Exhibit A Scope of Work and Deliverables

Size: px
Start display at page:

Download "Exhibit A Scope of Work and Deliverables"

Transcription

1 Table of Contents 1 Introduction and Background Information General Statement of Scope of Work Co-location Project Letting File Transfer Protocol (FTP) Site Project Scope Verification Team Organization Chart 6 2 Project Management DBVC Project Manager Staffing Requirements Co-location Deputy Project Manager Staffing Requirements Co-location Flexible Workforce Flexible Workforce - Project Support Staff Items Provided by the State Items Provided by Contractor Web Based Teleconferencing Tasks Deputy Project Management DBVC Staffing Approval Weekly Verification Team Meetings Performance of the Contractor Reviews Monthly Progress Report Meetings 10 3 Contract Team Design-Build Contract Manager Staffing Requirements Tasks Construction Expert Staffing Requirements Tasks Office Management and Document Control Management Staffing Requirements Tasks CPM Schedule Reviewer Staffing Requirements Tasks 15 4 Design Team Design Manager Staffing Requirements Tasks Roadway Design Review 18 Page 1 of 33

2 4.2.1 Roadway Design Engineer Roadway Design Engineer Assistant Tasks Traffic Review Staffing Requirements Tasks Structures Design Review Structures Design Engineer Structures Design Engineer Assistant Tasks Geotechnical and Foundations Review Staffing Requirements Tasks Drainage Design Verification Drainage Engineer Drainage Engineer Assistant Tasks Utility Coordination Utility Coordinator25 5 Quality Management Team Staffing Requirements Quality Manager Roadway Inspector Structures Inspector Co-location Tasks Document Control System Quality Manual Design Quality Management and Auditing As-Built Documents Inspection and Testing Plan Materials Control Schedule (MCS) Quantities and Production Tracking Construction Inspection 30 6 Environmental Team Environmental Compliance Manager (ECM) Staffing Requirements NPDES Expert: Erosion Control Inspector & SWPPP Designer Staffing Requirements Permitting Specialist Staffing Requirements Tasks Design Review Construction Inspection State Document Control System 33 Page 2 of 33

3 1 Introduction and Background Information 1.1 General Statement of Scope of Work Work with State as the Design-Build Verification Consultant (DBVC), which will be called the Contractor throughout this scope of work. Collectively the MNDOT Staff and Contractor are collectively known as the Design-Build Verification Team (DBVT) for the State Project (SP) Interstate (I)35W North MNPASS Design-Build Project (Project). Provide design verification, construction verification, and contract administration for the Project. The goal of the DBVC contract is that State receives assistance in performing the tasks necessary to verify that the Design-Build Construction Contractor (DB Contractor) is meeting all requirements of the Design-Build Conformed Contract (DB Conformed Contract) for the Project. Attend conferences or meetings necessary for close coordination during day-to-day progress of the work or as required to carry out the Project. Notify State s Project Manager immediately of any unanticipated project conditions. Maintain a record of design submittals, approvals, changes, and modifications using State s Document Control System Microsoft SharePoint. Collect, properly label or identify, and deliver to State all original calculations, drawing and sketches, electronic design files, records, reports, and other documents prepared by the DB Contractor in the performance of the work as described in this contract upon completion or termination of the Project. Provide interpretations of the plans, specifications and contract provisions. Consult with State s Project Manager when an interpretation involves complex issues or may have an impact on the cost of performing the work. When warranted, State s Project Manager may request an interpretation from the Contractor. 1.2 Co-location This project will be a full co-location project. The DBVT Team must meet the following requirements. Design-Build Project Manager. Locate in the co-located facility full-time for the duration of the Project. Design-Build Construction Manager. Locate in the co-located facility full-time for the duration of the Project. Design Manager. Locate in the co-located facility full-time for the duration of the design. Construction Quality Manager. Locate in the co-located facility full-time for the duration of construction during the Project. Lead Roadway Engineer. Locate in the co-located facility full-time for the duration of the design. Lead Structural Engineer. Locate in the co-located facility full-time for the duration of the structural design. Contract Environmental Compliance Officer. Locate in the co-located facility 50 percent of the time during design and 75 percent of the time for the duration of the Project. Maintenance of Traffic (MOT) Engineer Locate in the co-located facility full-time during the duration of the MOT design and the first five days after any traffic switch Intelligent Transportation System (ITS) Engineer Locate in the co-located facility full-time during the duration of the ITS design and full-time during the ITS installation and testing activities Traffic Engineer Locate in the co-located facility full-time during the duration of the traffic design. Quality Manager Locate in the co-located facility full-time for the duration of the Project. Page 3 of 33

4 Design Quality Manager Locate in the co-located facility full-time for the duration of the design. Critical Path Method Scheduler Locate in the co-located facility one day a month for schedule comment resolution meetings. Permit Specialist - Locate in the co-located facility 50 percent of the time during design. Hydraulic Engineer/Water Resource Engineer Locate in the co-located facility full-time during the duration of the storm water design. Utility Coordination Manager. Locate in the co-located facility full-time during the first year of activities and then co-located 50 percent of the time for the remainder of the project. Public Information Liaison. Delegated personnel located in the co-located facility 25 percent of the time for the duration of the Project. Document Manager. Locate in the co-located facility full-time during the duration of the Project. Safety Manager. Locate in the co-located facility full-time for the duration of construction during the Project. Erosion Control Supervisor. Locate in the co-located facility full-time for the duration of construction during the Project. Signing Design Engineer. Locate in the co-located facility full-time for the duration of the sign design. Throughout this scope of work, some roles of the DBVT are designated as being co-located and others are not. Co-located personnel are expected to be physically located in the project office for the time indicated for each role. Co-located personnel will have a physical workspace, computer, phone and other common office supplies at the co-location office. Keep in mind, all personnel on the DBVT are obligated to meet the requirements of the Flexible Workforce section of this scope. In order to effectively manage the budget for the DBVT, co-located personnel will be expected to inform the Verification Consultant Project Manager & Design-Build Contract Manager and the State Project Manager, if co-location requirements are excessive based on the current verification activities of that role. If, in agreement with the State s Project Manager, it is decided that the co-located role can be just as effectively performed partly from the team member s home office then it may be determined that the co-location requirements be temporarily relaxed. Personnel that are not to be co-located at the project office can perform their role from their home office. However, non-co-located personnel are required to report to the project office or project site as needed for specific meetings, over the shoulder reviews, inspections, and other duties in a timely and efficient manner to fulfill the obligations of their roles on the DBVT. It is incumbent upon all DBVT members to utilize current web-conferencing best practices to be an effective resource to the DBVT and the DB Contractor during meetings, over the shoulder reviews and questions that arise from the DB Contractor for the DBVT. The purpose of a co-location office is to minimize difficulty of communication between the DBVT and the DB Contractor, so technology cannot be a hindrance in this relationship. If web-conferencing is not working efficiently to communicate between the two teams, the role member will be expected to be present at the co-location office as needed so the DB Contractor is not unduly delayed. It is important that any phone or web conference technical difficulties be minimized or eliminated so that co-location can be effectively minimized for each role. 1.3 Project Letting The Project letting is September 12, Page 4 of 33

5 1.4 File Transfer Protocol (FTP) Site When this scope refers to using FTP sites, the Contractor must use the following procedures: Contractor placing files on the State FTP site 1) On your computer create a folder that contains all the information you want to transmit. Name the folder as follows: YYYYMMDD_SPXXXX-XX. For example: _SP ) Open Windows Explorer (not Internet Explorer) 3) Type or copy/past the following URL in the Address Box (the URL is case sensitive): ftp://ftp2.dot.state.mn.us/pub/incoming/metrowatersedge 4) The folder will appear empty, and no contents will be visible. Copy/Paste the desired folder to this location. Once the folder is uploaded, an internal, State user can download the folder. 5) Notify the intended recipient by that the folder has been uploaded and provide the folder name. Note: Once the file(s) are uploaded to the site, they will disappear. This is an automatic process to hide the files from outside users. Troubleshooting: Sometimes the files will not upload and error messages will occur. Often it is only one file that is being rejected by the system. Try uploading only the large files and ing the small files and see if that works. Contractor retrieving files on the State FTP site The State employee will send an to the Contractor stating that they uploaded a folder or file and they will provide the name of the folder or file. It is possible to locate files that have been placed on MnDOT Metro District s FTP site using the following directions: 1) Open Internet Explorer or Windows Explorer 2) Type or copy/paste the following URL in the Address Box (note that this is case sensitive): ftp://ftp2.dot.state.mn.us/pub/outbound/metrowatersedge 3) To open files: Double (left) click a file to open it. If a menu pops up, select OK without supplying a password. 4) To save files either: Save a file as would be normal for the program while it is open, or Right click a file in the menu and select Save Target As. Troubleshooting: If you are unable to view files you may need to change a setting within Internet Explorer. To do this open the Tools pull-down menu, select Internet Options, then click on the Advanced tab at the top of the new window. Click and place a checkmark besides Enable FTP folder view (outside of Internet Explorer) under the Browsing header. Click the Apply button at the bottom of the window, then close the window. If this does not solve the problem, turn on Compatibility View by opening the Tools pull-down menu and selecting Compatibility View. 1.5 Project Scope Add a lane to I35W, which will be a MnPASS lane, from County Road (CR) C in Roseville to Lexington Avenue (Ave) (CR 17) in Blaine. Repave I35W and ramps with an unbonded concrete overlay from CR C in Roseville to 0.1 mile north of Sunset Ave (CR 53) in Lino Lakes. Project length is about 12 miles. Replace the four I35W bridges at CR C and adjacent Railroad (RR), replace the I35W bridge at CR I, Page 5 of 33

6 and do bridge rehabilitation to the bridge from northbound I35W to westbound United States Highway (US) 10. Install seven separate noise walls with a total length of about 4.1 miles. Approximate Project cost: $200 million. To find additional project information related to the Project, refer to the project website located here: Project information such as design files, layouts and more can be found on the project FTP site, which is found on the project website. Download and review all files on the project FTP site. 1.6 Verification Team Organization Chart Exhibit B is the DBVT organization chart, and shows how the State will staff the DBVT for this project. It graphically shows the chain of command. It also shows how the Contractor staff described in this contract interacts with the State staff. 2 Project Management Perform all work necessary to manage this DBVC Contract and its personnel. Perform all work necessary to assist with managing the DB Conformed Contract. 2.1 DBVC Project Manager This person is responsible for managing the consultant contract Staffing Requirements Supply one person, in total, to perform the duties of the DBVC Project Manager. The person serving as the DBVC Project Manager may also serve as either the Design Manager or the DB Contract Manager Co-location The DBVC Project Manager is not required to be co-located. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W. 2.2 Deputy Project Manager This person is responsible for performing the duties of the State s Project Manager as needed. This person is not expected to have experience in Construction Management. Work includes the proper coordination and management of contract administration activities with all parties involved in accomplishing completion of a Minnesota Department of Transportation (MnDOT) construction project. This may include some or all of the following: 1) Ensure that Contractor performs all work in accordance with the Contract. 2) Maintenance of complete, accurate records of the activities and events relating to a project. 3) Interpretation of plans, specifications and contract provisions of a project Staffing Requirements Supply one person, in total, to perform the duties of the Deputy Project Manager. The person serving as the Deputy Project Manager must be either the Design Manager or the DB Contract Manager. Page 6 of 33

7 2.2.2 Co-location The Deputy Project Manager will be co-located with the State s Project Manager and is expected to be in the co-located facility full-time for the duration of the project. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W. 2.3 Flexible Workforce DBVC personnel approved by the State s Project Manager are considered by the State to be committed to performing services for the durations listed in this scope of work. Any changes will require written approval from the State s Project Manager and include both adding additional staff and reducing staff. The Contractor will be advised of the official Notice of Award of the Design-Build Contract and will be ready to fully staff all personnel on the DBVT for the project within one week after notification. No personnel will be assigned until written notification by the State Project Manager has been issued. If the DB Contract is suspended for any reason, the Contractor s forces will be adjusted to correspond with the type of cessation, either complete or partial suspension. Contractor will continuously look ahead to fully understand what type of staff are needed and in what numbers. The Contractor s schedule will be dictated by the DB Contractor s schedule. Contractor will provide a flexible work force so that only those staff that can be fully utilized during any given project activity are present and billing hours to the Contract. Contractor will continuously monitor all activity to ensure that all work carried out is within the agreed scope and completed with resources that can complete the work as budgeted. In the event it becomes necessary to complete work outside the original scope of work, the Contractor s Project Manager will notify State s Project Manager immediately before proceeding. No work outside the original scope will be done without written authorization from State s Project Manager. Throughout this scope of work, the availability in the co-located facility will be defined as full-time (40 hours per week) or part time (less than 40 hours per week) for a specified duration. Throughout the course of the Project, it may become evident that two or more Contractor roles would be more efficiently staffed by a single qualified person. If this situation arises, the Contractor can make a request to the State s Project Manager to modify the staff by combining roles. The State s Project Manager will evaluate the experience and workload of the remaining staff member and will make a determination of whether the roles should be combined. If multiple roles are allowed to be staffed by a single person, the State Project Manager may reverse that decision at a later date, if circumstances call for more attention to those roles than the single person can effectively handle. Conversely, it is expected that the Contractor have staff available to fulfill the obligations of each role described within this Contract. Certain roles are defined as being co-located with the DBVT office and have estimates of the amount of time expected to be co-located per week. To meet the requirements of this Flexible Workforce section, team members that are co-located and even those that are not co-located may need to be present at the co-location office more often than estimated in order to efficiently and effectively fulfill the duties of those roles so that the DB Contractor is not unduly burdened by the verification activities. When the DB Contractor s operations on the Project diminish, the Contractor will reduce the number of its personnel assigned to the Project as appropriate. Any adjustment of Contractor forces as recommended by the State s Project Manager will be accomplished within one week after notification. The State s Project Manager will provide said notification to the Contractor in writing, and the Contractor will provide confirmation of notification in writing Flexible Workforce - Project Support Staff The Responders will only bid hours for those positions described in this scope of work. In reality, the Contractor will need to leverage additional project support staff, whether within their company or through subconsultants, to assist the various roles on the DBVT. The additional staff are expected to be available to Page 7 of 33

8 help with the task of reviewing plans and calculations, use MicroStation and GEOPAK to draft alternative designs/create quantities to counter claims by the DB Contractor, and use other software listed in this scope to evaluate products the DB Contractor creates using that software Uniform Bid for Hours The hours for Project support staff will not be included in the Uniform Bid for Hours. Refer to requirements under the Flexible Workforce and Monthly Progress Reports Meetings herein Co-location The support staff for any roles will not be co-located with the State Project Manager. They may reside at their normal business office. Arrange meetings via a web based teleconferencing system. 2.4 Items Provided by the State State will provide office space, phone, computer, basic furniture, and access to State servers and printers. Expendable office supplies will be paid for by State, and will be ordered by the Contractor through the State supply system. Expendable office supplies are defined as items that generally are used one time and then discarded and include, but are not limited to: staples, rubber bands, note pads, paper, folders, pens, and clips. 2.5 Items Provided by Contractor Provide durable office supplies and reference material for their own employees as needed. Durable office supplies are defined as items that can be reused and include, but are not limited to: staplers, tape dispensers, scissors, rulers, three hole punches, staple removers, and mechanical pencils. Provide own equipment and testing supplies for all testing of component materials used on the Project. Provide, service, and maintain a sufficient number of clearly identifiable vehicles to maintain the necessary coverage of the Project and to adequately transport personnel and equipment. The vehicles will have the necessary safety features to be within the work zone. Contractor will be solely responsible for risk of loss of or damage to vehicles, and will replace or repair vehicles at its own cost. Contractor will be required to obtain adequate insurance coverage for such loss or damage. Provide service and maintain cellular phones for all Contractor field personnel assigned to the Project. A list of these phone numbers will be available to State s Project Manager. Contractor will be solely responsible for risk of loss of or damage to cellular phones, and will replace or repair cellular phones at its own cost. 2.6 Web Based Teleconferencing Provide the means for the DBVT to meet via web based teleconferencing. Such a system will allow participants to log into a website to view the desktop of the meeting organizer. Participants will be able to take control of the virtual desktop as needed to point out things on the file being displayed. Voice communication will occur via phone teleconferencing. 2.7 Tasks Deputy Project Management Assist the State s Project Manager to complete the duties of the State s Project Manager, which includes leading the team that is responsible for achieving the project objectives. Page 8 of 33

9 2.7.2 DBVC Staffing Approval Utilize only personnel who are qualified by experience and education. Submit, in writing, to the State s Project Manager the names of all personnel to be considered for assignment to the project, together with detailed resumes with respect to education, experience (including specific durations) and qualification of each individual. Minimum qualifications for the Contractor personnel are set forth in this Request for Proposal (RFP). The State may require that these minimum qualifications be altered in instances when the unique nature of the work requires specific specialized skills. No personnel will be assigned to this Project by the Contractor until the qualifications of each person proposed have been reviewed and approved in writing by the State s Project Manager. The Contractor s personnel approval request will be submitted at least two weeks prior to the date an individual is scheduled to report to work. An individual previously approved by the State s Project Manager whose performance is later determined by the State to be unsatisfactory will be replaced by the Contractor. Be responsible for obtaining proper licenses for equipment and personnel operating equipment when licenses are required. (A) Deliverable: DBVC Personnel Approval Request. One request may include multiple people. (B) Format: Electronic Microsoft Word 2013 document (docx extension). Deliver to State s Project Manager electronically either by or FTP site. (C) Due: At least two weeks prior to the date an individual is scheduled to report to work. (D) Standard: Written as a letter/ . (E) State Review: Five business days. (F) Contractor Update: Update and resubmit the deliverable to State within five business days of receiving State review comments Weekly Verification Team Meetings Contractor s Project Manager will schedule and if requested, facilitate weekly meetings with State s Project Manager and the entire DBVT. Meetings will be held at the co-housed facility. Any personnel not co-housed may attend the meeting via conference call or web based teleconference. The MnDOT conference call system may be used to reduce costs if web based teleconferencing is not required for a particular meeting. (A) Deliverable: A weekly verification team meeting. Meeting minutes are not required. (B) Format: Meet in co-housed office conference room. (C) Due: Weekly. (D) Standard: Intentionally left blank. Minutes are not required Performance of the Contractor Reviews During the life of the Project, the State s Project Manager may conduct reviews of the various phases of the Contractor s performance and operations. Reviews will be to determine compliance and the sufficiency with which procedures are being effectively applied to assure that this Contract s scope of work is being performed in substantial conformity with State policies, plans, specifications, and DB Conformed Contract requirements. The Contractor will cooperate and assist the State s Project Manager, or his representative(s), in the conduct of the reviews. When deficiencies are indicated in a review, remedial action will be immediately implemented by the Contractor in conformance with the State s Project Manager s recommendations. The State s Project Manager s remedial recommendations and the Contractor s actions will be properly documented by the Page 9 of 33

10 Contractor in a Performance of the Contractor Review Report. In general, remedial action will be required commensurate with the degree and nature of the deficiencies cited. Additional compensation will not be allowed for remedial action taken to correct deficiencies by the Contractor. Remedial actions may include any or all of, but are not necessarily limited to, the following actions: 1) Further subdivide assigned design review responsibilities, reassign design review or assign additional personnel. The Contractor will comply with this action within 24 hours of notification by the State s Project Manager. 2) Replace personnel whose performance has been determined by the State s Project Manager to be inadequate. When directed by the State s Project Manager, any person whose performance has been determined to be unsatisfactory will be immediately removed. (A) Deliverable: Performance of the Contractor Review Report. (B) Format: Electronic Microsoft Word 2013 document (docx extension) delivered via or FTP site (C) Due: Within five business days of the reviews occurrence. (D) Standard: A formal business report. (E) State Review: Within five business days. (F) Contractor Update: Five business days of receipt of State review of deliverable Monthly Progress Report Meetings Contractor s Project Manager, when requested, will meet with State s Project Manager to review the monthly progress reports and invoices. Contractor s Project Manager will solicit feedback from State s Project Manager to assess whether all services meet or exceed the requirements of the project. If needed, Contractor will direct changes to personnel and/or procedures to correct identified deficiencies and implement opportunities for improvements. (A) Deliverable: An informal meeting with the monthly progress reports, invoices, and s-curves supplied. (B) Format: See requirements in Contract and in this Scope of Work. (C) Due: Monthly at the same time as the contract progress reports and invoices. (D) Standard: Intentionally left blank. Meeting minutes are not required. (E) State Review: During the meeting. (F) Contractor Update: Update progress reports, invoices, and s-curves as needed within five business days of State review Contract S-Curve In addition to the monthly progress reports and invoices create a contract s-curve to graphically depict a summary of the budget status. The contract s-curve shows how the project budget is projected to be used over the life of the project and compares actual expenditure versus the budget. Use this information to determine if the project can be completed within budget or if amendments are needed to complete the work load. (A) Deliverable: Monthly contract s-curve. (B) Format: The s-curve analysis can be created in any program, but the final printout delivered to the State must be in Adobe PDF format. (C) Due: Monthly at the same time as the contract progress reports and invoices. (D) Standard: Intentionally left blank. Page 10 of 33

11 (E) State Review: At monthly progress report meeting. (F) Contractor Update: Five business days of receipt of State review of deliverable. 3 Contract Team 3.1 Design-Build Contract Manager Assist with the evaluation of Value Engineering (VE) Proposals, change order management, and preparation for dispute resolution and litigation Staffing Requirements Provide one person, in total, to perform the duties of the Design-Build Contract Manager Co-location The DB Contract Manager will be co-located with the State s Project Manager and is expected to be in the co-located facility part time. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W Tasks Evaluation of Value Engineering Proposals Assist with the evaluation of VE Proposals and analysis of Project Changes. (A) Deliverable: Evaluation of Value Engineering Proposals (B) Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe PDF. (C) Due: As needed. (D) Standard: Conformed Contract and MnDOT Contract Administration Manual. (E) State Review: Five business days of receipt of Contractor deliverable. (F) Contractor Update: Five business days of receipt of State review of deliverable Change Order Management Assist the Construction Manager as needed in the creation, management, and investigation of designbuild contract change order documents. Track the status of each change order, and send documents to the correct recipients as the process dictates. Inform the State s Project Manager if the due dates at each step in the process are not being met. Review and investigate all change orders. Review and investigation includes all work necessary to confirm that the change order is accurate and may involve, review of plans, review of site conditions, review of calculations, review of DB Contractor allegations and claims, and etc. May also need to verify the claims being made or provide an alternative solution. This verification will be done by creating independent cost estimates to be used as a comparison to the DB Contractor s claims. The Contractor will use all Contractor staff described in this contract as needed to assist with this work. (A) Deliverable: Change Orders. (B) Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe PDF. (C) Due: As needed. (D) Standard: Conformed Contract and MnDOT Contract Administration Manual. (E) State Review: Five business days of receipt of Contractor deliverable. (F) Contractor Update: Five business days of receipt of State review of deliverable. Page 11 of 33

12 Preparation for Dispute Resolution or Litigation Assist State in preparing for dispute resolution or litigation regarding the Project. This may require assembling documents for review by others and tracking status of dispute or litigation and writing letters as needed. Review and investigate all disputes or litigation. Review and investigation includes all work necessary to confirm that the dispute or litigation is accurate and may involve, review of plans, review of site conditions, review of calculations, review of DB Contractor allegations and claims, and etc. May also need to verify the claims being made or provide an alternative solution. This verification will be done by creating independent cost estimates to be used as a comparison to the DB Contractor s claims. The Contractor will use all Contractor staff described in this contract as needed to assist with this work. (A) Deliverable: Assembled documents with letters with independent cost estimates. (B) Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe PDF. (C) Due: As needed as determined by the State. (D) Standard: Conformed Contract and MnDOT Contract Administration Manual. (E) State Review: Five business days. (F) Contractor Update: Five business days. 3.2 Construction Expert Assist State s Construction Manager. Provide expert advice and support regarding construction management including inspections and materials testing. The work includes resolution of field problems as quickly as possible. Generally, field problems are any types of difficulties encountered during construction through circumstances that require some degree of engineering evaluation and decision. Field problems may involve situations such as: plan omissions, out tolerance work, out of specification materials, structural defects, accidental damage, underground obstructions, etc. These problems may have a significant impact on the execution, progress or cost of the project. It is therefore of paramount importance that they be resolved expeditiously. Work includes the services necessary to assure that proper coordination and management of the construction inspection, surveying, materials sampling & testing and contract administration activities are coordinated with all parties involved in accomplishing completion of a Minnesota Department of Transportation (MnDOT) construction project. This may include some or all of the following: 1) Ensure that Contractor performs all work in accordance with the Contract. 2) Maintenance of complete, accurate records of the activities and events relating to a project. 3) Serve as Compliance Officer to ensure Contactor s compliance with Contract requirements, including Equal Employment Opportunity (EEO) Affirmative Action plans and Disadvantaged Business Enterprise (DBE) requirements. 4) Proper documentation of significant changes to a project. 5) Interpretation of plans, specifications and contract provisions of a project. 6) Making recommendations to State to resolve disputes which arise in relation to the Contracts. 7) Resolution of field problems, including situations such as: out of place piling, out tolerance work, out of specification materials, structural defects, accidental damage, underground obstructions, etc. 8) Hiring and managing of qualified sub-consultants in some or all of the following work types: Grading & Base, Bituminous and Concrete Inspection; Bridge Page 12 of 33

13 Inspection; Construction Surveying; Materials Sampling & Testing Field, Plant Inspection/Bituminous, and Plant Inspection/Concrete and Public Involvement. 9) Evaluation of Value Engineering Proposals and analysis of Project Changes. 10) Assist State in preparing for dispute resolution or litigation regarding the Project Staffing Requirements Provide one person, in total, to perform the duties of the Construction Expert Co-location Will be co-located and is expected to be in the co-located facility full time during construction. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W Tasks Construction Management Assist with construction management. (A) Deliverable: Well organized construction inspection reports. (B) Format: State s document control system. (C) Due: Continuous throughout project. Final delivery occurs when DBVC contract ends. (D) Standard: DB Conformed Contract. 3.3 Office Management and Document Control Management This work will assist the State s Project Manager with the document management and administrative support. Become an expert in using the State s document control management system. Train both State and DB Contractor staff to use State s document control management system. State will perform the initial training for the system. Serve as Compliance Officer to ensure Contactor s compliance with Contract requirements, including Equal Employment Opportunity (EEO) Affirmative Action plans and Disadvantaged Business Enterprise (DBE) requirements Staffing Requirements Provide one person, in total, to perform the duties of the Office Manager and Document Control Manager (OMDCM) Co-location The OMDCM will be co-located with the State s Project Manager, and is expected to be in the colocated facility full time. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W Tasks Document Control System The OMDCM will thoroughly understand all functions of the State document control system. They will be responsible for organizing the documents in the system and enforcing that all documents are properly submitted. They will coordinate document control items with the Design-Builder s document control manager to ensure that submittals from the Design-Builder are done properly. State will perform the initial training to both the DBVC and Design-Builder. The OMDCM will be responsible for identifying document Page 13 of 33

14 control procedure errors in a submittal from the Design-Builder and then will inform and train the Design- Builder, so the Design-Builder corrects their errors and ultimately begins making submittals following the correct procedures. (A) Deliverable: A well maintained and organized document control system for this project. (B) Format: Microsoft SharePoint (C) Due: Continuous throughout project. Final delivery occurs when DBVC contract ends. (D) Standard: DB Conformed Contract Administration Support Provide miscellaneous administration support activities including but not limited to document drafting & formatting, reviewing letters, filing, copying, answering office phone, taking messages, and mail processing. (A) Deliverable: Letters, filing, copying and mail processing, etc. (B) Format: Electronic Microsoft Word 2013 document (docx extension), hard copies, and Adobe PDF. (C) Due: Continuous throughout project. Each item will have its own deadline. Contractor must adapt to the work load to meet deadlines. Filing of a specific item should occur within 5 business day of the item being received. (D) Standard: Intentionally left blank Affirmative Action/Equal Employment Opportunity (AA/EEO) Contract Compliance Serve as Compliance Officer to ensure Contactor s compliance with Affirmative Action/Equal Employment Opportunity (AA/EEO) plans. The Contractor will arrange a meeting with the State s Project Manager no later than two weeks after the DB Contract award to determine exact reporting requirements needed for this task. Contractor will schedule and facilitate monthly meetings with State s Project Manager to review AA/EEO requirements. (A) Deliverable: Monthly Compliance Reports and other documentation. (B) Format: Electronic Microsoft Word 2013 document (docx extension) and hard copies. (C) Due: Monthly (D) Standard: Conformed Contract and MnDOT Contract Administration Manual. (E) State Review: One day. Review will occur at the monthly meeting. (F) Contractor Update: Five business days DBE Contract Compliance Serve as Compliance Officer to ensure Contactor s compliance with DBE requirements. The Contractor will arrange a meeting with the State s Project Manager no later than 2 weeks after the Design-Build Contract award to determine exact reporting requirements needed for this task. Contractor will schedule and facilitate monthly meetings with State s Project Manager to review DBE requirements. (A) Deliverable: Required forms and reports as described in the MnDOT Contract Administration Manual. (B) Format: Electronic Microsoft Word 2013 document (docx extension) and hard copies. Page 14 of 33

15 (C) (D) (E) (F) Due: See MnDOT Contract Administration Manual. Standard: Conformed Contract and MnDOT Contract Administration Manual. State Review: One day. Review will occur at the monthly meeting. Contractor Update: Five business days. 3.4 CPM Schedule Reviewer Review the Design-Builder s CPM schedules in accordance with the DB Conformed Contract. The Design Builder is required to using State s Enterprise Project Management System (EPMS) Primavera P6 software, herein referred to as P6, and the Contractor is required to use the same software. Contractor s review may include the following with specific tasks directed by the State s Project Manager: 1) A comparison of the schedule s content as it relates to the requirements of the DB Conformed Contract. 2) An evaluation of its completeness of the work and all areas of the Project. 3) A review of the inclusion of the required deliverables during the design process. 4) An evaluation of the Design-Builder s applied logic, with attention paid to float suppression and sequestering techniques such as excessive lags, excessive durations, non-contractual constraints and non-tangible relationships. 5) Criticality will be reviewed for specified compliance, and the critical path will be reviewed for reasonableness. 6) The cost and resource loading of the schedule will be reviewed to ensure the total cost of the activities rolls up to equal the Contract price. 7) Activities will be reviewed for cost and resource assignments. They will also be reviewed for imbalances amongst like activities. 8) Cash flow will be reviewed for front loading. 9) In-depth schedule analysis, including a comparison of the schedule update against the baseline for changes between the two. 10) The critical path and overall progress will be monitored and reported on. 11) The Baseline Schedule s cash flow will be graphed to be used as a measure tool to reflect the planned outlay compared to the actual. 12) Monthly review of DB Contractor s invoices to verify payment requested matches work shown as completed in the monthly updated CPM schedule. 13) Review of DB Contractor s Time Impact Analysis. 14) Assist in reviewing, coordinating and processing contractor Partial Estimate pay vouchers. 15) Collaborate with other verification team members to review and analyze recovery schedules as required by the Design Builder within the CPM Specifications Staffing Requirements Provide one or more persons to perform the duties of the CPM Schedule Reviewer Co-location Locate in the co-located facility one day a month for schedule comment resolution meetings Tasks Baseline schedule review Review and check the DB Contractor s baseline schedule. Page 15 of 33

16 (A) Deliverable: Comments entered into DCS and verification that all comments were addressed. (B) Format: Microsoft SharePoint (C) Due: According to DB Conformed Contract. (D) Standard: DB Conformed Contract and State DCS Training Monthly invoice and schedule review Review and check the DB Contractor s monthly invoices and schedule. (A) Deliverable: Comments entered into DCS and verification that all comments were addressed. (B) Format: Microsoft SharePoint (C) Due: According to DB Conformed Contract. (D) Standard: DB Conformed Contract and State DCS Training Time Impact Analysis review Review and check the DB Contractor s Time Impact Analysis. (A) Deliverable: Comments entered into DCS and verification that all comments were addressed. (B) Format: Microsoft SharePoint (C) Due: According to DB Conformed Contract. (D) Standard: DB Conformed Contract and DCS Training Recovery Schedule review Review and check the DB Contractor s Recovery Schedule. (A) Deliverable: Comments entered into State DCS and verification that all comments were addressed. (B) Format: Microsoft SharePoint (C) Due: According to DB Conformed Contract. (D) Standard: DB Conformed Contract and DCS Training. 4 Design Team 4.1 Design Manager Manage the verification of the DB Contractor s design by making sure the right specialized engineers are reviewing the relevant plans, making sure designs are well coordinated across all disciplines, maintaining a consistent and predictable enforcement of the DB Conformed Contract, and meeting all verification responsibilities of the DB Conformed Contract Staffing Requirements Provide one person, in total, to perform the duties of Design Manager. Page 16 of 33

17 Co-location Will be co-located during design activities. At this time the location of the office is unknown, but is expected to be within three miles of CR J and I35W Tasks Design Review Review and check the Design-Builder s plans for conformance with the DB Contract. The Contractor will use the procedures for checking plans and calculations described in the DB Conformed Contract Book 2, Section 5, Exhibit A Quality Management Template. Must pay special attention to making sure that all the separate plans and disciplines are well coordinated with each other. For example, understanding that a change on the Roadway Plans may impact the Drainage, Bridge or ITS plans and vice versa. The Design Manager reviews all comments for each Release for Construction package for consistency and conformance to the DB contract, does a cursory review of plans sets, but leaves the detailed checking of plans and calculations to the specialized engineers. Perform coordination with all project participants, maintenance of records, interpretations of plans and specifications, and recommendations regarding dispute resolution. Must have general familiarity with the DB Conformed Contract. Must have general familiarity in understanding the requirements of MnDOT manuals, standards and specifications related to all disciplines. Attend all conferences or meetings as needed. Coordinate their review with the relevant external stakeholders with the requirement of obtaining the stakeholders acceptance of the design and plans. Stakeholders include Cities, Counties, and permitting agencies. Manage the review and checking of the Design Builder s plans for conformance to the design concept upon which the preliminary plans were prepared. Verify that the final plans are prepared in accordance with the DB Conformed Contract including current State standards and practices. These reviews will include overthe-shoulder plans, release for construction plans, notice of design changes, field design changes, and as-built plans. Contractor will use the following criteria to check and review the plans: 1) Review A comparative analysis for agreement with standard practice, conformance to the contract requirements, agreement with similar structures, all with application of professional judgment. Mathematical analysis is not specifically required, but may be necessary where a discrepancy appears likely. Work will include an analysis of the Design-Build Contractor s methods, assumptions, and calculations. 2) Check Contractor will check mathematical computations provided by the Design- Build Contractor and provide independent calculations when an issue occurs during the check. (A) Deliverable: Hardcopy plan sets that show checked, corrected, and verified redlines corrections. (B) Format: Hardcopy plans and calculations. (C) Due: Continuous throughout project and as described in the DB Conformed Contract. Final delivery occurs when DBVC contract ends. (D) Standard: DB Conformed Contract. Page 17 of 33

18 As-Built Documents Within 15 calendar days of the DB Contract Award, the Contractor will hold an As-Built Document coordination meeting with the DB Contractor. At this meeting the DB Contractor will explain how they will meet the conformed contract requirements for delivering as-built documents. The Contractor will audit the as-built plans upon their delivery for conformance to the conformed contract. (A) Deliverable: A meeting to determine DB Contractor s proposal for as-built documents. Contractor will provide a write-up explaining how the DB Contractor will organize the as-built documents. (B) Format: Electronic Microsoft Word 2013 document (docx extension) and hard copies. (C) Due: Meeting to occur 15 calendar days after DB Contract Award and write-up is due within 15 calendar days of the meeting. (D) Standard: Intentionally left blank. (E) State Review: Five business days. (F) Contractor Update: Five business days State Document Control System Thoroughly understand the Submittal Control methods for using the Microsoft SharePoint Document Control System. They will be responsible for entering comments, and reviewing and tracking responses in the DCS for all design related issues. State will perform the DCS training. (A) Deliverable: Enter comments, review and track responses in DCS. (B) Format: Microsoft SharePoint (C) Due: Continuous throughout project. Final delivery occurs when DBVC contract ends. (D) Standard: State Training and DB Conformed Contract. (F) Contractor Update: Continuous 4.2 Roadway Design Review Supply a team of people to perform all verification tasks related to roadway design, which includes all requirements covered under the DB Conformed Contract, Book 2. Perform all verification tasks related to roadway design, which includes all requirements covered under the DB Conformed Contract, Book 2. Duties include coordination with all project participants, maintenance of records, interpretations of plans and specifications, and recommendations regarding dispute resolution. The Contractor will have general familiarity with the DB Conformed Contract. This position must be an expert in understanding the requirements of the DB Conformed Contract, Book 2, Section 1, 2, 5, 7, 9, 10, 11, 14, 20; and MnDOT manuals, standards and specifications related to roadway design. Attend all meetings as needed. Verify that the Design-Builder s plans appear to meet the requirements of the DB Conformed Contract including current State standards and practices. These reviews will include over-the-shoulder reviews, release for construction plans, notice of design changes, field design changes, and as-built plans. Thoroughly understand the Submittal Control methods. They will be responsible for entering comments, and reviewing and tracking responses in the Microsoft SharePoint Document Control System for all design related issues. State will perform the DCS training. Page 18 of 33

Exhibit A DRAFT Scope of Work and Deliverables 11/21/2016

Exhibit A DRAFT Scope of Work and Deliverables 11/21/2016 Exhibit A DRAFT Scope of Work and Deliverables 11/21/2016 MnDOT Contract No. XXXXXX 1 Table of Contents 2 General Statement of Scope of Work... 4 2.1 Targeted Group Business and Vet Owned Business Cooperation

More information

Exhibit A Scope of Work and Deliverables

Exhibit A Scope of Work and Deliverables DRAFT SUBJECT TO CHANGE MnDOT Contract No. xxxx Exhibit A Scope of Work and Deliverables Table of Contents 1 General Statement of Scope of Work... 4 1.1 Co-location 4 2 Project Letting... 4 3 FTP Site...

More information

Exhibit A Scope of Work and Deliverables. 2 General Statement of Scope of Work Co-location... 3

Exhibit A Scope of Work and Deliverables. 2 General Statement of Scope of Work Co-location... 3 Exhibit A Scope of Work and Deliverables 1 Table of Contents 2 General Statement of Scope of Work... 3 2.1 Co-location... 3 3 Current Letting of the Design-Build Projects... 3 4 FTP Site... 3 5 Project

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work Mn/DOT Contract No. 05497 PROJECT OVERVIEW The Minnesota Department of Transportation (MnDOT) requires the services of a Contractor for construction lead inspection, materials testing

More information

Post Letting Services Master Contract Program Scope of Work Appendix A

Post Letting Services Master Contract Program Scope of Work Appendix A I. Construction Inspection Grading and Base, Bituminous and Concrete 1. For this Program, inspection work is intended to assure that grading and base, bituminous and concrete work performed on state construction

More information

Exhibit A Mn/DOT Contract No SCOPE OF WORK AND DELIVERABLES

Exhibit A Mn/DOT Contract No SCOPE OF WORK AND DELIVERABLES SCOPE OF WORK AND DELIVERABLES Construction Oversight for US 52 & CSAH 9 Interchange Design-Build Project in Goodhue County State Project (SP) 2506-72 PROJECT OVERVIEW The State of Minnesota has identified

More information

Exhibit A Scope of Work

Exhibit A Scope of Work 1.0 Purpose: The purpose of the contract is to provide a Construction Project Engineer, Senior Inspector Roadway, and two certified G&B inspectors, as needed, to assist State staff on S.P. 0120-24 during

More information

SCOPE 1.0 General Requirements

SCOPE 1.0 General Requirements SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT staff

More information

DRAFT SCOPE 1.0 General Requirements

DRAFT SCOPE 1.0 General Requirements DRAFT SCOPE 1.0 General Requirements This section outlines a general list of the responsibilities and requirements for the GEC. It is anticipated that the GEC will be used to support and supplement MnDOT

More information

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP &

TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP & TH 25 Bituminous Mill, Full Depth Reclamation and Overlay SP 4910-29 & 0504-14 Contract No. 1002252 Project Overview is in need of professional and technical assistance to provide detail design for State

More information

Proposers are encouraged to view background information on the RICWS Design Build project at the following website:

Proposers are encouraged to view background information on the RICWS Design Build project at the following website: MnDOT Contract No. 02665 RICWS Oversight The State of Minnesota, through its Department of Transportation (MnDOT), requests proposals to assist the Department with design, testing, and construction oversight

More information

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN

EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN EXHIBIT A SCOPE OF SERVICES FOR DISTRICTWIDE CONSULTING ENGINEERNG SERVICES STRUCTURES DESIGN Financial Project ID: 417069-1-32-04 Work Program Item No.: N/A Federal Aid Project ID: County/Section No.:

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

EXHIBIT 2-2-C SCHEDULES

EXHIBIT 2-2-C SCHEDULES EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,

More information

This topic focuses on how to prepare a customer for support, and how to use the SAP support processes to solve your customer s problems.

This topic focuses on how to prepare a customer for support, and how to use the SAP support processes to solve your customer s problems. This topic focuses on how to prepare a customer for support, and how to use the SAP support processes to solve your customer s problems. 1 On completion of this topic, you will be able to: Explain the

More information

Exhibit A Scope of Work and Deliverables

Exhibit A Scope of Work and Deliverables General Statement of Scope of Work Perform steps 1 through 9 of the State Utility Coordination Manual (UCM). Conduct all work necessary to meet the requirements for creating certified Subsurface Utility

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01 40 00 PART 1 - GENERAL 1.1 SUMMARY A. This section covers the establishment and operation of the Contractor s Quality Control (CQC) system as specified by the General Conditions of the Contract.

More information

Design-Builder Peformance Evaluation (DBPE)

Design-Builder Peformance Evaluation (DBPE) Design-Builder Peformance Evaluation (DBPE) There are five (5) major components of the DBPE document. Each component has multiple categories to facilitate performance evaluation for the Design-Builder,

More information

EXHIBIT A SCOPE OF SERVICES MAINTENANCE PERSONNEL SUPPORT

EXHIBIT A SCOPE OF SERVICES MAINTENANCE PERSONNEL SUPPORT EXHIBIT A SCOPE OF SERVICES I. PURPOSE: MAINTENANCE PERSONNEL SUPPORT The Department is requesting Personnel Support Services to augment the Department s Maintenance personnel in the administration of

More information

Highway / Utility Guide

Highway / Utility Guide Oregon Department of Transportation Highway Division Right of Way Section Highway / Utility Guide Railroad & Utilities Unit Right of Way Section STATEMENT OF PURPOSE It is important to understand that

More information

NOTICE TO DESIGN PROFESSIONALS / CONTRACTORS REQUEST FOR LETTERS OF INTEREST S.R. 408/ S.R. 417 INTERCHANGE IMPROVEMENTS PHASE 2 PROJECT NO.

NOTICE TO DESIGN PROFESSIONALS / CONTRACTORS REQUEST FOR LETTERS OF INTEREST S.R. 408/ S.R. 417 INTERCHANGE IMPROVEMENTS PHASE 2 PROJECT NO. NOTICE TO DESIGN PROFESSIONALS / CONTRACTORS REQUEST FOR LETTERS OF INTEREST S.R. 408/ S.R. 417 INTERCHANGE IMPROVEMENTS PHASE 2 PROJECT NO. 253G, CONTRACT NO. 001266 The Central Florida Expressway Authority

More information

Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014

Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014 Maine Turnpike Authority Construction Resident Engineer/Inspector SCOPE OF WORK July 14, 2014 A. GENERAL DESCRIPTION The Consultant, acting as an independent contractor will serve to supplement the Authority

More information

PUBLIC NOTICE MARYLAND DEPARTMENT OF TRANSPORTATION NOTICE ARCHITECTS & ENGINEERS TRANSPORTATION PROFESSIONAL SERVICES SELECTION BOARD

PUBLIC NOTICE MARYLAND DEPARTMENT OF TRANSPORTATION NOTICE ARCHITECTS & ENGINEERS TRANSPORTATION PROFESSIONAL SERVICES SELECTION BOARD PUBLIC NOTICE MARYLAND DEPARTMENT OF TRANSPORTATION NOTICE TO ARCHITECTS & ENGINEERS TRANSPORTATION PROFESSIONAL SERVICES SELECTION BOARD REQUEST FOR PROFESSIONAL SERVICES The Secretary of the Maryland

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

Florida Department of Transportation District 4

Florida Department of Transportation District 4 I-595 RFP Volume II - Technical Requirements Division II, Section 3, Attachment 3 Concessionaire Construction Engineering & Inspection Requirements Florida Department of Transportation District 4 To Design,

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES SOP #.004 Title: MONITORING OF CONTRACT PERFOMANCE AND DELIVERABLES Version: 1 Approval Date: May 10, 2018 1. Purpose. The purpose of a contract monitoring

More information

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW January 31, 2018 To Whom It May Concern: I. INSTRUCTIONS ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project 18-0018PW A. The following additions, deletions, revisions, and/or

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

Department of Public Works Division of Engineering. Nassau County, New York

Department of Public Works Division of Engineering. Nassau County, New York TOWN OF OYSTER BAY Department of Public Works Division of Engineering Nassau County, New York REQUEST FOR PROPOSALS FOR CONSULTANT SERVICES SOLICITATION NO. 2017-12 NOTES: 1. ISSUANCE DATE: Thursday, October

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS Professional Construction Management Services Harrisburg International Airport Rehabilitate Runway 13-31 Susquehanna Area Regional

More information

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,

More information

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07

P-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 PART 1 GENERAL 1.1 REFERENCES SECTION 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 The publications listed below form a part of this specification to the extent referenced. The publications

More information

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference.

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference. 2 PROJECT MANAGEMENT 2.1 Scope Management 2.1.1 General The Design-Builder shall conduct all Work necessary to meet the requirements of scope management, including preparing, documenting, revising, and

More information

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11)

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) , Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) Request for Qualifications Construction Inspection and Testing Services Issued: January 3, 2017 Due: January 24, 2017 I. INTRODUCTION

More information

SADDLE CREEK CSD LANDSCAPE ARCHITECT REQUEST FOR PROPOSALS. (Boilerplate language, map and other contract language to be added on approval of Board)

SADDLE CREEK CSD LANDSCAPE ARCHITECT REQUEST FOR PROPOSALS. (Boilerplate language, map and other contract language to be added on approval of Board) October 17, 2017 SADDLE CREEK CSD LANDSCAPE ARCHITECT REQUEST FOR PROPOSALS (Boilerplate language, map and other contract language to be added on approval of Board) PROPOSAL SUBMITTALS DUE NOVEMBER 17,

More information

0100 GENERAL 0200 PROJECT MANAGEMENT

0100 GENERAL 0200 PROJECT MANAGEMENT TEXAS DEPARTMENT OF TRANSPORTATION 0100 GENERAL 0101 General requirements A. Maintenance Contractor shall be responsible for and shall carry out Maintenance Services for the Maintained Elements set forth

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Chapter 18. Quality Assurance and Quality Control

Chapter 18. Quality Assurance and Quality Control Chapter 18 Quality Assurance and Quality Control The following are changes, additions or deletions to the January 2016, Topic #625-000-007, Plans Preparation Manual (PPM), for use on Turnpike projects

More information

SPECIFICATION NO. TxDOT * REVISED: AUGUST 2017 CRIMINAL BACKGROUND CHECKS

SPECIFICATION NO. TxDOT * REVISED: AUGUST 2017 CRIMINAL BACKGROUND CHECKS SPECIFICATION NO. TxDOT 961-30-16 * REVISED: AUGUST 2017 CRIMINAL BACKGROUND CHECKS PUBLICATION This specification is a product of the Texas Department of Transportation (TxDOT). This specification may

More information

EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION FOR THE LOCAL AGENCY PROGRAM (LAP) SCOPE OF SERVICES FOR

EXHIBIT A CONSTRUCTION ENGINEERING AND INSPECTION FOR THE LOCAL AGENCY PROGRAM (LAP) SCOPE OF SERVICES FOR 1/30/2019 EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION FOR THE LOCAL AGENCY PROGRAM (LAP) SCOPE OF SERVICES FOR Project Description: Construction Engineering Inspection (CEI) Support for the Local

More information

RESIDENT ENGINEER S MANUAL

RESIDENT ENGINEER S MANUAL Peninsula Corridor Joint Powers Board 1250 San Carlos Avenue San Carlos, California 94070-1306 RESIDENT ENGINEER S MANUAL Revision 2 Page 1 of 336 Caltrain Standard Manual RESIDENT ENGINEER S MANUAL Manual

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

San Antonio Water System Standard Specifications for Construction

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 Construction Qc/Qa Program Formatted: Font: 11.5 pt Formatted: Font: 11.5 pt 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality

More information

Exhibit A Mn/DOT Contract No

Exhibit A Mn/DOT Contract No Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR:

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE. CFS:BD 1 of 14 APPR:MB:JJG FHWA:APPR: MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD SCHEDULE CFS:BD 1 of 14 APPR:MB:JJG 09-29-18 FHWA:APPR:10-01-18 a. Description. Prepare and submit a critical path method

More information

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12 3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda

Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 to 15.1 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

STRS Ohio Employer Self Service (ESS) Instructions Table of Contents

STRS Ohio Employer Self Service (ESS) Instructions Table of Contents STRS Ohio Employer Self Service (ESS) Instructions Table of Contents Log in to ESS... 1 Account Settings... 2 Navigating ESS... 3 Additional Tips and Suggestions... 4 New Hire Information... 6 Reemployed

More information

Design-Build Reconstruction of I-494 in Plymouth, Minnetonka and Eden Prairie, Minnesota. PMI MN 2009 Professional Development Days

Design-Build Reconstruction of I-494 in Plymouth, Minnetonka and Eden Prairie, Minnesota. PMI MN 2009 Professional Development Days Design-Build Reconstruction of I-494 in Plymouth, Minnetonka and Eden Prairie, Minnesota PMI MN 2009 Professional Development Days Agenda Project Overview Best Practices: Knowing the Right Things Doing

More information

CONTRACT MANAGEMENT AND ADMINISTRATION

CONTRACT MANAGEMENT AND ADMINISTRATION CONTRACT MANAGEMENT AND ADMINISTRATION KEY ELEMENTS FOR EFFECTIVE C.A: COMMUNICATION Contract that Clearly Identifies what Success looks like Effective Written Communication Track Milestones and Conduct

More information

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate

Exhibit A Scope of Work. 0.0 Separation of work Types and Cost Estimate 0.0 Separation of work Types and Cost Estimate Exhibit A Scope of Work 0.1 Prepare scope of work and cost estimate for MnDOT efforts relating to all items numbered less than 20.0. 0.2 Prepare scope of

More information

CLEAN WATER SERVICES AND CAROLLO ENGINEERS, INC. RECITALS. 1. District and Consultant previously entered into the Master Contract.

CLEAN WATER SERVICES AND CAROLLO ENGINEERS, INC. RECITALS. 1. District and Consultant previously entered into the Master Contract. THIRTY-FOURTH AMENDMENT TO MASTER CONTRACT FOR WASTEWATER TREATMENT PLANT ENGINEERING SERVICES ROCK CREEK AWWTF DIGESTER 1 AND 2 MODIFICATIONS PROJECT NO. 6787 CLEAN WATER SERVICES AND CAROLLO ENGINEERS,

More information

SECTION 50 CONTROL OF WORK

SECTION 50 CONTROL OF WORK SECTION 50 CONTROL OF WORK 50-01 AUTHORITY OF THE ENGINEER. The Engineer shall decide any and all questions which may arise as to the quality and acceptability of materials furnished, work performed, and

More information

STATEMENT OF WORK Design Engineering Services On-Call

STATEMENT OF WORK Design Engineering Services On-Call Page 1 of 23 STATEMENT OF WORK Design Engineering Services On-Call A. Purpose of Work The Consultant will perform professional and technical services required for Design Engineering Services on an on-call

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

City of Palo Alto (ID # 4369) City Council Staff Report

City of Palo Alto (ID # 4369) City Council Staff Report City of Palo Alto (ID # 4369) City Council Staff Report Report Type: Consent Calendar Meeting Date: 1/13/2014 Summary Title: Seismic Upgrade Project Amendment #1 w/ URS Title: Approval of Amendment Number

More information

YOUR TRANSPORTATION CO.

YOUR TRANSPORTATION CO. For fast dependable Transportation Services YOUR TRANSPORTATION CO. Compliments of Marc T. Smith CAYMAN SYSTEMS INTERNATIONAL Specializing in Small & Medium Business Compliance Help e-mail to:cayman@qs9000.com

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

PROFESSIONAL SERVICES BULLETIN 18-2 ADDENDUM 2

PROFESSIONAL SERVICES BULLETIN 18-2 ADDENDUM 2 PROFESSIONAL SERVICES BULLETIN 18-2 ADDENDUM 2 ADDENDUM 2 does not change the due date or time. STATEMENTS OF INTEREST are due by 4:30:00 p.m. (local time) Due Date: April 24, 2018 Successful Offerors

More information

CONSTRUCTION MANAGEMENT SERVICES

CONSTRUCTION MANAGEMENT SERVICES DrAFTDRAFTdd EXHIBIT 1 CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS () SELECTION PROCESS School District of Lee County, Florida TABLE OF CONTENTS 1. INTRODUCTION 1 Lobbying 2 2. REQUEST

More information

REQUEST FOR QUALIFICATIONS ARCHITECTURAL

REQUEST FOR QUALIFICATIONS ARCHITECTURAL REQUEST FOR QUALIFICATIONS ARCHITECTURAL and ENGINEERING CONSULTING SERVICES FOR CAPITAL RENEWAL AND REPLACEMENT PROJECTS SQ # 10565 MIDDLESEX COUNTY COLLEGE 2600 WOODBRIDGE AVENUE EDISON, NEW JERSEY 08818

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

DISTRICTWIDE MODAL DEVELOPMENT OFFICE (MDO) RAIL CONSULTANT SERVICES SCOPE OF SERVICES FM# Ad # 19627

DISTRICTWIDE MODAL DEVELOPMENT OFFICE (MDO) RAIL CONSULTANT SERVICES SCOPE OF SERVICES FM# Ad # 19627 DISTRICTWIDE MODAL DEVELOPMENT OFFICE (MDO) RAIL CONSULTANT SERVICES SCOPE OF SERVICES FM# 433056-4-12-01 Ad # 19627 Qualification Requirements for Type of Work 99.0 I. Purpose II. Rail Services III. Administration

More information

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE

REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE REQUEST FOR PROPOSALS FOR PROFESSIONAL ENGINEERING SERVICES FOR CITY OF NANTICOKE Proposals Solicited by: City of Nanticoke 15 East Ridge Street Nanticoke, PA 18634 C:\Users\jim\Desktop\Nanticoke City\07222013professionalengservices\Engineer

More information

Operations Engineering

Operations Engineering Operations Assistant BC Oil & Gas Commission, Fort St John Grid 11 - $41,352.09 - $46,841.86* * Posted salary includes a Location Allowance of 3% This opportunity is geographically restricted to Fort St

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS FOR COMPENSATION STUDY Proposals Due: November 3, 2016, 4:00 PM 1.0 OBJECTIVE SECTION 1 SUBMITTAL PROCEDURES & DEADLINE The City of Signal Hill is seeking proposals from qualified

More information

MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET IT SERVICES for FileNet Enterprise Content Management (ECM) STATEMENT OF WORK

MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET IT SERVICES for FileNet Enterprise Content Management (ECM) STATEMENT OF WORK MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET IT SERVICES for FileNet Enterprise Content Management (ECM) STATEMENT OF WORK Michigan Commission on Law Enforcement Standards The FileNet Enterprise

More information

TH 169/TH 494 DESIGN BUILD PROJECT

TH 169/TH 494 DESIGN BUILD PROJECT TH 169/TH 494 DESIGN BUILD PROJECT PROJECT OVERVIEW Eliminates traffic signals at Highwood/Townline, South Ramp termini, and North Ramp termini. Adds WB 494 to SB 169 flyover ramp. Adds direct NB 169 to

More information

MnDOT Contract Exhibit A - Scope of Services

MnDOT Contract Exhibit A - Scope of Services Project Development for Pavement Rehabilitation and Pedestrian Access -Improvements on TH 22 in Glencoe, MN from US 212 to Cedar Ave. (R.P. 106+00.650 to 108+00.141) -Improvements on TH 71 in Olivia, MN

More information

REFERENCE GUIDE. January, 2018

REFERENCE GUIDE. January, 2018 REFERENCE GUIDE January, 2018 1 Contents Introductory Evaluation for New Hires and Transfers... 3 Adding Goals After Introductory Eval... 5 Re-Evaluation: Introductory & Annual... 7 Focus Review 1 and

More information

Construction Management Plan

Construction Management Plan P.I.N. 1759.59 TITLE: Geyser Road Safe Routes to School Project LOCATION: City of Saratoga Springs COUNTY: Saratoga County I. Supervision of Project Construction Management Plan a. Roles and Responsibilities:

More information

BMPs: Best Management Practices are water pollution control practices.

BMPs: Best Management Practices are water pollution control practices. 11.30 EROSION AND SEDIMENT CONTROL ENTIRE SPECIFICATION IS AN ADDITION BELOW The Contractor s attention is directed to Section 20, Erosion Control and Highway Planting, Section 7-1.01G, Water Pollution,

More information

0100 GENERAL. C. The limits for Maintenance Services are set forth in Attachment 3 to this Maintenance Specification.

0100 GENERAL. C. The limits for Maintenance Services are set forth in Attachment 3 to this Maintenance Specification. 0100 GENERAL 0101 General requirements A. Maintenance Contractor shall be responsible for and shall carry out Maintenance Services for the Maintained Elements set forth in Exhibit 2, Attachment 2 throughout

More information

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Review MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Introduction to Quality Management Dave Ahlvers, P.E. Review of Job Special Provision & Terms Dennis

More information

I. Project Overview and Limits. Project Goal

I. Project Overview and Limits. Project Goal Scope of Work and Deliverables for Subsurface Utility Engineering (SUE) for both Underground and Overhead Utilities on T.H. 10, and its Connecting Roads under S.P. 8001-40 I. Project Overview and Limits

More information

PREPARATION OF THE AUTHORIZATION / OFFICIAL CONSTRUCTION COST ESTIMATE AND CONTRACT BID REVIEW PACKAGE

PREPARATION OF THE AUTHORIZATION / OFFICIAL CONSTRUCTION COST ESTIMATE AND CONTRACT BID REVIEW PACKAGE Approved: Effective: August 19, 2011 Office: Specification and Estimates Topic No. 600-010-001-f Department of Transportation PREPARATION OF THE AUTHORIZATION / OFFICIAL CONSTRUCTION COST ESTIMATE AND

More information

Town of Brandon, Vermont Brandon Union St. Sidewalk STP EH 05 (4) Request for Qualifications Construction Inspection and Testing Services

Town of Brandon, Vermont Brandon Union St. Sidewalk STP EH 05 (4) Request for Qualifications Construction Inspection and Testing Services , Vermont Brandon Union St. Sidewalk STP EH 05 (4) Request for Qualifications Construction Inspection and Testing Services Issued: March 13, 20192 Due: April 3, 2019 I. INTRODUCTION The, Vermont, herein

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

REQUEST FOR QUALIFICATIONS AND QUOTES 1716 VEHICLE WRAPS AND DECALS

REQUEST FOR QUALIFICATIONS AND QUOTES 1716 VEHICLE WRAPS AND DECALS OLYMPIA, WASHINGTON REQUEST FOR QUALIFICATIONS AND QUOTES 1716 VEHICLE WRAPS AND DECALS REQUEST FOR QUALIFICATIONS AND QUOTES (RFQQ) RELEASE DATE: April 13, 2017 PRE-PROPOSAL MEETING: Date: April 24, 2017

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: PROCEDURE NO.: 015 DATE: 08I'4I09 TITLE: CONSTRUCTION

More information

May 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS

May 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS May 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS You are hereby invited to submit a proposal to the McPherson Implementing Local Redevelopment Authority (hereafter referred

More information

AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA

AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA AGREEMENT BETWEEN OWNER AND ENGINEER FOR PROFESSIONAL ENGINEERING SERVICES FOR WATERMAIN EXTENSION FROM CASPIAN AVENUE CITY OF VOLGA, SOUTH DAKOTA This Agreement, made and entered into this day of, 2018,

More information

Financial Project ID(s):

Financial Project ID(s): EXHIBIT "A" CONSTRUCTION ENGINEERING AND INSPECTION SCOPE OF SERVICES FOR Widening of the Turnpike Mainline from four (4) and six (6) lanes to eight (8) lanes from North of Boynton Beach Boulevard at Mile

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

RAPID INCIDENT SCENE CLEARANCE (RISC)

RAPID INCIDENT SCENE CLEARANCE (RISC) Approved: Effective: September 18, 2008 Traffic Engineering and Operations Topic No. 750-030-020-a RAPID INCIDENT SCENE CLEARANCE (RISC) PURPOSE: Rapid Incident Scene Clearance (RISC) is a highly innovative

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved: VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Revisions to Chapter VII of Manual of Instructions Materials Acceptance and Materials Notebook Program NUMBER: MD 407-17

More information

MnDOT Contract No Exhibit A Scope of Work

MnDOT Contract No Exhibit A Scope of Work GENERAL DESCRIPTION OF THE PROJECT In accordance with the National Bridge Inspection Standards (NBIS), the Minnesota Department of Transportation Bridge and Structure Inspection Program Manual (BSIPM)

More information

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO. Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions

More information

LEADER ICT System User Guide Project Claim

LEADER ICT System User Guide Project Claim LEADER ICT System Guide Project Claim Index Project Claim... 1 Overview... 1 Roles... 2 Claim Rules... 3 Claim Approval... 4 Claim Stages... 5 Stage 01 Create New Claim... 6 Stage 02 or Check... 24 Stage

More information