Sustainable Utility Construction: Methods and Techniques
|
|
- Ernest Kelley
- 6 years ago
- Views:
Transcription
1 Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas Sustainability Is In Public Works, best encapsulated in the phrase everything we do with an eye to the future. Essentially this means designing and constructing infrastructure that will not become a cost or maintenance burden to future generations and at the same time being mindful of the fact that the resources we need today must also be available for those to come after us. Sustainable infrastructure is the development of water, sewer, roads and other infrastructure systems that meet the needs of current and future generations in a socially, economically and environmentally sustainable manner. 1
2 Why Should The Sustainability of Our Rights-of Way Be of Concern Today? This Is NOT Sustainable For The Future Nor Is This 2
3 Or This The Concern Is Sustainability/viability of the physical property that makes up our Rights of Way. Overcrowding from new buried facilities without removing abandoned plant or implementing organized utility corridors will eventually render our ROW unmanageable and unable to meet demands of future generations. Removal Of Abandoned Facilities Not a popular subject The elephant in the room Generally not enforced although it is a requirement in some ROW mgmt. ordinances If our ROW is to remain viable for future generations, abandoned facility removal MUST be addressed Some lines may be re-purposed (i.e. fiber optic cable in abandoned gas line) Greatest challenge is managing abandoned lines (abandoned vs. live) 3
4 Removal Of Abandoned Facilities Utility corridors should be considered critical for any new development but are not feasible for existing infrastructure. Removal of abandoned facilities is also becoming a critical issue but is costly and not currently pursued by facility or ROW owners. Why Remove Abandoned Facilities? Abandoned facilities complicate repair of viable facilities Physical size of abandoned line renders that amount of ROW unavailable for future installations Abandoned lines/cables cause increasing confusion during locating activities Current practice is remove when encountered Removal of Abandoned Facilities Until abandoned facility removal is adopted as a BMP, coupled with the inescapable fact that our ROW s are becoming over congested, we must embrace construction methods that will allow us to work within the physical constraints we find ourselves in. One very important alternative at our disposal is Trenchless Technologies 4
5 Why Use Trenchless Technology? To prevent this: 4 lane thoroughfare reduced to two lanes of traffic Why Use Trenchless Technology? And this Even though street is repaired properly it is still a patch Why Use Trenchless Technology? In favor of this Service Line connections 5
6 Last But Not Least Contractor SAFETY and SAFETY of the Public Some of The Most Common Trenchless Methods Are: Auger Boring used for casing installations Pipe Bursting used for pipe replacement Slip Lining - used for pipe replacement Horizontal Directional Drilling and Pneumatic Piercing Tools used for pipe and cable installations of all types and sizes CIPP (Cured in Place Pipe) 6
7 Auger Boring Used primarily for road crossings Pipe Bursting Pipe Bursting has been used primarily to replace water lines Methods vary but operation used in OP employed a winch assisted/pneumatic powered bursting head pulling in HDPE butt-fused pipe Open street cuts still necessary to install Tee s and valves Pipe Bursting 7
8 Pipe Bursting Slip Lining New method of water line replacement Made possible due to opportunity to downsize pipe (HDPE provides smoother flow characteristics) 1,350 8 diameter HDPE pipe pulled in place in just over 4 hours As with pipe bursting, open street cuts are still necessary The Pipe String 8
9 Slip Lining in Progress HDPE being pulled into host pipe HDD and Missiles Horizontal Directional Drilling (HDD) and Pneumatic Piercing Tools (Missiles) are by far the most predominant methods of trenchless technology. Both processes lend themselves very well to installation of coax, copper and fiber optic cables. HDD is fast gaining acceptance for installation of gas and water lines as well. The HDD Operation Bore out to termination point Typical bore length is 500 ft. Pre-ream if needed to increase bore diameter Mixing (removes soil) vs. compaction (displaces soil) reamer Problems can arise if this step is neglected Pull back product 9
10 The Drill The Reamer Product Pullback 10
11 Product Pullback The Missile Operation Rectangular pits dug approximately 20 apart Pneumatically powered non-steerable missile is lowered into pit and through percussive effect moves through the soil to exit into the next pit Conduit/cable is then manually pulled through newly created tunnel The Missile 11
12 Missile Operation Not a pretty sight Vacuum Excavation Is critical to trenchless technologies Is ideally suited for locating existing buried utilities prior to trenchless construction activities Is far less intrusive than open cut excavations Is the perfect complement to the Keyhole/Coring/Reinstatement process Damage to existing utilities is virtually eliminated Vacuum Excavation 12
13 CIPP (Cured in Place Pipe) Method to rehabilitate existing pipe s internal functionality without total pipe replacement Uncured material is introduced into host pipe; material is then inflated until contact is made with entire inside diameter of host pipe. New material is cured with steam or hot water. CIPP (Cured in Place Pipe) Before CIPP (Cured in Place Pipe) Material ready for installation 13
14 CIPP Curing Process CIPP (Cured in Place Pipe) After Additional Trenchless Methods Pipe Reaming - a system that was developed to utilize a directional drilling unit, specialized tooling and techniques to grind and remove the existing pipe as the replacement is pulled into place. Pipe reaming offers an alternative to abandoned facility removal. 14
15 Pipe Reaming Pipe Reaming Arrowbore Arrowbore Patented Horizontal Directional Drilling Construction Method Technology that allows very precise line and grade control for installations of gravity flow lines Because Arrowbore uses HDD as the primary construction technique, surface disturbance is substantially reduced when compared to traditional open trench sewer installations 15
16 Arrowbore Vertical Casing Installation Arrowbore the Key to On Grade Installation Arrowbore Process 16
17 Cost Comparison Open Excavation Fuel Consumption Verses The Patented ArrowBore Method Green Solutions for Today s Environment Excavate and install 15 foot deep, with backfill only ArrowBore and install 15 foot deep "This doesn't include the cost of restoration". "90% less restoration" Gallons per day Gallons per day 125 Excavator #1 5 Vertical drilling rig 100 Excavator #2 10 Horizontal drilling rig 50 Front end loader 3 Mini Excavator 10 Uni Loader 4 Fluid mixing system 40 Two dump trucks 5 Portable vacuum 15 Misc. Pumps, generators, ect. 15 Truck vacuum 1/2 day 20 Pickup trucks 15 Pickup trucks 0 Dewatering System 0 0 Setting up the dewatering system Total gallon per day 57 Total gallon per day $3.00 Diesel fuel price per gallon $3.00 Diesel fuel price per gallon $5, Fuel cost per week $ Fuel cost per week 36 Weeks per year (9months) 36 Weeks per year (9months) $194, Fuel cost per crew per year $30, Fuel cost per crew per year FUEL SAVING PER YEAR PER CREW $163, Open Cut Crew $110, Restroation Crew $243, Total Savings All Trenchless Methods Are Intended to Get Us from This.. Or This 17
18 To This.. Arrow Bore installation Locating Utilities Underground utilities can be located using this method Locating Utilities Unfortunately, there are many utility lines under pavement that need to be visually located prior to any trenchless activity and to avoid this 18
19 Keyhole, Coring and Reinstatement Process This process involves core drilling through pavement cross section then using vacuum excavation to remove sub grade material until utility in question is found. Sub grade is then replaced and previously removed core is bonded back into place providing a waterproof virtually invisible repair. Keyhole/Coring/Reinstatement As can the vacuum unit Core drills can be small or large The Keyhole process Keyholing can not only be used for utility exploration investigations but for utility repairs as well. Long handled tooling has been developed that allows certain types of repair work to be accomplished while on the street surface 19
20 Repairs Being Made Through Keyhole Core Reinstatement Backfill & Compact Bonding Compound Core Placement Finished Repair The Finished Product 20
21 Coring-Keyhole Process Which would you prefer on your streets? Sustainability Benefits from Trenchless Technology Significantly reduced surface disturbance therefore significantly reduced restoration costs Significant reduction of inputs needed (i.e. fuel, asphalt, pieces of equipment, manpower, etc.) Significant reduction in traffic impact Significant overall reduction in carbon footprint of project Many methods require little or no additional ROW to be used Sustainable Construction Techniques (Concepts) for Utility Installations Shared Trench Common Trench BDN (Buried Duct Network) Nojitech Duct Banks 21
22 Why use these methods? To Avoid This Or This 22
23 Or This Shared Trench Two or more utilities agree to construct their facilities in the same excavated trench. This agreement saves all utilities who participate; Construction cost including restoration cost Reduces carbon footprint Reduces the area of right of way used Shared Trench 23
24 Shared Trench Common Trench Semi-Engineered trench in which two or more utilities agree to co-locate in the same trench. Locations within the trench are established based on clearances and depths that each utility requires. Common Trench 24
25 Common Trench A Different type of Shared Trench BDN (Buried Duct Networks) BDN s overlay a minimum number of empty ducts on top of or next to direct buried cables for future expansion or replacement of damaged direct buried cables. Can be used by one utility operator or as extra space for future providers. The BDN can hold from 2 to 8 ducts ranging in size from 2 to 6. 25
26 BDN (Buried Duct Networks) BDN (Buried Duct Network) BDN Installation Over Existing Utilities 26
27 BDN Installation Along Side Communications Project Nojitech Raceway System Multiple square sectioned PVC tubes placed in an outer casing that is either fire proof or has high weight tolerance. Connection design is simple, requiring four bolts to secure sections. Designed for quick and safe installation saving time and money. Nojitech Raceway System Spider Series 27
28 Nojitech Raceway System Spider Series Nojitech Raceway System Gopher Series Nojitech Raceway System 28
29 Duct Banks Engineered with input from all existing utilities in the area where the duct bank will be constructed. Can be designed for any number or combination of compatible utilities. Installation cost can be shared in a number of ways to facilitate participation in the duct bank. Duct Banks Each utilities' cost is proportional to the size and amount of ducts they require. How are cost savings attained: One trench One contractor doing construction One location for all utilities One restoration effort Japan s Concrete Box Tunnel 29
30 European Duct Tunnel Open Trench Installed Communications and Electric Power Duct Bank Duct Bank for Ontario Highway Project 30
31 Lenexa Duct Banks Lenexa has been incorporating duct banks with some road projects since 1998 The construction of these duct banks has changed 4 times over the last 13 years The change of design was the result of more cooperation with the utility companies. New design characteristics will be added to future duct bank projects. Duct Bank 3 rd Generation Duct Bank Prairie Star Parkway 31
32 87 th Street Duct Bank Road project the first phase of a 240 acre mixed use development project. Project took two years to design. City and design engineering firm meet with each utility 7 to 10 times during design to layout duct bank locations. New Road Alignment 87 th Street Duct Bank Configuration 32
33 87 th Street Duct Bank Vault Location #3 87 th Street Duct Bank Vault location #1 Duct Bank 87 th Street 33
34 Duct Bank 87 th Street Duct Bank 87 th Street Duct Bank 87 th Street 34
35 Duct Bank 87 th Street Intersection Connections 87 th Street Intersection Sweeps Manhole Placement 35
36 Hand Holes and Vaults 87 th Street Power Manhole Power Manholes 36
37 Power Duct and Manhole Power Duct Bank Questions? 37
38 Murv Morehead City of Overland Park Monty Zimmerman City of Lenexa 38
SECTION HORIZONTAL DIRECTIONAL DRILLING
SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using
More informationNo-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.
No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for
More informationSPECIAL SPECIFICATION 6664 Level (3) Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,
More informationSPECIAL SPECIFICATION 6658 Time Warner Communications System
2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable
More informationTrenchless Technology
TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology
More informationSliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control
More informationAPPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer
APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY
More informationNorth End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No
Hauled Wastewater Receiving Facilities Page 1 Part 1 General 1.1 SECTION INCLUDES.1 Materials and installation for sewage force mains. 1.2 RELATED SECTIONS.1 CW 2110 Watermains and all specifications referenced
More informationAgenda for Today s Workshop
Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour
More informationH. Underground Transmission System Design
H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,
More informationCS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS
TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger
More informationPIPE BURSTING SUCCESS
GRUNDOCRACK PNEUMATIC PIPE BURSTING SYSTEM PIPE BURSTING SUCCESS STARTS HERE TT Technologies is the world leader in pipe bursting equipment and experience. For over 20 years contractors have relied upon
More informationEXHIBIT E SCHEDULE OF UNIT PRICES
SCHEDULE OF UNIT PRICES TO ACCOMPANY THE BID OF (Bidder/Contractor) ON CALL UTILITY SERVICES AND MISCELLANEOUS CONSTRUCTION FOR SEWER AND WATER LINES SOLICITATION NO.: IFB SA1703 Any bidder who enters
More informationREVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule
1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238
More informationMokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation
Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Presented by Mike York, Insituform Technologies, Inc. Trenchless v. Dig and Replace What is CIPP? Developed
More informationCLICK, LISTEN & LEARN INSTRUCTIONS
CLICK, LISTEN & LEARN INSTRUCTIONS - This email contains the following information: login instructions, handout information, tests, equipment requirements, and other essential information. TITLE: Trenchless
More informationLarge Diameter Pipe Bursting
Water Research Foundation Large What Pressure is Pipe Pipe Structural Bursting? Rehabilitation Conference Metropolitan Water District - 700 North Alameda, Los Angeles -January 20, 2016 Large Diameter Pipe
More informationRFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered
RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater
More informationSPECIAL SPECIFICATION 6666 Charter Communications System
2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The following changes are made to the Proposal, Specifications, and Plans. PROPOSAL Proposal Sheets
More informationDISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY
North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY Keith Cheek, Manager of Water Distribution
More informationPipe Bursting Services. pipe bursting. services
Pipe Bursting Services pipe bursting services We have decades of experience solving the really big problems. Concern over the condition of the nation s infrastructure has caused government, municipalities,
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationSection HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.
Section 02450 PART 1 GENERAL 1.01 SUMMARY A. This Section includes: 1. Installing water line by directional drilling methods. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for water lines installed
More informationIndex to Technical Specifications
Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation
More informationPublic Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION
RIGHT-OF-WAY USE PERMIT APPLICATION INSTRUCTIONS 1. The Engineering Section of the City of Bradenton Department of Public Works and Utilities is responsible for processing and approving all ROW Use Permits.
More informationCHAPTER 11 CONDUITS AND FITTINGS
CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1
More information1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.
MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01
More informationVacuum Excavation Services. vacuum excavation. services
Vacuum Excavation Services vacuum excavation services Saving time and money is no small feat. In the U.S., the gas industry spends over a billion dollars a year on pipeline rehabilitation. The conventional
More informationHow to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.
How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study Jessica M. W. Hou, P.E., BCEE Agenda What is a jack and bore? What is does the Underground
More informationAPPLICATION FOR RIGHT OF WAY PERMIT
City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER
More information2.1.4 PROJECT CONSTRUCTION
Alignment 2C Alignment 2C is the preferred alternative. The new 36-inch force mains would follow the existing alignment along the existing utility road within the OCSD easement from the Bitter Point Pump
More informationTS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE
TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationITEM NO. 824 SERVICE SUPPLY LINES (WATER)
ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed
More informationE. CONSTRUCTION PROCEDURES
E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)
San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation
More informationCONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS
More informationInternational Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010
International Aramoon Corp. 1 Pipe Inspection and Rehabilitation By: Faiz Al-Elweet SAWEA Al-Khobar KSA February 24, 2010 International Aramoon Corp. 2 Nobody would like to wait until the problem appears
More informationTRENCHLESS TECHNOLOGY. Department of Civil Engineering.
TRENCHLESS TECHNOLOGY GUIDED BY Ms. PRAJEESHA.M.P Lecturer. Department of Civil Engineering. PRESENTED BY DEEPAK.C Semester 7,Civil Roll No:58 CONTENTS INTRODUCTION TRENCHLESS CONSTRUCTION METHODS TRENCHLESS
More informationSKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation
SKSC Civils (pty) LTD Brilliance Technology Quality - Innovation About us SKSC Civils was inspired by numerous individuals in South Africa, ranging from the civil to the construction industry, to truly
More informationUnderground Conduit Systems
Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different
More informationTECHNICAL NOTE HDPE Pipe and Utility Crossings
TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING
More informationUnderground System Design TADP 547
Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the
More informationCITY OF WILSON. Public Services Engineering. Backfilling, Compaction, & Patching Policy on Existing Pavements
CITY OF WILSON Public Services Engineering Backfilling, Compaction, & Patching Policy on Existing Pavements INTRODUCTION The City of Wilson recognizes that proper backfilling, compaction, and patching
More informationNorth Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title
TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction
More informationRange Point Monuments
Department of Public Works Survey Department Right-of-Way Services - Dept. 507 201 W. Colfax Avenue Denver, CO 80202 www.denvergov.org/publicworks Range Point Monuments If in asphalt - #6 rebar, 30 long,
More informationSECTION 1 GENERAL NOTES
ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS
More informationPILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR
PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR TOM LOYER, ENGINEERS CONSTRUCTION INC JOHN HRABOSKY, HAMMERHEAD TRENCHLESS NASTT s 2019 No-Dig Show What is pipe ramming? A pneumatic
More informationA Trenchless Approach to Lift Station Elimination
A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations
More informationClay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TA-T2-04 Clay County Utility Authority Utilization of Trenchless Water & Wastewater
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract
More informationHorizontal Directional Drilling
Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social
More informationSECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section
02540-1 of 10 SECTION 02540 STORM DRAIN REHABILITATION 02540.01 GENERAL A. Description Storm drain rehabilitation shall include, but not necessarily be limited to, pipe joint sealing, inlet and manhole
More informationSPECIFICATIONS SCOPE OF WORK
SPECIFICATIONS SCOPE OF WORK The intent of this contract is for the supply of all necessary labour, materials, and equipment to install underground traffic signal plant, vehicles detection loops, installation
More informationChapter 3: Permit Procedures and Requirements
Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8
More informationEXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES
CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL
More informationTrenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries
Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Dr. Moustafa Kassab Systems Design Engineering / Civil Engineering Departments
More informationUNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer
More informationPipe-Bursting Success with AC Pipe
Texas Municipal Utilities Association Annual Conference Inn on Barons Creek January 26, 2012 Pipe-Bursting Success with AC Pipe Pre-chlorinated Pipe Bursting to Replace Potable Waterlines in Round Rock,
More informationUNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1
GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe
More information10/11/2013. Trenchless Methods for Service and Mainline Pipe Rehab and New Install
Trenchless Methods for Service and Mainline Pipe Rehab and New Install Eddie Ward TT Technologies, Inc. Tennessee Gas Association Distribution & Operations Conference April 9 th 11 th Murfreesboro, TN
More informationSECTION ELECTRICAL SITE UTILITIES
SECTION 16402 ELECTRICAL SITE UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.
More informationMethod One: Liner/Bladder Assembly-Inversion Method.
CIPP Sectional/Point Repairs Critical Factors Finally Explained By: Shaun M. Flanery Abstract A 1999 report from the American Society of Civil Engineers indicated at that time that the nation s 500,000
More informationINSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT
UNDERGROUND ELECTRICAL PART 1 GENERAL 1.1 SECTION INCLUDES: A. The work specified in this section consists of furnishing and installing underground utilities using the method of installation commonly referred
More informationPipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam
Pipe User Group Tuesday March 14, 2017 Walnut Creek, CA Matt Wassam 720-333-4500 Agenda AWWA M-28 liner definitions brief overview What information is required to bid a project? Technology Overview Transmission
More informationSioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons
WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationDIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION
DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION Adedamola Adedapo (Graduate student, Department of Civil Engineering, University
More informationUNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06
Communications Underground Ducts, Structures and Raceways PART 1: GENERAL The Contractor is held responsible to be familiar with the provisions contained herein and with other Sections of this Specification
More informationSECTION 920 SANITARY AND STORM SEWER MANHOLES
SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C
More informationA. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.
16402 ELECTRICAL SITE UTILITIES ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 33 50 00. *************************************************************************************************************
More informationKeyhole Technology. Logo here
Keyhole Technology A M I N I M A L L Y I N V A S I V E & C O S T E F F E C T I V E M E T H O D F O R T H E M A I N T E N A N C E, R E P A I R A N D M A P P I N G O F U N D E R G R O U N D U T I L I T I
More informationCW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS
December 2012 CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions Specifications...
More informationT-WALL Retaining Wall System
CONSTRUCTION MANUAL T-WALL Retaining Wall System The T-WALL Solution... THE NEEL COMPANY 8328 Traford Lane Springfield, VA 22152 Phone 703-913-7858 Fax 703-913-7859 T-WALL Retaining Wall System CONSTRUCTION
More informationHDD Training. Mitigation. Mark Miller, PE Jon Robison, PE
HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing
More information3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).
SECTION 16111 CONDUITS PART 1 - GENERAL 1.01 DESCRIPTION A. General: Provide conduits, complete, as shown, specified or required per Contract Documents. Principal items include: 1. Rigid aluminum conduit.
More informationNAME STREET ADDRESS CITY, STATE & ZIP CODE. GAS ELECTRIC TELEVISION TELECOMMUNICATION OTHER (check one) UNDERGROUND OVERHEAD BOTH (check one)
Des Plaines Utility Permit #: PUBLIC WORKS AND ENGINEERING 1420 Miner Street Des Plaines, IL 60016 P: 847.391.5390 F: 847.391.5619 desplaines.org CITY OF DES PLAINES UTILITY PERMIT APPLICATION All entities
More informationCured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore
Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline
More informationGeotechnical Investigations Water Main Construction
Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine
More informationSection 2: Underground
Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,
More informationSECTION MEASUREMENT AND PAYMENT
SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following
More informationHORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL
I. GENERAL I.1. I.2. I.3. Driven or bored casing pipe provides an effective housing for duct. Its use is required in situations where open cutting is not permitted such as crossings under railroads and
More informationCITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST
CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area
More informationTechnology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill
Trenchless Technology Planning, Equipment, and Methods Mohammad Najafi Mc Gravu Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto
More informationSECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)
SECTION 33 05 07.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD) PART 1 GENERAL 1.1 SCOPE A. Scope: 1. Design, furnish and install the proposed piping alignment by horizontal directional drilling (HDD)
More informationCIPP Cured-in-Place Pipeline CIPP. cured-in-place pipe. trenchless pipe rehabilitation
CIPP Cured-in-Place Pipeline CIPP cured-in-place pipe trenchless pipe rehabilitation MPC ToughTube cured-in-place pipe lives up to its name. The lining process is accomplished by either inverting or pulling
More informationSECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.
SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section
More informationDUO-THERM 505 Specification Guide
STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish
More informationTHE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject
56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea
More informationPipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.
Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)
ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING
More informationHow PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works
How PGW Manages Pipeline Installation in a Congested Underground Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works Summary Philadelphia by the numbers Philadelphia Gas
More informationA Cost Saving Strategy for Minimizing Pavement Restoration Costs
International Gas Union Research Conference 2014 A Cost Saving Strategy for Minimizing Pavement Restoration Costs Authors: Dennis Jarnecke Gas Technology Institute USA Marshall Pollock Utilicor Technologies
More informationHORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES
HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES Siddharth J. Jariwala 1, Prof. Jayeshkumar Pitroda 2, Prof. J. J. Bhavsar 3 1 P. G. Student (C.E & M), B.V.M Engineering College, Vallabh
More informationInfrastructure Solutions Pressure Pipe Overview
Infrastructure Solutions 2017 Pressure Pipe Overview Pipe problems Costly repairs & lost revenue Water quality Water main breaks Water loss Leaking pipes Flow capacity Aging pipelines 2 Infrastructure
More information