DRAW POINT CONSTRUCTION IMPROVEMENT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA USING THE SIX SIGMA METHOD

Size: px
Start display at page:

Download "DRAW POINT CONSTRUCTION IMPROVEMENT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA USING THE SIX SIGMA METHOD"

Transcription

1 DRAW POINT CONSTRUCTION IMPROVEMENT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA USING THE SIX SIGMA METHOD Andrew Parhusip, Freeport-McMoRan Inc., Papua, Indonesia Fikky Hartono, Freeport-McMoRan Inc., Papua, Indonesia Mario Siray, Freeport-McMoRan Inc., Papua, Indonesia Rakhmat Mulyanto, former Freeport-McMoRan Inc., Papua, Indonesia Abstract PT Freeport Indonesia is preparing the Deep Mill Level Zone (DMLZ) mine to be the successor of the currently operating Deep Ore Zone (DOZ) mine. The DMLZ is block cave mine situated 500 m below the DOZ mine and approximately 1,600 m depth from surface. the 2570 level with column heights of roughly 500 m. The Undercut is on 2590 level, some 20 meters above the extraction level. Both of the block caving mines require draw point construction in the extraction level to extract the ore from caved area above. Learning from the experience in DOZ, the construction & maintenance of draw points in the production panels is a significant challenge in supporting consistent production. The average DOZ draw point construction duration is approximately 46 shifts per draw point. The time frame for construction is dependent on several variables; availability of the conventional forming system, material availability, and development tolerances. The repair of concrete floors and lintel sets causes production downtime. Reviewing the old DOZ draw point design, there is an opportunity to increase constructability, durability, and reliability of DMLZ draw points. This paper discusses how the DMLZ has improved draw point construction productivity and is on track to significantly reduce costs whilst increasing the quality by using the Six Sigma Improvement Method. Introduction The DMLZ Mine is part of the PT. Freeport Indonesia (PTFI) future expansion to its underground mining complexes. It is the fourth vertical lift in the East Ertsberg Skarn System (EESS) deposit (figure 1). Figure 1 Future Underground Mine Layout at PTFI The DMLZ mine will replace the production from the DOZ mine, which is planned to be complete in The DMLZ mine initiated caving in September 2015 and is continuing with production ramp-up activities. A significant amount of pre-production development and construction work was required to get the DMLZ to its current state and to initiate the cave. Development access began in September 2004 with the initial blast of the AB Adit portals. Looking at historical DOZ costs, it can be seen in Figure 2 below that the largest percentage of Currently, it is under development phase. The DMLZ mine will be a block cave mine using an advanced undercutting method. The DMLZ extraction level will be approximately 1,600 meters below the surface on 1

2 expenditures is associated with draw point construction and shotcreting activities. approximately 60% of the DOZ extraction level footprint. With an identified issue around drawpoint availability, a Six Sigma approach was applied in the DOZ and the draw point design was improved to create a more efficient construction method, at a lower total cost, and a stronger and more durable product. Figure 2 Detail cost per activity on Production Sequences Draw Point Construction The draw points are the critical link in connecting the caved material to the extraction level and allowing for LHD s to extract ore. These draw points consist of double steel lintel sets and formed concrete that are required to protect the drawpoint and keep it viable over its planned life. Definition Stage Improvement Project This first stage of the project charter, and describes the background and actual data of the DOZ draw point design, the working method and actual duration plus cost of Draw point Construction. The graph below collected from actual data , indicates that based on historical data the DOZ draw point constructed an average of 9.2 DP s/month,with maximum achievement 14.9 DP s a month and a minimum of 6.2 DP s. This variation in achievement was due to several factors including the draw point construction process employed and production rate. At that time DOZ production rate 80K per day on average. Figure 3 Active Draw Point Learning from the experience in the DOZ, the construction & maintenance of draw points in production panels can have a significant impact to production. The construction and repair durations for the DOZ draw points is dependent on availability of key materials and logistical support. In addition, roadway repair from ground movement and water damage can further impact draw point and panel availabilities. Repeated secondary blasting activities can damage lintel sets and lead to major repair activities being undertaken. Non-uniform roadways, drift profiles and lintel set damage make it difficult for the tele-remote and automated LHD operations to be carried out in Figure 4 DOZ Accomplishment for Draw Point Construction Reviewing the DOZ drawpoint construction data for revealed that an average of DP s per month were constructed that year from a plan of 12 per month. The average time taken to construct a DP was measured at 1,432 man-hours per DP versus a plan of 1,292 man-hours, or a 10% actual increase versus the plan. A review of the work method with the goal of a significant improvement in productivity was undertaken as part of this improvement program. The graph below in Figure 5 shows the actual distribution of time taken to construct a drawpoint in the DOZ. The graph indicates that there is quite a spread in times taken per draw point and is indicative 2

3 of the impact of external influences such as logistical support, actual drawpoint opening requirements, development tolerances and variations in construction methodologies. The average time take was 16 days per drawpoint. Figure 7 Average hour duration per Draw point activity Figure 5 DOZ duration completion for 1 DP The chart below in Figure 6 describes the detail workflow of draw point construction work method that was used in the DOZ mine. Figure 8 Pareto chart for DOZ Draw point Construction Figure 6 DOZ Drawpoint Construction Work Method Measurement Stage Target vs Plan The graph below (Figure 7) indicates average completion hours and standard deviation per sequence for each activity. From this data it can be concluded that the wall and roof meshing and forming is the longest duration activity, followed by the steel erection. These activities account for 41% of the total draw point construction time as can be seen in Figure 8. Both of these activities also exhibit the highest swings in standard deviation indicating potential process issues to be improved. Actual Cost of DOZ draw point construction Cost is an important factor to be improved upon. The table and pie chart shown in Table 1 and Figure 9 shows the distribution of costs for the different actives in a percentage of the total. From this data it is clear that the concrete and steel works are the bulk of the expenditure per drawpoint. Table 1 Detail cost of DOZ Draw point Figure 9 Detail cost for Draw point DOZ 3

4 Analysis Stage Root Cause Finding Based on the DOZ historical data an analysis was conducted to identify the root causes behind the DOZ drawpoint duration and cost drivers. From the analysis it was concluded that the wall & roof meshing and forming was the longest sub process of draw point construction. In addition, any significant development over break at a drawpoint also caused delays as the larger excavation required the installation of more materials and concrete. A further delay factor was the variable logistical supply efficiency in providing materials to the work place to be used in the manually intensive forming process The DOZ drawpoints utilize a double lintel set with each set having a double cap. This resulted in erection issues when the excavation was tight in the shoulder areas and required chipping by crews to make room for sets to fit into the correct position. In some cases the construction crews would need to burn holes in the steels sets to fit tie rods to hold the plywood forms in place. At certain periods, rail was installed in the floor of the drawpoints to help reduce wear in the concrete from the LHD mucking action. Over time the rail was exposed from excessive wear and lifted out of place, requiring time consuming repair activities. Other areas of concern identified were the abrasion resistance of the concrete, the application of high strength concrete products and the impact of water on the roadways. Figure 10 Trial Draw point Modular forming Figure 11 Trial Draw Point Modular forming at jobsite (Figure 12). Improvement Stage Reviewing and Selecting Options Drawpoint Construction and Formwork Once the issues with the current drawpoint construction process were identified then several options to help improve the process were selected for review. It was decided to move away from the manual forming process that utilized plywood and go to a modular and re-usable forming system. This would reduce wastage of materials, provide a consistent and uniform product, and simplify and accelerate the construction process. A re-usable formwork system from PERI was adopted in the DMLZ and is shown in Figures 10 and 11. Figure 12 DMLZ Drawpoint Concrete Slab design Lintel Set Re-Design The DMLZ lintel sets designs are significantly different from the sets used in the DOZ. Several key changes were adopted to help overcome some of the problems encountered in the DOZ construction process and for the higher stress levels anticipated in the DMLZ, 500m below the DOZ. The lintel sets are installed in pairs and the DMLZ system utilizes four connector beams between the two sets to provide additional stiffness and improve load shedding. This will help the lintel set survive anticipated higher ground stress, hang-up blasting 4

5 damage and loader impacts. Figure 13 illustrates the results of FEM analysis by Beck Engineering on the existing DOZ sets. The results of the analysis indicated that the main failure mode was experienced in the columns. Figure 15 DMLZ Lintel Set Structural Analysis using Staad Pro V8i The other concern raised during the lintel set redesign process was the impact of secondary blasting in the drawpoints to bring down hang-ups and break up boulders. This blasting process impacts the lintel sets and can move them laterally. In order to stiffen the dual lintel set package four connector beams were added (Casten, 2015), to connect the two lintel sets together, as can be seen in Figure 16. Figure 13 Beck Engineering FEM analysis on DOZ lintel set To get a better analysis on the failure modes, the DOZ and DMLZ lintel sets were compared using STAAD Pro V8i, a structural steel analysis software. This resulted in failures occurring in the columns and reinforced the work by Beck Engineering. Figures 14 and 15 show the STAAD analysis. An important factor for increasing the shear capacity of the columns is the cross sectional area of the web. By increasing the web size the lintel set capacity increased from KPa/lintel (in DOZ) to be KPa/lintel (in DMLZ), an increase of 72%. The redesigned DMLZ lintel set has a smaller actual ratio overall (ratio of total load to structural capacity of the steel member). A smaller actual ratio indicates a stronger structural capacity. The DOZ has a ratio of while the DMLZ linte set has a ratio of 0.389, over twice the shear stress capacity. Figures 16 and 17 show the DMLZ lintel set with the following notable changes in the design: The DMLZ set uses a single 350 mm beam for the cap versus two 327 mm stacked caps in the DOZ. This cap has a 20 mm web versus a 10.5 mm web thickness and provides much greater strength in a more compact system. This change increased the capacity of the sets from 260 KPa in the DOZ to 450 KPa in the DMLZ. This also reduces overall height and helps avoid development tights which are a source of construction delay. Figure 14 DOZ Lintel Set Structural Analysis using Staad Pro V8i Figure 16 Comparison of DOZ lintel set vs DMLZ lintel set The lintel sets were designed to work with the PERI formwork and incorporate holes for tie rods and connectors (Figure 18). 5

6 and the LHD buckets were able to catch and move the rail. Figure 17 3D Design of DMLZ Lintel set. In the DMLZ mine the combination of AnvilTop and embedded rail were substituted for high strength, abrasion resistant concrete.. The high strength concrete planned for the DMLZ draw point roadways underwent testing at the University of Indonesia in Jakarta. It was shown that 80 MPa concrete with fiber (6kg/m3 plastic fiber) had same performance on abrasion resistance to AnvilTop and concrete in the MPa range (Table 1). One of the key challenges in producing the high strength fibrecrete is ensuring that the batch plant can provide the correct level of quality on a consistent basis based on the required concrete recipe (Table 2). Table 1 Laboratory test on abrasive resistance of HPC Figure 18 Actual Lintel set on DMLZ Concrete Works In the DOZ, the draw point floor was reinforced concrete with a minimum thickness of 30 cm, a compressive strength of 50 MPa with the addition of 4 cm of an iron aggregate mortar topping known asanviltop for increased abrasion resistance. Based on the vendor specifications from BASF, AnvilTop is a heavy duty cement-based metallic-aggregate floor topping. It provides heavy-duty protection in key areas subject to abrasion and impact. Its energy absorbing capacity is significantly greater than plain concrete, integral fiber concrete, and high-strength naturalaggregate toppings The road gradient was also kept at a minimum of 3% in order to minimize water ponding. It was noted that the presence of standing water greatly decreases the durability of the road concrete. In some areas of the DOZ mine used rail was installed as part of the concrete process to provide additional wear protection against bucket loading. This proved to be problematic one the concrete wore down past the rail embedment Table 2 Mix Design and trial result for HPC DMLZ Draw point Construction Performance The DMLZ mine has applied all of the improvements discussed to the draw point construction process. Figure 19 shows a picture of a completed draw point in the DMLZ mine. 6

7 Table 3 Improvement List on DMLZ Draw point Category Description Lintel set already proven to hold static load with overall static load max (452.5kPa or452.5kn/m2) Lintel set wall & roof forming Rail Installation & Anvil top Air blast effect must be include on design calculation (covering concrete) - add connector beam on cross beam and column beam put additional hole on cross beam and column for PERI modular system Eliminate tight risk on lintel installation by improving design reduce height of double beam Improving material procurement and reducing 4 column different marking and 2 beam different marking to be 1 column and 1 beam marking to eliminate factor lack of material Find alternate design which enable to apply modular system which have standard work methodsubtituted by PERI modular forming system Find concrete technologies to increase water, impact & abrasive resistance on concrete floorsubtituted with High Perfomance concrete (HPC) with minimum requirement UCS test 80 Mpa Figure 20 Comparison of histogram DOZ vs DMLZ (Duration completion) The reduced construction duration in DML and the redesign has resulted in a reduction in cost and manhours needed per draw point as shown in Figure 21. The DMLZ has achieved an average of 14 draw points constructed per month which equates to annual savings of several millions dollars in materials and labor. Figure 19 Complete draw point construction on DMLZ A comparison of draw point construction durations based on the draw points constructed in DMLZ in 2015 and DOZ data is shown in Figure 20. In summary the DMLZ average time to construct one draw point is 410 hours compared to 444 hours for the DOZ. Figure 20 also shows the standard deviation between the two statistical distributions. The DMLZ mine has a lower variation on construction timing than DOZ which is attributable to the new method and also the impact to construction in DOZ from other activities such as production and caving activities, currently not present in DMLZ. Figure 21 Cost Comparison DMLZ vs DOZ 7

8 ACKNOWLEDGEMENT The authors would like to thank to management teams of PT Freeport Indonesia for permission to prepare and publish this paper,and Underground DMLZ Construction team for support and sharing knowledge. REFERENCES 1. Mulyanto, Rakhmat. Six Sigma Method for Draw point Construction. MBA-ITB Thesis, (2011). 2. Manggala, D. Mengenal Six Sigma Sederhana., (2013). 3. Tarigan, A., Widiyanto, F., Ramirez, M., & Osborne, K., (2010). The Deep Ore Zone (DOZ) Mine Cave Sequence Modifications. SME Annual Meeting Beck Engineering, Beck Engineering Analyis on Lintel set Drawpoint DOZ BASF. MasterTop 300 Technical Data Guide. (2014). 6. Casten, Tim, personal discussion, 2015, 8

CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA

CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA Rian Nugroho, PT Freeport Indonesia, DMLZ Engineering, Papua, Indonesia Andrew Parhusip, PT Freeport Indonesia, DMLZ

More information

Grasberg Block Cave mine: cave planning and undercut sequencing

Grasberg Block Cave mine: cave planning and undercut sequencing Caving 2018 Y Potvin and J Jakubec (eds) 2018 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-9-4 https://papers.acg.uwa.edu.au/p/1815_26_beard/ Grasberg Block Cave mine: cave planning and

More information

Concrete Roof Support at Waihi Gold. Bruce Cloughley¹. Introduction

Concrete Roof Support at Waihi Gold. Bruce Cloughley¹. Introduction Concrete Roof Support at Waihi Gold Bruce Cloughley¹ Introduction Gold Mining at Waihi on the edge of the Coromandel is entering a new phase in mining as it moves from open pit to underground ore recovery.

More information

FDA OC/ORA Office Building

FDA OC/ORA Office Building FDA OC/ORA Office Building Table of Contents Executive Summary... 3 Introduction... 4 Structural System... 5 Foundation:... 5 Floor System:... 7 Building 31:... 7 Building 32:... 9 Columns... 10 Lateral

More information

Concrete Framing Systems - Walls and Columns

Concrete Framing Systems - Walls and Columns Concrete Framing Systems - Walls and Columns Casting a Concrete Wall Wall Footing Reinforcing Wall Forms Pouring Concrete Finishing the Concrete Controlling Cracking Insulating Concrete Forms (ICF) Tilt-Up

More information

Pro-Con Structural Study of Alternate Floor Systems

Pro-Con Structural Study of Alternate Floor Systems Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary

More information

Rock support testing in Luossavaara-Kiirunavaara AB s underground mines, Sweden

Rock support testing in Luossavaara-Kiirunavaara AB s underground mines, Sweden Deep Mining 2014 M Hudyma and Y Potvin (eds) 2014 Australian Centre for Geomechanics, Perth, ISBN 978-0-9870937-9-0 https://papers.acg.uwa.edu.au/p/1410_07_swedberg/ Rock support testing in Luossavaara-Kiirunavaara

More information

ADVANTAGES THE LIGHTEST FILLING SOLUTION HIGH LOAD-BEARING CAPACITY

ADVANTAGES THE LIGHTEST FILLING SOLUTION HIGH LOAD-BEARING CAPACITY SINGLE-USE FORMWORK SYSTEM UP TO 300 CM elevetor new the evolution of crawl space LOGISTICAL ADVANTAGES THE LIGHTEST FILLING SOLUTION HIGH LOAD-BEARING CAPACITY w w w. g e o p l a s t. i t BUILDING 02

More information

Park Potomac Office Building E

Park Potomac Office Building E Kyle Wagner (IP) Advisor: Professor Kevin Parfitt 12/11/2009 Table of Contents I. Executive Summary. 3 II. Introduction / Material Strengths. 4 III. Codes and Design Standards.. 5 IV. Existing Structural

More information

SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS

SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS ABSTRACT Megha Kalra Assistant Professor, The North Cap University, Gurgaon(India) Multistoreyed buildings are most affected by

More information

SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS

SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS SEISMIC ANALYSIS OF SIX STOREYED RC FRAMED BUILDING WITH BRACING SYSTEMS ABSTRACT Megha Kalra Assistant Professor, The North Cap University, Gurgaon(India) Multistoreyed buildings are most affected by

More information

mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE

mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE SECTION 1. mortarless Design Manual Part 1 (AS 3600:2009) Section 1 Page 1 AS 3600:2009 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE 1.1 Overview of AS 3600:2009 AS 3600:2009 is the latest Australian

More information

Hollow Core Slabs Applications

Hollow Core Slabs Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Hollow Core Slabs Applications Hollow Core Slabs Technology for the Precast and Prestressed Concrete Industry HOLLOW RESIDENTIAL,

More information

Good Construction Practices Part I

Good Construction Practices Part I Good Construction Practices Part I This report is solely for the internal use. No part of it may be circulated, quoted, or reproduced for distribution outside the company organization without prior written

More information

Council on Tall Buildings. and Urban Habitat BACKGROUND SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL

Council on Tall Buildings. and Urban Habitat BACKGROUND SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL BACKGROUND CATALOG SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL STEEL PLATE SHEAR WALL CONCLUSION BACKGROUND With the rapid development of our economy and advancement of

More information

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building Thayapraba M Civil Department, NIT Trichy, (India) ABSTRACT Designers have a huge number of choices

More information

Comparative Study of R.C.C and Steel Concrete Composite Structures

Comparative Study of R.C.C and Steel Concrete Composite Structures RESEARCH ARTICLE OPEN ACCESS Comparative Study of R.C.C and Steel Concrete Composite Structures Shweta A. Wagh*, Dr. U. P. Waghe** *(Post Graduate Student in Structural Engineering, Y.C.C.E, Nagpur 441

More information

Rock support in the Kiirunavaara Mine

Rock support in the Kiirunavaara Mine Ground Support 2013 Y. Potvin and B. Brady (eds) 2013 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-7-0 https://papers.acg.uwa.edu.au/p/1304_26_jacobsson/ Rock support in the Kiirunavaara

More information

Design Guidance for TAB-Deck Composite Slabs using SMD Metal Decking reinforced with ArcelorMittal Steel Fibres

Design Guidance for TAB-Deck Composite Slabs using SMD Metal Decking reinforced with ArcelorMittal Steel Fibres Design Guidance for TAB-Deck Composite Slabs using SMD Metal Decking reinforced with ArcelorMittal Steel Fibres Version 2 Revised October 2008 Design Guidance for TAB-Deck Composite Slabs using SMD Metal

More information

EVALUATION OF TIME-DEPENDENT BEHAVIOUR OF COMPOSITE CONCRETE SLABS WITH STEEL DECKING (AN EXPERIMENTAL STUDY)

EVALUATION OF TIME-DEPENDENT BEHAVIOUR OF COMPOSITE CONCRETE SLABS WITH STEEL DECKING (AN EXPERIMENTAL STUDY) VIII International Conference on Fracture Mechanics of Concrete and Concrete Structures FraMCoS-8 J.G.M. Van Mier, G. Ruiz, C. Andrade, R.C. Yu and X.X. Zhang (Eds) EVALUATION OF TIME-DEPENDENT BEHAVIOUR

More information

DESIGN AND ANALYSIS OF FOUR IN ONE SCHOOL COMPLEX

DESIGN AND ANALYSIS OF FOUR IN ONE SCHOOL COMPLEX DESIGN AND ANALYSIS OF FOUR IN ONE SCHOOL COMPLEX AHMED ABDULLAH AHMED MUQAIS 1, AAQIB FIRDOUS 2, ARNOLD PUKHRARAMBAM 3, D.MYTHILI 4 1,2,3UG Student,Department of Civil Engineering, Excel Engineering College.

More information

International Construction Consulting, LLC. Modularization Overview.

International Construction Consulting, LLC. Modularization Overview. International Construction Consulting, LLC Modularization Overview Presentation Overview 1 Modularization Overview 2 An Alternative Construction Method to Deliver Projects 3 Quick Selection Criteria for

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 03100 CONCRETE FORMWORK 1.0 GENERAL 1.1 DESCRIPTION This section defines requirements and limitations for design, construction, erection, and removal of concrete formwork for

More information

Product Information Bulletin

Product Information Bulletin Product Information Bulletin CCMC Evaluation Report 13101-R Advantage Insulating Concrete Forming (ICF) System BULLETIN NO. ISSUED: REPLACES: 201 November 25, 2010 January 2, 2009 Canadian Construction

More information

NATIONAL HARBOR BUILDING M

NATIONAL HARBOR BUILDING M NATIONAL HARBOR BUILDING M 120 Waterfront St. Oxon Hill, Maryland Ryan Sarazen Structural Option Senior Thesis Presentation Spring 2008 Faculty Consultant Dr. Lepage BUILDING LOCATION BUILDING M SITE PLAN

More information

SPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60

SPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60 SPECIFICATION FOR SECTION E60 A 2007-09-26 S.W. Revision Date Issue Authorised By Approved for Issue SW Date 24.09.07 clarkebond Page 1 of 6 To be read with Preliminaries/ General Conditions. GENERAL 10

More information

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

Prepared by Elie F. Issa, Eng. D.E.C. August 2016 Prepared by Elie F. Issa, Eng. D.E.C. August 2016 SAMA BEIRUT Sama Beirut is the tallest reinforced concrete tower in Lebanon soaring at a height of 220m from ground level Project Entities Owner Antonios

More information

6. Design of Portal Frames (For class held on 20 th, 26 th and 27 th March 07)

6. Design of Portal Frames (For class held on 20 th, 26 th and 27 th March 07) 6. Design of Portal Frames (For class held on 0 th, 6 th and 7 th March 07) By Dr. G.S.Suresh, Professor, Civil Engineering Department, NIE, Mysore (Ph:934188467, email: gss_nie@ yahoo.com) 3.1 Introduction:

More information

REINFORCED CONCRETE MASONRY SECTION

REINFORCED CONCRETE MASONRY SECTION SECTION 04 22 02 - REINFORCED CONCRETE MASONRY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CONSTRUCTION SUMMARY REPORT

CONSTRUCTION SUMMARY REPORT Edison Engineers Inc. 89 King Street W. Suite 3 Dundas (Hamilton) Ontario Canada L9H 1V1 Info@edisonengineers.ca CONSTRUCTION SUMMARY REPORT To: Halton Condominium Corporation No. 70 c/o Wilson Blanchard

More information

Continuous Beam Design with Moment Redistribution (CSA A )

Continuous Beam Design with Moment Redistribution (CSA A ) Continuous Beam Design with Moment Redistribution (CSA A23.3-14) Continuous Beam Design with Moment Redistribution (CSA A23.3-14) A structural reinforced concrete continuous beam at an intermediate floor

More information

KANPUR SMART CITY LIMITED

KANPUR SMART CITY LIMITED Nagar Nigam Mukhyalay, 3 rd Floor, Moti Jheel, Kanpur - 208002 Tel.: +91 512 2541258, 2546194 Email:ksclkanpur@gmail.com KANPUR SMART CTY LMTED No.: KSCL/PMC/Open Gym/01/2 Date: 17/02/2018 Reply to queries

More information

MCEER Hospital Demonstration Project

MCEER Hospital Demonstration Project 15 MCEER Hospital Demonstration Project Tsung Yuan Tony Yang Department of Civil, Structural & Environmental Engineering, University of Buffalo Research Supervisor: Andrew S. Whittaker, Associate Professor

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

Axial load behaviour of pierced profiled composite walls

Axial load behaviour of pierced profiled composite walls Axial load behaviour of pierced profiled composite walls K M Anwar Hossain, 1 BScEng, MScEng, PhD, MASCE, MIEPNG, MBCS, RegE This paper compares the behaviour of a novel form of pierced and non-pierced

More information

THE STUDY ON PRuDuLIluN AN L) S1KtNU1H OF ARCH PAN AS PERMANENT FORMWORK FOR FLOOR SLABS ZAID FIKRI BIN ZAINAL RASHID

THE STUDY ON PRuDuLIluN AN L) S1KtNU1H OF ARCH PAN AS PERMANENT FORMWORK FOR FLOOR SLABS ZAID FIKRI BIN ZAINAL RASHID PERPUSTAKAAN UMP U 110 I11I0I I 111 0 VIU 0000092396 THE STUDY ON PRuDuLIluN AN L) S1KtNU1H OF ARCH PAN AS PERMANENT FORMWORK FOR FLOOR SLABS ZAID FIKRI BIN ZAINAL RASHID A final year report submitted

More information

Structural Characteristics of New Composite Girder Bridge Using Rolled Steel H-Section

Structural Characteristics of New Composite Girder Bridge Using Rolled Steel H-Section Proc. Schl. Eng. Tokai Tokai Univ., Univ., Ser. ESer. E 41 (2016) (2016) - 31-37 Structural Characteristics of New Composite Girder Bridge Using Rolled Steel H-Section by Mohammad Hamid ELMY *1 and Shunichi

More information

Application of High Performance Concrete on a 85-story High Rise Building in Taiwan ABSTRACT

Application of High Performance Concrete on a 85-story High Rise Building in Taiwan ABSTRACT Application of High Performance Concrete on a 85-story High Rise Building in Taiwan Sy-Jye Guo * Tung-Ho Tsai** *Associate Professor, Dept. of Civil Engineering, National Taiwan University, Taiwan ** Project

More information

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? Chris Raison BEng MSc CEng MICE MASCE Raison Foster Associates Introduction A few

More information

ICBO Evaluation Service, Inc Workman Mill Road, Whittier, California

ICBO Evaluation Service, Inc Workman Mill Road, Whittier, California Reissued June 1, 2002 ICBO Evaluation Service, Inc. 5360 Workman Mill Road, Whittier, California 90601 www.icboes.org Filing Category: DESIGN Concrete DURISOL WALL FORMS FOR CONCRETE CONSTRUCTION DURISOL

More information

Redi Rock Specification and Installation Manual

Redi Rock Specification and Installation Manual Redi Rock Specification and Installation Manual 1.0 General Scope This Specification covers the Design, Materials and Installation of Redi Rock modular block Retaining and Freestanding Wall systems as

More information

PAN PAC PULPMILL TREATMENT TANK

PAN PAC PULPMILL TREATMENT TANK PAN PAC PULPMILL TREATMENT TANK B. PENG 1, M. ROMANES 2, P. GABY 1 1 Holmes Consulting Group 2 Concrete Structures (NZ) Ltd ABSTRACT The recently completed MBBR and AS tank is part of a multi-million dollar

More information

Beam-column joint tests with grade 500E reinforcing

Beam-column joint tests with grade 500E reinforcing Beam-column joint tests with grade 500E reinforcing L.M. Megget & N.J. Brooke Department of Civil & Environmental Engineering, University of Auckland, New Zealand. R.C. Fenwick Visitor, Department of Civil

More information

Construction Management Study

Construction Management Study Construction Management Study CONSTRUCTION MANAGEMENT STUDY A construction management study of the alternate concrete system was done to examine the impact that changing the building s superstructure material

More information

Health & Safety Policy and Procedures Manual SECTION 23 MASONRY CONSTRUCTION

Health & Safety Policy and Procedures Manual SECTION 23 MASONRY CONSTRUCTION SECTION 23 MASONRY CONSTRUCTION 1. Masonry Construction: A. Whenever a masonry wall is being constructed, a limited access zone will be established prior to construction meeting the following requirements.

More information

PAUL PARFITT. BAE/MAE Structural Option Senior Thesis Tower 333 May 4 th 2007

PAUL PARFITT. BAE/MAE Structural Option Senior Thesis Tower 333 May 4 th 2007 PAUL PARFITT BAE/MAE Structural Option Senior Thesis Tower 333 May 4 th 2007 Tower 333 Introduction Proposal Lateral System Redesign Elimination of Moment Frames Core-Only Solution Cost Analysis & Schedule

More information

EXPOMIN 2012, Santiago, Chile

EXPOMIN 2012, Santiago, Chile Caterpillar Global Mining Product Line Hard Rock CAT Rock Flow System Markus Frenzel 2012-04-11 EXPOMIN 2012, Santiago, Chile CAT Rock Flow System System Products CAT Rock Flow System Hard Rock Haulage

More information

CONCRETE BLOCK MASONRY

CONCRETE BLOCK MASONRY CONCRETE BLOCK MASONRY CONTENT Introduction Types Manufacturing process Properties Advantages Introduction These are the concrete blocks either hollow or solid. A hollow unit is that unit which has core

More information

STUDY ON SEISMIC PERFORMANCE OF LOW EARTHQUAKE RESISTANT MASONRY BUILDINGS RETROFITTED BY PP-BAND MESH

STUDY ON SEISMIC PERFORMANCE OF LOW EARTHQUAKE RESISTANT MASONRY BUILDINGS RETROFITTED BY PP-BAND MESH The 13th Japan Earthquake Engineering, Symposium (2010) STUDY ON SEISMIC PERFORMANCE OF LOW EARTHQUAKE RESISTANT MASONRY BUILDINGS RETROFITTED BY PP-BAND MESH Navaratnarajah SATHIPARAN 1 and Kimiro MEGURO

More information

mortarless masonry Design Manual Part 1 (IS 456:2000) Section 1 Page 1 IS 456:2000 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE

mortarless masonry Design Manual Part 1 (IS 456:2000) Section 1 Page 1 IS 456:2000 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE SECTION 1. mortarless masonry Design Manual Part 1 (IS 456:2000) Section 1 Page 1 1.1 Overview of IS 456:2000 IS 456:2000 PLAIN AND REINFORCED CONCRETE - CODE OF PRACTICE IS 456:2000 is the current Indian

More information

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION MANUAL FOR RAILROAD PROJECTS T-WALL railroad units are 5.0' high x 7.5' wide. (stem lengths will vary) The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION

More information

SECTION PORTLAND CEMENT CONCRETE

SECTION PORTLAND CEMENT CONCRETE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this

More information

Lessons learned: 3.2.Stability concepts

Lessons learned: 3.2.Stability concepts The contractor did not follow the contract requirement to limit the advancement of the uppermost lifted slabs to not more than three levels above the level of completed shear walls. Also, he did not provide

More information

CONCRETE & MASONRY SAFETY

CONCRETE & MASONRY SAFETY CONCRETE & MASONRY SAFETY Safety and Quality Relationship REINFORCING MISS-PLACED IN CONCRETE RESULTS IN WEAKEN STRUCTURE IMPROPER PLACEMENT OF LINTEL BEAMS INCORRECT MASONRY CEMENT OR GROUT MIX DESIGN

More information

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE

NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE NEW PERFORMANCE CRITERIA FOR FRESH TREMIE CONCRETE Karsten Beckhaus (1), Martin Larisch (2), Habib Alehossein (3,4) (1) BAUER Spezialtiefbau GmbH, Deutschland (2) Keller Australia Pty Ltd, Australia (3)

More information

Imaging Research Building

Imaging Research Building University of North Carolina s Imaging Research Building Thesis Proposal, LEED AP Structural Option Consultant- Dr. Thomas Boothby January 15, 2010 Table of Contents Executive Summary... 3 Architectural

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Structural Design: Goals: The original design of 200 Minuteman Drive was dictated largely by Brickstone Properties, the building s owner. The new design of 200 Minuteman Drive, with additional floors,

More information

Experimental Study on behavior of Interior RC Beam Column Joints Subjected to Cyclic Loading P.Rajaram 1 A.Murugesan 2 and G.S.

Experimental Study on behavior of Interior RC Beam Column Joints Subjected to Cyclic Loading P.Rajaram 1 A.Murugesan 2 and G.S. Experimental Study on behavior of Interior RC Beam Column Joints Subjected to Cyclic Loading P.Rajaram 1 A.Murugesan 2 and G.S.Thirugnanam 3 1 P.G.Student, Department of Civil Engineering, Institute of

More information

Study of Shear Walls in Different Locations of Multistoried Building with Uniform Thickness in Seismic Zone III

Study of Shear Walls in Different Locations of Multistoried Building with Uniform Thickness in Seismic Zone III Study of Shear Walls in Different Locations of Multistoried Building with Uniform Thickness in Seismic Zone III Ambreshwar 1, Mahesh D 2, Nithinchary 3, Satish Baag 4, Sachin 5 1,2 Assistant Professors,

More information

IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 08, 2016 ISSN (online):

IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 08, 2016 ISSN (online): IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 08, 2016 ISSN (online): 2321-0613 Retrofitting of Reinforced Concrete Frames using Steel Bracing Mohammed Hyderuddin 1

More information

SPECIAL SPECIFICATION 4491 Type CAC Concrete

SPECIAL SPECIFICATION 4491 Type CAC Concrete 2004 Specifications SPECIAL SPECIFICATION 4491 Type CAC Concrete 1. Description. Remove unsound concrete and replace with Type CAC, calcium aluminate concrete for ultra high early strength concrete repairs.

More information

An Investigation of Bond Strength in Straw Bale Construction

An Investigation of Bond Strength in Straw Bale Construction An Investigation of Bond Strength in Straw Bale Construction ID number: 32 Colin Smith, Research Associate, Colin MacDougall, PhD, P.Eng. Associate Professor (corresponding author) Department of Civil

More information

Precast concrete structures

Precast concrete structures Precast concrete structures History of prefarication early 20.century 1904 concrete precast panels system in Liverpool (house.12 flats) 1907 hollow wall and slab panels for low-storey family houses 1926

More information

Technical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design

Technical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design Executive Summary Technical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design The Food Science Building in State College, Pennsylvania is a four story above ground steel composite

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

Note on the assessment:

Note on the assessment: EXCERPTS Note on the assessment: The following is an excerpt from the book Post-disaster shelter: 10 Designs, IFRC, 2013. Inclusion of this design is for information purposes and does not necessarily imply

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

SHEAR OF CONCRETE MASONRY WALLS

SHEAR OF CONCRETE MASONRY WALLS 11 th Canadian Masonry Symposium, Toronto, Ontario, May 31- June 3, 2009 SHEAR OF CONCRETE MASONRY WALLS A.F. Oan 1 and N.G. Shrive 2 1 PhD Student, Department of Civil Engineering, University of Calgary,

More information

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE 001 First Draft W Hession 12.02.2014 Introduction This document

More information

Seismic Evaluation of the Historic East-Memorial Building Retrofitted with Friction Dampers, Ottawa, Canada

Seismic Evaluation of the Historic East-Memorial Building Retrofitted with Friction Dampers, Ottawa, Canada Seismic Evaluation of the Historic East-Memorial Building Retrofitted with Friction Dampers, Ottawa, Canada S. Jabbour & D.J. Carson Parsons Brinckerhoff Halsall Inc. SUMMARY: A seismic evaluation under

More information

REVISIONS. App Sud. App PC. App Thom AA 2014/10/28 AA 2014/11/24 AA 2015/06/24

REVISIONS. App Sud. App PC. App Thom AA 2014/10/28 AA 2014/11/24 AA 2015/06/24 1/5 REVISIONS Rev Description Rev n by Sud PC Thom VB LH Clyd Act Issue Date YYYY/MM/DD 1 New Specification 2014/10/28 2014/10/28 N/A N/A N/A N/A N/A N/A 2014/11/12 2 Drawing Revised See endix A 2014/11/24

More information

Concrete Framing systems. Design choices. Basic flavors

Concrete Framing systems. Design choices. Basic flavors Concrete Framing systems Design choices Site Cast Concrete gives a designer a lot of freedom in the design and construction of walls, columns and surface textures. When it comes to spanning, concrete offers

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Program Evaluation and Review Technique (PERT)

Program Evaluation and Review Technique (PERT) Program Evaluation and Review Technique (PERT) PERT Bar charts and CPM networks assume all activity durations are constant or deterministic. The assumption of constant durations may not be realistic because

More information

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations. DURA-CRETE S-SERIES PRECAST CONCRETE WALL SPECIFICATIONS PART 1 GENERAL 1.01 SECTION INCLUDES A. Concrete Screen Wall Description: Work under this item shall consist of furnishing and erecting a wall in

More information

STAY-FORM TRANSFORMING MATERIALS. into products that make a better world

STAY-FORM TRANSFORMING MATERIALS. into products that make a better world STAY-FORM TRANSFORMING MATERIALS into products that make a better world TABLE OF CONTENTS Product Information... Page 1 Blindside Walls...Pages 2-4 Bulkheads...Page 5 Pile Caps...Page 6 Grade Beams...

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

Integration of Sustainable Structural Elements and Evaluating Mechanical System Effects

Integration of Sustainable Structural Elements and Evaluating Mechanical System Effects Integration of Sustainable Structural Elements and Evaluating Mechanical System Effects Mike Hopple Structural Option AE Senior Thesis Spring 2008 Penn State University Presentation Outline 1. North Mountain

More information

Winding systems and construction equipment for ultra-deep shaft sinkings: examples based on the ongoing WS-10 and SKS-1 projects in Norilsk

Winding systems and construction equipment for ultra-deep shaft sinkings: examples based on the ongoing WS-10 and SKS-1 projects in Norilsk Pic. left: WS-10 shaft headframe is highlighted against the Polar night Pic. right: SKS-1 shaft facilities Winding systems and construction equipment for ultra-deep shaft sinkings: examples based on the

More information

SPECIFICATION FOR JET GROUTING

SPECIFICATION FOR JET GROUTING SPECIFICATION FOR JET GROUTING 1.0 GENERAL The Specialist Contractor shall construct jet grout columns of nominal diameter and spacing as specified in the drawing(s) to the requirements of the Contract.

More information

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES BOUNDARY FENCING C265 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C265 ISSUE: NO:1 October 2007 TABLE OF CONTENTS CLAUSE CONTENTS PAGE

More information

Lateral System Analysis and Confirmation Design

Lateral System Analysis and Confirmation Design Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY November 15, 2004 Pictures courtesy of Fox & Fowle Architects Lateral System Analysis and Confirmation Design Executive Summary This

More information

SDCS-02 CONSTRUCTION STANDARD FOR

SDCS-02 CONSTRUCTION STANDARD FOR الشركة السعودية للكهرباء DATE: November 2016 CONSTRUCTION STANDARD FOR UNDERGROUND DISTRIBUTION NETWORK This specification is property of SEC and subject to change or modification without any notice الشركة

More information

Alternate Formwork System Evaluation

Alternate Formwork System Evaluation Alternate Formwork System Evaluation Executive Summary The current handset aluminum formwork system used in the Navy League Building s parking garage is a labor and material (plywood) intensive process.

More information

[THESIS PROPOSAL] North Hall American University Washington, D.C.

[THESIS PROPOSAL] North Hall American University Washington, D.C. 2013 Brandon Tezak, LEED Green Associate Construction Management Option Faculty Advisor: Dr. Anumba January 9, 2013 [THESIS PROPOSAL] North Hall American University Washington, D.C. Executive Summary After

More information

Terra Technologies LLC. Company Overview

Terra Technologies LLC. Company Overview Terra Technologies LLC Company Overview Terra Technologies LLC Terra Technologies LLC was founded on the core principle that most utility conflicts and utility replacements encountered in roadway construction

More information

A Review Paper on Shotcrete Technology

A Review Paper on Shotcrete Technology A Review Paper on Shotcrete Technology Aditya Tripathi Student Researcher Delhi Technological University, Delhi Email: adityatripathi3107@gmail.com Kushagra Gahlaut Student Researcher Delhi Technological

More information

Concrete. Chapter 10 Properties of Fresh Concrete. Materials of Construction-Concrete 1. Wikipedia.org

Concrete. Chapter 10 Properties of Fresh Concrete. Materials of Construction-Concrete 1. Wikipedia.org Wikipedia.org Concrete Chapter 10 Properties of Fresh Concrete Materials of Construction-Concrete 1 What is Concrete? Concrete is a composite material that consists of a cement paste within which various

More information

Strengthening or Retrofitting

Strengthening or Retrofitting Post-earthquake School Reconstruction Project Workshop on Earthquake Resilient Design for School Buildings Day-2 Session 4 Strengthening or Retrofitting Chandani Chandra Neupane Various Terms used with

More information

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Table of Contents 1. Executive Summary.....Page 2 2. Existing Floor System....Page 4 2.1. Composite steel beams with composite

More information

Building Construction

Building Construction Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When

More information

Lecture 13 CONCRETE WORKS

Lecture 13 CONCRETE WORKS Lecture 13 TSP-308 MPK Ferdinand Fassa CONCRETE WORKS Concrete works Concrete is a man-made (rock) construction material, which is a mixture of portland cement, water, aggregates, and in some cases, admixtures.

More information

Rapid mine development using efficient in-cycle shotcrete

Rapid mine development using efficient in-cycle shotcrete Caving 2018 Y Potvin and J Jakubec (eds) 2018 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-9-4 https://papers.acg.uwa.edu.au/p/1815_59_erismann/ F Erismann Sika Services AG, Switzerland

More information

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

PPC PRODUCT BROCHURE PPC prod brochure portrait 2017_1.indd /04/11 3:09:48 PM

PPC PRODUCT BROCHURE PPC prod brochure portrait 2017_1.indd /04/11 3:09:48 PM PPC PRODUCT BROCHURE C prod brochure portrait 2017_1.indd 1 2017/04/11 3:09:48 PM PPC is a proudly South African business, founded in 1891. With more than 100 years of experience and a large footprint

More information

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 1 of 23 The following presentation discusses

More information

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information