Replacing an Existing Elevated Storage Tank on the Same Site

Size: px
Start display at page:

Download "Replacing an Existing Elevated Storage Tank on the Same Site"

Transcription

1 Replacing an Existing Elevated Storage Tank on the Same Site 2015 North Carolina Spring Conference NC AWWA-WEA April 13, 2015 Eric Williams, PE

2 Existing Facilities Maintenance Issues Tank Alternatives Challenges

3 Bid Challenges Tank Construction Tank Demolition Construction Costs

4 Project Location

5 Project Location

6 01 Existing Facilities

7 Existing Facilities 2 Inch -12 Inch Water Lines Materials Including PVC, Ductile Iron and Asbestos Cement 3 Master Meters 2 Elevated Storage Tanks

8 West End Elevated Storage Tank Constructed in 1998 Capacity 250,000 Gallons Style Single Pedestal Contractor Brown Steel Contractors

9 East End Elevated Storage Tank Constructed in 1973 Capacity 200,000 Gallons Style Leg Overflow Elevation Approximately 2.2 Feet Lower than West End Tank Contractor Brown Steel Contractors

10 02 Maintenance Issues

11 East End Storage Tank Maintenance Issues Tank in Need of Painting Repainting would Require Complete Shrouding Drip Line of Tank Extended Over 2 Adjacent Properties

12 03 Tank Alternatives

13 East End Storage Tank Alternatives Repaint and Repair Existing Tank o Costs were Estimated at $500,000-$600,000 (Lead Based Paint) o Tank Would Still Be 40+ Years Old Build a New Tank o Can Increase Capacity o Can Match West End Overflow Elevation o Can Match Tank Style o Future Maintenance Less Costly

14 04 Challenges

15 Challenges New Tank Construction Close Proximity of Homes Pile Installation Painting Telecommunications Facilities Demolition of Existing Tank Resort/Vacation Destination Construction Schedule Restrictions

16 Challenges - Tank Site

17 05 Bid Challenges

18 Bid Challenges Planned to Bid Tank Construction and Tank Demolition Separately Only One Bid Received on Bid Day Only One Bid Received on the Rescheduled Bid Day Bid not Submitted by a Tank Contractor A. C. Schultes Bid Received Exceeded Budget Able to Negotiate a Lower Price Negotiations Included Adding Tank Demolition

19 06 Tank Construction

20 Tank Construction Water Line Installation 12-Inch Water Line Design was to Cut In New Tee Existing Isolation Valve Would not Hold

21 Tank Construction Foundation Installation Driven 12-Inch Steel H Piles Minimum Depth Required - 40 Feet Monitored Vibration at Adjacent Homes Noise Restrictions (8:00 am 8:00 pm) Pile Cap 4 Feet Thick by 2.5 Feet Wide 24 2 Anchor Bolts by 3 Feet 4 Inches Long (To Extend 7 Inches Above Concrete)

22 Tank Construction Structure by Caldwell Tanks Challenges o Close Proximity of Homes o Total Site Less than ½ Acre o Storage Space for Steel Components o Existing Tank o Telecommunications Structures

23 Tank Construction Structure Single Pedestal Complaints/Damage to Private Property

24 Tank Construction Painting Shrouding Required Tightly Woven Nylon Windy Conditions 15 mph Maximum Summer Season Restrictions

25 Tank Construction Shrouding Outriggers Extensive Cabling Equipment at Base of Tank for Raising and Lowering Shroud

26 Tank Construction Paint by Tnemec Interior (Dry) 2 Coat System o Shop Prime 5.0 mils Series N-140 Epoxy o Stripe Coat 5.0 mils Series N-140 Epoxy For all Seams and Abraded Areas o Finish Coat 5.0 mils Series N-140 Epoxy Stripe Coat then Full Coat Interior (Wet) 3 Coat System o Shop Prime 3.0 mils Series 94 Hydro-Zinc o Stripe Coat 3.0 mils Series 94 Hydro-Zinc For all Seams and Abraded Areas o Finish Coat 5.0 mils Series N-140 Epoxy Stripe Coat to all Weld Seams, Edges, Corners, Bolts and Nuts Tank White 5.0 mils Series N140 Epoxy Beige Color 5.0 mils Series N140 Epoxy Tank White

27 Tank Construction Paint by Tnemec Exterior 4 Coat System o Shop Prime 3.0 mils Series 94 Zinc Rich Polyurethane o Stripe Coat 3.0 mils Series 94 For all Seams and Abraded Areas o Finish Coat 3 Separate Coats 3.0 mils Series N69 Hi-Build Epoxy 2.0 mils Series 73 Endura Shield (Polyurethane Enamel) 2.5 mils Series 700 Hydroflon

28 Tank Construction Tank Components Standby Generator for SCADA Electrical and SCADA Equipment Discharge Headwall Structure Altitude Valve

29 Tank Construction Telecommunication Vendors ATMC/AT&T Verizon Town Communication Antenna SCADA Antenna Verizon ATMC/AT&T

30 Tank Construction Telecommunications Cabling in Tank Cabling Continues Through Access Tube

31 07 Tank Demolition

32 Tank Demolition Protect Telecommunications Structures Protect Brand New Tank Loading of Steel Components

33 Tank Demolition No Complaints or Damage During Demolition Three Days from Start to Finish

34 Tank Demolition Valve Vault Other Structures

35 08 Construction Costs

36 Construction Costs Original Budget - $1,400,000 As Bid Without Demolition - $1,574,618 After Negotiations with Demolition - $1,498,600 Final Cost after Change Orders - $1,475, Approximately $35,000 Paid by Telecommunications Vendors

37 QUESTIONS Eric Williams, PE 910/

SECTION 2 DIVISION 05 METALS

SECTION 2 DIVISION 05 METALS SECTION 2 DIVISION 05 METALS DIVISION 5 - METALS Note: This is a guide for Designers only. Contents shall not be used in lieu of specifications as part of the Designer s Contract Documents. GENERAL DESIGN:

More information

KENT COUNTY WATER AUTHORITY. ERRATUM to Rules and Regulations of the Kent County Water Authority

KENT COUNTY WATER AUTHORITY. ERRATUM to Rules and Regulations of the Kent County Water Authority KENT COUNTY WATER AUTHORITY ERRATUM to Rules and Regulations of the Kent County Water Authority Section 4.9.1.1 Resilient Seat Gate 4 inch to 12 inch: Replace with the attached. Section 4.9.1.3 Tapping

More information

Extend the Service Life of Water Storage Tanks using the revised ANSI/AWWA D102 Standard

Extend the Service Life of Water Storage Tanks using the revised ANSI/AWWA D102 Standard Extend the Service Life of Water Storage Tanks using the revised ANSI/AWWA D102 Standard BTW AWWA D102 Revision Task Group: Revises and Updates Existing Edition. Discusses changes to improve the Standard.

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

Section FLUSHING HYDRANTS

Section FLUSHING HYDRANTS STANDARD SPECIFICATION Section 02520 PART 1 GENERAL 1.01 SUMMARY This Section includes: A. Flushing hydrants. B. Adjustment of flushing hydrants and gate valves. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices.

More information

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light

More information

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces. SECTION 05500- METAL FABRICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

FOR STEEL POTABLE WATER TANKS INTERIOR AND EXTERIOR CORROSION PROTECTION. Hydro-Zinc

FOR STEEL POTABLE WATER TANKS INTERIOR AND EXTERIOR CORROSION PROTECTION. Hydro-Zinc FOR STEEL POTABLE WATER TANKS INTERIOR AND EXTERIOR CORROSION PROTECTION Hydro-Zinc KEY BENEFITS TENACIOUS ADHESION EASY APPLICATION FAST CURE GALVANIC PROTECTION NSF/ANSI STD. 61 CERTIFIED LOW TEMPERATURE

More information

A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA

A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION ALBERTVILLE, ALABAMA McKee and Associates Architecture and Interior Design Addendum No. FOUR Date: 09.24.18 Project: A NEW PRE-K BUILDING FOR BIG SPRING LAKE KINDERGARTEN SCHOOL FOR THE ALBERTVILLE CITY BOARD OF EDUCATION

More information

ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO. PS 061 SEVEN SPRINGS WASTEWATER TREATMENT FACILITY IMPROVEMENTS PASCO COUNTY,

More information

SERIES STB30 STEEL FIXED THERMAL BREAK DETENTION WINDOWS SECTION 08651

SERIES STB30 STEEL FIXED THERMAL BREAK DETENTION WINDOWS SECTION 08651 SERIES STB30 STEEL FIXED THERMAL BREAK DETENTION WINDOWS SECTION 08651 PART 1 GENERAL 1.1 DESCRIPTION A. Work Included: 1. Furnish all labor and materials to complete the fabrication of detention windows

More information

East Central College

East Central College SECTION 230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 WORK INCLUDES A. Base Bid and Alternate Bids: 1. Contractor provide the following hangers and supports for HVAC system

More information

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT SECTION 230548 - VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

3. Roof Expansion Joints between New Building and Existing Building.

3. Roof Expansion Joints between New Building and Existing Building. SECTION 077200 - ROOF ACCESSORIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Amendments to General Conditions and Division 01 Specification

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY GROUND STORAGE. Section GROUND STORAGE TANK (GST) MODIFICATIONS, CLEANING AND DISINFECTION

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY GROUND STORAGE. Section GROUND STORAGE TANK (GST) MODIFICATIONS, CLEANING AND DISINFECTION Section 13207 GROUND STORAGE PART 1 GENERAL 1.01 SUMMARY This Section includes the furnishing and installation of surface water inlet piping, appurtenances, cleaning and disinfection of existing ground

More information

SECTION GROUND STORAGE TANK

SECTION GROUND STORAGE TANK SECTION 13210 GROUND STORAGE TANK PART 1 GENERAL 1.01 Summary A. Section Includes: Provision for welded steel storage tank design, fabrication, construction and erection, including tank accessories. B.

More information

SECTION WELDED STEEL WATER STORAGE TANKS

SECTION WELDED STEEL WATER STORAGE TANKS SECTION 33 16 20 WELDED STEEL WATER STORAGE TANKS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Elevated tanks. 2. Appurtenances and accessories. B. Related Sections: 1. Section 03 31 20 - Concrete

More information

SECTION MISCELLANEOUS METALS THIS SECTION TO BE INCLUDED IN SUB BID FOR SECTION MISCELLANEOUS AND ORNAMENTAL IRON

SECTION MISCELLANEOUS METALS THIS SECTION TO BE INCLUDED IN SUB BID FOR SECTION MISCELLANEOUS AND ORNAMENTAL IRON SECTION 055000 THIS SECTION TO BE INCLUDED IN SUB BID FOR SECTION 050001 MISCELLANEOUS AND ORNAMENTAL IRON PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a

More information

Extend the Service Life of Water Storage Tanks using the revised ANSI/AWWA D102 Standard

Extend the Service Life of Water Storage Tanks using the revised ANSI/AWWA D102 Standard PAINT A TANK IN A DAY! Presented by Tony Ippoliti, Water Storage Business Development Manager The Sherwin-Williams Company, Protective & Marine Division, 6535 E. 82 nd Street, Suite 206, Indianapolis,

More information

SECTION MISCELLANEOUS METALS

SECTION MISCELLANEOUS METALS PART 1 GENERAL 1.1 WORK OF THIS SECTION A. Contractor shall provide all labor, materials, equipment and incidentals as shown, specified and required to furnish and install all miscellaneous metal fabrications

More information

B. Shop Drawings: Include plans, elevations, sections, details, and attachments.

B. Shop Drawings: Include plans, elevations, sections, details, and attachments. SECTION 055119 - METAL GRATING STAIRS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

4. Section 01170, Special Construction Permits, Page : Part 1; ADD the following paragraph 1.5 after paragraph 1.4:

4. Section 01170, Special Construction Permits, Page : Part 1; ADD the following paragraph 1.5 after paragraph 1.4: 1700 East Iron Ave. Salina, KS 67401 785-827-0433 phone 785-827-5949 fax Arizona California Colorado Kansas Missouri Nebraska New Mexico Oklahoma Texas Utah 1 December 2017 ADDENDUM NO. 2 RE: City of Conway

More information

CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION

CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION CITY OF PLACERVILLE, CALIFORNIA DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION ADDENDUM #4 DATE: 02/08/2016 PROJECT: CONTRACT No: 40604 BID DATE, TIME: 02/11/2016, 2:00PM NOTICE TO ALL CONTRACTORS

More information

CITY OF GLENDORA COUNTRY CLUB RESERVOIR IMPROVEMENTS PLAN NO REQUEST FOR INFORMATION (RFI) LOG RFI # DATE SHEET # RFI RESPONSE DATE

CITY OF GLENDORA COUNTRY CLUB RESERVOIR IMPROVEMENTS PLAN NO REQUEST FOR INFORMATION (RFI) LOG RFI # DATE SHEET # RFI RESPONSE DATE CITY OF GLENDORA COUNTRY CLUB RESERVOIR IMPROVEMENTS PLAN NO. 1124 REQUEST FOR INFORMATION (RFI) LOG RFI # DATE SHEET # RFI RESPONSE DATE 1 4/13/2016 Questions below pertain to note 4 per drawing, which

More information

SERIES SA30 STEEL/ALUMINUM FIXED DETENTION WINDOWS SECTION 08651

SERIES SA30 STEEL/ALUMINUM FIXED DETENTION WINDOWS SECTION 08651 SERIES SA30 STEEL/ALUMINUM FIXED DETENTION WINDOWS SECTION 08651 PART 1 GENERAL 1.1 DESCRIPTION A. Work Included: 1. Furnish all labor and materials to complete the fabrication of detention windows as

More information

Extending Tank Life Water Storage Tank Construction & Rehab OTCO Columbus

Extending Tank Life Water Storage Tank Construction & Rehab OTCO Columbus Extending Tank Life Water Storage Tank Construction & Rehab 2017 OTCO Columbus AWWA Standards & Manuals D100 Welded Carbon Steel Tanks for Water Storage D101 Inspection of Water Tanks and Related Facilities

More information

ELEVATED WATER TANK REHABILITATION GETTING IT RIGHT WHEN THINGS GO WRONG

ELEVATED WATER TANK REHABILITATION GETTING IT RIGHT WHEN THINGS GO WRONG ELEVATED WATER TANK REHABILITATION GETTING IT RIGHT WHEN THINGS GO WRONG ABSTRACT Jeremy Allen PE, Project Engineer, Highfill Infrastructure Engineering, PC Tim Greene, Coating Service Manager, S&ME, Inc.

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

SECTION GROUND WATER STORAGE TANKS

SECTION GROUND WATER STORAGE TANKS SECTION 33 16 13 GROUND WATER STORAGE TANKS PART 1: GENERAL 1.01 SCOPE A. Section includes requirements for designing, fabricating, and erecting a welded steel ground storage tank. 1.02 SYSTEM DESCRIPTION

More information

Section Page 2 Specification No. PG F

Section Page 2 Specification No. PG F The contractor shall also be required to spot prime and apply a full intermediate and top coat to the outside surfaces and all related steel appurtenances of the tank as directed by this specification.

More information

METALS Commissioning of Metals Structural Steel Framing Steel Studs... 2

METALS Commissioning of Metals Structural Steel Framing Steel Studs... 2 ~ 05-1 ~ 05 00 00 Metals 05 00 00 METALS... 2 05 08 00 Commissioning of Metals... 2 05 12 00 Structural Steel Framing... 2 05 12 30 Steel Studs... 2 05 45 00 METAL SUPPORT ASSEMBLIES... 2 05 50 00 METAL

More information

Standard Specifications Water Storage Tank Painting

Standard Specifications Water Storage Tank Painting SECTION 09 97 00 WATER STORAGE TANK PAINTING PART 1: GENERAL 1.01 SCOPE A. Section includes surface preparation, priming, and field coating for interior wet, interior dry, and exterior surfaces of steel

More information

SECTION 8 SEPARATION OF LINES

SECTION 8 SEPARATION OF LINES SECTION 8 SEPARATION OF LINES 8.01 INDEX 8.01 INDEX 8.02 PURPOSE 8.03 DEFINITIONS 8.04 SEWER SEPARATION 8.05 NON-POTABLE SEPARATION 8.06 REFERENCES 8.02 PURPOSE This section states the requirements and

More information

Corrosion Control for Water/Wastewater Industry

Corrosion Control for Water/Wastewater Industry Corrosion Control for Water/Wastewater Industry Presenter: Mongkol Mahavongtrakul, P.E. Corrosion Engineer San Francisco Public Utilities Commission LOCATION: Brown & Caldwell, Walnut Creek June 14, 2016

More information

STRUCTURAL STEEL FRAMING

STRUCTURAL STEEL FRAMING SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical

More information

SIERRA MODEL 12 X 24 SPECIFICATIONS

SIERRA MODEL 12 X 24 SPECIFICATIONS SIERRA MODEL 12 X 24 SPECIFICATIONS Dimensions: Roof Dimensions 12-0 x 24-0 Column Dimensions (center to center) 9-0 x 21-0 Minimum Clearance 8-0 Shed Roof 1:12 pitch Square Feet Under Roof 288 Columns

More information

1. Seismic Loads: Reference structural drawings.

1. Seismic Loads: Reference structural drawings. SECTION 102213 ~WIRE MESH PARTITIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general prov1s1ons of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

University of Central Florida Main Campus. Domestic Water. Service and Meter Installations Requirements. Issued January 26 th, 2017.

University of Central Florida Main Campus. Domestic Water. Service and Meter Installations Requirements. Issued January 26 th, 2017. University of Central Florida Main Campus Domestic Water Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS...

More information

STEEL WATER STORAGE TANKS/SINGLE PEDESTAL

STEEL WATER STORAGE TANKS/SINGLE PEDESTAL PART 1 - GENERAL 1.1 SUMMARY 33 16 19.13 A. Provide steel water storage tank(s) as shown on the Drawings, as specified herein, and as needed for a complete and proper installation. B. Related work: 1.

More information

SECTION FENCING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION FENCING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 323100 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

ADDENDUM TO THE CONTRACT. for the. East Valley Reservoir Exterior and Lemon Creek Reservoir Interior Repainting. Contract No.

ADDENDUM TO THE CONTRACT. for the. East Valley Reservoir Exterior and Lemon Creek Reservoir Interior Repainting. Contract No. ADDENDUM TO THE CONTRACT for the ENGINEERING DEPARTMENT East Valley Reservoir Exterior and Lemon Creek Reservoir Interior Repainting Contract No. E12-210 ADDENDUM NO.: ONE CURRENT DEADLINE FOR BIDS: May

More information

SECTION 1043 FENCE MATERIAL

SECTION 1043 FENCE MATERIAL SECTION 1043 FENCE MATERIAL 1043.1 Scope. This specification covers the material required in the construction of chainlink fence and woven wire fence. 1043.2 Basis of Acceptance. The basis of acceptance

More information

B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.

B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work. SECTION 055116 - METAL FLOOR PLATE STAIRS PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

East Central College HANSEN HALL LEVEL 300/400 RENOVATIONS CONSTRUCTION PACKAGE

East Central College HANSEN HALL LEVEL 300/400 RENOVATIONS CONSTRUCTION PACKAGE SECTION 220529 - HANGERS AND SUPPORTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01

More information

Water & Industrial Products Catalog

Water & Industrial Products Catalog Water & Industrial Products Catalog www.smith-blair.com info@smith-blair.com Phone: 800..9705 or 870.77.527 After Hours Number: 90.277.998 Fax: 800.8.792 or 870.77.52 EMERGENCY PHONE 90.277.998 In the

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

SECTION DECORATIVE METAL FENCES AND GATES

SECTION DECORATIVE METAL FENCES AND GATES SECTION 32 31 19 SPEC WRITER NOTE: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

Port of Lake Charles RE: 3501 Bayou D Inde Road 200,000 Gallon EWT

Port of Lake Charles RE: 3501 Bayou D Inde Road 200,000 Gallon EWT P.O. Box 3753 Lake Charles, LA 70602 July 21, 2016 Mr. Nick Pestello Assistant Director of Engineering (337) 794-3687 Job No. 316288 If you would like to speak with Patrick Heltsley concerning this report,

More information

Tnemec 394 Proprietary Long Form Coatings Schedule

Tnemec 394 Proprietary Long Form Coatings Schedule 1.1 PRIMER Tnemec 394 Proprietary Long Form Coatings Schedule A. Primer: Tnemec Series 394 PerimePrime Aromatic Polyurethane Mio/Zinc filled Primer applied @ 2.5-3.5 mils DFT and conforming to the following

More information

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION SECTION 21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 - GENERAL 1.1 SUMMARY A. This section supplements all sections in this division, including pipe, fittings, valves, and connections for sprinkler

More information

More than Just Paint TEXAS PUBLIC WORKS ASSOCIATION AUSTIN, TEXAS

More than Just Paint TEXAS PUBLIC WORKS ASSOCIATION AUSTIN, TEXAS More than Just Paint TEXAS PUBLIC WORKS ASSOCIATION AUSTIN, TEXAS Charles Kucherka, P.E. June 25, 2015 Tank Rehabilitation Pre Design 30% Submittal 90% Submittal Bid and Construction Phases Pre Design

More information

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit.

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit. SECTION 08510 STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit. PART 1 GENERAL 1.1 SECTION INCLUDES A. Fire Rated Steel Windows

More information

SECTION STRUCTURAL METAL FRAMING

SECTION STRUCTURAL METAL FRAMING SECTION 05100 STRUCTURAL METAL FRAMING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Structural steel framing including lintels, shelf angles, bearing plates, anchor bolts and other items as shown on

More information

Service Saddles/ Brass Alloy/ Stainless Steel Straps for Cast, Ductile & PVC Pipe

Service Saddles/ Brass Alloy/ Stainless Steel Straps for Cast, Ductile & PVC Pipe F 1 F 1.1 F 1.2 F 2 F 2.1 F 3 Service Saddles/ Hinged Type for 2 PVC Service Saddles/ Brass Alloy/ Stainless Steel Straps for Cast, Ductile & PVC Pipe Service Saddles/ Ductile Iron/ Stainless Steel Straps

More information

05510: TAPERED STEEL TROLLEY POLES AND ACCESSORIES

05510: TAPERED STEEL TROLLEY POLES AND ACCESSORIES PART 1 GENERAL 1.01 DESCRIPTION A. The Vendor shall fabricate, furnish, test and deliver tapered steel trolley poles, including base plates, reinforced hand holes, anchor bolts, nuts and washers, and accessories

More information

University of Colorado Colorado Springs. National Cybersecurity Center Roof Replacement Package CSNA Project Number

University of Colorado Colorado Springs. National Cybersecurity Center Roof Replacement Package CSNA Project Number ADDENDUM NUMBER 0 TO PROJECT MANUAL AND DRAWINGS August 9, 6 OWNER: ARCHITECT: University of Colorado Colorado Springs CSNA Architects PROJECT: National Cybersecurity Center Roof Replacement Package CSNA

More information

CURRENT NORTH LAS VEGAS ADDENDA

CURRENT NORTH LAS VEGAS ADDENDA SECTION 1 Section 1.01.73 Fire Service Meter ADD: Type I is not approved for installation in the City of North Las Vegas service area. Section 1.01.107 Pressure Reducing Valve (PRV) or Pressure Regulator

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 44 A solvent based coating system High Performance 7400 System 450 VOC DTM Alkyd Enamel

More information

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit.

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit. SECTION 08510 STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit. PART 1 GENERAL 1.1 SECTION INCLUDES A. Fire Rated Steel Windows

More information

MODELS: SM & SMSS

MODELS: SM & SMSS Most Dependable Fountains, Inc. OPERATIONS MANUAL MODELS: 410-18 SM & 410-18 SMSS Most Dependable Fountains, Inc 5705 Commander Drive Arlington, TN 38002 800-552-6331 FOUNTAINS, MOST DEPENDABLE FOUNTAINS,

More information

P.E. 4-1,000,000 12, 2014 (270) C

P.E. 4-1,000,000 12, 2014 (270) C 111 Fifth Street Henderson, KY 42420 March 12, 2014 Mr. Tom Williams, P.E. General Manager (270) 869-6621 Job No. 314031- C If you would like to speak with Patrick Heltsley concerning this report, call

More information

1. Hangers and supports for electrical equipment and systems. 2. Construction requirements for concrete bases.

1. Hangers and supports for electrical equipment and systems. 2. Construction requirements for concrete bases. SECTION 260529 - HANGERS AND SUPPORTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Hangers and supports for electrical equipment and systems. 2. Construction requirements for concrete bases. 1.2

More information

ITEM 442 METALS FOR STRUCTURES

ITEM 442 METALS FOR STRUCTURES AFTER NOVEMBER 1, 2008 ITEM 442 METALS FOR STRUCTURES 442.1 Description. These specifications shall govern for materials such as structural steel, wrought iron, bronze, and other metals used in structures,

More information

Diffused Aeration Piping Equipment

Diffused Aeration Piping Equipment 1.0 General 1.1. The specifications in this section include all components of the Diffused Aeration System with the exception of the individual diffuser units. Refer to additional specification sections

More information

1. Division 23 Section "Hangers and Supports for HVAC Piping and Equipment" for pipe insulation shields and protection saddles.

1. Division 23 Section Hangers and Supports for HVAC Piping and Equipment for pipe insulation shields and protection saddles. SECTION 23 07 19 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES PART 1 GENERAL 1.01 SUMMARY This Section includes: Section 02081 CAST-IN-PLACE A. Cast-in-place concrete manholes for sanitary sewers and storm sewers, including box sewers. B. Pile-supported concrete

More information

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION SECTION 22 11 16.13 CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION PART 1: GENERAL 1.01 SUMMARY A. This Section includes water-distribution backflow prevention products and installation specifications.

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 052100 - STEEL JOISTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections

More information

Invitation to Bid # CC Project Title: High Zone 5.0 Million Gallon Reinforced Concrete Culinary Water Tank Project No.

Invitation to Bid # CC Project Title: High Zone 5.0 Million Gallon Reinforced Concrete Culinary Water Tank Project No. Riverton City Purchasing Department 12830 South 1700 West Riverton, UT 84065 801-208-3175 Fax: 801-254-1810 May 5, 2017 ADDENDUM #3 Invitation to Bid # CC17-332 Project Title: High Zone 5.0 Million Gallon

More information

DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS

DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS Dimensions: Roof Dimensions 10-0 x 24 Column Dimensions (center to center) 6-7 x 22-9 Minimum Clearance 7-6 Minimum Clearance @ Front ±9-2 Roof Pitch 2:12 pitch

More information

NC State University Design and Construction Guidelines Division 33 Utilities

NC State University Design and Construction Guidelines Division 33 Utilities 1.0 Purpose A. These guidelines provide methods and requirements to ensure that the connections, attachments, extensions, or other site utility modifications meet NC State standards. B. NC State is responsible

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT SECTION 220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS

CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS January 2014 SPECIFICATION CW 3550 R3 CW 3550 Chain Link and Drift Control Fence TABLE OF CONTENTS 1. GENERAL CONDITIONS... 1 3. DESCRIPTION... 1 5. MATERIALS... 1 5.1 Drift Control Fence... 1 5.1.1 Approved

More information

. SECTION HANGERS AND SUPPORTS

. SECTION HANGERS AND SUPPORTS . SECTION 230529 - HANGERS AND SUPPORTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division I Specification

More information

1. Hangers and supports for electrical equipment and systems.

1. Hangers and supports for electrical equipment and systems. PART 1 - GENERAL... 1 1.1 RELATED DOCUMENTS... 1 1.2 SUMMARY... 1 1.3 DEFINITIONS... 1 1.4 PERFORMANCE REQUIREMENTS... 1 1.5 SUBMITTALS... 2 1.6 QUALITY ASSURANCE... 2 1.7 COORDINATION... 2 PART 2 - PRODUCTS...

More information

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT Page 230548-1 SECTION 230548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

Invitation For Sealed Bids

Invitation For Sealed Bids Invitation For Sealed Bids ISSUE DATE: February 11, 2016 CONTACT: Caryl Ann Giles PHONE NUMBER: (931) 489-5791 EMAIL: cgiles@springhilltn.org SUBMIT PROPOSAL/OFFER PRIOR TO: CLOSING DATE: Wednesday March

More information

FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW

FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW FORT MONMOUTH PLANNING, ENGINEERING, ARCHITECTURAL & ENVIRONMENTAL CONSULTING SERVICES OVERVIEW D A N S C H N E P F, P R I N C I P A L F R A N K T Y B O R O S K I, D I R E C T O R, F E D E R A L P R A

More information

SECTION AWNINGS

SECTION AWNINGS SECTION 10 73 13 AWNINGS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Fixed metal awnings. 1.2 DEFINITIONS A. Awning: An architectural projection that provides weather protection,

More information

Coming and Going An Overview of Infrastructure Common to Water Distribution and Wastewater Collection Systems

Coming and Going An Overview of Infrastructure Common to Water Distribution and Wastewater Collection Systems Coming and Going An Overview of Infrastructure Common to Water Distribution and Wastewater Collection Systems Eric A. Smith, P.E. November 14, 2016 Raleigh, NC Agenda Introduction Importance of Distribution/Collection

More information

SECTION HOLLOW METALWORK. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION HOLLOW METALWORK. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 081113 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION STEEL DOORS AND FRAMES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION STEEL DOORS AND FRAMES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 08110 - STEEL DOORS AND FRAMES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General, Supplementary, and Special Conditions and Division 1 Specification

More information

Engineering Design Center. Standard Drawings. 1st Edition -January 2016

Engineering Design Center. Standard Drawings. 1st Edition -January 2016 Engineering Design Center Standard Drawings 1st Edition -January 2016 Golden State Water Company Standard Drawings 1/11/2016 Table of Contents PART A STANDARD DRAWINGS Section I Pipeline Construction P-1

More information

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab.

Item 2.3 Unit pricing GC to provide a square foot unit cost for material and labor to replace plywood decking beneath new concrete walkway slab. Willow Glen Housing Repairs Project #9-59 Addendum Item. Change to bid date The bid date will be extended to March 8, 09, :00pm at the Housing Authority of Columbus Central Office,000 Wynnton Road Columbus,

More information

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART 1 - GENERAL 1.01 SECTION INCLUDES A. Concrete Steps B. Handrails C. Safety Rail 1.02 DESCRIPTION OF WORK A. Construction of concrete steps. B. Furnishing

More information

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK or our breadth of capability. Of all the storage tank manufacturers doing business today, no other offers Caldwell s range of capability. We are the only manufacturer

More information

DECORATIVE METAL RAILINGS

DECORATIVE METAL RAILINGS SECTION 057300 - DECORATIVE METAL RAILINGS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Steel and iron decorative railings. 1.2 PERFORMANCE REQUIREMENTS A. Delegated Design: Design railings, including

More information

7. New railings for existing buildings shall be designed to match any existing railings unless there is a compelling reason for change.

7. New railings for existing buildings shall be designed to match any existing railings unless there is a compelling reason for change. Division 05. Metals 05 50 00. Metal Fabrications 05 50 00. Roof - Fall Protection The contractor shall provide a horizontal cable lifeline system on steel posts complying with applicable regulatory requirements.

More information

METAL HANDRAILS AND RAILINGS. A. Properly identified manufacturer's literature, including shop and erection drawings before starting work.

METAL HANDRAILS AND RAILINGS. A. Properly identified manufacturer's literature, including shop and erection drawings before starting work. SECTION 05520 METAL HANDRAILS AND RAILINGS PART 1 GENERAL 1.01 SUBMITTALS A. Properly identified manufacturer's literature, including shop and erection drawings before starting work. B. Railing Assemblies

More information

SECTION STRUCTURAL STEEL

SECTION STRUCTURAL STEEL PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor, equipment and incidentals required to provide structural steel shown on the Contract Drawings and as

More information

High Priority: Force Main Condition Evaluation in Chapel Hill

High Priority: Force Main Condition Evaluation in Chapel Hill 2014 NC AWWA-WEA Spring Conference High Priority: Force Main Condition Evaluation in Chapel Hill Jim Perotti, PE Brown and Caldwell Vishnu Gangadharan, PE OWASA April 7 2014 Presentation Agenda Project

More information

Special Provision No. 911F04 March 1997

Special Provision No. 911F04 March 1997 COATING STEEL RAILING SYSTEM(S) - Item No. Special Provision No. 911F04 March 1997 Definitions, Elimination of Pre-Start Material Sample, Material Requirements, Operational Constraints, Time Between Surface

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB #

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

CONTENTS. B. System Design and Performance Requirements

CONTENTS. B. System Design and Performance Requirements 16060 Grounding and Bonding This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or

More information