1 Reaming Tunnel Boring Machine Undercutting Technique
2 Hat trick in the Uetliberg Tunnel State of the art technology Reaming Tunnel Boring Machine It is a well known fact that mechanically excavated tunnels are mostly round; and also that this fact is not necessarily desirable. The innovative technology of WIRTH GmbH, with their new Reaming Tunnel Boring Machine in the Uetliberg Tunnel, has remedied this for the first time. For the task in the Uetliberg hardrock near Zurich, the WIRTH TBE 500/1440 H-HST combines three elements, which have proven themselves several times in preceding projects. Seite These elements are reaming techniques; an undercutting technique; and the ability to bore tunnel sections which are not round. This combination offers a range of advantages for the tunnel constructor. WIRTH tunnel boring machines that apply the reaming technique are especially suitable for large diameter tunnels. It is a characteristic of the reaming system that a previously bored smaller tunnel is increased up to its final diameter. Tunnel boring machines with reaming technique are braced in the pilot gallery, not in the actual tunnel, as it is done with conventional full-face machines. In this way, the reaming machine can be relatively easily adapted to different boring diameters, as modifications are required only on the cutter head not on the machine body itself. This is done by the attachment of different cutter head arms. In its original condition the boring diameter of the reaming tunnel boring machine described here was variable within a range of 8.00m to 12.00m. After its refurbishment for the Uetliberg tunnel project it is capable of coping with a diameter of 14.40m without problems. Directly in front of the hydraulically driven cutter head, the reaming machine is provided with a roof protecting shield to avoid uncontrolled caving in of the pilot tunnel roof, in insufficiently stable rock zones. Behind the cutter head the full tunnel cross-section is available for rock securing or concreting work.
3 Excavated tunnel section with Reaming Tunnel Boring Machine and pilot tunnel The undercutting technique is known as an especially effective principle. Here, it is not so much the high compressive strength that plays a role but the essentially lower tensile strength of the rock. Profiting from the undercutting technique distinctly increases the excavating performance per cutter. Whilst this technology was already applied in a Continuous Miner that WIRTH GmbH had constructed in the early nineties, in cooperation with the Canadian research organisation HDRK, this technical development has now been applied for the first time for the reaming principle. The WIRTH TBE 500/1440 H- HST is a Reaming Tunnel Boring Machine capable of boring diameters up to 14.40m. For a reaming tunnel boring project, firstly, a pilot gallery smaller in diameter (e.g. five meters in the Uetliberg) is bored over the whole distance. Secondly, the reaming machine is braced in the pilot gallery and reams the tunnel with six boring arms, to the final diameter. The new aspects of this procedure are the disk cutters arranged on radially displaceable skids. During the cutter rotation they are spirally moved to the outside. By varying, radial displacement of the disk cutters, for instance, the circular shape of the tunnel can be flattened to a certain extent; a method reducing the tunnel cross-section itself and limiting the material requirement for planing the bottom. Undercutting profile Seite
4 A further advantage is the reduced energy consumption, as the rock is broken against a free surface and, therefore, in coarser cuttings compared to conventional tunnel boring machines. The short cutter head construction allows securing work of the tunnel directly behind the face. A further advantage, in comparison to the conventional method, is the careful excavation and the depth of spacing, which is re-adjustable at any time, and adapted to the geology. For 20 years the City of Zurich has been planning a large bypass the West bypass, which includes two parallel tunnels 4.4 kilometres in length through the Uetliberg and the Ettenberg. Based on the geology (a mixture of unconsolidated soil and rock) at first, the use of a mixed shield machine was taken into consideration, but after the preparation of a risk assessment this possibility was ruled out. Whilst for the difficult unconsolidated sections the choice was a core construction, decision was made for blasting excavation in the rock section Eichholz. The most favourable solution for the 2,800 metres long rock gallery, in the Uetlibergtunnel, was the WIRTH, TBE 500/1440 H-HST reaming tunnel boring machine, modified to work with the undercutting technique. Both tunnels were initially bored to five metres in diameter, by means of a WIRTH TB III 450 E. The work for the first tunnel started early in May 2002, and the second tunnel started in the last quarter of the year In April 2003 the Reamer started in the westbound tunnel, finishing on the 1st of February 2005, with the best rate of 16.5m excavation achieved in one day. After refurbishment and removal, the TBM started the eastbound tunnel at the beginning of June 2005, and is now aiming for even better rates of excavation with the second drive. Undercutting head for boring diameter of m Cutter for undercutting technique WIRTH GmbH Kölner Str D Erkelenz Phone Fax Internet: info@wirth-europe.com B 311 e Technische Änderungen vorbehalten
5
6
7
N4.1.5 Uetliberg Tunnel
N4.1.5 Uetliberg Tunnel The world's largest tunnel bore extender (TBE), which excavates the molasse by undercutting, was commissioned on April 11, 2003. As already reported at the ITA 2003 in Amsterdam,
More informationTBM Selection and Specification
By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements
More informationNew Developments in Automated Tunnel Surveying Systems
New Developments in Automated Tunnel Surveying Systems N.J. Chittenden, H.P. Müller Amberg Measuring Technique Ltd, Regensdorf-Watt, Switzerland ABSTRACT The surveying requirements during tunnel construction
More informationUetiberg Motorway Tunnel (Switzerland)
Uetiberg Motorway Tunnel (Switzerland) Otto Schnelli Civil Engineer HTL, Engineering Department of the Canton of Zurich, Office of Civil and Underground Engineering, National and Main Highways Dept., Zurich/CH
More information2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January
Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations
More informationPipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2
Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers
More informationGrouting Bilfinger Spezialtiefbau GmbH
Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com
More informationDIFFICULT GROUND SOLUTIONS:
Tunnelling April/May 2016 www.tunnellingjournal.com journal The international journal for the tunnelling industry SEE PAGE 6 SEE PAGE 12 SEE PAGE 27 WORLD NEWS MONITOR PROGRESS CUTTER CARE HIGHLIGHTS FROM
More informationREHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL
REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL Roger BREMEN Engineer of the Hydraulic Department Lombardi Engineering Limited Via Simen 19 CH 6648 Minusio Switzerland ABSTRACT: A 7.5 km long
More informationRowa Customer Day. Niagara Falls - Sir Adam Beck. The worldwide largest open TBM with 14.4m diameter creates great challenges for the back
Rowa Customer Day Niagara Falls - Sir Adam Beck The worldwide largest open TBM with 14.4m diameter creates great challenges for the back Lecture: Jost Wenk September 13, 2007 Table of Content Table of
More informationUNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland
UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy 27160 Olkiluoto, Finland 1. Introduction ABSTRACT Posiva s repository for geological disposal
More informationThe Robbins Company. Bheri Babai Diversion Multipurpose Project (BBDMP) Company Facts. Headquarters
Bheri Babai Diversion Multipurpose Project (BBDMP) Presented by Jim Clark, Projects Manager India The Robbins Company THE ROBBINS COMPANY THE ROBBINS COMPANY Company Facts More than 50 years of innovation
More informationSOIL RESTRUCTURATION AND PREVENTATIVE INJECTIONS AFTER MAJOR FACE COLLAPSE IN URBAN TUNNEL - BARCELONA, SPAIN 2008
Miguel Ángel Cueto Suárez, Head Engineer Minova Codiv S.L. Pg. Ind. Riaño II, parcela 52, ES-33920 Riaño (Langreo), Asturias ESPAÑA Tel. +34 985 66 99 11, Fax +34 985 66 99 44, e-mail: info@minovacodiv.com,
More informationTrenchless Technology
TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology
More informationFrom Colonia Jardín to Cuatro Vientos
60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was
More informationMatrix Helical Anchoring System
Matrix Helical Anchoring System INNOVATIVE SOLUTIONS FOR PROFESSIONAL MASONRY REINFORCEMENT The uses of Matrix Remedial Ties and Matrix Crack Stitching Bar are both wide and varied and they can be utilised
More informationThe new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump
The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded
More informationHow we would build the proposed storm relief sewer
Counters Creek storm relief sewer How we would build the proposed storm relief sewer We would build the proposed Counters Creek storm relief sewer using the most advanced construction methods and we would
More informationDesign of pipeline installation. D-Geo Pipeline
Design of pipeline installation D-Geo Pipeline Design of pipeline installation D-Geo Pipeline General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern
More informationThe Pilot Pipe method is a very simple method for trenchless installation of supply lines. It is done in several steps:
Guided Auger Boring in South America Dr. Gregor Nieder, Director of Bohrtec Gesellschaft GmbH Juan Carlos Moreno Sales Manager Latin America Herrenknecht AG Introduction Bohrtec is a worldwide known manufacturer
More informationSecoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS
Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS PRODUCTIVITY IN A PIPE Creating stability Drilled casings, or casing advancement systems, are today's preferred method for drilling in difficult ground
More informationExperts in tunneling with Tunnel Boring Machines
www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution
More informationINFRASTRUCTURE TUNNELS
INFRASTRUCTURE TUNNELS Significance of infrastructure tunnels Increasing building density and the continuous growth of urban areas require not only effective supply and disposal routes, which are suitable
More informationTRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.
TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de
More informationConstruction of Uetliberg Tunnel. A. General Project Description. 1. General. 2. Geographical summary Project participants
Page 1 of 18 Construction of Uetliberg Tunnel A. General Project Description 1. General 1.1. Project participants Overall project and construction management: Canton of Zurich Engineering Department Project
More information2 Support of the cavity and settlement Support of the face Natural support Mechanical support...
Table of Contents The authors... VII Foreword to the 2nd Edition... IX 1 Introduction... 1 1.1 Basic principles and terms... 3 1.2 Types of tunnel boring machine according to DAUB... 5 1.2.1 Categories
More informationHardrock Tunnel Boring Machines
Bernhard Maidl, Leonhard Schmid, Willy Ritz, Martin Herrenknecht Hardrock Tunnel Boring Machines In co-operation with Gerhard Wehrmeyer and Marcus Derbort -=rnst & Sohn '-A Wiley Company Contents 1 Historical
More informationCOMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS
fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur
More informationTBM rescue projects using shafts and ground freezing
TBM rescue projects using shafts and ground freezing Dipl.-Ing. Michael Löffler, Dipl.-Ing. Helmut Haß (CDM Consult GmbH, Germany) Dipl.-Ing. Thomas Ahlbrecht (Deilmann-Haniel Shaft Sinking GmbH, Germany)
More informationROTARY DRILLING TECHNIQUES LARGE DIAMETER
INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /
More informationNumerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling
Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling W.L.Tan and P.G. Ranjith School of Civil & Environmental Engineering, Nanyang Technological University, Singapore 639798 Phone: 65-67905267,
More informationD&B versus TBM some case stories
D&B versus TBM some case stories TBM Applications II Bergen, June 6 th and 7 th Project Manager Anne Kathrine Kalager Case stories Two different Projects Considerations regarding excavation method: New
More informationØ1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati
Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati Steve Lamb The Robbins Company, Solon, Ohio, USA Steve Abernathy Midwest Mole, Inc., Indianapolis, Indiana, USA ABSTRACT: A Robbins
More informationLearning Legacy Document Duration of data recorded (approx.) 1
Table 1: Crossrail Water Consumption Data Contract C300/C410 - Crossrail Running Tunnels - West; Bond Street & Tottenham Court Road s - Early Access Shafts & SCL Works (JV: BAM Nuttall Ltd / Ferrovial
More informationDesign Data 4M. Jacking Concrete Pipe
Design Data 4M Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationHydraulic cutting units
Product range Produced by ATLAS Maschinen GmbH Hydraulic cutting units Hydraulic cutting units SCHAEFF hydraulic cutting units Proven for the toughest day-to-day use If you work with the toughest rock
More informationDesign of pipeline installation D-GEO PIPELINE
Design of pipeline installation D-GEO PIPELINE Design of pipeline installation D-GEO PIPELINE General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern
More informationTunnel Boring Machines
Tunnel Boring Machines IMIA WGP 60 Michael Spencer, Zurich London (Chairman) Alessandro Stolfa Generali Heiko Wannick Munich Re Ronan Gallagher Allianz John Forder Willis Beat Guggisberg Allianz Eric Bentz
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationCompaction and Jet Grouting
Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials
More informationBrief of evidence Tunnelling construction
Brief of evidence Tunnelling construction 1 Personal Information and Qualification My name is Dr. Tim Jaguttis. I am a mechanical engineer and carry a PhD in mechanical engineering. Since 2008 I m a managing
More informationPipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.
Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods
More informationrapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.
herrenknecht AG utility tunnelling Traffic tunnelling SEPARATION PLANTS HERRENKNECHT SEPARATION PLANTS KEEP IT FLOWING. RAPID TUNNELLING THANKS TO EFFICIENT SEPARATION. Low-impact mechanized tunnelling:
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationPipe Jacking. Japan Sewage Works Association
Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,
More informationcutting the world CUTTER TECHNOLOGY BROADEN YOUR HORIZONs
CUTTER TECHNOLOGY BROADEN YOUR HORIZONs There, where conventional methods are unsuitable or too expensive... Trenching With a production rate of 6- m /hr, this ER 500- X was used to produce a trench.5m
More informationConcrete Pipe Jacking
Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used
More informationDesign Data 4. Jacking Concrete Pipe
Design Data 4 Jacking Concrete Pipe FOREWORD Jacking or tunneling concrete pipe is an increasingly important construction method for installing concrete pipelines without interrupting commerce, or disturbing
More informationPipetron Tunnel Construction Issues
Pipetron Tunnel Construction Issues James E. Friant Colorado School of Mines and Excavation Engineering Associates, Inc., 1352 SW 175th St., Seattle, WA 98166 Robert A. Bauer and David L. Gross Illinois
More informationMetro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban tunnelling
EUROCK 2004 & 53 rd Geomechanics Colloquium. Schubert (ed.) 2004 VGE Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban
More informationDIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS
DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com
More informationCase study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan
Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -
More informationRowa Customers Day. Gotthard Base Tunnel Sedrun, Lot 360. Speaker: Heinz Jenni 07 September 2004
Rowa Customers Day Gotthard Base Tunnel Sedrun, Lot 360 Speaker: Heinz Jenni 07 September 2004 Highly mechanized heading installation for full excavation with large convergences in Tavetscher intermediate
More informationHDD Training. Mitigation. Mark Miller, PE Jon Robison, PE
HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing
More informationConcrete Pipe Jacking
Concrete Pipe Jacking Concrete Pipe Association of Australasia ACN 007 067 656 TECHNICAL BULLETIN CONTENTS ABSTRACT 1 INTRODUCTION 2 METHOD OF INSTALLATION 3 CONCRETE PIPE DESIGN 4 CONCRETE PIPE JOINT
More informationA New Concept for Selective Mechanical Mining of Hard Rock
A New Concept for Selective Mechanical Mining of Hard Rock Brian Asbury 1, Jamal Rostami 1, and Levent Ozdemir 1 1 EARTH MECHANICS INSTITUTE, MINING ENGINEERING DEPARTMENT, COLORADO SCHOOL OF MINES 1 ABSTRACT
More information2
Company(ผ บรรยาย): Shimizu Corporation Technical Name(ห วข อเทคโนโลย ): High Performance TBM TBM ค ณภาพส ง Presenter: 水戸聰 Akira Mito 1 2 Example of Water Supply Tunnel High Overburden Ing-Yot Tunnel L=50.9km
More informationHow to achieve faster drifting in mining, some aspects. SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden
How to achieve faster drifting in mining, some aspects SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden Comparison of objectives Objectives for the tunnel builder To make the tunnel
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationLARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL
Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore
More informationThe Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions
The Brenner Challenge - TBMs versus Drill & Blast in High Cover Conditions Detlef Jordan Robbins Europe GmbH, Germany ABSTRACT: The tunneling industry is abuzz about the upcoming Brenner Base Tunnel Project.
More informationTRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)
PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without
More informationCAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING
CAPABILITY STATEMENT RAISE BORE DIVISION 05 07 20 CAPABILITIES SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING PYBAR is a nationwide provider of mining services with core competencies in underground
More informationCAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING
CAPABILITY STATEMENT RAISE BORE DIVISION 05 07 20 CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING PYBAR is a nationwide provider of mining services with core competencies in underground
More informationTSP 203PLUS. Geophysical Prediction in Underground Construction
TSP 203PLUS Geophysical Prediction in Underground Construction Tunnelling a business with hidden pitfalls The trend towards mechanised production in underground construction is unmistakable. Successful
More informationRowa Customer Day. Interceptor Belgrad. GC Order for Construction Site Logistics
Rowa Customer Day Interceptor Belgrad GC Order for Construction Site Logistics Lecture: Jürg Leuthold September 17, 2009 Table of contents Table of contents... 2 1 Belgrade... 3 2 The Project... 4 3 Step-by-Step
More informationCS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS
TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger
More information2 3 4 Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling
More informationTunnel. Immersed Tunnels
Tunnel Tunnels are underground spaces, usually, in a tubular shape with substantial lengths. They can either be man-made or natural and can be used as passageways, storages, carriageways and utility ducts.
More informationIntroduction to Longwall Mining and Subsidence
Introduction to Longwall Mining and Subsidence Prepared by Mine Subsidence Engineering Consultants Level 1 / 228 Victoria Avenue Chatswood NSW 2067 PO Box 3047 Willoughby North NSW 2068 Tel. (02) 9413
More informationIntroduction to Tunnel Construction
Introduction to Tunnel Construction David Chapman, Nicole Metje and Alfred Stark *< \ Spon Press an imprint of Taylor & Francis LONDON AND NEWYORK * V TECHNISCHE INFORMATION S8IBLIOTHEK UNIVERSITATSBIBUOTHEK
More informationBRADSHAW CONSTRUCTION CORPORATION
BRADSHAW CONSTRUCTION CORPORATION TUNNELING SPECIALISTS From a Contractor s Perspective Bradshaw s Experience 54 years as a tunneling contractor 26 years as a microtunneling contractor 25 years using conventional
More informationS.No Description Unit Quantity Rate (Rs) Amount (Rs)
, S.No Description Unit Quantity Rate (Rs) Amount (Rs) 1 2 Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge method and preparation
More informationThe Use of the Roof The Upper Level Company
The Use of the Roof The Upper Level Company GTA - Your competent partner GTA made the upper level working By cooperation with the mining industry GTA have acquired vast experience in underground mining
More informationIndex. MEGA-Spike-Drill. Product presentation 4 General information 5 Technical specification 5. MEGA-Spike-Drill M9535 6
The tool specialists for the trade. Standard product line MEGA-Spike-Drill The tool specialists for the trade. MILLER GmbH, Präzisionswerkzeuge in Altenstadt is a member of the tool-traders-partner association
More informationExcellence in tunnel engineering. Consulting, planning, realisation
Excellence in tunnel engineering Consulting, planning, realisation Excellence in tunnel engineering Tunnelling remains one of the great challenges for engineers. Today, tunnels are built mainly in densely
More informationShort Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON
Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Earth Boring Co. Limited Trenchless Since 1947 Founded in Streetsville
More informationSELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley
SELECTION OF TUNNEL METHODS By: Dr. Gary S. Brierley Successful Tunnel Design 2 Produce a satisfactory finished facility for no more money and in no more time than is required for the existing ground conditions.
More informationDiaphragm wall Construction
Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support
More informationInnovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines
Innovation in the mining industry Derisking access to underground mines using Tunnel Boring Machines GHD Energy & Resources Brendan Henry Manager, Tunnels and Underground Spaces Safety Commitment Safety
More informationDesign and Implementation of the South Hartford CSO Tunnel
Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,
More informationEconomical mining of hard rock. Surface Miner 2500 SM
Economical mining of hard rock Surface Miner 2500 SM Breaking new ground in the efficient mining of hard rock Exploit mineral deposits right up to their boundaries How to mine useful minerals efficiently
More informationLATEST DEVELOPMENTS INCREASE THE CAPABILITIES OF SPIRAL WOUND LINERS
LATEST DEVELOPMENTS INCREASE THE CAPABILITIES OF SPIRAL WOUND LINERS John Monro, Interflow Pty Limited ABSTRACT For many years spiral wound liners have been the most used type of liner for the rehabilitation
More informationPerformance review of a pipe jacking project in Hong Kong
Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong
More informationLogistics of Limited Space Urban Tunnelling at Singapore s Mega Metro
Logistics of Limited Space Urban Tunnelling at Singapore s Mega Metro S. Smading The Robbins Company, Singapore ABSTRACT: Today s mega metro projects are using multiple TBMs in difficult ground, short
More informationHydraulic Rock Storage an efficient system for large grid scale storage
Hydraulic Rock Storage an efficient system for large grid scale storage Prof. Dr. Eduard Heindl, Heindl Energy GmbH, Stuttgart, Germany www.heindl- energy.com About us Heindl Energy GmbH, Stuttgart, Germany
More informationThe subsurface of the Métro is being reinforced with glass fibre
Case study Schöck Bauteile GmbH Judith Fischbach Vimbucher Strasse 2 76534 Baden-Baden, Germany Tel.: 0 72 23 967-247 E-mail: presse@schoeck.de Paris steps into the ring with Combar The subsurface of the
More informationPORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!
PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! FEBRUARY 12, 2014 FTBA CONSTRUCTION CONFERENCE PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner Operator Federal
More informationDeveloped countries require a modern infrastructure Roads Railways Power Communications Water Wastewater
Introduction to Soft Ground Tunnelling in Urban Environment Dr. Noppadol Phienwej Geotechnical and Geo-environmental environmental Engineering School of Engineering and Technology Asian Institute of Technology
More informationStructural Analyses of Segmental Lining Coupled Beam and Spring Analyses Versus 3D-FEM Calculations with Shell Elements
Structural Analyses of Segmental Lining Coupled Beam and Spring Analyses Versus 3D-FEM Calculations with Shell Elements C. Klappers, F. Grübl, B. Ostermeier PSP Consulting Engineers for Tunnelling and
More information8 Displacements near the Face of an Advancing Shaft
Displacements near the Face of an Advancing Shaft 8-1 8 Displacements near the Face of an Advancing Shaft 8.1 Problem Statement A circular shaft is excavated in chalk and lined with monolithic precast
More informationRAISE BORED SLOT RAISES: A MODERN MINING TECHNIQUE
RAISE BORED SLOT RAISES: A MODERN MINING TECHNIQUE Jarko Salo, TRB-Raise Borers Oy Slot raises refer to relief holes within a stope, intended to provide void space (or burncuts) for blasting, thereby allow
More informationField trips 7, 14, 15. Brenner Base Tunnel
Geo.Alp, Vol. 13 2016 205-214 Field trips 7, 14, 15 Brenner Base Tunnel Ulrich Burger 1, Georg Orsi 1, Roland Arnold 1, Andrea Lussu 1, Heimo Schierl 1 1 Brenner Basistunnel BBT-SE, Amraser Str. 8, 6020
More informationSlurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.
Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City
More informationRock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.
Rock Tunnel Engineering INTRODUCTION Tunnel a hole in the ground to provide for desired movement or as mobility channel. Serves as highway, railroad, pedestrian passageway, water conveyance, waste water
More informationProgress update (November to March) 03/23/2009 2
Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)
More informationLong-Term Relations Between Joint Venture Partners A Supplier s Perspective.
Long-Term Relations Between Joint Venture Partners A Supplier s Perspective. Dipl.-Ing. (FH) Gebhard Lehmann, Vice Chairman of the Board of Management, Herrenknecht AG Rotterdam, 2015-10-09 Herrenknecht
More informationEnergy & Data Transmission Systems for Underground Applications
Energy & Data Transmission Systems for Underground Applications Systems for Underground Applications Conductix-Wampfler energy & data transmission systems keep tunnels moving forward. Whether it s for
More informationEglinton Crosstown LRT Construction Liaison Committee
Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated
More informationTHE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject
56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea
More information