Sustainable Utility Construction: Methods and Techniques

Size: px
Start display at page:

Download "Sustainable Utility Construction: Methods and Techniques"

Transcription

1 Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas Sustainability Is In Public Works, best encapsulated in the phrase everything we do with an eye to the future. Essentially this means designing and constructing infrastructure that will not become a cost or maintenance burden to future generations and at the same time being mindful of the fact that the resources we need today must also be available for those to come after us. Sustainable infrastructure is the development of water, sewer, roads and other infrastructure systems that meet the needs of current and future generations in a socially, economically and environmentally sustainable manner. 1

2 Why Should The Sustainability of Our Rights-of Way Be of Concern Today? This Is NOT Sustainable For The Future Nor Is This 2

3 Or This The Concern Is Sustainability/viability of the physical property that makes up our Rights of Way. Overcrowding from new buried facilities without removing abandoned plant or implementing organized utility corridors will eventually render our ROW unmanageable and unable to meet demands of future generations. Removal Of Abandoned Facilities Not a popular subject The elephant in the room Generally not enforced although it is a requirement in some ROW mgmt. ordinances If our ROW is to remain viable for future generations, abandoned facility removal MUST be addressed Some lines may be re-purposed (i.e. fiber optic cable in abandoned gas line) Greatest challenge is managing abandoned lines (abandoned vs. live) 3

4 Removal Of Abandoned Facilities Utility corridors should be considered critical for any new development but are not feasible for existing infrastructure. Removal of abandoned facilities is also becoming a critical issue but is costly and not currently pursued by facility or ROW owners. Why Remove Abandoned Facilities? Abandoned facilities complicate repair of viable facilities Physical size of abandoned line renders that amount of ROW unavailable for future installations Abandoned lines/cables cause increasing confusion during locating activities Current practice is remove when encountered Removal of Abandoned Facilities Until abandoned facility removal is adopted as a BMP, coupled with the inescapable fact that our ROW s are becoming over congested, we must embrace construction methods that will allow us to work within the physical constraints we find ourselves in. One very important alternative at our disposal is Trenchless Technologies 4

5 Why Use Trenchless Technology? To prevent this: 4 lane thoroughfare reduced to two lanes of traffic Why Use Trenchless Technology? And this Even though street is repaired properly it is still a patch Why Use Trenchless Technology? In favor of this Service Line connections 5

6 Last But Not Least Contractor SAFETY and SAFETY of the Public Some of The Most Common Trenchless Methods Are: Auger Boring used for casing installations Pipe Bursting used for pipe replacement Slip Lining - used for pipe replacement Horizontal Directional Drilling and Pneumatic Piercing Tools used for pipe and cable installations of all types and sizes CIPP (Cured in Place Pipe) 6

7 Auger Boring Used primarily for road crossings Pipe Bursting Pipe Bursting has been used primarily to replace water lines Methods vary but operation used in OP employed a winch assisted/pneumatic powered bursting head pulling in HDPE butt-fused pipe Open street cuts still necessary to install Tee s and valves Pipe Bursting 7

8 Pipe Bursting Slip Lining New method of water line replacement Made possible due to opportunity to downsize pipe (HDPE provides smoother flow characteristics) 1,350 8 diameter HDPE pipe pulled in place in just over 4 hours As with pipe bursting, open street cuts are still necessary The Pipe String 8

9 Slip Lining in Progress HDPE being pulled into host pipe HDD and Missiles Horizontal Directional Drilling (HDD) and Pneumatic Piercing Tools (Missiles) are by far the most predominant methods of trenchless technology. Both processes lend themselves very well to installation of coax, copper and fiber optic cables. HDD is fast gaining acceptance for installation of gas and water lines as well. The HDD Operation Bore out to termination point Typical bore length is 500 ft. Pre-ream if needed to increase bore diameter Mixing (removes soil) vs. compaction (displaces soil) reamer Problems can arise if this step is neglected Pull back product 9

10 The Drill The Reamer Product Pullback 10

11 Product Pullback The Missile Operation Rectangular pits dug approximately 20 apart Pneumatically powered non-steerable missile is lowered into pit and through percussive effect moves through the soil to exit into the next pit Conduit/cable is then manually pulled through newly created tunnel The Missile 11

12 Missile Operation Not a pretty sight Vacuum Excavation Is critical to trenchless technologies Is ideally suited for locating existing buried utilities prior to trenchless construction activities Is far less intrusive than open cut excavations Is the perfect complement to the Keyhole/Coring/Reinstatement process Damage to existing utilities is virtually eliminated Vacuum Excavation 12

13 CIPP (Cured in Place Pipe) Method to rehabilitate existing pipe s internal functionality without total pipe replacement Uncured material is introduced into host pipe; material is then inflated until contact is made with entire inside diameter of host pipe. New material is cured with steam or hot water. CIPP (Cured in Place Pipe) Before CIPP (Cured in Place Pipe) Material ready for installation 13

14 CIPP Curing Process CIPP (Cured in Place Pipe) After Additional Trenchless Methods Pipe Reaming - a system that was developed to utilize a directional drilling unit, specialized tooling and techniques to grind and remove the existing pipe as the replacement is pulled into place. Pipe reaming offers an alternative to abandoned facility removal. 14

15 Pipe Reaming Pipe Reaming Arrowbore Arrowbore Patented Horizontal Directional Drilling Construction Method Technology that allows very precise line and grade control for installations of gravity flow lines Because Arrowbore uses HDD as the primary construction technique, surface disturbance is substantially reduced when compared to traditional open trench sewer installations 15

16 Arrowbore Vertical Casing Installation Arrowbore the Key to On Grade Installation Arrowbore Process 16

17 Cost Comparison Open Excavation Fuel Consumption Verses The Patented ArrowBore Method Green Solutions for Today s Environment Excavate and install 15 foot deep, with backfill only ArrowBore and install 15 foot deep "This doesn't include the cost of restoration". "90% less restoration" Gallons per day Gallons per day 125 Excavator #1 5 Vertical drilling rig 100 Excavator #2 10 Horizontal drilling rig 50 Front end loader 3 Mini Excavator 10 Uni Loader 4 Fluid mixing system 40 Two dump trucks 5 Portable vacuum 15 Misc. Pumps, generators, ect. 15 Truck vacuum 1/2 day 20 Pickup trucks 15 Pickup trucks 0 Dewatering System 0 0 Setting up the dewatering system Total gallon per day 57 Total gallon per day $3.00 Diesel fuel price per gallon $3.00 Diesel fuel price per gallon $5, Fuel cost per week $ Fuel cost per week 36 Weeks per year (9months) 36 Weeks per year (9months) $194, Fuel cost per crew per year $30, Fuel cost per crew per year FUEL SAVING PER YEAR PER CREW $163, Open Cut Crew $110, Restroation Crew $243, Total Savings All Trenchless Methods Are Intended to Get Us from This.. Or This 17

18 To This.. Arrow Bore installation Locating Utilities Underground utilities can be located using this method Locating Utilities Unfortunately, there are many utility lines under pavement that need to be visually located prior to any trenchless activity and to avoid this 18

19 Keyhole, Coring and Reinstatement Process This process involves core drilling through pavement cross section then using vacuum excavation to remove sub grade material until utility in question is found. Sub grade is then replaced and previously removed core is bonded back into place providing a waterproof virtually invisible repair. Keyhole/Coring/Reinstatement As can the vacuum unit Core drills can be small or large The Keyhole process Keyholing can not only be used for utility exploration investigations but for utility repairs as well. Long handled tooling has been developed that allows certain types of repair work to be accomplished while on the street surface 19

20 Repairs Being Made Through Keyhole Core Reinstatement Backfill & Compact Bonding Compound Core Placement Finished Repair The Finished Product 20

21 Coring-Keyhole Process Which would you prefer on your streets? Sustainability Benefits from Trenchless Technology Significantly reduced surface disturbance therefore significantly reduced restoration costs Significant reduction of inputs needed (i.e. fuel, asphalt, pieces of equipment, manpower, etc.) Significant reduction in traffic impact Significant overall reduction in carbon footprint of project Many methods require little or no additional ROW to be used Sustainable Construction Techniques (Concepts) for Utility Installations Shared Trench Common Trench BDN (Buried Duct Network) Nojitech Duct Banks 21

22 Why use these methods? To Avoid This Or This 22

23 Or This Shared Trench Two or more utilities agree to construct their facilities in the same excavated trench. This agreement saves all utilities who participate; Construction cost including restoration cost Reduces carbon footprint Reduces the area of right of way used Shared Trench 23

24 Shared Trench Common Trench Semi-Engineered trench in which two or more utilities agree to co-locate in the same trench. Locations within the trench are established based on clearances and depths that each utility requires. Common Trench 24

25 Common Trench A Different type of Shared Trench BDN (Buried Duct Networks) BDN s overlay a minimum number of empty ducts on top of or next to direct buried cables for future expansion or replacement of damaged direct buried cables. Can be used by one utility operator or as extra space for future providers. The BDN can hold from 2 to 8 ducts ranging in size from 2 to 6. 25

26 BDN (Buried Duct Networks) BDN (Buried Duct Network) BDN Installation Over Existing Utilities 26

27 BDN Installation Along Side Communications Project Nojitech Raceway System Multiple square sectioned PVC tubes placed in an outer casing that is either fire proof or has high weight tolerance. Connection design is simple, requiring four bolts to secure sections. Designed for quick and safe installation saving time and money. Nojitech Raceway System Spider Series 27

28 Nojitech Raceway System Spider Series Nojitech Raceway System Gopher Series Nojitech Raceway System 28

29 Duct Banks Engineered with input from all existing utilities in the area where the duct bank will be constructed. Can be designed for any number or combination of compatible utilities. Installation cost can be shared in a number of ways to facilitate participation in the duct bank. Duct Banks Each utilities' cost is proportional to the size and amount of ducts they require. How are cost savings attained: One trench One contractor doing construction One location for all utilities One restoration effort Japan s Concrete Box Tunnel 29

30 European Duct Tunnel Open Trench Installed Communications and Electric Power Duct Bank Duct Bank for Ontario Highway Project 30

31 Lenexa Duct Banks Lenexa has been incorporating duct banks with some road projects since 1998 The construction of these duct banks has changed 4 times over the last 13 years The change of design was the result of more cooperation with the utility companies. New design characteristics will be added to future duct bank projects. Duct Bank 3 rd Generation Duct Bank Prairie Star Parkway 31

32 87 th Street Duct Bank Road project the first phase of a 240 acre mixed use development project. Project took two years to design. City and design engineering firm meet with each utility 7 to 10 times during design to layout duct bank locations. New Road Alignment 87 th Street Duct Bank Configuration 32

33 87 th Street Duct Bank Vault Location #3 87 th Street Duct Bank Vault location #1 Duct Bank 87 th Street 33

34 Duct Bank 87 th Street Duct Bank 87 th Street Duct Bank 87 th Street 34

35 Duct Bank 87 th Street Intersection Connections 87 th Street Intersection Sweeps Manhole Placement 35

36 Hand Holes and Vaults 87 th Street Power Manhole Power Manholes 36

37 Power Duct and Manhole Power Duct Bank Questions? 37

38 Murv Morehead City of Overland Park Monty Zimmerman City of Lenexa 38

SECTION HORIZONTAL DIRECTIONAL DRILLING

SECTION HORIZONTAL DIRECTIONAL DRILLING SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using

More information

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e. No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No Hauled Wastewater Receiving Facilities Page 1 Part 1 General 1.1 SECTION INCLUDES.1 Materials and installation for sewage force mains. 1.2 RELATED SECTIONS.1 CW 2110 Watermains and all specifications referenced

More information

Agenda for Today s Workshop

Agenda for Today s Workshop Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

PIPE BURSTING SUCCESS

PIPE BURSTING SUCCESS GRUNDOCRACK PNEUMATIC PIPE BURSTING SYSTEM PIPE BURSTING SUCCESS STARTS HERE TT Technologies is the world leader in pipe bursting equipment and experience. For over 20 years contractors have relied upon

More information

EXHIBIT E SCHEDULE OF UNIT PRICES

EXHIBIT E SCHEDULE OF UNIT PRICES SCHEDULE OF UNIT PRICES TO ACCOMPANY THE BID OF (Bidder/Contractor) ON CALL UTILITY SERVICES AND MISCELLANEOUS CONSTRUCTION FOR SEWER AND WATER LINES SOLICITATION NO.: IFB SA1703 Any bidder who enters

More information

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule 1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238

More information

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Presented by Mike York, Insituform Technologies, Inc. Trenchless v. Dig and Replace What is CIPP? Developed

More information

CLICK, LISTEN & LEARN INSTRUCTIONS

CLICK, LISTEN & LEARN INSTRUCTIONS CLICK, LISTEN & LEARN INSTRUCTIONS - This email contains the following information: login instructions, handout information, tests, equipment requirements, and other essential information. TITLE: Trenchless

More information

Large Diameter Pipe Bursting

Large Diameter Pipe Bursting Water Research Foundation Large What Pressure is Pipe Pipe Structural Bursting? Rehabilitation Conference Metropolitan Water District - 700 North Alameda, Los Angeles -January 20, 2016 Large Diameter Pipe

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The following changes are made to the Proposal, Specifications, and Plans. PROPOSAL Proposal Sheets

More information

DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY

DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY Keith Cheek, Manager of Water Distribution

More information

Pipe Bursting Services. pipe bursting. services

Pipe Bursting Services. pipe bursting. services Pipe Bursting Services pipe bursting services We have decades of experience solving the really big problems. Concern over the condition of the nation s infrastructure has caused government, municipalities,

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods. Section 02450 PART 1 GENERAL 1.01 SUMMARY A. This Section includes: 1. Installing water line by directional drilling methods. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for water lines installed

More information

Index to Technical Specifications

Index to Technical Specifications Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation

More information

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION RIGHT-OF-WAY USE PERMIT APPLICATION INSTRUCTIONS 1. The Engineering Section of the City of Bradenton Department of Public Works and Utilities is responsible for processing and approving all ROW Use Permits.

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Vacuum Excavation Services. vacuum excavation. services

Vacuum Excavation Services. vacuum excavation. services Vacuum Excavation Services vacuum excavation services Saving time and money is no small feat. In the U.S., the gas industry spends over a billion dollars a year on pipeline rehabilitation. The conventional

More information

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E. How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study Jessica M. W. Hou, P.E., BCEE Agenda What is a jack and bore? What is does the Underground

More information

APPLICATION FOR RIGHT OF WAY PERMIT

APPLICATION FOR RIGHT OF WAY PERMIT City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER

More information

2.1.4 PROJECT CONSTRUCTION

2.1.4 PROJECT CONSTRUCTION Alignment 2C Alignment 2C is the preferred alternative. The new 36-inch force mains would follow the existing alignment along the existing utility road within the OCSD easement from the Bitter Point Pump

More information

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE

TS 803 DUCTS DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE TORONTO TRANSPORTATION March 2012 TS 803 DUCTS TABLE OF CONTENTS 1. DRAWINGS TTD 803.001 TTD 803.010 DUCT INSTALLATION, PROTECTION AND MARKING WITHIN A TRENCH OPEN TRENCH DUCT INSTALLATION PROFILE 2. CONSTRUCTION

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

International Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010

International Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010 International Aramoon Corp. 1 Pipe Inspection and Rehabilitation By: Faiz Al-Elweet SAWEA Al-Khobar KSA February 24, 2010 International Aramoon Corp. 2 Nobody would like to wait until the problem appears

More information

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

TRENCHLESS TECHNOLOGY. Department of Civil Engineering. TRENCHLESS TECHNOLOGY GUIDED BY Ms. PRAJEESHA.M.P Lecturer. Department of Civil Engineering. PRESENTED BY DEEPAK.C Semester 7,Civil Roll No:58 CONTENTS INTRODUCTION TRENCHLESS CONSTRUCTION METHODS TRENCHLESS

More information

SKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation

SKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation SKSC Civils (pty) LTD Brilliance Technology Quality - Innovation About us SKSC Civils was inspired by numerous individuals in South Africa, ranging from the civil to the construction industry, to truly

More information

Underground Conduit Systems

Underground Conduit Systems Section 32 Underground Conduit Systems Note 1 under the title of Sec. 32 defines how the NESC uses the following terms: Duct Conduit Conduit system The common trade use of these terms is slightly different

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

Underground System Design TADP 547

Underground System Design TADP 547 Underground System Design TADP 547 Transmission Cable Installation Presentation 5.4 Instructor: Frank Frentzas Transmission Design and Installation When planning an underground power cables system the

More information

CITY OF WILSON. Public Services Engineering. Backfilling, Compaction, & Patching Policy on Existing Pavements

CITY OF WILSON. Public Services Engineering. Backfilling, Compaction, & Patching Policy on Existing Pavements CITY OF WILSON Public Services Engineering Backfilling, Compaction, & Patching Policy on Existing Pavements INTRODUCTION The City of Wilson recognizes that proper backfilling, compaction, and patching

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

Range Point Monuments

Range Point Monuments Department of Public Works Survey Department Right-of-Way Services - Dept. 507 201 W. Colfax Avenue Denver, CO 80202 www.denvergov.org/publicworks Range Point Monuments If in asphalt - #6 rebar, 30 long,

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR TOM LOYER, ENGINEERS CONSTRUCTION INC JOHN HRABOSKY, HAMMERHEAD TRENCHLESS NASTT s 2019 No-Dig Show What is pipe ramming? A pneumatic

More information

A Trenchless Approach to Lift Station Elimination

A Trenchless Approach to Lift Station Elimination A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations

More information

Clay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation

Clay County Utility Authority Utilization of Trenchless Water & Wastewater Pipeline Installation North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TA-T2-04 Clay County Utility Authority Utilization of Trenchless Water & Wastewater

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section 02540-1 of 10 SECTION 02540 STORM DRAIN REHABILITATION 02540.01 GENERAL A. Description Storm drain rehabilitation shall include, but not necessarily be limited to, pipe joint sealing, inlet and manhole

More information

SPECIFICATIONS SCOPE OF WORK

SPECIFICATIONS SCOPE OF WORK SPECIFICATIONS SCOPE OF WORK The intent of this contract is for the supply of all necessary labour, materials, and equipment to install underground traffic signal plant, vehicles detection loops, installation

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES

EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL NOTES CITY OF SANTA MONICA Department of Public Works Civil Engineering Division 1685 Main, Room 116 Santa Monica, CA 90401 Tel: (310) 458-2240 or (310) 458-8737 EXCAVATION WORK IN PUBLIC RIGHT-OF-WAY GENERAL

More information

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Dr. Moustafa Kassab Systems Design Engineering / Civil Engineering Departments

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

Pipe-Bursting Success with AC Pipe

Pipe-Bursting Success with AC Pipe Texas Municipal Utilities Association Annual Conference Inn on Barons Creek January 26, 2012 Pipe-Bursting Success with AC Pipe Pre-chlorinated Pipe Bursting to Replace Potable Waterlines in Round Rock,

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

10/11/2013. Trenchless Methods for Service and Mainline Pipe Rehab and New Install

10/11/2013. Trenchless Methods for Service and Mainline Pipe Rehab and New Install Trenchless Methods for Service and Mainline Pipe Rehab and New Install Eddie Ward TT Technologies, Inc. Tennessee Gas Association Distribution & Operations Conference April 9 th 11 th Murfreesboro, TN

More information

SECTION ELECTRICAL SITE UTILITIES

SECTION ELECTRICAL SITE UTILITIES SECTION 16402 ELECTRICAL SITE UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

More information

Method One: Liner/Bladder Assembly-Inversion Method.

Method One: Liner/Bladder Assembly-Inversion Method. CIPP Sectional/Point Repairs Critical Factors Finally Explained By: Shaun M. Flanery Abstract A 1999 report from the American Society of Civil Engineers indicated at that time that the nation s 500,000

More information

INSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT

INSTALLATION OF AIRFIELD LIGHTING UNDERGROUND ELECTRICAL DIRECTIONAL BORE DUCT UNDERGROUND ELECTRICAL PART 1 GENERAL 1.1 SECTION INCLUDES: A. The work specified in this section consists of furnishing and installing underground utilities using the method of installation commonly referred

More information

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam Pipe User Group Tuesday March 14, 2017 Walnut Creek, CA Matt Wassam 720-333-4500 Agenda AWWA M-28 liner definitions brief overview What information is required to bid a project? Technology Overview Transmission

More information

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION

DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION Adedamola Adedapo (Graduate student, Department of Civil Engineering, University

More information

UNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06

UNM IT/Telecommunications Guide Specification Communications Underground Ducts, Raceways and Structures /27/06 Communications Underground Ducts, Structures and Raceways PART 1: GENERAL The Contractor is held responsible to be familiar with the provisions contained herein and with other Sections of this Specification

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications.

A. Section Includes: Electrical site utilities and coordination of requirements with the utility company and service specifications. 16402 ELECTRICAL SITE UTILITIES ************************************************************************************************************* SPECIFIER: CSI MasterFormat 2004 number: 33 50 00. *************************************************************************************************************

More information

Keyhole Technology. Logo here

Keyhole Technology. Logo here Keyhole Technology A M I N I M A L L Y I N V A S I V E & C O S T E F F E C T I V E M E T H O D F O R T H E M A I N T E N A N C E, R E P A I R A N D M A P P I N G O F U N D E R G R O U N D U T I L I T I

More information

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS

CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS December 2012 CW 3620 INSTALLATION OF UNDERGROUND TRAFFIC SIGNAL SERVICES TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions Specifications...

More information

T-WALL Retaining Wall System

T-WALL Retaining Wall System CONSTRUCTION MANUAL T-WALL Retaining Wall System The T-WALL Solution... THE NEEL COMPANY 8328 Traford Lane Springfield, VA 22152 Phone 703-913-7858 Fax 703-913-7859 T-WALL Retaining Wall System CONSTRUCTION

More information

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing

More information

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC).

3. Intermediate metal conduit (IMC). 4. Electric metallic tubing (EMT). 5. Flexible metal conduit (FLEX). 6. Polyvinyl chloride conduit (PVC). SECTION 16111 CONDUITS PART 1 - GENERAL 1.01 DESCRIPTION A. General: Provide conduits, complete, as shown, specified or required per Contract Documents. Principal items include: 1. Rigid aluminum conduit.

More information

NAME STREET ADDRESS CITY, STATE & ZIP CODE. GAS ELECTRIC TELEVISION TELECOMMUNICATION OTHER (check one) UNDERGROUND OVERHEAD BOTH (check one)

NAME STREET ADDRESS CITY, STATE & ZIP CODE. GAS ELECTRIC TELEVISION TELECOMMUNICATION OTHER (check one) UNDERGROUND OVERHEAD BOTH (check one) Des Plaines Utility Permit #: PUBLIC WORKS AND ENGINEERING 1420 Miner Street Des Plaines, IL 60016 P: 847.391.5390 F: 847.391.5619 desplaines.org CITY OF DES PLAINES UTILITY PERMIT APPLICATION All entities

More information

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline

More information

Geotechnical Investigations Water Main Construction

Geotechnical Investigations Water Main Construction Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine

More information

Section 2: Underground

Section 2: Underground Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL I. GENERAL I.1. I.2. I.3. Driven or bored casing pipe provides an effective housing for duct. Its use is required in situations where open cutting is not permitted such as crossings under railroads and

More information

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST

CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST CITY OF ROSEVILLE CONSTRUCTION STANDARDS - CST Abbreviations AB 1-3 Section 11 Purpose and Definitions 11-1 Purpose PD 1 11-2 Construction Practice PD 1 11-3 Definitions PD 1 Section 12 Construction Area

More information

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill Trenchless Technology Planning, Equipment, and Methods Mohammad Najafi Mc Gravu Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto

More information

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD) SECTION 33 05 07.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD) PART 1 GENERAL 1.1 SCOPE A. Scope: 1. Design, furnish and install the proposed piping alignment by horizontal directional drilling (HDD)

More information

CIPP Cured-in-Place Pipeline CIPP. cured-in-place pipe. trenchless pipe rehabilitation

CIPP Cured-in-Place Pipeline CIPP. cured-in-place pipe. trenchless pipe rehabilitation CIPP Cured-in-Place Pipeline CIPP cured-in-place pipe trenchless pipe rehabilitation MPC ToughTube cured-in-place pipe lives up to its name. The lining process is accomplished by either inverting or pulling

More information

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

DUO-THERM 505 Specification Guide

DUO-THERM 505 Specification Guide STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish

More information

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject 56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works How PGW Manages Pipeline Installation in a Congested Underground Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works Summary Philadelphia by the numbers Philadelphia Gas

More information

A Cost Saving Strategy for Minimizing Pavement Restoration Costs

A Cost Saving Strategy for Minimizing Pavement Restoration Costs International Gas Union Research Conference 2014 A Cost Saving Strategy for Minimizing Pavement Restoration Costs Authors: Dennis Jarnecke Gas Technology Institute USA Marshall Pollock Utilicor Technologies

More information

HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES

HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES Siddharth J. Jariwala 1, Prof. Jayeshkumar Pitroda 2, Prof. J. J. Bhavsar 3 1 P. G. Student (C.E & M), B.V.M Engineering College, Vallabh

More information

Infrastructure Solutions Pressure Pipe Overview

Infrastructure Solutions Pressure Pipe Overview Infrastructure Solutions 2017 Pressure Pipe Overview Pipe problems Costly repairs & lost revenue Water quality Water main breaks Water loss Leaking pipes Flow capacity Aging pipelines 2 Infrastructure

More information