Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
|
|
- Morgan Holt
- 6 years ago
- Views:
Transcription
1 Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director
2 Silver Line: Phase 2 Station Tour
3 Phase 1
4 Phase 1 Cost Summary Expenditures (May thru Oct 2017) Total Expenditures (Thru Oct 31, 2017) $ 12.7 Million $ Billion Forecast at Completion $ Billion
5 Phase 1 Update Closeout of VDOT Comprehensive Agreement There are two categories of work that must be performed: remediation of all remaining VDOT facility deficiency items and the Old Meadow Road intersection lane widening. Bechtel has agreed to perform a portion of the pipe remediation. MWAA will remediate the remainder of the deficiencies and recoup costs from Bechtel. Task Order Contract Status Task Orders with Notice To Proceed (NTP): 34 issued, including Old Meadow Road Design; 31 have been completed. Upcoming activities include: Americans with Disabilities Act sidewalk repair, storm drain remediation, manhole/structure repair, Chain Bridge Road drainage design, DCR Median Stormwater runoff repairs, and Dulles Connector Road left shoulder modification.
6 Old Meadow Road Schedule The final design is nearing completion for the realignment. 90% design is complete and responses to comments have been issued. VDOT has approved the curb radius design exception. Utility coordination (design) is required before completion of the 100% design. A modification for managing utility coordination was issued in October. Utility Issues: Numerous utility facilities require minor relocation work, but significant coordination and time effort for management, design and construction. 11 utility agencies/companies are involved. Plans Moving Forward: Start construction in early 2018, complete construction 2 nd quarter 2018.
7 Phase 2 Package A 74% Complete Package B 61% Complete
8 Phase 2 Cost Summary Expenditures (May thru Oct 2017) $ Million Total Expenditures $ Billion Total Budget $ Billion Total Forecast $ Billion
9 Current Guideway & Stations Design-Build Activities All Design Packages complete and issued for construction. 98 Identified Design and Field Changes in Progress: 32 to be submitted 12 in review process with MWAA 54 in response or IFC production process with CRC 23 reviewed/processed by MWAA last month 20 Permit Amendments issued for Design Revisions. 87 Supplier Submittals reviewed/processed last month.
10 Upcoming Guideway & Stations Design-Build Activities Electricians will continue receiving Traction Power Substation (TPSS) and Tie Breaker Station (TBS) buildings and connecting these facilities with power cables to the guideway and stations. Innovation/Herndon/Reston Stations Continue roofing, escalator installation, and electrical and plumbing; erect remaining pedestrian bridge spans and pour concrete pedestrian bridge decks. Dulles Station Continue mechanical and plumbing, elevator and escalator installation and continue the installation of the station canopy roof. Track Ballasted rail and switch installation continues on the east and west at-grade guideways, Aerial Direct Fix Track is being installed through the Dulles Station and continuing to the east from the station.
11 Installation of Pedestrian Bridge at Reston Station
12 Pedestrian Bridge at Reston Station
13 Herndon North Station Pedestrian Bridge Interface
14 Installation of Power Conduits at TPSS #12
15 Installation of Track Turnouts East of Innovation Station
16 Installation of Tie Extenders for Traction Power Rail in At-Grade Guideway
17 Relocation of Utilities along Sunrise Valley Drive at Herndon Garage Entrance
18 Preparation of Pedestrian Walkway Sections for Innovation North Pavilion Access
19 Reinstallation of Modified Moving Walkways In Airport Pedestrian Tunnel
20 Dulles Station Platform Canopy Roof Framing
21 Loudoun Gateway Station Structural Steel Roof Framing
22 Ashburn Station Precast Installation
23 Window Frame Installation Second Floor TB
24 Dulles International Airport Station Progress
25 Dulles International Airport Station Progress
26 Current WMATA Rail Yard & Maintenance Facility Design-Build Activities Final grading, paving and utility installation continues. Service and Inspection Building s (SIB) roofing and interior buildout continues. Maintenance of Way Building (MWB) roofing and interior buildout continues. Transportation Building (TB) interior buildout continues, roofing to start shortly. Train Wash Facility (TWF) structural steel underway. Rail welding progressing, 43 of 49 sections of special track work roughed in. Rail alignment/tamping/destressing ongoing.
27 WMATA Rail Yard & Maintenance Facility Design-Build Activities Ongoing SIB interior fit out, switchgear room buildout, machine shop equipment foundations and interior floors. Rail and special trackwork installation, tamping and aligning. Resolve open design and time extension changes. Review shop documents and construction submittals. Construction inspection and testing. Interface coordination with Package A.
28 Placing Concrete for TPSS# 21A Cable Pit Walls
29 Paving the Perimeter Road NW of the TB
30 Screeding Sidewalk Concrete Placement, Looking East TWF in Right Background
31 Placing Slab On Grade, SW Corner of TB
32 Installing Glazing in the South Wall of the SIB
33 Installing Concrete Masonry Walls in SIB
34 Installing Wall Stud Framing on the Second Floor of the TB
35 Welding Rebar for Stray Current Prevention in the SIB
36 DULLESMETRO.COM
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates May 31, 2018 Charles W. Stark Senior Vice President Phase 1 Phase 1 Cost Summary Expenditures (Nov 17 thru Apr 18) Total Expenditures (Thru Apr
More informationDulles Corridor Metrorail Project Phase 1 & Phase 2 Updates
Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates June 30, 2017 Charles W. Stark Executive Project Director Phase 2 Station Tour 2 Phase 1 Phase 1 Cost Summary Quarter Expenditures (Feb, Mar,
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2017 MARCH 2017 Phase 2 Cost Summary January Expenditures $ 10.6 Million Total Expenditures $ 1.078 Billion
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2016 FEBRUARY 2017 Phase 2 Cost Summary December Expenditures $ 79.6 Million Total Expenditures $ 1.068 Billion
More informationDulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018 2 Phase 2 Cost Summary September Expenditures $ 19.4 Million Total Expenditures $ 1.868
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF APRIL 30, 2016 JUNE 2016 Phase 2 Cost Summary April Expenditures $ 17.5 Million Total Expenditures $ 739.6 Million Total
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF DECEMBER 31, 2015 FEBRUARY 2016 Phase 2 Cost Summary December Expenditures $ 62.9 Million Total Expenditures $ 655.6 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2016 NOVEMBER 2016 Phase 2 Cost Summary September Expenditures $ 29.0 Million Total Expenditures $ 901.4 Million
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationCapital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager
Program Panelist Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager Moderator Kevin Pavuk, Structural Technologies Presentation 5:30 to 7:00 p.m.
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE PHASE 2 AS OF OCTOBER 31, 2015 DECEMBER 2015 Phase 2 Cost Summary October Expenditures $ 21.9 Million Total Expenditures $ 569.2 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF FEBRUARY 29, 2016 APRIL 2016 Phase 2 Cost Summary February Expenditures $ 25.7 Million Total Expenditures $ 690.1 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF JANUARY 31, 2016 MARCH 2016 Phase 2 Cost Summary January Expenditures $ 8.8 Million Total Expenditures $ 664.4 Million Total
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF MARCH 31, 2015 MAY 2015 0 Phase 2 Cost Summary March Expenditures $ 21.8 Million Total Expenditures $ 422.6 Million
More informationDulles Corridor Metrorail Project
Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationDulles Corridor Metrorail Expansion. Providing Safe Transportation for Northern Virginia
Dulles Corridor Metrorail Expansion Providing Safe Transportation for Northern Virginia Overview The Washington D.C. Metrorail is the second busiest rail transit network in the United States, with an average
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report July 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationEVALUATION OF ALTERNATIVES CARRIED FORWARD
1 EVALUATION OF ALTERNATIVES CARRIED FORWARD This chapter presents a comparative evaluation of the alternatives carried forward in this Final Environmental Impact Statement (EIS). The intent of this evaluation
More informationAuburn University Construction Project April
Small Animal Teaching Hospital Phase I: Construction Cost: $8.8 million. Phase I consists of (1) constructing an addition to the Overton-Rudd Auditorium to expand classroom and lecture hall capacity, (2)
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report December 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems February 1, 2013 (Rev. 1 - Issued with Final RFP) Final RFP Statement of Work February
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package A Rail Line, Stations, and Systems March 15, 2013 (Rev. 2 - Issued with Final RFP) Final RFP Statement of Work March
More informationPROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationCARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report
CARVER ELEMENTARY SCHOOL PROJECT May 2017 Monthly Status Report Project: Current Phase: Construction Construction Type: New Construction Construction Start Date: 03Oct2016 Building Size (New): 112,350
More informationPhase 2 Exposition Metro Line Project
Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCustomer Service and Operations Committee. Board Information Item III-B. October 9, 2014
Customer Service and Operations Committee Board Information Item III-B October 9, 2014 Major Red Line Construction Page 12 of 58 Washington Metropolitan Area Transit Authority Board Action/Information
More informationConstruction Project Briefing. October 10, 2018
Construction Project Briefing October 10, 2018 Today s Presentation ELMI East Lake, Milwaukee, Illinois Substation Upgrade Ravenswood Loop Signals Upgrade Project 95 th Street Terminal Improvement Program
More informationDulles Corridor Metrorail Project Phase 2 Package B
Dulles Corridor Metrorail Project Phase 2 Package B Quarterly Update to MWAA Board of Directors Michael Barker Hensel Phelps June 2018 Phase 2 Package B - Agenda Contract/Project Overview Safety Schedule
More informationMetropolitan Washington Airports Authority. Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK
Phase 2: Extension To Dulles Airport/Route 772 STATEMENT OF WORK Design Build Package P Stormwater Management Facilities February 13, 2017 Rev. 0 Statement of Work February 13, 2017 THIS PAGE INTENTIONALLY
More informationPhotos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek
Photos by Susie Fitzhugh BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek Arbor Heights Elementary School Site Plan July 1, 2015 July 10, 2015 Arbor Heights Elementary School
More informationCTA Capital Construction Update August 8, 2007
Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationConstruction Project Briefing. May 9, 2018
Construction Project Briefing May 9, 2018 Today s Presentation 95 th Street Terminal Improvement Program Quincy Loop Station Upgrade Ravenswood Loop Signals Upgrade Project Illinois Medical District (IMD)
More informationADDENDUM 2 - JULY 14, 2015
7/9/2015 The Professional(s) of Record above has signed for the following specification sections: DIVISION 1 GENERAL REQUIREMENTS Section 01 10 00 Summary of Work Section 01 25 00 Substitution Procedures
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationDoing Business with the Metropolitan Washington Airports Authority
Doing Business with the Metropolitan Washington Airports Authority MWMCA Quarterly Economic Summit Brown Advisory November 7, 2017 Introduction to MWAA Ronald Reagan Washington National Airport Washington
More informationJuly 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationConstruction Project Briefing. November 19, 2014
Construction Project Briefing November 19, 2014 Today s Presentation Traction Power Farwell/Armitage/Hill Substations Kimball/Princeton/State Substations O Hare Blue Line Station Improvements (Damen, Western,
More informationDULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue
DULLES CORRIDOR METRORAIL PROJECT Extension to Wiehle Avenue Submitted to the Federal Transit Administration For Final Design Submitted by Metropolitan Washington Airports Authority In cooperation with
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationConstruction Project Briefing. March 9, 2016
Construction Project Briefing March 9, 2016 Today s Presentation 95 th Street Terminal Improvement Program Wilson Transfer Station, Track, and Structure Reconstruction O Hare Line Addison, Irving Park,
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07 Latrobe Elementary School Greater Latrobe School District 08 January 2018 PROJECT SUMMARY Work Completed to date: Ductwork sealed off. Slab Prep in Main
More informationSPACE TYPE: OUTSIDE PARKING (STRUCTURE)
SPACE TYPE: OUTSIDE PARKING (STRUCTURE) Construction Criteria The unit costs for Outside Parking (Structure) space types are based on the construction quality and design features in the following table.
More informationUPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)
UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) DESIGN PHASE PROJECTS BCT - Building Program Development and Design for Maintenance and Administration
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction Phase 1 Overview The Re-routed Q train will
More informationConstruction Project Briefing. September 11, 2013
Construction Project Briefing September 11, 2013 Today s Presentation Farwell/Armitage/Hill Substations Red Line South Reconstruction Project (Track & Station) Bus Hoist Replacement Program Phase 1 Forest
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationAPPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED
APPENDIX H- ALTERNATIVES PREVIOUSLY CONSIDERED APPENDIX H: ALTERNATIVES PREVIOUSLY CONSIDERED This appendix provides an overview of the process that led to the selection of the Locally Preferred Alternative
More informationConstruction Update. April 2016
Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor
More informationUpdate on FCPS Construction/Renovation Projects. November 2015
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationProperty Condition Assessment
Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072
More informationAuburn University Construction Project Update March 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish
More informationProject Manual Index of Specifications Shenandoah Schools Concession Building
INDEX OF SPECIFICATIONS Division 0..BIDDING AND CONTRACT REQUIREMENTS 00 11 13 Advertisement for Bids 00 21 13 Instructions to Bidders 00 41 00 Bid Forms 00 43 13 Bid Security Form 00 72 00 General Conditions
More informationAviation Capital Construction Program Update
Aviation Capital Construction Program Update 2012 Completed Projects 2013 Active Projects Bern Seals Program Manager Parsons Management Consultants April 2013 0 Discussion Agenda Program Safety Performance
More informationConstruction Update. March 2018
Construction Update March 2018 Project Overview Western Zone Grid Line 1-10 Central Zone Grid Line 10-20 Eastern Zone Grid Line 20-35 2 Recent Activity 3 Recent Activity 4 Construction Activity Transit
More informationJune 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY
June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationConstruction Update. May 2016
Construction Update May 2016 Project Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor Statistics
More informationADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:
ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting October 25, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More informationConstruction Project Briefing. July 11, 2018
Construction Project Briefing July 11, 2018 Today s Presentation ELMI East Lake, Milwaukee, Illinois Substation Upgrade Ravenswood Loop Signals Upgrade Project 95 th Street Terminal Improvement Program
More informationAuburn University Construction Project Update June 2010
New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,
More informationArbor Heights Elementary School. Concrete for South Building Foundation Stem Walls
Arbor Heights Elementary School Concrete for South Building Foundation Stem Walls Arbor Heights Elementary School Workers Placing Concrete for South Building Foundation Stem Walls Arbor Heights Elementary
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationAIRWAYS CROSSING PHASE II BUILDING INFORMATION 5305 McCall Way N.E. T2E 7N7
AIRWAYS CROSSING PHASE II BUILDING INFORMATION 5305 McCall Way N.E. T2E 7N7 www.airwayscrossing.ca Excellent access to Barlow Trail/McKnight Blvd. Bays starting at 4,000 sq. ft. Surface loading T5 lighting
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationConstruction Project Briefing. November 14, 2012
Construction Project Briefing November 14, 2012 Today s Presentation Loop Track Purple Line Viaducts North Red Line Stations 2 Project Title: Loop Track Renewal Project Managing Department: Power & Way
More informationMONROE COUNTY ZONING OFFICE
MONROE COUNTY ZONING OFFICE 100 South Main Street Waterloo, IL 62298 618-939-8681 Ext. 260 mczoning@htc.net PROCEDURES FOR NEW CONSTRUCTION 1. Applicant must provide a recorded copy of deed to the property
More informationMarch 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT
March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationPhase 1 Final Revised Baseline Budget Approved June 9, 2016
Phase 1 Final Revised Baseline Budget Approved June 9, 2016 1 1 Phase 1 Budget History ($ millions) May 2010 Baseline Budget July 2013 Budget Revisions June 2016 Final Baseline Budget Revisions Total Adjustments
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationBuilding Inspection Report
Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941
More informationConstruction Project Briefing. November 14, 2018
Construction Project Briefing November 14, 2018 Today s Presentation ELMI East Lake, Milwaukee, Illinois Substation Upgrade Ravenswood Loop Signals Upgrade Project 95 th Street Terminal Improvement Program
More informationPreliminary Drainage Study: Town of Hillsboro Pedestrian & Traffic Safety Project Traffic Calming Project UPC# 70587
Preliminary Drainage Study: Town of Hillsboro Pedestrian & Traffic Safety Project Traffic Calming Project UPC# 70587 Introduction: The intent of this study was to perform a preliminary drainage study of
More informationNew Main Hospital, Site Park, and Underground Garage Construction Progress Update #16
New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 Date: March 1, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org More and more
More informationCOMPREHENSIVE MONTHLY REPORT. September 2010
COMPREHENSIVE MONTHLY REPORT Dulles Corridor Metrorail Project Extension to Wiehle Avenue Metropolitan Washington Airports Authority Washington, DC October 26, 2010 PMOC Contract Number: DTFT60-09-D-00016
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationCity of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements
Table of Contents City of San Pablo Community Development Department Building Inspection Division Plan Review & Permit Requirements General Requirements Application & Processing Procedures o Plan Requirements
More informationChristopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule
Christopher Glinski Construction Management AE Senior Thesis Appendix B Project Summary /Detailed Schedule 74 Task Name ation 1 Project 546 days Mon 5/3/04 Mon 6/26/06 29 Design 243 days Mon 5/3/04 Fri
More informationProject Budget and Schedule Status Report
Item 58 Transit Program Project Budget and Schedule Status Report Construction Committee October 16, 2014 & Schedule Performance Summary Chart Slide # Project Performance Schedule Performance Comments
More informationG2-0 List of Active Ministry of Transportation of Ontario Drawings (MTOD s)
G2-0 List of Active Ministry of Transportation of Ontario Drawings ( s) DIVISION 100 - ABBREVIATIONS 101.070 Legend - Pavement Markings 01/04/1994 04/01/1994 TOS/TO For use with Pavement Marking items.
More informationConstruction Look Ahead February 2018
To our 9 th and Colorado redevelopment neighbors: Construction Look Ahead February 2018 Block 7South Exterior Bridge walkway between Block 7 South building and the existing Parking Garage the installation
More informationEngineering & Construction -- Transit Status Report. Significant Issues
ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT
More informationG2-0 List of Active Ministry of Transportation of Ontario Drawings (MTOD s)
G2-0 List of Active Ministry of Transportation of Ontario Drawings ( s) DIVISION 100 - ABBREVIATIONS 101.070 Legend - Markings 01/04/1994 04/01/1994 TOS/TO For use with Marking items. DIVISION 200 GRADING
More informationHOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene
August 25, 2017 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE & SITE Turned All East Zone Parking Lots Over to Clemson. Completed Trench Drain on Bradley Road. Completed Pouring Walls for Building D
More informationRESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS
RESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS New Construction, Addition, or Alteration All plans submitted must be prepared, sealed, and signed by a Registered Nebraska Design Professional
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationPROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California
PROGRAM COST MODEL for PEER Tall Buildings Study Concrete Structural Option Los Angeles, California March 8, 2010 PEER Tall Buildings Study Concrete Structural Option March 8, 2010 CONTENTS Page Nos. Overall
More information3.10 Hydrology and Water Quality. Environmental Setting
3.10 Hydrology and Water Quality This section describes the potential hydrology and water quality impacts associated with the proposed changes to the approved project. Environmental Setting This section
More informationTRANSPORTATION HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA
HEAVY HIGHWAY ADOT I-10 WIDENING (PINAL AIR PARK TO PICACHO PEAK TRAFFIC INTERCHANGE) RED ROCK, ARIZONA 2008/09 $52.0 M 85% SELF-PERFORMED Widen 12 miles of Interstate 10 to six lanes including the reconstruction
More informationSite Bldg Fiscal Yr System Sub-System. Verde Valley Site site 2014/15 Parking Paving. Verde Valley Site site 2014/15 Sidewalks
Site Bldg Fiscal Yr System Sub-System Site site 2014/15 Parking Paving Site site 2014/15 Sidewalks Skill Center L 2015/16 Architectural Partitions Site Site 2015/16 Parking Striping Arc Center M 2014/15
More informationHILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District
HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District Facilities and School Safety Committee Meeting September 20, 2018 Progress Update PROGRESS UPDATE Rien Construction (General
More information