Progress update (November to March) 03/23/2009 2
|
|
- Frank Stevens
- 6 years ago
- Views:
Transcription
1 Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23,
2 Topics Covered Progress update (November to March) Launch Box Update Secant Wall Slurry Wall Concrete Decking Traffic Switch to East Side Shaft Site work at 69 th St. and 72 nd St. Upcoming Work 2
3 Launch Box Update Secant Pile Wall Construction Between 91 st and 93 rd Street 3
4 Secant Pile Wall Construction- 91 st to 93 rd St. Current Status Secant Wall Construction on West Side Completed Continuing Secant Wall Construction on East Side 4
5 Location of Secant Walls Portions Completely Installed SECANT WALL Portion Currently Being Installed 5
6 Secant Pile Wall Construction- 91 st to 93 rd St. 6
7 Secant Pile Wall Construction- 91 st to 93 rd St. 7
8 Launch Box Update Slurry Wall Construction Between 93 rd and 95 th Street 8
9 Slurry Wall Construction- 93 rd to 95 th St. Current Status Slurry Wall on West Side Completed Continuing to work on Slurry Wall Construction on East Side 9
10 Location for Slurry walls Portion Completely Installed CANT WALL SLURRY WALL Portion Being Installed Currently NORTH 10
11 Slurry Wall Work 2 nd Avenue Looking North Building Building Future 2 nd Avenue Subway 11
12 Slurry Wall Guide Wall 12
13 Slurry Wall Panel Excavation 13
14 Slurry Wall New Fence Panels to Protect Pedestrians 14
15 Slurry Wall Installation of Rebar Cages 15
16 Launch Box Update Concrete Decking Plan 16
17 Concrete Decking Plan Profile Looking North on Second Avenue Cap Beam Concrete Deck Panel Deck Beam Splice Box (Beam Pocket) 17
18 Concrete Decking Plan Current Status Cap Beams Are ALL Installed on the West Side All West Side Deck Beams are Installed All West Side Concrete Deck Panels are Installed Continuing Utility Relocation & Work Under Concrete Decking 18
19 Concrete Decking Construction Looking South on Second Avenue 19
20 Concrete Decking Construction Looking East on Second Avenue-MTA installed Rubber Noise Reduction Pads 20
21 Concrete Decking Construction Looking from Top of 2 nd Avenue 21
22 Launch Box Update Traffic Switch to East Side 22
23 Traffic Switch to East Side Switched Traffic to East Side on 03/10/
24 ShaftSiteworkat69 Site at th St. and 72 nd nd St St. 24
25 Shaft Site work at 69 th St. and 72 nd St. Current Status Pre-Construction Staging and Wok Zone Set-up Completed Sidewalk on West Side have been Reduced to 7 Feet All Parking Meters have been Removed Street Lights and Traffic Signals have been Relocated New Traffic Lane on West Side Completed Traffic Shifted to West Side Continuing Utility Relocation on East Side 25
26 Shaft Area Overall MPT Plan 69 th St. 70 th St. 72 nd 73 rd St. 71 st St. St. 26
27 69 th St. Shaft Section 27
28 Construction of New Traffic Lane on West Side 28
29 Utilities Relocation Work At Shafts 29
30 Utilities Relocation Work At Shafts 30
31 Shaft Area Bus Stop Relocation Removed Bus Stops between 69 th St. and 70 th St. and between 71 st St. and 72 nd St. New Bus Stop Between 70 th St. and 71 st St. has been Established 31
32 69th Street Garbage Disposal Plan Designated Garbage Disposal Areas 69 th Street Garbage Disposal Plan has been Coordinated d with Community and Implemented 32
33 72 nd Street Garbage Disposal Plan 72 nd Street Garbage Disposal Plan has been Coordinated with Community and Implemented 33
34 Upcoming Work Launch Box: Continue Slurry Wall Construction on East Side Continue Secant Wall Construction on East Side Continue placing Deck Beams and Concrete Deck Panels on East Side Continue Utility Work Under the Deck on East Side Continue Launch Box Excavation Controlled Rock Blasting and Removal Preparation 34
35 Controlled Rock Blasting and Removal The MTA has Performed Building Inspections Before Construction Started. The Buildings have Again been Inspected by Monitoring / Engineering Consultant Before this work Starts. Controlled Blasting Work has been Designed and Analyzed by a Specialty Blasting Consulting Expert. The Blasting Plans Are now Under Review and Must be Approved by NY City, Fire Department- Explosives Unit. NY City Fire Department Permit Will be Issued For All Aspects of This Blasting Work. Controlled Blasting and Rock Removal will be performed under a Permit Issued by NY City Dept. of Environmental Protection (DEP) The MTA has Installed Blasting Vibration Monitoring Equipment in Buildings at the Blast Area. Controlled Blasting WILL be monitored by NY City-Fire Dept, Explosives Unit. 35
36 Upcoming Work Shaft Area 69 th Street to 72 nd Street: Start Electric and ECS (Telephone) Utility Relocations. Start Gas Main Relocation. Start Steam Main Relocation. Start Water Main Relocation. 36
37 37
38 Second Avenue Subway Project Community Board 8 March 23 rd, 2009 March 27th, 2007
39 PROJECT SCHEDULE FOR 2009 DESIGN Final Design is scheduled to be completed in December 2009 PROCUREMENT IN 2009 Contract 2A: 96th Street Station - Site Work & Heavy Civil > Duration: 43 Months from April 2009 Contact 5A: 86 th Street Station - Open Cuts & Utilities Relocation > Duration: 22 Months from June 2009
40 Contract 2A: Scope of Work 92 nd Street 93 rd Street 94 th Street 95 th Street 96 th Street 97 th Street Existing Tunnel Connection Contract 2A: Site Work and Heavy Civil Ongoing Construction for TBM launch Box (Contract t 1) Contract 2A: 96th Street Station - Site Work & Heavy Civil > Duration: 43 Months from April 2009
41 Contract 5A Work Zone Lay out Plan West Side Stage of 2 nd Avenue Work Zone 83 rd Street 85 th Street 87 th Street Work Zone 2 nd Avenue 83 rd Street 85 th Street 87 th Street 82 nd Street 84 th Street 86 th Street 88 th Street East Side Stage of 2 nd Avenue Work Zone Work Zone 2 nd Avenue 82 nd Street 84 th Street 86 th Street 88 th Street Contact 5A: 86 th Street Station - Open Cuts & Utilities Relocation > Duration: 22 Months from June 2009
COMMUNITY BOARD EIGHT
SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and
More information3.6 Construction Methods
Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required
More informationMetro Purple Line Extension
metro.net/works Metro Purple Line Extension Construction Fact Sheet summer 2013 building the stations Construction at each station is estimated to take five to seven years. The station is a large box,
More informationHUDSON TUNNEL PROJECT
HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen
More informationGround Freezing for Tunnel, Shafts, and Adits
Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction
More informationCase study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan
Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -
More informationTRANSPORTATION RESEARCH FORUM March A State-of-the-Art of Underground Construction In Urban Areas
TRANSPORTATION RESEARCH FORUM March 2006 A State-of-the-Art of Underground Construction In Urban Areas Nasri Munfah PE Vice President Tunneling Practice Leader Parsons Brinckerhoff Underground Construction
More informationCROSSTOWN LRT Construction Liaison Committee November 1, 2017
CROSSTOWN LRT Construction Liaison Committee November 1, 2017 Avenue Construction Updates 2 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole
More informationSecond Avenue Subway. Quarterly Public Workshop. February 25, 2015
Second Avenue Subway Quarterly Public Workshop February 25, 2015 1 Current Project Status Overall Construction Progress is 78.7% complete as of 2/1/2015. All 10 SAS Contracts have been awarded for Phase
More informationFunding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.
FACT SHEET GENERAL INFORMATION The project extends the existing No.7 Line subway service via a 1.5 mile extension from Times Square to the new 34 Street Hudson Yards station located at West 34th Street
More informationUPCOMING DESIGN & CONSTRUCTION PROJECTS 2 nd Quarter 2018 (Project & Construction Management)
UPCOMING DESIGN & CONSTRUCTION PROJECTS 2 nd Quarter 2018 (Project & Construction Management) DESIGN PHASE PROJECTS Manchester - Rehabilitation and Repair of Wharf 2 Structural concrete repair, fender
More informationA. INTRODUCTION B. AIRBORNE NOISE
Chapter 12: Noise and Vibration A. INTRODUCTION This chapter of the FEIS assesses the potential for noise and vibration impacts from construction and operation of the proposed Second Avenue Subway. The
More informationPurple Line Extension Section 1 Construction Community Meeting September 26, 2017
Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western
More informationIronton Russell Bridge Project
Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationIronton Russell Bridge Project
Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationI-345 Feasibility Study Public Meeting
I-345 Feasibility Public Meeting December 11, 2012 December 11, 2012 1 Feasibility Team TxDOT Dallas District & Bridge Division Parsons Brinckerhoff Huitt-Zollars APM Halff Associates Civil Associates
More informationCROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY
CROSSRAIL INFORMATION PAPER TUNNELLING DURATION AND CONSTRUCTION STRATEGY This paper sets out the proposed Crossrail tunnel construction strategy and duration. It will be of particular relevance to those
More informationSafety and Security of the Patrons. June 12, 2017 Govind R. Sulibhavi Manager Track & Structures Division Maryland Transit Administration
Safety and Security of the Patrons June 12, 2017 Govind R. Sulibhavi Manager Track & Structures Division Maryland Transit Administration 1 Safety and Security of Patrons Adhere to MTA System Safety Program
More informationOngoing and Future Project Work. Construction Management
Ongoing and Future Project Work New Broward County Courthouse Tower 1,000 Car Courthouse Garage Midrise Building Renovations 714,000 square foot, 20-story Civil/Family Courthouse replacing 1950 s era
More informationCarpinteria Avenue Bridge Replacement Project Description Introduction
Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with
More informationThe Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.
The Technical and Contractual Matters of Bored Piling Works By Wallace Yeung Vibro (H.K.) Ltd. What is large diameter bored pile? How to construct a large diameter bored pile? Its advantages and limitation
More informationCrenshaw/LAX Transit Project Construction Update Meeting July 28, 2015
Crenshaw/LAX Transit Project Construction Update Meeting July, 2015 1 Project Overview Design-Build Contract - Walsh Shea Corridor Constructors (WSCC) 8.5 mile Light Rail Line Eight (8) new stations Three
More information7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by
Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than
More informationDIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS
OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006
More informationENGINEERING DESIGN & IMPROVEMENT STANDARDS
ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments
More informationProcurement timetable - FUT
Updated 15/02/2018/PM Procurement timetable - FUT Adjustement or addition from previous version Object designation / assignment (name of the procurement) Description/ scope Type Project (Extension part)
More informationIndirect and Cumulative Effects
Chapter 19: Indirect and Cumulative Effects A. INTRODUCTION The federal Council on Environmental Quality s regulations implementing the procedural provisions of the National Environmental Policy Act, set
More informationPattullo Bridge Replacement Project. Cost Report
Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...
More informationTHE KOSCIUSZKO BRIDGE PROJECT. The New York State Department of Transportation. Page 1
THE KOSCIUSZKO BRIDGE PROJECT The New York State Department of Transportation Page 1 THE KOSCIUSZKO BRIDGE PROJECT Constructed 70 years ago, the existing Kosciusko Bridge serves more than 160,000 vehicles
More informationSCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS
SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS Each Technical Proposal (Volume A of Package 2 of the Proposal) should address each of the items and requests for information described in this
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:
More informationDESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION
DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION INTRODUCTION By Dawn Tattle, P. Eng. Anchor Shoring & Caissons Ltd. TTC Yonge Station is the largest and most complicated of the
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationRt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016
Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb
More informationVenice Pumping Plant Dual Force Main Project Draft EIR
City of Los Angeles Venice Pumping Plant Dual Force Main Project Draft EIR 4.0 ALTERATIVES UDER COSIDERATIO Alternatives under consideration for this Project are defined by the alignment and construction
More information13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking
9-10 May 2016 KL Rectangular shield jacking/tbm and comparison with pipe roof Singapore Society for Trenchless Technology () Focuses Introduction of rectangular shield jacking Comparison of Pipe roof /
More informationLRFD Bridge Design Manual Changes
LRFD Bridge Design Manual Changes Dave Dahlberg Bridge Design Manual & Policy Engineer May 17, 2017 Bridge Office mndot.gov/bridge Overview 1) Concrete mix designations 2) Reinforcing bar development and
More informationSecond Avenue Subway
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction Phase 1 Overview The Re-routed Q train will
More informationPurple Line Extension Section 2 Construction Community Meeting February 22, 2018
Purple Line Extension Section 2 Construction Community Meeting February 22, 2018 Agenda Wilshire/Rodeo Station Advance Utility Relocation Demo of former Ace Gallery MOA for Design-Build Century City/Constellation
More informationStructural - Engineering Review Checklist
Structural - Engineering Review Checklist Project: List Corridor Criteria ID Review Priority (H,M,L) TOPICS S-_-## Structural Design Codes, Manuals and Specifications 6.1.0 REFERENCES DESIRED Criteria
More informationPROJECT ADDRESS: THRIFT AVE, WHITE ROCK, BC EXCAVATION -
Project Management By: SEMIAH :SITE SAFETY PLAN 5645-199th Street Langley, BC V3A 1H9 Tel: (604) 530-5646 Fax: (604) 530-0980 Website: www.marcon.ca PROJECT ADDRESS: 15241 THRIFT AVE, WHITE ROCK, BC EXCAVATION
More informationPipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.
Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods
More informationProject Purpose. Federal Railroad Administration
Project Purpose To preserve the current functionality of Amtrak s Northeast Corridor service and NJ TRANSIT s commuter rail service between New Jersey and Penn Station New York by repairing the deteriorating
More informationDistrict Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016
District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About
More informationI-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationContact Clark Public Utilities Construction Services department at (360) to initiate a request for service.
CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation
More informationCrossrail Brief to INCOSE Chris Sexton Technical Director
Crossrail Brief to INCOSE Chris Sexton Technical Director 24January 2012 Delivering a world-class affordable railway, safely, and through effective partnerships What is Crossrail? Largest civil engineering
More informationSECTION A1 EXCAVATION AND BACKFILL GENERAL
SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such
More information1. FROM (Bidder): (Name)
Tender No. [ ] Tender Forms Page 1 1. FROM (Bidder): (Name) (Address) TO: Alberta Transportation, Strategic Procurement Branch Main Floor, Twin Atria Building 4999 Avenue 5000 Edmonton, Alberta, T6B 2X3
More informationPurple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations May 2, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Rodeo Drive Station Seismic Boring Study Advance Utility Relocation
More informationOverview. O-Pile Attributes
Overview O-Pile is the most versatile, efficient and cost-effective steel retaining wall/support system that can replace standard Z sheet pile, combined pipe/ beam SSP, slurry, secant, contiguous concrete
More informationAPRIL 2017 UNDER CONSTRUCTION
APRIL 2017 UNDER CONSTRUCTION Highway construction is a complicated process that involves many tasks. Some of these, by nature, have an impact on nearby residents. To minimize these impacts, the Pennsylvania
More informationSAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS 1.0 DESCRIPTION This work shall consist of furnishing all materials and labor necessary for conducting an Osterberg Cell (O-cell)
More informationCHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS
CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS 2006 LADOTD ENGINEERING CONFERENCE Kim Martindale Garlington, P.E. Pavement & Geotechnical Services February 13, 2007
More informationDan Carrier Parsons Brinckerhoff Project Manager Cooper River Bridge Charleston, South Carolina
OTEC 2004 Dan Carrier Parsons Brinckerhoff Project Manager Charleston, South Carolina Dan Carrier Background! Hazelet & Erdal 1966-1984 (Cincinnati, Ohio Office) Bridge Designer! Parsons Brinckerhoff 1984-2004
More informationLos Angeles Westside Purple Line Extension Project Challenges and Lessons Learned
Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned Ashok Kothari, P.E. WSP USA, Sr. Vice President Los Angeles, California Michael McKenna, P.E. LACMTA Executive Officer,
More informationElectrical Work. NOV Embankments Over Swamps and Compressible Soils
GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification
More informationBuilding pit District adjacent to St.Katharinenkirche Hamburg, Germany
Building pit District adjacent to St.Katharinenkirche Hamburg, Germany Implenia Spezialtiefbau GmbH Infrastructure - Northern Branch Heidenkampsweg 81 D-20097 Hamburg GERMANY T +49 40 229257-201 F +49
More informationBridge Asset Management City of Battle Creek Planning and Projects
Bridge Asset Management City of Battle Creek Planning and Projects Michigan Bridge Conference, March 20, 2013 Gregory B. Rickmar P.E., Public Works Department, City of Battle Creek Alan Halbeisen, P.E.
More informationTunnel. Immersed Tunnels
Tunnel Tunnels are underground spaces, usually, in a tubular shape with substantial lengths. They can either be man-made or natural and can be used as passageways, storages, carriageways and utility ducts.
More informationGet In, Get Out, Stay Out!
Get In, Get Out, Stay Out! FHWA Accelerated Bridge Construction Program By Gary Jakovich, P.E. Senior Bridge Engineer, FHWA Virginia Concrete Conference Richmond, VA March 6-7, 2007 Federal Highway Administration
More informationBIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83
Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications
More informationAndy Kirby. Prepared for: Senior Project Manager for The Church of Jesus Christ of Latter-day Saints. April Graduate Mentor: Andrew Luna
Prepared for: Andy Kirby Senior Project Manager for The Church of Jesus Christ of Latter-day Saints April 2015 Graduate Mentor: Andrew Luna PROVO, UT Department of Civil & Environmental Engineering Ira
More informationCapital Rail Constructors: Quarterly Update to MWAA Board of Directors
Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule
More informationKIEWIT FOUNDATIONS GROUP
KIEWIT FOUNDATIONS GROUP KIEWIT AT-A-GLANCE With a strong local presence and access to a vast network Keeping safety at the forefront, the Kiewit Foundations Group self- OUR MARKETS of industry experts,
More informationSR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014
SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report
More informationCITY OF SAFETY HARBOR ENGINEERING
CITY OF SAFETY HARBOR ENGINEERING The Engineering Department provides the city with technical services including design of construction and maintenance projects, review of development plans, field surveys,
More informationFactor Potential Effects Mitigation Measures
Natural Environment No impacts of provincial significance to the natural environment are anticipated for the rapid transit project. Other impacts and how they will be mitigated are outlined in the table
More informationSPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006
Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable
More informationBrooklyn Station Construction Open House
Brooklyn Station Construction Open House November 16, 2011 Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Louise Little, Greater University
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationTunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions
City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles
More informationWINTERHAVEN PUBLIC SAFETY FACILITY PROJECT
WINTERHAVEN PUBLIC SAFETY FACILITY PROJECT Funded by: California Department of Housing and Community Development (HCD) through its Community Development Block Grant (CDBG) Program and the County of Imperial.
More informationAgenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014
Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More informationSECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
PART 1 GENERAL 1.1 DESCRIPTION A. Temporary Utilities: Electricity, lighting, heating, cooling, ventilation, water, and sanitary facilities. B. Temporary Controls: Barriers, fencing, erosion control, exterior
More informationHALIFAX REGIONAL MUNICIPALITY MUNICIPAL DESIGN GUIDELINES
HALIFAX REGIONAL MUNICIPALITY MUNICIPAL DESIGN GUIDELINES 2013 PART B STANDARD DETAILS Municipal Design Guidelines Contents PART B: STANDARD DETAILS Municipal Roads/Streets HRM 1 HRM 2 HRM 3 HRM 4 HRM
More informationCity of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018
City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House March 27, 2018 Agenda 1. Construction Team 2. Anticipated Construction Staging 3. Anticipated Construction Schedule
More informationCity of Wentzville. Standard Specifications and Construction Details Amendment List
Amendment No. 1 Standard Specifications and Construction Details Amendment List Date: September 21, 2009 Subject: SCD 700.23 - Residential Entrance Layout and drawing revised to more clearly show the location
More informationOutcomes Summary: Consultation on noise barrier options near Glamis Street, Armitree Street, and Rosebank Avenue, Kingsgrove January 2017
Outcomes Summary: Consultation on noise barrier options near Glamis Street, Armitree Street, and Rosebank Avenue, Kingsgrove January 2017 Overview In response to public submissions made during the Environmental
More informationA/E REVIEW CHECKLIST STRUCTURAL
A/E REVIEW CHECKLIST STRUCTURAL Reviewers should - Use Checklists when reviewing any type of VA construction project for the following disciplines: Site and Landscape, Architectural, Structural, Plumbing,
More informationSaudi Aramco General Bid Slates (GBS)
Saudi Aramco General Bid Slates (GBS) Copyright 2015, Saudi Aramco. All rights reserved. Agenda Saudi Aramco Contracting Strategy Saudi Aramco General Bid Slate (GBS) General Bid Slate Work Types 2 Saudi
More informationBellows Falls Tunnel
Bellows Falls Tunnel Track Lowering Project for Modified Double Stack Container Cars and Auto-Racks ECI Rail Constructors, Inc. Kenneth A Pidgeon, PE Circa 1913 during flood Project Background Project
More informationApplication of Accelerated Bridge Construction for Local Agencies
Application of Accelerated Bridge Construction for Local Agencies APWA Public Works Conference November 9, 2017 Dorie Mellon Senior Bridge Engineer, Caltrans Matt Randall Senior Engineer, County of Placer
More informationCONSTRUCTION ENGINEERING SERVICES
CONSTRUCTION ENGINEERING SERVICES Contact Our clients have relied upon TECTONIC to ensure the quality of construction projects and protect the value of their assets by employing: Experienced, Qualified
More informationKIEWIT FOUNDATIONS GROUP
KIEWIT FOUNDATIONS GROUP KIEWIT ADVANTAGE LOCAL CONTRACTOR, EXPANSIVE REACH With a strong local presence, access to a vast network of resources throughout North America and a focus on self-performing work,
More informationCHAPTER 11 CONDUITS AND FITTINGS
CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1
More informationSWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS
Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationSPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION
Proceedings of the 1999 Winter Simulation Conference P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds. SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION Simaan M.
More informationREPORT Condition D19 Permanent Noise Barriers
REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended
More information+/0'-/12!"&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=!
"#$%&'(&)&$*+,,-,,%-./ +/0'-/12"&21'1/345$1.1/36#''-7-8#9:;&?-/3@1$-2/#$&'#.7A1/0/0-B$#C-2/D&.&7-$&.*>EF-$G1,#$?#$/0-,1/-*1*/0-$1,H&,,-,,%-./?#$/0-.-A+/0'-/12"&21'1/3/0&/ 1,9-1.79E1'/#./0-7$#E.*,#?5$1.1/36#''-7->20##''#2&/-*&/
More informationDIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS
DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationTel: Neil: Tony: Website:
Australian Tunnelling Services are a consortium that has been formed to offer specialist underground services to both clients and contractors in the Civil Engineering, Mining & Building Industries. The
More informationSTATE AID GUIDE FOR: Updated: December 16, 2005
STATE AID GUIDE FOR: Updated: December 16, 2005 1. AFTER THE FACT RIGHT OF WAY DEPARTMENT OF MINNESOTA TRANSPORTATION 2. MISCELLANEOUS AFTER THE FACT Traffic Signals, Lighting, Retaining Walls, Sidewalk,
More informationThe Corporation of The City of London
The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and
More information