1 VIA / TCU 3rd semester workshop A2015 Building CASE 1 : SINGLE FAMILY HOUSE Component Technical Course VIA/ TCU workshop A2015 1

2 Aim of the Course: Discovery of Building component in Denmark & China Understanding of basic builidng component for single family hourse Improve Technical english in building sector Serving the technical skill attached to construction technology 2

3 Content: Foundation Flooring Solid ground floor/ground support floor Suspended ground floor/story partitions Upper suspended floor/story partitions Walls: Basement wall External wall: heavy / light Load bearing Internal wall Non-loading bearing Internal wall Windows Doors Roof Building service 3

4 Foundation: DEFINITION: Base of the building Connection between the house and soil FUNCTION: Provide a solid, secure and stable platform that will support and transfer the loads from the structure evenly through the sub-soil. 4

5 Foundation: TYPE: Direct foundation Indirect foundation MATERIAL: Made from concrete(a mixture of cement,sand and aggregate) Can be reinforced with steel bar or mesh Titel på præsentationen 5

6 Foundation: Direct foundation: Rest directly on the subsoil single family house Stepped foundation is stip foundation for use on sloping stie. 6

7 Foundation: Direct Foundation: Concrete Slab Fig 1 : Raft foundation Poor soil and natural ground Lightly loaded Fig 2 : Cross section raft foundation Titel på præsentationen 7

8 Foundation: Indirect foundation: Foundations are carried out by piles 8

9 Foundation : Material: Trench-fill foundation Light weight blocks Foundation blocks Cast-in-situ foundation in system formwork 9

10 Flooring: DEFINITION: Floor construction resting directly on the ground A floor form the division between two levels TYPE: Solid ground floors Suspended ground floors Upper suspended floors 10

11 Flooring-Solid groundfloor/ground supported floor: FUNCTION: Shall be insulated against ingress of moisture and loss of heat Shall be sealed in order to prevent the ingress of air containing radon MATERIAL: Capillary breaking layer Light weight clinker floor blocks or polystyrene inslulation slab Heating insulating layers Concrete slab Floor finishes 11

12 Flooring-Solid ground floor/ground supported floor: a.radon penetration is avoided by suspending bitumen felt across the edge insulation groove and bonding it to the concrete slab. b. load-carrying wall stand on top of the internal foundation c. a non load-carrying internal wall and the latter is directly on the capillary breaking layer, a.clinker concrete blocks with an insulation layer in the middle is broken the cold bring through the upper part of foundation b. load-carrying wall stand on top of the internal foundation. c. a non load-carrying internal wall and the latter is directly on the capillary breaking layer, 12

13 Flooring-Suspended groundfloor/storeypatition Construction: Floor (suspended floor/non suspended floor) Concrete deck element(hollow deck /concrete slab) Hardcore insulation with needs Need adequate ventilation and prevent the damp conditions. 13

14 Flooring-Upper suspendedfloor/storeypartition Solid: In large buildings, concrete deck elements very often provide the main flooring structure. (similiar with suspended ground floor ) Timber: The end of joists must be supported by load bearing walls. Normally to be built into the walls Alternatively use metal fixing 14

15 Wall: DEFINITION/FUNCTION: To divide up space and where necessary carry loads Vertical envelope against wind and rain MATERIAL: Brick Concrete Wood Steel TYPE: Basement wall External wall Internal wall 15

16 Wall-Basement external wall: CONSTRUCTION: Concrete (cast in situ) Solid light weight concrete blocks Sandwich element 16

17 Wall- External wall Heavy external wall: Load bearing Masonry : Concrete wall/ Brick wall 17

18 Wall- External wall Brick wall: Single row of brick or blocks in the walls(called course). Cavity wall with two parts: inner(internal) and Outer(external wall) Inner leaf Old type from 1950 Moden type from 2011 D.P.C Damp Proof Course Wall tiel Mortar joint Insulation Outer leaf 18

19 Heavy External wall: Brick cavity wall : Tradition in Northern Europe Protect from dampness Other type: Brickwork combing with concrete Brickwork combing with concrete element Brickwork combing with light weight concrete block 19

20 Light External wall: Loading bearing frame : Steel profiles/ wooden studs Light cladding/ brickwork outer leaf Ventilated cavity, a wind proof layer, insulation and a moister barrier 20

21 Load Bearing Internal wall: DEFINITION: A wall carrying a vertical load from roof/ storey partitions MATERIAL: Bricks Blocks Prefabricated elements of lightweight concrete Titel på præsentationen 21

22 Non-load Bearing Internal wall: DEFINATION: Do not carry the load No bracing MATERIAL: Stud walls (wood or steel) Clad in boards(plasterboard, plywood etc.) Titel på præsentationen 22

23 Window: DEFINITON: Allow light into the house Divide the facade TYPE: Top-hung Tit-and-turn hung Side-hung 23

24 Window: ROOFLIGHT WINDOW: Domed roofligt Skylight Rooflight Skylight 24

25 Window: MATERIAL: Timber Metal Plastic Timber and metal Cavity Double glazing Rubber tape Window frame Base Drain 25

26 Window: Joints with external wall : Head Head Sill Sill 26

27 Door: Types Folding doors Swinging doors Sliding doors Cylinder Winding drum Roll up doors grooves Steel strips Up and over doors Tipping doors Springs to assist 27

28 Door: Door frame structural elements Head Jamb Rebate Doorstep Sill Threshold 28

29 Door: Appearances Glass Panel doors Flush doors Plywood panel 29

30 Door: Components Handle Latch Door stop Bolt Escutcheon Lock Fastener 30

31 Roof: DEFINITION: Upper face of the building envelop FUNCTION: Protect the building from wind and rain CONSTRUCTION: Laid on battens, sheets or boards Supported by loading bearing structure: rafter 31

32 Roof: TYPE: 32

33 Roof: Pitched roof/gable roof: Ridge Roof cladding Roof covering A 45 slope Gable Attic / Loft Eave 33

34 Roof: Traditional Roof Timber frame: Ridge King post Purlin Truss Rafter 34

35 Roof: Timer trusses: Cat walk Brace 35

36 Roof: Roof covering: pan tiles or roman tile Fibre-cement roofing sheets Roofing felt Fibre-cement roofing slates Natural roofing slates Steel or aluminium sheeting 36

37 Roof: Roof detail: 37

38 Building service: DEFINITION: Enable or determine the use of a building during or after it construction. INCLUDING: Waste&Drains Water supply Space heating Gas supply Ventilation Electrical supply Telecommunications 38

39 Waste & Drain Waste: Inside a building Drain: From outside a building to the main sewer Sewer: Under the road and carring the waste to ourfall 39

40 Water supply: Water: Supply from a water treatment plant 40

41 Space Heating Energy required can be generated by: Gas or electricity Solid fuel (coal) Wood Solar energy Most common form is central heating, hot water passed through pipes and radiators with the heating being transferred to the space. 41

42 Gas supply Supplied from: From gas main Liquid petroleum gas from bottles Provide for: Hot water Space heating Cooking 42

43 Ventilation: TYPE: Natrual ventilation Mechnical ventilation 43

44 Electrical supply Electrical system conduct current to the sockets or outlets. 44

45 Time to work! Check on introduction of assignment Deadline for the assignment is Monday before kl 8.00 Titel på præsentationen 45

assembly an open space between the roof and ceiling of a building attic balloon frame a joist constructed of steel with bars in the verticle web space

assembly an open space between the roof and ceiling of a building attic balloon frame a joist constructed of steel with bars in the verticle web space assembly two or more interconnected structural components combined to meet a specific function or design requirement attic an open space between the roof and ceiling of a building balloon frame a type

More information

WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK )

WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK ) WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK ) 1.0 Comparative wall systems Wood stud walls * walls are normally 2x4, but may be 2x6. * studs are spaced 16. * studs carry vertical loads.

More information

PRELIMINARY INSPECTION FRAMEWORK

PRELIMINARY INSPECTION FRAMEWORK PRELIMINARY INSPECTION FRAMEWORK 1. Oversite Striping of topsoil Forming site entrance Clearing off topsoil for service roadway Roadside drainage continued under entrance bay Any mature trees in vicinity

More information

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw RESIDENTIAL CONSTRUCTION DETAILS U.S. EDITION A visual guide to construction detailing Emma Walshaw Contents INTRODUCTION 4 PRINCIPLES OF CONSTRUCTION DETAILING 6 FOUNDATIONS 9 PRINCIPLES OF FOUNDATION

More information

PAGE 415. Part 9. External works. 9.1 Garages. 9.2 Drives, paths and landscaping

PAGE 415. Part 9. External works. 9.1 Garages. 9.2 Drives, paths and landscaping PAGE 415 Part 9 External works 9.2 Drives, paths and landscaping Part 9 External works Chapter CONTENTS SCOPE Clause DESIGN Design standards D1 1 Statutory requirements D2 1 Garage foundations D3 1 Garage

More information

Construction Technology Revision Guide

Construction Technology Revision Guide Construction Technology Revision Guide Sub structures and Super structures Super structure (Wall, floors roof) Sub structure (Foundations) 2 Thermal Insulation Thermal insulation helps to prevent heat

More information

Building use, location etc. Option 1 Domestic type Pitched Roof 15, insulation at rafter line (heated habitable room) UV001 NOV 2015 (V2)

Building use, location etc. Option 1 Domestic type Pitched Roof 15, insulation at rafter line (heated habitable room) UV001 NOV 2015 (V2) U-Value & Condensation Risk calculation request form Due to high demand for our free calculation service, priority will be given to U-values requested via correctly completed forms as below. Please complete

More information

THE CONSTRUCTION OF BUILDINGS

THE CONSTRUCTION OF BUILDINGS THE CONSTRUCTION OF BUILDINGS Volume 1 FOUNDATIONS AND OVERSITE CONCRETE, WALLS, FLOORS, ROOFS FIFfH EDITION R. BARRY ARCHITECT 105017 IIIIIII i l ~ 11 1 ~! I~I I ill 111 ~II Malta. College of Arts, Science

More information

DRY CONSTRUCTION SYSTEMS

DRY CONSTRUCTION SYSTEMS DRY CONSTRUCTION SYSTEMS Adrienn LEPEL BUTE Dry construction systems Prefabricated elements assembly on site Minimal use of water dry construction systems Assembled partitions Suspended ceilings Raised

More information

BBA 001 Documents included under the scope of BBA s ISO UKAS accreditation

BBA 001 Documents included under the scope of BBA s ISO UKAS accreditation BBA 001 Documents included under the scope of BBA s ISO 17065 UKAS accreditation Product Standard Building Systems and Kits BBA Technical Specification 001 Ceiling Products BBA Technical Specification

More information

chapter Principles of building OVERVIEW

chapter Principles of building OVERVIEW Principles of building chapter 4 OVERVIEW Whatever type of building is being constructed there are certain principles/elements that must be included, for example a block of 75 Carpentry and Joinery NVQ

More information

Construction Studies Theory - Higher Level

Construction Studies Theory - Higher Level 2015. M76 Coimisiún na Scrúduithe Stáit State Examinations Commission Leaving Certificate Examination, 2015 Construction Studies Theory - Higher Level (300 marks) Friday, 12 June Afternoon, 2:00 to 5:00

More information

TW50. Insulation STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY. Low Energy Low Carbon Buildings. Wall lining. Inner leaf blockwork

TW50. Insulation STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY. Low Energy Low Carbon Buildings. Wall lining. Inner leaf blockwork Insulation CI/SfB (21.9) Rn7 M2 First Issue May 2017 e with retaining clip TW50 STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY 25 mm / 50 mm residual cavity Kingspan Thermawall TW50 Outer

More information

Appendix 4. Bills of Quantities

Appendix 4. Bills of Quantities Appendix 4. Bills of Quantities 201 A4.1 Deep trench latrines Partitions of local materials 1m apart Timber foot rests and floor plates Lightweight timber frame Excavated soil (used for back-fill) Plastic

More information

Wall lining Inner leaf blockwork. K106 Cavity Board. Flexible sealant STANDARD DETAILS FOR 115 MM INSULATION BOARD IN A 125 MM CAVITY

Wall lining Inner leaf blockwork. K106 Cavity Board. Flexible sealant STANDARD DETAILS FOR 115 MM INSULATION BOARD IN A 125 MM CAVITY Insulation CI/SfB (21.9) Rn7 M2 First Issue May 2017 oltherm Board rick outer leaf d retaining clip amp proof course om K106 Cavity Board y fill K106 Cavity Board STANDARD DETAILS FOR 115 MM INSULATION

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

chapter Principles of building OVERVIEW

chapter Principles of building OVERVIEW Principles of building chapter 4 OVERVIEW Whatever type of building is being constructed there are certain principles/elements that must be included, for example a block of flats and a warehouse will all

More information

Residential Building Inspections

Residential Building Inspections Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved

More information

Guidance on U Values from Domestic Heating Design Guide

Guidance on U Values from Domestic Heating Design Guide Guidance on U Values from Domestic Heating Design Guide The following U Values are from the Domestic Heating Design Guide, and the complete publication is available for purchase from members of the Domestic

More information

9.36. Energy Efficiency

9.36. Energy Efficiency Resources and Information NRCAN Energy Efficiency http://www.nrcan.gc.ca/energy/efficiency Canadian Wood Council Wall Thermal Design Tool http://cwc.ca/resources/wall-thermal-design/ 9.36. Energy Efficiency

More information

New Residential Building and Major Alterations / Additions

New Residential Building and Major Alterations / Additions SBCG 4R 13/02/2015 BUILDING CONSENT - APPLICANT CHECKLIST New Residential Building and Major Alterations / Additions APPLICANT NAME: This form is to be completed and submitted with your Form2 Building

More information

GAF EnergyGuard Polyiso Wall Sheathing

GAF EnergyGuard Polyiso Wall Sheathing From: Technical Services May 15, 2013 GAF EnergyGuard Polyiso Wall Sheathing GAF s EnergyGuard Polyiso Wall Sheathing is intended to be installed on residential construction only. Application types include:

More information

TECHNICAL INFORMATION SHEET NUMBER 1a

TECHNICAL INFORMATION SHEET NUMBER 1a BASIC BUILDING REQUIREMENTS FOR THE CONSTRUCTION OF TRADITIONAL SQUASH COURTS Building Requirements The dimensions of a singles or doubles court is shown on the attached diagram. Width and length of the

More information

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER Denis Creedon, B.E., MIEI. CONSULTING ENGINEER PROPERTY INSPECTION REPORT PROPERTY: CLIENT: DATE: Denis Creedon, B.E., MIEI, CONSULTING ENGINEER Tel: 02221157, 0868072327 N0.6 Chapel Lane, Mallow, Co.

More information

9/24/2015. Aalto! / ENG + ARC. Asuinrakennusten rakenneratkaisut. Requirements : Sound insulation requirements : Thermal insulation requirements :

9/24/2015. Aalto! / ENG + ARC. Asuinrakennusten rakenneratkaisut. Requirements : Sound insulation requirements : Thermal insulation requirements : Aalto! / ENG + ARC Asuinrakennusten rakenneratkaisut Requirements : Sound insulation requirements : Thermal insulation requirements : 1 Wall structures : Concrete wall : Concrete outer cover (with cavities)

More information

roofing ROOFING Design of the base ROOFING DETAILS

roofing ROOFING Design of the base ROOFING DETAILS DETAILS The general arrangement details and the principles to be followed at skirtings, upstands, abutments, verges, gutters and expansion joints are as details illustrated. SELECTION PARAMETERS It is

More information

Roofs at Structure. Roof project must be consist of top (plan), front, right and left side views as floor project.

Roofs at Structure. Roof project must be consist of top (plan), front, right and left side views as floor project. Roofs at Structure Structure member that s constructed at top of the building to eliminate the effect of rain, snow, wind, hot and cold weather. Roof project must be consist of top (plan), front, right

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY. Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY. Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR -SQA-SCOTTISH QUALIFICATIONS AUTHORITY Hanover House 24 Douglas Street GLASGOW G2 7NQ NATIONAL CERTIFICATE MODULE DESCRIPTOR -Module Number- 0085137 -Session-1988-89 -Superclass- TE -Title- BUILDING TECHNOLOGY

More information

Thermakraft FIRE RETARDANT SELF SUPPORTING ABSORBENT BREATHABLE SYNTHETIC NON-WOVEN ROOF UNDERLAY STRENGTH BREATHER SHEET WATER RESISTANCE

Thermakraft FIRE RETARDANT SELF SUPPORTING ABSORBENT BREATHABLE SYNTHETIC NON-WOVEN ROOF UNDERLAY STRENGTH BREATHER SHEET WATER RESISTANCE CI/SfB MAY 2012 MEMBRANES OF THE FUTURE FIRE RETARDANT SELF SUPPORTING ABSORBENT BREATHABLE SYNTHETIC NON-WOVEN ROOF UNDERLAY STRENGTH BREATHER SHEET WATER RESISTANCE FLAMMABILITY < FLAMMABILITY INDEX

More information

*X227/12/01* X227/12/01 BUILDING CONSTRUCTION HIGHER NATIONAL QUALIFICATIONS 2014 FRIDAY, 6 JUNE 9.00 AM AM

*X227/12/01* X227/12/01 BUILDING CONSTRUCTION HIGHER NATIONAL QUALIFICATIONS 2014 FRIDAY, 6 JUNE 9.00 AM AM X227/12/01 NATIONAL QUALIFICATIONS 201 FRIDAY, 6 JUNE 9.00 AM 11.00 AM BUILDING CONSTRUCTION HIGHER 100 marks are allocated to this paper. Attempt all questions in Section A (0 marks). Attempt any two

More information

CONCRETE BLOCK MASONRY

CONCRETE BLOCK MASONRY CONCRETE BLOCK MASONRY CONTENT Introduction Types Manufacturing process Properties Advantages Introduction These are the concrete blocks either hollow or solid. A hollow unit is that unit which has core

More information

Chapter 4 Test. Directions: Write the correct letter on the blank before each question.

Chapter 4 Test. Directions: Write the correct letter on the blank before each question. Chapter 4 Test Name: Date: Directions: Write the correct letter on the blank before each question. Objective 1: Describe the impact of fire on common building materials. 1. Which of the following is the

More information

0331 Brick and block construction

0331 Brick and block construction 0331 BRICK AND BLOCK CONSTRUCTION 1 GENERAL 1.1 STANDARDS Materials and construction: To AS 4773.1 and AS 4773.2. 2 PRODUCTS 2.1 DURABILITY Exposure environment: [complete/delete] Exposure locations: To

More information

2003 International Residential Building Code

2003 International Residential Building Code 2003 International Residential Building Code Section R305 Ceiling Height Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less

More information

Leaving Certificate Revision Notes. Airtightness. Potential air leakage paths (the numbered points in section 2.1 give a description for

Leaving Certificate Revision Notes. Airtightness. Potential air leakage paths (the numbered points in section 2.1 give a description for Leaving Certificate Revision Notes Airtightness 6 7 8 8 9 10 5 11 5 12 4 3 1 2 13 12 14 Potential air leakage paths (the numbered points in section 2.1 give a description for Airtightness Introduction

More information

Note on the assessment:

Note on the assessment: Excerpt from: Transitional shelter: 8 designs, IFRC, 2012 Note on the assessment: The following is an excerpt from the Book Transitional Shelters: 8 Designs, IFRC, 2012, available from www.sheltercasestudies.org.

More information

Framing Methods Structural Components

Framing Methods Structural Components Framing Methods Structural Components Balloon Framing *Balloon framing or Eastern framing the exterior studs run from the top of the foundation to the top of the highest level. Benefits of this type of

More information

Building Regulations for the Conservation of Fuel and Power

Building Regulations for the Conservation of Fuel and Power Insulation Second Issue (b) December 2012 Building Regulations for the Conservation of Fuel and Power EXISTING DWELLINGS 2010 Health Check Low Energy Low Carbon Buildings Contents Page Introduction 3 Approved

More information

Carpenter Level 2 Rev. September 2017

Carpenter Level 2 Rev. September 2017 Level 2 A5 Site Layout II Duration: 14 hours 7 hours 7 hours Upon completion of this unit the apprentice will demonstrate knowledge of site layout tools and equipment and their applications and procedures

More information

Construction Studies Theory - Higher Level

Construction Studies Theory - Higher Level 2014. M76 Coimisiún na Scrúduithe Stáit State Examinations Commission Leaving Certificate Examination, 2014 Construction Studies Theory - Higher Level (300 marks) Friday, 13 June Afternoon, 2:00 to 5:00

More information

COPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31

COPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31 Contents Preface to the Sixth Edition xi 1 Making Buildings 3 Learning to Build 4 Buildings and the Environment 5 The Work of the Design Professional 11 The Work of the Construction Professional 19 Trends

More information

THE FLORIDA BUILDING CODE

THE FLORIDA BUILDING CODE THE FLORIDA BUILDING CODE 1. According to the Florida Building Code, spiral stairway treads must all be identical and rise must be sufficient enough to provide a headroom of minimum. A. 6'- 4" B. 6'- 6"

More information

EXTERIOR WALLS. exterior wall systems, cladding w/ masonry. chapters SUBJECT

EXTERIOR WALLS. exterior wall systems, cladding w/ masonry. chapters SUBJECT SUBJECT EXTERIOR WALLS chapters 19 + 20 exterior wall systems, cladding w/ masonry DATE SPRING 2014 PROFESSOR MONTGOMERY CLADDING W/ MASONRY & PRE CAST CONCRETE CLADDING W/ BRICK MASONRY CLADDING W/ BRICK

More information

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 22' x 40' - 16' Tall Garage Plan #g22 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical

More information

11/09/2018 LBP licence classes

11/09/2018 LBP licence classes LBP licence classes Occupational Licensing aims to ensure that people in the building industry are competent and accountable so that homes and buildings are designed and built right first time. Summary

More information

4. Insulation of external walls

4. Insulation of external walls 4. Insulation of external walls 4.1. Insulation on the internal side of the walls For both internal and external types of insulation the major advantages are the decrease in energy consumption as well

More information

Typical detail: New roof with breathable underlay

Typical detail: New roof with breathable underlay New roof with breathable underlay 6. WALLTITE CL00 insulation to achieve target U-value. Vapour control layer. Plasterboard and skim. Unventilated air space 5. WALLTITE returned to insulated cavity stop

More information

External Steel Stud and Top Hat Walls. Details SYSTEMS 176 NON-FIRE RATED SYSTEMS 176 FIRE RATED SYSTEMS 178 BRICK VENEER SYSTEMS 183 INSTALLATION 185

External Steel Stud and Top Hat Walls. Details SYSTEMS 176 NON-FIRE RATED SYSTEMS 176 FIRE RATED SYSTEMS 178 BRICK VENEER SYSTEMS 183 INSTALLATION 185 Details SYSTEMS 176 NON-FIRE RATED SYSTEMS 176 FIRE RATED SYSTEMS 178 BRICK VENEER SYSTEMS 183 INSTALLATION 185 GENERAL REQUIREMENTS 185 FRAMING 185 PLASTERBOARD LAYOUT 189 PLASTERBOARD FIXING 190 EXTERIOR

More information

EXW3 EXISTING DOWEL NEW FOOTING TO EXISTING WALL WITH 3-15M DOWELS, DOWEL THE NEW

EXW3 EXISTING DOWEL NEW FOOTING TO EXISTING WALL WITH 3-15M DOWELS, DOWEL THE NEW -4 /4" 8" 4'-9 /" 6'-4" '-8" DEPRESS TO ACCOMODATE DOOR ABOVE DOWEL NEW FOOTING TO WITH 3-5M DOWELS, DOWEL THE NEW S TO THE S WITH 5M @ 4" O.C. VERTICALLY, PROVIDE -5M BARS 6" LONG IN THE FOOTING 4'-9"

More information

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 30 x 48-14' Tall Garage Plan #g226 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical Section

More information

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 10 Building Construction Roof Types Revised

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 10 Building Construction Roof Types Revised Truck Module Page 1 of 10 BASIC ROOF TYPES The following roof types will summarize the majority of different types of roofs found within the City of Escondido and surrounding areas. There are several others,

More information

EcoHome-Insulation.com. Aluminium Foil Bubble Insulation. General Purpose Insulation. Dry Lining. Cavity Wall. Insulation System.

EcoHome-Insulation.com. Aluminium Foil Bubble Insulation. General Purpose Insulation. Dry Lining. Cavity Wall. Insulation System. Suspended Timber Floor Applications Can be used with Floorboards or Tongue & Groove floor paneling Aluminium Foil Bubble Insulation Joist end Fitting General Purpose Insulation Dry Lining Insulation System

More information

Fundamentals of Building Construction: Materials and Methods

Fundamentals of Building Construction: Materials and Methods Fundamentals of Building Construction: Materials and Methods Allen, Edward ISBN-13: 9780470074688 Table of Contents Preface. Chapter 1: Making Buildings. Learning to Build. Sustainability. The Work of

More information

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio.

Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio. Module number 3 provides an on-line, self-paced training seminar on chapter 4, foundations and chapter 5, floors from the residential code of ohio. 1 This chapter sets forth the prescriptive requirements

More information

Module 10: Masonry walls

Module 10: Masonry walls Module 10: Masonry walls Module Objectives By the end of this session, participants will understand: 1. That there are three main types of walls used to building housing masonry, monolithic and frame walls.

More information

THERMAL MASS CHAPTER 6. Understanding thermal mass. Seasonal effects of thermal mass

THERMAL MASS CHAPTER 6. Understanding thermal mass. Seasonal effects of thermal mass CHAPTER 6 THERMAL MASS mud brick concrete block brick The contents of this chapter explain the effect of thermal mass and provide guidelines for its location and extent. Summer and winter effects of thermal

More information

CI/SfB (23) Suspended Timber Floor Applications Can be used with Floorboards or Tongue & Groove floor paneling Joist end Fitting Aluminium Foil Bubble Insulation General Purpose Insulation Dry Lining Insulation

More information

Project s fiche INOV. Frisomat Case study project's fiche INOV

Project s fiche INOV. Frisomat Case study project's fiche INOV Project s fiche INOV Clear Flatro building 49 metres long The Flatro industrial building in Villers-le-Bouillet measures 15 metres by 49 metres and is 6 metres high. The building rests on concrete plinths

More information

ROCKWOOL Construction Terminology A-Z

ROCKWOOL Construction Terminology A-Z ROCKWOOL Construction Terminology A-Z Construction Terminology A-Z A Anhydrite Screed Apex Lightweight free-flowing and self levelling screed used to give a concrete floor a finish suitable to receive

More information

TECHNICAL GUIDANCE XXXX 2015 EXXON QUESTION ANSWER. page 1 of 9

TECHNICAL GUIDANCE XXXX 2015 EXXON QUESTION ANSWER. page 1 of 9 MARKINGWALLING OF SAFETY GLASS SPANDREL CURTAIN PANELS FORMED TO COLDFROM ROOFS STACKED WINDOW 7.2 /25 January ARRANGEMENTS (First Issue) XXXX EXXON QUESTION Which factors should be taken into account

More information

Refusal to issue a building consent for a house with insulated concrete walls at 11 York Road, Riversdale, Southland

Refusal to issue a building consent for a house with insulated concrete walls at 11 York Road, Riversdale, Southland Determination 2009/104 Refusal to issue a building consent for a house with insulated concrete walls at 11 York Road, Riversdale, Southland 1. The matters to be determined 1.1 This is a determination under

More information

Suspended Timber Floor Applications Can be used with Floorboards or Tongue & Groove floor paneling Aluminium Foil Bubble Insulation Joist end Fitting General Purpose Insulation Dry Lining Insulation System

More information

Building Guide. olorado Chapter of the International Conference of Building Officials. Lancaster County Building Department

Building Guide. olorado Chapter of the International Conference of Building Officials. Lancaster County Building Department olorado Chapter of the International Conference of Building Officials Lancaster County Building Department Single Family Residential One Story Detached Garage How to Use this Guide Provide two sets of

More information

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS

BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS BROCHURE # 108 CONSTRUCTION PLAN COMPONENTS Please note: This construction plan component list is to be used as a guide to assist you with your project. There may be elements unique to your project not

More information

UCC Permit Application Procedures

UCC Permit Application Procedures How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.

More information

Refurbishment site guidance for solid-walled houses ground floors

Refurbishment site guidance for solid-walled houses ground floors GOOD PRACTICE GUIDE 294 Refurbishment site guidance for solid-walled houses ground floors What energy savings to aim for Key points to consider Energy savings and SAP ratings Environmental considerations

More information

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours *CVLTDM* This question paper consists of 13 pages, including 3 answer

More information

AS The External Waterproofing Membranes Standard

AS The External Waterproofing Membranes Standard AS 4654-2 The External Waterproofing Membranes Standard NOTE This external waterproofing standard contains solutions for problems which have not been addressed in other countries. CONFORMANCE CONDITIONS

More information

SITE VISIT REPORT DATE: JOB: NO. OF VISIT: PAGE OF : PURPOSE OF VISIT: CONTRACTOR: Items to be checked Observations Actions SETTING OUT

SITE VISIT REPORT DATE: JOB: NO. OF VISIT: PAGE OF : PURPOSE OF VISIT: CONTRACTOR: Items to be checked Observations Actions SETTING OUT SETTING OUT Correct to boundaries Correct to building lines? Diagonals accurate? Levels correct? EXCAVATIONS Adjoining structures OK? Centres of foundations line with walls? Bottoms of trenches uniform,

More information

BUILDING CONSTRUCTION HANDBOOK. Ninth edition. Roy Chudley. and. Roger Greeno. O Routledge ^ Taylor ^Francis Croup LONDON AND NEW YORK

BUILDING CONSTRUCTION HANDBOOK. Ninth edition. Roy Chudley. and. Roger Greeno. O Routledge ^ Taylor ^Francis Croup LONDON AND NEW YORK BUILDING CONSTRUCTION HANDBOOK Ninth edition Roy Chudley and Roger Greeno O Routledge ^ Taylor ^Francis Croup LONDON AND NEW YORK notations CONTENTS Preface to ninth edition xi Part One General Built environment

More information

A Handbook of thermal bridging details incorporating aircrete blocks

A Handbook of thermal bridging details incorporating aircrete blocks A Handbook of thermal bridging details incorporating aircrete blocks Book 2 Thermal bridging solutions for external wall full fill cavity details Prepared for the Aircrete Products Association by the BBA

More information

energy saving for the future

energy saving for the future CI/SfB (.) Rn (M) July 00 energy saving for the future Polyisocyanurate insulation board Introduction Ballytherm Insulation This brochure describes the use of Ballytherm Polyisocyanurate insulation to

More information

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs November 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements....................................

More information

MODERN CONSTRUCTION ROOFS ANDREW WATTS

MODERN CONSTRUCTION ROOFS ANDREW WATTS MODERN CONSTRUCTION ROOFS ANDREW WATTS 1 2 3 INTRODUCTION 4 METAL 32 GLASS 64 CONCRETE 108 Modern Construction Series 4 Aims of this book 5 Introduction 6 (1) An overview of roof systems 8 Metals Glass

More information

URSA TF Roll URSA GLASSWOOL.

URSA TF Roll URSA GLASSWOOL. URSA GLASSWOOL E-mail : ursauk@uralita.com URSA UK LTD Crest House 102-104 Church Road Teddington, Middlesex TW11 8PY United Kingdom Tel : 020 8977 96 97 Fax : 020 8977 94 56 Web : www.ursa-uk.co.uk E-mail

More information

R-Matte Plus-3: Insulation for the Building Envelope

R-Matte Plus-3: Insulation for the Building Envelope Attic and Crawl Space Applications R-Matte Plus-3 may be applied to the interior face of stud walls or roof rafters within attics and crawl spaces to provide a layer of continuous insulation (ci). Simply

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10 CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES 283 Chapter 10 FUNCTIONAL REQUIREMENTS FUNCTIONAL REQUIREMENTS 10.1 PLASTERWORK Workmanship i. All workmanship must be within the tolerances

More information

A Handbook of thermal bridging details incorporating aircrete blocks

A Handbook of thermal bridging details incorporating aircrete blocks A Handbook of thermal bridging details incorporating aircrete blocks Book 1 Thermal bridging solutions for external wall partial fill cavity details and full fill party wall details Prepared for the Aircrete

More information

Part E robustdetails. robustdetails. September 2015 Update Pack. Dear Colleague,

Part E robustdetails. robustdetails. September 2015 Update Pack. Dear Colleague, Part E September 2015 Update Pack Dear Colleague, Thank you for subscribing to receive updates to the Part E Robust Details Handbook. The most significant amendment is to the Besblock wall, E-WM-26, which

More information

All floors must have sufficient strength and stability in order to support various loads. Such as? People Furniture Equipment Machinery Partitions

All floors must have sufficient strength and stability in order to support various loads. Such as? People Furniture Equipment Machinery Partitions All floors must have sufficient strength and stability in order to support various loads Such as? People Furniture Equipment Machinery Partitions Functional requirements of ground floors What are the functions

More information

CI/SfB (23.4) Rn7 (M2) JUNE Polyisocyanurate insulation board. energy saving for the future

CI/SfB (23.4) Rn7 (M2) JUNE Polyisocyanurate insulation board. energy saving for the future CI/SfB (.) Rn (M) JUNE 0 Polyisocyanurate insulation board energy saving for the future Introduction Ballytherm Insulation This brochure describes the use of Ballytherm Polyisocyanurate insulation to create

More information

This document has been prepared to assist in the preparation of construction certificate plans and specifications in respect to BAL 12.5.

This document has been prepared to assist in the preparation of construction certificate plans and specifications in respect to BAL 12.5. ABN 26 807 194 868 Suite 1 146 Oak Road KIRRAWEE NSW Phone 8880 4480 Email: info@mybuildingcertifier.com.au Construction Standards to Comply with Australian Standard 3959 2009 & Appendix 3 of Planning

More information

SECTION THERMAL INSULATION

SECTION THERMAL INSULATION PART 1 - GENERAL 1.1 DESCRIPTION SECTION 07 21 13 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph not applicable

More information

Residential Plan Review for New One and Two Family Dwellings

Residential Plan Review for New One and Two Family Dwellings The following is a list of items that are normally included in a set of construction drawings for one and two family dwellings. The items in bold depict those items that will be reviewed for during the

More information

MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST AUGUST 2018

MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST AUGUST 2018 SCANDIA-HUS FACT SHEET NO. 3 MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST AUGUST 2018 THIS FACT SHEET SHOULD BE READ IN CONJUNCTION WITH OUR SHELL ERECTION SCHEDULE - FACT SHEET NO. 12 - WHICH CLEARLY

More information

MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST JANUARY 2019

MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST JANUARY 2019 SCANDIA-HUS FACT SHEET NO. 3 MATERIAL & COMPONENT SPECIFICATION DATE: 1 ST JANUARY 2019 THIS FACT SHEET SHOULD BE READ IN CONJUNCTION WITH OUR SHELL ERECTION SCHEDULE - FACT SHEET NO. 12 - WHICH CLEARLY

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES CONTENTS 10.1 PLASTERWORK 10.2 2 ND AND 3 RD FIX FINISHES FUNCTIONAL REQUIREMENT 10.1 Plasterwork Workmanship Design Technical Manual TS-011-09-010412 i. All workmanship must be within defined tolerances

More information

Designation of a Notified Body pursuant to the Construction Products Regulation

Designation of a Notified Body pursuant to the Construction Products Regulation Designation of a Notified Body pursuant to the Construction s Regulation From : Ministero dello Sviluppo Economico - Direzione Generale per il Mercato, la Concorrenza, il Consumatore, la Vigilanza e la

More information

Repair methods of the roofing structures. Mon

Repair methods of the roofing structures. Mon Repair methods of the roofing structures Mon 29.02.2016 Course Content Introduction & Conservation The use of ICT for condition assessment of structures Repair of fire damage Repair methods of the roofing

More information

Structural Engineering

Structural Engineering Structures can be classified based on deformation and type of primary load carried [i.e. Axial (tensile, compressive), flexure, shear and torsion] and their combinations. In order to determine the type

More information

BUDGET ESTIMATE - ISSUE No. 2

BUDGET ESTIMATE - ISSUE No. 2 REPAIRS & ESSENTIAL UPGRADING WORK AT WINGERWORTH PARISH HALL NEW ROAD, WINGERWORTH DERBYSHIRE, S42 6TB BUDGET ESTIMATE - ISSUE No. 2 OCTOBER 2016 GENERAL NOTES Patrick Meeds & Associates were asked to

More information

(Text with EEA relevance) (2017/C 10/02)

(Text with EEA relevance) (2017/C 10/02) C 10/2 EN Official Journal of the European Union 13.1.2017 Commission communication in the framework of the implementation of Regulation (EU) No 305/2011 of the European Parliament and of the Council laying

More information

Prospective Construction Systems for Mass Housing

Prospective Construction Systems for Mass Housing Prospective Construction Systems for Mass Housing TECHNOLOGY PROFILE Light Gauge Steel Framed Structures (LGSF) Building Materials & Technology Promotion Council Ministry of Housing & Urban Poverty Alleviation

More information

FirstEnergy Program Overview

FirstEnergy Program Overview FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio

More information

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory

More information

Roofing and Cladding. ALTERNA NT-slate APPLICATION INSTRUCTIONS 11

Roofing and Cladding. ALTERNA NT-slate APPLICATION INSTRUCTIONS 11 Roofing and Cladding ALTERNA NT-slate APPLICATION INSTRUCTIONS 11 DOUBLE COVER SLATE LAYING SYSTEM 1. GENERAL Throughout the world slates have been traditionally laid on millions of roofs in a double cover

More information

Part 5 Substructure and ground floors. Chapter 5.2. Suspended ground floors

Part 5 Substructure and ground floors. Chapter 5.2. Suspended ground floors Part 5 Substructure and ground floors Chapter CONTENTS SCOPE Clause Page DESIGN - General Design standards D1 1 Statutory and other requirements D2 1 Resistance to ground contaminants D3-D4 1 This Chapter

More information

How to fill in your Timber Frame Order Form

How to fill in your Timber Frame Order Form How to fill in your Timber Frame Order Form 1 General Would you like us to check slab or design the building to Architects drawings? Check Slab: Is the Slab in place already, if so has your architect checked

More information

Carpentry. The following describes the scope and sequence of instruction for Carpentry.

Carpentry. The following describes the scope and sequence of instruction for Carpentry. Carpentry The Montgomery County Students Construction Trades Foundation, Inc has developed a comprehensive construction technology program designed to prepare students for a rewarding career in the construction

More information