SAFE WORK PROCEDURE 041 CONCRETE WORKS SEPTEMBER 2014 DOC. NO. D14/265945

Size: px
Start display at page:

Download "SAFE WORK PROCEDURE 041 CONCRETE WORKS SEPTEMBER 2014 DOC. NO. D14/265945"

Transcription

1 MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: Approved by the Walter Street OHS committee Date: September 2014 Operation Brief Description of Activity Construction of Concrete Pavements and Kerbs Installation of formwork and reinforcing mesh (where applicable), placing and finishing of concrete in footpaths, roads, laneways and vehicle crossings. Limitations This Safe Work Procedure is applicable to the construction of concrete pavements and kerbing. Operator Skill Requirement Unit Induction, Traffic Control Certificate, Licence or Other Mandatory Qualification Required Victorian Driver s Licence for Class of Vehicle Safe Work Procedures and Risk Assessments to Be Read in Conjunction With This Safe Work Procedure Refer to: SWP 001 Driving Trucks; SWP 002 Towing Trailers; SWP 004 Working Outdoors; SWP 009 Noise SWP 011 Manual Handling; SWP 012 Traffic Control at Worksites; SWP 010 Dangerous Goods and Hazardous Substances Workplace Conditions Affecting Safety Weather rain, fog, icy conditions Sun glare Traffic density and movements Incidents and Safety Alerts Nil Personal Protective Equipment Safety Sunglasses, High Visibility Vest, Safety Footwear, Protective Headwear, Protective eyewear, Gloves SWP 041 Key OHS Public Health and Safety # Environmental Quality Page 1 of 5

2 Critical Steps in this Activity Potential Hazards Risk Controls Use of Mobile Plant and Vehicles # Refer to: SWP 001 Driving Trucks; SWP 002 Towing Trailers; SWP 004 Working Outdoors; SWP 009 Noise SWP 011 Manual Handling; SWP 012 Traffic Control All Manual Outdoor Tasks. # Refer to SWP 011 Manual Handling; SWP 004 Working Outdoors Working in Trafficked Areas. Refer to SWP 012 Traffic Control at Worksites Identify and Locate Services. # Refer to SWP 005 Overhead Services; SWP 006 Buried Services Saw cut concrete with demolition saw. # Soft tissue injuries. Inhalation of silica bearing dust. Foreign objects in eye. Not all damaged concrete removed. Uneven edges. Wear approved earmuffs or earplugs when operating demolition saw or working in the vicinity. Concrete saws on wheeled stands to remove need to lift or bend. Rotate sawing duties between crew members if extensive cutting is Arrange for large self propelled saw when extensive cutting Use water when cutting. Wear approved safety eye wear when sawing and breaking concrete. Plan cut to remove all damaged concrete. Cut full depth of concrete. SWP 041 Key OHS Public Health and Safety # Environmental Quality Page 2 of 5

3 Break out and removal of concrete. Prepare subgrade. Soft tissue injuries. Foreign objects in eye. Struck by hammer. Trip hazard on broken concrete. Inadequate subgrade. Premature failure of footpaths and vehicle crossings. Trip hazard public or employees tripping, stumbling or slipping in excavated area. Use backhoe with breaker to break concrete into manageable pieces wherever practicable. Use backhoe to remove broken concrete and load onto truck where practicable. Wear thick leather gloves when handling broken concrete. If breaking manually, cut corner from slab to allow levering by crowbar. Break concrete with sledge hammer. If removing by hand, break into segments not more than 400mm on largest dimension and not exceeding 10kg in weight. Rotate breaking duties between crew members if extensive breaking is Wear approved protective eye wear at all times. All crew and visitors to stand well clear of backhoe and trucks whilst loading. Remove broken concrete and place on truck. Do not place broken concrete on footpath or roadways. Safety fences are erected to prevent inadvertent entry into the work area. Footpath and vehicle crossings are excavated to subgrade level. The subgrade is compacted. All soft, wet or otherwise unsuitable material is removed below subgrade level and replaced with fine crushed rock or gravel, compacted to form a stable foundation. Erect warning signs at all approaches. Erect safety fencing to prevent pedestrian access where excavation greater than 50mm below existing surface levels. SWP 041 Key OHS Public Health and Safety # Environmental Quality Page 3 of 5

4 Place and compact crushed rock or recycled concrete base. # Place formwork and dowels. Reinforcement. General Safety Handling Concrete and Cement. whilst spreading sub base material and using vibrating plate compactor. Foreign objects in eyes. Soft tissue injury resulting from application of force whilst in when carrying timber or using hammer on pegs to secure timber. Soft tissue damage to back, whilst handling reinforcing steel due to weight and awkward posture. Puncture wounds to hands and limbs when handling reinforcing steel. Trip on reinforcing steel. Personnel may become sensitized to plastic concrete or cement. Refer to SWP 039 Crushed rock pavements Wear approved ear muffs or ear plugs whilst drilling or working within 5 metres of drilling activities. Wear approved safety eye wear whilst drilling. Rotate drilling duties if extensive drilling is Care in carrying formwork onto worksite use two person lift when necessary. Use of fibremesh where possible. Two person lift for heavy or awkward lengths of steel or mesh. Rotate tasks to ensure tasks involving awkward posture limited to 20 minutes continuous or 2 hours in total during the day. Wear leather gloves when handling reinforcing steel or mesh. Store reinforcing mesh clear of work area and travel paths until All workers using cement or plastic concrete must wear rubber gloves whilst handling cement and concrete (including finishing concrete). SWP 041 Key OHS Public Health and Safety # Environmental Quality Page 4 of 5

5 Placement of concrete. Removal of formwork. Backfilling against edges to footpaths and vehicle crossings. Soft tissue damage to back, whilst shoveling and screeding concrete, heavy load and Soft tissue injury resulting from application of force whilst in when carrying timber. Trip hazard that could result in personal injury. Place concrete as close to required position as practicable. Use shovel to top up levels or to remove excess concrete from in front of screed. Training in manual handling techniques for screeding. Rotate tasks. Care in carrying formwork from worksite use two person lift when necessary. Topsoil or other material as specified to be placed and compacted against completed concrete works prior to opening for pedestrian traffic. SWP 041 Key OHS Public Health and Safety # Environmental Quality Page 5 of 5

SAFE WORK PROCEDURE 037 STORMWATER DRAINAGE CONSTRUCTION MARCH 2014 DOC. NO. D14/184659

SAFE WORK PROCEDURE 037 STORMWATER DRAINAGE CONSTRUCTION MARCH 2014 DOC. NO. D14/184659 MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Approved by the Walter Street OHS committee Date: September 2014 Operation Brief Description of Activity Construction

More information

+/0'-/12!"&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=!

+/0'-/12!&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=! "#$%&'(&)&$*+,,-,,%-./ +/0'-/12"&21'1/345$1.1/36#''-7-8#9:;&?-/3@1$-2/#$&'#.7A1/0/0-B$#C-2/D&.&7-$&.*>EF-$G1,#$?#$/0-,1/-*1*/0-$1,H&,,-,,%-./?#$/0-.-A+/0'-/12"&21'1/3/0&/ 1,9-1.79E1'/#./0-7$#E.*,#?5$1.1/36#''-7->20##''#2&/-*&/

More information

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Carrying out concreting to simple forms 1 Element 1: Planning and preparing 3 Section 1.1: Obtaining, confirming and applying work instructions and 4

More information

Unit 9 Reinstatement of modular surfaces and concrete footways

Unit 9 Reinstatement of modular surfaces and concrete footways This unit covers the requirements that you must meet when reinstating modular surfaces and concrete. You must ensure that you act in accordance with all current specifications and procedures and that you

More information

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Bridge Inspection Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE:

More information

GROUNDtrax GROUNDGRIDZ

GROUNDtrax GROUNDGRIDZ INSTALLATION GUIDE The product is asymmetric and must be lifted by placing the hands on the diagonally opposed corners of the central paver (as shown). 1. Place grids onto the prepared well consolidated

More information

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement

Emergency Contact Numbers: Police, Fire, Ambulance 000 SES Vic Roads EPA Vic 1300 EPA VIC ( ) Safe Work Method Statement Safe Work Method Statement Emergency Contact Numbers: Police, Fire, Ambulance 000 SES 132 500 Vic Roads 13 11 70 EPA Vic 1300 EPA VIC (1300 372 842) WMS No: Task/Activity Grader Operation SPH Job No: Date

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

Reinforced Earth wall Construction Manual

Reinforced Earth wall Construction Manual COVER PAGE CT-PE-W02 Rev: 5 Reinforced Earth wall Construction Manual Concrete Facing Reinforced Earth Malaysia Sdn Bhd 80-1, Jalan 8/62A Bandar Menjalara 52200 Kuala Lumpur Tel : 03-62746162, Fax : 03-62747212

More information

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

NOVEMBER 2016 GRANDWALL. retaining walls installation guide NOVEMBER 2016 GRANDWALL retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry Grandwall retaining wall blocks are an ideal choice for retaining

More information

Hebden 402 Permeable Ecopaving Information Sheet

Hebden 402 Permeable Ecopaving Information Sheet www.ecopaving.co.uk www.britishrecycledplastic.co.uk Hebden 402 Permeable Ecopaving Information Sheet Applications: Car parking Emergency vehicle access Temporary and permanent roadways Quick fit shed

More information

HS709 Materials Handling Guideline

HS709 Materials Handling Guideline HS709 Materials Handling Guideline Policy Hierarchy link Responsible Officer Contact Officer Superseded Documents File Number 2016/00370 Work Health and Safety Act 2011 Work Health and Safety Regulation

More information

Industry guidance for the safe operation of tilt-tray vehicles

Industry guidance for the safe operation of tilt-tray vehicles Industry guidance for the safe operation of tilt-tray vehicles This document provides practical advice on meeting the Duty of Care requirements of the Occupational Safety and Health Act 1984 (the Act)

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

Gardenstone Retaining Walls

Gardenstone Retaining Walls Gardenstone Retaining Walls masonry. build in style build in style Our range of coloured, standard and premium masonry have set a new standard in quality and style for the versatile concrete block. By

More information

Risk Assessment Form (Qualitative)

Risk Assessment Form (Qualitative) Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS RA & Issue No: 004 Prepared by:.r.sit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: Tree Felling (Non Climbing) Employees

More information

asphalt applications Asphalt surfacings for high stress areas mpa asphalt Asphalt Information Service Mineral Products Association

asphalt applications Asphalt surfacings for high stress areas mpa asphalt Asphalt Information Service Mineral Products Association asphalt applications 6 Asphalt surfacings for high stress areas Asphalt Information Service mpa asphalt November 2009 Mineral Products Association Introduction Information Sheet 2 in this series, Construction

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information

RIIMPO318A Conduct skid steer loader operations Unit descriptor. Employability skills Application of the unit. Competency field

RIIMPO318A Conduct skid steer loader operations Unit descriptor. Employability skills Application of the unit. Competency field RIIMPO318A Unit descriptor Employability skills Application of the unit Competency field Conduct skid steer loader operations This unit covers conducting skid steer loader operations in resources and infrastructure

More information

SAFETY FACT SHEETS. Working with and around High Risk Plant Safety Non Negotiable. G-HS-ST Working with and around High Risk Plant

SAFETY FACT SHEETS. Working with and around High Risk Plant Safety Non Negotiable. G-HS-ST Working with and around High Risk Plant SAFETY FACT SHEETS Working with and around High Risk Plant Safety Non Negotiable G-HS-ST-00741 Working with and around High Risk Plant Safety Non-Negotiables (SNN) Zinfra Group is committed to providing

More information

OUTLAW AUTOMATION INC. Safety Management System

OUTLAW AUTOMATION INC. Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Purpose The purpose of this program is to provide employees general information for working on owner client or other

More information

Introduction to X-Grid Ground Reinforcement Grids.

Introduction to X-Grid Ground Reinforcement Grids. Introduction to X-Grid Ground Reinforcement Grids. X-Grid Ground Reinforcement grid is the new recycled plastic sustainable drainage system (SUDS) compliant solution. X-Grid Ground Reinforcement grids

More information

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5 1.0 EXCAVATION AND FILL 1.1 GENERAL.1 The excavation or fill shall be made to provide proper grade, lines and crosssection for the laying of

More information

WSH Guidelines Safeguarding Against Falling Objects

WSH Guidelines Safeguarding Against Falling Objects WSH Guidelines Safeguarding Against Falling Objects Morris Hiang Manager WSHC Practices 1/28 Focus Items dropping from height 2/32 Overview Struck by Falling Objects 2 nd top cause of fatalities High number

More information

Heron Retaining Walls

Heron Retaining Walls Heron Retaining Walls masonry. build in style build in style Our range of coloured, standard and premium masonry have set a new standard in quality and style for the versatile concrete block. By adding

More information

COMMERCIAL AND INDUSTRIAL CONCRETE SPECIALISTS CAPABILITY STATEMENT

COMMERCIAL AND INDUSTRIAL CONCRETE SPECIALISTS CAPABILITY STATEMENT COMMERCIAL AND INDUSTRIAL CONCRETE SPECIALISTS CAPABILITY STATEMENT INDEX ABOUT US OUR WORK ETHIC MANAGEMENT SYSTEMS ACCREDITATIONS & ASSOCIATIONS CAPABILITIES & COMPETENCIES PLANT AND EQUIPMENT PREVIOUS

More information

SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE

SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE SYNTHETIC GRASS INSTALLATION GUIDE SOFT AND HARD SURFACE HARD SURFACE INSTALLATION You will need: Tape measure Rope or spray paint Weed spray Sharp utility knife and spare blades Synthetic grass adhesive

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

Safe Work Procedure for installation of

Safe Work Procedure for installation of Safe Work Procedure for installation of external cladding This procedure has been formulated to cover safe systems of work for the installation of external cladding. This instruction will be used to reduce

More information

Operate a dozer (wheeled and tracked)

Operate a dozer (wheeled and tracked) Operate a dozer (wheeled and tracked) Code OHSCER209A Workplace Health and Safety Queensland is moving to a new learning and assessment system for certificates to work in prescribed occupations. Learning

More information

SAFE WORK PROCEDURE: MOBILE ELEVATED WORK PLATFORMS (MEWP)

SAFE WORK PROCEDURE: MOBILE ELEVATED WORK PLATFORMS (MEWP) Rev: 01 Date: March 2017 Page: 1 of 8 SAFE WORK PROCEDURE: MOBILE ELEVATED WORK PLATFORMS (MEWP) A. OVERVIEW: Safe Work Procedures are crucial to preventing workplace injuries and accidents. Safe Work

More information

PPC Cement TUTORIAL. how to screed a floor

PPC Cement TUTORIAL. how to screed a floor PPC Cement TUTORIAL how to screed a floor Pre-build: TOOLs & Materials ITEM Quantity Check. Builders bucket. Wheelbarrow 3. Shovel 4. Builder s line 5. 50mm steel pegs 6. Rigid timber forms 7. Flexible

More information

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT). SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish

More information

NEVER REMOVE THE SAFETY GUARDS

NEVER REMOVE THE SAFETY GUARDS Page 1 of 5 Name Recommended Use Designed for cutting stumps up to 200 mm above ground and 120 mm below ground. Maximum Stump diameter 300 mm. NOT suitable for stumps surrounded by rocks, stones, concrete

More information

This data sheet discusses problems

This data sheet discusses problems General excavation National Safety Council This data sheet discusses problems involved in general excavating operations where the excavation walls are vertical or nearly so, except shoreline excavating,

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 The following is an outline of the Safe Working Requirements for all Companies, staff and any other persons for this event. Please note that the terms Company

More information

Kingframe Steel Framing System ("SFS") Infill & Oversail - CDM Design Risk Assessment

Kingframe Steel Framing System (SFS) Infill & Oversail - CDM Design Risk Assessment , Likely () Major Injury () 0 (High) Unacceptable.0 Persons Prob' Exposed Rating Control Measures Required by Designer to Reduce Action Rating 1 Introduction

More information

Forklift Course Pre-Reading Information. Version 2.0. March 2011

Forklift Course Pre-Reading Information. Version 2.0. March 2011 Forklift Course Pre-Reading Information Version 2.0 March 2011 Reading through this manual prior to sitting your forklift course will assist you in preparing for your in-class theory session and written

More information

Landscaping and Fencing

Landscaping and Fencing Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing

More information

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1 March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural

More information

WORK HEALTH AND SAFETY AUDIT STANDARD

WORK HEALTH AND SAFETY AUDIT STANDARD WORK HEALTH AND SAFETY AUDIT STANDARD FORESTRY INDUSTRY South Australia, Victoria and Tasmania Safety Standards 2017 2017 Content I. Introduction... 2 II. Audit Criteria and Indicators... 3 1 PLANNING...

More information

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL

RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL 1st Edition January 2007 RECYCLING CONSTRUCTION AND DEMOLITION MATERIAL GUIDANCE ON COMPLYING WITH THE OCCUPATIONAL HEALTH AND SAFETY (ASBESTOS) REGULATIONS 2003 The information presented in Recycling

More information

RISK ASSESSMENT SHEET

RISK ASSESSMENT SHEET Task Generic install telecoms equipment Assessment date 3rd October 2017 Location Various Review date 2nd October 2018 Number of staff at work Various Signature 1 Selected locations Works carried out during

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

Personal Protective Equipment (PPE) Safety Program

Personal Protective Equipment (PPE) Safety Program Personal Protective Equipment (PPE) Safety Program ENVIRONMENTAL HEALTH & SAFETY pg. 1 Table of Contents A. Introduction And Purpose... 4 B. Background... 4 C. Policy... 4 D. Personal Protective Equipment

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Company Name: THE GROUP PTY LTD This SWMS has been developed and: (T/A ARTHUR S CONCRETE CUTTING) Approved by: ATHANASIOS Address: 18 PANANIA AVE PANANIA NSW 2213 Position: TEL:

More information

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength psi [45 MPa] min.

CHARACTERISTICS CSA A TECHO-BLOC Compressive strength psi [45 MPa] min. PATIOS, WALKWAYS, POOLSIDES & STEPPING STONES PHYSICAL AND GEOMETRICAL CHARACTERISTICS CHARACTERISTICS CSA A231.1 2 TECHO-BLOC Compressive strength - 6 500 psi [45 MPa] min. Flexural strength 650 psi [4.5

More information

RIIMPO324A Conduct civil construction grader operations Unit descriptor

RIIMPO324A Conduct civil construction grader operations Unit descriptor RIIMPO324A Unit descriptor Employability skills Application of the unit Competency field Conduct civil construction grader operations This unit covers conducting grader operations in the civil construction

More information

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete

More information

Retaining Wall Ranges Bribie 4 Daintree 6 Heron 8 Moreton 10 How to Build Retaining Walls 12 Pavers Ranges Ecology 14 How to Pave 16 Contact 18

Retaining Wall Ranges Bribie 4 Daintree 6 Heron 8 Moreton 10 How to Build Retaining Walls 12 Pavers Ranges Ecology 14 How to Pave 16 Contact 18 contents. Retaining Wall Ranges Bribie 4 Daintree 6 Heron 8 Moreton 10 How to Build Retaining Walls 12 Pavers Ranges Ecology 14 How to Pave 16 Contact 18 Front Cover: range. heron colour. limestone 2 Austral

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction) Civil Engineering Services Construction Operations (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 4 Qualification structure 5 Centre requirements

More information

Construction Procedures

Construction Procedures Construction Procedures 2014 Rev. 1.6 1 Introduction This manual presents the methods and procedures necessary for the proper erection of a LOCK+LOAD retaining wall. problems later during the service life

More information

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures lower in height that use the FrogStone unit weight combined with gravel core infill to resist earth pressures

More information

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction) Civil Engineering Services Highways Maintenance (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC.

BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC. BEST PRACTICE GUIDANCE THE SAFE OFF-LOADING OF REINFORCEMENT FABRIC www.uk-bar.org CONTENTS Introduction.... 3 Hazards.... 4 Accidents... 5 Working at Height... 6 Dunnage.... 7 Planning for a Safe Delivery....

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Safety Policy and Procedure

Safety Policy and Procedure Safety Policy and Procedure Policy Number: 030 Authorized By: The Cianbro Companies Alan Burton Title: Placing Concrete Effective Date: 10/01/94 Page 1 of 5 1 Status 1.1 Update of existing policy, effective

More information

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along

Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along Steps And Stairs Installation Option 1 - Steps In Wall Option 2 - Steps With Plant Space Option 3 - Steps In Front of Walls Option 4 - Steps Along Wall Face Option 5 - Steps In Wall; 10 (25cm) Tread Option

More information

Tasman Retaining Wall

Tasman Retaining Wall Tasman Retaining Wall EVALUATION AND INSTALLATION GUIDE Landscaping Tasman Retaining Wall Evaluation and Installation Guide This installation guide demonstrates the basics on how to construct: A. Tasman

More information

Guidelines for Working in Loading Docks

Guidelines for Working in Loading Docks 1.0 INTRODUCTION Loading docks are busy areas, where trucks, trailers, pedestrians, lifting devices, and other equipment typically move throughout the area on a frequent basis. Serious or even fatal injuries

More information

METHOD STATEMENT SCREEDING OF FLOOR

METHOD STATEMENT SCREEDING OF FLOOR 17-18 Gaerwen Industrial Estate Gaerwen Isle of Anglesey LL60-6HR Tel: 01248-422555 Fax: 01248-422556 Mobile: 07891-557581 Project/Contract Preparation of sub floors & screeding principal Contractor Apollo

More information

Pothole Patching / Edge Repair Work Instruction

Pothole Patching / Edge Repair Work Instruction Bundaberg Regional Council Infrastructure Services Issue Date: 15-05-2009 Review Date: 15-05-2011 PURPOSE/SCOPE Pothole Patching / Edge Repair Work Instruction WI-7-250. Rev. No. 1 This Work Instruction

More information

Construction of Polish PERS test section

Construction of Polish PERS test section PoroElastic Road SUrface: an innovation to Avoid Damages to the Environment EUROPEAN COMMISSION - DG RESEARCH Directorate 1 - Environment Seventh Framework Programme - Contract No. 226313 Document type

More information

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS CONCRETE SIDEWALKS AND DRIVEWAYS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain

More information

CONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PUB 343 (4-17)

CONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PUB 343 (4-17) CONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PREPARED BY: BUREAU OF MAINTENANCE AND OPERATIONS ASSET MANAGEMENT DIVISION P.O. Box 3437 HARRISBURG,

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS PERMEABLE PAVEMENTS (SUDS) This leaflet highlights the basic requirements for laying Ibstock clay pavers to form a permeable pavement. Ibstock clay pavers are intended for domestic use only i.e. patios

More information

PPLCC19 SQA Unit Code (H9FJ 04) Recognise airside hazards and minimise risks

PPLCC19 SQA Unit Code (H9FJ 04) Recognise airside hazards and minimise risks Overview This unit is about working safely in an airport environment. You must be able to understand the possible risks throughout the airport including the ramp area. You must be able to understand your

More information

PAVING SLABS ON A CONCRETE BASE

PAVING SLABS ON A CONCRETE BASE SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.

More information

SAFETY METHOD STATEMENT

SAFETY METHOD STATEMENT SAFETY METHOD STATEMENT OUR POLICY The safety of our employees and those of our clients is our main priority when carrying out any work on site. This method statement is designed to let you, the client

More information

AUGUST 2017 HASTINGS. retaining walls installation guide

AUGUST 2017 HASTINGS. retaining walls installation guide AUGUST 2017 HASTINGS retaining walls installation guide RETAINING WALL INSTALLATION GUIDE RETAINING WALL information Austral Masonry retaining wall blocks are an ideal choice for retaining walls in gardens,

More information

Select Subgrade Material, Compacted

Select Subgrade Material, Compacted 314.1 GENERAL B314 SHOULDER, SELECTED SUBGRADE, AND STOCKPILING OPSS.PROV 314 Granular materials meeting the requirements of OPSS.PROV 1010 are obtained from pits and quarries, and recycled materials.

More information

CPC30211 Certificate III in Carpentry

CPC30211 Certificate III in Carpentry CPC30211 Certificate III in Carpentry ONSITE RECOGNITION OF PRIOR LEARNING (RPL) Version number: 005.1 Version date: 14 th November 2017 Page 1 of 10 CPC30211 CERTIFICATE III IN CARPENTRY ONSITE RECOGNITION

More information

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to

Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Steps And Stairs Installation Steps In Wall - Option 1 Steps In Front of Walls - Option 2 Steps In Wall; 10 (25cm) Tread - Option 3 Step Parallel to Wall - Option 4 Steps and Stairs Q & A E CONSTRUCTION

More information

GROUND CONTROL THAT WORKS

GROUND CONTROL THAT WORKS GROUND CONTROL YOUR ESSENTIAL GUIDE TO GRASS AND GRAVEL STABILISATION GRASS AND GRAVEL GRID SYSTEMS GROUNDRINGS GROUND CONTROL GROUND CONTROL EARTHWORX Groundrings is a plastic modular grid system with

More information

MACHINE-LAY Installation Manual

MACHINE-LAY Installation Manual MACHINE-LAY Installation Manual PaveDrain Installation Manual Table of Contents Section 1: Base Preparation (pages 3 6) Section 2: Machine-Lay PaveDrain Blocks (pages 8 11) Section 3: Edge Restraints (pages

More information

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION... 19.1 19-1.01 Exploratory Excavation... 19.1 19-1.02 Trench Width... 19.1 19-1.02.A Storm Drain

More information

GRANDE WALL large CONCRETE BLOCKS FOR THE CONSTRUCTION OF RETAINING WALLS. 1339_Feuillet_Permacon_Grande_ang.indd 1

GRANDE WALL large CONCRETE BLOCKS FOR THE CONSTRUCTION OF RETAINING WALLS. 1339_Feuillet_Permacon_Grande_ang.indd 1 GRANDE WALL large CONCRETE BLOCKS FOR THE CONSTRUCTION OF RETAINING WALLS 1339_Feuillet_Permacon_Grande_ang.indd 1 27-05-15 14:03 GRANDE WALL The Grande wall system is designed for building retaining walls

More information

OLYMPIC VIEW WATER & SEWER DISTRICT JOB DESCRIPTION

OLYMPIC VIEW WATER & SEWER DISTRICT JOB DESCRIPTION OLYMPIC VIEW WATER & SEWER DISTRICT JOB DESCRIPTION Position: Maintenance Technician 1 Updated: May 10, 2016 Range: $32.37 $35.01 hourly BRIEF To provide safe and quality installation, repairs and preventative

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013 SPECIAL PROVISIONS - SP2014 BOOK Page 1 S-1 (2104) REMOVE AND REPLACE BITUMINOUS PAVEMENT (ADA) Always include SP2014-119 (PLANT MIXED ASPHALT PAVEMENT) or SP2014-121 (PLANT MIXED ASPHALT PAVEMENT FOR

More information

SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN

SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN 1. SUMMARY A. Work includes: 1. Pavement removal, topsoil stripping, and site grading for concrete slab.

More information

DRIVER CODE OF CONDUCT FOR TRUCK AND HEAVY VEHICLE OPERATORS PERFORMING WORK FOR OR ASSOCIATED WITH CDM LOGISTICS

DRIVER CODE OF CONDUCT FOR TRUCK AND HEAVY VEHICLE OPERATORS PERFORMING WORK FOR OR ASSOCIATED WITH CDM LOGISTICS DRIVER CODE OF CONDUCT FOR TRUCK AND HEAVY VEHICLE OPERATORS PERFORMING WORK FOR OR ASSOCIATED WITH CDM LOGISTICS 1. INTRODUCTION 1.1. General This driver code of conduct applies to all CDM LOGISTICS personnel

More information

Applications. 5 reasons why you should choose Hebden X Grid cellular paving

Applications. 5 reasons why you should choose Hebden X Grid cellular paving 5 reasons why you should choose Hebden X Grid cellular paving The British-made Hebden X Grid cellular paving system can be filled with grass or gravel, then driven over, parked on and walked on whilst

More information

Implementing an Effective Personal Protective Equipment (PPE) Programme

Implementing an Effective Personal Protective Equipment (PPE) Programme Implementing an Effective Personal Protective Equipment (PPE) Programme Introduction Personal protective equipment is preventive equipment which is used by the worker to protect his safety in many organisations

More information

Proposed Structure and Construction Method for Improved Interlocking Concrete Block Pavement Used in Residential Parking Spaces

Proposed Structure and Construction Method for Improved Interlocking Concrete Block Pavement Used in Residential Parking Spaces Proposed Structure and Construction Method for Improved Interlocking Concrete Block Pavement Used in Residential Parking Spaces Akihiko Karasawa, 1 Masahiko Nakamura, 1 Yoshio Yanagisawa 1 1 S-BIC Company

More information

Highway construction C 5

Highway construction C 5 Highway construction C 5 Contents Equipments used in Highway Construction Construction of Earth Roads Gravel Roads Water Bound Macadam Roads Bituminous Pavements Cement Concrete Pavements Equipment used

More information

A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet

A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet 01 This mandatory safety sign means. A. you must wear safety goggles B. you must wear hand gloves C. you must wear safety shoes D. you must wear safety helmet 02 If your employer asks you to work for another

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

Construction Management Plan (CMP) 227 Princess Highway, Dandenong Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale

More information

SECTION FLEXIBLE PAVING

SECTION FLEXIBLE PAVING SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications

More information

Selection of Proprietary Shoring Equipment

Selection of Proprietary Shoring Equipment CPA Safety Guidance Selection of Proprietary Shoring Equipment Introduction Every contractor involved with groundwork must ensure the safe support of trenches and excavations as part of their risk assessment.

More information

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING 402.1 Description. This work shall consist of placing, spreading and compacting a bituminous mixture as shown on the plans or as directed by the engineer.

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects. New Project (replacing grass/dirt) STEP 1 PREPARING YOUR PROJECT AREA Determine how much to excavate using the example below. Remove the grass to desired depth (skim rather than dig deep) and a few inches

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

To: Hyoksang Kwon, COBE Construction From: Joshua Marcley, Mei Wu Acoustics

To: Hyoksang Kwon, COBE Construction From: Joshua Marcley, Mei Wu Acoustics Experts in acoustics, noise and vibration To: Hyoksang Kwon, COBE Construction hyoksang@cobeinc.com From: Joshua Marcley, josh@mei-wu.com Mei Wu, meiwu@mei-wu.com Date: May 24, 2016 Subject: Cal Water

More information