1 Kern River Gas Transmission Company Customer Meetings
2 Exceptional Businesses and Assets 11.6 million customers worldwide Top-rated service provider within the industry 22,700 employees worldwide Exceptional safety and work environment 39% energy generation renewable and noncarbon Customer rates below national average $90b of total assets 33,500 miles of electricity transmission lines 16,400 miles of natural gas pipeline 30,000 MW owned generation 2017 net income $2.87b 2
3 Kern River System Based in Salt Lake City, UT 1,717-mile pipeline system, of which 1,300 miles are 36 diameter steel pipe 384,220 compressor horsepower 2.17 Bcf/day design capacity Access to Rocky Mountain basins and Elk Hills supply via 20 receipt meter stations Access to markets in Utah, Nevada and California via 73 delivery meter stations 3
4 Kern River Supply Flow Options Wyoming 5.0 Bcf/d Kern River customers have access to abundant and cost competitive supplies Rockies, Canadian, Permian, and San Juan supplies access premium markets in southern Nevada and southern California Salt Lake City Salt Lake City Goshen 0.6 Bcf/d Freemont Peak receipt point allows access to PG&E system supplies Wheeler Ridge and Kramer Junction allows access to SoCal system supplies 17Z Oxy receipt point provides access to Elk Hills supply Oxy 17Z 0.2 Bcf/d Los Angeles Fremont Peak 0.3 Bcf/d Las Vegas Dag Moj 0.4 Bcf/d 4
5 Kern River Advantages Provides a variety of transportation services Delivers highly reliable service Provides exceptional customer service Financially supported by Berkshire Hathaway to maintain the integrity of its pipeline system and to expand based on the needs of its customers Completed Projects Physical security installed at all compressor stations, select meter stations and valve sites Security data from field locations transmitted 24/7 to Kern River s gas control center Hardware and software upgrades Numerous computer applications updated and/or re-written Infrastructure (firewalls and switches) updated 5
6 Kern River System Operations Wholly-owned system is looped except thru Las Vegas Gas can flow down one pipeline when the other is out of service Gas control Staffed 24/7 Off-site back-up if needed during emergencies SCADA All facilities remotely monitored/controlled from gas control Real-time modeling Monitors system efficiency Predictive capabilities Integrated with SCADA System 6
7 Kern River System Received 27% of Rockies natural gas supply in 2017 Delivered 26% of California s 2016 demand for natural gas 1/ Is the primary source of natural gas for southern Nevada Scheduled throughput averaged 105% of design capacity in 2017 (same in / ) Average Scheduled Volume (Dth/day) 3,000,000 2,500,000 2,000,000 1,500,000 1,000, , Avg Daily Sched Design 1/ 2017 California Gas Report, California Gas and Electric Utilities 2/ January 1, 2018 through February 18,
8 2018 Customer Commitment To be the best energy company in serving our customers, while delivering sustainable energy solutions What does this mean? You will get what we promise accurately and on time Mutually beneficial relationships based on our core principles, not quarter over quarter profits We will share the purpose behind our actions No surprises either way Frank, candid discussions We will commit to making it easy to do business with us We will negotiate and perform in good faith We will continue to invest in the pipeline in order to provide you highly reliable service and to meet your future growth needs Seek balanced outcomes Do necessary due-diligence, but maintain an attitude of partnership 8
9 Customer Satisfaction 2018 Mastio Survey Results #1 in Regional Pipeline Group for past 10 years Placed #2 out of 37 Interstate Pipelines (#2 of 36 pipelines in 2017) 2018 vs overall score: vs (1.15 increase) Scores increased in 25 of 29 attributes We will continue to work with you to identify actions to address your concerns 9
10 Customer Satisfaction 2018 Mastio Survey Results No. Attribute st Edition nd Edition Difference 11 Effectiveness of contract negotiations (0.30) 27 Competitive rates and discounts (0.04) 29 How likely would you be to recommend this company to a friend or colleague? (0.03) 6 Representatives who listen well (0.03) 18 Accurate operational information is readily available Pipeline staff provides prompt & accurate responses to questions, requests and issues Representatives understand the needs and challenges of your business Accuracy of gas metering systems Expertise of the representatives to help solve your business needs Solution creativity & innovation Independent of costs, how would you rate each pipeline on overall performance? Effectiveness of the pipeline's system for nominating, confirming & scheduling Effectiveness of pipeline's capacity release and contract systems and procedures Accuracy of invoices Firm gas transportation is highly reliable Scheduled gas volumes are accurate Value received for the money paid to the pipeline Communicates in an honest & forthright manner Representatives are accessible when needed Effectiveness of pipeline's system training (i.e. their proprietary EBB) Management of pipeline initiated restrictions Effective after hours support Flexibility of physical gas flow delivery Financial stability Quality of pipeline initiated communications Flexibility of gas pooling & aggregation services Ample access to diverse supply and/or markets Flexible transport options (hourly vs. monthly firm) Access to available storage
11 Customer Comments What we can do better Inability to understand our business needs and poor communication More consistency in managing the pipeline Switching of staff Access to storage Customer Satisfaction 2018 Mastio Survey Results Restrictions on flexibility within the pipeline due to Aliso Canyon issues Provide more operating data to allow shippers to be proactive when scheduling, to avoid OFOs 11
12 Customer Satisfaction 2018 Mastio Survey Results Customer Comments What we re doing well Their honesty in explaining rationale for pricing contracts beyond existing period They are always accessible Accommodating and informative when asked for help with using nomination system Very stable company with the right attitude to respond to system changes They are very knowledgeable and easy to reach, they understand our business 12
13 2018 Customer Satisfaction Improvement Initiatives Rates and Contract Negotiations Continue pricing turnback and operational capacity based on market conditions Seek creative ways to structure deals in the current narrow spread environment Representatives Cross-train existing employees and train new employees Use 3-way communication to ensure Kern River understands your needs & challenges Customer inquiries receive a response within 8 hours Communication Monitor NAESB Version 3.1 and update customers after FERC approval Continue to update customers on Kern River operations, line pack, balancing conditions, weather and 3 rd party system information Flexibility Manage daily imbalances to ensure transportation services are not jeopardized Allow intra-day flexibility to the extent possible 13
14 2018 Customer Satisfaction Improvement Initiatives Transportation Services Firm Reservation/Volumetric Fixed/Indexed Short-term/Long-term Interruptible Peaking Pooling Park and Loan Rapids Integrate index-based pricing into transportation sales and invoicing systems Improve and automate the sales and contracting processes Enhance filtering in measurement window Follow-up discussions During the year ensure action items are still relative and ultimately resolved per customer expectations 14
15 2018 Customer Satisfaction Improvement Initiatives Quick Links New Category on the DOR Website Maps Rapids Setup Notices Currently Effective Rates Fuel Matrix Rapids Tips & Tricks (Training) Export-Import-Copy Nominations FERC Order 809 Scheduling Timelines NAESB 3.0 Capacity Release Timelines Agreement Request Tutorial Park & Loan Cut Notification Maximize Your Noms Export-Import-Copy Confirmations FERC Order 809 EPSQ Calculations Pooling-Title Transfer Tracking Tutorial Capacity Release System Overview Historical Fuel Rates Netting & Trading Imbalances Instructions for Use of Rapids on an ipad 15
16 2018 Customer Satisfaction Improvement Initiatives Pooling / Title Transfer Tracking on Kern River Kern River offers pooling service to any party with a valid pooling agreement number Pooling agreement numbers are used to aggregate supply into associated receipt pools and disaggregate supply out of associated delivery pools. Pooling agreement numbers are used to nominate transfers within receipt pools and delivery pools. Transportation agreements must be used to transport out of the receipt pools and into the delivery pools. Fuel will NOT be charged to pooling/title transfer tracking agreement numbers. Kern River has two pool types: Interruptible (IT) and Firm (FT). Separate pools have been created based on customer requests to be able to determine whether the pool gas is Firm or Interruptible capacity. 16
17 2018 Customer Satisfaction Improvement Initiatives Daily Operational Report (DOR) website ~ Real-time line pack by segments now available ~ Interactive pipeline system map coming soon 17
18 2018 Customer Satisfaction Improvement Initiatives 18
19 Pipeline System Management Critical Line Pack Events Line Pack Level Low High Several notices may have been posted for each critical line pack event Kern River has not issued a scheduling or imbalance penalty since the pipeline was placed into service (February 1992) We must continue to work together to avoid impacts to transportation services and extreme high and low line pack conditions 19
20 Firm Transportation RESERVATION/DEMAND RATES Original Period 2 Alternate Insulated Non-Insulated Period 2 Rolled-In Service Period 1 10-yr 15-yr 10-yr 15-yr 25-yr 2002 Exp 10-yr $ N/A $ N/A N/A $ Orig Sys/2002 Exp 15-yr $ $ $ $ $ $ Alternate Original Period 2 Period 2 Incremental Service Period 1 10-yr 15-yr 25-yr N/A 2003/2010 Exp 10-yr $ $ $ $ /2010 Exp 15-yr $ $ $ $ All rates are non-leap year rates. 20
21 Competitive Rates to Southern California* Source: Platts M2MS Modeled Natural Gas Curves, 120-Month Daily Assessments dated May 22, 2018 *Kern River is also the lowest cost option to Southern Nevada 21
22 Kern River Supply (Dth per day) WYOMING Interstate Pipelines Northwest Pipeline 327, , , , , , ,558 Colorado Interstate 35,736 53,067 46,983 58,327 54,885 48,919 62,021 Overland Trail ,435 4,043 Roberson Creek (Dominion Overthrust) 107, , , , , , ,967 Overthrust 121 (Dominion Overthrust) 22,346 33,637 20,507 25,906 68,976 58,245 39,651 Hams Fork (Questar Overthrust) 161, , , , , , ,117 Gas Processing Plants Opal (Williams Field Services) 345, , , , , , ,954 Carter Creek (Hilcorp Energy) 60 12,636 18,081 16, , Painter (Merit Energy) 36,498 28,522 27,068 32,441 45,238 42,583 57,107 Pioneer (Enterprise Products) 510, , , , , , ,553 Rendezvous (Blacks Fork) 353, , , , , , ,802 Storage Whitney Canyon (Ryckman) 8,738 16,242 20, ,167 3,182 Clear Creek (QEP Field Services) 7 3,648 6,311 3,083 5,602 7,541 6,161 UTAH Interstate Pipelines Goshen (Dominion Questar Pipeline) 264, , , , , , ,026 CALIFORNIA Gas Processing Plants CA Resources Elk Hills 31,365 50,501 49,246 50,376 55,416 47,868 57,462 TOTAL SUPPLY 2,205,948 2,281,484 2,400,388 2,468,127 2,335,870 2,430,292 2,590,114 22
23 Kern River Market (Dth per day) CALIFORNIA LDC (SoCal Gas / PG&E) 907, , , , , ,792 1,024,981 Industrial (Primarily EOR) 497, , , , , , ,270 Power Generation 137, , , , , , ,162 Commercial & Pipelines 1,147 3,922 2,693 1,969 9,233 15,983 13,152 Total California 1,542,920 1,563,423 1,632,163 1,708,300 1,682,729 1,704,321 1,884,565 NEVADA LDC (Southwest Gas) 218, , , , , , ,265 Power Generation (NV Energy / LADWP) 299, , , , , , ,546 Total Nevada 518, , , , , , ,811 UTAH LDC (Questar Gas) 88,937 93,295 94, , , , ,162 Industrial (North Salt Lake Refineries) 12,997 11,522 11,285 14,225 12,986 13,194 11,429 Other Pipelines Power Generation (West Valley) 3,129 3,818 3, ,211 14,309 10,556 Total Utah 105, , , , , , ,611 TOTAL MARKET 2,166,191 2,264,823 2,374,729 2,439,826 2,327,523 2,419,013 2,590,987 23
24 Market Dynamics Kern River de-contracting California pipeline s maintenance California storage and new regulations Renewables Hydro-electric generation Deliveries to Mexico LNG exports Growing production / shifting pipeline paths Coal and nuclear power plant retirements 24
Shelley Wright Kendrick General Manager, Marketing & Business Development. April 13, 2012 Platt s 6 th Annual Rockies Oil & Gas Conference
Shelley Wright Kendrick General Manager, Marketing & Business Development April 13, 2012 Platt s 6 th Annual Rockies Oil & Gas Conference 1 Questar Pipeline System Overview Overthrust Pipeline Company
More informationQuestar Pipeline Current Capacity and Development
Questar Pipeline Current Capacity and Development Gary A. Schmitt Manager, Marketing and Business Development April 27, 2007 Platts Rockies Gas and Oil Conference 1 Agenda Questar Pipeline Overview Basin
More informationQUESTAR PIPELINE CUSTOMER MEETING MARCH 2017 PARK CITY, UTAH
QUESTAR PIPELINE CUSTOMER MEETING MARCH 2017 PARK CITY, UTAH Ron Jorgensen Vice President Operations & Gas Control, Questar Pipeline 2 Merger Related Update February 1, 2016 Dominion/Questar merger announced
More informationMagnum Gas Storage, LLC
MAGNUM GAS STORAGE PROJECT OPEN SEASON FOR INTERSTATE NATURAL GAS STORAGE SERVICES Response Due By July 31, 2009, at 5:00 MDT June 9, 2009 Magnum Gas Storage, LLC (Magnum), invites your company to participate
More informationMagnum Gas Storage, LLC
September 2016 Non-Binding Open Season Providing the Western US with Critical Energy Infrastructure www.westernenergyhub.com/natural-gas-midstream.php MAGNUM GAS STORAGE PROJECT OPEN SEASON FOR FIRM INTERSTATE
More informationJim Cleary President, El Paso Western Pipelines. Platts Conference, Rockies Gas & Oil April 25, 2008
Jim Cleary President, El Paso Western Pipelines Platts Conference, Rockies Gas & Oil April 25, 2008 Cautionary Statement Regarding Forward-looking Statements This presentation includes forward-looking
More informationRuby Pipeline Project
Ruby Pipeline Project Ed Miller Ruby Project Manager October 21, 2008 El Paso Pipeline System Ruby Pipeline CIG & WIC Tennessee Gas Pipeline Mojave Pipeline El Paso Natural Gas Cheyenne Plains Pipeline
More informationAnalysis of California Natural Gas Market, Supply Infrastructure, Regulatory Implications, and Future Market Conditions. CIEE Subcontract No.
Analysis of California Natural Gas Market, Supply Infrastructure, Regulatory Implications, and Future Market Conditions CIEE Subcontract No. MNG-07 07-0101 Natural Gas Storage Forum: Modeling of Natural
More informationMajor Changes in Natural Gas Transportation Capacity,
Major Changes in Natural Gas Transportation, The following presentation was prepared to illustrate graphically the areas of major growth on the national natural gas pipeline transmission network between
More informationDirector TGP Facility Planning and Gas Control June 3, Prepared for the Harvard Electricity Policy Group
www.elpaso.com NYSE:EP Anders Johnson Director TGP Facility Planning and Gas Control June 3, 2011 Prepared for the Harvard Electricity Policy Group D E P E N D A B L E N A T U R A L G A S El Paso Corporation
More informationPresentation to State Commissions Northern Natural Gas Company Spring-Summer 2018
Presentation to State Commissions Northern Natural Gas Company Spring-Summer 2018 BHE Pipeline Group BHE Pipeline Group Northern Natural Gas Company Nation s largest pipeline system Web-like configuration
More informationUniversity of Wyoming The 2008 Conference The Wyoming Pipelines: The Territory Ahead
FERC CERTIFICATION University of Wyoming The 2008 Conference The Wyoming Pipelines: The Territory Ahead 1 Robert Cupina, Principal Deputy Director Federal Energy Regulatory Commission Cheyenne, Wyoming
More informationQUESTAR PIPELINE OPERATIONS & CUSTOMER SERVICE MEETING
QUESTAR PIPELINE OPERATIONS & CUSTOMER SERVICE MEETING 2013 Meeting Hotel Park City Park City, Utah WELCOME Larry Conti V.P. Operations & Engineering NEW PIPEVIEWER Jeannie Yerkovich SCADA Analyst Classic
More informationOutlook for Western U.S. Natural Gas Markets
Outlook for Western U.S. Natural Gas Markets Summer Energy Outlook Conference April, Contact: Kevin R. Petak Vice President, Gas Market Modeling ICF International 73-1 1-753753 kpetak@icfi.com ICF International.
More informationWELCOME & INTRODUCTIONS
WELCOME & INTRODUCTIONS Ron Jorgensen Vice-President, Operations & Gas Control 1 Agenda 8:30 a.m. Welcome and Introductions Ron Jorgensen 8:45 a.m. Meet the Pipeline President Micheal Dunn 9:10 a.m. Integrity
More informationWhite River Hub Customer Meeting November 6, 2008
White River Hub Customer Meeting November 6, 2008 Gary A. Schmitt Questar Pipeline Company General Manager, Marketing and Business Development Enterprise White River Hub Questar Northwest REX TransColorado
More informationNatural Gas Next: The Rockies and the West
Natural Gas Next: The Rockies and the West Callie Kolbe, Manager, Energy Analysis Sadie Fulton, Senior Energy Analyst September 25, 2017 Jordan Cove Back again? There is even more gas? NIMBY! Renewable
More informationBroad market presence: Growing demand regions, key supply basins, LNG terminals. Excellent connections to markets and supply
Pipeline Group Strong and Growing Broad market presence: Growing demand regions, key supply basins, LNG terminals Excellent connections to markets and supply Almost $4 billion of committed growth projects
More information) ) SUPPLEMENTAL DIRECT TESTIMONY OF DAVID BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY
Application No: A. 11-11-00 Exhibit No.: Witness: David Bisi ) In the Matter of the Application of San Diego Gas & ) Electric Company (U 90 G) and Southern California ) Gas Company (U 90 G) for Authority
More informationFERC GAS TARIFF THIRD REVISED VOLUME NO. 2. (Superseding Second Revised Volume No. 2) WYOMING INTERSTATE COMPANY, L.L.C.
FERC GAS TARIFF THIRD REVISED VOLUME NO. 2 (Superseding Second Revised Volume No. 2) of WYOMING INTERSTATE COMPANY, L.L.C. filed with the FEDERAL ENERGY REGULATORY COMMISSION Communication Covering This
More information2018 Customer Forum. May 9, 2018
2018 Customer Forum May 9, 2018 5/9/2018 Agenda Introductions Antitrust Disclaimer High OFO Review Low OFO Review System Reliability Support Activity Results Post Forum Report / Next Steps 2 Antitrust
More informationOctober 2010 Open Season Defining the Future of Natural Gas Storage
3 Riverway Suite 1110 Houston, Texas 77056 October 2010 Open Season Defining the Future of Natural Gas Storage RYCKMAN CREEK RESOURCES, LLC OPEN SEASON NOTICE Response Due By November 1, 2010, at 5:00
More informationWyoming Pipeline Authority Public Meeting. Anne Swedberg, Manager, North American Power and Gas Content
Wyoming Pipeline Authority Public Meeting Anne Swedberg, Manager, North American Power and Gas Content 2015 2014 Platts, McGraw Hill Financial. All rights reserved. Benposium 2015. Key Take-Aways US production
More informationPlatts Natural Gas Storage Conference. January 2012
Platts Natural Gas Storage Conference January 2012 Changing Storage Landscape Tremendous development and expansion in last 10 years has created excess capacity in the Natural Gas Storage Sector Majority
More informationRockies Alliance Pipeline. Presentation to the Wyoming Pipeline Authority. May 20, 2008
Rockies Alliance Pipeline Presentation to the Wyoming Pipeline Authority May 20, 2008 Slide 2 Rockies Alliance Pipeline Route RAP New Facilities New Hampto n Proposed Pipeline Facilities Wamsutter to Ventura:
More information) ) ) ) ) ) ) ) UPDATED DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY
Application No: A.1-1-01xxx Exhibit No.: Witness: David M. Bisi Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) For Authority To Recover North-South
More informationCustomer Seminar September 28, SCE&G 2016 Large Customer Seminar 1
Customer Seminar September 28, 2016 SCE&G 2016 Large Customer Seminar 1 Refreshments & Lunch Bathrooms Auditorium Entrance Designated Smoking Area SCE&G 2016 Large Customer Seminar 2 Meeting Agenda 8:00
More informationPOTENTIAL MARKET CHANGES IN THE WESTERN INTERCONNECTION
POTENTIAL MARKET CHANGES IN THE WESTERN INTERCONNECTION A View from Peak s Pike Caitlin Liotiris November 7, 2017 State of Play in the Western Interconnection Group of utilities located mostly in Colorado
More informationNational Association of Publicly Traded Partnerships MLP Conference Presentation New York, New York May 21, 2008
National Association of Publicly Traded Partnerships MLP Conference Presentation New York, New York May 21, 2008 Safe Harbor Statement Some of the statements in this document concerning future company
More informationExpanding Existing Pipeline Capacity to Meet New England s Energy Needs. Mike Dirrane Director, Marketing
Expanding Existing Pipeline Capacity to Meet New England s Energy Needs Mike Dirrane Director, Marketing January 27, 2015 Spectra Energy s Portfolio of Assets Based in Houston, TX with operations in 30
More informationNorth Region Transmission Function Employees Job Titles and Descriptions
ACCOUNT DIRECTOR ACCOUNT MANAGER SR II, ANALYST- COMMERCIAL, ACCOUNT SERVICES II ANALYST- COMMERCIAL, ACCOUNT SERVICES SR I ANALYST- COMMERCIAL ACCOUNT SERVICES SR II ANALYST-ACCOUNT SVC I ANALYST-ACCOUNT
More information) ) ) ) ) ) ) ) DIRECT TESTIMONY OF DAVID M. BISI SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY
Application No: A.1-1-xxx Exhibit No.: Witness: David M. Bisi Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) For Authority To Recover North-South Project
More informationOutline of Presentation
Outline of Presentation Management Team Why Ryckman Creek? Reservoir Facilities Location Market Aspects Financial 1 Senior Management Team John Hopper Jeffrey Foutch Luke Saban Mike Seward Chuck Sawyer
More informationWisconsin Public Utility Institute Gas: What s in the Pipeline September 13, 2012
Wisconsin Public Utility Institute Gas: What s in the Pipeline September 13, 2012 Kirk Lavengood Vice President Business Development Northern Natural Gas Company 1 Northern Natural Gas System Northern
More informationSpectra Energy - Infrastructure Expansion Solutions
Maine International Trade Center Canada Day Program Spectra Energy - Infrastructure Expansion Solutions Greg Crisp General Manager, Business Development March 26, 2015 Safe Harbor Statement Some of the
More informationFERC Job Title Account Representative III, Capacity Services
FERC Job Title Account Representative III, Capacity Services Description (Updated 9/5/2018) Members of this team are primarily responsible for assisting customers in transacting their daily business on
More informationGas Storage: Trends and Future Projections Compression Equipment Selection. Marybeth Nored Klaus Brun, Ph.D. Southwest Research Institute
Gas Storage: Trends and Future Projections Compression Equipment Selection Marybeth Nored Klaus Brun, Ph.D. Southwest Research Institute Gas Storage Ten Year Trend: Seasonal Variation on +/- 1400 BCF natural
More informationImpacts Associated with EPA Regulations and Gas- Electric Infrastructure Analysis
Impacts Associated with EPA Regulations and Gas- Electric Infrastructure Analysis Platts Transmission Planning & Development Conference, Washington, DC September 11, 2012 John Lawhorn MISO Overview Regional
More informationGas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead
Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead Harvard Electricity Policy Group 68 th Plenary Session Paul M. Sotkiewicz, Ph.D. Chief Economist PJM Interconnection October
More informationWyoming Pipelines - The Territory Ahead October 31, 2008 October 15, 2013
Wyoming Pipelines - The Territory Ahead October 31, 2008 October 15, 2013 1 $ per MMBtu Representative Wyoming Natural Gas Price by Month 10.00 9.00 8.00 7.00 6.00 5.00 4.00 3.00 2.00 1.00 0.00 Jan Feb
More informationFERC approves Transco natural gas pipeline expansion
FERC approves Transco natural gas pipeline expansion HOUSTON, Nov. 22 11/22/2013 By OGJ editors Williams Partners LP has received approval from the US Federal Energy Regulatory Commission for the $300
More informationFERC Job Title Description (Updated 2/2/2018) Account Representative II, Capacity Services
FERC Job Title Description (Updated 2/2/2018) Account Representative II, Capacity Services Account Representative II, Offshore Transportation Account Representative II, System Balances Members of this
More informationAccount Representative II, Capacity Services
FERC Job Title Account Representative II, Capacity Services Description Members of this team are primarily responsible for assisting customers in transacting their daily business on the pipeline with a
More information201 CALIFORNIA GAS REPORT. Prepared by the California Gas and Electric Utilities
201 CALIFORNIA GAS REPORT Prepared by the California Gas and Electric Utilities 2016 C A L I F O R N I A G A S R E P O R T PREPARED BY THE CALIFORNIA GAS AND ELECTRIC UTILITIES Southern California Gas
More informationRockies Alliance Pipeline. Presentation to the Wyoming Pipeline Authority. May 20, 2008
Rockies Alliance Pipeline Presentation to the Wyoming Pipeline Authority May 20, 2008 Slide 2 Rockies Alliance Pipeline Route RAP New Facilities New Hamp ton Proposed Pipeline Facilities Wamsutter to Ventura:
More information) ) ) ) ) ) PREPARED DIRECT TESTIMONY OF STEVE WATSON SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY
Application No: A.14-06- Exhibit No.: Witness: Steve Watson Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) for Low Operational Flow Order and Emergency
More informationSpecial Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System
Special Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System John Moura, Director, Reliability Assessment and System Analysis Natural Gas Supply Association Annual
More informationBackbone Transportation Service
Backbone Transportation Service California Producer Set-Aside Rights 2005 San Diego Gas and Electric and Southern California Gas Company. All copyright and trademark rights reserved Overview Firm Access
More information2000 California Gas Report P R E PA R E D B Y THE C A L I F O R N I A G A S U T I L I TIES
2000 California Gas Report P R E PA R E D B Y THE C A L I F O R N I A G A S U T I L I TIES 2000 CALIFORNIA GAS REPORT Table of Contents Page No. FOREWORD...3 EXECUTIVE SUMMARY...7 Demand Outlook...7 Gas
More informationSpectra Energy: Moving Ahead, Gaining Momentum
8 th ANNUAL PLATTS PIPELINE EXPANSION & DEVELOPMENT CONFERENCE HOUSTON, TX SEPTEMBER 17, 2013 Spectra Energy: Greg Crisp Director, Business Development Safe Harbor Statement Some of the statements in this
More informationIssued March 21, Permian Global Access Pipeline LLC. Notice of Non-Binding Open Season
Issued March 21, 2018 Permian Global Access Pipeline LLC Notice of Non-Binding Open Season Notice of Non-Binding Open Season Permian Global Access Pipeline LLC ( PGAP ), a wholly-owned subsidiary of Tellurian
More informationWestern Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group
Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group Demand Analysis of 215 Scenarios To Explore the Range of Need for a Canada/Pacific Northwest
More informationTESORO CREATES FULL-SERVICE LOGISTICS COMPANY TLLP ACQUIRES QEP FIELD SERVICES ASSETS
TESORO CREATES FULL-SERVICE LOGISTICS COMPANY TLLP ACQUIRES QEP FIELD SERVICES ASSETS October 20, 2014 FORWARD LOOKING STATEMENTS This Presentation includes forward-looking statements. These statements
More informationAliso Canyon Gas Electric Coordination Discussion
Aliso Canyon Gas Electric Coordination Discussion Market Surveillance Committee Meeting April 19, 2016 Cathleen Colbert Senior Market Design and Policy Developer Market & Infrastructure Policy Aliso Canyon
More informationPower & Natural Gas Planning Taskforce Informational Brief
Power & Natural Gas Planning Taskforce Informational Brief Gas Scheduling in the Northwest As the Northwest electric system becomes increasingly dependent on natural gas, it is important to understand
More informationFIRM TRANSPORTATION SERVICE AGREEMENT Rate Schedule KRF-1 CONTRACT NO. 1662
FIRM TRANSPORTATION SERVICE AGREEMENT Rate Schedule KRF-1 CONTRACT NO. 1662 THIS FIRM TRANSPORTATION SERVICE AGREEMENT ( Agreement ) is made and entered into as of this 29th day of November, 2017, by and
More informationGas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI
Gas-Electric Infrastructure Challenges WPUI Gas Program September 17, 2012 MISO EPA/Gas related efforts - Timeline EPA Rules & Regulations MISO EPA Impact Study, Oct 2011 Gas Consultant Phase 1 Study,
More informationCustomer WebEx October 10, 2018
Customer WebEx October 10, 2018 1 Type 3 OFO Provisions Purpose January 2018 Type 3 OFO Changes 2 3 Type 3 Operational Flow Orders (OFOs) are implemented when demand in an area of the system is forecasted
More informationNorth American Midstream Infrastructure Through 2035 A Secure Energy Future. Press Briefing June 28, 2011
North American Midstream Infrastructure Through 2035 A Secure Energy Future Press Briefing June 28, 2011 Disclaimer This presentation presents views of ICF International and the INGAA Foundation. The presentation
More informationMastio & Company s. Midstream Services Customer Value & Loyalty Benchmarking Study. Metrics to Manage the Midstream Customer Experience
Mastio & Company s Midstream Services Customer Value & Loyalty Benchmarking Study 6 th Edition 2018 Metrics to Manage the Midstream Customer Experience Tel: (001) 816-364-6200 Fax: (001) 816-364-3606 www.mastio.com
More informationReview of Pipeline Regions
Review of Pipeline Regions 76 Eastern Pipelines 77 Eastern Pipeline Group Overview Strategic Initiatives Project Development New Business Platforms Summary 78 Eastern Pipelines Great Lakes Gas Transmission
More informationTrailblazer Pipeline Company LLC Docket No. RP Exhibit No. TPC-0080
Trailblazer Pipeline Company LLC Docket No. RP- -000 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Trailblazer Pipeline Company LLC ) ) ) Docket No. RP- -000 SUMMARY OF PREPARED
More informationFrequently Asked Questions. DART Implementation
October 7, 2016 Frequently Asked Questions DART Implementation The Kinder Morgan West Region Pipelines, which include El Paso Natural Gas Company, LLC, (EPNG) and Mojave Pipeline Company, LLC, (Mojave)
More informationCalifornia Grid Operations: Current Conditions and Future Needs
California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify
More informationTable of Contents. Great Lakes Gas Transmission Limited Partnership. Third Revised Volume No. 1. Third Revised Volume No. 1 1 TABLE OF CONTENTS
Great Lakes Gas Transmission Limited Partnership Table of Contents 1 TABLE OF CONTENTS 2 PRELIMINARY STATEMENT 3 MAPS 4 STATEMENT OF RATES 4.1 Rate Schedules FT, LFT & EFT 4.2 Reserved for Future Use 4.3
More informationTen Years After Gas & Power in Perspective
Regional Market Trends Forum Ten Years After Gas & Power in Perspective Richard Levitan, rll@levitan.com May 1, 2014 Agenda 2014 Polar Vortex v. 2004 Cold Snap Northeast Gas & Power 10 Years After Gas
More informationTOTAL GENERATION WHOLESALE SALES
GWh GWh Preliminary Estimated Results thru June 30, 2017 GENERATION DETAIL 350 TOTAL GENERATION 300 250 200 150 100 50 - JUL 16 AUG 16 SEPT 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17 MAY 17 JUN
More informationSolar Power and the Future. Bryan Whitcomb General Manager, Solar Star Project October 18, 2016
Solar Power and the Future Bryan Whitcomb General Manager, Solar Star Project October 18, 2016 Topics Covered Berkshire Hathaway Energy (BHE) introduction Solar Technologies Photovoltaic (PV) and Concentrated
More informationMoving Forward: Agricultural Water Conservation, Productivity, and Water Transfers Workgroup
Moving Forward: Agricultural Water Conservation, Productivity, and Water Transfers Workgroup Water For Agriculture Colorado Mesa University Grand Junction, CO February 25, 2015 Outline Colorado River Basin
More informationLoads and Resources Methods and Assumptions
Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1
More informationSecond Revised Volume No. 1 Section Version: 5.0.0
Table of Contents Second Revised Volume No. 1 Section Version: 5.0.0 Description Section Preliminary Statement... Preliminary Statement System Maps System Map... System Map CHDP Zone Map... CHDP Zone Map
More informationTennessee Gas Pipeline Co, L.L.C. Northeast Energy and Commerce Association September 27, 2012
Tennessee Gas Pipeline Co, L.L.C. Northeast Energy and Commerce Association September 27, 2012 The Kinder Morgan System 4 th largest energy company in North America Enterprise value ~ $95 billion Largest
More informationDominion Energy Questar Pipeline, LLC 2018 Customer Meeting. February 27, 2018
Dominion Energy Questar Pipeline, LLC 2018 Customer Meeting 1 Shelley Kendrick Director Marketing and Business Development Dominion Energy Questar Pipeline 2 Ron Jorgensen Vice President Western Pipeline
More informationAliso Canyon Gas Electric Coordination
Aliso Canyon Gas Electric Coordination Cathleen Colbert Senior Market Design and Policy Developer Market & Infrastructure Policy Working Group Meeting April 6, 2016 Agenda Time Topic Presenter 10:00 10:30
More information1Line Customer Reports
1Line Customer s Number Name Description under ALLOCATIONS Allocations 1226 Allocation Audit LDC/Power Generation (Transco) Scheduled and Allocated quantities, Ranks, and Limit Values at a citygate location
More informationPanel: Re-plumbing the North American Gas Transmission Grid 2.0
Panel: Re-plumbing the North American Gas Transmission Grid 2.0 Presented to Platts Gas Storage Outlook Scott R. Smith President & CEO January 11, 2016 Outline of discussion Midstream Energy Holdings and
More informationAppendix A. Project Description
Appendix A Project Description I. Project Summary 1. The proposed Jordan Cove LNG export terminal ( Jordan Cove ) is a facility designed to produce and export liquefied natural gas ( LNG ). Jordan Cove
More informationNew England Electricity Outlook
O C T O B E R 2 1, 2 0 1 6 S O U T H P O R T L A N D, M E New England Electricity Outlook Environmental and Energy Technology Council of Maine (E2Tech) Eric Johnson D I R E C T O R, E X T E R N A L A F
More informationUNITED STATES OF AMERICA 100 FERC 61,204 FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE WITH ORDER NOS. 637, 587-G, AND 587-L
UNITED STATES OF AMERICA 100 FERC 61,204 FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, Linda Breathitt, and Nora Mead Brownell. Overthrust Pipeline
More informationDominion Energy Transmission, Inc. FERC Gas Tariff Tariff Record No. 20. Fifth Revised Volume No. 1 Version TARIFF RATE SCHEDULES
Rate Schedules FERC Gas Tariff Tariff Record No. 20. TARIFF RATE SCHEDULES TARIFF RATE RECORD SCHEDULE SERVICE NO. FT Firm Transportation Service 20.1 FTNN Firm Transportation, No-Notice Service 20.2 IT
More informationMidwest Supply Update: Alliance Pipeline and Rockies Alliance Pipeline
Midwest Supply Update: Alliance Pipeline and Rockies Alliance Pipeline Tony Straquadine Government Affairs Manager Forward looking statements and information o Certain information contained in this [presentation],
More informationTranscontinental Gas Pipe Line Company, LLC RP Technical Conference March 28, 2018
WE MAKE ENERGY HAPPEN Transcontinental Gas Pipe Line Company, LLC RP18-314-000 Technical Conference March 28, 2018 NYSE: WMB williams.com AGENDA > Introductions > Background Information > No-Notice Priorities
More informationConversion to the DART System: Update on Implementation Schedule
Conversion to the DART System: Update on Implementation Schedule March 11, 2015 WebEx at 1:00 p.m. CCT 1 Agenda Updated Timeline to Convert to DART Additional Tariff Changes Other Updates and Next Steps
More informationIV. ENVIRONMENTAL IMPACT ANALYSIS F. ENERGY CONSERVATION 1. ELECTRICITY
IV. ENVIRONMENTAL IMPACT ANALYSIS F. ENERGY CONSERVATION 1. ELECTRICITY ENVIRONMENTAL SETTING Energy consumption, including electricity, by new buildings in California is regulated by the State Building
More informationUtah Pipeline Association Operator List
Home Utah Pipeline Association Operator List Member Company Profiles Company Emergency Number Products Transported Anadarko 1-800-738-9816 Natural Gas Chevron Pipeline 1-800-762-3404 Crude Oil, Diesel
More informationNatural Gas Next 2017: Natural Gas Storage
Natural Gas Next 2017: Natural Gas Storage Callie Kolbe Manager, Energy Analysis September 26, 2017 Natural Gas Storage Introduction to Storage Why it is the market s balancer Where it exists and who owns
More informationNORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013
NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:
More informationCBIA Energy Conference Natural Gas- Coming to Your Neighborhood Soon October 10, 2013 Cromwell, Connecticut Michael Dirrane Director, Northeast
CBIA Energy Conference Natural Gas- Coming to Your Neighborhood Soon October 10, 2013 Cromwell, Connecticut Michael Dirrane Director, Northeast Marketing Spectra Energy U.S. Transmission Map Miles of Pipe
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF A COMMISSION ) INVESTIGATION INTO THE FEASIBILITY ) OF PUBLIC SERVICE COMPANY OF NEW ) MEXICO BECOMING A MEMBER OF THE ) Case No. 17-00261-UT
More informationIssued February 21, Haynesville Global Access Pipeline LLC. Notice of Non-Binding Open Season
Issued February 21, 2018 Haynesville Global Access Pipeline LLC Notice of Non-Binding Open Season Notice of Non-Binding Open Season Haynesville Global Access Pipeline LLC ( HGAP ), a wholly-owned subsidiary
More informationMerchant Energy Partners & The East Cheyenne Gas Storage Project
Merchant Energy Partners & The East Cheyenne Gas Storage Project Wyoming Pipeline Authority December 10, 2009 10901 West Toller Drive, Suite 200, Littleton, CO 80127 Merchant Energy Partners & The East
More informationPREPARED DIRECT TESTIMONY OF PAUL BORKOVICH ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY SAN DIEGO GAS & ELECTRIC COMPANY
Application No: A.1-- Exhibit No.: Witness: Paul Borkovich Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) Regarding Feasibility of Incorporating Advanced
More informationIdentifying the Problem
June 27, 2014 New England States Committee on Electricity 4 Bellows Road Westborough, MA 01581 Attn: Heather Hunt Via email: HeatherHunt@NESCOE.com Re: Enhancing Electric Reliability in New England Spectra
More informationLADWP WATER INFRASTRUCTURE PLAN
LADWP 2017-18 WATER INFRASTRUCTURE PLAN Introduction All major components of the Water System infrastructure are evaluated as part of the ongoing Asset Management (AM) Program. The goal of AM is to systematically
More information1998 California Gas Report PREPARED BY THE CALIFORNIA GAS AND ELECTRIC UTILITIES
1998 California Gas Report PREPARED BY THE CALIFORNIA GAS AND ELECTRIC UTILITIES i ii 1998 CALIFORNIA GAS REPORT Table of Contents Page No. FOREWORD... 1 EXECUTIVE SUMMARY... 5 Demand Outlook... 7 Gas
More informationItron Analytics. Maximize the Full Value of Your Smart Grid. Image
Itron Analytics Maximize the Full Value of Your Smart Grid Image Complete Data Intelligence Lifecycle The ultimate goal of the smart grid is to ensure safe and reliable delivery of energy. Building your
More informationWest Region Customer Meeting. September 23, 2015
West Region Customer Meeting September 23, 2015 Gas-Electric Coordination Update September 23, 2015 John Driscoll Manager West Region Transportation/Storage Services CIG CPG KGS Ruby WIC TCGT Young 9/23/2015
More informationRegional Round Up Washington D.C. Southwest Region and Questar Gas Dan Dent March 18, 2010
Regional Round Up Washington D.C. Southwest Region and Questar Gas Dan Dent March 18, 2010 24 Presentation Southwest Topics Region Highlights Utah Policy and Goals Questar Gas Targets and Goals Policy
More informationFERC GAS TARIFF. First Revised Volume No. 1 MILLENNIUM PIPELINE COMPANY, L.L.C. FILED WITH THE FEDERAL ENERGY REGULATORY COMMISSION
FERC GAS TARIFF First Revised Volume No. 1 Of MILLENNIUM PIPELINE COMPANY, L.L.C. FILED WITH THE FEDERAL ENERGY REGULATORY COMMISSION Communications concerning this Tariff should be addressed to: John