Pre-Bid Meeting Central Utility Plant ( CUP )

Size: px
Start display at page:

Download "Pre-Bid Meeting Central Utility Plant ( CUP )"

Transcription

1 NORTH TERMINAL PROJECT AT THE LOUIS ARMSTRONG NEW ORLEANS INTERNATIONAL AIRPORT Pre-Bid Meeting Central Utility Plant ( CUP ) Crowne Plaza New Orleans Airport April 13, 2016 North Terminal Project Overview 1

2 Team Introductions Hunt Construction Group Gibbs Construction Boh Bros. Construction Metro Service Group Agenda (CUP Pre-Bid Meeting) 1. Team Introductions (Hunt, Gibbs, Boh, Metro, a JV) 2. Project Overview 3. Bidding Process & Timeline 4. Bid Manual & Bid Forms 5. Websites/Documents (Design Documents, RFI Forms, Subcontract Documents, Scope, Bid Forms, Addendums, etc.) 6. DBE Goals 7. Summary/Questions 2

3 Central Utility Plant Central Utility Plant 3

4 Procurement Process CUP (No MEPF) Bidder Registration Document Distribution Addendums jv.com Bid Manual Instructions to Bidders RFI Forms and Process Substitution Requests Insurance Requirements Form of Subcontract EEO Requirements jv.com 4

5 Bid Manual E Verify Requirements Bonding Requirements (Bid Bond, Payment & Performance) Contract Terms and Conditions Schedule 5

6 Document Distribution Free Access to FTP Site Available for Review at Plan Rooms On Line Registration Registration Required for Access to FTP Site jv.com Bidder Registration 6

7 Website/Registration Register at jv.com jv.com Drawings at City Blue/Bid Documents 7

8 Bidding Procedure Bids Due on May 5, 2016 at 2:00 pm CST Hard Copy (5740 Citrus Blvd. Suite 102) Check List Bid Form Consideration of Bids Responsive Bids (Requirements) Bid Bond Insurance Certificate History of Liens, Claims, & Judgments License DBE Participation Form (Within 72 Hours) Responsible Bids Price Safety Qualifications Resources Approach 8

9 LAUCP DBE List Newspapers Outreach Events Attendee Lists Community Resource Providers AGC ABC Bidder Notification DBE Administration The Disadvantaged Business Enterprise (DBE) Participation Plan for the Louis Armstrong New Orleans International Airport Project North Terminal Project will follow the Federal DBE plan established for the Louis Armstrong New Orleans International Airport. This plan is available on the Louis Armstrong New Orleans International Airport website at program. The HGBM JV team is committed to supporting the NOAB and maximizing DBE participation. The HGBM JV team works in concert with the NOAB DBE Liaison Officer (DBELO), who is responsible with administering the Airport s DBE Program. 9

10 DBE Participation Goal The DBE goal is set for 70% for this bid package. When utilizing DBE Suppliers, only 60% of their subcontract value is credited towards the DBE goal. When a DBE contractor performs a furnish and install, 100% of their subcontract is credited towards the DBE goal. DBE Forms & Requirements Schedule of Contract Participation and DBE Commitment Form This completed form is required as a part of the Bid Submission for this project. A copy of this form and instructions are attached to the Bid Documents. DBE Forms are due 72 business hours (May 9 th ) post bid submission. 10

11 DBE Assistance Find a Certified DBE Company by company name, type of service and/or type of work performed via the DBE Directories posted on the following websites: If you are having trouble locating DBE subcontractors contact: Arkebia Matthews, HGBM JV DBE Coordinator amatthews@hgbm jv.com DBE Certifications The Airport requires that DBE s be certified at the time of bid by an approved certifying agency in Louisiana. Louisiana Department of Transportation & Development Louis Armstrong New Orleans International Airport New Orleans Regional Transit Authority Orleans Levee District Contact Philistine Ferrand at philisti@flymsy.com for more information regarding certification. 11

12 Monitoring & Compliance LCP Tracker Online certified payroll compliance system Labor Compliance Tracks Local Worker Participation Project specific and cumulative participation reports B2GNow Contract Compliance System (Forthcoming) Web-based contract compliance system Monitor and Report DBE Participation Tracks prompt payment Provides subcontractor participation up to 10 tiers Project specific and cumulative participation reports DBE & Prime Matchmaking Immediately Following Pre-Bid DBE Goal 70% Matchmaking/Teambuilding Prime Bidders/Introductions 12

13 Matchmaking Questions? 13

BUSINESS INFORMATION CENTER

BUSINESS INFORMATION CENTER Hillsdale BUSINESS INFORMATION CENTER 5655 Hillsdale Blvd., Suite 8 Sacramento, CA 95842 Hours: Monday-Thursday 8:30am to 4:30pm; Friday 8:30-12 (916) 263-4100; (916) 263-0656; (916) 263-4146 January 15,

More information

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards

More information

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL

SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT DOCUMENT BID PROPOSAL DOCUMENT 00 41 13 BID PROPOSAL TO: SAN JOSE / EVERGREEN COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees ("the District"). FROM: (Name of

More information

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous

More information

Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms

Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms Minority/Women Business Enterprise (M/WBE) Compliance Guidelines and Forms To be completed and signed by the Prime Vendor/Contractor Bid/RFP : Title: Company Name: Company Address: City: State: Zip: Contact

More information

CONTRACTOR S PROPOSAL

CONTRACTOR S PROPOSAL WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER PREQUALIFICATION

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005

CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS. August 2005 CONTRACT / CONSTRUCTION REQUIREMENTS FOR PUBLIC SCHOOLS PROJECTS August 2005 Projects Requiring Licensed Architect / Engineer: *Project Cost Threshold New Construction or Additions $135,000 + Major Repairs

More information

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY

SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS Professional Construction Management Services Harrisburg International Airport Rehabilitate Runway 13-31 Susquehanna Area Regional

More information

PROPOSED FTA DBE GOALS FY NEW JERSEY TRANSIT CORPORATION JUNE 9, 2016*

PROPOSED FTA DBE GOALS FY NEW JERSEY TRANSIT CORPORATION JUNE 9, 2016* PROPOSED FTA DBE GOALS FY 2017-2019 NEW JERSEY TRANSIT CORPORATION JUNE 9, 2016* Presented by: Samuel L. Myers, Jr. University of Minnesota * Revised and updated. Original presentation: May 25, 2016 Background

More information

REQUEST FOR LETTERS OF INTEREST IN PROFESSIONAL ENGINEERING SERVICES PROJECT NO /05. Ref: General Engineering Services

REQUEST FOR LETTERS OF INTEREST IN PROFESSIONAL ENGINEERING SERVICES PROJECT NO /05. Ref: General Engineering Services REQUEST FOR LETTERS OF INTEREST IN PROFESSIONAL ENGINEERING SERVICES PROJECT NO. 99-16-04/05 Ref: General Engineering Services The Ohio Turnpike and Infrastructure Commission ( Commission ) issues this

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

AGENDA STAFF REPORT. CLERK OF THE BOARD Pending Review COUNTY COUNSEL REVIEW. Approved Agreement to Form. Current Year Cost: NI A

AGENDA STAFF REPORT. CLERK OF THE BOARD Pending Review COUNTY COUNSEL REVIEW. Approved Agreement to Form. Current Year Cost: NI A Agenda Item AGENDA STAFF REPORT ASR Control 16-001333 MEETING DATE: 02/14/ 17 LEGAL ENTITY TAKING ACTION: Board of Supervisors BOARD OF SUPERVISORS DISTRICT(S): 2 SUBMITTING AGENCY/DEPARTMENT: John Wayne

More information

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES

ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES ARKANSAS STATE HIGHWAY AND TRANSPORTATION DEPARTMENT CONSULTANT SELECTION PROCEDURES FOR ENGINEERING AND DESIGN RELATED SERVICES Section I Application (These procedures do not apply to Design-Build Contracts.)

More information

INVITATION FOR BID. HVAC Equipment Replacement for Nordlof Center Lower Level West. Issued November 8, Name of Bidding Firm:

INVITATION FOR BID. HVAC Equipment Replacement for Nordlof Center Lower Level West. Issued November 8, Name of Bidding Firm: INVITATION FOR BID HVAC Equipment Replacement for Nordlof Center Lower Level West Issued November 8, 2017 Name of Bidding Firm: Address: City: State: Zip: Phone: Fax Bid Due Date: Bid Opening Time and

More information

ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS 1. INVITATION ADVERTISEMENT FOR BIDS Sealed proposals for the following work will be received by the University of Kentucky, Capital Construction Procurement Section, Room #322 Peterson Service Building,

More information

CITY OF CHINO HILLS. Request for Proposals (RFP) for. On-call Electrical Repair Service. On-call Electrical Repair including Water and Wastewater

CITY OF CHINO HILLS. Request for Proposals (RFP) for. On-call Electrical Repair Service. On-call Electrical Repair including Water and Wastewater CITY OF CHINO HILLS Request for Proposals (RFP) for On-call Electrical Repair Service March 30, 2016 Department: Project Name: Public Works On-call Electrical Repair including Water and Wastewater Proposal

More information

Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary FOR

Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary FOR 1 23 Commonwealth of Massachusetts DEPARTMENT OF HOUSING & COMMUNITY DEVELOPMENT Deval L. Patrick, Governor Aaron Gornstein, Undersecretary REQUEST FOR RESPONSES (RFR) FOR WEB-BASED BID DOCUMENT DISTRIBUTION

More information

AASHTOWARE PROJECT. Civil Rights and Labor Training Guide

AASHTOWARE PROJECT. Civil Rights and Labor Training Guide AASHTOWARE PROJECT Civil Rights and Labor Training Guide CONTACT INFORMATION AASHTOWare Project CRL Administrators KDOT#AWP.ADMIN@KS.GOV KDOT Computer Training Component KDOT.KCTC@KS.GOV SYSTEM BENEFITS

More information

ADDENDUM TO BID DOCUMENTS SCCD RFP: # Vacaville Classroom Building (Annex) Renovation. Date: 11/15/2017

ADDENDUM TO BID DOCUMENTS SCCD RFP: # Vacaville Classroom Building (Annex) Renovation. Date: 11/15/2017 Solano Community College District Vacaville Classroom Annex Renovation Documents #18-005 ADDENDUM TO BID DOCUMENTS ADDENDUM #01 SCCD RFP: #18 005 Project: Solano Community College District Vacaville Classroom

More information

March 6, 2015 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Addendum No. 1/RFP Y15-1023-CH DISASTER DEBRIS MONITORING SERVICES Proposal Opening Date: March 17, 2015 This addendum is hereby incorporated

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

COUNTY OF SAN JOAQUIN

COUNTY OF SAN JOAQUIN August 1, 2012 COUNTY OF SAN JOAQUIN General Services Department 44 North San Joaquin Street, Suite 590 Stockton, California 95202-2778 (209) 468-3357, Fax (209) 468-2186 GABRIEL E. KARAM Director Capital

More information

CITY OF ROSEVILLE ENGINEERING DEPARTMENT GUIDE TO ONLINE BIDDING FOR CITY PROJECTS

CITY OF ROSEVILLE ENGINEERING DEPARTMENT GUIDE TO ONLINE BIDDING FOR CITY PROJECTS CITY OF ROSEVILLE ENGINEERING DEPARTMENT GUIDE TO ONLINE BIDDING FOR CITY PROJECTS It is the City of Roseville s policy to provide all contractors and subcontractors with equal access to procurement opportunities.

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

UNC Chapel Hill Informal Contracting Guidelines

UNC Chapel Hill Informal Contracting Guidelines UNC Chapel Hill Informal Contracting Guidelines 1. Informal Contracts Informal bids are referenced by NC General Statute (NCGS) 143-131 as construction or repair work that does not reach the limits prescribed

More information

REQUEST FOR INFORMATION (RFI) 09-I-SM-028 PEOPLE COUNTERS. Issue Date: June 19, Submission Date: July 20, 2009.

REQUEST FOR INFORMATION (RFI) 09-I-SM-028 PEOPLE COUNTERS. Issue Date: June 19, Submission Date: July 20, 2009. REQUEST FOR INFORMATION (RFI) 09-I-SM-028 PEOPLE COUNTERS Issue Date: June 19, 2009 Submission Date: July 20, 2009 Point of Contact (Procedural Questions) Sean K. Mitchell, Contract Specialist Contract

More information

This presentation was prepared by TeHota Construction Management, LLC. on behalf of Hunt Construction Group for the AT&T Center Renovation Project.

This presentation was prepared by TeHota Construction Management, LLC. on behalf of Hunt Construction Group for the AT&T Center Renovation Project. February 11, 2015 This presentation was prepared by TeHota Construction Management, LLC. on behalf of Hunt Construction Group for the AT&T Center Renovation Project. It is provided, as a courtesy, to those

More information

Enclosed is Addendum No. 2 to SEPTA's Sealed Bid No ATMM 5 & Market Station Enhancement Project.

Enclosed is Addendum No. 2 to SEPTA's Sealed Bid No ATMM 5 & Market Station Enhancement Project. February 23, 2018 Dear Sir/Madam Enclosed is Addendum No. 2 to SEPTA's Sealed Bid No. 17-00265-ATMM 5 & Market Station Enhancement Project. The bid opening date and time scheduled for Wednesday, February

More information

INVITATION FOR BID. HVAC Equipment Replacement for Black Box Theatre at Nordlof Center. Issued June 14, Name of Bidding Firm:

INVITATION FOR BID. HVAC Equipment Replacement for Black Box Theatre at Nordlof Center. Issued June 14, Name of Bidding Firm: INVITATION FOR BID HVAC Equipment Replacement for Black Box Theatre at Nordlof Center Issued June 14, 2017 Name of Bidding Firm: Address: City: State: Zip: Phone: Fax Bid Opening Time and Date: Bid Deposit/Bid

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL DATE: February 24, 2015 Shimizu North America LLC 909 3rd Avenue, 28th Floor New York, NY 10022 RFP Queries (646) 205-4722 Fax (212) 223-1930 PROJECT: The Japan Foundation New York

More information

SEATTLE S NEW WMBE INCLUSION PLAN

SEATTLE S NEW WMBE INCLUSION PLAN SEATTLE S NEW WMBE INCLUSION PLAN This past summer Seattle Mayor Mike McGinn announced a new WMBE program for Seattle public works contracts he called an Inclusion Plan to increase women and minority owned

More information

Pre-Construction Meeting Minutes

Pre-Construction Meeting Minutes Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes

More information

YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects

YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects WORKING DOCUMENT YORK REGION DISTRICT SCHOOL BOARD Policy and Procedure #465.0, Tendering Capital Construction and Maintenance Projects The Tendering Capital Construction and Maintenance Projects policy

More information

700 CMR: MASSACHUSETTS DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION

700 CMR: MASSACHUSETTS DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION 700 CMR 14.00: PREQUALIFICATION OF CONTRACTORS FOR HORIZONTAL CONSTRUCTION Section 14.01: Definitions 14.02: Application for Prequalification of Contractors 14.03: Aggregate Bonding Capacity and Single

More information

Stacey Camillo, Contract Administration. As-Needed Construction Contracting

Stacey Camillo, Contract Administration. As-Needed Construction Contracting Stacey Camillo, Contract Administration As-Needed Construction Contracting November 3, 2016 Why we are here Agenda Introductions Methods of getting construction work in San Francisco New As-Needed Construction

More information

PROJECT MANUAL Volume 1. Project: Clayton Greenway System -Mark s Creek Bridge Replacement

PROJECT MANUAL Volume 1. Project: Clayton Greenway System -Mark s Creek Bridge Replacement PROJECT MANUAL Volume 1 Project: Clayton Greenway System -Mark s Creek Bridge Replacement Owner: Town of Clayton Construction Manager: Lysaght & Associates Issued August 9, 2017 COVER SHEET 000000-1 TABLE

More information

Pier C North Damaged Pile Repairs. Pre-Bid Meeting April 24, :00 AM. Agenda Items

Pier C North Damaged Pile Repairs. Pre-Bid Meeting April 24, :00 AM. Agenda Items Pier C North Damaged Pile Repairs Pre-Bid Meeting April 24, 2012 10:00 AM Agenda Items 1. SCOPE: Repair of 71 damaged piles. The piles are 16 and 18 square precast concrete piles that were installed around

More information

WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS

WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER CONTRACTOR

More information

Sample Social Clauses to Encourage Community Benefits from Waste

Sample Social Clauses to Encourage Community Benefits from Waste Sample Social Clauses to Encourage Community Benefits from Waste What are social clauses and community benefits? 1 The UK Sustainable Development Strategy has set the challenge of making the UK an EU leader

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Subcontractor Pre-Qualification Form

Subcontractor Pre-Qualification Form Subcontractor Pre-Qualification Form Page 1 of 3 Today s Date (MO/DAY/YEAR): / / Person Completing Form: Company Information Company Name: Company Website: President/Owner/Partner Name: Other Contact Name/Title:

More information

Request for Qualifications Professional Services For. Wood Recycling Center Facility. Contract Number: C City of Chattanooga, Tennessee

Request for Qualifications Professional Services For. Wood Recycling Center Facility. Contract Number: C City of Chattanooga, Tennessee Request for Qualifications Professional Services For Wood Recycling Center Facility Contract Number: C-17-017-101 City of Chattanooga, Tennessee December 2017 Section 1 Introduction REQUEST FOR QUALIFICATIONS

More information

MARCH 16, 2011 DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS FOR REROOF DFW BUSINESS CENTER SOUTH

MARCH 16, 2011 DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS FOR REROOF DFW BUSINESS CENTER SOUTH MARCH 16, 2011 DALLAS/FORT WORTH INTERNATIONAL AIRPORT BOARD ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS FOR REROOF DFW BUSINESS CENTER SOUTH CONTRACT NO. 9001810 The specifications are revised as follows.

More information

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID Solicitation #: ITB 151-2017 Title: Description: SEMINOLE TRIBE OF FLORIDA INVITATION TO BID General Home Repairs (Big Cypress Reservation) The Housing Department of the Seminole Tribe of Florida is requesting

More information

DISADVANTAGED BUSINESS ENTERPRISE PROGRAM (49 CFR PART 26) FOR FREDERICKSBURG REGIONAL TRANSIT POLICY STATEMENT

DISADVANTAGED BUSINESS ENTERPRISE PROGRAM (49 CFR PART 26) FOR FREDERICKSBURG REGIONAL TRANSIT POLICY STATEMENT DISADVANTAGED BUSINESS ENTERPRISE PROGRAM (49 CFR PART 26) FOR FREDERICKSBURG REGIONAL TRANSIT POLICY STATEMENT Section 26.1, 26.23 Objectives/Policy Statement FREDericksburg Regional Transit (FRED), a

More information

Document Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction

Document Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction Document 00 41 13 - Bid Form (General Contract) State of Ohio Standard Requirements for Public Facility Construction Sealed bids will be received by Miami University at 181 Cole Service Building, Oxford,

More information

LEVEL I PREQUALIFICATION DOCUMENTS

LEVEL I PREQUALIFICATION DOCUMENTS Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,

More information

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011 TO: All Bidders From: Gila River Indian Community, Property and Supply Department The following addendum to the George Webb Village Subdivision Infrastructure construction project is made. Acknowledgment

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information

BID AND PURCHASING LAWS/BEST PRACTICES

BID AND PURCHASING LAWS/BEST PRACTICES BID AND PURCHASING LAWS/BEST PRACTICES BEFORE YOU DO ANYTHING, ASK YOURSELF THIS QUESTION. Is this purchase or contract for goods or services exempt from the bid laws? Exemptions: Piggy back off a contract

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K CONTRACTS CATALOG Updated Docs Inside ou Ah ead o f the Cur v e gy epin e K ... BUILDING A BETTER WAY! Whether working at the office, from the road or even at home, the platform provides instant access

More information

Asbestos Removal at Forest Blvd., Hugo, MN

Asbestos Removal at Forest Blvd., Hugo, MN Request for Bids for Asbestos Removal at 14383 Forest Blvd., Hugo, MN This Request for Bids ( RFB ) is for the services of a qualified and licensed contractor to provide removal of Asbestos contaminated

More information

Request For Information (RFI) For a. Spectrum Management & Monitoring System (SMMS)

Request For Information (RFI) For a. Spectrum Management & Monitoring System (SMMS) Request For Information (RFI) For a Spectrum Management & Monitoring System (SMMS) Table of Contents 1 Introduction... 3 1.1 About Iraq CMC... 3 1.2 The Iraq CMC Objectives... 3 1.3 RFI Process... 4 2

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

PROJECT PROCUREMENT MANAGEMENT. 1 Powered by POeT Solvers Limited

PROJECT PROCUREMENT MANAGEMENT. 1  Powered by POeT Solvers Limited PROJECT PROCUREMENT MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited CONDUCT PROCUREMENT PROCESSES BY PROCESS GROUP Planning Executing Monitoring and controlling Closing 12.1 12.2 12.3 12.4

More information

FOGARTY MEMORIAL SCHOOL Plumbing Renovations

FOGARTY MEMORIAL SCHOOL Plumbing Renovations PROJECT MANUAL Issued For Construction June, 2017 FOGARTY MEMORIAL SCHOOL Plumbing Renovations 736 Snake Hill Road North Scituate, Rhode Island 02857 AHARONIAN & ASSOCIATES, INC. - ARCHITECTS 310 George

More information

SYSTEM SAFTEY AND OPERATIONS COMMITTEE SEPTEMBER 19, 2013 LIQUID WASTE REMOVAL SERVICES APPROVE CONTRACT AWARD ACTION: RECOMMENDATION

SYSTEM SAFTEY AND OPERATIONS COMMITTEE SEPTEMBER 19, 2013 LIQUID WASTE REMOVAL SERVICES APPROVE CONTRACT AWARD ACTION: RECOMMENDATION 29 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFTEY AND OPERATIONS COMMITTEE SEPTEMBER 19, 2013 SUBJECT: ACTION: LIQUID WASTE REMOVAL SERVICES APPROVE CONTRACT AWARD

More information

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR

DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR DALLAS/FORT WORTH INTERNATIONAL AIRPORT DESIGN, CODE AND CONSTRUCTION DEPARTMENT ADDENDUM NO. 2 FOR TAXIWAY Y BRIDGE REINFORCEMENT FOR GROUP VI AIRCRAFT CONTRACT NO. 9500498 November 30, 2017 The Request

More information

REQUEST FOR QUOTES (RFQ) # Issue Date: December 5, 2017

REQUEST FOR QUOTES (RFQ) # Issue Date: December 5, 2017 REQUEST FOR QUOTES (RFQ) #2017-25 Issue Date: December 5, 2017 Procurement & Contract Services Klamath Falls: Wilsonville: 541.885.1133 (office) 503.821.1266 (office) 3201 Campus Dr. 27500 SW Parkway Ave.

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

Addendum Number 1. August 31, Colcock Hall Windows. Owner Project Number: Prepared by:

Addendum Number 1. August 31, Colcock Hall Windows. Owner Project Number: Prepared by: Addendum Number 1 Colcock Hall Windows Owner Project Number: 50059 Prepared by: ADC Engineering, Inc. 1226 Yeamans Hall Road Hanahan, South Carolina 29410 To Bidders: This Addendum forms a part of the

More information

RFP IP-Based Surveillance Camera System

RFP IP-Based Surveillance Camera System RFP IP-Based Surveillance Camera System The Clinton Community School District (referenced as the DISTRICT throughout this proposal) desire to implement a district wide,tcp/ip based surveillance camera

More information

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE

CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE AZUSA UNIFIED SCHOOL DISTRICT 1 TABLE OF CONTENTS Filing of PreQualifications Submittals 3 PREQUALIFICATION QUESTIONNAIRE 6 Page Part I:

More information

Johns Hopkins University APL Building 201 December 5, Rob Dahms,

Johns Hopkins University APL Building 201 December 5, Rob Dahms, INVITATION TO BID BID DUE DATE: January 5, 2018 TO: 1:00 PM Rob Dahms, rdahms@tcco.com MWSDBE OUTREACH/ PRE-BID CONFERENCE: LOCATION: December 19, 2017 Tentative 9:00 AM JHU APL Building 200, 1 st Floor

More information

NORTHEAST TEXAS PUBLIC HEALTH DISTRICT (NET HEALTH) REQUEST FOR PROPOSALS (RFP)

NORTHEAST TEXAS PUBLIC HEALTH DISTRICT (NET HEALTH) REQUEST FOR PROPOSALS (RFP) NORTHEAST TEXAS PUBLIC HEALTH DISTRICT (NET HEALTH) REQUEST FOR PROPOSALS (RFP) PROJECT: SERVER REPLACEMENT November 28, 2016 OVERVIEW 1. Project Background and Description The Northeast Texas Public Health

More information

TEAMING, SUBCONTRACTING, AND JOINT VENTURES

TEAMING, SUBCONTRACTING, AND JOINT VENTURES 888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 TEAMING, SUBCONTRACTING, AND JOINT VENTURES 2013 NATIONAL HUBZONE CONFERENCE SEPTEMBER 10, 2013 Presented

More information

CLARIFICATIONS, CHANGES AND ADDITIONS TO THE BID DOCUMENTS

CLARIFICATIONS, CHANGES AND ADDITIONS TO THE BID DOCUMENTS The Philadelphia Parking Authority Mellon Independence Center 701 Market Street, Suite 5400 Philadelphia, PA 19106 Bid No. 16-33 To: From: See Email Distribution List Mary Wheeler Manager of Contract Administration

More information

SECTION 3 PARTICIPATION PLAN. (Owner/Developer and General Contractor)

SECTION 3 PARTICIPATION PLAN. (Owner/Developer and General Contractor) SECTION 3 PARTICIPATION PLAN (Owner/Developer and General Contractor) For (Name and Address of Construction Project) Submitted by: Name of Owner/Developer: Address: Primary Contact: Phone number: Email:

More information

RESIDENT ENGINEER S MANUAL

RESIDENT ENGINEER S MANUAL Peninsula Corridor Joint Powers Board 1250 San Carlos Avenue San Carlos, California 94070-1306 RESIDENT ENGINEER S MANUAL Revision 2 Page 1 of 336 Caltrain Standard Manual RESIDENT ENGINEER S MANUAL Manual

More information

UNC Charlotte Parking Lot 8 Expansion Charlotte, North Carolina SCO #: McAdams Project #: CLT-17010

UNC Charlotte Parking Lot 8 Expansion Charlotte, North Carolina SCO #: McAdams Project #: CLT-17010 ADDENDUM NUMBER ONE Date: March 8, 2018 From: McAdams Re: UNC Charlotte Parking Lot 8 Expansion Charlotte, North Carolina SCO #: 17-17177-01 McAdams Project #: CLT-17010 NOTICE TO BIDDERS: Bidder is hereby

More information

OHIO DEPARTMENT OF TRANSPORTATION MENTOR/PROTÉGÉ PROGRAM

OHIO DEPARTMENT OF TRANSPORTATION MENTOR/PROTÉGÉ PROGRAM OHIO DEPARTMENT OF TRANSPORTATION MENTOR/PROTÉGÉ PROGRAM Table of Contents INTRODUCTION AND OVERVIEW... 3 DEFINITIONS... 3 MEASURABLE OBJECTIVES... 4 ROLES & RESPONSIBILITIES... 4 OHIO DEPARTMENT OF TRANSPORTATION...

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center Construction 101 C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center This training is provided for educational, compliance and loss-prevention purposes only and, absent the

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

Transit Return on Investment (ROI) Study Request for Proposals (RFP)

Transit Return on Investment (ROI) Study Request for Proposals (RFP) Transit Return on Investment (ROI) Study Request for Proposals (RFP) Table of Contents 1. Introduction... 1 2. Scope of Services... 1 3. Project Schedule... 5 4. Evaluation Criteria... 5 5. Submission

More information

Next PBDG Meeting: PBDG Holiday Gift Giving

Next PBDG Meeting: PBDG Holiday Gift Giving January 2018 UPDATE PROFESSIONAL BUSINESS DEVELOPMENT GROUP A Trade Association for Construction and Professional Services Prosperity Success Profitability Thriving We hope you all enjoyed your holidays

More information

Step 1: Determination of Base Figure for Relative Availability of DBEs

Step 1: Determination of Base Figure for Relative Availability of DBEs MassDOT calculated the Transit Division goal utilizing a preliminary budget to identify federalaid service and supply contracts on USDOT-assisted projects to be performed. To determine the relative availability

More information

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES

LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES LABOR COMPLIANCE PROGRAM PRESENTATION CERRITOS COLLEGE BOARD OF TRUSTEES 1 of 15 CS & ASSOCIATES EXPERIENCE & BACKGROUND Established in 2003 by Charla Curtis, Former LCP Director for LAUSD Certified MBE/

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

County of Santa Barbara. Airport Security Enhancements. 900 Airport Road, Santa Ynez, California

County of Santa Barbara. Airport Security Enhancements. 900 Airport Road, Santa Ynez, California County of Santa Barbara Airport Security Enhancements 900 Airport Road, Santa Ynez, California Project No. 8595 MANDATORY JOB WALK: July 23 rd, 2015 10:00 A.M. BID OPENING DATE: August 13 th, 2015 at 2:00

More information

COVER PAGE. Bid Proposal #2016 INTERACTIVE VOICE RESPONSE SYSTEM (IVR)

COVER PAGE. Bid Proposal #2016 INTERACTIVE VOICE RESPONSE SYSTEM (IVR) COVER PAGE Bid Proposal #2016 Sealed bids and electronic submitted bids for the above will be received until 10:00 AM CST, TUESDAY, FEBRUARY 24, 2015, and publicly opened in the City of Alexandria Council

More information

ASA PM WORKSHOP PROJECT MANAGEMENT

ASA PM WORKSHOP PROJECT MANAGEMENT ASA PM WORKSHOP PROJECT MANAGEMENT SESSION 2 RECAP 1 ST SESSION Jonathan Mitz 1 st Session Presenters for Session 2 Bruce Spengler, Calvert Masonry Steve Groth, Chiaramonte Construction 1 SESSION 2 TOPICS

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

ATTENTION CONTRACTORS

ATTENTION CONTRACTORS ATTENTION CONTRACTORS If you download this RFQ from the website, it is your responsibility to advise WOU's Planning Office that you have done so. This will allow us to add you to the Respondent's List,

More information

NOTIFICATION OF ADDENDUM ADDENDUM NO. 1 DATED 12/20/2017

NOTIFICATION OF ADDENDUM ADDENDUM NO. 1 DATED 12/20/2017 NOTIFICATION OF ADDENDUM ADDENDUM NO. 1 DATED 12/20/2017 Control 6316-00-001 Project RMC - 631600001 Highway US0059 County HARRISON Ladies/Gentlemen: Attached please find an addendum on the above captioned

More information

Mentor-Protégé Program. Disadvantaged Business Enterprise NDOT External Civil Rights Division

Mentor-Protégé Program. Disadvantaged Business Enterprise NDOT External Civil Rights Division Mentor-Protégé Program Disadvantaged Business Enterprise NDOT External Civil Rights Division Date: July 2016 TABLE OF CONTENTS I. INTRODUCTION AND OVERVIEW II. DEFINITIONS III. MEASURABLE OBJECTIVES IV.

More information

Connoisseur Solutions Project Procurement Management

Connoisseur Solutions Project Procurement Management Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes

More information

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

CM470 Legal Issues in Construction [Onsite]

CM470 Legal Issues in Construction [Onsite] CM470 Legal Issues in Construction [Onsite] Course Description: This course explores the legal issues arising from design and construction services. Topics include contracts, land zoning and property ownership,

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

BUSINESS AND SUPPLIER DIVERSITY POLICY # 7.10

BUSINESS AND SUPPLIER DIVERSITY POLICY # 7.10 DOING BUSINESS WITH ABOUT THE OFFICE OF DIVERSITY AND INCLUSION The Diversity and Inclusion Department serves to support the mission of the Commission to promote equity in contracting, hiring, recruiting,

More information

Exhibit A Scope of Services and Deliverables

Exhibit A Scope of Services and Deliverables Exhibit A Scope of Services and Deliverables Attachment to MnDOT Contract No. for Project Name Project # 16-TZ dated Scope of Services includes: Programming / Schematic Design Phase Design Development

More information

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department

Peralta Community College District th Avenue Oakland, California Phone (510) Fax (510) Purchasing Department Peralta Community College District 501 5 th Avenue Oakland, California 94606 Phone (510) 466-7225 Fax (510) 587-7873 Purchasing Department Date: March 30, 2011 ADDENDUM No. 3 BID NO.: 10-11/27 PCCD Smart

More information

Sub-Contractor/Supplier Pre-Qualification Questionnaire

Sub-Contractor/Supplier Pre-Qualification Questionnaire CURRENT DATE: *Please submit form by Fax or E-Mail to: 317.846.3113 info@allieddiversified.com COMPANY NAME: CONTACT: ADDRESS: STREET: CITY: STATE: ZIP: PHONE: FAX: E-MAIL: WEBSITE: 1. ORGANIZATION 1.1

More information

DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019

DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019 DBE METHODOLOGY AND GOAL FOR VALLEY REGIONAL TRANSIT FOR FEDERAL FISCAL YEARS: 2017, 2018, and 2019 November 30, 2016 Page 1 of 6 OVERVIEW OF THE GOAL-SETTING PROCESS The following narrative explains the

More information