1 Energy Conservation & Demand Management Plan Town of Penetanguishene

2 TABLE OF CONTENTS 1.0 INTRODUCTION PLAN STRUCTURE COMMITMENT DECLARATIONS VISION GOALS OVERALL TARGET OBJECTIVES UNDERSTANDING MUNICIPAL ENERGY SITUATION HOW WE MANAGE ENERGY TODAY Lighting Upgrades Heating & Cooling Equipment Equipment Insulation Windows Building Envelope Roof Upgrades SUMMARY OF ENERGY CONSUMPTION AND GREENHOUSE GAS EMISSIONS GHG Emissions TRENDS IN ENERGY CONSUMPTION Trends in Energy Consumption Electricity Consumption Trend Natural Gas Consumption Trend Greenhouse Gas Emissions Trend Energy Consumption Trends of the Top 12 Buildings Streetlight Energy Consumption RENEWABLE ENERGY UTILIZED OR PLANNED PLANNING STRUCTURE PLANNING ENERGY LEADER ENERGY TRAINING ENERGY PURCHASING Page i

3 4.5 PROGRAMS/PROCESSES/PROJECTS Programs Processes Projects Planned Projects EXECUTION MUNICIPAL LEVEL ASSET LEVEL EVALUATION ENERGY PLAN REVIEW ENERGY CONSUMPTION LIST OF INSERTED FIGURES Figure 1 Combined Energy Use... 7 Figure 2 Energy Use Trend by Type... 7 Figure 3 Natural Gas Facility Consumption... 8 Figure 4 GHG Emissions Top 12 Facilities Figure 5 Total Energy Use Top 12 Facilities Figure 6 Department Energy Breakdown LIST OF INSERTED TABLES Table 1 Total Energy Consumption Table 2 Green House Gas Emissions Factors... 6 Table 3 Energy Trend & Profile... 6 Table 4 Electricity Consumption... 8 Table 5 Natural Gas Consumption... 9 Table 6 Annual GHG Emissions... 9 Table 7 Energy Related Projects from 5 Year Capital Plan LIST OF APPENDICES Appendix A Recommendations from 2009 Energy Audits Page ii

4 1.0 INTRODUCTION has undertaken the development and implementation of an Energy Conservation and Demand Management Plan (the Plan) in accordance with Ontario Regulation 397/11. This 5 year Plan runs from 2014 to 2019, and a revised and updated Plan will be required by July 1, The Town is a small, picturesque municipality located in northern Simcoe County on the shores on Georgian Bay. It was formed in 1882 as a farming and lumber Town. Penetanguishene has a population of approximately 9,400. The area is abundant in natural beauty, known for its long secluded harbour connecting to Georgian Bay, and its expansive forests. Beyond tourism, key economic drivers include commercial retail, industry, and large health and security institutions. 1.1 PLAN STRUCTURE The structure of this Plan follows the framework laid out by Local Authority Services Energy Planning Tool. Local Authority Services (LAS) is a subsidiary of the Association of Municipalities of Ontario. The LAS framework involves 5 key steps: Commitment, Understanding, Planning, Execution, and Evaluation. Each step is outlined, in order, below. Page 1

5 2.0 COMMITMENT 2.1 DECLARATIONS is committed to the promotion of responsible energy management, through the implementation of economically viable energy efficiencies and environmental care in all municipal facilities. 2.2 VISION We are continually approaching energy management in a strategic manner allowing for the proactive pursuit of optimal energy solutions that lead to environmental, societal, and economic benefits. 2.3 GOALS To maximize the efficient use of the Town s fiscal resources. To minimize negative environmental impact of the Towns operations. 2.4 OVERALL TARGET By 2019 we will reduce the energy consumption per square foot of our municipal facilities by 15%, versus our 2012 figure. The annual target will be approximately 3% reduction per year for five years to achieve the overall 15% reduction. Reducing the overall energy consumption of the Town will also directly reduce the associated greenhouse gas emissions. 2.5 OBJECTIVES 1. To improve the energy efficiency of our facilities by utilizing best practices to reduce our energy consumption and mitigate the impact of energy cost increases. 2. To create a culture of energy conservation among the Town s staff. 3. To improve our municipal staff knowledge of energy consumption and energy conservation. 4. To reduce greenhouse gas emissions associated with our energy use. Page 2

6 3.0 UNDERSTANDING 3.1 MUNICIPAL ENERGY SITUATION uses two types of energy in its facilities: electricity and natural gas. Electricity is currently purchased through Local Authority Services (LAS) bulk purchase program. LAS, is a subsidiary of the Association of Municipalities of Ontario (AMO). The LAS program is intended to provide municipalities with a hedge against price fluctuations, and therefore save them money on electricity. Electricity for the Town is provided by two Local Delivery Companies (LDC s): Powerstream and Hydro One. Natural Gas is purchased through the LAS Bulk Natural Gas Program and delivered through Enbridge. Electricity is used in nearly all of the Town s facilities, while natural gas is used only at five (5) facilities with one additional facility set to begin using natural gas in HOW WE MANAGE ENERGY TODAY has a solid history in energy conservation initiatives. In 2008 the Town undertook the first large scale installation of LED streetlights in Ontario. The Town changed 37% of the streetlights, replacing the higher energy use metal halide and mercury vapour bulbs, with much more efficient LED technology. The Town also completed energy audits in 2009 on the Public Works Administration/Water Building and the Roads Office. The energy audits comprised of a thorough external and internal inspection of the buildings. The tools used were able to measure heat loss, air leakage, humidity/moisture issues, and identify areas requiring upgrades and repairs. Energy conservation projects completed since 2009 have been driven in part by Energy Audits and fall into the categories of lighting, heating/cooling/ventilation, insulation, windows, building envelope upgrades and motors/pumps. Projects completed to date include the following: LIGHTING UPGRADES LED Traffic signal upgrades upgraded existing traffic signals to LED fixtures (2007) LED Streetlight Pilot Program replaced mercury vapour and metal halide lights with LED streetlights Water and Roads Division garage upgraded partial lighting (2009) Library Building replaced light bulbs to more energy efficient lights (2011) Town Hall installed T8 lighting (2008) Page 3

7 Arena installed T5 lighting for the arena surface (2012) installed T8 lighting for the remainder of the building ( ) HEATING & COOLING EQUIPMENT Public Works Admin Building replaced air source heat pump and installed new work duct (2011) & separated the building into three heating/cooling zones for more efficient temperature control Roads Division Building replaced air source heat pump and installed new HVAC duct work (2010) Water Division - Payette Well Facility- installed variable frequency drive (VFD) on booster pump (2009) Museum Building installed new furnace for second floor (2009) installed new air conditioner on the extension of the building (2013) installed two new air conditioners for main floor and second floor (2014) Library Building replaced all three furnaces with higher efficiency units (2009) Town Hall - added a new HVAC (2008) Town Hall OPP Office installed new HVAC (2012) EQUIPMENT Philip H. Jones PCP installed variable speed drive pumps (2013) INSULATION Public Works Admin Building spray foam insulation added to underside of roof spray foam insulation added to Water Division garage walls Museum Building - added more insulation in main roof (2014) WINDOWS Public Works Roads Building - upgraded windows to address air tightness and glazing issues (2010) Museum Building installed new window at front of museum (2014) Page 4

8 3.2.6 BUILDING ENVELOPE Public Works Administration Building replaced entrance vestibule (2011) replaced overhead doors Public Works Roads Building performed maintenance and upgrades to block wall (2015 ongoing) replaced overhead doors ROOF UPGRADES Public Works Roads Building added spray foam air seal at roof/wall joint added sprayed foam insulation overtop of steel roofing (2014) Museum Building installed new enviroshake roof on office extension with new insulation (2009) installed new enviroshake roof for replica fire hall building (2013) 3.3 SUMMARY OF ENERGY CONSUMPTION AND GREENHOUSE GAS EMISSIONS The Town s energy consumption is largely concentrated in several high energy use facilities: the arena, the two sewage treatment plants, the Town Hall, and the Payette Well Facility. In order to track total energy consumption, the various energy types (electricity and natural gas) have been converted into a common unit of the Gigajoule (GJ). To get an idea of how much energy one (1) gigajoule is, the average house uses gigajoules of energy in a year. One Gigajoule is equivalent to 30 L of Gasoline, 39 L of Propane, or 278 kwh of electricity. Furthermore, 1 kwh is equal to using a 100 Watt Light bulb for 10 hours. For the calendar year 2013, the Town used 3,971,089 kwh of electricity and 100,788 m3 of Natural Gas. This translates to a total energy consumption of 18,169 GJ, as shown in Table 1 below. Table 1 Total Energy Consumption 2013 Energy Source Energy Amount Converted Amount (GJ) Electricity 3,971,089 kwh 14,296 Natural Gas 100,778 m 3 3,873 Total Energy Consumption 18,169 Source: Town of Penetanguishene data Page 5

9 3.3.1 GHG EMISSIONS Each energy source has a different amount of greenhouse gas emissions associated with its use. The greenhouse gas emissions associated with electricity are derived from the way in which the electricity is generated. In Ontario, electricity is generated from a variety of sources: coal (prior to 2014) nuclear, hydroelectric dams, wind, natural gas, and photovoltaic solar. The Ontario government pledged to move away from coal power and towards renewable and with the closing of Nanticoke Generating Station in the spring of 2014, the province s electric gird is now coal-free. The greenhouse gas emissions associated with electricity use continues to decline as the province transitions towards clean and renewable energy sources. The greenhouse gas emissions associated with combustible fuels such as Natural Gas are derived from the actual combustion of those fuels. Table 2 below shows the corresponding greenhouse gas emissions associated with electricity and natural gas. Table 2 Green House Gas Emissions Factors Energy Source Emission Factor Electricity kg CO2e/kWh Natural Gas kg CO2e/m 3 Source: NRCAN Energy Conversion and Emission Factors 3.4 TRENDS IN ENERGY CONSUMPTION TRENDS IN ENERGY CONSUMPTION Table 3 below provides a summary of the Town s energy consumption. In order to be able to see overall energy use, the table shows electricity consumption and natural gas consumption in the common unit of Gigajoules (GJ), along with their more traditional measurement units of kilowatt hours (kwh) and cubic metres (m3). Table 3 Energy Trend & Profile Electricity 3,153,340 kwh 3,765,516 kwh 3,971,089 kwh Natural Gas 121,103 m3 105,905 m3 100,778 m3 Electricity Converted to GJ 11,352 GJ 13,556 GJ 14,296 GJ Natural Gas Converted to GJ 4,654 GJ 4,070 GJ 3,873 GJ Total Combined Energy Consumption 16,006 GJ 17,626 GJ 18,169 GJ As can be seen in Figure 1, the Town s overall energy use has risen over the past three (3) years. Electricity comprises the majority of the Town s energy use, with natural gas accounting for a smaller portion. Page 6

10 Figure 1 Combined Energy Use 20,000 Combined Energy Use ,000 GJ 10,000 5,000 Natural Gas Electricity Year While the Town s total energy use has increased over the past 3 years, the increase has been driven by an increase in electricity consumption. Natural gas consumption has actually fallen during the same period. Figure 2 below shows the change. Figure 2 Energy Use Trend by Type Energy Use m3 140, , ,000 80,000 60,000 40,000 20, ,500,000 4,000,000 3,500,000 3,000,000 2,500,000 2,000,000 1,500,000 1,000, ,000 0 kwh Electricity (kwh) Natural Gas (m3) Year Page 7

11 3.4.2 ELECTRICITY CONSUMPTION TREND All of the Town s facilities used electricity for a portion of their energy needs. The Town s electricity consumption has increased over the past three years, rising 19% and 5% respectively in 2012 and The associated electricity consumption figures were 3,153,340 kwh in 2011, 3,765,515 kwh in 2012 and 3,971,089kWh in Table 4 Electricity Consumption Electricity (kwh) 3,153,340 3,765,515 3,971,089 Percentage Increase 19% 5% NATURAL GAS CONSUMPTION TREND Five of the Town s facilities also use natural gas, mainly for heating, but also for cooking and backup generators where applicable: the arena, the fire hall, the library, the museum, and the Town Hall. The Philip H Jones Pollution Control Plant (Main Street) will be adding natural gas in The Library uses natural gas for the furnaces and air conditioners. The largest user of natural gas, the arena, uses natural gas for heating and cooking. At the arena, it is used for the following: the boiler, the HVAC system, the furnace, the seating arena radiant heaters, hot water tanks, the dehumidifier, and at the arena s snack bar. The newly constructed fire hall uses natural gas for the hot water tank and the back-up generator. The museum uses natural gas for the hot water tank only, while the Town Hall uses natural gas for its HVAC systems, and its back-up generator. Figure 3 below shows the natural gas consumption trend for each of the five buildings. Figure 3 Natural Gas Facility Consumption Natural Gas Consumption ( ) m Arena Fire Hall Library Museum Townhall *Source: Energy Consumption Data from Town of Penetanguishene Page 8

12 The overall consumption trend over the past three (3) years is downward: the Town is using less natural gas each year (see Table 5 below). While some facilities consumption has fluctuated, the largest natural gas using facility the arena has used less every year since Overall, the Town used 13% less natural gas in 2012 compared to 2011, and 5% less in 2013 compared to Table 5 Natural Gas Consumption Natural Gas Consumption (in m 3 ) 121, , ,778 Change over previous year -13% -5% GREENHOUSE GAS EMISSIONS TREND Greenhouse gas (GHG) emissions are measured in equivalent tonnes of carbon dioxide (CO2e). As outlined in Table 6 below, the Town s GHG emissions associated with facility energy use increased 7% and 2% respectively in 2012 and 2013, with the resulting GHG emissions being 576 tonnes in 2011, 614 tonnes in 2012 and 627 tonnes in [Note: 1 Tonne equals 1000 kg] Table 6 Annual GHG Emissions Combined GHG Emissions (MT C0 2 e) Change over previous year +7% +2% The total GHG emissions for each of the Top 12 buildings are shown in the Figure 4 below. Page 9

13 Figure 4 GHG Emissions Top 12 Facilities kg CO2e GHG Emission ( ) ENERGY CONSUMPTION TRENDS OF THE TOP 12 BUILDINGS Figure 5 below shows the three-year energy trend of Penetanguishene s top twelve facilities, in terms of energy use. Some facilities have reduced their energy use since 2011 such as: the arena, the sewage treatment plant (Fox), the town hall, the fire hall, and the library. However, a handful of facilities have increased their energy use dramatically which resulted in an overall increase for the Town. Those facilities include: the main sewage treatment plant and the Payette pump station. The Main Street sewage treatment plan has been under construction (expansion) since The increased energy use may be associated with the construction. Page 10

14 Figure 5 Total Energy Use Top 12 Facilities 6000 Combined Energy Use ( ) GJ *Source: Energy Consumption Data from Town of Penetanguishene Figure 6 below shows a breakdown of energy use by department. The water and wastewater facilities use a significant amount of energy due to the pumping and treatment equipment and the 24/7 nature of these facilities. The arena also uses a significant amount of energy, as required for heating and cooling the facility (often at the same time), along with ice making, rink maintenance, and lighting. Page 11

15 Figure 6 Department Energy Breakdown Total Energy Average ( ) 5% Parks Fire Hall 16% 24% Library Museum 5% Townhall 37% 7% 4% 2% Waste Water Water Public Works - Roads and Water Buildings STREETLIGHT ENERGY CONSUMPTION was one of the first municipalities in Ontario to begin switching to LED streetlights. The Town received provincial funding to be able to complete the replacement of approximately 37% of the streetlights. The Town installed the LED bulbs in two large installations, focusing on replacing the largest energy using bulbs, mercury vapour and metal halide. A total of 346 LED streetlights were installed in the two installations, which represented approximately 36% of the Town s total streetlights. The Town received $475,000 from the Rural Infrastructure Investment Initiative Fund to complete the installation. 3.5 RENEWABLE ENERGY UTILIZED OR PLANNED While the Town has reviewed several solar photovoltaic projects in the past, it currently utilizes no renewable energy. In addition, the Town currently has no renewable energy projects planned. Page 12

16 4.0 PLANNING 4.1 STRUCTURE PLANNING The 5-year Energy Conservation and Demand Management Plan includes both short term and mid-term strategies. Short-term is defined as years one through three of the Plan. Short-term focus areas will include: Establishing an Energy Management Team; Developing an energy consumption tracking and reporting process; Completing training and education of Town staff; Implementing no cost & low cost programs, processes, and projects; and Planning for larger expenditures in future years Mid-term is defined as years four and five of the Plan. Mid-term focus areas will be: Higher cost programs, processes, and projects 4.2 ENERGY LEADER Penetanguishene will develop a more focused effort on energy management through the creation of an energy management team. This team will be responsible for the implementation of the Plan and the review of corporate energy management strategies. The team will meet on a quarterly basis to review energy consumption reports, provide updates on energy initiatives, and discuss successes and challenges. Penetanguishene has already demonstrated initiative and progressive action with the LED Streetlight program, and Town Staff have begun to adapt and incorporate energy planning into each department. 4.3 ENERGY TRAINING Penetanguishene will train staff on energy use and energy conservation. General training will be offered for all staff, while additional, more technical training will be offered for operations staff. Natural Resources Canada s Dollars to Sense energy workshops will be considered as a training option where applicable. Page 13

17 4.4 ENERGY PURCHASING Penetanguishene will continue to purchase electricity through Local Authority Services (LAS) Electricity Program and natural gas through LAS s Natural Gas Procurement Program. LAS s program has the ability to purchase large bulk quantities for over a hundred municipalities resulting in significant savings for its participants. The Town saved 11.4% from the LAS Electricity Procurement Program from the period of July 2013 to June This translated into annual savings of $56,242, which included $6,895 savings from the streetlights accounts. During the previous 12 month period, the LAS program resulted in electricity savings of $48,020. The Town also recently signed up with LAS s Natural Gas Procurement Program, resulting in additional savings for the Town s five facilities which use natural gas. 4.5 PROGRAMS/PROCESSES/PROJECTS Energy conservation initiatives will take the form of programs, processes, and projects. initiatives to be considered over the duration of this Plan. Below is a list of PROGRAMS Continue with the ongoing implementation recommendations from the 2009 Public Works energy audits update cost and payback as necessary particularly for larger expenditure items. See Appendix A for a summary of Energy Audit Recommendations. Utilize the 2009 energy audit recommendations to develop similar initiatives in similar un-audited buildings. Investigate use of LAS free energy audit services for unaudited buildings. Continue with streetlight replacement program upgrade to LED as streetlights require replacement. Host quarterly Lunch & Learn sessions for Town staff to support the creation of a culture of conservation Investigate the possibility of participation in a demand management program to conserve energy and save money by reducing demand on the provincial electricity grid during peak periods. Develop stories/case studies of successful Town energy initiatives and share with entire Town staff and community PROCESSES Implement a process to track on a monthly basis energy use and costs for each building, and provide year over year comparative results to the operations team. Implement regular review of energy consumption data by appropriate Town staff members. Page 14

18 Utilize the LAS Audit++ and Energy Performance Benchmark Best Practice Reports as reference materials for best practices. Implement building start-up and shut-down schedules, where appropriate, and add into standard work procedure for key building personnel to eliminate waste and maximize equipment efficiencies. Ensure no build-up of dirt and dust on backside coils of vending machines and unplug them during offseason if possible. Renegotiate with suppliers for vending machine models with motion activated lighting. Use power bars on PCs and turn off at night, where possible. Make use of free cooling in summer by programming building control system to bring in 100% outdoor air at night. Turn off printers and copiers at night and on weekends, where possible. Adapt energy use to reflect Time-of-Use periods where possible. Shifting energy use to off-peak periods would use the same amount of energy but be more cost effective PROJECTS Complete an internal review of all un-audited Town buildings to confirm: type of lighting, type of heating/cooling, type of thermostats, presence of exhaust fans, presence/type/age of pumps, presence/condition of weather stripping and floor sweeps, and other equipment that utilizes energy. Continually investigate and pursue energy conservation funding opportunities, such as the Save ON Energy Small Business Lighting program. Additional potential sources of funding can be found at: Implement real-time monitoring at the highest energy use facilities. Use the baseline energy consumption data to complete benchmarking. Complete an analysis of energy demand for the various Town buildings including drivers of demand and associated costs. Install a system to automatically turn off heating/cooling when exterior overhead doors are left open. Investigate using free computer programs to automatically shut down computers when not in use. Install occupancy (motion) sensors for lights and heating, where appropriate. Enhance building envelope by replacing caulking, weather-stripping, and insulation where appropriate. Page 15

19 Install separate meters or sub-meters for facilities that are shared to allow for accurate division of energy consumption. Investigate the re-commissioning of buildings that have experienced significant change in use, space configuration, or expansion since their construction. Invest in plug-load power monitors to be shared between facilities PLANNED PROJECTS In addition to the projects listed above, Table 7 below provides a summary of energy related projects currently found in the Town s 5 Year Capital Plan. Page 16

20 Table 7 Energy Related Projects from 5 Year Capital Plan Year Facility/Department Project Description Cost 2015 Public Works - Main Replace and upgrade Mydrastral Secondary STP Effluent Pump $55,000 Public Works - Fox Upgrade Pumps to efficient Variable 2015 STP Frequency Drives $7, Library Replace air conditioner $14, Public Works Payette Pumpstation Construction phase of the Payette water Storage Upgrades $100, Arena Purchase new, more efficient ice resurfacing machine $8, Museum Replace furnace with new, more efficient model $6, Townhall Install new doors for old Fire Hall, reduce heat loss $30, Design, Upgrade, and Retrofit the Navy Lane Public Works pump station to include new, efficient and pump station properly sized pumps $150, Public Works - Fox Replace the return activated sludge pump with STP new, more efficient pumps $10, Arena Install new, more efficient HVAC rooftop units $20, Install energy control systems to reduce Arena $28,000 energy demand and consumption 2016 Arena Re-seal the aging condenser joints $12, Insulate the museum building roof and repair Museum west side to address building envelope issues $10, Public Works - Main Replace sludge loading pump with new, more STP efficient pumps $15, Upgrade and replace the roof membrane, Arena $220,000 opportunity to increase insulation and building 2017 Arena envelope Replace hot water tank with new and efficient model $10, Arena Replace and upgrade the compressor $55, Library Replace and upgrade the outer front doors $20, Museum Re-shingle roof $22, Public Works STP Replace the two filter compressors $30, Public Works - Fox Replace sludge loading pump with new, more STP efficient pumps $15, Public Works- Replacement - Two (2) Compressors at Main Street Main Street STP STP $30, Public Works- Robert Street Replacement Column Pump at Robert Street West Sanitary Pumpstation $20, West Public Sanitary Works - Fox Upgrade and replace the current dechlorination system STP $1,000, Public Works- Road Construction - Expansion of Roads Division Garage - Wash Bay $600,000 Page 17

21 5.0 EXECUTION 5.1 MUNICIPAL LEVEL On an annual basis the Town s Energy Team will develop a new Energy Action Plan, made up of a variety of programs, processes and projects. Action Plan items will be limited to one year for completion. Larger action items can be broken down into smaller steps to meet the one year timeline. By limiting actions to a single year, it facilitates forward movement on many projects simultaneously and allows for the incorporation of new information or technologies that may come available during the term of the Plan. While the Energy Conservation and Demand Management Plan is a snapshot of previously completed projects and planned energy projects, the Action Plan is essentially a to-do list. The Energy Team will implement and monitor the energy projects of the Town and will report annually to municipal council on its successes and challenges in implementing the Energy Conservation and Demand Management Plan. The Energy Team will also review and update the Plan every 5 years as legislated by the Green Energy Act. 5.2 ASSET LEVEL Once the annual Energy Action Plan is completed, it will be the responsibility of the operations team to implement the various action items. In particular, the individual(s) with responsibility for the specific buildings will be responsible for the implementation of the initiatives associated with those buildings. Tracking and reporting will be included in the implementation to allow for measurement of the impact of the actions. Facility energy use will be tracked and communicated on a regular basis to those responsible for the various assets. In addition, the department heads will review current operating practices of the facilities to ensure consistency across the Town. Page 18

22 6.0 EVALUATION 6.1 ENERGY PLAN REVIEW The Energy Management Team will review progress towards the overall goals and objectives of the Energy Conservation and Demand Management Plan on an annual basis. In addition, progress on the annual Energy Action Plan initiatives will be tracked and reviewed by the Energy Management Team on a quarterly basis. The regularly tracked energy consumption data will be used to evaluate the success of the implemented energy initiatives. To the extent possible, the costs and resulting energy and greenhouse gas savings of each energy initiatives will be calculated as part of the evaluation. The actions that were not completed by year s end will be re-evaluated for the potential inclusion in the following year s Energy Action Plan. By creating single-year Energy Action Plans, the Town will be able to adjust speed, size, and complexity of energy project based on current and future internal and external conditions. 6.2 ENERGY CONSUMPTION The total energy consumption by the municipality is represented in gigajoules (GJ). Both electricity consumption (in kwh) and natural gas consumption (in m3) have been converted into GJ for ease of comparison. As previously stated, the Town used 3,955,132 kwh of electricity and 100,778 m3 of Natural Gas in 2013, which equates to a total energy consumption of 18,169 GJ. Page 19

23 Appendix A Recommendations from 2009 Energy Audits

24 Recommendations from 2009 Energy Audits Projects - 24 Centennial Initial Costs Annual Savings Simple Electricity (GJ) Payback Windows $ 2, $ Overhead Door systems $30, $8, Roof Roof Membrane and Insulation $52, $2, Wall Assemblies $41, $1, Air Leakage $4, $10, Heating Air Source Heat pump $8, $6, Complete Retro-fit $135, $16, Projects - 22 Centennial Initial Costs Annual Savings Simple Electricity (GJ) Payback Windows $4, $ Overhead Door systems $18, $4, Roof $30, $6, Block Wall Assemblies $17, $9, Air Leakage $6, $6, Heating Air Source Heat pump $18, $1, Lighting $2, $ Complete Retro-fit $84, $16,

County of Perth. Energy Conservation and Demand Management Plan

County of Perth. Energy Conservation and Demand Management Plan County of Perth Energy Conservation and Demand Management Plan 2014 Contents Introduction 2 Perth County Courthouse 3 24 St. Andrews 5 5 Huron Street 6 Listowel EMS Base 7 St. Mary s EMS Base 8 Mitchell

More information

The Municipality of Leamington

The Municipality of Leamington The Five Energy Conservation and Demand Management Plan July, 214 Table of Contents Page # Section 1- Introduction 1.1 Background... 3 1.2 Purpose... 3 1.3 Approach... 4 Section 2- Our Organization 2.1

More information

The Municipality of Leamington

The Municipality of Leamington The Five Energy Conservation and Demand Management Plan July, 214 Table of Contents Page # Section 1- Introduction 1.1 Background... 3 1.2 Purpose... 3 1.3 Approach... 4 Section 2- Our Organization 2.1

More information

Lambton Kent District School Board

Lambton Kent District School Board Lambton Kent District School Board Management and Demand Management Plan June 24, 2014 1 Table of Contents Table of Contents Conservation and Demand Management Plan... 3 Introduction... 3 The Green Act...

More information

Energy Conservation and Demand Management Plan. Township of Wellesley: Developed by Wendy Smith, Administrative Assistant Fire/Recreation

Energy Conservation and Demand Management Plan. Township of Wellesley: Developed by Wendy Smith, Administrative Assistant Fire/Recreation Energy Conservation and Demand Management Plan Township of Wellesley: 2014-2019 The Township of Wellesley will strive to continually reduce our total energy consumption and associated greenhouse gases

More information

Energy Conservation & Demand Management Plan. Municipality of Strathroy-Caradoc

Energy Conservation & Demand Management Plan. Municipality of Strathroy-Caradoc Energy Conservation & Demand Management Plan Energy Conservation & Demand Management Plan 2014-2020 1 Contents Introduction... 2 Goals & Objectives... 3 Overview of Facilities & Usage... 4 Commitment...

More information

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT 2015 16 TABLE OF CONTENTS 1. SUMMARY 4 2. INTRODUCTION 6 3. BACKGROUND 8 4. GREENHOUSE GAS EMISSION IN 2014/2015 10 5. ENERGY CONSUMPTION IN 2014/2015

More information

ENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company.

ENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company. Report To: Mr. John Smith Smith Printing Company ENERGY AUDIT 123 Main Street Mississauga, Ontario January 1, 2009 120 Carlton Street, Suite 212 Toronto, Ontario M5A 4K2 Tel 416-964-3246 Toll Free 1-866-964-3246

More information

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT Report Clayville Elementary School October 2016 3 George Washington Highway, Clayville, RI 02815 Clayville Elementary School Summary of Findings On behalf of the School Building Authority at Rhode Island

More information

Energy Conservation Management Plan

Energy Conservation Management Plan Energy Conservation Management Plan June 2014 Municipality of Port Hope The Municipality s Energy Conservation Management Plan (ECMP) is the basis for implementation of improvements to our facilities and

More information

TOWNSHIP OF ADELAIDE METCALFE

TOWNSHIP OF ADELAIDE METCALFE TOWNSHIP OF ADELAIDE METCALFE (CDM) ENERGY CONSERVATION AND DEMAND MANAGEMENT PLAN TO 2019 Prepared & Submitted: June 30, Fran I. Urbshott, AMCT Township of Adelaide Metcalfe Energy Conservation and Demand

More information

Corporate Energy Conservation and Demand Management Plan 2014

Corporate Energy Conservation and Demand Management Plan 2014 Transportation and Waste Department Facilities Division June 18 th, 2014 1 Table of Contents 1 Current State of Corporate Energy Management... 4 1.1 Energy Data Management... 4 1.2 Energy Supply Management...

More information

ENERGY MANAGEMENT PLAN JUNE UPDATED OCTBER 2017.

ENERGY MANAGEMENT PLAN JUNE UPDATED OCTBER 2017. ENERGY MANAGEMENT PLAN JUNE 214. UPDATED OCTBER 217. Energy Management Plan Reporting update, October 217 As of October 217, Oxford County has provided a reporting update to the original Energy Management

More information

Town of Midland Energy Conservation and Demand Management Plan For the Period 2014 to 2019

Town of Midland Energy Conservation and Demand Management Plan For the Period 2014 to 2019 Town of Midland Energy Conservation and Demand Management Plan For the Period 2014 to 2019 July 2014 Page 2 of 22 Table of Contents: Introduction Page 3 ENERGY MANAGEMENT COMMITMENT Commitment Page 4 Vision

More information

SUBJECT: Annual Energy and Carbon Report for Burlington

SUBJECT: Annual Energy and Carbon Report for Burlington Page 1 of Report CW-25-17 SUBJECT: Annual Energy and Carbon Report for Burlington TO: FROM: Committee of the Whole Capital Works Report Number: CW-25-17 Wards Affected: Not applicable File Numbers: 210-09

More information

Energy Management Plan. Township of Black River-Matheson

Energy Management Plan. Township of Black River-Matheson From: 2014-01-01 to: 2018-12-31 Commitment Management Plan - Declaration of Commitment: Council Resolution: It is the commitment of Council for the Township of Black River-Matheson to allocate resources

More information

Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits

Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits AEP Ohio Customer Seminar Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits Presented by: Julie Birchfield Customer Manager Energy Optimizers, USA May, 2018 Test your Energy IQ 11

More information

Energy Reduction Strategy Through 2020

Energy Reduction Strategy Through 2020 Through 2020 Revised: August 2017 Executive Summary Auburn University is a land, sea and space grant university established in 1856. The university consists of 11,629,000 square feet on 1,840 acres and

More information

BC Hydro 2015 Carbon Neutral Action Report. BC Hydro 2015 Carbon Neutral Action Report

BC Hydro 2015 Carbon Neutral Action Report. BC Hydro 2015 Carbon Neutral Action Report This Carbon Neutral Action Report for the period January 1, 2015 to December 31, 2015 summarizes our emissions profile, the total offsets purchased to reach net zero emissions, the actions we have taken

More information

Toronto Hydro 500/500. Renewable Power and Conservation Plan Summary. October 16, 2009

Toronto Hydro 500/500. Renewable Power and Conservation Plan Summary. October 16, 2009 Toronto Hydro 500/500 Renewable Power and Conservation Plan Summary October 16, 2009 This document is for discussion purposes only, consistent with Toronto Hydro's strategy, but subject to regulatory approval.

More information

2015 Corporate Energy Consumption Report. london.ca. City of London. August 2016

2015 Corporate Energy Consumption Report. london.ca. City of London. August 2016 2015 Corporate Energy Consumption Report City of London August 2016 london.ca Contents 1. Background... 3 2. Corporate Energy Consumption Overview... 3 2.1 Methods of Measurement... 4 2.2 Limitations of

More information

Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007

Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007 Hawaii Energy Policy Forum and Energy Industries Energy by Example Audit Awards Status Report October 2006-November 2007 Introduction In August 2006, the Hawaii Energy Policy Forum (Forum) invited over

More information

TRW ENERGY AUDIT CHALLENGE

TRW ENERGY AUDIT CHALLENGE ALTERNATIVE ENERGY DOSSIN TRW ENERGY AUDIT CHALLENGE The chart above is based on current data observed and collected nationally by Energy Efficient Solutions, www1.eere.energy.gov/buildings/energysmartschools/plan.html.

More information

A l b e r t a G r e e n Condo G u i d e

A l b e r t a G r e e n Condo G u i d e A l b e r t a Green Condo Guide Alberta Green Condo Guide Funding for this initiative has been made available through the Alberta Real Estate Foundation (www.aref.ab.ca) and the City of Calgary (www.calgary.ca).

More information

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT 2014 2015 TABLE OF CONTENTS 1. SUMMARY 4 2. INTRODUCTION 6 3. BACKGROUND 8 4. GREENHOUSE GAS EMISSION IN 2014/2015 10 5. ENERGY CONSUMPTION IN 2014/2015

More information

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan

WAKE TECHNICAL COMMUNITY COLLEGE SUSTAINABLE ENERGY PLAN. Energy Plan Energy Plan 1 EXECUTIVE SUMMARY SCORECARD RESULTS An assessment of current energy management efforts was performed; current performance falls into all categories on the SEP-Performance Scorecard (Appendix

More information

Sonoma County Energy Independence Program APPENDIX A ELIGIBLE IMPROVEMENTS

Sonoma County Energy Independence Program APPENDIX A ELIGIBLE IMPROVEMENTS Sonoma County Energy Independence Program APPENDIX A ELIGIBLE IMPROVEMENTS The Sonoma County Energy Independence Program offers SCEIP funds for a number of equipment types, including water conservation

More information

A GUIDE TO ENERGY MANAGEMENT. U.S. Environmental Protection Agency ENERGY STAR

A GUIDE TO ENERGY MANAGEMENT. U.S. Environmental Protection Agency ENERGY STAR A GUIDE TO ENERGY MANAGEMENT U.S. Environmental Protection Agency ENERGY STAR 1 Agenda ENERGY STAR Overview Energy Management Guidelines ENERGY STAR Tools & Resources Building Upgrade Manual Energy Performance

More information

Bryant University s Energy Guidelines for Sustainability

Bryant University s Energy Guidelines for Sustainability Bryant University s Energy Guidelines for Sustainability Rising carbon emissions have a disruptive impact on global climate patterns and pose a risk to the security of communities around the world. The

More information

A Plan for a Sustainable Toronto Discovery District

A Plan for a Sustainable Toronto Discovery District A Plan for a Sustainable Toronto Discovery District Judy Simon, IndEco Strategic Consulting ABSTRACT The members of the Toronto Discovery District (TDD), located in downtown, Toronto Canada, have developed

More information

The Cities for Climate Change Protection. Local Action Plan for C02 Reductions Bathurst, New Brunswick

The Cities for Climate Change Protection. Local Action Plan for C02 Reductions Bathurst, New Brunswick The Cities for Climate Change Protection Local Action Plan for C02 Reductions Bathurst, New Brunswick First Report: May 30, 2002 Updated: October 2007 This report has been produced by Bathurst Sustainable

More information

2017 Corporate Energy Consumption and Activities Report City of London. August london.ca

2017 Corporate Energy Consumption and Activities Report City of London. August london.ca 2017 Corporate Energy Consumption and Activities Report City of London August 2018 london.ca Contents 1. Background... 1 2. Corporate Energy Consumption Overview... 1 2.1 Methods of Measurement... 3 2.2

More information

City of Toronto Tower Renewal Program

City of Toronto Tower Renewal Program Photo by Jesse Colin Jackson City of Toronto Tower Renewal Program CAC Presentation October 6, 2016 1 Tower Renewal A program to drive broad environmental, social, economic, and cultural change by improving

More information

Conservation & Demand Management Plan

Conservation & Demand Management Plan Conservation & Demand Management Plan Nipigon District Memorial Hospital www.ndmh.ca 397-11: Phase 2 2014-07-04 1 Executive Summary The following Energy Conservation and Demand Management Plan is written

More information

The Island University. A Campus of The Texas A&M University System Corpus Christi, Texas

The Island University. A Campus of The Texas A&M University System Corpus Christi, Texas ! The Island University A Campus of The Texas A&M University System Corpus Christi, Texas This document was prepared to comply with the Governor s Executive Order RP49 - October 27, 2005 relating to energy

More information

Community and Corporate Services Committee. SUBJECT: Report recommending approval of 2013 Corporate Energy Management Program update - Facilities

Community and Corporate Services Committee. SUBJECT: Report recommending approval of 2013 Corporate Energy Management Program update - Facilities Page 1 of Report CSI-05-14 TO: FROM: Community and Corporate Services Committee Corporate Strategic Initiatives SUBJECT: Report recommending approval of 2013 Corporate Energy Management Program update

More information

Raymore-Peculiar Schools. Energy Management Program Guidelines

Raymore-Peculiar Schools. Energy Management Program Guidelines Raymore-Peculiar Schools Energy Management Program Guidelines Raymore-Peculiar Schools Energy Management Program Purpose While schools cannot operate without lights, heating and cooling, they can reduce

More information

THE CORPORATION OF THE TOWN OF TECUMSEH. Parks and Recreation Report No. 32/13

THE CORPORATION OF THE TOWN OF TECUMSEH. Parks and Recreation Report No. 32/13 THE CORPORATION OF THE TOWN OF TECUMSEH Parks and Recreation Report No. 32/13 TO: FROM: Mayor and Members of Council Ray Hammond, Facilities Manager DATE: SUBJECT: Green Energy Act, O. Reg. 397/11 Update

More information

MUNICIPALTY OF HURON EAST ENERGY CONSERVATION AND DEMAND MANAGEMENT PLAN

MUNICIPALTY OF HURON EAST ENERGY CONSERVATION AND DEMAND MANAGEMENT PLAN MUNICIPALTY OF HURON EAST ENERGY CONSERVATION AND DEMAND MANAGEMENT PLAN 2014 2019 1 Municipality of Huron East Energy Consumption and Demand Management Plan July 2014 Background Green Energy Act and Ontario

More information

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges

More information

Technology and Disruptive Innovation in the Natural Gas Sector

Technology and Disruptive Innovation in the Natural Gas Sector Technology and Disruptive Innovation in the Natural Gas Sector Technology Innovation & Policy Forum 2016; Waterloo November 24, 2016 David Teichroeb Business Development; Low Carbon Energy Strategies Net-Zero

More information

Energy Benchmarking Report for Mt. Pleasant Elementary School. Millville, NJ

Energy Benchmarking Report for Mt. Pleasant Elementary School. Millville, NJ Energy Benchmarking Report for Mt. Pleasant Elementary School Millville, NJ (for the period: June 1, 2008 through May 31, 2009) Prepared by: Background & Findings: The New Jersey Clean Energy Program (NJCEP)

More information

Energy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007

Energy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007 Energy Auditing for Schools Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007 Schools Consumption breakdown 19% 6% 9% Space Heating 46% Water Heating Lighting Cooling 20%

More information

Energy Management Plan

Energy Management Plan Energy Management Plan June 2014 City of St. Catharines Page 1 TABLE OF CONTENTS Corporate Commitment 3 1 Introduction 4 1.1 Background 4 1.2 Targets 6 1.3 Legislation Compliance 7 2 Roles and Responsibilities

More information

The Value of Energy Ontario

The Value of Energy Ontario The Value of Energy Ontario Canadians for Affordable Energy: Household Research Series 1 NOVEMBER 2017 Canadians for Affordable Energy is a national non-profit organization. We promote the benefits of

More information

PARK DISTRICT ENERGY WALK-THROUGH. Andy Robinson, Training and Education, SEDAC

PARK DISTRICT ENERGY WALK-THROUGH. Andy Robinson, Training and Education, SEDAC PARK DISTRICT ENERGY WALK-THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy

More information

Nancy Kinner Donna Miller David Wetherbee Bath, ME June 24, 2018

Nancy Kinner Donna Miller David Wetherbee Bath, ME June 24, 2018 Grace Episcopal Church Energy for the Future Nancy Kinner Donna Miller David Wetherbee Bath, ME June 24, 2018 Grace: Energy for the Future Series 3 Meetings to Discuss Grace s Future Energy Needs Sunday,

More information

Energy Conservation & Demand Management Plan

Energy Conservation & Demand Management Plan Collingwood Public Utilities Energy Conservation & Demand Management Plan 2014-2019 Introduction Collingwood Public Utilities spends $1,204,861.62 per year on energy costs at 12 building and facilities,

More information

Establishing a Baseline, Energy Audits and Energy Star s Portfolio Manager

Establishing a Baseline, Energy Audits and Energy Star s Portfolio Manager Establishing a Baseline, Energy Audits and Energy Star s Portfolio Manager Glenn Barnes Environmental Finance Center University of North Carolina at Chapel Hill 919-962-2789 glennbarnes@sog.unc.edu Energy

More information

SUSTAINABILITY An Energy & Emissions Case Study

SUSTAINABILITY An Energy & Emissions Case Study SUSTAINABILITY An Energy & Emissions Case Study 1 Energy & Emissions Case Study WASHINGTON UNIVERSITY IN ST. LOUIS has a history of responsibly investing resources to increase the efficiency of our operations

More information

ENERGY AND WATER CONSERVATION AND DEMAND MANAGEMENT PLAN

ENERGY AND WATER CONSERVATION AND DEMAND MANAGEMENT PLAN ENERGY AND WATER CONSERVATION AND DEMAND MANAGEMENT PLAN 2014 2019 CONTENTS EXECUTIVE SUMMARY... 3 1. CENTENNIAL COLLEGE - DISTRIBUTION OF ENERGY CONSUMPTION IN 2012... 4 1.1. Overview of Centennial College

More information

ILLINOIS ENERGY NOW Energy Efficiency Incentives for State Facilities. December 2016

ILLINOIS ENERGY NOW Energy Efficiency Incentives for State Facilities. December 2016 ILLINOIS ENERGY NOW Energy Efficiency Incentives for State Facilities December 2016 1 ILLINOIS OFFICE OF ENERGY & RECYCLING Business Development Community Development Illinois Department of Commerce &

More information

Corporate Energy Management Plan

Corporate Energy Management Plan City of Kawartha Lakes Corporate Energy Management Plan 2016-2021 Page 1 Corporate Energy Management Plan Table of Contents Introduction... 3 Executive Summary...4 City of Kawartha Lakes Baseline Consumption...5

More information

CSIRO Energy Centre Newcastle, New South Wales, Australia

CSIRO Energy Centre Newcastle, New South Wales, Australia CSIRO Energy Centre Newcastle, New South Wales, Australia Trevor Moody BE, BEc Commonwealth Scientific and Industrial Research Organisation (CSIRO), Australia. PO Box 227 Dickson ACT 2602 Australia. Telephone:

More information

QUEEN S UNIVERSITY GREENHOUSE GAS INVENTORY REPORT 2017

QUEEN S UNIVERSITY GREENHOUSE GAS INVENTORY REPORT 2017 QUEEN S UNIVERSITY GREENHOUSE GAS INVENTORY REPORT 2017 September 2018 INTRODUCTION In 2010, Queen s University signed the University and College Presidents Climate Change Statement of Action for Canada,

More information

ELEMENTARY SCHOOL ENERGY AUDIT CHALLENGE

ELEMENTARY SCHOOL ENERGY AUDIT CHALLENGE ELEMENTARY SCHOOL ENERGY AUDIT CHALLENGE ALTERNATIVE ENERGY DOSSIN Table of Contents Introduction Page 2 General Questioner Audit (Step 1).. Page 4 Energy Basics.. Page 6 Tracking Energy.. Page 9 Recording

More information

The City of Hamilton ENERGY REPORT 2010

The City of Hamilton ENERGY REPORT 2010 The City of Hamilton ENERGY REPORT 2010 The City of Hamilton Year End Energy report prepared by the Public Works Office of Energy Initiatives, February 2011. amilton ublic Providing services that bring

More information

Least Cost Path to Achieving 50% Reduction in Residential Energy Use (in Heating Climates)

Least Cost Path to Achieving 50% Reduction in Residential Energy Use (in Heating Climates) Least Cost Path to Achieving 50% Reduction in Residential Energy Use (in Heating Climates) Jan Harris, X Prize Foundation Michael Blasnik, Blasnik and Associates ABSTRACT This paper describes the findings

More information

Interim report 2016 progress on the 5-Year Energy Management Plan

Interim report 2016 progress on the 5-Year Energy Management Plan Waypoint Centre for Mental Health Care 500 Church Street, Penetanguishene ON L9M 1G3 705-549-3181 www.waypointcentre.ca Interim report 2016 progress on the 5-Year Energy Management Plan Waypoint Centre

More information

Energy Reduction Programs: Understanding, Implementing & Delivering. PL Energy Services

Energy Reduction Programs: Understanding, Implementing & Delivering. PL Energy Services Energy Reduction Programs: Understanding, Implementing & Delivering PL Energy Services PL Energy Services Value to Condominium Directors Control Maintenance Fees Maximize Rebates Measurement & Verification

More information

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68%

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68% Address 666 Burrard St, Vancouver Management QuadReal Property Group Type of Building Office Year of Construction 1984 Number

More information

ENERGY EFFICIENCY AND CONSERVATION

ENERGY EFFICIENCY AND CONSERVATION Chapter 3 Greenhouse Gas Reduction Measures ENERGY EFFICIENCY AND CONSERVATION Citrus Heights has a substantial opportunity to reduce communitywide GHG emissions related to energy use in residential and

More information

Energy Efficiency in Multi-Tenant Office Buildings

Energy Efficiency in Multi-Tenant Office Buildings Energy Efficiency in Multi-Tenant Office Buildings Presented by David Herman, PE, LEED AP Principal, EnerG Associates, LLC 3/10/2015 1 Learning Objectives 1. List the principal sources and uses of energy

More information

Executive Summary Energy Conservation and Demand Management (ECDM) Plan

Executive Summary Energy Conservation and Demand Management (ECDM) Plan Appendix A Executive Summary Energy Conservation and Demand Management (ECDM) Plan The City of Toronto has been committed to reduction of greenhouse gas emissions, generation of renewable energy and improvement

More information

Greater Essex County District School Board Energy Conservation and Demand Management Plan. June 2014

Greater Essex County District School Board Energy Conservation and Demand Management Plan. June 2014 Greater Essex County District School Board Energy Conservation and Demand Management Plan June 2014 1 Table of Contents Greater Essex County District School Board... 4 Energy Conservation and Demand Management

More information

FUTURE OF HOME HEATING

FUTURE OF HOME HEATING FUTURE O F H O M E HEATIN G FUTURE OF HOME HEATING APRIL 218 A COLLABORATION The Advanced Energy Centre (AEC) completed this project in partnership with Enbridge Gas Distribution Inc. This project includes

More information

PACE for Homeowners. Website: paceab.green October 29, 2017

PACE for Homeowners. Website: paceab.green October 29, 2017 PACE for Homeowners Website: paceab.green October 29, 2017 Property Assessed Clean Energy, better known as PACE, is a financing innovation that has revolutionized the way property owners upgrade their

More information

SUMMARY OF SERVICES & INCENTIVES

SUMMARY OF SERVICES & INCENTIVES SMALL BUSINESS PROGRAM 2017 SUMMARY OF SERVICES & INCENTIVES Effective through December 31, 2017 Last updated February 1, 2017 EFFICIENCY INCENTIVES SUMMARY The Focus on Energy Small Business Program offers

More information

Farm Energy IQ. Farms Today Securing Our Energy Future. Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station

Farm Energy IQ. Farms Today Securing Our Energy Future. Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farms Today Securing Our Energy Future Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy IQ Farm Energy Efficiency Principles Tom Manning,

More information

Energy Efficiency & Renewable Energy Resources

Energy Efficiency & Renewable Energy Resources Energy Efficiency & Renewable Energy Resources Discuss with your table partner: What is the difference between energy conservation and energy efficiency? Give an example of each. Improving the percentage

More information

Texas Tech University Energy Savings Program October 2011 Update

Texas Tech University Energy Savings Program October 2011 Update Texas Tech University Energy Savings Program October 2011 Update The Texas Tech Energy Savings Update is being submitted in accordance with Governor s Executive Order RP 49, Electric Conservation by State

More information

2018 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager

2018 ENERGY REPORT. Mark J. Ferguson, P.E. Campus Operations & Plant Manager 2018 ENERGY REPORT Mark J. Ferguson, P.E. Campus Operations & Plant Manager Table of Contents Executive Summary... 2 Utilities Overview... 3 Avoided Cost... 4 Carbon Footprint... 5 Benchmarking Colorado

More information

RENOVATION UPGRADE REPORT

RENOVATION UPGRADE REPORT File Number: 79CGD00001 NRCan.gc.ca/myenerguide RENOVATION UPGRADE REPORT 214-620 View St Victoria, BC V8W 1J6 Potential rating Current rating 59 176 GJ/year GJ/year 65GJ/year Uses most energy E 0 GJ/year

More information

Results and Recommendations from Energy Audit of Kipnuk. For VEEP Grants. City of Kipnuk, Alaska

Results and Recommendations from Energy Audit of Kipnuk. For VEEP Grants. City of Kipnuk, Alaska ENERGY AUDIT POST INSTALLATION REPORT Results and Recommendations from Energy Audit of Kipnuk For VEEP Grants City of Kipnuk, Alaska June 20, 2012 Prepared By:, Inc. 6643 Brayton Drive Anchorage, AK 99507

More information

RETScreen ICE AND CURLING RINKS Model

RETScreen ICE AND CURLING RINKS Model - 1 - RETScreen ICE AND CURLING RINKS Model Daniel Giguère, Technology expert, CETC-Varennes, Natural Resources Canada 1615 Blvd. Lionel-Boulet, Varennes, Québec, Canada Nathalie Meloche, Project manager,cetc-varennes,

More information

PECO Smart Ideas for Your Business

PECO Smart Ideas for Your Business PECO Smart Ideas for Your Business April 2015 Agenda PECO Smart Ideas incentive programs Program measures and process Tools and Trade Allies 2 1 PECO Smart Ideas PA Act 129 Program incentives designed

More information

ENERGY EFFICIENCY GUIDEBOOK FOR EDUCATIONAL INSTITUTIONS

ENERGY EFFICIENCY GUIDEBOOK FOR EDUCATIONAL INSTITUTIONS ENERGY EFFICIENCY GUIDEBOOK FOR EDUCATIONAL INSTITUTIONS SUPPORTING PARTNERS ENERGY EFFICIENCY GUIDEBOOK FOR EDUCATIONAL INSTITUTIONS ENERGY EFFICIENCY GUIDEBOOK FOR EDUCATIONAL INSTITUTIONS OUTLINE OF

More information

Overview 7/24/2018. BOMA Chicago July 11, 2018

Overview 7/24/2018. BOMA Chicago July 11, 2018 2018 ComEd Business Programs & FEJA Overview for BOMA Chicago July 11, 2018 C O N F I D E N T I A L Overview Future Energy Jobs Act (FEJA) passed in December 2016 Legislation is a Win for Illinois RENEWABLES

More information

GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview

GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview GreenStep Cities Workshop Xcel Energy Rebates: Commercial Program Overview Mike Meyers, Xcel Energy Commitment from Leadership Our energy conservation programs are especially valuable because they give

More information

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC LIBRARY ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance

More information

Section 8 Energy and Energy Conservation

Section 8 Energy and Energy Conservation Section 8 Energy and Energy Conservation Energy powers our way of life. It heats our homes, cooks our food, allows us to travel and drives our economy. Where available in sufficient amounts, it allows

More information

SUSTAINABILITY TRACK Session 6

SUSTAINABILITY TRACK Session 6 SUSTAINABILITY TRACK Session 6 Facility-Wide Approach to Managing for Sustainability Judith Barry, Ph.D. Carbon Management Services GovEnergy 2008 Phoenix, AZ The World of a Facility NATURAL ATURAL SYSTEMS

More information

Energy Benchmarking Report for LaMonte Annex Elementary School Bound Brook, NJ

Energy Benchmarking Report for LaMonte Annex Elementary School Bound Brook, NJ Energy Benchmarking Report for LaMonte Annex Elementary School Bound Brook, NJ (for the period: March 2007 through February 2009) Prepared by: Background & Findings The New Jersey Clean Energy Program

More information

Conservation and Demand Management Plan

Conservation and Demand Management Plan Conservation and Demand Management Plan 2014-2019 Introduction Ontario Regulation 397/11 under the Green Energy Act 2009 requires public agencies municipalities, municipal service boards, school boards,

More information

2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012

2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012 2012 Ontario Building Code Requirements for New Construction Bradford West Gwillimbury Building Division March 5, 2012 1 Ontario Building Code changes Applicable to permits applied for after December 31,

More information

2014 Strategic Energy Conservation and Demand Management Plan

2014 Strategic Energy Conservation and Demand Management Plan 2014 Strategic Energy Conservation and Demand Management Plan All rights reserved. No part of this work may be produced or transmitted in any form or by any means, electronic or mechanical, including photocopying

More information

Farm Energy IQ. Farm Energy Efficiency Principles 2/16/2015. Farm Energy Efficiency. Basic Energy Principles

Farm Energy IQ. Farm Energy Efficiency Principles 2/16/2015. Farm Energy Efficiency. Basic Energy Principles Farm Energy IQ Farm Energy IQ Farms Today Securing Our Energy Future Farm Energy Efficiency Principles Tom Manning, New Jersey Agricultural Experiment Station Farm Energy Efficiency Principles Tom Manning,

More information

CORPORATE STRATEGIC INITIATIVES. Chair and Members of the Community and Corporate Services Committee

CORPORATE STRATEGIC INITIATIVES. Chair and Members of the Community and Corporate Services Committee Pg 1 of Report CSI-3/09 CORPORATE STRATEGIC INITIATIVES TO: SUBJECT: Chair and Members of the Community and Corporate Services Committee Corporate Energy Management Program Update Report Number: CSI 3/09

More information

Energy Audit. Town of Charlemont. Town Hall. 157 Main Street Charlemont, MA August 31, 2018

Energy Audit. Town of Charlemont. Town Hall. 157 Main Street Charlemont, MA August 31, 2018 Energy Audit Town of Charlemont Town Hall 157 Main Street Charlemont, MA 01339 August 31, 2018 Prepared by: Bowman Engineering, Inc. PO Box 410 Greenfield, MA 01302 (413) 303-0238 Preparer: Thomas Bowman,

More information

Berkeley Climate Action Plan: Tracking our Progress Building Energy Use Community-wide Greenhouse Gas Trend

Berkeley Climate Action Plan: Tracking our Progress Building Energy Use Community-wide Greenhouse Gas Trend Item 9 May 28, 214 Berkeley Climate Action Plan: Tracking our Progress Building Energy Use Community-wide Greenhouse Gas Trend Goal: Reduce conventional energy use and the associated greenhouse gas (GHG)

More information

STRATEGIC ENERGY MANAGEMENT PLAN FOR ST. THOMAS ELGIN GENERAL HOSPITAL 2015

STRATEGIC ENERGY MANAGEMENT PLAN FOR ST. THOMAS ELGIN GENERAL HOSPITAL 2015 STRATEGIC ENERGY MANAGEMENT PLAN FOR ST. THOMAS ELGIN GENERAL HOSPITAL 2015 Strategic Energy Management Plan Page 1 Contents About STEGH... 3 Introduction... 4 Energy Management Vision... 6 Guiding Principles

More information

2018 International Energy Conservation Code (IECC) Updates

2018 International Energy Conservation Code (IECC) Updates Providing effective energy strategies for buildings and communities 2018 International Energy Conservation Code (IECC) Updates 04.04.2018 12PM CDT Who we are Our goal: Reduce the energy footprint of Illinois.

More information

Local Government Energy Audit:

Local Government Energy Audit: Local Government Energy Audit: Energy Audit Report Abbott and Costello Center Copyright 2017 TRC Energy Services. All rights reserved. Reproduction or distribution of the whole, or any part of the contents

More information

QUEEN S UNIVERSITY GREENHOUSE GAS EMISSIONS INVENTORY SUMMARY 2015

QUEEN S UNIVERSITY GREENHOUSE GAS EMISSIONS INVENTORY SUMMARY 2015 QUEEN S UNIVERSITY GREENHOUSE GAS EMISSIONS INVENTORY SUMMARY 2015 INTRODUCTION In 2010, Queen s University signed onto the University and College Presidents Climate Change Statement of Action for Canada,

More information

Energy Benchmarking Report for Forked River Elementary School Forked River, NJ

Energy Benchmarking Report for Forked River Elementary School Forked River, NJ Energy Benchmarking Report for Forked River Elementary School Forked River, NJ (for the period: January 2006 through December 2008) Prepared by: Background & Findings The New Jersey Clean Energy Program

More information

Energy Consumption Investigation

Energy Consumption Investigation Energy Consumption Investigation Cambium Reference No.: 2990-003 Prepared for: Cambium Inc. P.O. Box 325 52 Hunter Street East, Peterborough Ontario, K9H 1G5 Telephone: (866) 217.7900 Facsimile: (705)

More information

2009 Power Smart Plan

2009 Power Smart Plan 2009 Power Smart Plan July 2009 *Manitoba Hydro is a licensee of the Official Mark Executive Summary The 2009 Power Smart Plan forecasts Manitoba Hydro s costs and savings to the benchmark year of 2024/25

More information

DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT

DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT DIGITAL AND ENVIRONMENTAL SKILLS FOR FACILITIES MANAGEMENT O3 A1 Learning unit 2 Energy efficiency and energy management in buildings Project Start Date - October 1st, 2016 Project End Date - March 31,

More information

THERMAL STORAGE SOLUTIONS WHITEPAPER

THERMAL STORAGE SOLUTIONS WHITEPAPER Contact Information Ed Whitaker: 802.584.4615 ewhitaker@thermalstoragesolutions.com Bruce McGeoch: 802.651.0571 bmcgeoch@thermalstoragesolutions.com Thermal Storage Solutions, LLC 119 Pleasant Street,

More information

Ventura County, CA Identifying Big Impact Opportunities for the Built Environment Using Energy Audits

Ventura County, CA Identifying Big Impact Opportunities for the Built Environment Using Energy Audits Ventura County, CA Identifying Big Impact Opportunities for the Built Environment Using Energy Audits Local government agencies can use energy audits to meet energy and climate action planning goals by

More information