QUALITY CONTROL AND SCHEDULE AND THEIR IMPACT ON SAFETY. Capital Improvement Business Line Chief Engineer NAVFAC EURAFSWA 8 Sept 2010
|
|
- Rafe Jordan
- 6 years ago
- Views:
Transcription
1 QUALITY CONTROL AND SCHEDULE AND THEIR IMPACT ON SAFETY Capital Improvement Business Line Chief Engineer NAVFAC EURAFSWA 8 Sept 2010
2 What Is Construction Quality Management Construction Quality Management (CQM) requires the combined efforts of contractor quality control (QC) personnel and government quality assurance (QA) personnel to achieve shared goals: Quality Construction Built Safely Delivered on Time Delivered within Budget QC is the contractor s role of inspection and oversight to ensure the points above are achieved QA is the government s role that ensures the contractor s QC system is effective in meeting project objectives 2 9/16/2010
3 Quality Control Contractors enhance their opportunity for Navy business by maintaining a strong QC system Schedule goals are achieved thru regular production/qc meetings Proactive contractor leadership that builds it right the first time and builds it safely Manage specific processes including: Submittals Preventative Controls Inspection Testing Documentation 3 9/16/2010
4 QC Manager Qualifications Spec section defines it as: An individual with a minimum of [5][10] years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual must have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM , and have experience in the areas of hazard identification, safety compliance, and sustainability. 4 9/16/2010
5 Accident Prevention Plan (APP) Before initiation of work at the job site, an APP must be submitted and approved by the Contracting Officer Articulate the specific work and hazards pertaining to the contract Written in English Job specific and include work to be performed by subcontractors Developed and submitted by the Contractor in the format provided in Appendix A (ACOE EM ) The Contractor shall be responsible for documenting the Qualified person s credentials Updates to the APP shall be reviewed and approved by the Contracting Officer 5 9/16/2010
6 Activity Hazard Analysis (AHA) AHA Risk Assessment Tool Defines the Activity or Work to be Performed Identifies Hazards Establishes Controls to Reduce the Hazard to an Acceptable Risk Level Living Document Changes with Site Conditions or Operations Changes of competent/qualified personnel 6 9/16/2010
7 QC Meetings Held weekly or bi-weekly depending on specification Reviews the three week look ahead schedule focusing mainly on the work to be accomplished in the next two weeks and the documentation required Reviews the accident prevention plan to address any issues or items that may require a change 7 9/16/2010
8 Definable Feature of Work (DFOW) A task that is separate and distinct from other tasks and has control requirements and work crews unique to that task DFOW is an item or activity on the construction schedule Requires a separate activity hazard analysis 8 9/16/2010
9 Three Phases of Control Contractors control of quality is divided into three phases for each definable feature of work (DFOW) Each control phase is an opportunity prevent problems and costly rework The three phase of control are: Preparatory Phase Initial Phase Follow-up Phase 9 9/16/2010
10 Preparatory Phase Performed and documented prior to starting DFOW Two requirements before this phase can be scheduled on any DFOW: all materials approved and AHAs accepted by Government Gov t is notified 2 working days in advance Discusses specific controls used and construction methods Provides quality construction by planning ahead Identifies potential problems for each DFOW Reviews APP and AHA to ensure applicable safety requirements are met Ensures that required Material Safety Data Sheets (MSDS) are submitted 10 9/16/2010
11 Initial Phase Performed when crews are ready to start work on a particular DFOW Gov t is notified 2 working days in advance Checks work procedures for compliance with APP and the appropriate AHA to ensure that all applicable safety requirements are met 11 9/16/2010
12 Follow-up Phase Surveillance, inspection and documentation of DFOW to determine continued compliance with established work procedures, levels of quality and safety precautions May be performed on a daily, routine, or predetermined basis as required by the work being performed Repeat preparatory and initial phases if there are changes in onsite production supervision or work crew or if work on DFOW is resumed after substantial period of inactivity 12 9/16/2010
13 Network Analysis Schedules Specifications require the use of Sure Trak or Primavera P3 only NAVFAC is migrating to Primavera P6 in near future 13 9/16/2010
14 Schedules Must include QC activities which also identify the preparatory and initial phase for each DFOW Three week look ahead schedules Provides more detailed day-to-day plan of upcoming work Includes upcoming outages, closures, three phase mtgs Reviewed at every QC meeting Provided to Gov t every week Properly detailed NAS schedules and adherence to the approved schedule allow the contractor to plan for potential unforeseens 14 9/16/2010
15 QUESTIONS? 15 9/16/2010
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES
More informationP-196 MARINE CORPS RESERVE VEHICLE MAINTENANCE FACILITY NWS CHARLESTON, SC SECTION DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07
PART 1 GENERAL 1.1 REFERENCES SECTION 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL 11/07 The publications listed below form a part of this specification to the extent referenced. The publications
More informationAccident Prevention Plans Randy Acosta Safety Officer OICC MCI East Camp Lejeune NC 31 October 2012
NAVFAC MIDLANT Accident Prevention Plans Randy Acosta Safety Officer OICC MCI East Camp Lejeune NC 31 October 2012 Accident Prevention Plans Sometimes the difference in Acceptance and re-submission is
More informationSECTION QUALITY CONTROL
SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.
More informationFacilities Planning and Construction (FP&C)
Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:
More informationUSACE NAVFAC Sample QA/QC Plan 20 selected pages (out of )
USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick the date]
More informationUSACE NAVFAC Design Sample QA/QC Plan
USACE NAVFAC Design Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01 40 00 PART 1 - GENERAL 1.1 SUMMARY A. This section covers the establishment and operation of the Contractor s Quality Control (CQC) system as specified by the General Conditions of the Contract.
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 20 (November 2011) Change 2-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02 (February 2010) UNIFIED FACILITIES
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (November 2016) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 00.00 10 (February 2010) UNIFIED FACILITIES GUIDE
More informationCQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,
More informationCommunications Contractor QA/QC Plan Sample
Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira
More informationModule 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
More informationFire Protection Contractor QA/QC Plan Sample
Fire Protection Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Fire Protection Standards & Inspection Forms Contact: Ed
More informationCONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS. Student Study Guide
Control #784 Revised 2004 CONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS Student Study Guide Produced By: U.S. Army Corps of Engineers Professional Development Support Center and U.S. Naval Facilities
More informationCONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS. Student Study Guide
Control #784 Revised 2004 CONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS Student Study Guide Produced By: U.S. Army Corps of Engineers Professional Development Support Center and U.S. Naval Facilities
More information150/ G Versus 150/ H Contractor Quality Control Program
AC 150/5370-10G AC 150/5370-10H 1 Part 1 of General Provisions Part 2 of General Construction Items 2 Section 100 Item C-100 3 Quality Control Program (CQCP) 4 100-01 General. When the specification requires
More informationAppendix I Construction Quality Control Plan
Appendix I Construction Quality Control Plan Construction Quality Control Plan River Mile 10.9 Removal Action at Lower Passaic River Study Area New Jersey Revision 00 Prepared for Cooperating Parties
More informationEarthworks QA/QC Plan Sample
Earthworks QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact: FirstTimeQuality
More informationSECTION CONTRACTOR QUALITY CONTROL
SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationFTA-DOT QA/QC Plan Sample Selected pages (not a complete plan)
FTA-DOT QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: FirstTimeQuality 410 451 8006 Pat [Pick the
More informationFlooring Contractor QA/QC Plan Sample Selected pages (not a complete plan)
Flooring Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:
More informationDRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL
1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and
More informationAPPENDIX B. PROJECT CONTRACTOR QUALITY CONTROL PLAN March 6, 2009
Base Realignment and Closure Program Management Office West 1455 Frazee Road, Suite 900 San Diego, California 92108-4310 CONTRACT NO. N62473-07-D-3211 CTO NO. 0009 APPENDIX B DRAFT PROJECT CONTRACTOR QUALITY
More informationJanitorial Essentials QA/QC Plan Sample
Janitorial Essentials QA/QC Plan Sample Good for smaller projects and bid qualifications Has All the Essential Elements of a well-founded Quality Control Plan Contact: FirstTimeQuality 410-451-8006 Pat
More informationSECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10
SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single
More informationQuality Control. Contact person Andrew Richardson Responsible Brent LeVander. Approval
Identification number: 0206500_CP_11_30_en_1.1 Quality Control Short description This section describes the means and methods for maintaining high levels of quality on our projects and operating an efficient
More informationPRE-INSTALLATION MEETING RECORD
Meeting Date: Meeting Location: Description of Work To Be Discussed: Attendees (in most cases must include the trade contractor s foreman who will actually be out in the field doing the work): NAME POSITION
More informationACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY
ACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY Engineering Controls Work Practices Personal Protective Equipment (PPE) SAFETY HEIRARCHY Engineering Controls Example: Three foot high parapet
More informationSelected pages (not a complete plan)
Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Contact: FirstTimeQuality 410 451 8006 Pat [Pick the date] PROJECT-SPECIFIC
More informationJOB DESCRIPTION. JOB TITLE: Project Superintendent DATE: 2/1/10. DIVISION: Construction EXEMPT STATUS: Exempt
JOB DESCRIPTION JOB TITLE: Project Superintendent DATE: 2/1/10 DIVISION: Construction EXEMPT STATUS: Exempt REPORTS DIRECTLY TO: Vice President-Construction POSITION OBJECTIVE A Model Construction Project
More informationOil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan)
Oil and Gas Contractor QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Part 4: Inspection Checklist Forms Contact:
More informationFMI Construction Professional Survey Job Description
s BIM1 Building Information Modeling - Level 1 Designer to create and modify 3D models, renderings and/or animations for promotion and proposals. Office-based work with various departments to integrate
More informationConstruction Management Plan
Use and Limitation: The Consultant may use this document as a guide in preparing a construction management plan to be included in the bid documents for their specific project. Consultants are cautioned
More informationTEXAS A&M UNIVERSITY-TEXARKANA QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) FACILITIES SUPPORT SERVICES AGREEMENT
TEXAS A&M UNIVERSITY-TEXARKANA QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) FACILITIES SUPPORT SERVICES AGREEMENT TABLE OF CONTENTS 1. INTRODUCTION... 1 2. ROLES AND RESPONSIBILITIES... 2 3. SURVEILLANCE
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION
USACE / NAVFAC / AFCEC / NASA UFGS-01 31 19.05 20 (September 2015) Change 1-02/18 ------------------------------------ Preparing Activity: NAVFAC Superseding UFGS-01 31 19.05 20 (May 2014) UFGS-01 31 19.05
More informationQuality Assurance Program for the Carolina Crossroads Project
Quality Assurance Program for the Carolina Crossroads Project 08/31/18 (Draft QAP) Contents Scope... 1 1.1 General... 1 1.2 Program Components... 1 1.3 Construction Quality Management Plan... 2 1.4 Owner
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 40 (November 2017) ----------------------------------- Preparing Activity: NASA Superseding UFGS-01 45 00.00 40 (November 2014) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationDOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)
DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: FirstTimeQuality 410 451 8006 Pat [Pick the
More informationISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Engineering Design Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal
More informationGENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN
Project Procedures GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN 07/28/2011 PAGE 1 OF 7 1.0 PURPOSE 1.1 PURPOSE OF ENGINEERING PROJECT PROCEDURES This P-4 series of Engineering Project Procedures provides
More informationShort Service Employee Program
Page 1 of 6 Sect: 1.0 Purpose 2.0 Responsibility The management of ARDENT recognizes that all new employees face a period of transition into new surroundings and work processes. It is during this period
More informationJanitorial Essentials QA/QC Plan Sample
Janitorial Essentials QA/QC Plan Sample Good for smaller projects and bid qualifications Has All the Essential Elements of a well-founded Quality Control Plan Contact: FirstTimeQuality 410-451-8006 Pat
More informationDeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT
DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE
More informationContractor Selection & Management Guideline Rev01. Revision 00. April 2011
Contractor Selection and Management Guideline Revision 00 April 2011 Document Details and Issue Record Rev No. Details Date Author 00 Draft 10/04/2011 CJMD Checked Text Calcs Approved Document Reference:
More information(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet
(To be printed on Professional s Letterhead) PRE-CONSTRUCTION MEETING AGENDA (Professional to provide attendance sign-up sheet Project Name: UM Project # Design Professional: Meeting Place: Meeting Time:
More informationJOB SITE FOREMAN - SAFETY RESPONSIBILITIES
- Have Makyle Electric Inc. 8/20/2012-8/26/2012 RISK CONTROL SERVICES FROM CNA talks toolbox JOB SITE FOREMAN - SAFETY RESPONSIBILITIES INTRODUCTION The key to success in any construction loss prevention
More informationSelected pages (not a complete plan)
Sample Selected pages (not a complete plan) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: FirstTimeQuality 410 451 8006 Pat [Pick the date] PROJECT QUALITY
More informationPatrick Malloy Communities Quality Assurance System
Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed
More informationSECTION G: SAFETY EVALUATION
SECTION G: SAFETY EVALUATION means an evaluation of a facility s safety culture, management systems and human factors program to determine strengths, weaknesses and gaps. The evaluation will include an
More informationSECTION L QUALITY ASSURANCE. 1) designating and managing quality control functions, including:
NT-L1.000 QUALITY ASSURANCE PROGRAM All NADOs shall have a QA Program. Current (2 nd Edition) NT-L1.100 BASIC ELEMENTS SECTION L QUALITY ASSURANCE The QA program shall include, at a minimum: 1) designating
More informationGuidance for Rating Each Performance Category on Contractor Performance Evaluation
Guidance for Rating Each Performance Category on Contractor Performance Evaluation Section 1: KNOWLEDGE Knowledge of WSSC Standards (Details/Specifications) Extremely knowledgeable of WSSC standards. Contractor
More informationSan Antonio Water System Standard Specifications for Construction
ITEM NO. 903 Construction Qc/Qa Program Formatted: Font: 11.5 pt Formatted: Font: 11.5 pt 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality
More informationDeveloping a Checklist
Developing a Checklist Robert Orkin Project QA/QC Manager Parsons Brinckerhoff Americas orkin@pbworld.com 19 th Annual Audit Division Conference October 7-8, 2010 Orlando, Florida I am Bob Orkin Introduce
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationSafety Documents for Research Reactors
Safety Documents for Research Reactors H. Abou Yehia Research Reactor Safety Section Division of Nuclear Installation Safety International Atomic Energy Agency Contents Safety Analysis Report Safety Analysis
More informationSECTION CHANGE ORDER (Instructions on ) No. 4 PROJECT: Bulldog Drive Improvements DATE OF ISSUANCE 12/17/2013 EFFECTIVE DATE 12/17/2013
CHANGE ORDER (Instructions on 008432) No. 4 PROJECT: Bulldog Drive Improvements DATE OF ISSUANCE 12/17/2013 EFFECTIVE DATE 12/17/2013 CITY OF PALM COAST CITY Contract/Purchase Order No.: 20110463 CONTRACTOR
More informationTHE COMMANDER NAVY REGION, SOUTHWEST (CNRSW) HAZARDOUS MATERIALS (HAZMAT) OPERATIONS QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) 20 June 2000
THE COMMANDER NAVY REGION, SOUTHWEST (CNRSW) HAZARDOUS MATERIALS (HAZMAT) OPERATIONS QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) 20 June 2000 TABLE OF CONTENTS 1.0 INTRODUCTION 1 1.1 PURPOSE... 1 2.0 OVERVIEW.2
More informationSECTION III -- RESPONSIBILITIES
SECTION III -- RESPONSIBILITIES 3.0 Management Staff direction and management of the Comprehensive Safety and Health Program will be accomplished by the Superintendent with authority delegated from the
More informationControlling Food Safety During Equipment or Facility Repair
Controlling Food Safety During Equipment or Facility Repair By David A. Baker, PhD, MPH, CQM Food safety standards accepted in support of the Global Food Safety Initiative require that maintenance of equipment
More informationHAZARD COMMUNICATION
1910.1200 HAZARD COMMUNICATION NOTE: THIS SAMPLE PROGRAM IS PROVIDED TO ASSIST IN COMPLYING WITH 29 CFR 1910.1200, HAZARD COMMUNICATION. IT IS NOT INTENDED TO SUPERSEDE THE REQUIREMENTS DETAILED IN THE
More informationBMP Element 7 Roles and Responsibilities City of Richmond Public Utilities Wastewater Treatment
BMP Element 7 Roles and Responsibilities City of Richmond Public Utilities Wastewater Treatment Date of Last Review 11/10/16 Revision 15 Revised By Biosolids Team Approved By Biosolids Supervisor Revision
More informationI. Development, Submittal, and Acceptance of a Quality Management System
I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor
More informationSafety Regulations and Procedures OCCUPATIONAL HEALTH Hazard Communication - Responsibility, Scope, and Application - S80.
Safety Regulations and Procedures OCCUPATIONAL HEALTH Hazard Communication - Responsibility, Scope, and Application - S80.61 - Rev 1/95 Hazard Communication - Responsibility, Scope and Application RESPONSIBILITY
More informationNAVFAC SOUTHWEST / OICC MCIWEST. World Class Construction Forum Commissioning
NAVFAC SOUTHWEST / OICC MCIWEST World Class Construction Forum Commissioning 17 August 2011 Agenda 0830-0845: Welcome Aboard & Forum Introduction 0845-0900: Commissioning 0900-1015: Commissioning Lessons
More informationEXHIBIT 2-2-C SCHEDULES
EXHIBIT 2-2-C SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The Work specified in this section consists of furnishing transportation, labor, materials, equipment, and incidentals necessary for preparation,
More informationJanitorial QA/QC Manual Sample
Janitorial QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Janitorial Services Operating Policies
More informationSITE-SPECIFIC QUALITY CONTROL PLAN
Hensel Phelps SITE-SPECIFIC QUALITY CONTROL PLAN Any reference to Contractor in this Quality Control Plan or attached documents refers to Hensel Phelps OIA South Airport Terminal C Phase 1 Proprietary
More informationINTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICES
INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICES EVALUATION CRITERIA FOR STRUCTURAL STEEL APPROVED FABRICATOR INSPECTION PROGRAMS 1.0 PURPOSE EC 020-2014 (Adopted
More informationMETHOD STATEMENT FOR PIPE WELDING WORKS
METHOD STATEMENT FOR PIPE WELDING WORKS Introduction This Method statement describes in detail the welding process for pipe work and the welder s qualification test procedures. This includes addressing
More informationREQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN Introduction Becker County is issuing a RFQ for Construction Management at Risk Services
More informationRoles & Responsibilities
Roles & Responsibilities Table of Contents Roles and Responsibilities... 2 Corporate Management, Total Energy Services Inc... 2 President/ CEO... 2 VP Legal & General Counsel... 2 Vice President, Operations...
More informationThe purpose of this procedure is to establish the system for initiating, processing, and controlling Nonconformance Reports and Stop Work Notices.
Project Procedure 09/21/2012 PAGE 1 OF 5 1.0 PURPOSE The purpose of this procedure is to establish the system for initiating, processing, and controlling Nonconformance Reports and Stop Work Notices. 2.0
More informationClick to edit Master text styles
Time Timeisisof ofthe theessence Essence Click to edit Master text styles Second level Third level Fourth level Fifth level 8/20/2013 1 Photo by Mark Toal SCHEDULING PROJECT STAKEHOLDERS Oregon Department
More informationINSPECTION SYSTEM REQUIREMENTS
MILITARY SPECIFICATIONS MIL-I-45208A INSPECTION SYSTEM REQUIREMENTS This specification has been approved by the Department of Defense and is mandatory for use by all Agencies. 1. SCOPE 1.1 Scope. This
More informationSAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES
JOB #: SAN ANTONIO WATER SYSTEM PRE-CONSTRUCTION MINUTES TITLE: DATE: TIME: PROJECT ENGINEER: DESIGNER / CONSULTANT: INSPECTOR: _ 704-7110 704-7199 AWARD DATE: BASIC BID AWARD AMOUNT: $ ADDENDUMS: Addendum
More informationQuality Assurance Program for Design-Build Projects with an Optional 15-Year Capital Maintenance Agreement
Quality Assurance Program for Design-Build Projects with an Optional 15-Year Capital Maintenance Agreement July 25, 2011 2011 by Texas Department of Transportation (512) 416-2055 All Rights Reserved TABLE
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS PROJECT: ISSUE DATE: October 22, 2018 ISSUED BY: INQUIRIES: SUBMISSION DEADLINE: SUBMIT TO: City of Delaware, Ohio Public Works Department, Traffic & Engineering Services 440
More informationHYDROGEOLOGIC, INC. CONTRACTOR QUALITY CONTROL PLAN
HYDROGEOLOGIC, INC. CONTRACTOR QUALITY CONTROL PLAN Prepared by: HydroGeoLogic, Inc. 4600 Northgate Boulevard, Suite 207 Sacramento, CA 95834 Revised: February 2004 TABLE OF CONTENTS Page 1.0 PURPOSE...
More informationAir Monitoring Directive Chapter 5: Quality System
Air Monitoring Directive Chapter 5: Quality System Version Dec 16, 2016 Amends the original Air Monitoring Directive published June, 1989 Title: Air Monitoring Directive Chapter 5: Quality System Number:
More informationPhone:
Washington State Construction Crane Certifiers Mobile Cranes (Lattice / Hydraulic / Fixed) Articulating Cranes Tower Maritime Crane Certification Experienced certifiers throughout Washington State More
More informationTransbay Transit Center Program
Transbay Transit Center Program Quality Management System Manual Revision 1 September 2013 Quality Management System Manual Revision 1 September 2013 Prepared for the Transbay Joint Powers Authority
More informationEXPERTS PREVENTING CONSTRUCTION DEFECTS THROUGH EFFECTIVE QUALITY CONTROL. Gregory Pestine, P.E. Civil Engineer Robson Forensic, Inc.
EXPERTS PREVENTING CONSTRUCTION DEFECTS THROUGH EFFECTIVE QUALITY CONTROL Gregory Pestine, P.E. Civil Engineer Robson Forensic, Inc. Preventing Construction Defects Effective Quality Control Well-administered
More informationHazard Identification & Risk Assessment
Purpose/ Objective: Berland River Safety Inc. has established this written safety policy and implemented procedures to ensure that hazard identification and risk assessment will be part of routine safety
More informationBuilding Enclosure Pre-construction Meeting
Building Enclosure Pre-construction Meeting Melissa Payne, BECxP, CxA+BE, CDT Miller Engineering, P.C. Air Barrier Association of America (ABAA) is a Registered Provider with The American Institute of
More informationPRODUCTION SUPPLY INCORPORATED. QUALITY ASSURANCE POLICY MANUAL (Mil-I-45208A) # QAD REV. A
Production Supply Co., Inc. 620 Oak Harbor Blvd Slidell, La, 70458 Phone: 985-290-2630 Fax: 985-643-1138 info@prodsupply.com PRODUCTION SUPPLY INCORPORATED QUALITY ASSURANCE POLICY MANUAL (Mil-I-45208A)
More informationThe construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.
L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally
More informationENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION
ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION Version 1.0 April 2015 Table of Contents 1.0 INVESTOR CONFIDENCE PROJECT 1.1 ENERGY EFFICIENCY PERFORMANCE QUALITY ASSURANCE SPECIFICATION 1.2
More informationSWT CONSTRUCTION PARTNERING
1 The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated
More informationBROOKHAVEN NATIONAL LABORATORY SBMS Interim Procedure
BROOKHAVEN NATIONAL LABORATORY SBMS Interim Procedure Interim Procedure Number: 2004-18001-005 Revision: 12 on 1-26-07 Title: 18001 Audit Checklist Point of Contact: Pat Williams Management System: Occupational
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time
More informationLandscape Services QA/QC Manual Sample Selected pages (not a complete plan)
Landscape Services QA/QC Manual Sample Selected pages (not a complete plan) Reporting Forms Inspection Forms Contact: Ed Caldeira 410-451-8006 Pat [Pick the date] [CompanyName] Landscape Services Operating
More informationSTATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC
STATEMENT OF WORK FOR HOLIDAY DECORATIONS AT WASHINGTON DULLES INTERNATIONAL AIRPORT WASHINGTON, DC PREPARED BY: Metropolitan Washington Airports Authority Washington Dulles International Airport Engineering
More informationField Leadership Safety Conference
Resident Officer In Charge of Construction MCB Camp Pendleton Field Leadership Safety Conference February 22, 2011 Agenda Program Review How are we doing? Andy s Safety Tool Box Recent Incidents/Near Misses
More informationProject Management Techniques
ALUMASA QATAR Project Management Techniques A project is usually one time effort. Although similar work may have been done previously, every project has its own features and therefore is of non-repetitive
More informationAssociation of American Railroads Quality Assurance System Evaluation (QASE) Checklist Rev. 1/12/2017
Company: Prepared By: Date: Changes from previous version highlighted in yellow. Paragraph Element Objective Evidence 2.1 Objective of Quality Assurance Program 2.2 Applicability and Scope 2.3 QA Program
More information9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction
9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes