Major Building and Special Structures

Size: px
Start display at page:

Download "Major Building and Special Structures"

Transcription

1 TECHNICAL SESSION 1 Major Building and Special Structures Moderator Russell B. Price, P.E. Suncoast Post-Tension L.P. Houston, Texas

2 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium Post-Tensioning at Invesco Field at Mile High Dennis M. Wittry, P.E., S.E. Walter P. Moore & Associates, Inc. Houston, Texas Post-tensioning was used extensively at Invesco Field at Mile High, the new 76,152-seat home to the Denver Broncos (NFL) and Colorado Rapids (MLS). The structural framing for the concourses of the stadium consist of 8 wide, 29 deep post-tensioned circumferential pan joists framing to post-tensioned 33 wide x 29 deep transverse girders. This structure was developed through post-bid, value engineering exercises with the concrete sub-contractor, Phipps/Baker, joint venture of Baker Concrete and Phipps Construction. The two-way post-tensioned system was considered due to the long joist spans (40 to 50 ) and high superimposed loads (3 topping slabs, 100 psf live loads and numerous masonry walls). Early scheme studies had concluded that a system of cast-in-place girders and columns with precast concrete double tee infill, which has been used for several other NFL stadiums, was the most economical. Schematic pricing of the two-way post-tensioned scheme, however, indicated an approximate $2 million savings over the original scheme. Creative long-pan forming and shoring systems developed by Baker Concrete and structural design that eliminated the need for reshoring resolved initial concerns about schedule and quality of finish. Additionally, the post-tensioned system allowed for a shallower structural depth, providing additional mechanical plenum space and allowing for the floor-to-floor height at one of the suite levels to be reduced for additional cost savings. Concerns with the original precast infill system were as follows: Curved Geometry Flying Formwork Structural Depth Coordination between precast and cast-in-place Excessive Topping Slab Advantages to the use of this two-way, post-tensioned system were: Cost. Approximately $2 million savings over original structural system. Geometry. The cast-in-place concrete system was better able to handle the varying geometry and loading. Structural Depth. Post-tensioning allowed for the structural depth to be reduced by 5 typically. Durability. As an open-air stadium, exposure to the elements was a major concern. Post-tensioning allowed the tensile stresses to be limited therefore reducing the number and size of flexural cracks. Reduced congestion. The original mild-girder system typically required multiple layers of reinforcement. Post-tensioning significantly reduced the amount of reinforcement required and eliminated the need for multiple layers of reinforcement in most members. Deflection. With significant extents of masonry, most of the concrete framing was under strict deflection limits. In most cases, post-tensioning allowed for these deflection limits to be meet without increasing member sizes. Challenges to the two-way, post-tensioned system used: Schedule. The original schedule of the precast infill system had to be maintained. Closed Geometry. The closed geometry required one-way pulls with building sections of almost 300 feet. Pour strips were required at two floors to allow the concourse to be closed. Education. The Owner and Sub-contractors were not familiar with post-tensioning and education was required to dispel post-tensioning myths. Copyright - Post-Tensioning Institute 2 All rights reserved

3 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium 2004 Post Tensioning Institute Conference Case Study: Invesco Field at Mile High Stadium Presented by Dennis M. Wittry, P.E., S.E. Walter P. Moore and Associates, Inc. Presentation Outline Overview of Invesco Field Why Did we Choose PT? Original Scheme Advantages of PT Scheme Challenges The Results Questions Overview of Invesco Field Overview of Invesco Field Located in Denver, Colorado Denver Broncos (NFL) Colorado Rapids (MLS) 76,125 seat Stadium 5 th Largest in NFL 124 Suites $408,000,000 Total Cost Completed August 2001 Overview of Invesco Field 1,700,000 Square Feet 5 Framed Levels Upper and Lower Concourse Levels 2 Suite Levels & 1 Club Level Concourse Structural System 2-way Post-Tensioned CIP Concrete PT Pan Joists and PT Girders 256 Miles of Post-Tensioning Charlotte to Atlanta 244 miles Overview of Invesco Field Design/Build Joint Venture Turner Construction HNTB Corporation Architects HNTB Sports Architecture Fentress Bradburn Architects Burtram A. Bruton and Associates Structural Engineer Walter P. Moore The Sheflin Group Copyright - Post-Tensioning Institute 3 All rights reserved

4 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium Overview of Invesco Field Overview of Invesco Field Contractor Turner Construction Empire Construction Services Alvarado Construction Concrete Sub-Contractor Gerald H. Phipps Baker Concrete Post-Tensioning Supplier/Installer Suncoast Post-Tension - Supplier Parker Steel - Installer Why Did We Choose PT Originally We Didn t! Why Did We Choose PT Original Concourse Structural System Mildly Reinforced CIP Concrete Frame with Double Tee Infill Preferred System by Turner Construction Used At 3 Other NFL Stadiums by Turner Bank of America Stadium (Charlotte) M&T Bank Stadium (Baltimore) Paul Brown Stadium (Cincinnati) Other Schemes Reviewed Structural Steel Mild Reinforced Concrete Beam and Slab Original Precast Infill System Copyright - Post-Tensioning Institute 4 All rights reserved

5 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium Original Concourse Structural System Advantages of the Precast System Lateral Frame Provided by CIP Elements Double Tees Could Easily Handle Spans Double Tee Spans of up to 50 + Quick Erection Time Precast is Very Prevalent in Denver Turner was Very Familiar with System Least Costly Scheme of 3 Initially Considered Why Did We Consider Changing? Geometry Curved Concourse Geometry 6 Different Radii Around Bowl Limited Repetition for Precast Load Variations Reduced Repetition Why Did We Consider Changing? Geometry Curved Concourse Geometry 6 Different Radii Around Bowl Limited Repetition for Precast due to Geometry Load Variations Reduced Repetition Excessive Flying Formwork Radial Beams Required for Lateral Stiffness Almost as Much Shoring as for full CIP Deck Structural Topping Slab Required Why Did We Consider Changing? Depth Limitations Girders were Overly Congested Trade Coordination Tolerance Issues b/w CIP and Precast More Crane Time Excessive Jointing in Topping Slab Pattern to follow edges of Double Tees Copyright - Post-Tensioning Institute 5 All rights reserved

6 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium Why Did We Choose PT Solution: Two-Way Post-Tensioned Cast-in-Place Pan Joist System Tendon Support Bar Unbonded Post-Tensioning 24 5 VARIES: TYP 30, 53, OR 66 8 Post-Tensioned Joists Why Did We Choose PT Why Did We Choose PT Unbonded Post-Tensioning Top Mild Reinf. 5 Bottom Mild Reinf Post-Tensioned Joist Beyond Post-Tensioned Joists Post-Tensioned Girder Why Did We Choose PT Post-Tensioned Girder Advantages PT Girders Reduce Congestion Cast-in-Place Better Handles Geometry PT Joists Allowed for Long Spans Shallower Structural Depth Allowed for a Reduction in Building Height Inherent Lateral Stiffness Better Crack Control & Durability Fully Encapsulated Tendons Copyright - Post-Tensioning Institute 6 All rights reserved

7 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium Why Did We Choose PT Challenges Schedule Needed to Maintain Tight Construction Schedule Solution: Custom Long Pan Forms Minimized Shoring Expedited Pan Turnover Formwork Re-Use Critical to Economy Adjustable End Cap Increased Formwork Repetition Upgrade Framing to Eliminate Reshores Added Value Provided Higher Finish Level for Exposed Panwork Custom Long Pans Why Did We Choose PT Challenges Closed Geometry Concourse Broken into 8 Sections Required One-Way Pulls Sections Up to 280 Long Solution: Add Tendons for 1 st Pour of Each Section Pour Strip Used to Close Circle Stress Pockets in Slab for Add Tendons The Results Challenges Myths and Rumors Regarding PT CIP Post-Tensioning not Prevalent in Denver Owner & Sub-Contractors Didn t Understand PT Solution PT Education Session Lead by Walter P. Moore / Baker Concrete / Suncoast Owner, Contractor and All Major Subs Represented Explained Benefits of PT and Dispelled Myths Copyright - Post-Tensioning Institute 7 All rights reserved

8 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco Field Stadium The Results Delivered On Schedule Improved Durability Improved Architectural Appearance $2,000,000 Saved Over Precast Infill System! Questions? Copyright - Post-Tensioning Institute 8 All rights reserved

9 Construction of the Four Seasons Hotel and Tower in Miami Phil Arana, P.E. Ricardo Lizarazu, P.E. Suncoast Post-Tension, L.P. Miami Division A general overview of the Four Seasons Hotel and Tower at Miami building is presented. Structural concepts, structural main frame-work and the posttensioned slab systems are discussed. Architectural, as well as essential structural challenges regarding mixed use, functionality and local environmental conditions are described. Detailed information about the core inside a core structural system, as well as the wind analysis is given. Construction phase problems and main concerns are addressed and solutions adopted are illustrated. Special attention is given to the primary slab system used on the elevated levels, in which a post-tensioned concrete slab was used. Illustrations are mainly focused on solutions given during the construction phase on issues related to the pour sequence of the slab, pour breaks and schedules, as well as special connection details developed for joining the slab system to the main inner core system and to the perimeter column-beam frame. This was done to allow reduction of overall construction time using a system of jump-forms for the inner core, which required the casting of the slabs after the walls of the inner core were poured. Details are presented for the use of post-tensioning on transfer areas of slabs and on shear walls. A final discussion is made on the future of high-rise construction. Copyright - Post-Tensioning Institute 9 All rights reserved

10 FOUR SEASONS BUILDING STRUCTURAL CONCEPTS STRUCTURAL MAIN FRAMEWORK POST-TENSIONED CONCRETE SLAB SYSTEM FOUR SEASONS HOTEL AND TOWER FACTS: Location:....Miami Owner:... Millennium Partners, NY Construction Manager: Bovis Lend Lease, Miami Architect:... Bermello Ajamil & Partners Architect:... Gary Edward Handel Assoc. Structural Engineer:.... DeSimone Consulting Eng. Post-tension Specialty Eng. & Supplier... Suncoast Post-tension Courtesy of Millennium Partners GENERAL FACTS Courtesy of Desimone Consulting Engineers Tallest Building South of Atlanta Tallest residential building south of New York City Among 50 tallest buildings in the world 8th tallest residential building in the world 67 floor mixed use Retail, Parking, Office, Hotel, Condominium Total area: 1,900,000 ft 2 Value $ 257,000,000 Date of Completion of Construction: 2003 HOTEL AND TOWER FEATURES 789 ft tall building 222 Rooms in 5 star Four Seasons Hotel 45,000 ft 2 fitness and spa facility 186 luxury condominiums 84 room extended stay apartments 200,000 ft 2 Class A office space 2 Acre pool terrace 10,600 ft 2 of retail space 934 parking spaces MAIN STRUCTURAL FACTS Reinforced Concrete Structure Tubular Lateral System Core Shear Walls & Perimeter Columns Post-tensioned slabs Span between supports between 40 and 50 ft Wind Tunnel Analysis Courtesy of Bovis Lend Lease Courtesy of Bovis Lend Lease Copyright - Post-Tensioning Institute 10 All rights reserved

11 CONSTRUCTION PHASE Formwork consisted of flat slab spanning between interior cores and perimeter beam-column frames. Cores were formed independently of a crane using PERI-ASC self climbing system After very short learning curve, form contractor crew accomplished very effective schedules. Fast cycle had to be slowed down to a 4-day cycle in order to not climb too far ahead of slab and facade work. Courtesy of Peri - Formwork and Scaffolding Courtesy of Peri - Formwork and Scaffolding UPPER LEVELS LAYOUT UPPER LEVELS SOFFIT LAYOUT Columns at facade Spandrel beam STRUCTURAL SLAB DESIGN BANDED TENDON LAYOUT General Layout of PT system Pour Sequence Pour Schedule Slab connection to main frame system Link beam construction PT anchorage placement Form savers for main mild reinforcement Breakdown areas Use of PT at transfer levels Copyright - Post-Tensioning Institute 11 All rights reserved

12 BANDED TENDON PERSPECTIVE DISTRIBUTED TENDON LAYOUT UNIFORM TENDON PERSPECTIVE POUR SEQUENCE - SCHEDULE Copyright - Post-Tensioning Institute 12 All rights reserved

13 INNER CORE SLAB CONNECTION TO MAIN FRAME SYSTEM PT ANCHORAGE PLACEMENT & REINFORCEMENT FORM SAVERS Top Slab Rebar Form Saver Copyright - Post-Tensioning Institute 13 All rights reserved

14 PT Reaction CONNECTION OF SLAB TO THE OUTER FRAME Maximum efficiency of PT tendons Column Schematic Not To Scale Bar placing due to anchor plate location Maximum efficiency of PT tendons Copyright - Post-Tensioning Institute 14 All rights reserved

15 LINK BEAM CONSTRUCTION Copyright - Post-Tensioning Institute 15 All rights reserved

16 BREAK-DOWN AREAS Link beams extended out to shorten spans and/or for stiffening areas Drops used to shorten spans and/or for stiffening areas USE OF POST- TENSIONING AT TRANSFER LEVELS Copyright - Post-Tensioning Institute 16 All rights reserved

17 Columns that will be hanging from this level Columns starting at this level 3rd Level 4th Level 3rd Level 4th Level Uniform cables with harped profile to receive band Concentrated band to pick up columns PT Tendons Profile at 4th Level Uplift force from band Column Reaction Copyright - Post-Tensioning Institute 17 All rights reserved

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari Thesis Presentation - Spring 2006 Contents Introduction Building Professionals Existing Structure

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Executive Summary The proposed thesis will include an investigation of two different alternative structural

More information

A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS

A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS Neil F. Dunbar Ketch u m-kon ke l-barrett-n i cke I-A u sti n Consulting Engineers Denver, Co!oredo Describes several structural systems using both

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

THE FORENSIC MEDICAL CENTER

THE FORENSIC MEDICAL CENTER THE FORENSIC MEDICAL CENTER Image courtesy of Gaudreau, Inc. TECHNICAL REPORT #2 OCTOBER 26, 2007 KEENAN YOHE STRUCTURAL OPTION DR. MEMARI FACULTY ADVISOR EXECUTIVE SUMMARY Image courtesy of Gaudreau,

More information

Hilton Baltimore Convention Center Hotel Western Podium

Hilton Baltimore Convention Center Hotel Western Podium Hilton Baltimore Convention Center Hotel Western Podium CHRIS SIMMONS Structural Option Faculty Consultant: Dr. Ali M. Memari Technical Report 2 TABLE OF CONTENTS EXECUTIVE SUMMARY. Page 3 INTRODUCTION..

More information

Thesis Proposal 12/13/06

Thesis Proposal 12/13/06 Photo courtesy of OTO Development, http://www.otodevelopment.com/ Dr. Memari Thesis Advisor Thesis Proposal 12/13/06 Executive Summary Structural System The in, is an eleven story hotel complex which reaches

More information

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems Technical Report 2 Pro-Con Structural Study of Alternate Floor Systems Columbia University Broadway & 120 th Street, New York, NY Jonathan R. Torch Pennsylvania State University Architectural Engineering

More information

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal PTI Journal Technical Session Paper USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS By FLORIAN AALAMI Authorized reprint from: December 2018 issue of the PTI Journal Copyrighted 2018, Post Tensioning

More information

Thin Slab Floor Systems for High Rise Towers. By Steven M. Baldridge, P.E., S.E., and Jeffrey Yoders

Thin Slab Floor Systems for High Rise Towers. By Steven M. Baldridge, P.E., S.E., and Jeffrey Yoders Thin Slab Floor Systems for High Rise Towers By Steven M. Baldridge, P.E., S.E., and Jeffrey Yoders SEPTEMBER 2012 Professional Development Series Thin Slab Floor Systems for High Rise Towers By Steven

More information

Technical Report #2 10/26/06

Technical Report #2 10/26/06 Photo courtesy of OTO Development, http://www.otodevelopment.com/ Dr. Memari Thesis Advisor Technical Report #2 10/26/06 Executive Summary Systems Overview Hollow Core Plank (precast) Solid Flat Slab (precast)

More information

Miami Marlins Baseball Park

Miami Marlins Baseball Park Miami Marlins Baseball Park Roof Support Track Beams Construction by Incremental Lifting Project Owner Miami Dade County General Contractor Hunt-Moss JV Frame Contractor Formworks-Baker Concrete JV Engineer

More information

POST-TENSIONING VS. PRESTRESSING

POST-TENSIONING VS. PRESTRESSING POST-TENSIONING VS. PRESTRESSING Miroslav F. VEJVODA, MBA, P.E. Managing Director Engineering & Professional Development PURPOSE STATEMENT This seminar is intended to develop an understanding for the differences

More information

CSU GUIDELINES. April 27, 2018 FOR POST-TENSIONED CONCRETE STRUCTURES.

CSU GUIDELINES. April 27, 2018 FOR POST-TENSIONED CONCRETE STRUCTURES. CSU GUIDELINES FOR POST-TENSIONED CONCRETE STRUCTURES April 27, 2018 http://www.calstate.edu/cpdc/ae California State University Seismic Review Board Technical Guidelines January 9, 2018 The CSU Seismic

More information

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1 Department of Civil Engineering Lecture 2.1 Methods of Prestressing Advantages of Prestressing Section remains uncracked under service loads Reduction of steel corrosion (increase durability) Full section

More information

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Christopher McCune Structural Option Eight Tower Bridge Faculty Advisor: Dr. Hanagan October 31 st, 2005 Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems Executive Summary This technical

More information

NATIONAL HARBOR BUILDING M

NATIONAL HARBOR BUILDING M NATIONAL HARBOR BUILDING M 120 Waterfront St. Oxon Hill, Maryland Ryan Sarazen Structural Option Senior Thesis Presentation Spring 2008 Faculty Consultant Dr. Lepage BUILDING LOCATION BUILDING M SITE PLAN

More information

181 Fremont San Francisco, CA. Tech Report 3 10/17/2014. PSUAE Structural Option Advisor: Dr. Thomas Boothby

181 Fremont San Francisco, CA. Tech Report 3 10/17/2014. PSUAE Structural Option Advisor: Dr. Thomas Boothby 181 Fremont San Francisco, CA Tech Report 3 10/17/2014 PSUAE Structural Option Advisor: Dr. Thomas Boothby Caroline Klatman cjk5258@psu.edu October 17, 2014 Dr. Thomas Boothby The Pennsylvania State University

More information

Technical Report #2. Matthew R Peyton

Technical Report #2. Matthew R Peyton Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study

More information

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung POST-TENSIONING APPLICATION AND TECHNOLOGY Moe Kyaw Aung Overview 1. Background 2. Basic Design Concept 3. Application and Benefits 4. Components of Post-tensioning System 5. Installation Process 6. Construction

More information

Shoring and Reshoring Fundamentals

Shoring and Reshoring Fundamentals Shoring and Reshoring Fundamentals by Mary Bordner Tanck, PE SHORING AND RESHORING FUNDAMENTALS Because it has such a significant impact on schedule and material movements, it is important for everyone

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 2 October 29 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

Pro-Con Structural Study of Alternate Floor Systems

Pro-Con Structural Study of Alternate Floor Systems Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary

More information

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering Outline Project Original Proposal Structural Design Proposal Design Objectives Design Criteria Presentation

More information

NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS

NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS NON-LINEAR STRUCTURAL INTEGRITY ANALYSIS AHMAD RAHIMIAN, PhD, PE, SE Dr. Ahmad Rahimian., PE, SE is President of Cantor Seinuk Structural Engineers in New York City. An expert in the behaviour of steel

More information

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #2 October 31,

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #2 October 31, 1 Executive Summary: Pro-Con Structural Study of Alternate Floor Systems is an investigation into possible alternative structural systems for Lexington II in Washington, D.C. For this report, several structural

More information

Topic Outline. Two Stage Analysis Procedure: Podium Design. Part 2: Rigid Lower Portion Philip Miller, S.E. 2/8/2018

Topic Outline. Two Stage Analysis Procedure: Podium Design. Part 2: Rigid Lower Portion Philip Miller, S.E. 2/8/2018 Two Stage Analysis Procedure: Podium Design Part 2: Rigid Lower Portion Philip Miller, S.E. Topic Outline Types of Podium Construction Example Buildings PT Basics PT Analysis Modeling Tips Load Balancing

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Newfoundland at Canary Wharf

Newfoundland at Canary Wharf Figure 1. Newfoundland during construction. Source: A. Denia Berrocoso. Newfoundland at Canary Wharf Angel Denia Berrocoso BSc, MSc, DIC Assistant Engineer, WSP UK Keywords: Hybrid structure, Diagrid,

More information

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete

More information

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options River Tower at Christina Landing Wilmington, DE Joseph Bednarz Structural Option Faculty Advisor: Dr. Boothby Executive Summary January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign

More information

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit Providing Engineered Concrete Solutions Precast and Mission Critical Facilities A Natural Fit Total precast solutions eliminate trade overlap in the construction of the core and shell system A total precast

More information

Franklin Square Hospital Center Patient Tower

Franklin Square Hospital Center Patient Tower Thomas Weaver Structural Option Franklin Square Hospital Center Patient Tower Baltimore, MD Thomas Weaver Structural Option AE 481W Senior Thesis Consultant: Professor M. Kevin Parfitt 12/14/2009 Page

More information

Totaling approximately 617,000

Totaling approximately 617,000 Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street

More information

C H A N T I L L Y, V A

C H A N T I L L Y, V A TOWERS CRESCENT BUILDING F CHANTILLY, VA Executive Summary This report is a study of the advantages and disadvantages of various potential structural floor systems for use in Towers Crescent Building F

More information

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems

A Composite Structural Steel and Prestressed Concrete Beam for Building Floor Systems University of Nebraska - Lincoln DigitalCommons@University of Nebraska - Lincoln Architectural Engineering -- Dissertations and Student Research Architectural Engineering Spring 4-20-2012 A Composite Structural

More information

Council on Tall Buildings. and Urban Habitat CAYAN TOWER CTBUH BEST TALL BUILDING MIDDLE EAST & AFRICA

Council on Tall Buildings. and Urban Habitat CAYAN TOWER CTBUH BEST TALL BUILDING MIDDLE EAST & AFRICA CAYAN TOWER CTBUH BEST TALL BUILDING MIDDLE EAST & AFRICA CTBUH AWARDS 2014 13 TH ANNUAL AWARDS NOVEMBER 6, 2014 SKIDMORE, OWINGS & MERRILL LLP CAYAN GROUP REAL ESTATE & INVESTMENT GEORGE J. EFSTATHIOU

More information

HIGH RISE CONDO SOHO, NEW YORK, NY

HIGH RISE CONDO SOHO, NEW YORK, NY HIGH RISE CONDO SOHO, NEW YORK, NY TECHNICAL ASSIGNMENT 1 October 5, 2006 Joseph The Pennsylvania State University Structural Option Faculty Advisor: Andres Lepage TABLE OF CONTENTS TABLE OF CONTENTS 2

More information

CBM Engineers India COMPANY PROFILE. Structural Engineering Firm established in 1975 in Houston, Texas - USA Services Offered:

CBM Engineers India COMPANY PROFILE. Structural Engineering Firm established in 1975 in Houston, Texas - USA Services Offered: 1 COMPANY PROFILE Structural Engineering Firm established in 1975 in Houston, Texas - USA Services Offered: Full Design Built Value Engineering Peer Review Construction Administration Office Locations:

More information

Structural Option April 7 th, 2010

Structural Option April 7 th, 2010 Gravity System (Depth Topic I) Post Tensioned Slab A new floor system was designed in an attempt to create a more consistent flooring system throughout the entire building. This new design consists of

More information

Campus Square Buildings C & D Lehigh University, Bethlehem, PA

Campus Square Buildings C & D Lehigh University, Bethlehem, PA Depth Study: Structural Redesign As noted previously, Building C is the focus of the spring semester redesign, though the proposed alternatives could be applied to the other buildings in the complex, including

More information

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be

More information

RETHINKING MULTIFAMILY RESIDENTIAL

RETHINKING MULTIFAMILY RESIDENTIAL RETHINKING MULTIFAMILY RESIDENTIAL Presented by: Neil Wexler, PhD PE Ali Maher, PE ABOUT US- WEXLER ASSOCIATES Founded 35 years ago NYC Structural Engineers Forensic Work Active in various markets BIM

More information

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...

More information

North Mountain IMS Medical Office Building

North Mountain IMS Medical Office Building North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 1 October 5 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,

More information

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 1 of 23 The following presentation discusses

More information

GUIDELINES FOR EXECUTION OF ADAPT-PT 1

GUIDELINES FOR EXECUTION OF ADAPT-PT 1 Structural Concrete Software System GUIDELINES FOR EXECUTION OF ADAPT-PT 1 Update: December 09, 2004 TN172 guide_to_run_pt_12 120904 The guidelines presented will assist you in the selection of design

More information

Matthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA

Matthew Kutzler. Structural Option Spring Buildings C and D Campus Square, Lehigh University Bethlehem, PA Matthew Kutzler Structural Option Spring 2004 Buildings C and D Campus Square, Lehigh University Bethlehem, PA Located at Lehigh University in Bethlehem, PA Complex consists of four dormitories and a parking

More information

Post-Tensioned Concrete in Buildings

Post-Tensioned Concrete in Buildings Post-Tensioned Concrete in Buildings A Half-Century Overview By Ken Bondy PTI Convention May 2012, Nashville 49 Years Ago It was 1963 I was 23 years old I had completed my MSCE course work at UCLA I was

More information

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report 1 THE ODYSSEY ARLINGTON, VA Aaron Snyder Structural Option Advisor: M. Kevin Parfitt, PE Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report Executive

More information

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth Analysis 2 Pre-fabricated -Structural Breadth Background The current façade design calls for stick built 3-5/8 masonry on a 7-5/8 metal stud back-up with exterior sheathing board, 1 cavity board insulation

More information

Simplified Building Schematic for Typical Floor (Levels 9 through 22):

Simplified Building Schematic for Typical Floor (Levels 9 through 22): Introduction to Structural System Simplified Building Schematic for Typical Floor (Levels 9 through 22): Key: - Tower Columns - Tower Shear Walls - Parking Garage Columns - Parking Garage Shear Walls Solid

More information

Learning Objectives. A Brief History

Learning Objectives. A Brief History Slide 1 Precast Structures and Frames Miles L. Blackman, P.E. Slide 2 Learning Objectives Discuss precast concrete characteristics, advantages and benefits, typical construction methods and construction

More information

Table of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5

Table of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 1 OCTOBER 5, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI Table of Contents Table of Contents

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Executive Summary: 200 Minuteman Park currently stands as a three story commercial building. The original design was limited to three stories by an industrial zoning law in Andover, Massachusetts. If this

More information

Johns Hopkins Graduate Student Housing. Thesis Proposal. 929 North Wolfe Street Baltimore, Maryland Brad Oliver Structural Advisor: Professor Memari

Johns Hopkins Graduate Student Housing. Thesis Proposal. 929 North Wolfe Street Baltimore, Maryland Brad Oliver Structural Advisor: Professor Memari Johns Hopkins Graduate Student Housing 929 North Wolfe Street Brad Oliver Structural Advisor: Professor Memari 12/09/2011 Table of Contents Executive Summary -... 3 Introduction... 4 Structural Systems...

More information

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2 University at Buffalo CTRC/Incubator Buffalo, New York William McDevitt October 27, 2010 Table of Contents Executive Summary...3 Introduction...4 Structural System Overview...5 Foundation...5 Floor System...5

More information

Biobehavioral Health Building

Biobehavioral Health Building Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor Heather Sustersic Location: The Pennsylvania State University University Park, PA Project Size: 5

More information

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating 2016 v2.1 Release Webinar PSC Composite Design Check / Load rating What is Composite Girder Module? Wizard-modeling - Steel Composite Bridge - PSC Composite Bridge Report Generation for Design & Load Rating

More information

Chuck Brooks, P.E., P.Eng. C&S Engineers

Chuck Brooks, P.E., P.Eng. C&S Engineers Chuck Brooks, P.E., P.Eng C&S Engineers 315-455-2000 cbrooks@cscos.com AGENDA INTRO BASICS KEY CONSIDERATIONS DESIGN CONSTRUCTION Questions to be Explored 1. Concrete Tiltup Panels are designed for the

More information

90% Design Submittal Structural Calculations Parking Garage CDRL

90% Design Submittal Structural Calculations Parking Garage CDRL NORTH METRO RAIL LINE PROJECT Thornton Crossroads at 104 th Avenue Station 90% Design Submittal Structural Calculations Parking Garage CDRL 03-037.11.06 June 2, 2017 Prepared by: Regional Rail Partners

More information

VARIOUS TYPES OF SLABS

VARIOUS TYPES OF SLABS VARIOUS TYPES OF SLABS 1 CHOICE OF TYPE OF SLAB FLOOR The choice of type of slab for a particular floor depends on many factors. Economy of construction is obviously an important consideration, but this

More information

Park Potomac Office Building E

Park Potomac Office Building E Kyle Wagner (IP) Advisor: Professor Kevin Parfitt 12/11/2009 Table of Contents I. Executive Summary. 3 II. Introduction / Material Strengths. 4 III. Codes and Design Standards.. 5 IV. Existing Structural

More information

Technical Assignment 3 December 3, 2007

Technical Assignment 3 December 3, 2007 Technical Assignment 3 December 3, 2007 101 Eola Drive, Orlando, FL Justin Raducha Pennsylvania State University Faculty Advisor: M. Kevin Parfitt Table of Contents Table of Contents... 2 Executive Summary...

More information

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari Office Building-G Thesis Proposal Structural Option December 10, 2010 Table of Contents Executive Summary... 3 Introduction... 4 Gravity System...4 Lateral System:...6 Foundation System:...6 Problem Statement...

More information

Structural Design Challenges for Plaza 66 Tower 2

Structural Design Challenges for Plaza 66 Tower 2 Structural Design Challenges for Plaza 66 Tower 2 Authors: Dennis C.K. Poon P.E., Managing Principal, Thornton Tomasetti, Inc. dpoon@thorntontomasetti.com Ling-en Hsiao, PhD, Principal, Thornton Tomasetti,

More information

ADAPT-BUILDER : General Analysis/Design Options

ADAPT-BUILDER : General Analysis/Design Options ADAPT-BUILDER : General Analysis/Design Options Quick Reference Guide Updated November 2017 Copyright All rights reserved 2017 1 2 3 4 5 6 7 8 9 General analysis/design options: 1. Both prestressed and

More information

Precast Wall Panel Design. By Edward Losch, PE, SE

Precast Wall Panel Design. By Edward Losch, PE, SE Precast Wall Panel Design By Edward Losch, PE, SE What is a Precast Concrete Sandwich Wall Panel? Typical Precast Concrete Sandwich Wall Panel Long-Line Form Wythe(s) Prestressed Trucked & Erected (Non-loadbearing)

More information

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS

PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS PARTIAL-DEPTH PRECAST DECK PANEL DESIGN AND CONSTRUCTION IN TEXAS Gregg Freeby, P.E., Leon Flournoy, P.E. & Sara Watts, E.I.T TxDOT Bridge Division Prefabricated Elements TxDOT s primary technique for

More information

Lateral System Analysis and Confirmation Design

Lateral System Analysis and Confirmation Design Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY November 15, 2004 Pictures courtesy of Fox & Fowle Architects Lateral System Analysis and Confirmation Design Executive Summary This

More information

Thesis Proposal Executive Summary Depth and Breadth Analysis

Thesis Proposal Executive Summary Depth and Breadth Analysis Mathew Nirenberg Structural Option Metropolis at Dadeland Adviser: Schneider Proposal Executive Summary 12/12/05 Thesis Proposal Executive Summary Depth and Breadth Analysis The Metropolis at Dadeland

More information

With several years of detailing experience and a vast range of knowledge, we have successfully helped clients with numerous projects, including:

With several years of detailing experience and a vast range of knowledge, we have successfully helped clients with numerous projects, including: EXCELLENCE IS IN THE DETAIL CMU & Masonry Our Company Prothious Engineering Services is one of the largest and most successful detailing companies in the world. Founded in 2002 as a subsidiary of JSL,

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

POST TENSIONED SLABS. Imagineering the possibilities

POST TENSIONED SLABS. Imagineering the possibilities POST TENSIONED SLABS Imagineering the possibilities imagineering... CCL post - tensioned slab solutions represent continuous development through involvement in building structures worldwide. CCL systems

More information

HIGH RISE CONDO SOHO, NEW YORK, NY

HIGH RISE CONDO SOHO, NEW YORK, NY HIGH RISE CONDO SOHO, NEW YORK, NY TECHNICAL ASSIGNMENT 3 November 21, 2006 Joseph Mugford The Pennsylvania State University Structural Option Faculty Advisor: Andres Lepage TABLE OF CONTENTS TABLE OF

More information

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA

THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA THE PLAZA AT PPL CENTER HAMILTON BOULEVARD AT 9 TH STREET - ALLENTOWN, PA Amy Graver, Structural Option - Dr. Hanagan, Advisor 10.21.2002 PRO-CON STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS Executive Summary

More information

Statement of Special Inspections

Statement of Special Inspections Statement of Special Inspections SUCF Project No: Project Title: Registered Design Professionals in Responsible Charge: (Name) (Address) Architect: Structural Engineer: Mechanical Engineer: Identification

More information

U.S. Pharmacopeia Headquarters Consolidation. Rockville, MD

U.S. Pharmacopeia Headquarters Consolidation. Rockville, MD Consolidation Jeff Rothermel Structural Option Advisor: Dr. Ali Memari Technical Report 2 Submitted: Oct. 24 th, 2008 Table of Contents Executive Summary.1 Floor Systems Existing Two Way Slab with Drop

More information

PT Slab Deflections. What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc PTI Annual Conference, Kansas City, MO

PT Slab Deflections. What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc PTI Annual Conference, Kansas City, MO PT Slab Deflections What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc. 2011 PTI Annual Conference, Kansas City, MO May 1, 2011 Types of Buildings Presentation Overview

More information

COURTYARD INFILL STRUCTURE DESIGN

COURTYARD INFILL STRUCTURE DESIGN COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is

More information

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address:

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address: SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division Permit Application #: Project Address: Purpose: To meet the requirements of City of Walnut Creek Municipal Code Section

More information

S p a c e e l e v a t o r. Structure selection and design Prof Schierle 1

S p a c e e l e v a t o r. Structure selection and design Prof Schierle 1 S p a c e e l e v a t o r Structure selection and design Prof Schierle 1 Selection criteria: 1 Morphology 2 Capacity Limits 3 Code Requirements 4 Cost 5 Load Conditions 6 Resources and Technology 7 Sustainability

More information

Table of Contents Executive Summary 2 Introduction 3 Structural Systems Problem Statement 9 Proposed Solution 10 Breadth Topics 11 Tasks and Tools

Table of Contents Executive Summary 2 Introduction 3 Structural Systems Problem Statement 9 Proposed Solution 10 Breadth Topics 11 Tasks and Tools Table of Contents Executive Summary...2 Introduction...3 Structural Systems Foundation System...4 Gravity System...6 Lateral System...7 Problem Statement...9 Proposed Solution...10 Breadth Topics...11

More information

Thesis Proposal. Matthew R Peyton

Thesis Proposal. Matthew R Peyton This Document is for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. S t r u c t u r a l O p t i o n P r o f e s s o r B e h r H o s p i t a l

More information

Crossroads at Westfields Building II

Crossroads at Westfields Building II Crossroads at Westfields Building II Chantilly, Va STEPHEN LUMPP Structural option Faculty Consultant: Dr. Andres Lepage Technical Report 2 EXECUTIVE SUMMARY This report is a study of alternate floor systems

More information

Design Criteria. Analysis and Design of a High Rise Steel Braced Frame Core 22

Design Criteria. Analysis and Design of a High Rise Steel Braced Frame Core 22 Analysis and Design of a High Rise Steel Braced Frame 22 Design Criteria Design Methodology The design of a high rise lateral force resisting system and gravity system poses itself as a daunting and cumbersome

More information

Mick Leso Structural Option 2006 Penn State AE Senior Thesis RESEARCH

Mick Leso Structural Option 2006 Penn State AE Senior Thesis RESEARCH RESEARCH CANTILEVERS To thoroughly understand the Renick Building requires background knowledge of cantilever structures. A cantilever is described as a projecting beam or a member supported at only one

More information

FOUR. at the Fore BY RICHARD B. GARLOCK, P.E.

FOUR. at the Fore BY RICHARD B. GARLOCK, P.E. The first tower to open at the original World Trade Center site, 4WTC maximizes its space and views with creative column construction. FOUR at the Fore BY RICHARD B. GARLOCK, P.E. Joe Woolhead APRIL 2015

More information

Technical Assignment 1 10/8/03

Technical Assignment 1 10/8/03 Executive Summary Technical Assignment 1 10/8/03 The is 55 story high-rise condominium being built off the northern Miami coast. The structural design presented in this building is a direct result of its

More information

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004 Ismail Al-Hadhrami Structural Option Faculty Consultant: Dr. Thomas Boothby Agricultural Hall and Annex East Lansing, MI Pro-Con Structural Study for Alternative Floor Systems October 27, 2004 Executive

More information

Technical Report 3. Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R

Technical Report 3. Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R Technical Report 3 Alyssa Stangl Structural Option Advisor Dr. Linda Hanagan L A J O L L A C O M M O N S P H A S E I I O F F I C E T O W E R Site and Location La Jolla Commons, San Diego, California General

More information

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems Table of Contents 1. Executive Summary.....Page 2 2. Existing Floor System....Page 4 2.1. Composite steel beams with composite

More information

This report investigates alternative floor systems for the building. A brief summary of each system is as follows:

This report investigates alternative floor systems for the building. A brief summary of each system is as follows: Technical Report 2 Analysis and Comparison of Alternative Floor Systems Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and tourist attraction for Boyds Collections

More information

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Revised Thesis Proposal

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Revised Thesis Proposal University at Buffalo CTRC/Incubator Buffalo, New York Revised William McDevitt January 14, 2011 Table of Contents Executive Summary...2 Introduction...3 Structural System Overview...4 Foundation...4 Floor

More information

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan Brief Building Overview: 200 Minuteman Park stands as a 200,000 square foot Class A office building in Andover, Massachusetts, worth roughly $15,000,000. Although the building has a large square footage,

More information

ENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2016 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2016 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M X Buildings $2M-$10M Other Structures Under $5M Buildings

More information

Copyright. magazine. CFS Load Bearing Construction

Copyright. magazine. CFS Load Bearing Construction Progressive Collapse Requirements Cold-Formed Steel Load Bearing Construction By Nabil A. Rahman, Ph.D., P.E., Michael Booth and Gary Bennett Figure 1: Cold formed steel load bearing mid-rise construction.

More information

cornish concrete products Structural precast

cornish concrete products Structural precast cornish concrete products Structural precast / Ground and edge beams / Retaining Walls / crosswall construction / concrete frames / Staircases and Floors / seating and terracing / Loading Bays / Lift shafts

More information

Pennsylvania College Of Technology Dauphin Hall Williamsport, Pennsylvania

Pennsylvania College Of Technology Dauphin Hall Williamsport, Pennsylvania Pennsylvania College Of Technology Dauphin Hall Williamsport, Pennsylvania Aubert Ndjolba Structural Option AE Senior Thesis- 2011 Thesis Advisor: Dr. Boothby Existing Building Overview Introduction Existing

More information