Plan... 1 1.1 Scope

More information

Wastewater Collection System

Wastewater Collection System WASTEWATER COLLECTION SYSTEM CE 370 1 Wastewater Collection System The function of the collection system is to collect the wastewater from residential, commercial, and industrial areas within the service

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS ESTIMATING RUNOFF FROM SMALL WATERSHEDS June 2011 THIS PAGE LEFT BLANK INTENTIONALLY. June 2011 TABLES Table E.1 Table E.2 Return Frequencies for Roadway Drainage Design Rational Method Values June 2011

More information

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) Tararua District Council Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) NOTE: This is a draft ESCP in current preparation. Additional and updated information will

More information

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS

Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Lagan Cement Ltd. IPPC Licence Application Attachment N o F.2 EMISSIONS MONITORING AND SAMPLING POINTS Air Contents F.2.0 Air Emissions.3 Water

More information

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion.

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion. Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Stormwater Best Management Practices for Marinas and Boatyards

Stormwater Best Management Practices for Marinas and Boatyards Stormwater Best Management Practices for Marinas and Boatyards December 17, 2014 Jonathan Rivin University of Wisconsin - Extension Solid and Hazardous Waste Education Center Environmental regulations

More information

Ayrburn Farm Development Infrastructure Assessment Report

Ayrburn Farm Development Infrastructure Assessment Report Ayrburn Farm Development Infrastructure Assessment Report 1 EXECUTIVE SUMMARY Further to Clark Fortune McDonald & Associates correspondence dated 12 February 2015 please find below the assessment of foul

More information

Guidance on each of the 23 basic elements follows: Plan Index showing locations of required items: The plan index should include a list of the

Guidance on each of the 23 basic elements follows: Plan Index showing locations of required items: The plan index should include a list of the Guidance on each of the 23 basic elements follows: A1 Plan Index showing locations of required items: The plan index should include a list of the required items in the rule and where they occur in the

More information

ET COVER SYSTEM IN ARID ENVIRONMENTS

ET COVER SYSTEM IN ARID ENVIRONMENTS ET COVER SYSTEM IN ARID ENVIRONMENTS JUSTIFYING THE USE OF AN EVAPO TRANSPIRATIVE COVER SYSTEM FOR CAPPING AN INDUSTRIAL WASTE PILE SAVES CLIENT MILLIONS Martin E. Carlson, PE May 8, 2018 PRESENTATION

More information

Grovelands Park Wetlands, Enfield

Grovelands Park Wetlands, Enfield Grovelands Park Wetlands, Enfield Description This project was undertaken as part of the Salmons Brook Healthy River Challenge, an initiative designed to improve water quality in the Salmons Brook and

More information

Guidance Document for Storm Water Pollution Prevention Plan (SWPPP) Submittal. A2 Plat showing building lot numbers/boundaries and road layout/names:

Guidance Document for Storm Water Pollution Prevention Plan (SWPPP) Submittal. A2 Plat showing building lot numbers/boundaries and road layout/names: Exhibit SW12-3 Page 1 of 10 Guidance Document for Storm Water Pollution Prevention Plan SECTION A CONSTRUCTION PLAN ELEMENTS A1 Plan Index showing locations of required items: The plan index should include

More information

4.0 ENVIRONMENTAL IMPACT ANALYSIS 4.10 UTILITIES -- WASTEWATER

4.0 ENVIRONMENTAL IMPACT ANALYSIS 4.10 UTILITIES -- WASTEWATER 4.0 ENVIRONMENTAL IMPACT ANALYSIS 4.10 UTILITIES -- WASTEWATER ENVIRONMENTAL SETTING Existing Conditions The BLRC generates wastewater in two forms: the liquid that is produced when water percolates through

More information

Drainage Servicing Report - Terms of Reference

Drainage Servicing Report - Terms of Reference Urban Form and Corporate Strategic Development City Planning 7th Floor, Edmonton Tower 10111 104 Avenue NW Edmonton, AB T5J 0J4 edmonton.ca July 2018 1 Introduction: Drainage Servicing Reports Drainage

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills Waste/Solid Waste #5.02, October 2005

Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills Waste/Solid Waste #5.02, October 2005 Solid Waste Program Guidance for Liner Design for Demolition Debris or Industrial Solid Waste Landfills, October 2005 INTRODUCTION In Minnesota, ground water is owned by the people of the state until it

More information

LOT GRADING GUIDELINES FOR LOW DENSITY RESIDENTIAL PROPERTIES

LOT GRADING GUIDELINES FOR LOW DENSITY RESIDENTIAL PROPERTIES LOT GRADING GUIDELINES FOR LOW DENSITY RESIDENTIAL PROPERTIES Contents LOT GRADING GUIDELINES... 3 LOW DENSITY RESIDENTIAL PROPERTIES... 3 Introduction... 3 Definitions:... 3 Purpose... 3 LOT GRADING APPROVAL

More information

STORM DRAINAGE CHAPTER 11

STORM DRAINAGE CHAPTER 11 CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,

More information

Stormwater Management. Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC

Stormwater Management. Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC Stormwater Management Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC Agenda What is Stormwater? Why is Stormwater a Problem? NY State Regulations Stormwater Pollution Prevention Plans What

More information

8.1 Introduction 8.2 Summary 8.3 Conclusion. Contents

8.1 Introduction 8.2 Summary 8.3 Conclusion. Contents Summary and Conclusion Contents Chapter 8 SUMMARY AND CONCLUSION 8.1 Introduction 8.2 Summary 8.3 Conclusion 8.1 Introduction In landfills without liners between the waste and the underlying geology or

More information

DRAINAGE REVIEW: Berwick Health and Education Precinct. for. Victorian Planning Authority

DRAINAGE REVIEW: Berwick Health and Education Precinct. for. Victorian Planning Authority DRAINAGE REVIEW: Berwick Health and Education Precinct for Victorian Planning Authority April 2017 Document history Revision: Revision no. 03 Author/s Jonathon McLean Approved Jonathon McLean Distribution:

More information

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL New Chevrolet and Cadillac Dealership Jasper, AL Andrew Kennedy Homework #6 July 24, 2007 0 Table of Contents Table of

More information

LIFE Project Number LIFE03 ENV/GR/ Layman s Report

LIFE Project Number LIFE03 ENV/GR/ Layman s Report LIFE Project Number LIFE03 ENV/GR/000213 LIFE PROJECT NAME Rehabilitation of abandoned bauxite surface mines using alumina red mud as filler (REFILL) Reporting Date 30-11-2006 The large open pit areas

More information

Upland Landfill Waste Discharge Application 7295 Gold River Highway Campbell River, British Columbia

Upland Landfill Waste Discharge Application 7295 Gold River Highway Campbell River, British Columbia Upland Landfill Waste Discharge Application 7295 Gold River Highway Campbell River, British Columbia Upland Excavating Ltd. Engineering Consultant: GHD Limited Presentation Agenda Project Background Site

More information

Performance Evaluation of Rainwater Harvesting Systems Toronto, Ontario

Performance Evaluation of Rainwater Harvesting Systems Toronto, Ontario Performance Evaluation of Rainwater Harvesting Systems Toronto, Ontario Prepared by: Toronto and Region Conservation 2010 Toronto, Ontario A final report prepared by: Toronto and Region Conservation Authority

More information

SECTION 6 STORMWATER AND LAND DRAINAGE

SECTION 6 STORMWATER AND LAND DRAINAGE SECTION 6 STORMWATER AND LAND DRAINAGE Final Version, Approved September 2003 Section 6 and Land Drainage Contents 6.1 PERFORMANCE STANDARDS... 2 6.1.1 General... 2 6.2 MEANS OF COMPLIANCE... 3 6.2.1 General...

More information

Infiltration Trench Factsheet

Infiltration Trench Factsheet Infiltration Trench Factsheet Infiltration Trench is a practice that provides temporary storage of runoff using the void spaces within the soil/sand/gravel mixture that is used to backfill the trench for

More information

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1

To: From: Date: Subject: Sherwood Lakes Drainage Alternatives Analysis 1 To: From: The City of Virginia Beach Lewis White and Rachael Johnson on behalf of WSP Date: June 6, 2017 Subject: s Drainage Alternatives Analysis This memorandum represents the summary of findings from

More information

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar Hydrology and Water Management Dr. Mujahid Khan, UET Peshawar Course Outline Hydrologic Cycle and its Processes Water Balance Approach Estimation and Analysis of Precipitation Data Infiltration and Runoff

More information

Appendix A9.1: Private Water Supply Supplementary Environmental Information

Appendix A9.1: Private Water Supply Supplementary Environmental Information Appendix A9.1: Private Water Supply Supplementary Environmental Information 1.1 Introduction SEPA objected to the planning application for the Project in their consultation response dated 19 October 2013

More information

Lowen Hydrogeology Consulting Ltd.

Lowen Hydrogeology Consulting Ltd. Consulting Ltd. September 23, 2012 LHC Project File: 1218 Shawnigan Residents Association PO Box 443 Shawnigan Lake, BC V0R 2W0 Attention : Gary Horwood, President Dear Sir: Re: Proposed SIA Contaminated

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Hough, M., Stewart, W.I., Uderstadt, K.F. & Wood, A.

Hough, M., Stewart, W.I., Uderstadt, K.F. & Wood, A. DESIGN, CONSTRUCTION, OPERATION AND EFFECTIVENESS OF A PILOT ARTIFICIAL WETLAND SYSTEM TO REMOVE STORMWATER AND SEWAGE POLLUTANTS ENTERING THE SWARTKOPS RIVER ESTUARY VIA THE MOTHERWELL CANAL, NELSON MANDELA

More information

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI

Report. Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan. DTE Energy Company One Energy Plaza, Detroit, MI Report Inflow Design Flood Control System Plan St. Clair Power Plant St. Clair, Michigan DTE Energy Company One Energy Plaza, Detroit, MI October 14, 2016 NTH Project No. 62-160047-04 NTH Consultants,

More information