1 The Construction (Design and Management) Regulations 2015 Industry guidance for Principal designers This industry guidance has been produced by members of CONIAC (Construction Industry Advisory Committee) CDM15/2 DRAFT

2 Published by CITB, Bircham Newton, King s Lynn, Norfolk, PE31 6RH Construction Industry Training Board 2015 CITB is registered as a charity in England and Wales (Reg No ) and in Scotland (Reg No SC044875) First published 2015 ISBN CITB has made every effort to ensure that the information contained within this publication is accurate. Its content should be used as guidance only and not as a replacement for current regulations, existing standards or as a substitute for legal advice and is presented without any warranty, either express or implied, as to its accuracy. In no event will CITB be liable for any damages arising from reliance upon its content. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission in writing from CITB save that it may be read and saved by the original recipient, for whose private use it was originally intended. CDM15/2 DRAFT Page 1 of 22

3 Contents 1 Introduction General introduction Who should be the principal designer? The role of a principal designer What do you have to do? Assist with project set up Assist with compiling the pre-construction information Co-ordinate the pre-construction phase Liaise during the construction phase Prepare the health and safety file Information required by the principal designer Information at project set up Information during the pre-construction phase Information during the construction phase Information for completion and handover Information provided by the principal designer Information at project set up Information during the pre-construction phase Information during the construction phase Information for completion and handover What does good look like? Good examples when assisting with project set up Good examples when co-ordinating the pre-construction phase Good examples when liaising during the construction phase Good examples for completion and handover of health and safety file Advice for principal designers working for domestic clients 15 Annex A: CDM duty holders and their roles summarised Annex B: Pre-construction information Annex C: The health and safety file Annex D: Information flow Annex E: Red, amber, green (RAG) lists CDM15/2 DRAFT Page 2 of 22

4 1 Introduction 1.1 General introduction The Construction (Design & Management) Regulations (CDM) are the main set of regulations for managing the health, safety and welfare of construction projects. CDM applies to all building and construction work including new build, demolition, refurbishment, extensions, conversions, repair and maintenance. This guide is based on sound industry practice and will help small businesses and organisations deliver building and construction projects in a way that prevents injury and ill-health.. There are six guides: one for each of the five duty holders under CDM and an additional one for workers. The six guides are: These guides should help you better understand your role and that of other duty holders, especially if you have more than one role under CDM. The Health and Safety Executive (HSE) has produced the CDM L-series to offer further guidance. It is downloadable from the HSE website: Who should be the principal designer? The principal designer must be a designer on the project and be in a position to have control over the design and planning stage. A designer is an organisation or individual that prepares or modifies a design for a construction project, including the design of temporary works, or arranges for or instructs someone else to do so. The principal designer will usually be an organisation or, on smaller projects, an individual with: a technical knowledge of the construction industry, relevant to the project an understanding of how health and safety is managed through the design process the skills to be able to oversee health and safety during the pre-construction phase of the project and the ongoing design. CDM15/2 DRAFT Page 3 of 22

5 The principal designer needs to have good relationships with the client and principal contractor and also essential for them to establish good relationships with other designers working on the project. If you are also acting as a designer, refer to the Industry guidance for designers (CDM15/3). 1.3 The role of a principal designer The CDM Regulations define three main roles for managing the health and safety of a construction project. The client has the overall responsibility for the successful execution of the project and the principal designer and principal contractor lead on different phases of the project. The principal designer and principal contractor have an important role in co-ordinating health and safety. All three duty holders must have good working relationships from the outset if the project is to be delivered in a safe and healthy manner. This enables the provision and flow of information to ensure that health and safety is considered when making decisions. This is the arrangement for the majority of projects. The only exception is when the client does not need to appoint a principal designer or principal contractor because the work is to be undertaken by a single contractor. Appointing the principal designer You must be appointed in writing by the client. You can combine your role as principal designer with other roles such as the project manager. This will assist with the integration of health and safety in the project. Main duties of the role Your role as principal designer is to plan, manage and monitor the co-ordination of the pre-construction phase, including any preparatory work carried out for the project. You must: assist the client in identifying, obtaining and collating the pre-construction information provide pre-construction information to designers, principal contractor and contractors ensure that designers comply with their duties and co-operate with each other liaise with the principal contractor for the duration of your appointment prepare the health and safety file. Your duties as the principal designer apply regardless of the contractual arrangements for the appointment of other designers on the project. If you appoint other designers, you are responsible for ensuring that they have the relevant skills, knowledge, training and experience to deliver their work. CDM15/2 DRAFT Page 4 of 22

6 2 What do you have to do? As the principal designer, you have responsibility for managing health and safety during the preconstruction phase. 2.1 Assist with project set up Firstly, you will want to know the client s level of knowledge and experience of this type of project. A client who is unfamiliar with construction projects will need to be made aware that the CDM Regulations apply to their project. You could refer them to the Industry guidance for clients (CDM15/1) for further information about what they need to do. You may be asked to help the client to develop their initial brief. This is a good way of outlining the client s key requirements and expectations for the project, including any limitations or restrictions, such as budget, planning constraints and timescales. This brief is likely to be developed further as the project progresses and may include specifications and standards, which will in turn help to outline health and safety expectations. For example, the brief could highlight safety in design, via use of risk registers, RAG lists and raising any other specific concerns. Refer to annex E for further information about RAG lists. 2.2 Assist with compiling the pre-construction information The client is required to identify and obtain pre-construction information. You may need to assist the client in doing this and then collating it for passing initially to the designers and then to the principal contractor for the construction phase. For further information on the content of the pre-construction information, see Annex B. This information should be reviewed to identify any potential impacts on health and safety. Where you identify any shortfalls in the information, you will need to advise the client on how to address them. Review of existing pre-construction information and what to look for The following should be considered when reviewing existing information: Is the information reliable? Where has it come from? How old is it? Could it have been superseded by subsequent works? Is there any information missing (e.g. asbestos records)? Would a site visit help to confirm the accuracy of the information (e.g. location of manhole covers)? Are further surveys or investigations required? Remember that the information was not prepared with your work in mind. You and the client should also agree when updates will be provided, as well as the level and type of information they would like to receive, for example whether they want to see a copy of the developing pre-construction information that will be issued to the principal contractor. CDM15/2 DRAFT Page 5 of 22

7 2.3 Co-ordinate the pre-construction phase You should discuss with the client how you will manage the pre-construction phase. Meeting regularly with the client provides an opportunity to update them on the developing pre-construction information. Co-ordinate designers You have a responsibility to co-ordinate health and safety with all the designers, including temporary works designers. You will need to provide relevant information to designers when it becomes available. You should tell the designers what you expect from them, including how they will work with each other. You need to be sure that designs are co-ordinated between the different designers to identify any potential impacts on health and safety during the full project lifecycle, from construction to maintenance, cleaning and, where relevant, during its use as a workplace. You must ensure that the designers comply with their duties during the design stage. You should talk to them early on to find out how they will consider health and safety and how they will review its effectiveness. This will help you to decide which elements of the design you wish to review in detail as the design develops. Oversee design decisions You are not expected to review everything during design development. You should focus your attention on areas where there is a high risk to health and safety, including changes made to the original design. You can do this by leading design review meetings. Even if you do not have technical knowledge of all aspects of the design, you should be prepared to challenge the designers on their decisions and the process they followed, including any assumption they have made. Once the designs are ready for inclusion in the pre-construction information, you will want to undertake a review of the health and safety information provided, such as any remaining risks, sequencing of the construction process, the details of a phased handover and statements about any assumptions and key decisions. Many risks may remain; if they are well known or expected by a contractor they do not need to be included in the pre-construction information but it is important that any unusual risks are clearly identified and communicated, for example on drawings. This not only helps you to confirm that designers have considered health and safety in their designs, but it also helps to demonstrate to the client that you are fulfilling your duties. Communicate with the client You should communicate with the client regularly, to provide them with updates on progress and to raise any potential issues, such as concerns that designers are not co-operating. However, you are expected to resolve such problems directly with the designers first, before involving the client. 2.4 Liaise during the construction phase You must provide the pre-construction information to the principal contractor. This is required so that they can develop the construction phase plan to help them plan and manage the construction work. Prepare the pre-construction information To do this, you need to compile and review the pre-construction information to check that the information provided is appropriate for supporting the construction phase. It should be specific to the project and should not include information that a principal contractor familiar with this type of work would be expected to know. Examples of things to include could be particular risks identified on drawings, specific erection sequencing and any temporary support that is required. CDM15/2 DRAFT Page 6 of 22

8 Communicate with the principal contractor You must ensure that the principal contractor receives the pre-construction information, including any significant health and safety issues arising from the original client brief, and any subsequent changes to the brief or issues identified by the designers. You must liaise with the principal contractor throughout your appointment, communicating with them regularly to ensure that the design, including temporary works design, is co-ordinated. This provides you with the opportunity to raise any potential issues. You should also support the principal contractor in obtaining responses from designers to any questions relating to health and safety. You and the principal contractor should agree methods of communication with other contractors, as the principal contractor has a co-ordination role and may wish to be involved in the discussions. 2.5 Prepare the health and safety file It is your responsibility to prepare and develop the health and safety file and ensure it is handed over to the client. However, if your appointment ends before the project is completed, you must hand over the file to the principal contractor. They will then continue to develop it and hand over the completed file to the client. For further information on the health and safety file, see Annex C. CDM15/2 DRAFT Page 7 of 22

9 3 Information required by the principal designer As the principal designer, you should receive certain information during the different phases of the project. 3.1 Information at project set up Before you start work as the principal designer, it is important to obtain details of your appointment in writing, which should outline the scope of services you will provide, including timescales and resources required. The client brief Whilst the initial client brief sets out their requirements and expectations for the project, it is also important that it details their health and safety expectations. You should ask for existing information from the client, which could include any previous health and safety file, site services, drawings, asbestos information, ground conditions and other relevant surveys. Further useful information could be obtained from the client s maintenance and operational staff. You may also need information about site arrangements and restrictions, for example security, existing occupants and access. At this stage of the project, it is useful to obtain details of the client s main contacts, as well as any designers and contractors involved in the project. 3.2 Information during the pre-construction phase The designers should tell you if there are any issues with the health and safety content of the client brief or any other existing information. The designers may have questions or queries and identify any ambiguous or missing information. As the principal designer you will need to respond, either directly or by obtaining further information from the client. The designers should give you regular updates, including information about issues or design changes that could potentially impact on health and safety. You may need to inform the client about these, especially where changes have been made to their original brief. The designers must provide health and safety information relating to their design, including any unusual remaining risks and details of the key assumptions and decisions they have made. This information is an important part of the pre-construction information that will be provided to the principal contractor. Examples could include risks identified on drawings, specific sequencing of erection, any phased handovers and any temporary support that is required. You will also need design information for the health and safety file. This should include information that would be required for the post-construction life of the building, such as during cleaning, maintenance, alteration or demolition. 3.3 Information during the construction phase The principal contractor could provide feedback on the adequacy of the pre-construction information and/or design information provided. They may have questions or queries and may identify ambiguous or missing information. As the principal designer you will need to respond, either directly or by obtaining further information from the client or the designers. CDM15/2 DRAFT Page 8 of 22

10 The principal contractor should provide information about any issue or change that could potentially impact on health and safety during maintenance, operation and demolition. As the principal designer, you need to understand this impact and, where necessary, discuss this with the designers and client. An example would be installing cladding in such a way that it will be harder to replace, maintain or clean. 3.4 Information for completion and handover For the health and safety file, the principal contractor will need to provide construction information, including any changes to the original design and as-built drawings. This should include information that is required for cleaning, maintenance, alteration or demolition. CDM15/2 DRAFT Page 9 of 22

11 4 Information provided by the principal designer As the principal designer, you should provide certain information during the different phases of the project. 4.1 Information at project set up Your proposal You should produce a proposal for the client outlining the scope of the principal designer role and explaining how you intend to fulfil it. The proposal may include an overview of your resources, as well as you r skills, knowledge, training and experience. Requirements for the pre-construction information Part of your role is to provide advice to the client about the information required for the pre-construction information (see Annex B), in particular any gaps in the available information and how they could be addressed. A review of this information is particularly important in order to identify potential issues early in the project. 4.2 Information during the pre-construction phase Information for the designers You need to provide relevant pre-construction information to all the designers, which may include the client brief for the project and any specifications or minimum standards. Existing information also needs to be provided, which could include a previous health and safety file, services, drawings, asbestos information, ground conditions and any other relevant surveys. This information could also include health and safety expectations for the project, as well as information obtained from the client s maintenance and operational staff. As part of your co-ordination role, it is useful to share details of the client or their representative(s), as well as any other designers and contractors involved in the project, with the designers. You should inform the designers of your expectations for how the pre-construction phase will be managed, including methods of communication, circulation of information and attendance at meetings. Information for the client You should update the client on the progress of the pre-construction phase, such as the status of information gathering and development of the design. Your updates should also include feedback on any significant health and safety issues arising from their original brief, and any subsequent changes to the brief or the design. 4.3 Information during the construction phase The pre-construction information You must provide the pre-construction information to the principal contractor. This information will be used to prepare the construction phase plan, as well as developing the health and safety file. Annex B outlines the content required for the pre-construction information, which will include existing information as well as design information for construction, identify unusual remaining risks, list key assumptions and decisions made and clarify sequencing requirements. Information about the health and safety file In addition, you will need to provide the principal contractor with details of any agreed format, structure and required content for the health and safety file. See Annex C for more information. CDM15/2 DRAFT Page 10 of 22

12 Passing on queries Even though you may have provided the principal contractor with details of the main contacts for the project, you are responsible for ensuring that all designers receive any health and safety- related questions or queries from the principal contractor regarding the design. 4.4 Information for completion and handover Ensure that the health and safety file is handed over to the client. However, if your appointment ends before the project is completed, you must hand over the file to the principal contractor. CDM15/2 DRAFT Page 11 of 22

13 5 What does good look like? This section identifies good practice. While the examples provided are not a requirement of the CDM regulations, they may help you be more effective as the principal designer. The examples are not exhaustive but illustrate how the principal designer can contribute to the success of the project. 5.1 Good examples when assisting with project set up Provide a schedule on appointment As soon as you have been appointed, you should provide the client with a detailed schedule of services and resources to help plan what you need to do to ensure the client is clear about what to expect and to reassure them that you are fulfilling your role. Develop a good relationship with the client This will assist you in managing health and safety on the project and resolving any issues. It will take time but should be worthwhile. Talk to the client so that you understand their needs; this is easier at face-to-face meetings than by phone or . Ensure you understand the brief Talk to the client about their brief, to receive a further insight into their requirements. This will also give you an opportunity to ask questions and offer suggestions. Clarify roles To avoid confusion, you should distinguish between the purpose of the principal designer and the designer roles by separating the scope of service and resources required for each. Encourage project team meetings Leadership from the client is important and they should be encouraged to hold project team meetings to bring all parties together. Involving the client and principal contractor in meetings should improve co-ordination and understanding, particularly when making decisions. Undertake an early site visit This should assist you with the review of the existing information, as well as helping you to understand the site arrangements and conditions. The context provided by a site visit should also aid you with the design co-ordination. Where possible, involve the client in your site visit to identify and understand any potential issues. Use BIM If the project is using building information modelling (BIM), consider how you could u tilise this in your role as principal designer. It could help you to: consider the co-ordination of health and safety information when developing the BIM execution plan obtain existing information in order to review it and pass it to all designers obtain design information to review health and safety risks provide pre-construction information to the principal contractor monitor and gather information for the health and safety file develop a database of good practice guides and prompt lists. Be proactive For example: where the client does no produce an adequate brief, you should spend time with them to help develop it you need to raise any significant health and safety concerns with the client as soon as possible do not wait for the next meeting CDM15/2 DRAFT Page 12 of 22

14 consider how elements of the final structure can be utilised during the construction, for example by installing stairs early in the build to reduce the need for scaffolding. This will not only have a health and safety benefit but could also reduce time and costs ensure that any significant health and safety risks identified are added to the project risk register encourage safer designs through the use of RAG lists. 5.2 Good examples when co-ordinating the pre-construction phase Arrange a pre-design meeting with the client and the designers This is an opportunity to discuss the brief and the approach to health and safety on the project. This will ensure that everyone fully understands what is required and provides an opportunity to ask questions and make suggestions. It will also start to build relationships. Where possible, seek contractor input during the design phase This helps to anticipate potential construction issues, and to identify opportunities for improving the design. Where a contractor has not yet been appointed you could consult a contractor with relevant knowledge. Participate in design co-ordination meetings across all disciplines This helps to better understand how the design is being developed, allows you to ensure that health and safety is integrated into design meetings and provides an opportunity to challenge the design by asking: Can this be done more safely and can we reduce harm to health? Actively encourage designers to work together as a team Encourage designers to regularly talk and listen to each other throughout the design period. You can support their communication by providing breakfast for an early meeting or by celebrating project milestones. Encourage the designers to involve end users from the early stages of the design This helps them to further understand the proposed use and maintenance requirements. This could also provide an opportunity to test the original client brief and ensure all aspects have been considered. Embed health and safety into everything To ensure that health and safety is actively managed as part of the project and is not seen as a bolton, you should suggest that it is integrated within project reporting and in meetings as a standard agenda item. By avoiding additional reporting and more meetings this also creates efficiencies. Encourage a consistent approach to how information is provided by the designers This will assist in producing the pre-construction information and the health and safety file. Using a consistent format, including the same software, is a more efficient way for you to review and collate the information. This should also benefit those who receive the information. Where practical, consider asking the principal contractor for their preferred format for the pre-construction information, as this may help them to understand the content more quickly and reduce their queries. Evaluate the process Undertake a review towards the end of the design stage to determine any design-related lessons learnt that may benefit the client, designers and you on future projects. You could also take this opportunity to review the way in which you have undertaken the principal designer role and identify areas for improvement. This could include obtaining feedback from the client and other designers. CDM15/2 DRAFT Page 13 of 22

15 5.3 Good examples when liaising during the construction phase Attend site or progress meetings This will help you to maintain a good working relationship with the principal contractor. This should also allow you to actively discuss queries and issues. 5.4 Good examples for completion and handover of health and safety file Prepare content for the health and safety file early Gather information for the health and safety file as soon construction progresses rather than leaving it until the end of the project. This is more efficient and recognises that it may be difficult to obtain certain information once the project has been completed. Evaluate the process Undertake a review towards the end of your involvement in the project to determine any lessons learnt. This should include whether the risks identified during the design stage were relevant and whether any other unusual risks arose that were not identified. You could also undertake a specific review with the principal contractor to find out whether the pre-construction information assisted them during the construction phase. CDM15/2 DRAFT Page 14 of 22

16 6 Advice for principal designers working for domestic clients Domestic clients are people who have construction work carried out on their own home, or the home of a family member. When working on a project for a domestic client your role is very similar to that undertaken for other clients. However, this is the only circumstance where you may become a principal designer without a written appointment. Where there is more than one contractor, the first designer involved becomes the principal designer, unless the client appoints another designer to the role. The domestic client duties usually default to the contractor or the principal contractor, although you could be asked to undertake these duties. If this is the case, there must a written agreement in place. Refer to the Industry guidance for client s (CDM15/1) for further information on the client s duties. For a typical domestic project, a builder is likely to produce a quotation, a schedule of works or list of items which will be classed as design. If you are the first appointment and there is more than one contractor, you will become the principal designer. However, the co-ordination and effort required should be proportionate to the scale of the project. The health and safety file could include information on any equipment installed such as manufacturer instructions. Where drawings or sketches exist, these should also be included. For example, for a bathroom refurbishment the builder has appointed a plumber and an electrician. As the builder was appointed first, they are the principal designer as well as the principal contractor. In this case, planning and co-ordination for the design could happen through conversations to understand the work required, including the potential for using existing electrical and water supplies. The health and safety file for this work may include the manufacturer s instructions for a new shower and a sketch of the new bathroom layout. CDM15/2 DRAFT Page 15 of 22

17 Annex A CDM duty holders and their roles summarised CDM duty holders* who are they? Clients Organisations or individuals for whom a construction project is carried out. Domestic clients People who have construction work carried out on their own home, or the home of a family member, that is not done in furtherance of a business, whether for profit or not. Principal designers** Designers appointed by the client in projects involving more than one contractor. They can be an organisation or an individual with sufficient knowledge, experience and ability to carry out the role. Designers Those who, as part of a business, prepare or modify designs for a building, product or prepare or modify designs to system relating to construction work. Principal contractors Contractors appointed by the client to co-ordinate the construction phase of a project where it involves more than one contractor. Summary of role/main duties Make suitable arrangements for managing a project. This includes making sure that: other duty holders are appointed sufficient time and resources are allocated. Clients must also make sure that: relevant information is prepared and provided to other duty holders the principal designer and principal contractor carry out their duties welfare facilities are provided. Domestic clients are in scope of CDM 2015, but their duties as a client are normally transferred to: the contractor, on a single contractor project, or the principal contractor, on a project involving more than one contractor. However, the domestic client can choose to have a written agreement the principal designer to carry out the client duties. Plan, manage, monitor and co-ordinate health and safety in the preconstruction phase of a project. This includes: identifying, eliminating or controlling foreseeable risks ensuring designers carry out their duties. Prepare and provide relevant information to other duty holders. Liaise with the principal contractor to help in the planning, management, monitoring and co-ordination of the construction phase. When preparing or modifying designs, eliminate, reduce or control foreseeable risks that may arise during: construction the maintenance and use of a building once it is built. Provide information to other members of the project team to help them fulfil their duties. Plan, manage, monitor and co-ordinate the construction phase of a project. This includes: liaising with the client and principal designer preparing the construction phase plan organising co-operation between contractors and co-ordinating their work. Ensure that: suitable site inductions are provided reasonable steps are taken to prevent unauthorised access workers are consulted and engaged in securing their health and safety welfare facilities are provided. CDM15/2 DRAFT Page 16 of 22

18 Contractors Those who do the actual construction work. They can be either an individual or a company. Workers The people who work for or under the control of contractors on a construction site Plan, manage and monitor construction work under their control so that it is carried out without risks to health and safety. For projects involving more than one contractor, co-ordinate their activities with others in the project team in particular, comply with directions given to them by the principal designer or principal contractor. For single-contractor projects, prepare a construction phase plan. They must: be consulted about matters which affect their health, safety and welfare take care of their own health and safety and that of others who may be affected by their actions report anything they see which is likely to endanger either their own or others health and safety co-operate with their employer, fellow workers, contractors and other duty holders. * Organisations or individuals can carry out the role of more than one duty holder, provided they have the skills, knowledge, experience and (if an organisation) the organisational capability necessary to carry out those roles in a way that secures health and safety. ** Principal designers replace the role undertaken by CDM co-ordinators under CDM CDM15/2 DRAFT Page 17 of 22

19 Annex B Pre-construction information What is pre-construction information? 1. Pre-construction information provides the health and safety information needed by: a. designers and contractors who are bidding for work on the project, or who have already been appointed, to enable them to carry out their duties b. principal designers and principal contractors in planning, managing, monitoring and co-ordinating the work of the project. It also provides a basis for the preparation of the construction phase plan. Some material may also be relevant to the preparation of the health and safety file (see Annex C). 2. Pre-construction information is defined as information about the project that is already in the client s possession or which is reasonably obtainable by or on behalf of the client. The information must: a. be relevant to the particular project b. have an appropriate level of detail c. be proportionate, given the nature of the health and safety risks involved. 3. Pre-construction information should be gathered and added to as the design process progresses to reflect new information about the risks to health or safety and how they should be managed. Preliminary information gathered at the start of the project is unlikely to be sufficient. 4. When pre-construction information is complete it must include proportionate information about: a. the project, such as the client brief and key dates of the construction phase b. the planning and management of the project, such as the resources and time being allocated to each stage of the project and the arrangements to ensure there is co-operation between duty holders and that the work is co-ordinated c. the health or safety hazards of the site, including design and construction hazards and how they will be addressed d. any relevant information in an existing health and safety file. 5. The information should be in a convenient form and be clear, concise and easily understandable to allow other duty holders involved in the project to carry out their duties. CDM15/2 DRAFT Page 18 of 22

20 Annex C The health and safety file The health and safety file is defined as a file appropriate to the characteristics of the project, containing relevant health and safety information to be taken into account during any subsequent project. The file is only required for projects involving more than one contractor. The file must contain information about the current project that is likely to be needed to ensure health and safety during any subsequent work such as maintenance, cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion: a. A brief description of the work carried out. b. Any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (for example, surveys or other information concerning asbestos, contaminated land, water-bearing strata, buried services and so on). c. Key structural principles (for example, bracing or sources of substantial stored energy including pre- or post-tensioned members) and safe working loads for floors and roofs d. Hazardous materials used (for example, lead paints and special coatings. e. Information regarding the removal or dismantling of installed plant and equipment (for example, any special arrangements for lifting such equipment). f. Health and safety information about equipment provided for cleaning or maintaining the structure. g. The nature, location and markings of significant services, including underground cables, gas supply equipment and fire-fighting services. h. Information and as-built drawings of the building, its plant and equipment (for example, the means of safe access to and from service voids, and the position of fire doors). There should be enough detail to allow the likely risks to be identified and addressed by those carrying out the work and be proportionate to those risks. The file should not include things that will not help when planning future construction work, such as pre-construction information, the construction phase plan, construction phase risk assessments or contractual documents. CDM15/2 DRAFT Page 19 of 22

21 Annex D Information flow This chart illustrates the information flow during the key stages of a project, including information received from set up to completion and handover. CDM15/2 DRAFT Page 20 of 22

22 Annex E CDM Red, amber, green (RAG) lists RAG lists are practical aids to designers on what to eliminate, avoid and encourage. Red lists Hazardous procedures, products and processes that should be eliminated from the project where possible. Lack of adequate pre-construction information (e.g. asbestos surveys, details of geology, obstructions, services, ground contamination and so on). Hand-scabbling of concrete (e.g. stop ends ). Demolition by hand-held breakers of the top sections of concrete piles (pile cropping techniques are available). Specification of fragile roof lights and roofing assemblies. Processes giving rise to large quantities of dust (e.g. dry cutting, blasting and so on). On-site spraying of harmful substances. Specification of structural steelwork which is not purposely designed to accommodate safety nets. Designing roof mounted services that require access (for maintenance and so on), without provision for safe access (e.g. barriers). Glazing that cannot be accessed safely. All glazing should be anticipated as requiring cleaning replacement, so a safe system of access is essential. Entrances, floors, ramps, stairs and escalators not specifically designed to avoid slips and trips during use and maintenance, including taking into account the effect of rain water and spillages. Design of environments involving adverse lighting, noise, vibration, temperature, wetness, humidity and draughts or chemical and/or biological conditions during use and maintenance operations. Designs of structures that do not allow for fire containment during construction. Amber lists Products, processes and procedures to be eliminated or reduced as far as possible and only specified or allowed if unavoidable. Including amber items would always lead to the provision of information to the principal contractor. Internal manholes and inspection chambers in circulation areas. External manholes in heavily used vehicle access zones. Specification of lip details (i.e. trip hazards) at the tops of pre-cast concrete staircases. Specification of small steps (e.g. risers) in external paved areas. Specification of heavy building blocks (e.g. those weighing more than 20kgs). Large and heavy glass panels. Chasing out concrete, brick or blockwork walls or floors for the installation of services. Specification of heavy lintels (slim metal of hollow concrete lintels are better alternatives). Specification of solvent-based paints and thinners, or isocyanates, particularly for use in confined areas. Specification of curtain wall or panel system without provision for the tying or raking of scaffolds. Specification of blockwork wall more than 3.5 metres high using retarded mortar mixes. Site traffic routes that do not allow for one-way systems and/or vehicular traffic segregated from site personnel Site layout that does not allow adequate room for delivery and/or storage of materials, including site specific components. Heavy construction components which cannot be handled using mechanical lifting devices (because of access restrictions/floor loading and so on). On-site welding, in particular for new structures. Use of large piling rigs and cranes near live railways and overhead electric power lines or where proximity to obstructions prevents guarding of rigs. CDM15/2 DRAFT Page 21 of 22

23 Green lists Products, processes and procedures to be positively encouraged. Adequate access for construction vehicles to minimise reversing requirements (one-way systems and turning radii). Provision of adequate access and headroom for maintenance in plant room, and adequate provision for replacing heavy components. Thoughtful location of mechanical and electrical equipment, light fittings, security devices and so on to facilitate access, and placed away from crowded areas. Specification of concreate products with pre-cast fixings to avoid drilling. Specification of half board sizes for plasterboard sheets to make handling easier. Early installation of permanent means of access, and prefabricated staircases with hand rails. Provision of edge protection at permanent works where there is a foreseeable risk of falls after handover. Practical and safe methods of window cleaning (e.g. from the inside). Appointment of a temporary works co-ordinator (BS 5975) Off-site timber treatment if PPA- and CCA-based preservatives are used (boron or copper salts can be used for cut ends on site). Off-site fabrication and prefabricated elements to minimise on site hazards. Encourage the use of engineering controls to minimise the use of personal protective equipment. CDM15/2 DRAFT Page 22 of 22

CDM FAQ Sheet

CDM FAQ Sheet CDM 2015 - FAQ Sheet 1. The change to the regulations means Domestic works are now included. What if you are doing DIY in your own house? Do the regulations apply to this? If the home owner is doing the

More information

Annex G to Loughborough University Facilities Management Health and Safety Procedure

Annex G to Loughborough University Facilities Management Health and Safety Procedure Annex G to Loughborough University Facilities Management Health and Safety Procedure Working with Contractors Including the Construction (Design and Management Regulations) 2015 General 1. The Construction

More information

2 Ensure there are arrangements in place for managing and organising the project

2 Ensure there are arrangements in place for managing and organising the project A principal contractor is required to plan, manage and coordinate the construction work. Appoint them as early as possible so they are involved in discussions with the principal designer about the work.

More information

CDM2015 The Construction (Design and Management) Regulations Industry guidance for Designers

CDM2015 The Construction (Design and Management) Regulations Industry guidance for Designers CDM2015 The Construction (Design and Management) Regulations 2015 Industry guidance for Designers CDM15/4 This industry guidance has been produced by members of CONIAC (Construction Industry Advisory Committee).

More information

Health and Safety Guidance Principal Designer Construction Design and Management Regulations 2015

Health and Safety Guidance Principal Designer Construction Design and Management Regulations 2015 Health and Safety Guidance Designer Construction Design and Management Regulations 2015 Unless well managed construction sites are some of the most dangerous workplaces in the UK. The Construction, Design

More information

Managing health and safety in construction

Managing health and safety in construction Managing health and safety in construction Construction (Design and Management) Regulations 2015 Guidance on Regulations The Construction (Design and Management) Regulations 2015 (CDM 2015) came into force

More information

Curo Group HEALTH & SAFETY POLICY: CONSTRUCTION SAFETY MANAGEMENT & CDM PROCEDURE

Curo Group HEALTH & SAFETY POLICY: CONSTRUCTION SAFETY MANAGEMENT & CDM PROCEDURE Curo Group HEALTH & SAFETY POLICY: CONSTRUCTION SAFETY MANAGEMENT & CDM PROCEDURE Introduction Curo Group have a statutory duty to ensure that construction projects and works are managed effectively in

More information

CDM comes into force on 6 April 2015

CDM comes into force on 6 April 2015 CDM 2015 comes into force on 6 April 2015 Why the change? The Client adviser role of the CDM coordinator is not working as well as many had hoped Industry views the regulations as being too bureaucratic,

More information

Health and Safety Guidance - Designers Construction Design and Management Regulations 2015

Health and Safety Guidance - Designers Construction Design and Management Regulations 2015 Health and Safety Guidance - Designers Construction Design and Management Regulations 2015 Unless well managed construction sites are some of the most dangerous workplaces in the UK. The Construction,

More information

Designer and CDM Co-ordinator Guidance

Designer and CDM Co-ordinator Guidance Designer and CDM Co-ordinator Guidance Five or more employees 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to

More information

Managing Contractors (Scotland)

Managing Contractors (Scotland) Managing Contractors (Scotland) University Health and Safety Policy Author: Health & Safety Services 1 Managing Contractors Procedures (Scotland) to support University Health and Safety Policy CONTENT

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT: A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V.2 10.5.17) PROJECT: Oakdale Primary School, Peterborough Extension, Refurbishments and Associated Works.

More information

Site Safety Plus. Site Management Safety Training Scheme (SMSTS) Course appendix G

Site Safety Plus. Site Management Safety Training Scheme (SMSTS) Course appendix G Site Safety Plus Site Management Safety Training Scheme (SMSTS) Course appendix G 1. Introduction 2. Aims and objectives 3. Entry requirements 4. Assessment 5. Delegate numbers 6. Course duration and attendance

More information

Designer and CDM Co-ordinator Guidance

Designer and CDM Co-ordinator Guidance Designer and CDM Co-ordinator Guidance Fewer than five employees Health and Safety 1 CONTENTS INTRODUCTION...5 Further reading / additional resources...5 Note to suppliers...6 QUESTION 1: POLICY AND ORGANISATION...8

More information

CHAS Assessment Standards

CHAS Assessment Standards CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the

More information

Temporary Works Forum (TWf) Chairman: Bill Hewlett MA CEng FICE Secretary: John Carpenter CEng, FICE, FIStructE, CFIOSH

Temporary Works Forum (TWf) Chairman: Bill Hewlett MA CEng FICE Secretary: John Carpenter CEng, FICE, FIStructE, CFIOSH TW/11/027 Rev F (issued: February 12). Rev G (minor changes March 12) COMPETENCIES OF THE TWC 1 1 Background It is important that those individuals appointed to the roles of Temporary Works Coordinators

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK.

In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK. CDM Regulations at Retail Expo 2018 In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK. In April 2015 the Construction (Design and

More information

HANDING-OVER CERTIFICATE - SCAFFOLDING

HANDING-OVER CERTIFICATE - SCAFFOLDING HANDING-OVER CERTIFICATE - SCAFFOLDING Contractor : Site : Contractor. customername Site. Site name Date : Time : Erected by : Signature : Description of section handed over Job specification. description

More information

Level 3 NVQ Diploma in Controlling Lifting Operations Supervising Lifts (Construction)

Level 3 NVQ Diploma in Controlling Lifting Operations Supervising Lifts (Construction) Level 3 NVQ Diploma in Controlling Lifting Operations Supervising Lifts (Construction) Qualification Specification ProQual 2017 1 Contents Page Introduction 3 Qualification profile 3 Qualification structure

More information

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE The purpose of the health and safety questionnaire is to provide Clients with assurances that all companies on

More information

CDM (Set Construction) Information Sheet and Template Introduction

CDM (Set Construction) Information Sheet and Template Introduction CDM (Set ) Information Sheet and Template Introduction The (Design and Management) Regulations (CDM) are the main set of regulations for managing the health, safety and welfare of construction projects.

More information

FACT SHEET CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2015 THE PROPERTY PROFESSIONALS AUGUST 2016

FACT SHEET CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2015 THE PROPERTY PROFESSIONALS AUGUST 2016 MANAGEMENT) REGULATIONS forget the Legal Helpline ( members only) uk/uksi//51/pdfs/ uksi_0051_en.pdf CONTEXT The Management) (CDM) Regulations came into force on 6 April and replace the 2007 Regulations.

More information

Title of presentation. goes here CDM2015. Implementing the role of Principal Designer

Title of presentation. goes here CDM2015. Implementing the role of Principal Designer Title of presentation CDM2015 goes here Implementing the role of Principal Designer Secondary Andrew Leslie title or 26 presenters May 2016 name Andrew Leslie Technical and Standards Manager The Association

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

Level 5 NVQ Diploma in Controlling Lifting Operations Planning Lifts (Construction)

Level 5 NVQ Diploma in Controlling Lifting Operations Planning Lifts (Construction) Level 5 NVQ Diploma in Controlling Lifting Operations Planning Lifts (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure

More information

Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT ASBESTOS

Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT ASBESTOS Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT ASBESTOS Asbestos Asbestos is a naturally occurring, fibrous material which if inhaled can cause serious diseases. These include cancers of the lungs

More information

Managing health and safety in construction

Managing health and safety in construction Managing health and safety in construction Construction (Design and Management) s 2007 Approved Code of Practice Managing health and safety in construction Health and Safety Construction (Design and Management)

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 4 Qualification structure 5 Centre requirements

More information

Establish health and safety requirements

Establish health and safety requirements 16. 1for Establish health and safety requirements projects The Health and Safety at Work Act (Section 2 (2) (a)) requires that employers should provide and maintain plant and systems of work that are,

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction) Civil Engineering Services Highways Maintenance (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

Construction (Design and Management) Safety Guidance Document

Construction (Design and Management) Safety Guidance Document Construction (Design and Management) Safety Guidance Document Lead Directorate and Service: Corporate Resources - Human Resources, Safety Services Effective Date: April 2011 Contact Officer/Number Garry

More information

Health and Safety Toolkit

Health and Safety Toolkit Health and Safety Toolkit H&S Conception, Design & Planning Checklist This checklist is for use at the outset of a project and should be regularly reviewed as the concept and design phases progress. The

More information

C D M R e g u l a t i o n s

C D M R e g u l a t i o n s C D M R e g u l a t i o n s 2 0 1 5 CDM Consultancy - Support for Client - Principal Designer - Principal Contractor c l a r i t y t h r o u g h s i m p l i c i t y Reducing the risk to health and safety

More information

Work Health and Safety Consultation, Cooperation and Coordination

Work Health and Safety Consultation, Cooperation and Coordination Work Health and Safety Consultation, Cooperation and Coordination Code of Practice December 2012 CP135 Workplace Standards Department of Justice This code of practice has been approved by the Tasmanian

More information

CDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V

CDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V CDM-C Guidance Five or more employees Health and Safety 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to provide...6

More information

working with partnerships

working with partnerships A practical guide to: working with partnerships Practical step-by-step building blocks for establishing an effective partnership in the not-for-profit sector N 2 (squared) Consulting with Nottingham Council

More information

219 Make sure your own actions reduce risks to health and safety

219 Make sure your own actions reduce risks to health and safety 219 Make sure your own actions reduce risks to health and safety QCF Reference Number R/501/0874 Level: 2 Credit Value: 5 Learning outcomes The learner will: 1. Identify the hazards and evaluate the risks

More information

Safety in Building Services Design

Safety in Building Services Design BG 55-14 Safety in BDS COVER_BSRIA Guide Cover 29/07/2014 09:20 Page 1 A BSRIA Guide www.bsria.co.uk Safety in Building Services Design By Richard Tudor BG 55/2014 Acknowledgements 1 This guide was authored

More information

SCAFFOLDS AND SCAFFOLDING WORK

SCAFFOLDS AND SCAFFOLDING WORK SCAFFOLDS AND SCAFFOLDING WORK Code of Practice TABLE OF CONTENTS FOREWORD... 4 SCOPE AND APPLICATION... 4 1. INTRODUCTION... 5 1.1 What is a scaffold and scaffolding work?... 5 1.2 Who has health and

More information

Level 2 NVQ Diploma in Wood Occupations (Construction)

Level 2 NVQ Diploma in Wood Occupations (Construction) Qualification Specification ProQual 2015 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile 4 Rules of combination 5 Centre requirements 8 Support for candidates

More information

Health, Safety and Welfare Policy

Health, Safety and Welfare Policy Health, Safety and Welfare Policy Contents Introduction Our objectives Health and Safety Policy Statement Health and safety organogram Responsibilities for health, safety and welfare 2 3 4 5 6 13 Arrangements

More information

The Construction (Design and Management) Regulations 2015

The Construction (Design and Management) Regulations 2015 Draft Guidance on The Construction (Design and Management) Regulations 2015 For Production Managers working in places of Entertainment And for guidance is to help the authorities understand theatre management

More information

Level 2 NVQ Certificate in Erection of Precast Concrete (Construction)

Level 2 NVQ Certificate in Erection of Precast Concrete (Construction) Level 2 NVQ Certificate in Erection of Precast Concrete (Construction) Qualification Specification ProQual 2016 Contents Introduction 3 Qualification profile 3 Qualification Structure 4 Pathway 1 Flooring

More information

Want construction work done safely?

Want construction work done safely? Want construction work done safely? A quick guide for clients on the Construction (Design and Management) Regulations 2007 Health and Safety A quick guide for clients on the Construction (Design and Management)

More information

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy.

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy. Bowmer Kirkland & Kirkland & Accommodation Health & Safety Policy December 2013 www.bandk.co.uk Index Policy Statement Page 3 Interaction of Health and Safety Responsibilities Page 5 Organisation Page

More information

Safe System of Work Policy

Safe System of Work Policy Reviews and Revisions Safe System of Work Policy Action Date Reason Reviewer Safe System of Work Policy 1 1. Introduction Campus Services manage and deliver a wide range of activities, accommodation, catering,

More information

Corporate Health and Safety Policy July 2012

Corporate Health and Safety Policy July 2012 Corporate Health and Safety Policy July 2012 Contents Page General Statement of Health and Safety Policy and Intent 2 1. ORGANISATION 3 1.1 Elected Members 3 1.2 Cabinet Members 3 1.3 Governing Bodies

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 July 2014 Approved Plan Jon Fahie This, the University

More information

COMPETENCE & COMMITMENT STATEMENTS

COMPETENCE & COMMITMENT STATEMENTS COMPETENCE & COMMITMENT STATEMENTS The Institution for Rail Infrastructure Engineers A Permanent Way Engineer is one who supports and promotes the advancement of the design, construction and maintenance

More information

METHOD STATEMENT First Fix Joinery

METHOD STATEMENT First Fix Joinery North West Facilities Ltd 17-18 Gaerwen Industrial Gaerwen Isle of Anglesey LL60-6HR Tel: 01248-422555 Fax: 01248-422556 Mobile: 07891-557581 Project/Contract CCG Contractor Apollo Property Services Group

More information

UCLH Asbestos Management Plan. July 2017

UCLH Asbestos Management Plan. July 2017 UCLH Asbestos Management Plan July 2017 Out of Hours and Emergency contacts: Larne Fuller Tel: 0345 5040 303 Mob: 07881 108 17 Joe Beesley Tel: 0345 5040 303 Mob: 07710 306 326 E-mail: uclh@ lucionservices.com

More information

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

Health & Safety Xpert User Guide

Health & Safety Xpert User Guide Health & Safety Xpert User Guide Software by Steven Mulgrew Written by Joanna Mulgrew, Olivia Wild, Dave Price, Ed Britten & John Rees House Builder XL Limited House Builder XL Limited Contents Contents

More information

Response to a Bridge Strike. at a Bridge carrying the Railway. over a Road

Response to a Bridge Strike. at a Bridge carrying the Railway. over a Road Response to a Bridge Strike at a Bridge carrying the Railway over a Road A Protocol for Highway and Road Managers, Emergency Services and Bridge Owners NR/GPG/CIV/008 3 rd March 2009 Note This protocol

More information

CDM 2015: The regulator s experience to date. Simon Longbottom Head of HSE Construction Sector. Thoughts for Conference and Beyond

CDM 2015: The regulator s experience to date. Simon Longbottom Head of HSE Construction Sector. Thoughts for Conference and Beyond Health and and Safety Executive Small Projects Differently CDM 2015: The regulator s experience to date Simon Longbottom Head of HSE Construction Sector APS Conference 14 th September 2016 Thoughts for

More information

Level 2 NVQ Diploma in Associated Industrial Services Occupations Passive Fire Protection (Construction)

Level 2 NVQ Diploma in Associated Industrial Services Occupations Passive Fire Protection (Construction) Level 2 NVQ Diploma in Associated Industrial Services Occupations Passive Fire Protection (Construction) Qualification Specification ProQual 2016 Contents Page Introduction 3 Qualification profile 3 Qualification

More information

CHANGES TO THE CDM REGULATIONS

CHANGES TO THE CDM REGULATIONS CHANGES TO THE CDM REGULATIONS WHAT DEVELOPERS NEED TO KNOW INTRODUCTION The Construction (Design and Management) Regulations 2015 (CDM 2015) came into force on 6 April 2015 and replace the Construction

More information

Ensure your own actions reduce risks to health and safety

Ensure your own actions reduce risks to health and safety Ensure your own actions reduce risks to health and safety UNIT SM 1 Area of competence This unit is designed to demonstrate competence in following the health and safety duties required in the workplace

More information

BHC-P-03.1 Training, Competence and Induction

BHC-P-03.1 Training, Competence and Induction BHC-P-03.1 Training, Competence and Induction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision register Date Version Description

More information

Asbestos Safety Toolkit

Asbestos Safety Toolkit HUMAN FOCUS Self-help Asbestos Safety Toolkit Contents Preparing to improve asbestos safety 2 An example asbestos safety policy statement 3 Main steps of the risk assessment process 5 Risk assessment form

More information

Lone Working Policy and Guidance

Lone Working Policy and Guidance Date: October 2016 Page: 1 of 12 Lone Working Policy and Guidance Synopsis This policy specifies the roles, responsibilities, actions and processes necessary to ensure safety of lone workers. This document

More information

QUALIFICATION HANDBOOK

QUALIFICATION HANDBOOK QUALIFICATION HANDBOOK Level 6 NVQ Diploma in Construction Site Management (Construction) (6578) November 2013 Version 1.0 Qualification at a glance Subject area City & Guilds number 6578 Age group approved

More information

hss.com / Safety / Value / Availability / Support The 2013 HSS Guide to Working Safely at Height

hss.com / Safety / Value / Availability / Support The 2013 HSS Guide to Working Safely at Height The 2013 HSS Guide to Working Safely at Height Working Safely at Height - Your Guide to the Law 2011 / 2012-40 fatal injuries to workers and over 3,000 major injuries as a result of a fall from height

More information

Code of practice for safe working on lifts

Code of practice for safe working on lifts BSI Standards Publication NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW raising standards worldwide Code of practice for safe working on lifts BS 7255:2012 BS 7255:2012 Publishing

More information

The safe management and control of Temporary Works

The safe management and control of Temporary Works The safe management and control of Temporary Works What are TW s? The HSE describe Temporary Works (TW s) as; an engineered solution that may include any structure, provision for access, item or technique

More information

21311 PROCEDURE - HEALTH AND SAFETY - RISK ASSESSMENT. 2. Risk Assessments/Health and Safety Considerations

21311 PROCEDURE - HEALTH AND SAFETY - RISK ASSESSMENT. 2. Risk Assessments/Health and Safety Considerations Version 13 Last updated 16/03/2017 Review date 16/03/2018 Equality Impact Assessment Low Owning department Health and Safety / Risk 1. About this Procedure 1.1. This procedure explains the Force Procedure

More information

Health, Safety and Fire Specialists Ltd

Health, Safety and Fire Specialists Ltd 17 Chescombe Road, Yatton, North Somerset, BS49 4EE. 0784 1916 730 01934 832 851 HealthSafetyAndFire@gmail.co.uk www.healthsafetyandfire.co.uk ASBESTOS RISK MANAGEMENT : For those WORKING on buildings..

More information

Registered as a Scottish Charity - No. SC Job Description

Registered as a Scottish Charity - No. SC Job Description Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Neighbourhood Maintenance Surveyor Assets and Investment Selkirk Grade 8, salary

More information

HEALTH & SAFETY POLICY

HEALTH & SAFETY POLICY Deeds not words - Be the best you can be HEALTH & SAFETY POLICY Updated: Spring 2018 Approved by Governors Resource Management Committee: 13 February 2018 NEXT REVIEW 2020 WHITLEY ACADEMY HEALTH AND SAFETY

More information

Scaffolding. Safety Guide. STOP! Before you climb

Scaffolding. Safety Guide. STOP! Before you climb Scaffolding Safety Guide Printed FEB 2015 rebr. AUG 2016 Contents Safety Guide Disclaimer... 1 Safety Guide Objectives... 2 Roles & Responsibilities of Workplace Parties Employers, Supervisors, Workers...

More information

Health and Safety Management Standards

Health and Safety Management Standards Management Standards Curtin University Sept 2011 PAGE LEFT INTENTIONALLY BLANK Management Standards Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Documents... 4 2. Management System Model...

More information

NEBOSH International Technical Certificate in Oil & Gas Operational Safety

NEBOSH International Technical Certificate in Oil & Gas Operational Safety NEBOSH International Technical Certificate in Oil & Gas Operational Safety UNIT IOG Management of International Oil & Gas Safety Operational Safety Sample Trainer Pack RRC Trainer Packs are designed to

More information

Community and Renewable Energy Scheme Project Development Toolkit Planning Module

Community and Renewable Energy Scheme Project Development Toolkit Planning Module Community and Renewable Energy Scheme Project Development Toolkit Planning Module Module structure The Local Energy Renewables Toolkit is intended to be used as a reference by community groups and community

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information

Insulation and Building Treatments (Cavity Wall Insulation) Qualification Specification

Insulation and Building Treatments (Cavity Wall Insulation) Qualification Specification Level 2 NVQ Certificate in Insulation and Building Treatments (Cavity Wall Insulation) Qualification Specification Qualification Recognition Number: 600/6017/7 ABBE Qualification Code: CertIBT(CWI)L212

More information

HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd

HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd HEALTH & SAFETY POLICY Of JMC Mechanical Electrical & Air Conditioning Ltd Company Trading Address 242 Fort Austin Avenue Crownhill Plymouth PL6 5NZ Tel: 01752 657227 Fax: 01752 657227 Email: enquiries@jmc-sw.com

More information

Waste Management Policy

Waste Management Policy Waste Management Policy Contents 1. Introduction 2. Policy Statement 3. Policy Objectives 4. Application 5. Organisation and Management 6. Glossary of Terms Document Control Information: Last updated on:

More information

Education Infrastructure Service. Asbestos Management Process

Education Infrastructure Service. Asbestos Management Process Education Infrastructure Service Asbestos Management Process Version 9 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by

More information

Part A Returning Officer role and responsibilities

Part A Returning Officer role and responsibilities Part A Returning Officer role and responsibilities Local government elections in England and Wales: guidance for Returning Officers Published October 2016 (last updated November 2017) In this guidance

More information

Isle of Wight Council Job Description

Isle of Wight Council Job Description Isle of Wight Council Job Description Identifying Facts Title of Post: Youth Offending Team Officer Directorate: Children s Services Post No: 50043897 Section: Youth Offending Team Date: May 2014 Responsible

More information

HEALTH & SAFETY POLICY TABLE OF CONTENTS RESPONSIBILITIES

HEALTH & SAFETY POLICY TABLE OF CONTENTS RESPONSIBILITIES TABLE OF CONTENTS INTRODUCTION Page 1 STATEMENT OF INTENT Page 2 Employer's Responsibilities Management Regulations Page 3 Employee's Responsibilities Page 4 Information for Employees Joint Consultation

More information

Your Checklist Guide for Effortless Crane Hire

Your Checklist Guide for Effortless Crane Hire Your Checklist Guide for Effortless Crane Hire (Plus Frequently Asked Questions) There are 6 key Processes that can make your Crane Hire experience effortless if we work together to manage them efficiently:

More information

Managing Asbestos in Premises, the Duty Holder Requirements Qualification Specification

Managing Asbestos in Premises, the Duty Holder Requirements Qualification Specification P407 Advanced Proficiency Qualification Managing Asbestos in Premises, the Duty Holder Requirements Qualification Specification Issue 1 January 2016 Issue 1.2 January 2018 Contents Page Section 1 About

More information

Construction OS&H Project planning and control for safe OS&H

Construction OS&H Project planning and control for safe OS&H Construction OS&H Project planning and control for safe OS&H Summary General principles of project planning and control OS&H by design as a key element of project planning and control OS&H performance

More information

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2014 Rail Safety and Standards Board Limited GE/GN8640 Method on Risk Evaluation and Assessment Issue One; June 2014 Rail

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17 Quality Manual DRAFT Page 1 of 17 Document Acceptance and Release Notice This is Revision A1 of the East Coast Designer Builders Quality Manual. The Manual is a managed document. For identification of

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

Registered as a Scottish Charity - No. SC Job Description. Grade 8, Salary commences 25,339 per annum

Registered as a Scottish Charity - No. SC Job Description. Grade 8, Salary commences 25,339 per annum Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Asset Safety Officer Assets and Investment Selkirk Grade 8, Salary commences

More information

Garage Conversions. Technical Issues

Garage Conversions. Technical Issues Garage Conversions Introduction: if you need more space and you do not want to move house you may wish to consider converting your garage. Your home is probably your most valuable asset so it is important

More information

Case specification. Norbert Nadudvari Mikkel Bo Mathiesen Mikolaj Osinski. Group nr 2. Vitas Architects Aps. 4/25/2016

Case specification. Norbert Nadudvari Mikkel Bo Mathiesen Mikolaj Osinski. Group nr 2. Vitas Architects Aps. 4/25/2016 2016 Case specification Norbert Nadudvari Mikkel Bo Mathiesen Mikolaj Osinski Group nr 2. Vitas Architects Aps. 4/25/2016 Client: Aarhus Municipality Multi-purpose hall Table of content Page : 1/Error!

More information

SERVICE PROCEDURE NOVEMBER 2011

SERVICE PROCEDURE NOVEMBER 2011 DERBYSHIRE FIRE & RESCUE SERVICE SERVICE PROCEDURE INCIDENT COMMAND TRAINING AND ASSESSMENT NOVEMBER 2011 VERSION 2.0 CONTENTS INTRODUCTION Introduction Procedure Training Courses Assessments Appeals Maintenance

More information

CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety

CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety Health and and Safety Executive CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety What this event is about A brief background to the changes An outline

More information

University of Birmingham

University of Birmingham University of Birmingham Health and Safety Policy Manager responsible for review: Facilities Manager Date of last review and update: April 2015 Approved by: H&S committee 2015 Next scheduled review date:

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

Occupational Health and Safety Management Manual v2.2

Occupational Health and Safety Management Manual v2.2 Occupational Health and Safety Management Manual v2.2 Written: February 2013 Author: David Seymour, Director of Operations Co Author: Mathew Sprake, Operations Manager Approved: Board of Directors 1. Introduction

More information

Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation

Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation Mini Tender Questionnaire for Subcontractors Section B involves a questionnaire oriented around the provision of key

More information

Contaminated Land - Managing the Risk

Contaminated Land - Managing the Risk Contaminated Land - Managing the Risk Signatures removed from electronic version Submitted by... Peter Wigley Nominated Responsible Manager Approved by... Tom Stevenson Chairman, Civil Engineering Subject

More information