1 DEN Process: Project Closeout David Mashburn, Director of Facility Services DENVER INTERNATIONAL AIRPORT February 8, 2017
2 PRIMARY POINT(s) OF PROJECT CLOSEOUT Financial Re-capitalize funds to do more capital projects Collect Lessons learned library to reduce future risks Handing off of commissioned assets Maintaining a strong position with the City Auditor. Our AIM Processes have set up a Culture of Transparency and Accountability 2
3 PMG Moment: Project Lifecycle 0Lifecycle% pdf 3
4 PCA Replacement Concourse B Closeout Tollgate - SAMPLE JOSHUA SPOON, PROJECT MANAGER DENVER INTERNATIONAL AIRPORT 11/18/2016
5 AGENDA Overview Pictures Budget Overview Accomplishments Lessons Learned 5
6 Before Submitting to PowerPoint Review PROJECT OVERVIEW Replacement of existing PCA Units on all mainline gates on Concourse B for United Airlines Installed 38 new units 23 bridge mounted 15 stand mounted Removal and disposal of all excising units R-22 refrigerant was properly evacuated and recycled. Evacuation reports were submitted for project record. Installation of new pantographs on all bridges. Upgrade of electrical feeders and circuit breakers to support new units. Units were upsized to meet the need of a modern fleet mix. Existing units were 20 ton. New Units are 45, 60 and 90 ton. Installed new hose trollies on most bridges. 6
7 Before Submitting to PowerPoint Review PROJECT PICTURES 7
8 8
9 9
10 BUDGET OVERVIEW Completed project with minimal additional costs Change orders were.83% of construction contract costs. Value engineering items Removal of B35 from scope Reuse of existing feeders, conduit and MCP panels that we slated to be replaced. Exceeded Construction Management and Quality Assurance (CM/QA) budget due to quality and performance issues with specified vendor. Addressed multiple issues to assist HVAC with maintenance life cycle costs. Lowered 3 existing units to meet new manufacturer s specification Addition of hail guards for all new and existing ground mounted PCA units. Addressed subpar single casters for hose trollies, vendor replaced them with new 3 wheel casters. 10
11 Before BUDGET Submitting OVERVIEW to PowerPoint Review Original Budget Actual Expense % of Budget Budget % of Const EAC Delta Design & Construction Admin 2.2% 226, % 198,800 (27,200) Construction 83.4% 8,484,774 8,555,248 70,474 Construction Management 2.5% 254, % 284,236 29,693 Contingency 8.3% 848, % 778,003* Permit 1.3% 127, % 50,879 (76,393) Commissioning 1.7% 169, % 110,762 (58,933) ROCIP 0.6% 60, % 60,321 Total Project Cost: 10,171,082 10,038,249 ($62,359) * Contingency to be returned 11
12 PROJECT SUCCESSES AND ACCOMPLISHMENTS Completed project with zero safety incidents. Successfully addressed and resolved major equipment performance issues with equipment vendor Twist Aero Discharge air temperatures Lack of vibration isolation in the refrigeration circuits. Faulty casters on hose trolleys Completed original scope 137 days ahead of schedule. Contract substantial completion date 2/17/2017 Actual substantial completion date 10/2/2016 Change order were held to.83% of original contract value 12
13 Before Submitting to PowerPoint Review LESSONS LEARNED Significant issues with PCA vendor Possible solutions Kick-off meeting with vendor on-sight staff to set expectation and communications protocols. Good Communication All gate closures were completed successfully One point of contact for United was efficient Clear and consistent communication with DEN Operations 13
14 KPIs 2016: Be Proud, start running 14 AIM - Facility Services All Objectives List of Activities Operational Excellence Key Performance Indicators Financial Performance Investing in Sustainability Inspiring Employees Winning Hearts of Customers Building Airport City Putting DIA on World Map nd Quarter 3 rd Quarter 4 th Quarter Goal (Target) April May June July AUG SEP OCT NOV DEC 2016 Deliver all approved projects within budget 80% X X X X X Deliver all approved projects on time 80% X X X X X Projects 80% Closeout on under time 90 days X X X X 0% 33% 39.6% Minimize Change Orders 15% X X X X 2.16% 2.10% 4.71% 3.8% 4.39% 3.82% 3.92% 4.12% 3.5% All employees will be provided personal protective equipment (PPE) necessary for their position Close to 100% 100% X X X 42.8% 98.1% 88.4% Respond to Requests for Information (RFIs) in less than 5 business days 95% X X 77.78% 85.04% 59.20% 83.8% 92.86% 88.51% 87.5% 74.73% 83.5% Respond to Contractor Submittals within 14 calendar days. 95% X X X 95.05% 92.04% 94.65% 93.8% 85.75% 81.57% 90.28% 87.39% 88.2% Monthly 1 x 1 100% X X X X X X 100% 95.50% 50% 100% 75% Close to 100% Excellent numbers for 2016 In 2017, Unifier should make this data more solid and less manual Developing KPI! in But this is an awesome start PPE, is the responsibility of the P. 1:1 s are a 2 way street
15 Who?: 15
16 Thank You for your participation David Mashburn, Director of Facility Services DENVER INTERNATIONAL AIRPORT February 8, 2017
17 PROJECT CLOSEOUT PROCESS & PROCEDURES MARY HENDERSON-REPS, CONTRACT ADMINISTRATOR DENVER INTERNATIONAL AIRPORT FEBRUARY, 2016
18 CLOSEOUT PROCESS - Closeout is defined as being The period that represents the time when the Project Manager reviews the Project, verifies that all the Contract Document requirements have been met and the systems or facility is functioning as intended. - The Closeout Process begins at the beginning of the Job. - Five Steps to the Process: - Step 1 Issuance of Closeout Checklist to Contractor - Step 2 Substantial Completion - Step 3 Final Completion - Step 4 Advertisement - Step 5 Retention Billing 2
19 Step 1 Closeout Checklist to Contractor The Closeout Checklist should be reviewed by the DIA Project Manager (PM) and Contract Administrator (CA) and edited for any Non-Applicable Items. The CA issues the Closeout Checklist (CM-75) within the Bid Documentation. The purpose of this change is to begin the Closeout Process at the beginning of the Project. Contractor reviews and provides a Serial Letter stating which Items they believe are Non-Applicable or can be closed and why. Contractor provides required Closeout documentation throughout the Project or Task. Originals must be provided for the Consent of Surety and all Subcontractor Lien Releases. 3
20 Step 2 Substantial Completion The City & County of Denver General Conditions (Yellow Book) defines Substantial Completion as the Work has progressed to the point that the City can take beneficial occupancy or utilize the Work for the purpose that is intended, and the Work complies with all applicable coded and regulations, including if required, issuance of a Certificate of Occupancy, or certificate of suitability for use from appropriate governmental agencies, as determined by the Manager in his sole discretion. Contractor will request Substantial Completion on their company s letterhead accompanied by the Punch List (CM-74) prepared during the Walk-thru with the Project Managers, Designer of Record, and Quality Assurance Inspector (QA). CA will fill out the Request for Substantial Completion to be routed for signatures. 4
21 Step 3 Final Completion Final Completion will be issued when the following criteria have been met: Contractors portion of the Closeout Checklist is complete. All Original Subcontractor Final Lien Releases have been provided by the Contractor. All RFI s have been answered and Submittals have been provided, accepted and the Logs have been closed. All NCR s and Deficiencies have been addressed, remediated, and accepted by QA and DIA s PM. All Contractors Change Requests and Change Orders have been issued and executed, including the Final Reconciliation Change Order if applicable. Deductions have been made for liquidated damages or work not provided if applicable. Final Completion inspection has been made and there are no open items on the Final Punch List. Final Punch List has been signed off by the PM, DOR, and QA. Disposition of all failing tests have been agreed to or remediated and signed off. All Permits have been signed off, closed and provided to the Project Management Team (PMT). All Owner training has been completed to DIA s end user satisfaction. All Spare Parts and O & M Manuals have been turned over to DIA if applicable. 5
22 Step 4 Project Advertisement When Final Completion and Acceptance has been issued and executed, the CA will Request Advertisement from Business Management Services (BMS). Contractors Consent of Surety from their Bond Issuance company must be included. This can be attained with the executed Substantial Completion document. Advertisement will be scheduled and run for 21 consecutive days giving any parties with claims to the Project an opportunity to file for Claim. A Notice of Settlement is issued by BMS and notification sent to the PMT. 6
23 Step 5 Retention Billing Final Billing or Retention billing may be requested by the Contractor when the following criteria have been met: Executed Final Completion. Contractor s Settlement Publication Advertisement has expired. Sales Tax Exemption Certificate has been provided. Original Final Lien Releases have been provided. Completed Closeout Checklist. Original Consent of Surety has been provided. Contractors Affidavit of Completion has been provided. Statement of Accounting from the Contractor has been provided. Billing for Retention is essentially the same as all other billings, but must be billed separately from all other Tasks or billings. Once Retention has been billed and paid, other than any Warranty work that arises, the Project is considered closed. 7
24
25 Project Closeout: Legal Issue Max Taylor, Assistant City Attorney DENVER INTERNATIONAL AIRPORT Tuesday, February 08, 2017
26 Legal Overview of CCD - DIA Denver is a Home Rule City Rules and Regulations Bond Ordinance Yellow Book 2
27 3 Yellow Book General Conditions
28 Title 12 Contract Claims for Adjustment and Disputes 4
29 Title 13 Disputes GC 1301 Disputes D.R.M.C Subcontractors Verified Statement of Claim C.R.S Final Settlement & Publication Bonding Over/Around C.R.S
30 Title 15 Performance and Payment Bonds 1502 Performance Bond 1503 Payment Bonds 6
31 Title 16 Insurance and Indemnification 1601 Insurance 1602 Defense and Indemnification 7
32 Title 17 Inspection and Defects 1701 Construction Inspection by the City 1702 Authority of Inspectors 1703 Observable Defects 1704 Defects Uncovering Work 1705 Latent Defects 1706 Removal of Defective Materials and Work 8
33 Title 18 Warranties, Guarantees and Corrective Work 1801 Contractor s Warranties, Guarantees and Correction of Work 1802 Performance During Warranty Period 9
34 Title 19 Substantial Completion of the Work 1901 Contractor s Notice of Substantial Completion 1902 Inspection and Punch List 1903 Certificate of Substantial Completion 1904 Right of Early Occupancy or Use 10
35 Title 20 Final Completion and Acceptance of the Work 2001 Clean-Up Upon Completion 2002 Final Completion and Acceptance of the Work 2003 Final Settlement 11
36 Project Goals DSBO - Denver Small Business Office SBE - Small Business Enterprise MWBE - Minority / Women Owned Business Goods and Services DBE - Disadvantaged Business Enterprise ACDBE - Airport Concession Disadvantaged Business Enterprise Navigating Legal Issues
37 Prevailing Wage D.R.M.C , et seq D.R.M.C & Yellow Book Title 10 Contract Exhibit Failure to Pay: YB 1005 Practical Information: LCP Tracker Online submittals Weekly payroll System verifies classifications Contact: (720)
38 Max Taylor, Assistant City Attorney
ATTACHMENT D SCOPE OF SERVICES
ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.
More informationShutdown Requests. Gian Catano Contract Administrator December 17, 2014
Shutdown Requests Gian Catano Contract Administrator December 17, 2014 1 Topics - Two types of Shutdown Requests: - Airside Shutdown Requests - System Shutdown Requests - What is required from the Contractor
More informationActivation, Transition & Close Out Step 7. July 13, 2012
Activation, Transition & Close Out Step 7 July 13, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
More informationNeighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
Subrecipient Administrative Training (SAT) Meeting McAfee Center, Fort Monmouth, NJ August 13, 2014 Neighborhood Community and Revitalization Program (NCR) Procurement, Contract, and Construction Standards
More informationQUALIFICATION MATRIX ADDENDUM:
QUALIFICATION MATRIX ADDENDUM: The following are just some examples of typical Responsible-in-Charge (RIC) functions for each of the fifteen specific areas identified in the experience matrix, Section
More information1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:
SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationPre-Construction Meeting Minutes
Project Name Project # Project Address Tel: Fax: Gilbane Building Company Pre-Construction Meeting Date Start End Next Meeting Next Time Prepared By Company Purpose Location Next Location General Notes
More informationManage Deliverables - Construction Step 6 February 2015
Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection
More informationConstruction Administration Process
Construction Administration Process February 1, 2009 Division of Construction, MCPS START COMPLETED OPEN SCHOOL 25.6 1 ISSUE TICE TO PROCEED LETTER TO BOE ACCEPTS FROM 30 BOE MEMBER INSPECTS 29 TEACHERS
More information1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES
TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING
More informationRequest for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION
Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for
More informationCOUNTY OF SAN JOAQUIN
August 1, 2012 COUNTY OF SAN JOAQUIN General Services Department 44 North San Joaquin Street, Suite 590 Stockton, California 95202-2778 (209) 468-3357, Fax (209) 468-2186 GABRIEL E. KARAM Director Capital
More informationREQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320
REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE 2015 2016 ROOF AND HVAC REPLACEMENT PROJECT PW1320 Issued by: City of Stockton Public Works Department 22 E. Weber Avenue, Room 301 Stockton, CA 95202
More informationSUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY
SUSQUEHANNA AREA REGIONAL AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS Professional Construction Management Services Harrisburg International Airport Rehabilitate Runway 13-31 Susquehanna Area Regional
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationRESIDENT ENGINEER S MANUAL
Peninsula Corridor Joint Powers Board 1250 San Carlos Avenue San Carlos, California 94070-1306 RESIDENT ENGINEER S MANUAL Revision 2 Page 1 of 336 Caltrain Standard Manual RESIDENT ENGINEER S MANUAL Manual
More informationState Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund
State Historic Preservation Office Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund April 2014 Table of Contents Conflict of Interest... 3 Floodplains... 3 Hazardous
More informationAPWA Public Works Construction Management Seminar. March 22, 2018
APWA Public Works Construction Management Seminar March 22, 2018 Seminar Objectives Exchange of Ideas CM - Definition & Purpose Relationship to Overall Effort Your Expectations Working with Contractors
More informationWebinar Project Close Out. December 14, 2017 / 10:00 - Noon
Welcome to Project Close Out We will begin shortly. (for higher quality, dial a number based on your current location) To listen to this webinar: 1.669.900.6833 or + 1.408.638.0968 Access Code: 393.375.631
More informationINVITATION FOR BID. HVAC Equipment Replacement for Black Box Theatre at Nordlof Center. Issued June 14, Name of Bidding Firm:
INVITATION FOR BID HVAC Equipment Replacement for Black Box Theatre at Nordlof Center Issued June 14, 2017 Name of Bidding Firm: Address: City: State: Zip: Phone: Fax Bid Opening Time and Date: Bid Deposit/Bid
More informationDesign-Builder Peformance Evaluation (DBPE)
Design-Builder Peformance Evaluation (DBPE) There are five (5) major components of the DBPE document. Each component has multiple categories to facilitate performance evaluation for the Design-Builder,
More informationUNC Chapel Hill Informal Contracting Guidelines
UNC Chapel Hill Informal Contracting Guidelines 1. Informal Contracts Informal bids are referenced by NC General Statute (NCGS) 143-131 as construction or repair work that does not reach the limits prescribed
More informationJOB ORDER CONTRACTING (JOC)
JOB ORDER CONTRACTING (JOC) A LEAN Best Management Practice for Efficient Construction Project Delivery All product and company names are trademarks or registered trademarks of their respective holders.
More informationINVITATION FOR BID. HVAC Equipment Replacement for Nordlof Center Lower Level West. Issued November 8, Name of Bidding Firm:
INVITATION FOR BID HVAC Equipment Replacement for Nordlof Center Lower Level West Issued November 8, 2017 Name of Bidding Firm: Address: City: State: Zip: Phone: Fax Bid Due Date: Bid Opening Time and
More informationCITY MANAGER MEMORANDUM. John Anderson Drive Roadway Improvements - Construction Engineering and Inspection Services
City Manager 22 S. Beach Street Ormond Beach Florida 32174 (386) 676-3200 Fax (386) 676-3384 CITY MANAGER MEMORANDUM To: Through: From: The Honorable Mayor Kelley and City Commissioners Joyce A. Shanahan,
More informationStacey Camillo, Contract Administration. As-Needed Construction Contracting
Stacey Camillo, Contract Administration As-Needed Construction Contracting November 3, 2016 Why we are here Agenda Introductions Methods of getting construction work in San Francisco New As-Needed Construction
More informationCITY OF MODESTO REQUEST FOR PROPOSAL (RFP) CONSTRUCTION MANAGEMENT SERVICES FOR STATE ROUTE 99 AND PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT
CITY OF MODESTO REQUEST FOR PROPOSAL (RFP) CONSTRUCTION MANAGEMENT SERVICES FOR STATE ROUTE 99 AND PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT September 2013 Page 1 of 39 REQUEST FOR PROPOSAL CONSTRUCTION
More informationPrevailing Wage Overview
City and County of Denver 201 West Colfax Avenue, Dept. 705 Denver, Colorado 80202 Prevailing Wage Overview Why Must Denver Contractors Pay Prevailing Wage? It's the Law. Denver Revised Municipal Code
More informationSchedule Guidance Document
Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationFACILITY PROJECTS. David Mashburn Director of Facility Services AIRPORT INFRASTRUCTURE MANAGEMENT
FACILITY PROJECTS David Mashburn Director of Facility Services AIRPORT INFRASTRUCTURE MANAGEMENT FIS FINISH IMPROVEMENTS Image Ideas 2 CAPITAL PLAN FIS Finish Improvements - pictures of current condition
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Wide HVAC Upgrades - Steam Lines Response
More informationREQUIRED FORM I - SPECIAL CONDITIONS REGARDING MINORITY AND WOMEN OWNED BUSINESS ENTERPRISES
REQUIRED FORM I - SPECIAL CONDITIONS REGARDING MINORITY AND WOMEN OWNED BUSINESS ENTERPRISES NAME OF PROJECT: PROJECT NUMBER: PROPOSER: SECTION I. POLICY STATEMENT AND TERMS In accordance with the Metropolitan
More informationUNIVERSITY OF CENTRAL FLORIDA. Facilities & Safety Business Office
UNIVERSITY OF CENTRAL FLORIDA Facilities & Safety Business Office UNIVERSITY OF CENTRAL FLORIDA LIST OF REQUIRED DOCUMENTS PAYMENT DOCUMENTS CHANGE ORDER DOCUMENTS DIRECT OWNER PURCHASE ORDER DOCUMENTS
More informationPROJECT CHECKLIST Links to Relevant Links to Relevant Responsible Suggested Red Folder
PROJECT CHECKLIST Links to Relevant Links to Relevant Responsible Suggested Red Folder Phase Forms/DataBase FAMIS Tab SOP Person File Category APPLICABLE FAMIS STATUSES: SCHEM_DES and SD_EST_SENT DESIGN
More informationDocument B252TM 2007
Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation
More informationVista Ridge Integration Project Progressive Design-Build Services
Vista Ridge Integration Project Progressive Design-Build Services Linda Bevis, P.E. Manager Water Resources/Vista Ridge Integration Diana L. Woltersdorf Manager Contract Administration Marisol Robles SMWVB
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Bishop Woods Landscape Restoration Response
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationThank you for coming this morning and learning about us.
Thank you for coming this morning and learning about us. Government agencies are one of the largest consumers of goods and services in the country. As you likely know, selling to government agencies is
More informationConnoisseur Solutions Project Procurement Management
Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes
More informationDefinition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan.
Definition of Terms **Non-capitalized references to a state refer to a state other than the State of Michigan. Addenda - Documents used by the Owner to incorporate interpretations or clarifications, modifications,
More informationSECTION 10. WASTE TIRE FACILITIES and WASTE TIRE HAULERS Standards for Tire Retailers, Wholesalers and Fleet Service Facilities
SECTION 10 WASTE TIRE FACILITIES and WASTE TIRE HAULERS 10.1 Scope and Applicability 10.2 General Provisions 10.3 Standards for Waste Tire Hauling 10.4 Standards for Tire Retailers, Wholesalers and Fleet
More informationFacilities Planning and Construction (FP&C)
Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:
More informationCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.
More informationSECTION CLOSEOUT PROCEDURES
SECTION 017700 - PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for contract closeout, including, but not limited to, the following: 1. Substantial Completion procedures. 2. Final Completion
More informationFacilities Planning Policy & Procedure #20
Facilities Planning Policy & Procedure #20 TITLE: OBJECTIVE AND PURPOSE RESPONSIBILITY MINOR PROJECTS To establish a procedure for proper initiation, implementation, filing and closeout for projects included
More informationOhio Public Employees Retirement System. Request for Proposal
Ohio Public Employees Retirement System For: Consulting Services for Development of the Business Intelligence & Analytics Office Date: 9/11/2017 Project Name: Business Intelligence & Analytics Program
More informationINSTRUCTIONS FOR COMPLETING PRE-QUALIFICATION STATEMENT
INSTRUCTIONS FOR COMPLETING PRE-QUALIFICATION STATEMENT Item 1 Select only those projects that you wish to pre-qualify. Item 2 Enter full company name. Item 2a Check the appropriate box. Item 2b Insert
More informationALL-IN-ONE CLOUD BASED CITIZEN SERVICE PLATFORM FOR PERMITTING, LICENSING, INSPECTIONS, AND ENFORCEMENT
City of McMinnville, Community Development Department ALL-IN-ONE CLOUD BASED CITIZEN SERVICE PLATFORM FOR PERMITTING, LICENSING, INSPECTIONS, AND ENFORCEMENT Bid Document Nolan Ming 10/11/2017 ALL-IN-ONE
More information6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents
Document (00 21 13) Rudolph/Libbe Inc. www.rlcos.com 6494 Latcha Rd. Walbridge, Ohio 43465 v: 419.241-5000 f: 419.837.9373 Table of Contents 1.0 General Instructions 1.1 Document Hierarchy 1.2 Safety 1.3
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationCONSTRUCTION PROCEDURES HANDBOOK
CONSTRUCTION PROCEDURES HANDBOOK SECTION V SUBSECTION A DATE CONSTRUCTION AFFIRMATIVE ACTION CONTRACTOR S COMPLIANCE WITH EEO, ON THE JOB TRAINING, AND LABOR REQUIREMENTS Contractors, subcontractors, consultants
More informationNC State University OESAD GUIDELINES Contract Year
July 1, 2014 NC State University OESAD GUIDELINES Contract Year 2014-2016 I. Informal Projects A. Preface Based on the North Carolina Administrative Code (NCAC), Title 01, Subchapter 30D Section.0300 Selection
More informationREQUEST FOR PROPOSAL TOWN OF MIDDLESEX, NEW YORK WATER SYSTEM IMPROVEMENTS PROJECT
REQUEST FOR PROPOSAL TOWN OF MIDDLESEX, NEW YORK WATER SYSTEM IMPROVEMENTS PROJECT PROJECT DESCRIPTION SUMMARY The Town of Middlesex ( the Town ) has been awarded a CDBG.730PW50-14 grant to renovate and
More informationEXHIBIT A INDEX TO TECHNICAL SPECIFICATIONS DOCUMENT FOLLOWS
EXHIBIT A INDEX TO TECHNICAL SPECIFICATIONS (Attach list of Technical Specifications.) DOCUMENT FOLLOWS Exhibit A EXHIBIT B LIST OF DRAWINGS (Attach List of Drawings) DOCUMENT FOLLOWS Exhibit B EXHIBIT
More informationReport to the BOARD OF AIRPORT COMMISSIONERS
Los A ngeles W orld A irports Report to the BOARD OF ARPORT COMMSSONERS tem h 0 r ApProve b : ntissar am,,s a.-f Airports Engineer Meeting Date: August 20, 2013 - "Af Reviewed by oger A. on, Deputy Executive
More informationEXHIBIT A FOR. March 31, 2017
EXHIBIT A FLORIDA DEPARTMENT OF TRANSPORTATION TECHNICAL SPECIFICATIONS FOR MODIFICATION & REFURBISHMENT OF FTE SELF-SUPPORTING TOWERS March 31, 2017 FILE: T:\PUBLIC\ITS\TELECOMMUNICATIONS\TURNPIKE SUPPORT\TOWER
More informationINSTRUCTIONS FOR COMPLETING WAGE CLAIM FORM
INSTRUCTIONS FOR COMPLETING WAGE CLAIM FORM The Delaware Department of Labor, Office of Labor Law Enforcement, enforces 21 laws including: the Wage Payment and Collection Act and the Minimum Wage Act.
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Harshman Demolition Response Deadline 3/28/18
More informationNOTICE OF ADVERTISEMENT FOR BIDS. Furnishing and Delivery of 5kV Switchgear for Panora Municipal Electrical Utility Panora, Iowa, 50216
NOTICE OF ADVERTISEMENT FOR BIDS Furnishing and Delivery of 5kV Switchgear for Panora Municipal Electrical Utility Panora, Iowa, 50216 Notice is hereby given that proposals for furnishing and delivery
More information1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
More informationOWNER S AFFIDAVIT. I, certify that I am the owner of the property described as: ADDRESS: LOT: BLOCK: SUBDIVISION:
DEVELOPMENT SERVICES DIVISION 3521 NW 43 rd Avenue Lauderdale Lakes, FL 33319 (954) 535-2480 Fax (954) 731-5309 www.lauderdalelakes.org OWNER S AFFIDAVIT ATTENTION: BUILDING OFFICIAL I, certify that I
More informationA. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663
August 2013, Rev 00 01 7419 Construction Waste Management PART 1. GENERAL 1.01 Requirements Include: A. Each Contractor provide: 1. Participation in Construction Waste Management plan, including separation
More informationDAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower
DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate
More informationREQUEST FOR PROPOSAL FOR. CONSTRUCTION MANAGER and DESIGN TEAM FOR. Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER and DESIGN TEAM FOR Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH December 2010 I. GENERAL The Urban Redevelopment Authority of
More informationOwner s Representative SCOPE OF SERVICES
Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,
More informationTERMS OF AGREEMENT AND TERMINATION. This agreement is made between and MILO TRANSPORTATION INC (MTI) on day of, 20.
MILO TRANSPORTATION INC. 525 S. Colfax Suite B. Griffith, IN 46319 PHONE# (888)881-6690 FAX# (219) 207-5635 TERMS OF AGREEMENT AND TERMINATION This agreement is made between and MILO TRANSPORTATION INC
More informationFinance & Technology Administrator (815) ext 223
2017 PAVING IMPROVEMENTS BID PACKET Due: Location: April 26, 2017 by 10:00 am Oregon Park District Fairgrounds Park 607 Fair Park Drive Oregon, IL 61061 Bid Proposal: 2017 Paving Improvements Administrative
More informationCONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE
CONTRACTOR PREQUALIFICATION REQUIREMENTS DATA CONTRACTORS FOR THE AZUSA UNIFIED SCHOOL DISTRICT 1 TABLE OF CONTENTS Filing of PreQualifications Submittals 3 PREQUALIFICATION QUESTIONNAIRE 6 Page Part I:
More informationFacilities Management Project Delivery Model - Process Map - v
Project Delivery Model - Process Map - v8.0-2016-05-25 Overview PLANNING DESIGN IMPLEMENTATION CLOSE OUT Project Identification Initiation Page 2 Project Planning Page 3 Schematic Design / Design Development
More informationREQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT RISK SERVICES SUPPLEMENTAL INFORMATION PACKAGE
MASSACHUSETTS PORT AUTHORITY CAPITAL PROGRAMS DEPARTMENT SUITE 209S - LOGAN OFFICE CENTER ONE HARBORSIDE DRIVE EAST BOSTON, MASSACHUSETTS 02128-2909 REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT AT
More informationDCMA INSTRUCTION 2501 CONTRACT MAINTENANCE
DCMA INSTRUCTION 2501 CONTRACT MAINTENANCE Office of Primary Responsibility: Contract Maintenance Capability Effective: August 14, 2017 Releasability: Cleared for public release New Issuance Incorporates:
More informationEnclosed is Addendum No. 1 to the above reference contract documents. Please execute and attach this Addendum No. 1 to your Project Manual.
January 5, 2005 Traffic Signal Installation NE Lakewood Blvd. and NE Anderson Dr. Bid No. 06-075 ADDENDUM NO. 1 Contract Bidders: Enclosed is Addendum No. 1 to the above reference contract documents. Please
More information600 - Phase C Intermediate Review Checklist for the Architect- Engineer
600 Phase C Intermediate Review Checklist for the Architect Engineer This checklist is to be used by the ArchitectEngineer during Phase C of the Project and shall be included in the Intermediate Review
More informationINVITATION TO BID. WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226
INVITATION TO BID WHATCOM COUNTY LIBRARY SYSTEM ADMINISTRATIVE SERVICES BUILDING REMODEL 5205 Northwest Drive, Bellingham, WA 98226 February 23, 2016 DESCRIPTION OF SERVICES The intent of this invitation
More informationSPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project
RES. NO. PROPOSAL FOR THE COMPLETION OF 2015-28 TO THE SATISFACTION OF THE BUTLER COUNTY COMMISSIONERS AND THE COUNTY ENGINEER: SAID WORK CONSISTING OF TYLERSVILLE ROAD IMPROVEMENTS, PHASE I TO THE COUNTY
More informationAttachment 04 Substantial and Final Completion Approval Form. Project Description Project # Date of Completion Permit # Project Manager Phone #
UCF Design, Construction, and Renovation Standards Attachment 04 Substantial and Final Completion Approval Form Project Description Project # Date of Completion Permit # Phone # Intent: This Substantial
More informationAIA Paper Contract Documents Price List, prices as of March 1, 2014
A Chapter of the American Institute of Architects AIA Paper Contract Documents Price List, prices as of March 1, 2014 The AIA provides free PDF copies certain Documents and Guides, General Guides, and
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationIBMF STATE OF GOOD REPAIR UPGRADES
IBMF STATE OF GOOD REPAIR UPGRADES City of North Las Vegas, Nevada SPECIFICATIONS For 14-092 December 26, 2013 TABLE OF CONTENTS SECTION 01100 SECTION 01250 SECTION 01290 SECTION 01310 SECTION 01322 SECTION
More informationMay 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS
May 17, 2017 REQUEST FOR PROPOSALS for SECURITY SERVICES ATTENTION RESPONDENTS You are hereby invited to submit a proposal to the McPherson Implementing Local Redevelopment Authority (hereafter referred
More informationCity of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services
ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017
More informationEffective Vendor Risk Management. April 21, Mario A. Mosse. This Training is Brought to you by ComplianceOnline. Presenter:
This Training is Brought to you by ComplianceOnline. Effective Vendor Risk Management Presenter: Mario A. Mosse April 21, 2017 This training session is sponsored by 2014 ComplianceOnline www.complianceonlie.com
More informationPublicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build
1 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Mark Kelley, Dannis Woliver Kelley Deidree Sakai, Dannis Woliver Kelley 2 1 Publicly Bid: Design-Bid-Build Multiple-Prime
More informationKPMG s Major Projects Advisory Project Leadership Series: Stakeholder Management and Communication
KPMG Global Energy Institute KPMG International KPMG s Major Projects Advisory Project Leadership Series: Stakeholder Management and Communication Stakeholder management and communication is critical to
More informationSEALED BID. Contract for the Implementation of the State Standard Plan for Electronic Collection and Recycling
Waste Management Division REQUEST FOR PROPOSAL SEALED BID Contract for the Implementation of the State Standard Plan for Electronic Collection and Recycling DATE: March 1, 2013 QUESTIONS DUE BY: April
More informationINS QA Programme Requirements
Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued
More informationDocument B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified
More informationPOSITION DESCRIPTION September 2017
POSITION DESCRIPTION September 2017 Classification: Team / Section: Bureau / Division: Position Number: CONSTRUCTION REPRESENTATIVE - JOURNEY Construction Quality Control / Construction Oversight Architecture
More informationCommissioning Communications
Commissioning Communications James Bochat Pro Services, a Linc Service Company Synopsis This paper describes the importance of communication in the commissioning process as well as basic commissioning
More informationGuide for the Preservation of Records For Public Water Utilities
Guide for the Preservation of Records For Public Water Utilities No. Types of Records Record Retention Corporate and General 1. Capital Stock Records:.. 2. Proxies and Voting Lists:... 3. Annual Report
More informationINSPECTION AND ACCEPTANCE FOR MAINTENANCE
Inspection and Acceptance For Maintenance Page 1 (Last revised 6/29/10) INSPECTION AND ACCEPTANCE FOR MAINTENANCE SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Acceptance Sewer As Built Drwg Example
More informationBID AND PURCHASING LAWS/BEST PRACTICES
BID AND PURCHASING LAWS/BEST PRACTICES BEFORE YOU DO ANYTHING, ASK YOURSELF THIS QUESTION. Is this purchase or contract for goods or services exempt from the bid laws? Exemptions: Piggy back off a contract
More informationQUALITY MANUAL DISTRIBUTION. Your Logo Here. Page 1 1 of 57. Rev.: A
Page 1 1 of 57 President Design Engineering Production Production Engineering Materials Control Purchasing Service Marketing Sales Contracts Human Resources Quality Assurance Quality Control Production
More informationGeneral Services Administration
General Services Administration Federal Acquisition Service Authorized Federal Supply Schedule Price List Values you can build on Professional Engineering Services (PES) Federal Supply Group: 871-7 and
More informationModule Practical Application Checklist:
Module Practical Application Checklist: MODULE 1 The Practical Application Checklists outline specific workplace tasks, by competency area, that CASB students are able to perform upon completion of each
More information2. Representatives of the facility user and operation and maintenance personnel.
PART I 1 GENERAL COMMISSIONING REQUIREMENTS 1.1 Description of Work a) The purpose of the commissioning process is to provide the owner/operator with assurance that the systems have been installed according
More informationASA PM WORKSHOP PROJECT MANAGEMENT
ASA PM WORKSHOP PROJECT MANAGEMENT SESSION 2 RECAP 1 ST SESSION Jonathan Mitz 1 st Session Presenters for Session 2 Bruce Spengler, Calvert Masonry Steve Groth, Chiaramonte Construction 1 SESSION 2 TOPICS
More informationAIA Contract Documents
AIA Contract Documents Availability by series Series Document # Former # Document Title Software Available at AIAOC DOD aia.org A101 2007* A101 2007 SP* A101 2017 A102 2007* A111 1997 A102 2017 A103 2007*
More information