THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

Size: px
Start display at page:

Download "THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA"

Transcription

1 THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor PRO-CON STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS Executive Summary The Plaza at PPL Center is an eight-story mixed-use building, with first floor rentable retail space, office space on the second through sixth floors and securities trading on the two upper floors. Core areas border the east and west sides of a central atrium. For the given site, steel framing is best. Steel systems are light and that is desirable for the Plaza at PPL Center since the soil conditions are poor. Steel also allows for large open plans which the architect has designed for the Plaza at PPL Center. A precast concrete system may be worth investigating for the building on an alternate site because it has many advantages, but does require a review of the lateral system. Existing Framing System Members The existing structure for the Plaza at PPL Center is a composite steel system. The floor framing is typically W-shape, composite steel beams spaced at 10 on center with a maximum span of 42. A 5-1/4 a light-weight concrete slab on composite steel deck spans 10 from beam to beam in no less than a three-span condition. See Figure 1 for typical member sizes. Strengths A992 Steel: F y = 50ksi Steel Deck: F y = 40ksi Lightweight concrete slab: f c = 4ksi Figure 1: Existing Framing 1

2 System Characteristics With an extended slab and spray-on fireproofing, this system offers a two-hour fire rating. The Plaza at PPL Center site had poor soil bearing capacity, which was supplemented by compaction grouting, however, the building is still at high risk for differential settlement. A steel system is typically lighter which is beneficial given the soil conditions. Lightweight systems are more subject to vibration and this will have to be considered. In the typical office area, the height of the floor structure is nearly two feet. The HVAC design had to be coordinated with the structural design to allow ducts to penetrate some of the beams. The long spans require the steel beams to be cambered typically 1-1/2 to counteract the effects of deflection. The Plaza at PPL Center has a strict time constraint, since the unregulated subsidiaries of PPL Corporation must be relocated prior to April 30, Steel construction requires early planning to account for fabrication time but goes quite quickly from there. Variations on the Existing Steel Systems Removal of Moment Connections Moment connections are costly, in time and money. As designed, the Plaza at PPL Center direction resists lateral loads with braced frames in the north-south direction and moment frames in the east west-direction to allow for flexibility within the plan. However, the primary tenant, PPL Energy Plus, has signed a thirty-year contract with the owner, Liberty Property Trust. The tenant has designed large conference rooms and storage areas along the central core of the building. Unlike office cubicles these spaces will have full-height walls. Provided there is coordination with the tenant s architect, it would be possible to eliminate the moment connections in the east-west direction and use braced frames to resist lateral loads in this direction as well. 2

3 Diagonal Girders The architect for the Plaza at PPL Center located columns so they would align with the window mullions. It is desirable to have girders, which carry a large portion of the floor load to frame from column to column. For the exterior columns to be aligned with the window mullions they were not aligned with the rest of the columns in the building. Therefore, the girders framing from column to column ran along a diagonal line (see Figure 2), forcing the beams framing into the column to be of staggered lengths and sizes. The floor plan is close to symmetrical. It would be economical to recenter the core to align with the exterior Figure 2: Diagonal Beams column lines. The windows are in 5 panes that would be a convenient module to work with. As the building is laid out the spaces appear to be symmetrical but in actually it is not. Realigning the columns would permit the smaller sizes as they are now, but it would also allow for more redundancy among the beams. It would be possible to run the girders into the perpendicular beams; however, this results in heavier beams, which would be less economical than the current layout with staggered lengths. Steel Bar Joists Members Steel bar joists could be used instead of steel beams as the primary framing. The 24 joists would be spaced at 2 on center and span the 42 to W-shape girders. With the closer spacing, a 4 slab can be used instead of the original 5-1/4 slab or a shallower slab can be used but this may cause vibration issues. Steel Deck is 22 ga. B-lok deck with no studs. See Figure 3. Figure 3: K-series Joists and Metal Deck 3

4 Strengths Steel Deck: F y = 33ksi Normal Weight Concrete Slab: f c = 3ksi Steel Joist Chords: F y = 50ksi Steel Joist Webs: F y = 36ksi Characteristics It is more difficult to obtain a 2-hour fire rating as required for office buildings with a bar joist system. However, it is possible to do so when used in conjunction with a fire-rated ceiling assembly. Steel bar joists are commonly used in the Lehigh Valley and are often an economical system. The downfall comes in the installation and labor. The original design has beams at 10 on center and the steel joists spaced at 2 on center will call for five times as many members to be placed. Mechanical ducts up to 10 square, 13 round and 8 x13 can run through the 24 K- Series joist. The joist manufacture requires the size and location of mechanical ducts to be noted on structural drawings if they are to pass through a joist. This would be possible for the Plaza at PPL Center. While most of the sub-contractors are contracted at a maximum price, the mechanical contractor is working as design-build. It would be convenient for coordination between the mechanical and structural designs. A bar joist system is lightweight which would be advantageous for the site. The lightweight system may turn out to be problematic in that it will be more prone to vibration. 4

5 Concrete Pan Joists and Girders Members Concrete pan joists spanning in the 42 direction are 29 deep and 8 wide. The joists would be spaced at 4 o.c. since shear reinforcement will be required due to the long span and this module is achieved with 40 pans and 8 joists. Turning the framing, pan joists running the 30 direction required a minimum depth of 23, but the concrete girders would be spanning 42 instead of the 30 direction which is more practical for the heavier members. A five Figure 4: Concrete Pan Joists inch slab is required for the two hour fire-rating. Girder depth should be equal to the joist depth, so interior T-beam girders will be 29 deep and 24 wide. See Figure 4. for typical framing plan. Strengths f c = 4ksi F y = 60ksi Characteristics This system will be a heavy system given the weight of concrete and the large member sizes, so it is not the most appropriate system give the poor soil conditions. Cast-in place concrete is not common in the Lehigh Valley and the labor force is not readily available. This system is the deeper than any of the other systems and does not allow for mechanical penetrations. Concrete is a good system in that it does not have the lead time that steel has, but it generally takes more time to place in the field. Concrete is inherently fireproof and not as susceptible to vibrations which are advantages over the steel systems. 5

6 Hollow Core Plank and Prestressed Beams Members For the Plaza at PPL Center 12 hollow-core planks of lightweight concrete could be used to span the 42 direction with a 2 normal weight concrete topping to provide a flat surface for carpeting. The planks span 42 to pre-cast, pre-stressed girders that are 24 deep. L-Beams used around the perimeter and T-beams used in center spans provide a flush floor condition without dropping beams See Figure 5 for typical framing layout. Strengths Concrete: f c = 5ksi Steel Strands: F pu = 270 ksi Figure 5: Precast Concrete System System Characteristics A concrete system will be heavier than steel, which may be problematic considering the soil conditions at the Plaza for PPL Center site. The site on which the Plaza at PPL Center is being constructed was not always available. A hockey arena was initially planned for the site, until PPL Corporation declared interest in the lot. If PPL Corporation could not develop the site next to their current headquarters, the company stated that it would look to sites outside the city limits. Had the corporation been denied the site, the soils conditions may not have been such a governing factor. A different structure could be proposed for a building on an alternate site. Precast concrete systems allow for quick on-site construction. The precast members can be fabricated as the foundations are started. The floor and framing would be supplied by one contractor, which can also speed up construction. The existing building uses precast panels for the façade. It would be convenient to incorporate a precast structure as well. 6

7 Concrete systems offer good resistance to fire. Additional fireproofing is not needed as with steel construction. With the conversion from a steel system to concrete the lateral system has to be reevaluated as well. It is possible for precast systems to incorporate rigid frames however; it is not typically economical to do so. It is most efficient to use precast elements in simple span conditions because: 1. It is more difficult and expensive to achieve negative moment resisting capacity in precast members 2. Moment resisting connections are more expensive 3. Rigidity of connection may cause cracking since it cannot respond to temperature movement. It is most desirable to incorporate shear walls into the structure to act with floor and roof diaphragms to resist lateral loads. The Plaza at PPL Center has adequate room for shear walls in the north-south direction. As stated previously the layout could be planned so that shear walls could be incorporated in the east-west direction as well. Comparison System Advantages Disadvantages Potential? 1 Existing Lightweight Susceptible to Vibration YES Fast On-site Erection Long Lead Time Spray-on Fireproofing Crane Required Common to the Area Camber required Can incorporate Mech. Eq. 1a Braced Frames Econmomical Need Arch. Approval of Floor Layout YES 1b Move Columns Provides redundancy Need Arch. Approval of Floor Layout YES 2 K-Series Joists Lightweight Susceptible to Vibration YES Fast Erection More pieces to erect Common to the Area Fire-rated Ceiling Assembly Can Incorporate Mech. Eq. Crane required Deep System 3 Conc. Pan Joists Short Lead Time Heavy NO Fireproof Large Members Less Susecpitible to Vibration Deepest System Less deflection Mech. Eq. Must be Dropped Not Common to the Area 4 Precast Conc. Quick Heavy YES Already using Precast Panels Crane Required Shallowest System Economical Fireproof 7

8 References PCI Design Handbook, 5 th Edition AISC Load Resistance and Factor Design, 3 rd Edition United Steel Deck Design Manual The New Columbia Joist Company Steel Joists and Joists Girders 8

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor 12.16.2002 THESIS PROPOSAL Executive Summary Architecture The Plaza at PPL

More information

David A. Walenga Technical Assignment #2

David A. Walenga Technical Assignment #2 Executive Summary This report explores multiple structural design alternatives for the Residence Inn by Marriott. The existing system, precast concrete plank on steel, is the basis for comparison with

More information

These systems are evaluated on the basis of serviceability issues such as:

These systems are evaluated on the basis of serviceability issues such as: 1 Traci Peterson Option: Structural Faculty Consultant: Memari The Del Monte Center at The North Shore Pittsburgh, PA Structural Technical Report 2 Pro Con Structural Study of Alternate Floor Systems Date

More information

Eric Alwine Structural Option George Read Hall The University of Delaware Dr. Boothby Technical Assignment #2 October 31, 2005 EXECUTIVE SUMMARY:

Eric Alwine Structural Option George Read Hall The University of Delaware Dr. Boothby Technical Assignment #2 October 31, 2005 EXECUTIVE SUMMARY: EXECUTIVE SUMMARY: THIS REPORT IS A COMPARISON OF ALTERNATE FLOOR SYSTEMS FOR GEORGE READ HALL. FOUR DIFFERENT SYSTEMS WERE DESIGNED AND COMPARED TO THE EXISTING HAMBRO FLOOR SYSTEM. THE FOUR SYSTEMS WERE

More information

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Christopher McCune Structural Option Eight Tower Bridge Faculty Advisor: Dr. Hanagan October 31 st, 2005 Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Executive Summary This technical

More information

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004 Ismail Al-Hadhrami Structural Option Faculty Consultant: Dr. Thomas Boothby Agricultural Hall and Annex East Lansing, MI Pro-Con Structural Study for Alternative Floor Systems October 27, 2004 Executive

More information

Pro-Con Structural Study of Alternate Floor Systems

Pro-Con Structural Study of Alternate Floor Systems Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary

More information

THE FORENSIC MEDICAL CENTER

THE FORENSIC MEDICAL CENTER THE FORENSIC MEDICAL CENTER Image courtesy of Gaudreau, Inc. TECHNICAL REPORT #2 OCTOBER 26, 2007 KEENAN YOHE STRUCTURAL OPTION DR. MEMARI FACULTY ADVISOR EXECUTIVE SUMMARY Image courtesy of Gaudreau,

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 2 October 29 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

Crossroads at Westfields Building II

Crossroads at Westfields Building II Crossroads at Westfields Building II Chantilly, Va STEPHEN LUMPP Structural option Faculty Consultant: Dr. Andres Lepage Technical Report 2 EXECUTIVE SUMMARY This report is a study of alternate floor systems

More information

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...

More information

Technical Report #2 10/26/06

Technical Report #2 10/26/06 Photo courtesy of OTO Development, http://www.otodevelopment.com/ Dr. Memari Thesis Advisor Technical Report #2 10/26/06 Executive Summary Systems Overview Hollow Core Plank (precast) Solid Flat Slab (precast)

More information

Caitlin Ferrell Structural Option Dr. Boothby, AE Faculty Consultant. Erie Convention Center and Sheraton Hotel

Caitlin Ferrell Structural Option Dr. Boothby, AE Faculty Consultant. Erie Convention Center and Sheraton Hotel Caitlin Ferrell Structural Option Dr. Boothby, AE Faculty Consultant Erie Convention Center and Sheraton Hotel Erie, Pennsylvania Technical Report #2: Pro-Con Structural Study of Alternate Floor Systems

More information

SIGNAL HILL PROFESSIONAL CENTER Manassas, Virginia Morabito Consultants EXECUTIVE SUMMARY

SIGNAL HILL PROFESSIONAL CENTER Manassas, Virginia Morabito Consultants EXECUTIVE SUMMARY EXECUTIVE SUMMARY Like most suburban office building in Northern Virginia, the Signal Hill Professional Center, a four-story office structure in Manassas features composite steel construction for both

More information

Structural Technical Report #2 By Robert Whitaker

Structural Technical Report #2 By Robert Whitaker Structural Technical Report #2 By Robert Whitaker Robert Whitaker Structural ~ Parfitt Parkview at Bloomfield Station Bloomfield, NJ 10-31-05 Executive Summary This report covers the comparative redesign

More information

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems Technical Report 2 Pro-Con Structural Study of Alternate Floor Systems Columbia University Broadway & 120 th Street, New York, NY Jonathan R. Torch Pennsylvania State University Architectural Engineering

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

U.S. Pharmacopeia Headquarters Consolidation. Rockville, MD

U.S. Pharmacopeia Headquarters Consolidation. Rockville, MD Consolidation Jeff Rothermel Structural Option Advisor: Dr. Ali Memari Technical Report 2 Submitted: Oct. 24 th, 2008 Table of Contents Executive Summary.1 Floor Systems Existing Two Way Slab with Drop

More information

Earth and Engineering Sciences Building

Earth and Engineering Sciences Building Executive Summary The purpose of this report is to provide an analysis of the existing floor system of the Earth and Engineering Sciences Building at University Park, Pennsylvania, as well as investigating

More information

TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS

TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS Chris Vanaskie Structural Peninsula Regional Medical Center Salisbury, MD December 22, 2008 TABLE OF CONTENTS Executive Summary... 3 Introduction...

More information

THE PLAZA AT PPL CENTER ALLENTOWN, PA

THE PLAZA AT PPL CENTER ALLENTOWN, PA Building Function and Primary Use The owner of the new Plaza at PPL Center is Liberty Property Trust, but the primary tenant is PPL, which will use the building as the headquarters for its new subsidiaries

More information

Technical Report 2: Pro-Con Structural Study of Alternate Floor Systems

Technical Report 2: Pro-Con Structural Study of Alternate Floor Systems Gateway Plaza Wilmington, DE October 31, 2005 Elizabeth Hostutler Structural Option Advisor: Linda Hanagan Technical Report 2: Pro-Con Structural Study of Alternate Floor Systems EXECUTIVE SUMMARY The

More information

Danielle Shetler - Structural option Courtyard by Marriott Lancaster, PA

Danielle Shetler - Structural option Courtyard by Marriott Lancaster, PA Structural Analysis Overview: During the structural analysis of the in Lancaster, Pa, a redesign of the lateral and gravity system from masonry bearing and shear walls to a staggered truss system was performed.

More information

Technical Report 3. Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R

Technical Report 3. Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R Technical Report 3 Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R Site and Location La Jolla Commons, San Diego, California General

More information

STEEL STRUCTURAL SYSTEMS

STEEL STRUCTURAL SYSTEMS STEEL STRUCTURAL SYSTEMS Steel elements are of two basic types: Structural steel shapes are formed into their final shapes by hot-rolling. This method produces such common elements as wide flange sections,

More information

Hershey Research Park Building One. Technical Report 2. Jonathan Krepps Structural Option Advisor: Dr. Hanagan 10/12/12

Hershey Research Park Building One. Technical Report 2. Jonathan Krepps Structural Option Advisor: Dr. Hanagan 10/12/12 Hershey Research Park Building One Technical Report 2 Advisor: Dr. Hanagan 10/12/12 Table of Contents Executive Summary..3 Building Introduction 4 Structural Overview..5 Materials 9 Design Codes 10 Design

More information

STRUCTURAL TECHNICAL REPORT 2

STRUCTURAL TECHNICAL REPORT 2 Technical Report 2 Page 1 David Lee AE 481W Structural Option Advisor: Andres Lepage URS Office Building October 27, 2006 STRUCTURAL TECHNICAL REPORT 2 Pro-Con Structural Study of Alternate Floor System

More information

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2 University at Buffalo CTRC/Incubator Buffalo, New York William McDevitt October 27, 2010 Table of Contents Executive Summary...3 Introduction...4 Structural System Overview...5 Foundation...5 Floor System...5

More information

Best Buy Corporate Building D (4) Richfield, MN

Best Buy Corporate Building D (4) Richfield, MN Best Buy Corporate Building D (4) Thesis Proposal Professor Boothby December 12 th, 2008 Executive Summary: The Best Buy Corporate Building D is a 6 story building with a total area of 304,610 square feet.

More information

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor

More information

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Table of Contents 1. Executive Summary.....Page 2 2. Existing Floor System....Page 4 2.1. Composite steel beams with composite

More information

Technical Report #2. Matthew R Peyton

Technical Report #2. Matthew R Peyton Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study

More information

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #2 October 31,

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #2 October 31, 1 Executive Summary: Pro-Con Structural Study of Alternate Floor Systems is an investigation into possible alternative structural systems for Lexington II in Washington, D.C. For this report, several structural

More information

181 Fremont San Francisco, CA. Tech Report 3 10/17/2014. PSUAE Structural Option Advisor: Dr. Thomas Boothby

181 Fremont San Francisco, CA. Tech Report 3 10/17/2014. PSUAE Structural Option Advisor: Dr. Thomas Boothby 181 Fremont San Francisco, CA Tech Report 3 10/17/2014 PSUAE Structural Option Advisor: Dr. Thomas Boothby Caroline Klatman cjk5258@psu.edu October 17, 2014 Dr. Thomas Boothby The Pennsylvania State University

More information

Temecula Medical Center Temecula, CA

Temecula Medical Center Temecula, CA Temecula Medical Center Temecula, CA Technical Assignment #2 Sean F. Beville The Pennsylvania State University Architectural Engineering Structural Option Senior Thesis Project Student Advisor: Thomas

More information

Hilton Baltimore Convention Center Hotel Western Podium

Hilton Baltimore Convention Center Hotel Western Podium Hilton Baltimore Convention Center Hotel Western Podium CHRIS SIMMONS Structural Option Faculty Consultant: Dr. Ali M. Memari Technical Report 2 TABLE OF CONTENTS EXECUTIVE SUMMARY. Page 3 INTRODUCTION..

More information

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity System Codes and Criteria Design Codes and Standards The design code used is the Wisconsin Administrative Code along with the State of Wisconsin Department of Commerce-Safety & Buildings Chapters Comm

More information

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural

More information

Park Potomac Office Building E

Park Potomac Office Building E Kyle Wagner (IP) Advisor: Professor Kevin Parfitt 12/11/2009 Table of Contents I. Executive Summary. 3 II. Introduction / Material Strengths. 4 III. Codes and Design Standards.. 5 IV. Existing Structural

More information

Matthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA

Matthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA Matthew Kutzler Structural Option Spring 2004 Buildings C and D Campus Square, Lehigh University Bethlehem, PA Located at Lehigh University in Bethlehem, PA Complex consists of four dormitories and a parking

More information

GEN*NY*SIS CENTER FOR EXCELLENCE IN CANCER GENOMICS Rensselaer, NY

GEN*NY*SIS CENTER FOR EXCELLENCE IN CANCER GENOMICS Rensselaer, NY Existing Typical Floor Plan The typical floor plan of the Gen*NY*Sis Center for Excellence in Cancer Genomics (CFG) consists of mainly laboratories and offices with an atrium in the center. The hallway

More information

Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI

Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI Courtesy of HGA Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI Jessel Elliott Structural 2011 Architectural Engineering Senior Thesis Studio Advisor: Dr. Richard Behr Date:

More information

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal Project San Jose City College Physical Education Building PLACE IMAGE HERE Prepared For Ken Bauer, AIA Principal LPAS 2484 Natomas Park Drive Sacramento, CA 95833 916.443.0335 Prepared By Steve Ratchye,

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

Structural Redesign Gravity System

Structural Redesign Gravity System Redesign Gravity System Design Considerations A composite floor system was used for this design to maximize the efficiency of the material being used. This type of system requires less material and provides

More information

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Revised Thesis Proposal

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Revised Thesis Proposal University at Buffalo CTRC/Incubator Buffalo, New York Revised William McDevitt January 14, 2011 Table of Contents Executive Summary...2 Introduction...3 Structural System Overview...4 Foundation...4 Floor

More information

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS

Kiski Area High School Allegheny Township, PA FLOOR SYSTEM ANALYSIS FLOOR SYSTEM ANALYSIS Objective The objective of the following breadth study is to determine if an alternative floor system for Building N would be more advantageous than the existing floor system. The

More information

RETHINKING MULTIFAMILY RESIDENTIAL

RETHINKING MULTIFAMILY RESIDENTIAL RETHINKING MULTIFAMILY RESIDENTIAL Presented by: Neil Wexler, PhD PE Ali Maher, PE ABOUT US- WEXLER ASSOCIATES Founded 35 years ago NYC Structural Engineers Forensic Work Active in various markets BIM

More information

Stephan Northrop Structural Option Dr. Linda Hanagan. North Shore Equitable Building Pittsburgh, PA Senior Thesis Proposal

Stephan Northrop Structural Option Dr. Linda Hanagan. North Shore Equitable Building Pittsburgh, PA Senior Thesis Proposal Stephan Northrop NORTHROP THESIS PROPOSAL PAGE - 1 TABLE OF CONTENTS Executive Summary.. 3 1. Introduction.. 4 2. Structural Systems.. 5 Foundation.. 5 General Floor Framing.. 6 Turret Framing.. 7 Roof

More information

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete

More information

Imaging Research Building

Imaging Research Building University of North Carolina s Imaging Research Building Technical Report 2, LEED AP Structural Option Consultant- Dr. Thomas Boothby October 5, 2009 Table of Contents Executive Summary..3 Introduction...4

More information

Nasser Marafi. Alternate Floor Systems. Pro Con Structural Study of. Technical Report 2. Center & Facility Service Building

Nasser Marafi. Alternate Floor Systems. Pro Con Structural Study of. Technical Report 2. Center & Facility Service Building Pro Con Structural Study of Alternate Floor Systems St. Joseph Hospital of Orange Patient Care Center & Facility Service Building Technical Report 2 Professor Andres Lepage STRUCTURAL OPTION October 26th

More information

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series

SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series SUMMARY David Samuelson Steel joists are growing in recognition as being a very economical

More information

October 19, The Pennsylvania State University. Hunter Woron Structural. Professor M. Kevin Parfitt

October 19, The Pennsylvania State University. Hunter Woron Structural. Professor M. Kevin Parfitt October 19, 2011 Hunter Woron Structural Professor M. Kevin Parfitt The Pennsylvania State University Table of Contents Executive Summary.. 2 Introduction 3 Structural Systems. 4 Foundation.. 4 Superstructure

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Brief Building Overview: 200 Minuteman Park stands as a 200,000 square foot Class A office building in Andover, Massachusetts, worth roughly $15,000,000. Although the building has a large square footage,

More information

This report investigates alternative floor systems for the building. A brief summary of each system is as follows:

This report investigates alternative floor systems for the building. A brief summary of each system is as follows: Technical Report 2 Analysis and Comparison of Alternative Floor Systems Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and tourist attraction for Boyds Collections

More information

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering Outline Project Original Proposal Structural Design Proposal Design Objectives Design Criteria Presentation

More information

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary 1 Traci Peterson Option: Structural Faculty Consultant: Memari The Del Monte Center at The North Shore Pittsburgh, PA Structural Technical Report 3 Lateral System Analysis and Confirmation Design Date

More information

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan Proposal Xiaodong Jiang Structure Option Advisor: Dr. Linda Hanagan December 12, 2014 Executive Summary Xyston Inn is a 17-story hotel building that will be located in Brooklyn, New York. The design of

More information

Structural Option Indiana Regional Medical Center Indiana, PA

Structural Option Indiana Regional Medical Center Indiana, PA West View of IRMC Southeast View of IRMC Structural Option Indiana Regional Medical Center Indiana, PA West View of IRMC Southeast View of IRMC Arial View of IRMC Project Information N Location: Occupancy

More information

House of Sweden. Structural Study of Alternative Floor Systems K St. NW Washington, DC 20007

House of Sweden. Structural Study of Alternative Floor Systems K St. NW Washington, DC 20007 Structural Study of Alternative Floor Systems 2900 K St. NW 20007 The Pennsylvania State University Department of Architectural Engineering Senior Thesis 2008-2009 October 24, 20008 Prepared by: Prepared

More information

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1 North Shore at Canton Baltimore, MD Beau Menard Technical Report 1 Structural Schneider 10/05/05 Structural Concepts Executive Summary North Shore at Canton is a 4 story town home and parking garage structure

More information

Spring Hill Suites Marriott

Spring Hill Suites Marriott Spring Hill Suites Marriott Project Location: Amarillo, TX Prepared for: Girder Slab Technologies Contact: Daniel Fisher, Sr. January 15, 2008 Prepared by: Monica Stockmann Regional Engineer: Erika Winters-Downey

More information

Trump Taj Mahal Hotel

Trump Taj Mahal Hotel Trump Taj Mahal Hotel Atlantic City, New Jersey Thesis Proposal Prepared By: Stephen Reichwein, Structural Option Faculty Advisor: Dr. Andres Lepage The Pennsylvania State University Department of Architectural

More information

Franklin Square Hospital Center Patient Tower

Franklin Square Hospital Center Patient Tower Thomas Weaver Structural Option Franklin Square Hospital Center Patient Tower Baltimore, MD Thomas Weaver Structural Option AE 481W Senior Thesis Consultant: Professor M. Kevin Parfitt 12/14/2009 Page

More information

Executive Summary. Non-Composite Steel system 2- Way Flat Concrete Slab Wood Beam with Form Deck Pre-Cast Hollow Core Plank

Executive Summary. Non-Composite Steel system 2- Way Flat Concrete Slab Wood Beam with Form Deck Pre-Cast Hollow Core Plank Executive Summary This report is a description, analysis and comparison of the existing floor system and four alternatives. The proposed floor system for the Kenneth Langone Athletic and Recreation Center

More information

David A. Walenga Technical Assignment #1

David A. Walenga Technical Assignment #1 Executive Summary Contained in this report is design information related to the structural system of the Residence Inn by Marriot located in Stamford, Connecticut. Specifically, this report covers: code

More information

State Street New Haven CT Structural Sabrina Duk T. Boothby

State Street New Haven CT Structural Sabrina Duk T. Boothby 360 State Street New Haven CT 06510 360 State Street New Haven CT 06510 Breadth Study Cost & Schedule Comparison About 360 State Street Project Team Owner/Architect: Becker + Becker Associates Structural

More information

Aubert Ndjolba Structural Option PENN COLLEGE OF TECHNOLOGY. Pro-Con Structural Study of Alternate Floor Systems. Faculty advisor: Dr.

Aubert Ndjolba Structural Option PENN COLLEGE OF TECHNOLOGY. Pro-Con Structural Study of Alternate Floor Systems. Faculty advisor: Dr. TECHNICAL REPORT II Aubert Ndjolba Structural Option PENN COLLEGE OF TECHNOLOGY Pro-Con Structural Study of Alternate Floor Systems Faculty advisor: Dr. Boothby Date: 10/19/11 Table of Contents: Executive

More information

Structural Technical Report 1 Structural Concepts / Existing Conditions

Structural Technical Report 1 Structural Concepts / Existing Conditions Chris Shelow Structural Advisor: M. Kevin Parfitt Koshland Integrated Natural Science Center 10/05/05 AE 481W Structural Technical Report 1 Structural Concepts / Existing Conditions Executive Summary The

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this

More information

Technical Report #1. Indiana Regional Medical Center Indiana, PA. Cody A. Scheller. Structural Concepts & Existing Conditions Report

Technical Report #1. Indiana Regional Medical Center Indiana, PA. Cody A. Scheller. Structural Concepts & Existing Conditions Report Technical Report #1 Technical Report #1 Structural Concepts & Existing Conditions Report Indiana Regional Medical Center Cody A. Scheller The Pennsylvania State University Architectural Engineering Faculty

More information

Thesis Proposal. Student Health Center Penn State University. Prepared By: Jacob Brambley (Structural Option) Prepared For: Dr.

Thesis Proposal. Student Health Center Penn State University. Prepared By: Jacob Brambley (Structural Option) Prepared For: Dr. Thesis Proposal Penn State University Prepared By: Jacob Brambley () Prepared For: Table of Contents Executive Summary..3 Introduction 4 Structural Systems. 5 Foundation....5 Floor System/Beams...5 Columns...6

More information

Thesis Proposal. Executive Summary:

Thesis Proposal. Executive Summary: Executive Summary: Thesis Proposal Contained in this report are the following items: Building background related to proposal topics Investigation topics with their proposed solutions Solutions methods

More information

George Read Hall. The University of Delaware. Eric Alwine Structural Option Thesis April 2006 Dr. Boothby

George Read Hall. The University of Delaware. Eric Alwine Structural Option Thesis April 2006 Dr. Boothby George Read Hall The University of Delaware Eric Alwine Structural Option Thesis April 2006 Dr. Boothby Presentation Outline Introduction Existing Structural System Problem Statement Problem Solution Depth

More information

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS PARKERSBURG, WEST VIRGINIA DOMINIC MANNO STRUCTURAL OPTION FACULTY CONSULTANT: DR. ANDRES LEPAGE PROPOSAL 12-12-08 TABLE OF CONTENTS TABLE OF CONTENTS.

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

33 Harry Agganis Way Boston, Massachusetts Tyler Meek

33 Harry Agganis Way Boston, Massachusetts Tyler Meek 33 Harry Agganis Way Boston, Massachusetts Tyler Meek Structural Option Tech Report 2 October 27, 2010 Table of Contents Executive Summary... 2 Introduction... 3 Structural Systems... 4 Foundation... 4

More information

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan Proposal Xiaodong Jiang Structure Option Advisor: Dr. Linda Hanagan December 12, 2014 Executive Summary Xyston Inn is a 17-story hotel building that will be located in Brooklyn, New York. The design of

More information

Totaling approximately 617,000

Totaling approximately 617,000 Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street

More information

PricewaterhouseCoopers Building Oslo, Norway

PricewaterhouseCoopers Building Oslo, Norway PricewaterhouseCoopers Building Oslo, Norway James Wilson Structural Option Senior Thesis Presentation 2009 The Pennsylvania State University Location Bjørvika B10 A Oslo, Norway BARCODE Building Data

More information

FAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA

FAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA 10/28/2009 TECHNICAL REPORT II FAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA Advisor: Dr. Ali Memari Structural Option TABLE OF CONTENTS Table of Contents 2 Executive Summary...3 Introduction: Fairfield

More information

Campus Square Buildings C & D Lehigh University, Bethlehem, PA

Campus Square Buildings C & D Lehigh University, Bethlehem, PA Depth Study: Structural Redesign As noted previously, Building C is the focus of the spring semester redesign, though the proposed alternatives could be applied to the other buildings in the complex, including

More information

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit Providing Engineered Concrete Solutions Precast and Mission Critical Facilities A Natural Fit Total precast solutions eliminate trade overlap in the construction of the core and shell system A total precast

More information

OF THREE NEW BUILDINGS BEING CONSTRUCTED TO REPLACE THE EXISTING COMPLEX. THE FLOOR SYSTEM OF GEORGE READ HALL IS A HAMBRO COMPOSITE SYSTEM

OF THREE NEW BUILDINGS BEING CONSTRUCTED TO REPLACE THE EXISTING COMPLEX. THE FLOOR SYSTEM OF GEORGE READ HALL IS A HAMBRO COMPOSITE SYSTEM EXECUTIVE SUMMARY: GEORGE READ HALL IS A FIVE STORY DORMITORY ON THE UNIVERSITY OF DELAWARE S CAMPUS. EMCOMPASSING 129,000 SQUARE FEET, IT IS THE LARGEST OF THREE NEW BUILDINGS BEING CONSTRUCTED TO REPLACE

More information

AISC Steel & Timber Research for High-Rise Residential Buildings

AISC Steel & Timber Research for High-Rise Residential Buildings AISC Steel & Timber Research for High-Rise Residential Buildings Final Report December 4 th, 2017 SOM Designed Benchmark Concrete Building Skidmore, Owings, and Merrill, LLP 2017 224s Michigan Avenue Suite

More information

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari Thesis Presentation - Spring 2006 Contents Introduction Building Professionals Existing Structure

More information

A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS

A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS Neil F. Dunbar Ketch u m-kon ke l-barrett-n i cke I-A u sti n Consulting Engineers Denver, Co!oredo Describes several structural systems using both

More information

MITRE 3 Building McLean VA

MITRE 3 Building McLean VA Executive Summary: The MITRE 3 building is an eight story office building. Its current frame is composed of A992 wide flange shapes. The lateral resisting system is a moment frame. This moment frame consists

More information

2011 Technical Assignment 2 Thomas J Kleinosky Structural Option Patient Care Pavilion; Albany, NY 10/19/2011 Advisor: Dr. Hanagan

2011 Technical Assignment 2 Thomas J Kleinosky Structural Option Patient Care Pavilion; Albany, NY 10/19/2011 Advisor: Dr. Hanagan 2011 Technical Assignment 2 Thomas J Kleinosky Structural Option Patient Care Pavilion; Albany, NY 10/19/2011 Advisor: Dr. Hanagan October 19, 2011 [TECHNICAL ASSIGNMENT 2] Table of Contents Executive

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 1 October 5 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

Point Pleasant Apartments Point Pleasant, NJ Ryan P. Flynn Structural Option Faculty Consultant: Dr. Hanagan

Point Pleasant Apartments Point Pleasant, NJ Ryan P. Flynn Structural Option Faculty Consultant: Dr. Hanagan Point Pleasant Apartments Point Pleasant, NJ Ryan P. Flynn Structural Option Faculty Technical Report #3: Lateral System Analysis and Confirmation Design Table of Contents Introduction... 3 Executive Summary...

More information

Thesis Proposal. Matthew R Peyton

Thesis Proposal. Matthew R Peyton This Document is for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. S t r u c t u r a l O p t i o n P r o f e s s o r B e h r H o s p i t a l

More information

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign

More information

STRUCTURAL TECHNICAL REPORT 1

STRUCTURAL TECHNICAL REPORT 1 Technical Report 1 Page 1 David Lee AE 481W Structural Option Advisor: Andres Lepage URS Office Building October 5, 2006 STRUCTURAL TECHNICAL REPORT 1 Structural Concepts / Structural Existing Conditions

More information

Lateral System Analysis and Confirmation Design November 15, 2004

Lateral System Analysis and Confirmation Design November 15, 2004 Jonathan Hill Structural AE Faculty Consultant Dr. Hanagan Lynde and Harry Bradley School of Technology & Trade Milwaukee, Wisconsin Lateral System Analysis and Confirmation Design November 15, 2004 Executive

More information

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS PARKERSBURG, WEST VIRGINIA DOMINIC MANNO STRUCTURAL OPTION FACULTY CONSULTANT: DR. ANDRES LEPAGE Technical Report 3 11-21-08 TABLE OF CONTENTS TABLE OF

More information

1000 CONTINENTAL SQUARE

1000 CONTINENTAL SQUARE 1000 CONTINENTAL SQUARE KING OF PRUSSIA, PENNSYLVANIA Carter Davis Hayes Structural Option January 13, 2008 Advisor: Dr. Hanagan TABLE OF CONTENTS TABLE OF CONTENTS... 2 EXECUTIVE SUMMARY... 3 I. STRUCTURAL

More information

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax:

ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA Tel: Fax: ROOME & GUARRACINO, LLC Consulting Structural Engineers 48 Grove Street Somerville, MA 02144 Tel: 617.628.1700 Fax: 617.628.1711 March 3, 2016 Mr. Jeff Hoover, Principal Tappe Architects, 6 Edgerly Place

More information

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems University of Nebraska - Lincoln DigitalCommons@University of Nebraska - Lincoln Architectural Engineering -- Dissertations and Student Research Architectural Engineering Spring 4-20-2012 A Composite Structural

More information