THE PLAZA AT PPL CENTER ALLENTOWN, PA
|
|
- Madeleine Allen
- 6 years ago
- Views:
Transcription
1 Building Function and Primary Use The owner of the new Plaza at PPL Center is Liberty Property Trust, but the primary tenant is PPL, which will use the building as the headquarters for its new subsidiaries EnergyPlus, an energy marketing and trading organization and PPL Generation. The Plaza at PPL Center is a 256,000 square feet multi-use building, with the ground level designated as retail space. PPL will lease around 200,000 square feet, including the second through the six floors for office areas, which will be rented by the unregulated subsidiaries of PPL Corporation, PPL Energy Plus and PPL Generation. The primarily function of Energy Plus is to buy and sell gas, oil and electric. The top two floors are reserved for traders and equipped with screens to allow them to monitor energy prices. Location and Site Site The site for the Plaza at PPL Center is in the center of downtown Allentown, PA. As picture below, it is located on the northeast corner of 9 th and Hamilton streets adjacent to the PPL tower, which stands on the northwest corner. The site was 6
2 formally Hess s department store and the building was demolished in 2000 after being vacated by the Bon-Ton department store. The Plaza at PPL Center is an important project for the downtown area since, like many cities, businesses continue to close and new development has been rare. PPL Corporation is a primary corporation in downtown Allentown and the current headquarters occupies the tower on the northwest corner of Ninth and Hamilton streets. Soil Properties The Corporate Plaza was built in 1986 and was the last commercial building to be built in downtown Allentown prior to the Plaza at PPL Center. However, the Corporate Plaza was demolished in 1994 after a sinkhole opened underneath the building causing irreversible damage. The geotechnical report indicated that there were not active sinkholes at the Plaza at the PPL Center site but the soil is of poor quality only capable of supporting 3000 psf without sitework and that is with possible long-term instability. Most of the soil on the site is fill from remains of previous structures. 7
3 Architecture Architect s Vision One of the design considerations for the eight-story building, designed by Robert A. M. Stern Architects of New York, was the fact that downtown Allentown is densely developed with little open space. To help with this, the architect included a plaza in his design, which sets the building back 85 from Hamilton Street. This is uncharacteristic of most of the buildings along this main street. The architect wanted to try to bring nature into the building and he provided an atrium that allows light into all the floors from above. A winter garden on the third floor can be viewed from the floors above with the exception of the two upper trading floors and a roof-top garden provides additional green space for the Plaza at PPL Center. Building Envelope The exterior of the building consists of pre-cast concrete panels with 7-6 ribbons of windows on an aluminum-clad frame. The roof of the Plaza at PPL Center consists of two stories. The lower roof is constructed like a typical floor with composite steel beams spanned with a lightweight concrete slab on composite metal deck. The larger portion is curved. This profile is obtained with curved steel beams spanned by metal deck. 8
4 Overall Structural System Composite Construction Steel framing was chosen for the Plaza at PPL Center because of its favorable performance in long span conditions and light weight. The Plaza at PPL Center has clear spans up to 42 feet. Without pre-stressing, concrete beams cannot reasonably span this distance. The soil bearing capacity after compaction grouting was only 5000psf. A concrete system would have increased the overall dead load of the system and the column reactions. Steel has the advantage again in that its light weight adds less load and therefore allows for smaller footing sizes. W-shape beams and columns are the primary framing members. The steel beams act as composite members with the concrete slab on metal deck. Columns line the perimeter of the building to support the glass curtain wall exterior. Lateral System Four moment frames resist lateral loads in the east-west direction and two braced frames resist lateral loads in the north-south direction. During schematic design, it was decided that moment frames were therefore needed in the long direction to minimize obstructions in the façade or plan. The eccentric braced frames were appropriate for the short direction because there was space along the core where the diagonals will not block openings and the links allow openings for doorways. 9
5 Plan View Elevations Moment Frame A Moment Frame B/C Moment Frame D Braced Frames 3/8 10
6 Foundation System The Plaza at PPL Center has a partial 16-6 high basement level. Columns of the superstructure sit on the cast-in-place basement walls, which are supported by continuous spread footings. Interior columns which are part of the moment frames in the E-W direction, also sit on a continuous spread footing. The continuous spread footing has advantages over single square column footings. It is easier to excavate and pour because it remains at a constant level and the added mass helps to resist the uplift from the moment frames when lateral loads are applied. The site for the Plaza at PPL Center has poor soil bearing capacity. With compaction grouting, the soil capacity was increased to 5,000psf, but differential settlement is highly probable. The continuous center footing allows for a more consistent settlement across the building. 11
7 Mechanical System Air System The Plaza at PPL Center is supplied by a variable air volume system. The outdoor air intake is located at the first floor and the air is sent to the basement where it combines with the return air to enter the air-handling unit. This custom air-handling unit is actually built into the walls of the basement. A 2000 MBH heat recovery unit is located on the rooftop. Hydronic System The building has two 240 ton, chillers in the basement. A 1500 gallon per minute cooling tower is located in the adjacent North Building, which is another building occupied by PPL Corporation. A 2000 MBH boiler is required for the building. An interesting feature of the mechanical system is that there are three ice tanks in the basement. The storage tanks have a 761 ton-hr latent capacity. The tanks accumulate ice throughout the night and utilize the ice during the peak hours of the day to provide chilled water to the building. 12
8 Construction Information Project Delivery System Method The primary tenant PPL needed space in which to expand its developing subsidiary, Energy Plus. The tenant sought out Liberty Property Trust to develop the former Hess s lot and lease the building to PPL. The owner then proceeded to hire an architect under a time plus fee contract and a construction manager. The construction manager, L.F. Dricsoll was hired after submitting the lowest bid in the guaranteed maximum price (GMP) job. Dates of Construction Construction began in January of 2002 and the steel was topped out ahead of schedule on July 24, The building is expected to be complete by April 30, The top two floors are energy securities trading floors and will be occupied prior to the six floors remaining floors. Therefore, fitout of the seventh and eighth floors as well as the first floor lobby and other public spaces will take place first and completion will proceed to the sixth floor and down from there. Cost Information The new PPL Center projects are estimated to cost $60 million. This figure includes a new parking deck, which falls within a different scope of work. The estimated base building cost is $29 million and the cost of tenant fitouts is $19 million. 13
THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA
THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor 12.16.2002 THESIS PROPOSAL Executive Summary Architecture The Plaza at PPL
More informationTHE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA
THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor 10.21.2002 PRO-CON STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS Executive Summary
More informationStructural Breadth. Landmark Façade
Jessica Lucas Hearst Tower Mechanical Option New York, NY Structural Breadth Landmark Façade As mentioned before, the building has two distinct pieces: the historic landmark façade and the new office tower.
More informationBest Buy Corporate Building D (4) Richfield, MN
Best Buy Corporate Building D (4) Thesis Proposal Professor Boothby December 12 th, 2008 Executive Summary: The Best Buy Corporate Building D is a 6 story building with a total area of 304,610 square feet.
More informationFDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider
Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor
More informationOverall Existing Conditions Summary
September 12, 2002 Overall Executive Summary: The multi-use project on 250 West Street is a 7-story building with space for offices, retail, storage and parking. The project is a small part of the development
More informationBrent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan
Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this
More informationJanuary 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options
River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign
More informationDead Loads (psf): Concrete Floor Slab on Metal Deck 45 psf Mechanical and Ceiling 7 psf Miscellaneous 5 psf Exterior Wall 80 psf
CODES AND REQUIREMENTS The structural design of Northbrook Corporate Center was based on the International Building Code 2003, which incorporates many of the provisions of ASCE 7. The lateral load design
More informationThesis Proposal December 5, 2003
Executive Summary Thesis Proposal December 5, 2003 Brennan Hall is a five-story office/classroom building. It is located on a slightly sloping site, surrounded by other structures and a small green space.
More informationThe building on 250 West Street is a 7-story multi-use that provides space for parking,
December 5, 2002 Thesis Executive Summary The proposal for the investigation of the building on 250 West Street will include an in depth look at the floor and lateral systems. A continuation of the Pro-Con
More informationTraci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary
1 Traci Peterson Option: Structural Faculty Consultant: Memari The Del Monte Center at The North Shore Pittsburgh, PA Thesis Proposal Date of Submission: 12/10/04 Executive Summary Currently under construction
More informationMOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS
MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS PARKERSBURG, WEST VIRGINIA DOMINIC MANNO STRUCTURAL OPTION FACULTY CONSULTANT: DR. ANDRES LEPAGE Technical Report 3 11-21-08 TABLE OF CONTENTS TABLE OF
More informationPro-Con Structural Study of Alternate Floor Systems
Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary
More informationTechnical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction
Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building
More information200 Minuteman Drive. New Design for Additional Floors and Vibration Sensitive Equipment. Brent Ellmann. Structural Option
200 Minuteman Drive New Design for Additional Floors and Vibration Sensitive Equipment Brent Ellmann Structural Option Dr. Linda Hanagan - Consultant Project Players Owner- Brickstone Properties Architects-Burt
More informationStructural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B
Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural
More informationBrent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan
Brief Building Overview: 200 Minuteman Park stands as a 200,000 square foot Class A office building in Andover, Massachusetts, worth roughly $15,000,000. Although the building has a large square footage,
More informationTaking It to the Limit BY JOHN ROACH, PE, AND JOHN BOEKELMAN, SE, PE, RA CannonDesign
A Pennsylvania healthcare facility needed additional clinical space in a tight urban center. So it expanded the only way it could: up. Taking It to the Limit BY JOHN ROACH, PE, AND JOHN BOEKELMAN, SE,
More informationStructural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report
1 THE ODYSSEY ARLINGTON, VA Aaron Snyder Structural Option Advisor: M. Kevin Parfitt, PE Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report Executive
More informationMOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS
MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS PARKERSBURG, WEST VIRGINIA DOMINIC MANNO STRUCTURAL OPTION FACULTY CONSULTANT: DR. ANDRES LEPAGE PROPOSAL 12-12-08 TABLE OF CONTENTS TABLE OF CONTENTS.
More informationState Street New Haven CT Structural Sabrina Duk T. Boothby
360 State Street New Haven CT 06510 360 State Street New Haven CT 06510 Breadth Study Cost & Schedule Comparison About 360 State Street Project Team Owner/Architect: Becker + Becker Associates Structural
More informationTechnical Assignment 1
Westinghouse Electric Company Nuclear Power Engineering Campus Technical Assignment 1 Construction Project Management Mark Speicher Advisor: Dr. David Riley October 5 th, 2009 09 TABLE OF CONTENTS EXECUTIVE
More informationChristopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania
Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering Outline Project Original Proposal Structural Design Proposal Design Objectives Design Criteria Presentation
More informationThe Towers at the City College of New York. Robin Scaramastro - Structural Option - Advisor: Dr. Memari
The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation Spring 2007 Presentation Overview Introduction Existing Structural
More informationAllison M. Clarke Construction Management Capital One Headquarters McLean, VA Executive Summary Overall Existing Conditions Summary
Executive Summary Overall Existing Conditions Summary The results of my researching the topics requested for the Overall Existing Conditions Summary, ended up helping me to learn more about the items I
More informationMassachusetts General Hospital - Building for the Third Century Lateral System Analysis and Confirmation Design
Massachusetts General Hospital - Building for the Third Century Lateral System Analysis and Confirmation Design 55 Fruit Street 02114 The Pennsylvania State University Department of Architectural Engineering
More informationJohns Hopkins Graduate Student Housing. Thesis Proposal. 929 North Wolfe Street Baltimore, Maryland Brad Oliver Structural Advisor: Professor Memari
Johns Hopkins Graduate Student Housing 929 North Wolfe Street Brad Oliver Structural Advisor: Professor Memari 12/09/2011 Table of Contents Executive Summary -... 3 Introduction... 4 Structural Systems...
More informationCORPORATE HEADQUARTERS
TECHNICAL REPORT 1 `` CORPORATE HEADQUARTERS Great Lakes Region, U.S.A. M. JULIA HAVERTY STRUCTURAL OPTION ADVISOR: H. SUSTERSIC 12 SEPTEMBER 2014 Contents Executive Summary... 2 Purpose and Scope... 3
More informationBy Thomas Taylor, PE, Datum Engineers Inc.
Project Profile: Irving Convention Center The Art of Structure By Thomas Taylor, PE, Datum Engineers Inc. The 275,000 sq ft Irving Convention Center, in Irving, TX is recognized for its unique architecture
More informationCORPORATE HEADQUARTERS
TECHNICAL REPORT 1 REVISIONS `` Image Courtesy RTKL CORPORATE HEADQUARTERS Great Lakes Region, U.S.A. M. JULIA HAVERTY STRUCTURAL OPTION ADVISOR: H. SUSTERSIC 12 DECEMBER 2014 Contents Executive Summary...
More informationSchematic Design in Revit Structure: Leveraging the Value of BIM for Early Design Decisions
Schematic Design in Revit Structure: Leveraging the Value of BIM for Early Design Decisions David J. Odeh, PE, SECB Principal, Odeh Engineers, Inc Class Summary In this class we will explore ways to use
More informationBUILDING DESCRIPTION
BUILDING DESCRIPTION ARCHITECTURAL ENGINEERING SENIOR THESIS 1 Building Description Location: The Residences of Sherman Plaza are located in the diverse community of downtown Evanston, IL, just north of
More informationMITRE 3 Building McLean VA
Executive Summary: The MITRE 3 building is an eight story office building. Its current frame is composed of A992 wide flange shapes. The lateral resisting system is a moment frame. This moment frame consists
More informationTechnical Report #2. Matthew R Peyton
Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study
More informationBiobehavioral Health Building
Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor Heather Sustersic Location: The Pennsylvania State University University Park, PA Project Size: 5
More informationTECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania
TECHNICAL REPORT 1 Structural Concepts / Structural Existing Conditions Penn State Hershey Medical Center Children s Hospital Matthew V Vandersall The Pennsylvania State University Architectural Engineering
More informationTraci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary
1 Traci Peterson Option: Structural Faculty Consultant: Memari The Del Monte Center at The North Shore Pittsburgh, PA Structural Technical Report 3 Lateral System Analysis and Confirmation Design Date
More informationBrent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan
Structural Design: Goals: The original design of 200 Minuteman Drive was dictated largely by Brickstone Properties, the building s owner. The new design of 200 Minuteman Drive, with additional floors,
More informationECMC Skilled Nursing Facility Architectural Engineering Senior Thesis AE 481W Thesis Proposal Dr. Ali Memari December 12 th, 2011
ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis 2011 Class: Subject: Faculty Consultant: Submitted: AE 481W Thesis Proposal Dr. Ali Memari December 12 th, 2011 Table of Contents Executive
More informationENTRY FORM. DVASE 2018 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2018 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $M Buildings Over $100M Buildings $M - $1M Other Structures Under $1M Buildings $1M
More informationTechnical Report #1. Matthew R Peyton
Technical Report #1 This Document is Technical Report #1 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report will include structural
More information111 MORGAN ST. Ryan Friis
Technical Report No. 1 September 30, 2002 Executive Summary: 111 Morgan St. is a 9 story cast-in-place concrete condominium building being constructed in Chicago, Illinois. The building s floor system
More informationTHOUGH STILL SUCCESSFUL, Keeping all of the stores open was critical during renovation and vertical expansion of the this 40-year-old mall
Keeping all of the stores open was critical during renovation and vertical expansion of the this 40-year-old mall By Howell A. Gordy, R.A. THOUGH STILL SUCCESSFUL, THE 40-YEAR-OLD SOUTH SHORE PLAZA IN
More informationXyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan
Proposal Xiaodong Jiang Structure Option Advisor: Dr. Linda Hanagan December 12, 2014 Executive Summary Xyston Inn is a 17-story hotel building that will be located in Brooklyn, New York. The design of
More informationTHESIS PROPOSAL. Page 1 of 20
THESIS PROPOSAL A. EXECUTIVE SUMMARY BUILDING DESCRIPTION The Comcast Center is located in downtown Philadelphia, Pennsylvania. The 57 story building functions primarily as office space with some retail
More informationXyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan
Proposal Xiaodong Jiang Structure Option Advisor: Dr. Linda Hanagan December 12, 2014 Executive Summary Xyston Inn is a 17-story hotel building that will be located in Brooklyn, New York. The design of
More informationAngela Mincemoyer Structural Option Advisor: Dr. Boothby Peggy Ryan Wil iams Center Ithaca, New York 3 March 2014 Peggy Ryan Williams Center Proposal
Angela Mincemoyer Structural Option Advisor: Dr. Boothby Peggy Ryan Williams Center Ithaca, New York 3 March 2014 Peggy Ryan Williams Center Proposal Executive Summary The Peggy Ryan Williams Center, formerly
More informationECMC Skilled Nursing Facility Architectural Engineering Senior Thesis AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012
ECMC Skilled Nursing Facility Architectural Engineering Senior Thesis 2011 Class: Subject: Faculty Consultant: Submitted: AE 481W Thesis Proposal Dr. Ali Memari January 13 th, 2012 Table of Contents Executive
More informationKORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No
000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20
More informationSTRUCTURE ANALYSIS OF SIMMONS COLLEGE SCHOOL OF MANAGEMENT. Fang Xu, Kara Wetzel, Kevin Walsh, Yuting Song
STRUCTURE ANALYSIS OF SIMMONS COLLEGE SCHOOL OF MANAGEMENT Fang Xu, Kara Wetzel, Kevin Walsh, Yuting Song General Building Data General Building Data Building Name: Simmons College School of Management
More informationSection 4 - Design and Construction Overview
Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First
More informationDrexel University Race Street Dormitory REVISED THESIS PROPOSAL Doug Tower Structural Advisor: Kevin Parfitt 2/7/07
Drexel University Race Street Dormitory REVISED THESIS PROPOSAL Doug Tower Structural Advisor: Kevin Parfitt 2/7/07 Table of Contents I. Executive Summary... 3 II. Introduction... 4 III. Background...
More informationOffice Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari
Office Building-G Thesis Proposal Structural Option December 10, 2010 Table of Contents Executive Summary... 3 Introduction... 4 Gravity System...4 Lateral System:...6 Foundation System:...6 Problem Statement...
More informationTotaling approximately 617,000
Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street
More informationSENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING
SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING THE TOWERS AT THE CITY UNIVERSITY OF NEW YORK NEW YORK CITY, NEW YORK ROBIN SCARAMASTRO AE 481 W DR. MEMARI EXECUTIVE SUMMARY The Towers at
More informationOn Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)
TECHNICAL NOTE On Cold-Formed Steel Construction $5.00 Light Gauge Steel Engineers Association Washington, D.C. 20005 Toll Free (866) 465-4732 www.lgsea.com DESIGN OF BY-PASS SLIP CONNECTORS IN COLD-FORMED
More informationBuilding Architecture
The front of the building consists of the three story town homes with facades to remain, as well as one leg of the condominium tower that reaches the street. The main condo portion of the building is L
More informationStructural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/
120 Montgomery Street, Suite 1410 San Francisco, California 94104 415/781-1505 Fax 415/781-2718 sde@sdesf.com Rajendra Sahai, SE Principal John W. Laws, SE Principal Steven Lepisto, SE Principal STRUCTURAL
More informationSpring Run Assisted Living Willow Street, Pennsylvania Architectural The Pennsylvania State University Introduction
Introduction ANDREW SOLOMON 9 Introduction: The purpose of this report is to summarize my thesis project. Thesis was a 2 semester course in which I performed multiple analyses and a new design of the structural
More informationThe owner is Oral Roberts University, while management and leasing is handled by Trinity Corporate Real Estate Advisors, LLC.
CityPlex Towers is Oklahoma s largest mixed use office and medical complex comprising of approximately 2.2 million square feet. The structure is reinforced, poured in place concrete, built in 1980. The
More informationTechnical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI
Courtesy of HGA Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI Jessel Elliott Structural 2011 Architectural Engineering Senior Thesis Studio Advisor: Dr. Richard Behr Date:
More informationROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:
ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA 02144 Tel: 617.628.1700 Fax: 617.628.1711 March 3, 2016 Mr. Jeff Hoover, Principal Tappe Architects, 6 Edgerly Place
More information4. Construction Analysis Façade Sequencing
4. Construction Analysis Façade Sequencing Problem Statement As a developer catering to Class-A tenants, the owners of are placing a strong emphasis on the occupancy schedule for the office spaces. The
More informationGEN*NY*SIS CENTER FOR EXCELLENCE IN CANCER GENOMICS Rensselaer, NY
Existing Typical Floor Plan The typical floor plan of the Gen*NY*Sis Center for Excellence in Cancer Genomics (CFG) consists of mainly laboratories and offices with an atrium in the center. The hallway
More informationJames W. & Frances G. McGlothlin Medical Education Center Virginia Commonwealth University Richmond, VA
James W. & Frances G. McGlothlin Medical Education Center Virginia Commonwealth University Richmond, VA October 18, 2013 Professor Linda Hanagan 212 Engineering Unit A University Park, PA 16802 lhanagan@engr.psu.edu
More informationTECHNICAL REPORT III. University Academic Center. Eastern USA. Alexander Altemose. Structural Option. Advisor: Thomas E. Boothby
TECHNICAL REPORT III University Academic Center Eastern USA Alexander Altemose Structural Option Advisor: Thomas E. Boothby November 12, 2012 Table of Contents Executive Summary 3 Introduction 4 Structural
More informationThesis Proposal. Matthew R Peyton
This Document is for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. S t r u c t u r a l O p t i o n P r o f e s s o r B e h r H o s p i t a l
More informationVoigt 1. Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1.
Voigt 1 Russell Voigt Construction Option Advisor Ed Gannon Louis at 14 th Washington, D.C. 16 September 2013 Technical Report #1 Executive Summary Located in northwest Washington, D.C. at the corner of
More informationWeill Cornell Medical Research Building 413 E. 69 th Street New York, NY
Weill Cornell Medical Research Building 413 E. 69 th Street New York, NY Structural Option Thesis Proposal Submitted: 1/2/12 Table of Contents Executive Summary..3 Introduction.4 Structural Systems...5
More informationENTRY FORM. DVASE 2018 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2018 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $5M Buildings Over $100M Buildings $5M - $15M Other Structures Under $1M Buildings
More informationTechnical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design
Executive Summary Technical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design The Food Science Building in State College, Pennsylvania is a four story above ground steel composite
More informationFDA OC/ORA Office Building
FDA OC/ORA Office Building Table of Contents Executive Summary... 3 Introduction... 4 Structural System... 5 Foundation:... 5 Floor System:... 7 Building 31:... 7 Building 32:... 9 Columns... 10 Lateral
More informationWeill Cornell Medical Research Building 413 E. 69 th Street New York, NY
Weill Cornell Medical Research Building 413 E. 69 th Street New York, NY Structural Option Technical Report 1 9/23/11 Table of Contents Executive Summary..3 Introduction.4 Structural Systems...5 Foundation
More informationStructural Requirements
Structural (for the design Engineer of Record) Presented by: Lindsay Anderson Consultant Structural Plan Examiner and Dixit Patel Structural Plan Examiner 1 Overview 1. Department Clarification Memorandums
More informationLIGHTWEIGHT STEEL FRAME M A R G A R E T K R A M E R K E L L Y S T R A U S B E R G E R
LIGHTWEIGHT STEEL FRAME M A R G A R E T K R A M E R K E L L Y S T R A U S B E R G E R BASIC USES Interior Partitions Curtain Walls Load Bearing Walls Floor Joists Roof Trusses INTERIOR PARTITIONS Most
More informationOVERALL STRUCTURAL SYSTEM
EXECUTIVE SUMMARY The at the Pittsburgh International Airport, PA, is a 275,000 square foot multi-use building located directly adjacent to the airport s landside terminal. The building consists of an
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationExpansion. Goes Up and Over. Steel framing facilitates multi-phase project designed to add space and functionality.
health care Expansion Goes Up and Over By Erin Kelly, AIA, and Ralph D Apuzzo, P.E. WWhen Atlantic Health began to implement its 330,000-sq.-ft master plan for Morristown Memorial Hospital in Morristown,
More informationREVISED PROPOSAL. University Academic Center. Eastern USA. Alexander Altemose. Structural Option. Advisor: Thomas E. Boothby
REVISED PROPOSAL University Academic Center Eastern USA Alexander Altemose Structural Option Advisor: Thomas E. Boothby January 11, 2013 Table of Contents Executive Summary 3 Introduction 4 Structural
More informationTechnical Report 1. Hakuna Resort Swift Water, Pennsylvania. Image Courtesy of LMN Development LLC
Technical Report 1 Hakuna Resort Swift Water, Pennsylvania Image Courtesy of LMN Development LLC Young Jeon Structural Option Advisor: Heather Sustersic 13 September 2014 1 Table of Contents Technical
More informationDavid A. Walenga Technical Assignment #1
Executive Summary Contained in this report is design information related to the structural system of the Residence Inn by Marriot located in Stamford, Connecticut. Specifically, this report covers: code
More informationShow how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality
Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge
More informationThesis Proposal. Executive Summary:
Executive Summary: Thesis Proposal Contained in this report are the following items: Building background related to proposal topics Investigation topics with their proposed solutions Solutions methods
More informationProject Design Overview
Project Design Overview Primary Engineering Systems Architecture (Design and Functional Components): The Canton Crossing Tower is the first of many new additions to the 65-acre Canton Crossing campus.
More informationKatie Sennett. Dec. 18, Baltimore, Maryland. Proposal. Page 2. Page 1
Table of Contents o Executive Summary......... Page 2 o Building Introduction..........Page 4 o Analysis 1.................. Page 8 o Analysis 2................. Page 10 o Analysis 3.................Page
More informationOffice Building. Katey Andaloro. Technical Assignment #1. Washington, D.C. Construction Management Dr. John Messner
Washington, D.C Technical Assignment #1 Table of Contents Executive Summary 2 Project Schedule Summary 3 Building Systems Summary 5 Project Cost Evaluation 9 Site Plan of Existing Conditions 13 Local
More informationThird Avenue New York, NY. Structural Concepts/ Structural Existing Conditions Report September 30, Michelle L.
Executive Summary The structural design of 554-556 Third Avenue is composed of two way concrete slabs supported by a system of columns spanning an average of twenty feet. Lateral loads are resisted by
More informationEast Lyme Middle School EAST LYME MIDDLE SCHOOL
Description: N EAST LYME MIDDLE SCHOOL The school consists of a multi story building with lower, main and upper level floors. The typical floor framing for the main and upper levels is wide flange steel
More informationPROPOSAL MONONGALIA GENERAL HOSPITAL THESIS PROPOSAL: BLAST AND PROGRESSIVE COLLAPSE ANALYSIS (REVISED)
MONONGALIA GENERAL HOSPITAL 1200 J.D. ANDERSON DRIVE, MORGANTOWN, WEST VIRGINIA THESIS PROPOSAL: BLAST AND PROGRESSIVE COLLAPSE ANALYSIS (REVISED) PROPOSAL THE PENNSYLVANIA STATE UNIVERSITY DEPARTMENT
More informationTechnical Report #1. Indiana Regional Medical Center Indiana, PA. Cody A. Scheller. Structural Concepts & Existing Conditions Report
Technical Report #1 Technical Report #1 Structural Concepts & Existing Conditions Report Indiana Regional Medical Center Cody A. Scheller The Pennsylvania State University Architectural Engineering Faculty
More informationExisting Construction Conditions
Tracy Lo Terrell Place 575 7 th Street NW Washington DC September 23, 2002 Construction Management Existing Construction Conditions Executive Summary For this assignment, I have sent out an email to gather
More informationDVASE 2018 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2018 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $5M Buildings Over $100M Buildings $5M - $15M Other Structures Under $1M Buildings
More informationMichael A. Hebert Spring 2006
4.0 Depth Analysis Lateral Force Resisting System 4.1 Existing System Braced Frames The existing lateral force resisting system was previously assessed for its load carrying capacity and potential for
More informationENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2016 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings
More informationProject. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal
Project San Jose City College Physical Education Building PLACE IMAGE HERE Prepared For Ken Bauer, AIA Principal LPAS 2484 Natomas Park Drive Sacramento, CA 95833 916.443.0335 Prepared By Steve Ratchye,
More informationThesis Proposal. CHRIS VANDELOGT Structural Option
Thesis Proposal CHRIS VANDELOGT Global Village Rochester Institute of Technology The Pennsylvania State University Faculty Advisor: Dr. Hanagan 12/12/2011 Executive Summary identifies a problem with the
More informationENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2016 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M X Buildings $2M-$10M Other Structures Under $5M Buildings
More informationStephan Northrop Structural Option Dr. Linda Hanagan. North Shore Equitable Building Pittsburgh, PA Senior Thesis Proposal
Stephan Northrop NORTHROP THESIS PROPOSAL PAGE - 1 TABLE OF CONTENTS Executive Summary.. 3 1. Introduction.. 4 2. Structural Systems.. 5 Foundation.. 5 General Floor Framing.. 6 Turret Framing.. 7 Roof
More information