West Region Customer Meeting. September 23, 2015

Size: px
Start display at page:

Download "West Region Customer Meeting. September 23, 2015"

Transcription

1 West Region Customer Meeting September 23, 2015

2 Gas-Electric Coordination Update September 23, 2015 John Driscoll Manager West Region Transportation/Storage Services CIG CPG KGS Ruby WIC TCGT Young 9/23/2015 2

3 Agenda Topics FERC 809 NAESB 3.0 Portal Page Updates 9/23/2015 3

4 FERC Update FERC s Goal: Change regulations for the scheduling of transportation services on interstate natural gas pipelines to better coordinate the scheduling practices of the gas and electric industries and to provide scheduling flexibility to all shippers Order 809 highlights: Effective April 1, 2016 Start of Gas Day to remain at 9:00 a.m. CCT Timely nomination deadline moved to 1:00 pm CCT Intra-day nomination cycles from 2 cycles to 3 cycles Capacity release open bidding for next day business happens prior to Timely nomination deadline Capacity released will be recallable for the ID3 cycle KM Pipelines Action Plan: Currently working on coding changes in DART Primary testing to occur October December Further testing will be done up to implementation date Full staffing end of March and beginning of April to assist customers Re-structure of daytime and evening work schedules to accommodate new cycle timelines 9/23/2015 4

5 New Cycle Timelines (Central Standard Time) Timely All times CCT Current Effective 4/1/2016 All times CCT Current Effective 4/1/2016 Timely day-ahead Nom Deadline 11:30 AM 1:00 PM ID2 Nom Deadline 5:00 PM 2:30 PM Confirmations 3:30 PM 4:30 PM Confirmations 8:00 PM 5:00 PM Schedule Issued 4:30 PM 5:00 PM Schedule Issued 9:00 PM 5:30 PM Start of Gas Flow 9:00 AM 9:00 AM Start of Gas Flow 9:00 PM 6:00 PM ID2 Hours of Flow Left 24 hours 24 hours Hours of Flow Left 12 hours 15 hours IT Bump Rights n/a n/a IT Bump Rights no bump bumpable EPSQ n/a n/a EPSQ 1/2 9/24 Process Time (Nom to Sch) 5 hours 4 hours Process Time (Nom to Sch) 4 hours 3 hours Evening Evening Day-ahead Nom Deadline 6:00 PM 6:00 PM ID3 Nom Deadline n/a 7:00 PM Confirmations 9:00 PM 8:30 PM Confirmations n/a 9:30 PM Schedule Issued 10:00 PM 9:00 PM Schedule Issued n/a 10:00 PM Start of Gas Flow 9:00 AM 9:00 AM Start of Gas Flow n/a 10:00 PM ID3 Hours of Flow Left 24 hours 24 hours Hours of Flow Left n/a 11 hours IT Bump Rights bumpable bumpable IT Bump Rights n/a no bump EPSQ n/a n/a EPSQ n/a 13/24 Process Time (Nom to Sch) 4 hours 3 hours Process Time (Nom to Sch) n/a 3 hours ID1 ID1 Nom Deadline 10:00 AM 10:00 AM Confirmations 1:00 PM 12:30 PM Schedule Issued 2:00 PM 1:00 PM Start of Gas Flow 5:00 PM 2:00 PM Hours of Flow Left 16 hours 19 hours IT Bump Rights bumpable bumpable EPSQ 1/3 5/24 Process Time (Nom to Sch) 4 hours 3 hours 9/23/2015 5

6 New Cycle Timelines (Mountain Standard Time) All times MST Current Effective 4/1/2016 All times MST Current Effective 4/1/2016 Timely Timely day-ahead Nom Deadline 10:30 AM 12:00 PM ID2 Nom Deadline 4:00 PM 1:30 PM Confirmations 2:30 PM 3:30 PM Confirmations 7:00 PM 4:00 PM Schedule Issued 4:30 PM 4:00 PM Schedule Issued 8:00 PM 4:30 PM Start of Gas Flow 8:00 AM 8:00 AM Start of Gas Flow 8:00 PM 5:00 PM ID2 Hours of Flow Left 24 hours 24 hours Hours of Flow Left 12 hours 15 hours IT Bump Rights n/a n/a IT Bump Rights no bump bumpable EPSQ n/a n/a EPSQ 1/2 9/24 Process Time (Nom to Sch) 5 hours 4 hours Process Time (Nom to Sch) 4 hours 3 hours Evening Evening Day-ahead Nom Deadline 5:00 PM 5:00 PM ID3 Nom Deadline n/a 6:00 PM Confirmations 8:00 PM 7:30 PM Confirmations n/a 8:30 PM Schedule Issued 9:00 PM 8:00 PM Schedule Issued n/a 9:00 PM Start of Gas Flow 8:00 AM 8:00 AM Start of Gas Flow n/a 9:00 PM ID3 Hours of Flow Left 24 hours 24 hours Hours of Flow Left n/a 11 hours IT Bump Rights Bumpable bumpable IT Bump Rights n/a no bump EPSQ n/a n/a EPSQ n/a 13/24 Process Time (Nom to Sch) 4 hours 3 hours Process Time (Nom to Sch) n/a 3 hours ID1 ID1 Nom Deadline 9:00 AM 9:00 AM Confirmations 12:00 PM 11:30 AM Schedule Issued 1:00 PM 12:00 PM Start of Gas Flow 4:00 PM 1:00 PM Hours of Flow Left 16 hours 19 hours IT Bump Rights bumpable bumpable EPSQ 1/3 5/24 Process Time (Nom to Sch) 4 hours 3 hours 9/23/2015 6

7 Action Cycle Timelines Order 809 Timely, Cycle 1 Evening, Cycle 2 Intraday 1, Cycle 3 Intraday 2, Cycle 4 Intraday 3, Cycle 5 Nomination Deadline** 12:00 pm 5:00 pm 9:00 am 1: 30 pm 6:00 pm Scheduling Complete* Confirmation Deadline Final Scheduled Results Between 12:30 pm and 1:00 pm Between 5:30 pm and 6:00 pm Between 9:30 am and 10:00 am Between 2:00 pm and 2:30 pm Between 6:30 pm and 7:00 pm 3:30 pm 7:30 pm 11:30 am 4:00 pm 8:30 pm 4:00 pm 8:00 pm Noon pm 4:30 pm 9:00 pm All Times are Mountain Standard Time * = Targeted times for completion ** = NAESB Deadline (seamless transactions); all others add 15 minutes 9/23/2015 7

8 Flow 2:00 pm, current calendar day Scheduling Reports Out: Noon Confirmations Close: 11:30 am Nominations Close: 9:00 am Process Intraday 1 Cycle Flow 5:00 pm, current calendar day Scheduling Reports Out: 4:30 pm Confirmations Close: 4:00 PM Nominations Close: 1:30 pm Process Intraday 2 Cycle Processing -- Today's Gas Day Flow 10:00 pm, current calendar day Scheduling Results Out: 9:00 pm Confirmations Close: 8:30 pm Nominations Close: 6:00 pm Prcoess Intraday 3 Cycle Calendar Day 1 Calendar Day Process Timely Cycle Nominations Close: Noon Confirmations Close: 3:30 pm Scheduling Reports Out: 4:00 pm Flow 8:00 am next calendar day Process Evening Cycle Nominations Close: 5:00 pm Confirmation Close: 7:30 pm Scheduling Reports Out: 8:00 Flow 8:00 am next calendar day Processing -- Tomorrow's Gas Day 9/23/2015 8

9 FERC NOPR - NAESB 3.0 NAESB 3.0 NOPR - Notice of Proposed Rulemaking on the Standards for Business Practices of Interstate Natural Gas Pipelines (Docket No. RM ) issued on July 16, Proposed effective date is April 1, 2016 Compliance filings February 1, 2016 Discontinued use of location common codes system commonly referred to as DRN. Pipelines can now use their proprietary codes to replace DRN. DART refers to these as a PIN (Point Identification Number) and Passport uses location code. Each pipeline will be required to maintain a new downloadable list of all their locations and associated proprietary codes. In addition pipelines will be required to track their pipeline interconnections and their corresponding proprietary code. EDI nomination and confirmation processes that has used the DRN code for communications will continue to be supported for interim period. Further communications will occur in the next month to lay out options for EDI customers. 9/23/2015 9

10 FERC NOPR - NAESB 3.0 continued Notices/Offers to purchase release capacity Post via Notices, Instructions and request template Display notice postings of offers to purchase capacity GRID OPERATIONAL AVAILABLE CAPACITY Addition of All Quantity indicator For any column that does not have a quantity then must include a comment/notes as to reason quantity is not included 9/23/

11 Questions? 9/23/

12 El Paso Natural Gas Pipeline Winter Preparedness September 23, 2015 Kevin Johnson Director-West Region Pipeline Management EPNG / Mojave / Sierrita 9/23/

13 EPNG System Overview: Supply Locations and Flow Direction Rockies Gas Rockies Gas A R I Z O N A San Juan Basin Supply Rockies Gas N E W M E X I C O Albuquerque T E X A S C A L I F O R N I A Phoenix Tucson Washington Ranch Storage Permian Basin Supply Production Areas El Paso Gas Supplies Transport Flow Directions Waha Compressor Stations Pipelines 9/23/

14 9/23/

15 9/23/

16 9/23/

17 Staffing Winter Preparedness Plans Gas Control is 24 x 7 x 365 Field technicians are on-site or on-call Facility preparation Facility inspections with focus on weatherproofing Assessment of back-up power needs (existing stand-by generation and rental generators as deemed necessary) Prepare vehicles for cold weather Communication Customer Winter Preparedness Meeting (WebEx) October 15, 2015 Customer-specific winter preparedness meetings or communications Kinder Morgan Footprint Potential for coordinated emergency operational assistance between TransColorado Gas Transmission (TC), Colorado Interstate Gas (CIG), Natural Gas Pipeline (NGPL) and EPNG (three of which are in the same Gas Control group) provides additional layer of contingency management 9/23/

18 Rockies Pipeline Systems Overview and Winter Preparedness Jim Cordaro Director West Region Pipeline Management CIG CPG KGS Ruby WIC TCGT Young 9/23/

19 Agenda Rockies Pipeline Systems Overview Seasonal Variations in Demand Seasonal Storage Operations Autumn Preparation Winter Storm Preparedness 9/23/

20 Rockies Pipeline Systems Overview 9/23/

21 W Y O M I N G Approximate Design Capacities Ruby 1,460 U T A H Seg 190 Trans Colorado (TCGT) KGS Seg Seg CIG Dry C O L O R A D O N E W 105 WIC 552 Wet / Denver 200 Colorado Springs Pueblo 133 M E X I C O 1,520 CIG, CP, KGS, Ruby, TCGT, WIC Approximate Design Capacities (MMscf/d) as of Cheyenne CIG Valley Line (Focus of next slide) Amarillo CIG High Plains N E B R A S K A K A N S A S T E X A S 9/23/

22 Valley Line: Air Blended Sources of Supply Raw gas (inlet) supplies 09A Watkins: Wyoming, DJ Spruce Hill Drennan Watkins 247A 212A 248A 07A Picketwire Spruce Hill: Wyoming, DJ (maybe Raton) Drennan: Wyoming, DJ (maybe Raton) Picketwire: Raton Campo: Raton Air supply Watkins: 50,000/10,000 Mcf/d* Spruce Hill: 2,400 Mcf/d Drennan: 4,000 Mcf/d Picketwire: 1,500 Mcf/d Campo: 7,000 Mcf/d *Only about 10,000 required for 09A from Watkins Campo Air blending facilities 9/23/

23 Seasonal Variations in Demand 9/23/

24 MMcf/d CIG 3500 CIG Total System Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec /23/

25 CIG Front Range Seasonal Demand 9/23/

26 MMcf/d Cheyenne Plains Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 9/23/

27 MMcf/d 1400 Ruby PG&E Redwood Path Pressure Reduction Limited PG&E Capacity to 1.8 Bscfd through Jun, Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec /23/

28 MMcfd TransColorado Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec /23/

29 MMcf/d MMcf/d MMcf/d MMcf/d WIC Mainline and Key Laterals Mainline Medicine Bow Lateral Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Kanda Lateral Piceance Lateral Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 9/23/

30 CIG Seasonal Storage Operations 9/23/

31 CIG Storage Fields CIG Young Storage Cheyenne 510 Totem Storage Ft Morgan Storage (NNT) Denver Latigo Storage (NNT) Colorado Springs Pueblo Boehm Storage (NNT) Flank Storage (NNT) 9/23/ Amarillo

32 Total CIG NNT Storage Fields 9/23/

33 Autumn Preparation and Winter Storm Preparedness Ensure reliability of service to our customers by preparing Company facilities to withstand the forces of winter 9/23/

34 Autumn Facilities Preparation Air Blending Facilities Ready for winter service no later than October 31 Critical valves inspected and serviced Btu measurement tested for proper operation (including spares) Dehys: Dry filter replacement, Heater operation verification, Boilers lit Electric heat trace on and operational Air compression inter-stage fin fan louvers inspected Telecom Microwave Sites Chargers, batteries, building HVAC equipment inspected Backup generators tested, fluid levels inspected Anti-freeze effective to -30 Fahrenheit Propane tanks and regulation systems functional and adequately supplied 9/23/

35 Autumn Facilities Preparation Compression and Metering Facilities Heaters inspected and activated Boiler systems inspected for leaks and proper circulation Piping/equipment heat trace tested and insulation inspected Engine/compressor Hot Start equipment on and working Critical spare parts inventory or availability Emergency generators started and power transfer tested Storage tanks prepared for product handling Air dryer systems checked and serviced Valves/regulators/reliefs inspected and serviced Snow removal equipment inspected and tested Inspect and test batteries, UPS systems (AC and DC) Solar panels and gas flow computers (GFC) at block valves inspected Gas analyzer supplies checked/replenished 9/23/

36 Gas Control Storm Preparation Pack the system Coordination calls with Field Operations Discuss areas of focus Establish communication avenues for employees to convey intentions before, during, and after storms Establish manning of key facilities including those that may not be accessible after a storm 9/23/

37 Questions? 9/23/

38 Contracts and Capacity Release Sherry Saunders Manager-West Region Contract Administration 9/23/

39 FERC 809 NAESB 3.0 Capacity Release Tips Agenda 9/23/

40 FERC 809 Capacity Release Changes Effective April 1, 2016 Open season begins at 9 AM CT, 8 AM MT Open season closes at 10 AM CT, 9 AM MT Match due by 11:30 AM CT, 10:30 AM MT Additional ID3 recall option available on post offer 9/23/

41 Capacity Release Timeline 9/23/

42 Recall Timeline 9/23/

43 NAESB 3.0 For EPNG: Path becomes Route For EPNG and Mojave: DRN becomes Loc For DART: PIN will remain PIN Bidder Designation of Bid Basis goes away Offer must be either volumetric or reservation 9/23/

44 Capacity Release Tips Biddable offers must be confirmed before the bid period begins DART will send an auto-generated notification that there is a bid that needs confirmation The is sent to the Bidder listed in the offer A default bidder address can be set up in the Preferences folder under Business Preferences Group distribution is recommended 9/23/

45 Questions? 9/23/

Broad market presence: Growing demand regions, key supply basins, LNG terminals. Excellent connections to markets and supply

Broad market presence: Growing demand regions, key supply basins, LNG terminals. Excellent connections to markets and supply Pipeline Group Strong and Growing Broad market presence: Growing demand regions, key supply basins, LNG terminals Excellent connections to markets and supply Almost $4 billion of committed growth projects

More information

University of Wyoming The 2008 Conference The Wyoming Pipelines: The Territory Ahead

University of Wyoming The 2008 Conference The Wyoming Pipelines: The Territory Ahead FERC CERTIFICATION University of Wyoming The 2008 Conference The Wyoming Pipelines: The Territory Ahead 1 Robert Cupina, Principal Deputy Director Federal Energy Regulatory Commission Cheyenne, Wyoming

More information

Frequently Asked Questions. DART Implementation

Frequently Asked Questions. DART Implementation October 7, 2016 Frequently Asked Questions DART Implementation The Kinder Morgan West Region Pipelines, which include El Paso Natural Gas Company, LLC, (EPNG) and Mojave Pipeline Company, LLC, (Mojave)

More information

Freddie Salas Manager Passport Nominations and Scheduling

Freddie Salas Manager Passport Nominations and Scheduling www.kindermorgan.com Freddie Salas Manager Passport Nominations and Scheduling Agenda Passport2DART Implementation Timeline What you can do to prepare Available Tools Nomination Model Questions 2 Timeline

More information

Marcellus Shale Advisory Commission Infrastructure Work Group Meeting El Paso Corporation Tennessee Gas Pipeline Company April 11, 2011

Marcellus Shale Advisory Commission Infrastructure Work Group Meeting El Paso Corporation Tennessee Gas Pipeline Company April 11, 2011 Interstate Pipelines Exploration & Production Marcellus Shale Advisory Commission Infrastructure Work Group Meeting El Paso Corporation Tennessee Gas Pipeline Company April 11, 2011 El Paso Corporation

More information

SNG/EEC Expansion Projects & SNG Seamless Service. WebEx Training November 15, 2016

SNG/EEC Expansion Projects & SNG Seamless Service. WebEx Training November 15, 2016 SNG/EEC Expansion Projects & SNG Seamless Service WebEx Training November 15, 2016 1 Agenda Update on Expansion Status Elba Express Company ( EEC ) Expansion Fuel Southern Natural Gas ( SNG ) Seamless

More information

Ruby Pipeline Project

Ruby Pipeline Project Ruby Pipeline Project Ed Miller Ruby Project Manager October 21, 2008 El Paso Pipeline System Ruby Pipeline CIG & WIC Tennessee Gas Pipeline Mojave Pipeline El Paso Natural Gas Cheyenne Plains Pipeline

More information

Project Report: SunMaxx Commercial Case Studies

Project Report: SunMaxx Commercial Case Studies Project Report: 14 x ThermoPower-VHP30 Total Gross Surface Area: 738.50 sq.ft Azimuth: 10 Incl.: 37 2100 gal/day 130 F Gas Boiler - 9 150 kbtu/hr StorMaxx NP Vol:2500 gal Existing Hot Water Heater Vol:1000

More information

FERC GAS TARIFF THIRD REVISED VOLUME NO. 2. (Superseding Second Revised Volume No. 2) WYOMING INTERSTATE COMPANY, L.L.C.

FERC GAS TARIFF THIRD REVISED VOLUME NO. 2. (Superseding Second Revised Volume No. 2) WYOMING INTERSTATE COMPANY, L.L.C. FERC GAS TARIFF THIRD REVISED VOLUME NO. 2 (Superseding Second Revised Volume No. 2) of WYOMING INTERSTATE COMPANY, L.L.C. filed with the FEDERAL ENERGY REGULATORY COMMISSION Communication Covering This

More information

WEBEX Etiquette. Please do not place your phone on hold at anytime. If you have music on your hold, it disrupts the meeting.

WEBEX Etiquette. Please do not place your phone on hold at anytime. If you have music on your hold, it disrupts the meeting. WEBEX Etiquette Please mute your phone by pressing *6. Please do not place your phone on hold at anytime. If you have music on your hold, it disrupts the meeting. Questions If you have a question, please

More information

Natural Gas Pipelines Deb Macdonald

Natural Gas Pipelines Deb Macdonald Natural Gas Pipelines Deb Macdonald Infrastructure Development Need for Natural Gas Infrastructure EIA predicts demand for natural gas to grow at 2% per year from 23 Tcf currently to 34 Tcf by 2020. Foster

More information

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008 Transmission Planning at the Midwest ISO Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008 Midwest ISO: What We Do Monitor flow of power over the high voltage

More information

ROUTINE MAINTENANCE EMERGENCY SERVICES EQUIPMENT REPAIR

ROUTINE MAINTENANCE EMERGENCY SERVICES EQUIPMENT REPAIR critical facilities preventative maintenance ROUTINE MAINTENANCE EMERGENCY SERVICES EQUIPMENT REPAIR a l p h a t e c h n o l o g i e s s e r v i c e s, i n c. m e m b e r o f t h e a l p h a g r o u p

More information

PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, Prepared by Operations Planning Division

PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, Prepared by Operations Planning Division PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, 2017 Prepared by Operations Planning Division PJM 2017 Table of Contents Table of Contents Table of Exhibits...4 Approval...5

More information

a meaningful company doing meaningful work delivering meaningful results Monthly Imbalance Settlement and Volume Allocation Working Group Changes

a meaningful company doing meaningful work delivering meaningful results Monthly Imbalance Settlement and Volume Allocation Working Group Changes a meaningful company doing meaningful work delivering meaningful results Monthly Imbalance Settlement and Volume Allocation Working Group Changes 1 Creating a New Culture the place to work the neighbor

More information

Backbone Transportation Service

Backbone Transportation Service Backbone Transportation Service California Producer Set-Aside Rights 2005 San Diego Gas and Electric and Southern California Gas Company. All copyright and trademark rights reserved Overview Firm Access

More information

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Administration Division Public Works Department Anchorage: Performance. Value. Results. Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,

More information

ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA

ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA Bulletin of the Transilvania University of Braşov Series I: Engineering Sciences Vol. 5 (54) No. 2-212 ANNUAL ENERGY PERFORMANCE OF SOLAR THERMAL SYSTEMS IN BRAŞOV, ROMANIA C. ŞERBAN 1 E. EFTIMIE 1 Abstract:

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Trial and Participant Test Plan VERSION: 1.1 STATUS: Final for Publication DATE: 17 th JULY 2017 Contents Introduction...

More information

Customer Select Supply/Storage. Effective May 2009

Customer Select Supply/Storage. Effective May 2009 Customer Select Supply/Storage Effective May 2009 Service Territory Nicor Gas Territory Area: 17,000 square miles Population: 5.7 million (est.) Communities Served: 640 Customers: 2.2 million Rockford

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

New Jersey Natural Gas Market Update

New Jersey Natural Gas Market Update March 25, 2015 Mullica Hill, NJ New Jersey Natural Gas Market Update Presentation to: SNJDC Natural Gas Seminar Tom Kiley Northeast Gas Association Issues Regional Market Developments New Jersey Gas Market

More information

Capacity Release Frequently Asked Questions

Capacity Release Frequently Asked Questions What is? Capacity release is a tool available for Northern s customers to maximize the use of their contracted firm transportation and storage capacity. Capacity release allows a customer that holds firm

More information

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh) For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold

More information

Analysis of Solar Capacity Equivalent Values for the South Carolina Electric and Gas System

Analysis of Solar Capacity Equivalent Values for the South Carolina Electric and Gas System Analysis of Solar Capacity Equivalent Values for the South Carolina Electric and Gas System John D. Wilson, Southern Alliance for Clean Energy March 21, 2017 The assessment of solar energy s contribution

More information

UNITED STATES OF AMERICA 100 FERC 61,204 FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE WITH ORDER NOS. 637, 587-G, AND 587-L

UNITED STATES OF AMERICA 100 FERC 61,204 FEDERAL ENERGY REGULATORY COMMISSION ORDER ON COMPLIANCE WITH ORDER NOS. 637, 587-G, AND 587-L UNITED STATES OF AMERICA 100 FERC 61,204 FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; William L. Massey, Linda Breathitt, and Nora Mead Brownell. Overthrust Pipeline

More information

Electric Price Outlook April 13, 2017

Electric Price Outlook April 13, 2017 Electric Price Outlook April 13, 2017 Scott Drzycimski, Director Customer, Community and Economic Development Jason Nielsen, Manager Regulatory Affairs Keeping you informed Ongoing pricing outlook webinars

More information

WELCOME & INTRODUCTIONS

WELCOME & INTRODUCTIONS WELCOME & INTRODUCTIONS Ron Jorgensen Vice-President, Operations & Gas Control 1 Agenda 8:30 a.m. Welcome and Introductions Ron Jorgensen 8:45 a.m. Meet the Pipeline President Micheal Dunn 9:10 a.m. Integrity

More information

Renewables. Vacuum Tube Solar Systems. Solar Energy to the Power of

Renewables. Vacuum Tube Solar Systems. Solar Energy to the Power of Renewables Vacuum Tube Solar Systems Solar Energy to the Power of FREE HOT WATER FROM DAWN TO DUSK AND THROUGHOUT THE YEAR WITH Thermomax advanced vacuum tube solar systems provide hot water in all seasons.

More information

APPENDIX 4. Task 4. Evaluate solar walls performance and GHG impact. Evaluate the

APPENDIX 4. Task 4. Evaluate solar walls performance and GHG impact. Evaluate the APPENDIX 4 Task 4. Evaluate solar walls performance and GHG impact. Evaluate the performance of existing solar walls in terms of energy use and GHG emissions. I. Building-specific degree day data and solar

More information

Reducing Peak Energy Demand: The Hidden Benefit of Cool Roofs

Reducing Peak Energy Demand: The Hidden Benefit of Cool Roofs Reducing Peak Energy Demand: The Hidden Benefit of Cool Roofs Dr. James L. Hoff, DBA, TEGNOS Research, Inc., Keith Gere and Robert Carnick, Duro-Last Inc. November 11, 2014 MW Peak Energy Demand 30,000

More information

Energy Report - February 2008

Energy Report - February 2008 Energy Report - February 28 Glossary Ampere - The unit of measurement of electrical current produced in a circuit by 1 volt acting through a resistance of 1 Ohm. British thermal unit (Btu) - The quantity

More information

Gas-Electric Coordination A NYISO Perspective

Gas-Electric Coordination A NYISO Perspective Gas-Electric Coordination A NYISO Perspective Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Energy in the Northeast Boston, MA September 9, 2013 Generation Capacity

More information

The Call Center Balanced Scorecard

The Call Center Balanced Scorecard The Call Center Balanced Scorecard Your Overall Measure of Call Center Performance! MetricNet Best Practices Series Some Common Call Center KPIs Cost Cost per Contact Cost per Minute of Handle Time Quality

More information

WELCOME TO IROQUOIS CAPACITY RELEASE TRAINING

WELCOME TO IROQUOIS CAPACITY RELEASE TRAINING WELCOME TO CAPACITY RELEASE TRAINING George Alcoforado Helena Clancy Business Analyst Sr. Transportation Services Rep (203) 944-7081 (203) 944-7047 George_Alcoforado@Iroquois.com Helena_Clancy@Iroquois.com

More information

TNTP 2012 Scope of Work. Providence Schools I November 28, 2011

TNTP 2012 Scope of Work. Providence Schools I November 28, 2011 TNTP 2012 Scope of Work Providence Schools I November 28, 2011 Presentation Overview Agenda 1) TNTP overview 2) Review of work to date 3) Scope of work overview Objectives Provide an overview of the organization

More information

Social Media A Valuable Tool in Risk & Crisis Communications. Agenda

Social Media A Valuable Tool in Risk & Crisis Communications. Agenda Social Media A Valuable Tool in Risk & Crisis Communications Massachusetts Emergency Management Agency (MEMA) May 21, 2014 Agenda MEMA s Use of Social Media History Platforms Preparedness, Response, Recovery

More information

Ground-Coupled Heat Pump And Energy Storage

Ground-Coupled Heat Pump And Energy Storage Ground-Coupled Heat Pump And Energy Storage By Ed Lohrenz, Member ASHRAE; and Sergio Almeida, P.Eng., Member ASHRAE Ground-coupled heat pump (GCHP) systems consume less purchased energy than an HVAC system

More information

EIA Winter Fuels Outlook

EIA Winter Fuels Outlook EIA Winter Fuels Outlook For Washington, D.C. By Adam Sieminski, Administrator, U.S. Energy Information Administration U.S. Energy Information Administration Independent Statistics & Analysis www.eia.gov

More information

John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216)

John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216) John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216) Wilmington District, Corps of Engineers Stakeholder Update Presentation January 24, 2014 Authorized under Section 216 of Public

More information

Fueling the Future with Natural Gas: Bringing It Home

Fueling the Future with Natural Gas: Bringing It Home NCSL Energy Policy Summit Minneapolis, MN August 19, 2014 Fueling the Future with Natural Gas: Bringing It Home Kathryn Clay, Ph.D. Vice President, Policy Strategy American Gas Association Shale Gas Resources

More information

Strategic Cost Management in Black Tea Processing

Strategic Cost Management in Black Tea Processing Strategic Cost Management in Black Tea Processing Dr W S Botheju, Head Process Technology Division Te a Re se arch Institute of S ri Lank a Background Quality consumer demand driven Good Quality Tea better

More information

YWCA 1503 S. Denver Tulsa, Oklahoma 5/18/2010 Performed By

YWCA 1503 S. Denver Tulsa, Oklahoma 5/18/2010 Performed By Energy Audit for YWCA 1503 S. Denver Tulsa, Oklahoma 5/18/2010 Performed By 220 E. 8th Street Tulsa, Oklahoma 74119 918-582.0229 Fax: 918.599.0665 www.craftontullsparks.com Table of Contents Cover Page...

More information

2014 EAST TENNESSEE NATURAL GAS PIPELINE AND SALTVILLE GAS STORAGE CUSTOMER MEETING. Welcome to Barnsley Gardens!

2014 EAST TENNESSEE NATURAL GAS PIPELINE AND SALTVILLE GAS STORAGE CUSTOMER MEETING. Welcome to Barnsley Gardens! 2014 EAST TENNESSEE NATURAL GAS PIPELINE AND SALTVILLE GAS STORAGE CUSTOMER MEETING 2014 EAST TENNESSEE NATURAL GAS PIPELINE AND SALTVILLE GAS STORAGE CUSTOMER MEETING Welcome to Barnsley Gardens! Welcome

More information

QUICK START GUIDE. SQF Implementation. for.

QUICK START GUIDE. SQF Implementation. for. QUICK START GUIDE for SQF Implementation www.22000-tools.com CONTENTS WHAT IS SQF? BENEFITS OF SQF SQF LEVELS SQF MODULES IMPLEMENTING SQF AND PREPARING FOR CERTIFICATION ASSIGN YOUR PEOPLE RESOURCES

More information

Expanding Existing Pipeline Capacity to Meet New England s Energy Needs. Mike Dirrane Director, Marketing

Expanding Existing Pipeline Capacity to Meet New England s Energy Needs. Mike Dirrane Director, Marketing Expanding Existing Pipeline Capacity to Meet New England s Energy Needs Mike Dirrane Director, Marketing January 27, 2015 Spectra Energy s Portfolio of Assets Based in Houston, TX with operations in 30

More information

Annual Greenhouse Gas Emissions Inventory Update for FY 2016 (October 7, 2016)

Annual Greenhouse Gas Emissions Inventory Update for FY 2016 (October 7, 2016) Annual Greenhouse Gas Emissions Inventory Update for FY 2016 (October 7, 2016) Background and Overview Bowdoin College committed to become carbon-neutral by the year 2020 and released a detailed implementation

More information

Solar Power Realities

Solar Power Realities Solar Power Realities Supply-Demand Characteristics, Storage and Capital Costs by Peter Lang Abstract This paper provides a simple analysis of the capital cost of solar power and energy storage sufficient

More information

Tennessee Gas Pipeline Customer Meeting Business Session Thursday August 13,2015

Tennessee Gas Pipeline Customer Meeting Business Session Thursday August 13,2015 Tennessee Gas Pipeline 2015 Customer Meeting Business Session Thursday August 13,2015 1 Agenda Thursday, August 13 th, 2015 8:30 a.m. Welcome Sital Mody 8:45 a.m. Pipeline Operations Update Ray Miller

More information

Value of Air Source Heat Pumps in Light of Variable Energy Prices. Jeff Haase. Energy Design Conference February 27, 2013

Value of Air Source Heat Pumps in Light of Variable Energy Prices. Jeff Haase. Energy Design Conference February 27, 2013 Value of Air Source Heat Pumps in Light of Variable Energy Prices Jeff Haase Energy Design Conference February 27, 2013 Agenda Overview of Air Source Heat Pump Technologies History, General Comparison

More information

TRACKING THE GAS TEMPERATURE EFFECT IN A DISTRIBUTION SYSTEM

TRACKING THE GAS TEMPERATURE EFFECT IN A DISTRIBUTION SYSTEM TRACKING THE GAS TEMPERATURE EFFECT IN A DISTRIBUTION SYSTEM Eric Kelner, P.E. - Letton-Hall Group, San Antonio, TX Bryan Niebergall, P.E. - Questar Gas, Salt Lake City, UT AGA Operations Conference, Nashville,

More information

Union College Combined Cooling, Heat and Power Project

Union College Combined Cooling, Heat and Power Project Union College Combined Cooling, Heat and Power Project Presented by: Mark Donovan, PE Union College, Assistant Director of Utilities Aaron Bolhous, PEng CHA, Project Engineer Agenda Introduction to Union

More information

Missouri River Basin Water Management

Missouri River Basin Water Management Missouri River Basin Water Management Spring 2011 Public Meetings April 12 th 11:00 a.m. Nebraska City, NE April 12 th 7:00 p.m. Fort Peck, MT April 13 th 1:00 p.m. Bismarck, ND April 13 th 7:00 p.m. Pierre,

More information

Appendix A. Project Description

Appendix A. Project Description Appendix A Project Description I. Project Summary 1. The proposed Jordan Cove LNG export terminal ( Jordan Cove ) is a facility designed to produce and export liquefied natural gas ( LNG ). Jordan Cove

More information

Lehman Brothers T Conference San Francisco. Craig DeYoung, Vice President Investor Relations December 9, 2004

Lehman Brothers T Conference San Francisco. Craig DeYoung, Vice President Investor Relations December 9, 2004 Lehman Brothers T4 2004 Conference San Francisco Craig DeYoung, Vice President Investor Relations December 9, 2004 Safe Harbor Safe Harbor Statement under the U.S. Private Securities Litigation Reform

More information

Hotels: Water and Energy

Hotels: Water and Energy Hotels: Water and Energy Agenda 01 Introduction 05 Hotel System Options 02 Company Overview 06 Hotel Energy Conservation 03 Hotel Energy & Water Use 07 Hotel Project Examples 04 Design Philosophy Introduction

More information

McGraw-Hill Education, Inc. Where We Came From

McGraw-Hill Education, Inc. Where We Came From What is BPO Business Process Outsourcing (BPO) It is partnering with a third party company to perform most back office data entry functions of your organization. McGraw-Hill Education, Inc. Where We Came

More information

Spectra Energy: Moving Ahead, Gaining Momentum

Spectra Energy: Moving Ahead, Gaining Momentum 8 th ANNUAL PLATTS PIPELINE EXPANSION & DEVELOPMENT CONFERENCE HOUSTON, TX SEPTEMBER 17, 2013 Spectra Energy: Greg Crisp Director, Business Development Safe Harbor Statement Some of the statements in this

More information

Retrocommissioning (RCx)

Retrocommissioning (RCx) Retrocommissioning (RCx) Facilities & Services - Engineering Services Saving the planet, two buildings at a time. Mr. Karl Helmink Mr. Damon McFall Creating a Sustainable Campus What is Retrocommissioning

More information

The Service Desk Balanced Scorecard

The Service Desk Balanced Scorecard The Service Desk Balanced Scorecard Your Overall Measure of Service Desk Performance MetricNet Best Practices Series Your Speaker: Jeff Rumburg Co Founder and Managing Partner, MetricNet, LLC Winner of

More information

Soil Temperature Damping Depth in Boreal Plain Forest Stands and Clear Cuts: Comparison of Measured Depths versus Predicted based upon SWAT Algorithms

Soil Temperature Damping Depth in Boreal Plain Forest Stands and Clear Cuts: Comparison of Measured Depths versus Predicted based upon SWAT Algorithms Soil Temperature Damping Depth in Boreal Plain Forest Stands and Clear Cuts: Comparison of Measured Depths versus Predicted based upon SWAT Algorithms G. Putz and B.M. Watson Civil & Geological Engineering,

More information

Midwest Supply Update: Alliance Pipeline and Rockies Alliance Pipeline

Midwest Supply Update: Alliance Pipeline and Rockies Alliance Pipeline Midwest Supply Update: Alliance Pipeline and Rockies Alliance Pipeline Tony Straquadine Government Affairs Manager Forward looking statements and information o Certain information contained in this [presentation],

More information

Energy Efficient Buildings: Realizing Money and Energy- Saving Opportunities

Energy Efficient Buildings: Realizing Money and Energy- Saving Opportunities January 10 th, 2013 Energy Efficient Buildings: Realizing Money and Energy- Saving Opportunities 1 Energy Efficient County Buildings: Realizing Money and Energy- Saving Opportunities Energy Efficient Buildings:

More information

) ) ) ) ) ) PREPARED DIRECT TESTIMONY OF STEVE WATSON SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY

) ) ) ) ) ) PREPARED DIRECT TESTIMONY OF STEVE WATSON SOUTHERN CALIFORNIA GAS COMPANY AND SAN DIEGO GAS & ELECTRIC COMPANY Application No: A.14-06- Exhibit No.: Witness: Steve Watson Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) for Low Operational Flow Order and Emergency

More information

PhD Dissertation Defense Presentation

PhD Dissertation Defense Presentation PhD Dissertation Defense Presentation Wednesday, September 11 th, 2013 11:00am 1:00pm C103 Engineering Research Complex ADVANCED INVERTER CONTROL FOR UNINTERRUPTIBLE POWER SUPPLIES AND GRID-CONNECTED RENEWABLE

More information

Future Trends in Corrosion Control

Future Trends in Corrosion Control INTERSTATE PIPELINES EXPLORATION & PRODUCTION MIDSTREAM Future Trends in Corrosion Control NACE Houston Section January 10, 2012 Drew Hevle Manager, Corrosion Control El Paso Obligatory Pipeline Map Colorado

More information

Gas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI

Gas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI Gas-Electric Infrastructure Challenges WPUI Gas Program September 17, 2012 MISO EPA/Gas related efforts - Timeline EPA Rules & Regulations MISO EPA Impact Study, Oct 2011 Gas Consultant Phase 1 Study,

More information

Alliance Pipeline Monetizing Gas & NGLs. Jason Feit Business Development Manager Platt's 6 th Annual Rockies Oil & Gas Conference

Alliance Pipeline Monetizing Gas & NGLs. Jason Feit Business Development Manager Platt's 6 th Annual Rockies Oil & Gas Conference Alliance Pipeline Monetizing Gas & NGLs Jason Feit Business Development Manager Platt's 6 th Annual Rockies Oil & Gas Conference Forward looking statements and information Certain information contained

More information

RENEWABLE ENERGY INTEGRATION IN TAMILNADU

RENEWABLE ENERGY INTEGRATION IN TAMILNADU RENEWABLE ENERGY INTEGRATION IN TAMILNADU Generator Installed Capacity in MW CGS Nuclear 6% PURCHASE (LTOA, MTOA) 18% TN Hydro 2308 TN Thermal 4320 TN Gas 516 TN IPP 746 CGS Thermal 15% CPP 3% TN IPP 3%

More information

Tertiary reserve: 15 min 1 h

Tertiary reserve: 15 min 1 h DESCRIPTION OF THE REQUIRED POSITIVE TERTIARY RESERVE ENERGY ABSTRACT Eva Marie Kurscheid Transmission system operators need tertiary to guarantee reliable grid operation. The used tertiary energy varies

More information

European Freight Forwarding Index

European Freight Forwarding Index European Freight Forwarding Index 1 February 1 Sentiment is improving in the freight market Johannes Møller joml@danskebank.dk +45 45 12 36 Main conclusion from survey Our proprietary European Freight

More information

AEE New England New England Energy Update 1/6/2016. Tim Bigler Senior Market Strategist

AEE New England New England Energy Update 1/6/2016. Tim Bigler Senior Market Strategist AEE New England New England Energy Update 1/6/2016 Tim Bigler Senior Market Strategist Agenda NYMEX NG/Oil Prices New England NG/Electric Prices Future Gas Produc:on Influences New England NG Pipeline

More information

Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results.

Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results. Refuse Collections Division Solid Waste Services Department Anchorage: Performance. Value. Results. Mission Provide solid waste collection and disposal service to rate-paying customers within our defined

More information

Status of Canadian Energy Storage. Edward Morofsky Richard Stockton College May 2006

Status of Canadian Energy Storage. Edward Morofsky Richard Stockton College May 2006 Status of Canadian Energy Storage Edward Morofsky Richard Stockton College May 2006 Ottawa Average Temps and RH Monthly Ottawa Temperatures Ottawa Humidity 30 90 25 80 Degrees C 20 15 10 5 0-5 -10-15 Jan

More information

[N]COLONIAL PIPELINE COMPANY [C] SHELL PIPELINE COMPANY LP

[N]COLONIAL PIPELINE COMPANY [C] SHELL PIPELINE COMPANY LP This tariff is being filed solely for the convenience and information of carriers, shippers and potential shippers. Texas R.R.C. No. 3.0.0 (Adopts Texas R.R.C. No. 157.6.0) *Shell Pipeline Company LP series

More information

Iroquois. Capacity Release. Training Guide

Iroquois. Capacity Release. Training Guide PAGE 1 OF 20 Iroquois Capacity Release Training Guide 10/14/2014 PAGE 2 OF 20 TABLE OF CONTENTS OVERVIEW... 3 DEFINITIONS OF TERMS... 3 INITIAL CONTRACTING REQUIREMENTS FOR RELEASING SHIPPERS... 4 INITIAL

More information

I/I Analysis & Water Balance Modelling. Presented by Paul Edwards

I/I Analysis & Water Balance Modelling. Presented by Paul Edwards I/I Analysis & Water Balance Modelling Presented by Paul Edwards Contents Background Wet Weather Model Calibration Inflow / Infiltration Assessment Flow Containment Options Water Balance Model 20 Year

More information

HV SHRM Member Survey

HV SHRM Member Survey HV SHRM Member Survey 1. Currently, we meet 7:30 a.m. 10:00 a.m. on the first Thursday of the month. In general, do Thursdays work for you? Yes 89.5% 34 No 10.5% 4 Of not, what days work better? 2 2. What

More information

Annual Report. December 2010 November Bradley Cole 2/7/2012

Annual Report. December 2010 November Bradley Cole 2/7/2012 Annual Report December 2010 November 2011 Bradley Cole 2/7/2012 CH2M HILL annual report to the Board of Directors of the Pine-Strawberry Water Improvement District. This annual report provides an overview

More information

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am

Wind Workshop. Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Wind Workshop Technical Characterization: Dependable Capacity & Firm Energy 10:00-10:30am Objective of this session: Understand BC Hydro s definitions and calculation methodology of dependable capacity

More information

OREGON AND SW WA MARKET UPDATE February 2017

OREGON AND SW WA MARKET UPDATE February 2017 OREGON AND SW WA MARKET UPDATE February 2017 Portland Metro and Southwest Washington (Multnomah, Clackamas, Washington, Columbia, & Clark Counties) Single Family Homes Resale (RMLS & Trendgraphix). Summary:

More information

EIA Short-Term Energy and

EIA Short-Term Energy and EIA Short-Term Energy and Winter Fuels Outlook Washington, DC U.S. Energy Information Administration Independent Statistics & Analysis www.eia.gov Overview EIA expects higher average fuel bills this winter

More information

PJM Roadmap for edart

PJM Roadmap for edart PJM Roadmap for edart As of March 15, 2017 Background edart (electronic Dispatcher Application and Reporting Tool) is suite of electronic applications used to facilitate dispatcher-todispatcher communications,

More information

Solar Energy Technologies

Solar Energy Technologies 1 Solar Energy Technologies ME 430 Queen s University The Solar Energy Resource Varies over day and year, (i.e., intermittent) Generally non-dispatchable Ottawa average for year ~4 kwh/m 2 per day e.g.,

More information

PacifiCorp 2017R Request for Proposals. Pre-Issuance Bidders Conference May 31, 2017

PacifiCorp 2017R Request for Proposals. Pre-Issuance Bidders Conference May 31, 2017 PacifiCorp 2017R Request for Proposals Pre-Issuance Bidders Conference May 31, 2017 Logistics Conference Date May 31, 2017, 1:00 2:00 PM (Mountain) Location Rocky Mountain Power, North Temple Office 1407

More information

2017 Contact Center Overflow Vendor Request for Proposals Responses to RFP Questions

2017 Contact Center Overflow Vendor Request for Proposals Responses to RFP Questions 2017 Contact Center Overflow Vendor Request for Proposals Responses to RFP Questions May 5, 2017 All questions are addressed below: Q1: Will the vendor s geographic location(s) or potential location(s)

More information

Implications of Measured Commercial Building Loads on Geothermal System Sizing

Implications of Measured Commercial Building Loads on Geothermal System Sizing Implications of Measured Commercial Building Loads on Geothermal System Sizing ASHRAE Annual Meeting June 23, 1999 Hugh I Henderson, Jr.. P.E. CDH Energy Corp. Cazenovia,, NY www.cdhenergy.com Overview

More information

Urban Greening and the UHI: Seasonal Trade-offs in Heating and Cooling Energy Consumption in Manchester, UK

Urban Greening and the UHI: Seasonal Trade-offs in Heating and Cooling Energy Consumption in Manchester, UK Urban Greening and the UHI: Seasonal Trade-offs in Heating and Cooling Energy Consumption in Manchester, UK T H E R E S E A R C H E R S C y n t h i a S k e l h o r n PhD Physical Geography Post-Doctoral

More information

Great Ocean Rd Ice Creamery

Great Ocean Rd Ice Creamery Great Ocean Rd Ice Creamery BCA Section J - JV3 Compliance Report Revision: 01 Job No: 2171 Date: 7 July 2015 ADP Consulting Pty Ltd Level 10, 10 Queens Rd, Melbourne Vic 3004 www.adpconsulting.com.au

More information

CHP Case Studies. Midwest CHP Application Center (MAC) .org (312) University of Illinois at Chicago Energy Resources Center UIC

CHP Case Studies. Midwest CHP Application Center (MAC) .org (312) University of Illinois at Chicago Energy Resources Center UIC CHP Case Studies Midwest CHP Application Center (MAC) www.chpcentermw.org.org (312)413-5448 University of Illinois at Chicago Energy Resources Center CHP Case Studies Elgin Community College Presbyterian

More information

IRRIGATION CONTROLLERS

IRRIGATION CONTROLLERS IRRIGATION CONTROLLERS TIMERS FOR THE HOMEOWNER Recommended Water Saving Features Water too precious to waste! IRRIGATION CONTROLLERS TIMERS FOR THE HOMEOWNER Recommended Water Saving Features While controllers

More information

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission

More information

EIA: gas storage design capacity slightly up May NYMEX natural gas futures at $2.674/MMBtu drifts in search of support

EIA: gas storage design capacity slightly up May NYMEX natural gas futures at $2.674/MMBtu drifts in search of support Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 8: 8:45 9:3 1:15 11: 11:45 12:3 13:15 14: Prior Day s NYMEX May-18 Contract (CT) 2.78 2.76 2.74 2.72 2.7 2.68

More information

Modeling and analyzing solar cooling systems in Polysun

Modeling and analyzing solar cooling systems in Polysun Modeling and analyzing solar cooling systems in Polysun Seyed H. Rezaei (seyed.rezaei@velasolaris.com) 1 Andreas Witzig (andreas.witzig@velasolaris.com) 1 Michael Pfeiffer (michael.pfeiffer@velasolaris.com)

More information

Millennium Pipeline Company, LLC. Capacity Release Quick Reference Millennium Pipeline Shipper Meeting

Millennium Pipeline Company, LLC. Capacity Release Quick Reference Millennium Pipeline Shipper Meeting Millennium Pipeline Company, LLC Capacity Release Quick Reference 2014 Millennium Pipeline Shipper Meeting Types of Releases Per NAESB Requirements, the following are guidelines for Capacity Release: Biddable

More information

GMS Irvine - Energy Efficiency

GMS Irvine - Energy Efficiency GMS Irvine - Energy Efficiency GSK Irvine Winner - Low Carbon Award 2013 The European Chemical Industry Council Winner of the 2013 Energy Efficiency Award GSK High Level Environmental Sustainability Strategy

More information

Missouri River Basin Water Management

Missouri River Basin Water Management Missouri River Basin Water Management Spring 2015 Public Meetings April 7 th April 7 th April 8 th April 9 th April 9 th 11:00 a.m. 6:00 p.m. 11:00 a.m. 11:00 a.m. 6:00 p.m. Pierre, SD Bismarck, ND Fort

More information

Emissions Modeling For Photochemical Modelers. Mark Janssen LADCO Photochemical Modelers Training August 3-4 th 2010

Emissions Modeling For Photochemical Modelers. Mark Janssen LADCO Photochemical Modelers Training August 3-4 th 2010 Emissions Modeling For Photochemical Modelers Mark Janssen LADCO Photochemical Modelers Training August 3-4 th 2010 Overview Emissions Modeling (EM) Issues Every Photochemical Modeler Needs To understand

More information

Climate Change: Scientific basis and risks for the finance sector

Climate Change: Scientific basis and risks for the finance sector Climate Change: Scientific basis and risks for the finance sector P. Hadjinicolaou 1,2 and C. Zerefos 1,3 1 Lab. of Climatology and Atmospheric Environment, University of Athens 2 Frederick Institute of

More information

Environmental Improvement Plan. Sohar Refinery

Environmental Improvement Plan. Sohar Refinery Environmental Improvement Plan Sohar Refinery Feb 2014 Page 1 of 18 Waste Water Treatment Plant Improvements Background The treatment of the waste water of the Refinery was malfunctioning for a long period.

More information