1 Audio Presentation Session 1 FUNDAMENTALS Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and The Construction Specifications Institute is prohibited. The Construction Specifications Institute AIA The Construction Specifications Institute is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 2 1

2 Learning Objectives To understand the composition and responsibilities of four Project Teams who come together as a single Team. To gain an insight into the definitions of the various stages of the life cycle of a facility, the activities and documents produced during each stage, and team member responsibilities. To introduce the basic relationship between drawings and specifications and to emphasize the importance of coordination. To introduce the basic structure of OmniClass TM, UniFormat TM, and MasterFormat TM and the primary ways in which they are utilized in construction documents. To understand the basic concepts of the environmental impact of buildings, sustainability, GreenFormat TM, and green building. The Construction Specifications Institute 3 Session Outline STUDY GUIDE: Subject Matter Area No. 1 - FUNDAMENTALS A. Job roles and responsibilities of the four Project Teams B. Factors that contribute to an effective team C. Stages of Facility Life Cycle with associated activities and documents D. Project stages with associated activities and documents E. OmniClass TM F. UniFormat TM G.MasterFormat TM H. 4 C s of communication I. Legal interpretations and/or conflicts of Contract Documents J. GreenFormat TM K. Sustainability/Green Building The Construction Specifications Institute 4 2

3 FUNDAMENTALS STUDY GUIDE AREA NO. 1 The Construction Specifications Institute 5 JOB ROLES AND RESPONSIBILITIES OF THE FOUR PROJECT TEAMS STUDY GUIDE: Subject Matter Area No. 1 - A. The Construction Specifications Institute 6 3

4 Stakeholders and Participants Design and construction merges Collective Needs Ideas Talents Knowledge Services Widely diverse group Individuals Organizations Specialized services Stakeholders Individuals or organizations Major Project involvement Interests positively or negatively affected by the constructed facility Investment Operational Reputation Example: stockholders owner

5 Participants Individuals or organizations Minor Project involvement Interests not affected by the constructed facility Example: Product representative or Authority Having Jurisdiction Owner Team Project Team Composition Design Team Contractor Team Supplier Team

6 Owner Team Responsibilities Initiates Project Assumes risk Provides funding Controls, manages, approves Occupies facility Owner Team Project Types Private Public Funding not from taxation Funding from taxation Individuals Federal Businesses State Developers County City Town Other Authorities and

7 Financial institutions Attorneys Insurance companies Owner Team Advisors Real estate agents Appraisers Marketing companies Owner Team Owner s Consultants Surveyors Environmental engineers Geotechnical engineers Hazardous materials / abatement Traffic engineers Sustainability Wetland biologists Wildlife biologists

8 Occupants Facility manager Facility users Visitors Owner Team Others Utility service providers Authorities Having Jurisdiction through Transforming Owner s vision and requirements into a design and construction documentation Includes multiple design disciplines Specialized design services and expertise Design Team Responsibilities

9 Principal-in-Charge Project Manager Programmer Project Designer Interior Designer Project Captain Drafter Specifier Construction Administrator Design Team Architect Design Team Engineers and Consultants Civil Engineer Structural Engineer Mechanical Engineer Electrical Engineer Plumbing Engineer Landscape Architect Fire Protection Engineer Exterior Enclosure Consultant Roofing and Waterproofing Consultant Cost Estimator thru

10 Design Team Engineers and Consultants Code Consultant Sustainability Consultant Commissioning Consultant Food Service Consultant Parking Consultant Acoustical Consultant Lighting Design Consultant Building Transportation Consultant Swimming Pool, Fountain, and Water Feature Consultant Building Maintenance Equipment Consultant thru Contractor Team Responsibilities Transforms construction documentation into a finished facility Cost estimating Time scheduling Contracting Procurement (Bidding, Negotiating, Purchasing) Management of construction

11 Contractor Principal-in-Charge Project Manager Estimators Supervisors Accountants Layout Technician Safety Director Sustainability Consultant Subcontractor Contractor Team Roles and Supplier Team Responsibilities Furnishes materials and products necessary to construct Project Manufacturer Distributor Supplier Fabricator

12 Supplier Team Forms of Representation Manufacturer s employees Sales Marketing Technical Independent sales representation Supplier Team Assets Dual nature of representation Consultant Sales Valuable to Owner, Design, and Contractor Teams

13 FACTORS THAT CONTRIBUTE TO AN EFFECTIVE TEAM STUDY GUIDE: Subject Matter Area No. 1 - B. The Construction Specifications Institute 25 When is a Project Team Effective? Participants and stakeholders work toward mutual goals Project delivered on time and in budget Satisfied Owner I would add: and everyone else

14 Partnering and Collaboration Partnering (proactive problem solving) Concept of team building Helps ensure cooperative efforts Priorities and goals set Attempts to make participants and stakeholders into partners Collaboration Individuals working as a team Benefits of Working as a Team Better communications and coordination Understand extent of contractual rights and responsibilities and effectively and ethically perform Work fairly, efficiently, and swiftly to solve problems through communications Increased productivity Reduced Project costs Earlier Project completion Improved Project Team morale Fewer claims and delays

15 Obstacles to Working as a Team Adversarial relationships and personalities Incomplete or inaccurate Contract Documents Unreasonable schedule requirements Inordinate number of changes Labor issues Delays in fabrication or delivery Poor communications Ineffective management Integrated Project Delivery (IPD) Good Example of Effective Team Mutual respect Mutual benefit and reward Collaborative innovation and decision making Early involvement of key participants Early goal definition Intensified planning Open communications Appropriate technology Organization and leadership AIA IPD Guide and

16 STAGES OF FACILITY LIFE CYCLE WITH ASSOCIATED ACTIVITIES AND DOCUMENTS STUDY GUIDE: Subject Matter Area No. 1 - C. The Construction Specifications Institute 31 Facility Life Cycle 3.4 and Figure

17 Facility Life Cycle Project Conception Owner identifies need Completes planning activities to verify feasibility Secures financial resources Develops a facility program Identifies a site Facility Life Cycle Project Delivery Owner determines method to be used Assembles a Project Team

18 Facility Life Cycle Design Project Team evaluates following to seek issues and form design solutions Preliminary studies Collected data Program requirements Budget Schedule Project Team prepares and documents Schematic design and preliminary project descriptions Design development and outline specifications Facility Life Cycle Construction Documents A/E Team prepares graphic and written documents Pricing Regulatory approvals Construction

19 Facility Life Cycle Procurement (Bidding/Negotiating/Purchasing) Project cost is determined Prior to In conjunction with Following construction document development Depends on Project Delivery Method selected Facility Life Cycle Construction Project is constructed according to Contract Documents Regulatory requirements

20 Facility Life Cycle Facility Management Facility Manager manages and assumes control Facility placed in service Operations and maintenance procedures PROJECT STAGES WITH ASSOCIATED ACTIVITIES AND DOCUMENTS STUDY GUIDE: Subject Matter Area No. 1 - D. The Construction Specifications Institute 40 20

21 Project Distinction between PROJECT and FACILITY Process of planning, designing, documenting, procuring, contracting, and constructing Goal of a Project is a facility Object of delivery process Delivery process itself Facility Completed Project intended for a specific purpose and function Quality of each Project is Unique Quality is a balance between Extent (Scope) Cost (Budget) Time (Schedule) and Figure

22 Design Stage All projects proceed through following phases of design Design development Schematic design Conceptual design 3.4 and Master planning Design Stage Design Variations Design of multiple projects Integrated and complementary functions Same or contiguous site Prototype design Single design developed Multiple projects Different sites Consistent identity and purpose

23 Design Stage Conceptual Design Not an official phase, but is common Concept Representations of abstract object, creatively given Shape Form Meaning Design Journey of exploring and defining possibilities and constraints by using critical thinking skills Design Stage Conceptual Design Documentation Drawings of basic information Physical or electronic massing models Narrative descriptions

24 Design Stage Schematic Design Site plan and area relationships Spatial relationships and functional characteristics General size, shape, volume, massing of building elements Elevations and exterior finishes Basic information about structural and services Design Stage Schematic Design Documentation Sketches and drawings in more detail than conceptual documentation Physical or electronic models Preliminary project descriptions

25 Design Stage Design Development Size and character fixed Technical issues of constructability Integration of structural and services Definition of Materials Surfaces Details Design Stage Design Development Documentation More precise and specific drawings Physical or electronic models Outline specifications

26 Construction Documents Stage Depends on Project Delivery Method Defines following among parties Rights Responsibilities Relationships Graphic and written technical information necessary for procurement and construction Construction Documents Stage Standardization MasterFormat TM SectionFormat TM PageFormat TM National CADD Standard Building Information Modeling Standard contracts and forms by professional organizations

27 Construction Documents Stage Documentation Drawings Specifications Procurement requirements Contracting requirements and Figure OMNICLASS TM STUDY GUIDE: Subject Matter Area No. 1 - E. The Construction Specifications Institute 54 27

28 Multi-table framework for Organizing information Serving participants who work To sustain built environment Throughout Facility Life Cycle OmniClass TM Derived from internationally accepted standards developed by International Organization for Standards (ISO) Construction Entities by Function 12 Spaces by Function 13 Construction Entities by Form 14 Spaces by Form 21 Elements 22 Work Results OmniClass TM Tables 23 Products 31 Phases 32 Services 33 Disciplines 34 Organizational Roles 41 Information 42 Materials 49 - Properties

29 OmniClass TM Tables 11-Construction entities by function Learning Facilities Human Arts College 12- Construction entities by form Auditorium 13- Spaces by function General Performance Spaces Auditorium 14-Spaces by form Fully enclosed spaces Auditorium 57 UNIFORMAT TM STUDY GUIDE: Subject Matter Area No. 1 - F. The Construction Specifications Institute 58 29

30 UniFormat TM Developed by CSI Uniform classification system for organizing preliminary construction information into a standard order or sequence on basis of systems and assemblies UniFormat TM Project Description Categories and Figure

31 UniFormat TM Example of Levels 1 A Substructure 2 A10 Foundations 3 A1010 Standard Foundations 4 A Wall Foundations 5 A CF Continuous Foundations UniFormat TM Example of Use Autodesk s Revit using 3 rd level designations for categorizing objects C1020 Single Flush Door 62 31

32 MASTERFORMAT TM STUDY GUIDE: Subject Matter Area No. 1 - G. The Construction Specifications Institute 63 MasterFormat TM Developed by CSI Organization structural for the subject matter for construction of a project, and operation, and maintenance of a facility

33 MasterFormat TM Master list of numbers and titles Arranges related construction practices or work results Different types of construction addressed equally Promotes standardization Facilitates organization of information Improves construction communications Divisions MasterFormat TM 50 division format Not organized around traditional subcontracts or construction trades Follows logical groupings of work results Sections 6 digit numbers (some 8) Section covers one portion of work results Different Consistent

34 Procurement and Contracting Requirements Group 00 Procurement and Contracting Requirements Specifications Group General Requirements Subgroup 01 General Requirements MasterFormat TM Divisions Facility Construction Subgroup 02 Existing Conditions 03 Concrete 04 Masonry 05 Metals 06 Wood, Plastics, and Composites 07 Thermal and Moisture Protection 08 Openings 09 Finishes 10 Specialties 11 Equipment Furnishings 13 Special Construction 14 Conveying Equipment 15 thru 19 Reserved Facility Services Subgroup 20 Reserved 21 Fire Suppression 22 Plumbing 23 Heating, Ventilating, and Air Conditioning 24 Reserved MasterFormat TM Divisions 25 Integrated Automation 26 Electrical 27 Communications 28 Electronic Safety and Security 29 Reserved Site and Infrastructure Subgroup 30 Reserved 31 Earthwork 32 Exterior Improvements 33 Utilities 34 Transportation 35 Waterway and Marine Construction 68 34

35 36 thru 39 Reserved Process Equipment Subgroup 40 Process Integration 41 Material Processing and Handling Equipment 42 Process Heating, Cooling, and Drying Equipment 43 Process Gas and Liquid Handling, Purification and Storage Equipment 44 Pollution and Waste Control Equipment MasterFormat TM Divisions 45 Industry-Specific Manufacturing Equipment 46 Water and Wastewater Equipment 47 Reserved 48 Electrical Power Generation 49 Reserved MasterFormat TM Levels of Details 1 The 50 Divisions 2 Broad Scope Sections widest latitude of information 3 Medium Scope Sections more limited information 4 Narrow Scope Sections specific information 5 Very Narrow Scope Sections user defined

36 MasterFormat TM Example of Levels 1 Division 04 - Masonry 2 Section Unit Masonry (Broad Scope) 3 Section Clay Unit Masonry (Medium Scope) 4 Section Brick Masonry (Narrow Scope) 5 Section Brick Veneer Masonry (Very Narrow Scope) FOUR C s OF COMMUNICATION STUDY GUIDE: Subject Matter Area No. 1 - H. The Construction Specifications Institute 72 36

37 Four C s of Communication Proper grammar Simple sentence construction Avoid ambiguity Clear Correct Accurate and precise information Selected words to convey exact meanings Eliminate unnecessary words, but not at expense of clarity, correctness, or completeness Concise Complete Important information not left out LEGAL INTERPRETATION AND/OR CONFLICTS OF CONTRACT DOCUMENTS STUDY GUIDE: Subject Matter Area No. 1 - I. The Construction Specifications Institute 74 37

38 5.10 Important Legal Issues Need for a written Historical Record Professional Standard of Care Professional Negligence Compliance with Building Codes, Laws and Regulations Spearin Doctrine The contractor is entitled to rely on the construction documents provided by the owner to be sufficient for their intended purpose and is NOT responsible for the consequences of defects (errors, inconsistencies or omissions) in the documents Actions can change the terms of a contract Interpretation by the courts. 75 Design Team Coordination Effective coordination requires Good coordination Attention to detail Reviewing interface between design disciplines Sufficient number of decisions proportionate for stage of Work

39 Components of Successful Coordination Organization Selecting team members Establishing management procedures Execution Project design Production of construction documents Quality Assurance Meetings Checklists Communications Checking and crosschecking construction documents Components of Incomplete Coordination Duplications Omissions Discrepancies Division 01 not coordinated Terminology differences

40 Critically Important Relationships Representation of design concept shown on construction documents among multiple design disciplines Architectural design with other design disciplines Drawings and specifications Coordinating Drawings and Specifications Drawings and specifications are complementary Coordination must occur at all levels of Project Team Drawings detail should be consistent with specification detail Clear, concise, correct, and complete are critically important

41 Characteristics of Drawings Indicates generic and graphic representation of products and Materials Size Form Location Quantity Relationships Generic representations and Characteristics of Specifications Defines qualitative requirements for Product, materials, equipment Physical properties of products Performance requirements Standards of workmanship Describes administrative procedures

42 GREENFORMAT TM STUDY GUIDE: Subject Matter Area No. 1 - J. The Construction Specifications Institute 83 GreenFormat TM Developed by CSI Web based tool that allows manufacturers to accurately report product sustainability properties Provides designers, constructors, and building operators with basic information to help meet green requirements

43 Background information Product details Product lifecycle Additional information Authorization GreenFormat TM Categories 85 SUSTAINABILITY/GREEN BUILDING STUDY GUIDE: Subject Matter Area No. 1 - K. The Construction Specifications Institute 86 43

44 Environmental preservation has become an important issue Public policy Private enterprise Sustainability Sustainability EPA Sustainable building involves Developing healthier methods of construction, operations, and demolition Using resources more efficiently ASTM E 2114 Standard Terminology for Sustainability Relative to the Performance of Buildings defines green building as One that meets specified performance requirements While minimizing disturbance to and improving the functioning of local, regional, and global ecosystems During and after its construction and specified service life

45 Sustainable Design Emphasis on environmental performance of a facility over its life cycle Fundamental approaches common to tools and assessments Site optimization Use of energy Water use Building materials and products Indoor environmental quality Optimizing operational and maintenance practices Environmental Design Tools Various tools available for use by product manufacturers, Contractors, and A/E s NIST s BEES Building for Environmental and Economic Sustainability EPA s Energy Star Program USGBC s LEED Program

46 Assessing Product Sustainability Requires life cycle assessment by a qualified agency NIST s BEES (Building for Environmental and Economic Sustainability) Model is one method Global warming potential Acidification Nitrification potential Natural resource depletion Solid waste produced Indoor air quality Another is ASTM E 2129 Standard Practice for Data Collection for Sustainable Assessments of Building Products Assessing Facility Sustainability Methods of assessing environmental performance USGBC s LEED Green Building Rating System Advanced Buildings Green Guidelines for Healthcare Construction Green Globes Greenguard Environmental Institute Stars

47 Product Evaluation Sustainability attributes is one of many categories for evaluation of products Low embodied energy Recyclability, material reuse, or salvaged Natural or renewable resources Locally or regionally produced Energy efficiency Low environmental impact Durability Recycled content Waste minimization Promotes good indoor air quality Absence of unhealthful chemicals, toxic substances, or volatile organic compounds Biodegradable or bio-based composition Conservation of resources Responsible wood supplies Review Outline STUDY GUIDE: Subject Matter Area No. 1 - FUNDAMENTALS A. Job roles and responsibilities of the four Project Teams B. Factors that contribute to an effective team C. Stages of Facility Life Cycle with associated activities and documents D. Project stages with associated activities and documents E. OmniClass TM F. UniFormat TM G.MasterFormat TM H. 4 C s of communication I. Legal interpretations and/or conflicts of Contract Documents J. GreenFormat TM K. Sustainability/Green Building The Construction Specifications Institute 94 47

CONSTRUCTION DOCUMENTS Part 1

CONSTRUCTION DOCUMENTS Part 1 Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

Audio Presentation. Session 3 DESIGN. Project Delivery Education Program. Construction Document Technology (CDT) Preparatory Course

Audio Presentation. Session 3 DESIGN. Project Delivery Education Program. Construction Document Technology (CDT) Preparatory Course Audio Presentation Session 3 DESIGN Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 www.csinet.org This presentation is protected by US and International

More information

ROLES AND RESPONSIBILITIES

ROLES AND RESPONSIBILITIES Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

Construction Administration: Contact, Contract or Crisis? AIA St. Louis CONTINUING EDUCATION WORKSHOPS

Construction Administration: Contact, Contract or Crisis? AIA St. Louis CONTINUING EDUCATION WORKSHOPS Construction Administration: Contact, Contract or Crisis? Presented by the St. Louis Chapters of the: AMERICAN INSTITUTE OF ARCHITECTS CONSTRUCTION SPECIFICATIONS INSTITUTE AIA St. Louis CONTINUING EDUCATION

More information

Design Review Process FACILITY OPERATIONS

Design Review Process FACILITY OPERATIONS Design Review Process FACILITY OPERATIONS DESIGN REVIEW LEAN TEAM AUGUST 2016 CONTENTS Introduction...3 Participants...3 Design Reviewers Facility Operations...4 Providing Feedback...5 Design Review Sessions...6

More information

The New MasterFormat TM & Your HVAC Business

The New MasterFormat TM & Your HVAC Business SMACNA & SMWIA 2006 Partners In Progress Conference Las Vegas/March 30, 2006 The New MasterFormat TM & Your HVAC Business Thomas E. Glavinich, D.E., P.E. Civil, Environmental, & Architectural Engineering

More information

Eastern Michigan University

Eastern Michigan University Eastern Michigan University Prepared by: EMU Physical Plant Facilities Planning and Construction Page Intro-1 Purpose of Eastern Michigan University Physical Plant; Facilities Planning and Construction

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

Audio Sessions. Session 5 MEETINGS. Construction Contract Administration Education Program

Audio Sessions. Session 5 MEETINGS. Construction Contract Administration Education Program Audio Sessions Session 5 MEETINGS Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org This presentation

More information

Thoughts on Managing Site Visits

Thoughts on Managing Site Visits Hanover Architects & Engineers Advantage Thoughts on Managing Site Visits Construction phase services are an important element of any design contract involving construction. Design documents cannot be

More information

Note year for Reference as Specified in the LEED V Manual.

Note year for Reference as Specified in the LEED V Manual. PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Sustainable design Project goals. 2. Sustainable design product requirements. B. Related Sections: 1. Section 01810 - Commissioning: General commissioning

More information

Ex AC. Examination for Architects in Canada Examen des architectes du Canada

Ex AC. Examination for Architects in Canada Examen des architectes du Canada Ex AC Examination for Architects in Canada Examen des architectes du Canada General and Specific Objectives Theme 1 general objective specific objectives rogramming 1.1 Understand the process for the preparation

More information

Involving Stakeholders in the Professional s Design and Construction Process

Involving Stakeholders in the Professional s Design and Construction Process Involving Stakeholders in the Professional s Design and Construction Process Presented By: Peter Trozze, AIA Managing Director of Middle Eastern Operations Continuing Education The Middle East Chapter

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Attachment 8 Statement of Work (SOW)

Attachment 8 Statement of Work (SOW) Attachment 8 Statement of Work (SOW) The following requirements are necessary for successful implementation of the contract for the proposer to provide design A/E services to assist the County in the Development

More information

Construction Specifition takeoff.com/

Construction Specifition  takeoff.com/ Construction specifications Construction Specifition A specification (often abbreviated as spec) can be termed as a type of a technical standard to be referenced by a contract or procurement document.

More information

INCORPORATING LEED INTO PROJECT SPECIFICATIONS. Session 2

INCORPORATING LEED INTO PROJECT SPECIFICATIONS. Session 2 INCORPORATING LEED INTO PROJECT SPECIFICATIONS Session 2 THE CONSTRUCTION SPECIFICATIONS INSTITUTE Incorporating LEED into Project Specifications, Part 2 1.5 AIA The Construction Specifications Institute

More information

Avoiding Specification Pitfalls!

Avoiding Specification Pitfalls! 1 Continuing Education This program is a registered provider with The American Institute of Architects Continuing Education Systems. Credit Earned on completion of this program will be reported to CES

More information

National Standard of Competency for Architects

National Standard of Competency for Architects The (NSCA) Architecture Program Accreditation Procedure The AACA manages the accreditation of architecture programs and administers the on behalf of the architect registration boards. The Accreditation

More information

Efficiently Produced Construction Documents are Quality Construction Documents

Efficiently Produced Construction Documents are Quality Construction Documents Efficiently Produced Construction Documents are Quality Construction Documents Creative Disruption - AIA Minnesota November 13, 2015; 10:15 am 11:45 am Micheal J. Lough Good design makes a difference CES

More information

Learning Objectives. The Role of LCA in Green Building Design and Assessment: Focusing on True Environmental Performance Measures

Learning Objectives. The Role of LCA in Green Building Design and Assessment: Focusing on True Environmental Performance Measures The Role of LCA in Green Building Design and Assessment: Focusing on True Environmental Performance Measures Program Education Credit Information Wood Products Council and the Wood Solutions Fair is a

More information

What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems

What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems What happened to Division 17? and what is CLA? A Strategic Plan for Communications, Life Safety and Building Automation Systems Discussion Points History of MasterFormat and CLA CLA Consultant What BICSI

More information

BSc. BE & CM Courses Brief Description

BSc. BE & CM Courses Brief Description BSc. BE & CM Courses Brief Description 2801010-BUILDING MATERIALS, (3, 0, 0: 3) This course will cover the engineering properties of basic and modern building materials to materials such as plastics, synthetic

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Document Synopses by Series

Document Synopses by Series Document Synopses by Series AIA Contract Documents are divided into six alphanumeric series by document use or purpose: A Series: Owner/Contractor Agreements B Series: Owner/Architect Agreements (p. 13)

More information

2008 Questions & Solutions Engineering, Inc.

2008 Questions & Solutions Engineering, Inc. BNP Media is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates

More information

Best Practices Manual

Best Practices Manual Best Practices Manual Canada, C1A 7L3 Page 1 of 18 Table of Contents Introduction 0 Division 00 - Bid Documents 0.1 Alternate Bids 0.2 To be developed 1 Division 01 - General Requirements 1.1. Tender Document

More information

FACILITY INVENTORY: GET WHAT YOU ASK FOR by William Faesenmeier

FACILITY INVENTORY: GET WHAT YOU ASK FOR by William Faesenmeier FACILITY INVENTORY: GET WHAT YOU ASK FOR by William Faesenmeier A comprehensive inventory of a facility is the foundation of any facility asset management program. Due to limitations of staff, qualifications

More information

Copyright Materials. Learning Objectives

Copyright Materials. Learning Objectives Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited.

More information

- DATA REQUIREMENTS BIM

- DATA REQUIREMENTS BIM UHS BIM Protocol S E C T I O N 1 - DATA REQUIREMENTS BIM authoring software: The design team is required to use parametric BIM authoring software for creation of models that include all geometry, physical

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program?

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program? What is the Architectural Experience Program? The Architectural Experience Program (AXP ) is an essential step in the path to becoming an architect. Through the AXP, you will learn about the daily realities

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

A. Section Includes: 1. [Hydraulic] [Traction] [Variable Voltage-Variable Frequency] Elevators.

A. Section Includes: 1. [Hydraulic] [Traction] [Variable Voltage-Variable Frequency] Elevators. This is a guidance document with sample specification language intended to be inserted into project specifications on this subject as appropriate to the agency's environmental goals. Certain provisions,

More information

Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS

Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute

More information

BIM Checklist. Introduction

BIM Checklist. Introduction Introduction This Building Information Modeling (BIM) Checklist is intended to be used as a guide for project stakeholders who are looking to implement BIM/VDC in a design-build project. Since integration

More information

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois. University of Illinois

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois. University of Illinois Keys to success: Sustainable design strategies included early. Clear and early benchmarking choice. Integrated design process. Consensus building. Keys to success: Sustainable design strategies considered

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction, manages a full range of challenging projects to design or construct park or recreation facilities as a Registered Professional Architect; works fully proficiently as

More information

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC.

SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA EDWARD TUCKER ARCHITECTS, INC. SUSTAINABLE ARCHITECTURAL DESIGN JOSH DYGERT, AIA WHAT DOES IT MEAN TO BE GREEN? Sustainable of, or relating to, or being a method of harvesting or using a resource so that the resource is not depleted

More information

NAME OF PROJECT Design Development. General Objectives of Phase. Phase Task Checklist. Quality Management Phase

NAME OF PROJECT Design Development. General Objectives of Phase. Phase Task Checklist. Quality Management Phase General Objectives of Phase Drawings and other documents to fix and describe the size and character of the project as to architectural, structural, mechanical and electrical systems, materials and such

More information

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT PROJECT MANUAL RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT CITY OF RICHMOND Richmond, Virginia Architect s Project No. 563107 ARCHITECT/ENGINEER RICHMOND, VIRGINIA A/E s Project No. 563107 set

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

Longmeadow High School Section 12.1

Longmeadow High School Section 12.1 Longmeadow High School Section 12.1 Schematic Design 12 Total Project Budget and MSBA Form 3011 The attached Total Project Budget and Form 3011 includes all costs associated with Administrative, Architecture

More information

INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL BUSINESS OFFICIALS ( MSBO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION

INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL BUSINESS OFFICIALS ( MSBO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION INSTRUCTIONS FOR USING THE MICHIGAN SCHOOL USINESS OFFICIALS ( MSO ) PROTOTYPE FORM OWNER/ARCHITECT AGREEMENT WITH CONSTRUCTION MANAGER COORDINATION Please be advised that the purpose of this Instruction

More information

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3

More information

Exhibit A Scope of Services and Deliverables

Exhibit A Scope of Services and Deliverables Exhibit A Scope of Services and Deliverables Attachment to MnDOT Contract No. for Project Name Project # 16-TZ dated Scope of Services includes: Programming / Schematic Design Phase Design Development

More information

POSITION DESCRIPTION June 16, 2017

POSITION DESCRIPTION June 16, 2017 POSITION DESCRIPTION June 16, 2017 Common Name: Classification: Team / Section: Bureau / Division: ROOFING / BUILDING ENVELOPE PROJECT MANAGER ENGINEERING SPECIALIST MANAGEMENT Project Delivery Services

More information

GREENING EXISTING FEDERAL BUILDINGS:

GREENING EXISTING FEDERAL BUILDINGS: P a g e 1 GREENING EXISTING FEDERAL BUILDINGS: EXECUTIVE ORDERS, GUIDING PRINCIPLES AND ENERGY STAR S PORTFOLIO MANAGER Conrad T. Kelso, PE, CEM, LEED AP O+M Facility Engineering Associates, P.C. 12701

More information

An Introduction To BIM INTEGRATED Architectural Specifications

An Introduction To BIM INTEGRATED Architectural Specifications An Introduction To BIM INTEGRATED Architectural Specifications WHAT ARE SPECIFICATIONS? Specifications are documents that accompany and govern the construction of a building. The guiding library of master

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year Two Thousand and BETWEEN the Architect s client identified as the Owner: Capitol

More information

Educational Use Only S A M P L E S A M P L E

Educational Use Only S A M P L E S A M P L E CONSENSUSDOCS 240 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER This document was developed through a collaborative effort of entities representing a wide cross-section of the construction

More information

FACILITIES DESIGN STANDARDS

FACILITIES DESIGN STANDARDS FACILITIES DESIGN STANDARDS 7th Edition June 21, 2016 Use only the most current copy of these Design Standards. Most current Edition including revisions can be found at the MnSCU Facilities website. http://www.finance.mnscu.edu/facilities/design-construction/resources.html

More information

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction - State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

Learning Objectives. Eden Project The Core Cornwall, England

Learning Objectives. Eden Project The Core Cornwall, England The Wood Products Council is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction, manages a full range of challenging projects to design or construct park or recreation facilities as a Registered Professional Landscape Architect; works fully proficiently

More information

Keynotes RLGA. QA and QC: Are They Different?

Keynotes RLGA. QA and QC: Are They Different? QA and QC: Are They Different? By Ronald L. Geren, AIA, CSI, CCS, CCCA, SCIP Quality assurance (QA) and quality control (QC) are often used interchangeably to mean the same thing or together as if one

More information

COSBEDMC03 - SQA Unit Code FM6L 04 Develop and agree detailed design information in built environment design management

COSBEDMC03 - SQA Unit Code FM6L 04 Develop and agree detailed design information in built environment design management Develop and agree detailed design information in built environment Overview This unit is concerned with carrying out detailed designs and is the technical heart of the award. Candidates must know about

More information

Civil Engineering and Architecture Detailed and Performance Objective Outline

Civil Engineering and Architecture Detailed and Performance Objective Outline Civil Engineering and Architecture Detailed and Performance Objective Outline Deadlines Unit 1: 11 Blocks 1/20/2015 Unit 2: 27 Blocks 2/27/2015 Unit 3: 28 Blocks 4/15/2015 Unit 4: 17 Blocks 5/8/2015 Unit

More information

1.0 ABOUT THE NU GUIDELINES

1.0 ABOUT THE NU GUIDELINES Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner

More information

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project: RLS CONSTRUCTION GROUP Phone: 717-502-6680 Fax: 717-502-6681 www.rlscg.com Invitation to Bid RLS Construction Group requests your firm to submit a quotation on the following project: Project: Location:

More information

Certified Vinyl Siding: Verifiably Green

Certified Vinyl Siding: Verifiably Green Certified Vinyl Siding: Verifiably Green Presented by Tad Radzinski P.E, LEED AP, SFP This webinar will use Voice over Internet Protocol (VoIP) Please make sure your speakers are turned on USGBC Education

More information

Copyright Materials 11/8/2012. Learning Objectives

Copyright Materials 11/8/2012. Learning Objectives Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited.

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

BUILDING ENCLOSURE COMMISSIONING EDUCATION

BUILDING ENCLOSURE COMMISSIONING EDUCATION BUILDING ENCLOSURE COMMISSIONING EDUCATION Building Enclosure Technology and Environment Council - BETEC Wagdy Anis, FAIA, LEED AP Lead Instructor Building Enclosure Technology and Environment Council

More information

Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits

Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits Cornell Rolling Counter Fire Doors Comprehensive Guide to Earning LEED v4 Credits 1 Cornell Rolling Counter Fire Doors Earning LEED v4 Credits Cornell Rolling Counter Fire Doors can provide a significant

More information

ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES

ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES - Architect/Engineer s Scope of Services (Multiple-Prime Project) State of Ohio Professional Services Agreements for Public Facility Construction 1.1 General ARTICLE 1 - ARCHITECT/ENGINEER S BASIC SERVICES

More information

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS GENERAL The commercial bidding process is a well-defined path of positioning oneself to be the successful bidder amongst a group purporting to offer the same quality materials and labor. There are certain

More information

B. OPR and BoD documentation may be included by reference for information only.

B. OPR and BoD documentation may be included by reference for information only. SECTION 01 91 13 - GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD

PROJECT DESIGN EVALUATION AND APPROVAL PROCESS DESIGN AND CONSTRUCTION STANDARD PART 1: GENERAL 1.01 General Requirements A. These guidelines are intended to provide a framework to evaluate building projects for the University of Texas at Austin to: 1. Verify the feasibility of options

More information

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards

I. INTRODUCTION. Purpose: Design Guidelines Components: Introduction To Design Process and Standards I. INTRODUCTION The Los Angeles Community College District is currently undertaking the largest public sector sustainable building effort in the United States, funded by its Proposition A/AA and J Bond

More information

Quality Safety Service Value

Quality Safety Service Value Quality Safety Service Value Generating Value Through Sustainable Asset & Energy Solutions MOPAC is a multi-specialty services contractor focused on the design, construction and preservation of commercial,

More information

GENERAL AND SPECIFIC OBJECTIVES

GENERAL AND SPECIFIC OBJECTIVES GENERAL AND SPECIFIC OBJECTIVES 2017 LICENSING AUTHORITIES WHICH RECOGNIZE THE EXAC ARE: Alberta Association of Architects [ AAA ] Architectural Institute of British Columbia [ AIBC ] Architect s Association

More information

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management Manage project completion and handover in built environment design Overview This unit applies to designers who are engaged in projects at site level at the handover stage and who are responsible for completing

More information

Continuing Education Credits

Continuing Education Credits Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks

More information

Deyelopment stages & actions to be taken

Deyelopment stages & actions to be taken Deyelopment stages & actions to be taken I. Development stages and actions to be taken - ho 322, disk 162 1.1. By Ralph J. Stephenson PE 1.2. This material is designed to 1.2.1. 1. Provide a direct stimulus

More information

CAST STONE AND LEED v4 [1 of 6]

CAST STONE AND LEED v4 [1 of 6] CAST STONE AND LEED v4 [1 of 6] INTRODUCTION Sustainable design has become one of the most prominent trends in the building industry. Designers aiming for a more environmentally-friendly building design

More information

THE DESIGN PROCESS HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN AUGUST 2010 AUG. 02, 2010

THE DESIGN PROCESS HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN AUGUST 2010 AUG. 02, 2010 THE DESIGN PROCESS AUGUST 2010 HEALTHCARE DESIGN RESOURCE INDUS HOSPITAL, KARACHI PAKISTAN TAQ ASSOCIATES. ARCHITECTURE & INTERIOR DESIGN KARACHI PAKISTAN 1 SO A BLANK PIECE OF PAPER. HOW DO WE GET FROM

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi Management of BIMProject: BIM Management Plan Cairo University, Faculty of Engineering MSc in Integrated Engineering Design Management IEDM 611: BIM for Facility Management Prepared and Presented by: Mohamed

More information

MASSEY HOFFMAN ARCHITECTS

MASSEY HOFFMAN ARCHITECTS Green is Simply Good Practice How Good Design Strategies and Construction Practices can Achieve a LEED for Homes Certification Often it seems that the motivation for building green comes from the desire

More information

Architectural Design and Build Process. A Client Guide

Architectural Design and Build Process. A Client Guide Architectural Design and Build Process A Client Guide This guide has been prepared to summarise the various stages of a new-build residential design & construction process. It identifies important tasks

More information

Construction Advisory Board s CSM Course Rating for 2016/2017

Construction Advisory Board s CSM Course Rating for 2016/2017 Construction Advisory Board s CSM Course Rating for / Q CSM Introduction to the Construction and Concrete Industry. (-) An introductory course for Construction and Concrete Industry Management (CIM) majors.

More information

Owner's Representative Scope Matrix - D/B Rev 10/28/2013

Owner's Representative Scope Matrix - D/B Rev 10/28/2013 Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS PROJECT DELIVERY: AN INTRODUCTION A profound design process eventually makes the patron, the architect, and every occasional visitor in the building a slightly better human being. JUHANI PALLASMAA The

More information

Building Design & Construction Standards. Prepared By Operations Services Design Standards Team

Building Design & Construction Standards. Prepared By Operations Services Design Standards Team Building Design & Construction Standards Prepared By Operations Services Design Standards Team August, 2008 CITY OF FORT COLLINS BUILDING DESIGN & CONSTRUCTION STANDARDS were prepared by the Operations

More information

toxicity/ieq: Refer to Division 09 (9) for information on resilient flooring and carpeting. Refer to Division 05 (5) for information on metals.

toxicity/ieq: Refer to Division 09 (9) for information on resilient flooring and carpeting. Refer to Division 05 (5) for information on metals. This is a guidance document with sample specification language intended to be inserted into project specifications on this subject as appropriate to the agency's environmental goals. Certain provisions,

More information

Plan Your Facilities. Manage Your Cons truction

Plan Your Facilities. Manage Your Cons truction Plan Your Facilities Manage Your Cons truction Presentation Team R us s Allen S cott R os e, LEED AP Karen Montovino, AIA, R EFP David McKay Business Director Greater Albany Public S chools Principal DLR

More information

toxicity/ieq: While many media can be very toxic during production, most are considered inert when cured/compete.

toxicity/ieq: While many media can be very toxic during production, most are considered inert when cured/compete. This is a guidance document with sample specification language intended to be inserted into project specifications on this subject as appropriate to the agency's environmental goals. Certain provisions,

More information

Careers List Professional Careers in Construction

Careers List Professional Careers in Construction Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize

More information

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality Executive Summary: Thesis Proposal Final Draft The following pages contain a final draft of the thesis proposal for the South Baltimore District Court House. The basic layout consists of focusing on Knowledge

More information

OBTAINING LEED CERTIFICATION FOR TOILET PARTITIONS. By AMPCO Products, LLC

OBTAINING LEED CERTIFICATION FOR TOILET PARTITIONS. By AMPCO Products, LLC OBTAINING LEED CERTIFICATION FOR TOILET PARTITIONS By AMPCO Products, LLC AMPCO PRODUCTS is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on

More information

An evaluation of existing environmental buildings rating systems and suggested sustainable material selection assessment criteria

An evaluation of existing environmental buildings rating systems and suggested sustainable material selection assessment criteria Sustainable Development and Planning VIII 111 An evaluation of existing environmental buildings rating systems and suggested sustainable material selection assessment criteria H. M. Alhumaidi Kuwait University,

More information

The Maryland-National Capital Park and Planning Commission

The Maryland-National Capital Park and Planning Commission Class Definition: Under direction and as a Licensed Registered Professional Architect, Landscape Architect or Engineer, manages (1) a set of the most challenging park, recreation facility design or construction

More information