Dulles Corridor Metrorail Project

Size: px
Start display at page:

Download "Dulles Corridor Metrorail Project"

Transcription

1 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016

2 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ Million Total Budget $ Billion Total Forecast $ Billion

3 Phase 2 Contingency Utilization Total Contingency Contingency Utilized through January 2016 Contingency Utilized in February 2016 Total Contingency Utilized through February 2016 Remaining Contingency $ Million $ 75.6 Million $ 0.6 Million $ 76.2 Million $ Million

4 February Contingency Utilization Total Contingency Utilized in February 2016 Package A (CRC) Innovation Center Station North Alternative Site Layout Change - Design Relocation of CenturyLink Conduit and Cable at Van Buren Overpass - Construction Additional Modifications to the Dynamic Messaging Signage System Design (Settled for $120,000) Sign Panel Replacement of Herndon Station Overhead Signs Survey for Proposed New Fiber Cable Replacement at Dulles Airport Pedestrian Tunnel Survey for VDOT Resurfacing of Sunrise Valley Drive (Settled for $18,000) $ 0.6 Million $ 0.5 Million $ 300,000 $ 125,474 $ 60,000 $ 35,530 $ 30,000 $ 9,000

5 February Contingency Utilization Package B (HP) $ 0.1 Million Wheel Truing and Grease Room Change - Design $ 40,000 Car Track Equipment Maintenance Shop & Equipment Changes at Maintenance of Way Building Design Exploratory Trench Excavation to Expose Existing Rock Located on the Northeast Corner of the Yard $ 10,000 $ 3,500

6 Current Guideway & Stations Design-Build Activities Advancement of Design Packages: 97% (393/406) Complete Overall 92% (65/71) Packages Issued for Construction Issued 13 Permit Amendments due to Design Revisions Project Office Review/Approval Activities: 20 Design Change Packages 63 Contractor Submittals 21 Non-Conformance Reports

7 Guideway & Stations Design-Build Activities Set Girders North of Autopilot Drive

8 Guideway & Stations Design-Build Activities Abutment Between Package A and Package B

9 Guideway & Stations Design-Build Activities Constructing Aerial Guideway Columns at Airport

10 Guideway & Stations Design-Build Activities Construct and Wrap Heating Blankets Around Straddle Bent Form

11 Guideway & Stations Design-Build Activities Precast Panel and Platform Support Installation at Innovation Station

12 Guideway & Stations Design-Build Activities Pile Driving at Reston Station

13 Guideway & Stations Design-Build Activities Setting Elevations for Herndon Station Foundations and Walls

14 Guideway & Stations Design-Build Activities Dulles Station Lower Level Service Rooms

15 Guideway & Stations Design-Build Activities Utility Crossings Under Greenway

16 Upcoming Guideway & Stations Design-Build Activities Reston Station Continue to drive steel piles for foundation, continue small tunnel/directional drilling for wet utilities and installation of 34.5 KV Herndon Station Form and pour station foundations and walls and continue installation of underground systems and utilities Innovation Station Continue station precast element placement and begin foundations for South Pavilion Dulles Station Continue station foundation and aerial guideway substructures, continue walkway demolition and tie in to pedestrian tunnel Aerial Guideway Pour drilled shafts, columns, and pier caps, decks, and girders installation, move straddle bent forms and crane to Airport flag pole area for bents #11 and #13 in S-1 Guideway

17 WMATA Rail Yard & Maintenance Facility Design-Build Activities Current Structures and Long Lead Items (Integrated Permit Package (IPP) #3) Permit application package is with the Authority Having Jurisdiction (AHJ) awaiting permit Issued for Permit (IFP) Package for track, traction power/ductbank, site utilities, industrial designs (IPP #2, Part 2) is with the AHJ awaiting permit Construction of final grading, utilities and yard layout (IPP #2, Part 1) permitted and progressing Drilling and blasting operations continue Service and Inspection Building basement excavation complete awaiting permit

18 WMATA Rail Yard & Maintenance Facility Design-Build Activities Current Mass cut/fill operation progressing Replacement of unsuitable/uncompacted soil nears completion 90% project-wide design submittal for Yard buildings and automatic train control completed and returned to the Contractor for action

19 WMATA Rail Yard & Maintenance Facility Design-Build Activities Upcoming Construction Permit issuance Traction power/ductbank, site utilities (IPP #2, Part 2) Construction Permit issuance Structures and long lead items (IPP #3) Incorporation of WMATA design refinements

20 WMATA Rail Yard & Maintenance Facility Design-Build Activities Lowering of grade on the North Side

21 WMATA Rail Yard & Maintenance Facility Design-Build Activities Drilling for blasting

22 DULLESMETRO.COM

23 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 MONTHLY COST SUMMARY As of February 29, 2016 Description Budget Total Expenditures to Date Contract Contract Amount 1,3 Forecast 2 Amount Total NTP Substantial 4 DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Percent b c c/b DESIGN-BUILD Package A 1,193,777,000 1,272,149, ,090,706 31% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280, ,595,418 45,590,406 17% 18-Nov Jun-18 ROW 58,600,000 58,600,000 5,591,250 10% 8-Jul Sep-17 WMATA 305,324, ,324,718 42,929,307 14% N/A 3-Feb-20 PRELIMINARY ENGINEERING 75,000,000 75,000,000 73,264,856 98% 15-Jul Dec-13 PROJECT MANAGEMENT 320,802, ,264, ,604,697 38% N/A 2-Jan-19 CONTINGENCY 551,451, ,301,801 TOTAL FOR DCMP 2,778,235,564 2,778,235, ,071,221 Notes: 1 Budget Amount includes contingency as separate line item and does not include finance costs. 2 Total Forecast includes funded changes. It does not include finance costs. 3 Budget Amount includes commodity escalation of $20 million for Package A & B+S. 4 Package A Contract Substantial Completion date changed from 7-Jul-2018 to 7-Aug-2019

24 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 CONTINGENCY UTILIZATION As of February 29, 2016 ATTA Description Amount in million ($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Total Contingency $ Contingency Utilized through January 2016 $ 75.6 Expended Contingency in February 2016* $ 0.6 Total Contingency Utilized through February 2016 $ 76.2 Remaining Contingency $ *See table below for details Package A (CRC) $0.5 Million Innovation Center Station North Alternative Site Layout Change - Design $ 300,000 Relocation of CenturyLink Conduit and Cable at Van Buren Overpass - $ 125,474 Construction Additional Modifications to the Dynamic Messaging Signage System Design $ 60,000 (Settled for $120,000) Sign Panel Replacement of Herndon Station Overhead Signs $ 35,530 Survey for Proposed New Fiber Cable Replacement at Dulles Airport Pedestrian $ 30,000 Tunnel Survey for VDOT Resurfacing of Sunrise Valley Drive (Settled for $18,000) $ 9,000 Package B (HP) $0.1 Million Wheel Truing and Grease Room Change - Design $ 40,000 Car Track Equipment Maintenance (CTEM) Shop & Equipment Changes at $ 10,000 Maintenance of Way Building - Design Exploratory Trench Excavation to Expose Existing Rock Located on the Northeast Corner of the Yard $ 3,500

25 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A DCMP 5401 Package A - Mainline (CRC) 1,177,777,000 DCMP 5406 Commodity Escalation 16,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package A 1,193,777,000 DESIGN-BUILD Package B+S DCMP 5402 Package B - Yard 269,280,530 DCMP 5402 Package S - Yard Site Preparation incl above DCMP 5406 Commodity Escalation 4,000,000 DCMP 5408 Contingency amount DCMP 5408 Secondary mitgation amount SUBTOTAL - DESIGN-BUILD Package B+S 273,280,530 ROW DCMP 5404 Land & Relocation 47,225,000 DCMP 5404 Support Services 11,375,000 DCMP 5408 Contingency SUBTOTAL - ROW 58,600,000 WMATA DCMP 5405 WMATA Vehicles 205,868,200 DCMP 5405 WMATA other costs 90,205,767 DCMP 5405 WMATA Non Revenue Vehicles 9,250,751 DCMP 5408 Contingency SUBTOTAL - WMATA 305,324,718 PRELIMINARY ENGINEERING DCMP 5406 PRELIMINARY ENGINEERING 75,000,000 SUBTOTAL - PRELIMINARY ENGINEERING 75,000,000 PROJECT MANAGEMENT DCMP 5406 MWAA Staff 34,000,000 DCMP 5406 MWAA Allocated Cost 13,560,000 DCMP 5406 Rent 9,200,000 DCMP 5406 Relocation, IT, Furniture 2,700,000

26 Dulles Rail ATTACHMENT 1 Airport Project No Description Budget Amount DCMP 5406 MWAA ODCs 17,060,000 DCMP 5406 Insurance (OCIP) 49,082,137 DCMP 5406 PMSS 140,000,000 DCMP 5406 VDOT 10,000,000 DCMP 5406 DRC Prof Svcs 2,500,000 DCMP 5406 CTI (Special Inspections) 14,000,000 DCMP 5406 DGS 2,000,000 DCMP 5406 TRIP II 2,000,000 DCMP 5406 Dept of Conservation & Recreation (DCR) 2,000,000 DCMP 5406 MWAA Permits/Inspection 4,000,000 DCMP 5406 Power for System Testing 16,000,000 DCMP 5406 Historical/Archaeologic 2,700,000 DCMP 5408 Contingency SUBTOTAL - PROJECT MANAGEMENT 320,802,137 CONTINGENCY DCMP 5408 Contingency - Package A 289,067,231 DCMP 5408 Secondary mitgation amount - Package A 0 DCMP 5408 Contingency - Package B 109,006,387 DCMP 5408 Secondary mitgation amount - Package B 0 DCMP 5408 Contingency - ROW 5,860,000 DCMP 5408 Contingency - WMATA 30,532,472 DCMP 5408 Contingency Project Management 116,985,089 SUBTOTAL - CONTINGENCY 551,451,179 TOTAL FOR DCMP - PHASE 2 2,778,235,564

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ 739.6 Million Total

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2016 NOVEMBER 2016 Phase 2 Cost Summary September Expenditures $ 29.0 Million Total Expenditures $ 901.4 Million

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF MARCH 31, 2015 MAY 2015 0 Phase 2 Cost Summary March Expenditures $ 21.8 Million Total Expenditures $ 422.6 Million

More information

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting

Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting Dulles Corridor Enterprise Financial Update Dulles Corridor Advisory Committee Meeting June 22, 2016 Discussion Outline Finance Plan for the Metrorail Project Financial Developments Since December 2015

More information

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

Dulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia

Dulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia Dulles Corridor Metrorail Expansion Providing Safe Transportation for Northern Virginia Overview The Washington D.C. Metrorail is the second busiest rail transit network in the United States, with an average

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee February 20, 2014 & Schedule Performance Summary Chart Slide # Project

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

COMPREHENSIVE MONTHLY REPORT. April 2011

COMPREHENSIVE MONTHLY REPORT. April 2011 COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC May 27, 2011 PMOC Contract Number: DTFT60-09-D-00016

More information

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011

Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. January 2011 Annual Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE January 2011 Annual Report TABLE OF CONTENTS

More information

COMPREHENSIVE MONTHLY REPORT. December 2011

COMPREHENSIVE MONTHLY REPORT. December 2011 COMPREHENSIVE MONTHL REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC January 20, 2012 PMOC Contract Number: DTFT60-09-D-00016

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 52 Transit Program Project Budget and Schedule Status Report Construction Committee June 19, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments 3 Crenshaw/LAX

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

COMPREHENSIVE MONTHLY REPORT. September 2010

COMPREHENSIVE MONTHLY REPORT. September 2010 COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC October 26, 2010 PMOC Contract Number: DTFT60-09-D-00016

More information

CTA Capital Construction Update August 8, 2007

CTA Capital Construction Update August 8, 2007 Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block

More information

Project Budget and Schedule Status Report

Project Budget and Schedule Status Report Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments

More information

APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED

APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H: ALTERNATIVES PREVIOUSLY CONSIDERED This appendix provides an overview of the process that led to the selection of the Locally Preferred Alternative

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

7/30/2014 Correspondence

7/30/2014 Correspondence 7/30/2014 Correspondence July 29, 2014 Mr. Mark Canale Fairfax County 4050 Legato Rd Suite 400 Fairfax, VA 221822228 Project [813C001] Dulles Corridor Metrorail Project, Phase 2 Pkg A Location Code (multi)

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 47 Program Management Project Budget and Schedule Status Transit Project Delivery Transit Project Delivery Construction Committee January 16, 2014 & Schedule Performance Summary Chart Project Performance

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item Program Management Project Budget and Schedule Status Transit Project Delivery Construction Committee November 21, 2013 & Schedule Performance Summary Chart 2 1 Crenshaw/LAX Transit 1,749 2,058 2,058

More information

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS

Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS Metropolitan Washington Airports Authority PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF REQUEST FOR PROPOSALS Metropolitan Washington Airports Authority Procurement and Contracts Dept., MA-29 1 Aviation

More information

EVALUATION OF ALTERNATIVES CARRIED FORWARD

EVALUATION OF ALTERNATIVES CARRIED FORWARD 1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

College Football Hall of Fame HAMMOCK R

College Football Hall of Fame HAMMOCK R - Contract Schedule MILESTONES DESIGN / PRECONSTRUCTION PROCUREMENT Construction Procurement CONSTRUCTION Hardscape / Landscape Hall Of Fame Building Sitework Earthwork A1060 Mobilize 5 18-Feb-13 A 22-Feb-13

More information

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview

M E T R O P O L I T A N W A S H I N G T O N A I R P O R T S A U T H O R I T Y. DTR Toll Collection Overview DTR Toll Collection Overview 1 The Dulles Toll Road A Traditional Tolling Facility * Payment Options * EZ Pass * Exact Change (all coins) * Full Service (but no Credit Card capability) * Some higher (but

More information

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016

Report to the Finance Committee Comprehensive Annual Financial Report. Prepared by the Office of Finance April 2016 Report to the Finance Committee 2015 Comprehensive Annual Financial Report Prepared by the Office of Finance April 2016 Audit Opinion date April 11, 2016 Unmodified or clean audit opinion on financial

More information

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON

CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON Council Meeting Date: June 15, 2015 Agenda Item: 7(c) CITY COUNCIL AGENDA ITEM CITY OF SHORELINE, WASHINGTON AGENDA TITLE: DEPARTMENT: Motion to Authorize the City Manager to execute Change Order No. 1

More information

Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner

Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner Dulles Corridor Metrorail Project Phase 1 NATM Tunnel Construction at Tysons Corner Committee on Tunnels and Underground Structures (AFF60) 23 January 2012 Vojtech Gall, PhD, PE Project Overview Project

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013129 COLUMBIA, CHEROKEE COUNTY, SOUTH CAROLINA I-85 UNDERPASS PROJECT (1) REPLACEMENT OF EXISTING I-85 UNDERPASS BRIDGE MILEPOST SB-141.35 DOT/AAR

More information

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc. Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package P Stormwater Management Facilities February 13, 2017 Rev. 0 Statement of Work February 13, 2017 THIS PAGE INTENTIONALLY

More information

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek

More information

INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT

INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT INNOVATION STATION MIXED USE DEVELOPMENT A RECO DEVELOPMENT ROCKS ENGINEERING COMPANY 1960 Gallows Road, Suite 300 Vienna, VA 22182 Voice (703) 556-4000 INNOVATION STATION MIXED USE DEVELOPMENT PROJECT

More information

Appendix C. Construction Programme

Appendix C. Construction Programme Appendix C Construction Programme Activity ID Activity Name Orig Dur Planned Start Planned Finish Revision 2 827d 14-Oct-13 31-Jul-16 0d Preliminaries 827d 14-Oct-13 31-Jul-16 0d Total Float Contract Key

More information

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 2010 update TABLE OF CONTENTS

More information

Construction Update. July 2015

Construction Update. July 2015 Construction Update July 2015 Current Project Overview Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Status Schedule # Milestone Current 2014 2015

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT MARCH 2015 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report March 2015 TABLE OF CONTENTS Project Manager

More information

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10 EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems February 1, 2013 (Rev. 1 - Issued with Final RFP) Final RFP Statement of Work February

More information

I2-0 LIST OF ACTIVE SSDs

I2-0 LIST OF ACTIVE SSDs I2-0 0002.0001 Structural Standard Drawings - Layering Structure Aug 1, 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details Jun 1, 2002 Jul 17, 2002 0007.0002 Grout Vent Detail Mar 1, 2006

More information

VRE Gainesville-Haymarket Extension (GHX) Study. December 16, 2016

VRE Gainesville-Haymarket Extension (GHX) Study. December 16, 2016 VRE Gainesville-Haymarket Extension (GHX) Study December 16, 2016 1 Project Origins System Plan 2040 and Financial Plan Follow Natural Growth profile to run longer trains Continue to pursue funding for

More information

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK

Metropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems March 15, 2013 (Rev. 2 - Issued with Final RFP) Final RFP Statement of Work March

More information

Millennium Line Broadway Extension Project. Cost Report

Millennium Line Broadway Extension Project. Cost Report Millennium Line Broadway Extension Project Cost Report March 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

Doing Business with the Metropolitan Washington Airports Authority

Doing Business with the Metropolitan Washington Airports Authority Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington

More information

PCDO. May Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. May Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO May-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

PCDO. April Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. April Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO April-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

Project Budget And Schedule Status Report

Project Budget And Schedule Status Report Item 47 Project Budget And Schedule Status Report Presented by Brian Boudreau Executive Director, Program Management Construction Committee June 18, 2015 & Schedule Performance Summary Chart Slide # Project

More information

ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study. 1. Work Accomplished This Period (4 Weeks)

ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study. 1. Work Accomplished This Period (4 Weeks) ONTARIO-MICHIGAN BORDER TRANSPORTATION PARTNERSHIP Planning/Need and Feasibility Study MONTHLY #5 Period Ending July 31, 2002 1. Work Accomplished This Period (4 Weeks) Strategic and Geographic Area Overview

More information

Tri-State Oversight Committee. Three-Year Safety and Security Review. of the Washington Metropolitan Area Transit Authority. Structures Maintenance

Tri-State Oversight Committee. Three-Year Safety and Security Review. of the Washington Metropolitan Area Transit Authority. Structures Maintenance Tri-State Oversight Committee Three-Year Safety and Security Review of the Washington Metropolitan Area Transit Authority Structures Maintenance Elements 14, 15 and 16 Review Conducted: April/May 2015

More information

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014

Customer Service and Operations Committee. Board Information Item III-B. October 9, 2014 Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue

DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue Submitted to the Federal Transit Administration For Final Design Submitted by Metropolitan Washington Airports Authority In cooperation with

More information

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs)

LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) LIST OF ACTIVE STRUCTURAL STANDARD DRAWINGS (SSDs) 0002.0001 Structural Standard Drawings - Layering Structure n/a Aug 2014 Dec 18, 2014 0005.0002 Retaining Wall - Rustication Details n/a Jun 2002 Jul

More information

AMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia

AMENDED RECORD OF DECISION. by the Federal Transit Administration. Dulles Corridor Metrorail Project Fairfax and Loudoun Counties, Virginia AMENDED RECORD OF DECISION by the Federal Transit Administration Fairfax and Loudoun Counties, Virginia DECISION The Federal Transit Administration (FTA), in accordance with 23 CFR part 771, the regulation

More information

Neptune Cargill Overpass Extension

Neptune Cargill Overpass Extension Project Environmental Review UPDATE November 23, 2017 Northshore Waterfront Liaison Committee Teck Agenda Project Objectives Project Description Project Discussion VFPA PER process Project Review Status

More information

I-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010

I-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010 VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY Dan Staron, P.E. HNTB Corporation MARCH 4, 2010 PRESENTATION OVERVIEW Project Background/Highlights Design Challenges Technical Details Concrete Applications/Details

More information

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows: PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD LCB File No. R090-08 May 14, 2008 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted. AUTHORITY: 1,

More information

Ø Contents of Price Proposal:

Ø Contents of Price Proposal: ATTACHMENT 4.0.1.2 Addendum#1 February 13, 2015 DESIGN-BUILD PRICE PROPOSAL CHECKLIST Project Name: Route 7 Widening and Bridge Rehabilitation over Dulles Toll Road and Airport Access Highway Contract

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018

No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018 व जय शर म vkbzvkj,lb Vijay Sharma IRSE No. Secy.CAO/USBRL/JAT/PCDO Dated: 10/08/2018 Sub: PCDO for the Month of July, 2018. 1. Highlights of the month of July, 2018. 1.1 During this month 2035 m of tunneling

More information

Results you can rely on

Results you can rely on z 1 I-49 North Segment K Project 2 AGENDA PROJECT OVERVIEW BRIDGE DESIGN ARCHITECTURAL ENHANCEMENTS SPECIAL PROVISIONS COST ESTIMATE AND FINAL BIDS CONSTRUCTION 3 SITE LOCATION PROJECT SITE ARKANSAS 185

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

4.0 CONSTRUCTION METHODS AND ACTIVITIES

4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential

More information

SP 1.02 SHEET INDEX 1 OF 2 SITE SURVEY 2 OF 2 SITE SURVEY OVERALL SITE PLAN FOOTBALL & TRACK LAYOUT AND MATERIALS PLAN

SP 1.02 SHEET INDEX 1 OF 2 SITE SURVEY 2 OF 2 SITE SURVEY OVERALL SITE PLAN FOOTBALL & TRACK LAYOUT AND MATERIALS PLAN P.O. Box 768 Overland Park, KS 6627 ph: (93) 484-52 47 W. 4th Terrace Lenexa, KS 6625 ph: (93) 894-55 SPOIL DISPOSAL SITE 255 Valley Parkway, Suite 2 Olathe, KS 666 ph: (93) 344-29 SHEET INDEX OF 2 SITE

More information

Welcome! October 18, 2016

Welcome! October 18, 2016 Welcome! October 18, 2016 1 Today s Topics Welcome Building the Future: Project & Construction Overview Employment Opportunities Staying Connected Questions? 2 METRO System: All-Day, Frequent Service Light

More information

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS 1.0 DESCRIPTION The Work shall consist of:.1 Transportation, unloading, erection and grouting of precast prestressed concrete

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Completing downspouts and other final touches on the Mukilteo Sounder Program new platform. September 2015 Prepared by Project Control September 2015 l Design, Engineering

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project 395795» Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions

Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Jane Addams Memorial Tollway (I 90) Fox River Bridge Traffic Needs Drive Innovative Solutions Scott Eshleman, P.E., S.E, CVS, Stanley Consultants Keith Sargent, P.E., Thomas Engineering Group, LLC February

More information

CAC Meeting Construction Update April 8, 2014

CAC Meeting Construction Update April 8, 2014 CAC Meeting Construction Update April 8, 2014 Period Summary There have been over 1,000,000 craft hours completed, excluding demolition, through March 31, 2014. An increase of nearly 50,000 hours since

More information

AAPA. Port Operations/Safety and Information Technology Seminar

AAPA. Port Operations/Safety and Information Technology Seminar AAPA Port Operations/Safety and Information Technology Seminar 4/24/-27, 2007 Jacksonville, FL Innovation in Port Efficiency: Processes, Simulations and Modeling for better Terminal Operations, Planning

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information